Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 1 J M Environet Pvt. Ltd.
APPENDAPPENDAPPENDAPPENDIIIIXXXX----1111
(See pa(See pa(See pa(See parrrragragragragraaaaphphphph----6666))))
FORM 1FORM 1FORM 1FORM 1
I.I.I.I. Basic InfoBasic InfoBasic InfoBasic Informrmrmrmationationationation
S. S. S. S.
No.No.No.No.
ItemItemItemItem Details Details Details Details
1. Name of the project Proposed Group Housing Project, At Plot No. –GH-11A,
Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.)
2. S. No. in the Schedule Building and Construction Project, Category ‘B’ [(As per
14.09.2006 Notification, Project or Activity-8 (a)]
3. Proposed capacity /area/
length/ tonnage to be handled/
command area /lease area/
number of wells to be drilled:
Total Plot area: 20,000 sq. m. (4.94 Acres approx)
F.A.R. Permissible: 73500.00 sq. m. (@3.675)
Proposed: 73491.96 sq. m. (@3.674)
Ground
coverage
Permissible: 7000.00 sq. m. (35 % of plot
area)
Proposed: 6639.55 sq. m. (33.19 % of plot
area)
Built up area: 116015.357 sq. m. (F.A.R- 73491.96 sq. m.
+ Non F.A.R – 10052.957 sq. m. +
Basement Area- 32470.44 sq. m. +)
4. New/Expansion/Modernization The proposed project is New Group Housing Project.
5. Existing Capacity/Area etc. Not Applicable, as the proposed project is a New Group
Housing Project
6. Category of Project i.e.' A' or 'B' Category ‘B’
7. Does it attract the general
condition? If yes, Please specify.
No, it is applicable on S. No.– 8 projects of EIA Notification
dated 14.09.2006 does not attract the general condition, as
General Conditions are not
8. Does it attract the specific
condition? If 'yes, please specify.
No, it does not attract the specific condition, as Specific
Conditions are not applicable on S. No. –8 projects of EIA
Notification dated 14.09.2006.
9. Location: Plot No. –GH-11A, Sector-01, Greater Noida (U.P.)
Land documents are attached as Annexure IAAnnexure IAAnnexure IAAnnexure IA
Plot/Survey/Khasra. No. GH-11A
Sector 01,Greater Nodia
District Gautam Budh Nagar
State Uttar Pradesh
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 2 J M Environet Pvt. Ltd.
10. Nearest Railway Station/
Airport along with distance in
kms.
Nearest AirportNearest AirportNearest AirportNearest Airport: IGI International Airport which is about 31.0
km from project site in WSW direction.
Nearest Railway StationNearest Railway StationNearest Railway StationNearest Railway Station: Maripat Railway Station which is
about 6.5 km in ENE direction from the project site.
11. Nearest Town, city, District
Headquarters along with
distance in kms.
The Project site fall within Greater Noida Industrial
Development Authority limits. District Headquarter, Greater
Noida.
12. Village Panchayats, Zilla
Parishad, Municipal
Corporation, Local body
(complete postal addresses with
telephone nos. to be given)
Greater NoidaGreater NoidaGreater NoidaGreater Noida Industrial DevelopmentIndustrial DevelopmentIndustrial DevelopmentIndustrial Development AuthorityAuthorityAuthorityAuthority
