Project+management+basics

Post on 03-Dec-2014

2,029 views 0 download

Tags:

description

project management

transcript

PROJECT MANAGEMENT BASICS

ISOM 502

2

3

4

5

WBS

6

7

Function Point Analysis (FPA)

1000

Code of Lines 1.4 Estimate Time *

* Measured in person months

8

PERT Time/Work Estimation

Estimates Days

Optimistic (To) 20

Likely (TL) 24

Pessimistic (TP) 34

20 4 24 34Time Estimate = 25 Days

6

6

4Estimate Time PLo TTT

9

10

Gantt Chart

Task Duration

Task

SummaryTask

11

Gantt Chart

Task Dependency

12

13

Types of Dependencies

Gantt ChartCritical Tasks

Non-Critical Tasks

14

15

Network Diagram

A1day

G6 days

I2 days

F4 days

C3 days

D4 days

B2 days

E5 days

H6 days

J3 days

Path Length

A-D-H-J 1+4+6+3 = 14 days

B-E-H-J 2+5+6+3 = 16 days

B-F-J 2+4+3 = 9 days

C-G-I 3+6+2+3 = 14 days

CRITICALPATH

16

17

Critical Path Analysis (CPA)

Example: Project Y

Task

Duration

Dependency

K 5 days

L 10 days

M 7 days K, L

K5 days

L10 days

M7 days

18

K5 days

L10 days

M7 days

ES=0

ES=0

EF=5

EF=10

ES=10 EF=17

LF=17LS=10

LF=10

LF=10

LS=5

LS=0

19

K5 days

0 5

105

Activity Total Slack

K 5 – 0 = 5

Total Slack is the amount of time that an activity can be delayed without delaying the project completion date

Total Slack = LS - ES

20

K5 days

M7 days

0 5 10 17

1710105

Activity Free Slack

K 10 – 5 = 5

Free Slack is the amount of time that an activity can be delayed without delaying the next activity.

Free Slack = ESM - EFK

21

Three Inter-related Concepts of Scheduling

22

23

Day 1 Day 2 Day 3 Day 4

8 Hrs 8Hrs 8Hrs 8Hrs

Day 1

Day 2

Day 3

Day 4

Day 5

Day 6

2 Hrs 2 Hrs

4 Hrs 8Hrs 8 Hrs 8 Hrs

Day 1

Day 2

Day 3

Day 4

Day 5

Day 6

8 Hrs 8 Hrs

8 Hrs 4Hrs 2 Hrs 2 Hrs

24

Tracking Gantt Chart

100% complete

20% Complete

25

Tracking Gantt Chart

Baseline(Initial Scheduleof task)

Actual Start Dateof Task

Scheduled Start Dateof Task is now delayed

26

AB

D

C

27

Task Y

Task Y

Planned Budget(BAC)

$10,000

Planned Time 10 days

10 Days

28

Illustrative Case

BAC: Budget at Completion

Task Y

Progress at the end of 5 days

Actual Cost (AC) $6,000

% Work Completed

40%

5 Days

29

Illustrative Case

40%

Task Y

5 Days

30

Illustrative Case

40%

Earned Value (EV)=

Planned Value (PV)=

000,4$000,10$100

40

000,5$000,10$10

5

Progress at the end of 5 days

Actual Cost (AC) $6,000

Earned Value (EV)

$4,000

Planned Value (PV)

$5,000

31

Illustrative Case

$4,000Cost Performance Index (CPI)

$6,000

0.67

EV

AC

Cost Variance (CV) $4,000 $6,000

$2,000

EV AC

Progress at the end of 5 days

Actual Cost (AC) $6,000

Earned Value (EV)

$4,000

Planned Value (PV)

$5,000

32

Illustrative Case

$4,000Scheduled Performance Index (SPI)

$5,000

0.80

EV

PV

Schedule Variance (SV) $4,000 $5,000

$1,000

EV PV