Plot No. 01, Knowledge Park-04, Greater Noida, Gautam
Budh Nagar, Uttar Pradesh, India- 201308
Fax: +91-120 232-6143
Help Line No. +91-120 232-6150
E-Mail: authority@gnida.in
13. Name of the applicant Enticement Infrastructure Pvt. Ltd.
14. Registered address B1/105 , Tower 8, Purvanchal Silver City 2, opp. Wipro, Pi 2,
Greater Noida, Uttar Pradesh -201306
15. Address for correspondence (1)
Name Mr. Himanshu Goyal S/o Mr. Pawan Kumar Goyal
Designation
(Owner/Partner/CEO)
Authorized signatory
(Authorization Letter is enclosed as Annexure IBAnnexure IBAnnexure IBAnnexure IB)
Address B1/105 , Tower 8, Purvanchal Silver City 2, opp. Wipro, Pi 2,
Greater Noida, Uttar Pradesh
Pin Code 201306
E-mail himanshu@crcadvisor.com
Telephone No. 09911024362
Fax No. -
Address for correspondence (2): Environnemental Consultant
Mr. Sunil Dixit
(Associates Director)
J. M. Environet Pvt. Ltd.
202-A, ABW Tower, MG Road, IFFCO Chowk,
Sector 25, Gurugram-122001 (Haryana) INDIA
Tel. 0124 – 3206559
Mobile No. 09971699906
Email: jmgurgaon@hotmail.com
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 3 J M Environet Pvt. Ltd.
Disclosure of the consultant is enclosed as AnnexureAnnexureAnnexureAnnexure IIIIIIII. . . .
16. Details of Alternative Sites
examined, if any. Location of
these sites should be shown on
a topo sheet.
There is no alternative site related to this project as this is a
New Group Housing Project of Enticement Infrastructure Pvt.
Ltd. which is proposed to be setup in residential area.
Keeping in view the above narrated facts, no alternative site
can be given here. Hence it is Not Applicable in this case.
17. Interlinked Projects There is no interlinked project, related to this project as this
is a New Group Housing Project of Enticement Infrastructure
Pvt. Ltd.
18. Whether separate application of
interlinked project has been
submitted
Not Applicable, as this is a New Group Housing Project of
Enticement Infrastructure Pvt. Ltd.
19. If yes, date of submission Not Applicable, as this is a New Group Housing Project of
Enticement Infrastructure Pvt. Ltd.
20. If no, reason Not Applicable, as this is a New Group Housing Project of
Enticement Infrastructure Pvt. Ltd.
21. Whether the proposal involves
approval/ clearance under: if
yes, details of the same and
their status to be given.
(a) The Forest
(Conservation) Act, 1980?
(b) The Wildlife (Protection)
Act, 1972?
(c) The C.R.Z. Notification,
1991?
Not Applicable, as no approval / Clearance involves under
any Notification and under any Act, a New Group Housing
Project of Enticement Infrastructure Pvt. Ltd.
22. Whether there is any
Government Order/ Policy
relevant/ relating to the site?
Not any, Proposed Project is a New Group Housing Project
of Enticement Infrastructure Pvt. Ltd.
23. Forest land involved (hectares) No any Forest land involved is a New Group Housing
Project of Enticement Infrastructure Pvt. Ltd.
24. Whether there is any litigation
pending against the project
and/or land in which the
project is proposed to be set
up?
(a)Name of the Court
No litigation is pending against the project and/or land in
which the project is proposed to be set up.
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 4 J M Environet Pvt. Ltd.
(b)Case No.
(c) Orders/directions of the
Court, if any and its relevance
with the proposed project
(II)(II)(II)(II) AcAcAcActivitytivitytivitytivity
1.1.1.1. Construction, operation or decommissioning of the Project involving actions, which will cause Construction, operation or decommissioning of the Project involving actions, which will cause Construction, operation or decommissioning of the Project involving actions, which will cause Construction, operation or decommissioning of the Project involving actions, which will cause
physical changes in the locality (topography, land use, changes in water bodies, etc.physical changes in the locality (topography, land use, changes in water bodies, etc.physical changes in the locality (topography, land use, changes in water bodies, etc.physical changes in the locality (topography, land use, changes in water bodies, etc.
S. S. S. S.
No.No.No.No.
Information/Checklist confirmationInformation/Checklist confirmationInformation/Checklist confirmationInformation/Checklist confirmation Yes/ Yes/ Yes/ Yes/
NoNoNoNo
Details thereoDetails thereoDetails thereoDetails thereof (with approximate quantities f (with approximate quantities f (with approximate quantities f (with approximate quantities
/rates, wherever possible) with source of /rates, wherever possible) with source of /rates, wherever possible) with source of /rates, wherever possible) with source of
information datainformation datainformation datainformation data
1.1 Permanent or temporary change in
land use, land cover or topography
including increase in intensity of land
use (with respect to local land use
plan)
Yes The Proposed Project will be developed by
Enticement Infrastructure Pvt. Ltd. and this is a
construction of new Building Group Housing
project on plot area 20,000 sq. m. (4.94 Acres
approx) of a vacant land.
There Will bé green-area development on
6700.032 of the plot to provide beautiful and
natural environment to the site.
1.2 Clearance of existing land, vegetation
and buildings?
No The proposed site is an open land, with scanty
vegetations mainly herbs and low lying shrubs &
possesses existing no structure. Hence no
clearance of structure and vegetation will be
required.
Site photographs showing the present condition
of the site have been enclosed as AnnexureAnnexureAnnexureAnnexure IIIIIIIIIIII....
1.3 Creation of new land uses? No Project has been earmarked for residential
development as per Master Plan of Noida The
project site will be developed as per the local
building by-laws. So, no new land use will be
created. Location map of the project site along
with the Noida Master Plan is being enclosed as
AnnexureAnnexureAnnexureAnnexure----IIIIV.V.V.V.
1.4 Pre-construction investigations e.g.
bore holes, soil testing?
Yes Soil investigation was carried out and the results
were found satisfactory.
1.5 Construction works? Yes This is a building construction project. The
construction activities will be confined within
the project site; there will be no physical
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 5 J M Environet Pvt. Ltd.
changes due to project development activities
outside the project boundary.
1.6 Demolition works?
No No demolition is required, as no building
structure exits at the proposed project site.
1.7 Temporary sites used for construction
works or housing of construction
workers?
No No temporary residential facilities will be
required for the workers, as all the workers will
be coming from nearby area. The construction
work will be done only in the daytime.
There will be provision of facilities such as rest
shelter, drinking water, toilet creach (if required)
etc. for workers at the project site & will be
arranged by contractor.
1.8 Above ground buildings, structures or
earthworks including linear
structures, cut and fill or excavations
Yes Excavation carried out for foundation and
construction of basement. The excavated earth
material will be used for back filling, and other
site developmental activities like leveling and
horticulture at the project site. The fertile top
soil will be stack at separate place and it will be
reused for plantation / horticulture purpose on
site of the project.
Land/soil environment may be temporarily
affected due to activities like Site preparation,
excavation, material handling & storage etc.
during construction phase, which will be
mitigate by dust suppression and regular water
sprinkling.
1.9 Underground works including mining
or tunnelling?
No No underground works including mining /
tunnelling is required, except excavation of
earth only for the construction of basement.
1.10 Reclamation works? No No reclamation work required, as the basement
shall be used for parking and other services.
1.11 Dredging? No No dredging required, as case of building
development project.
1.12 Offshore structures? No No offshore construction will be done for the
said proposed project.
1.13 Production and manufacturing
processes?
No Since, it is a construction of Building Project,
hence, no production / manufacturing process is
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 6 J M Environet Pvt. Ltd.
involved in this project.
1.14 Facilities for storage of goods or
materials?
Yes Separate raw material storage yard will be made
during construction phase:
• Cement will be separately stored under
cover in bales.
• Sand will be stacked neatly under tarpaulin
cover.
• Bricks and steel will be laid in open
• The raw material handling yard will be
located within the project site and
separated by enclosures.
1.15 Facilities for treatment or disposal of
solid waste or liquid effluents?
Yes Construction Phase: Construction Phase: Construction Phase: Construction Phase:
7-10% of construction material Construction
and demolition waste will be generate.
Operation Phase: Operation Phase: Operation Phase: Operation Phase:
Solid WasteSolid WasteSolid WasteSolid Waste
Solid wastes which are likely to be generated in
project will be domestic and commercial in
nature.
Domestic wastes: Domestic wastes: Domestic wastes: Domestic wastes:
Approximately 2370.15 kg/day of solid waste
will be generated from the existing and project
activity; these will be collected from designated
locations and segregated into inorganic and
organic wastes.
Organic waste converter will be installed on site
& Organic biodegradable waste will be
composted in the composter at site only
The inorganic non-biodegradable wastes will be
segregated and sold to Authorized vendors for
recycling as per MSW rules, 2016.
Commercial waste (ECommercial waste (ECommercial waste (ECommercial waste (E----wasteswasteswasteswastes):::: E-waste will start
being generated after a latency period of 4-5
years. Since most of these components are
recyclable in nature, efforts will be made to
recycle it to the maximum extent, hence actual
waste generated as E-waste should be minimal.
It is estimated that from the project about 0.25
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 7 J M Environet Pvt. Ltd.
MT/yr E-waste will be generated after 4-5 years.
Management of EManagement of EManagement of EManagement of E----wastewastewastewaste
The principle idea of E-waste management is to
recycle the E-waste generated. Authorized
vendors of electronic goods will take back their
old equipment/cartridge/toner rolls etc. and pay
some concessions on the new equipment. On
the other hand, reusable material like
cartridges/toners will be refilled and reused.
Outdated computers/ fax/ phones etc. will be
value added and sold to downstream uses
through resellers. These arrangements will be
made with existing CPCB authorized vendors to
simultaneously & effectively reduce the quantity
of E-waste generated and also to generate
substantial revenue for running the management
system. Whatever E-waste left, will be collected
separately in HDPE drums and will be stored in
special containments, onto puckka platforms
and under lock and key. The collected e –waste
will be handed over to the CPCB authorized
vendors for further disposal.
Liquid Effluent:Liquid Effluent:Liquid Effluent:Liquid Effluent:
During construction phase only sewage
generated from office toilets and same will be
treated and disposed through soak pits via septic
tanks.
During operation phase 336 KLD waste water
will be generated which will be treated in the
Sewage Treatment Plant (STP) up to tertiary
level and treated water will be reuse in flushing
and green area development excess water will
be drain in municipal sewage line after
permission.
Dewatered/ dried sludge from STP will be used
as manure in horticulture.
Hazardous Wastes:Hazardous Wastes:Hazardous Wastes:Hazardous Wastes:
No hazardous wastes will be produced from
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 8 J M Environet Pvt. Ltd.
project activities except some Spent Oil
(Category 5.1) generated from D.G. sets; it will
be stored in HDPE tank properly and will be
handed over to authorized processor for the
facility.
1.16 Facilities for long term housing of
operational workers?
No This is a group Housing project in which total
857 D.U. with 86 servant unit proposed in
project.
1.17 New road, rail or sea traffic during
construction or operation?
No No rail or sea traffic involve in the project. Our
project site is well connected by road, So no
new road will be laid during construction or
operation of the project activities except for
internal roads.
1.18 New road, rail, air or waterborne or
other transport infrastructure
including new or altered routes and
stations, ports, airports etc?
No The project site is located in a developed area. It
is well connected by roads to whole of the city,
so there will be no alteration of routes or lying
down of new routes done due to project
activity. Internal roads within the project site
will be constructed for smooth movement of
traffic.
1.19 Closure or diversion of existing
transport routes or infrastructure
leading to changes in traffic
movements?
No There shall not be any closure or diversion of
existing transport routes. So there shall not be
any change in traffic movement.
1.20 New or diverted transmission lines or
pipelines?
No There will be no shifting of electrical
transmission line and pipeline.
1.21 Impoundment, damming, culverting,
realignment or other changes to the
hydrology of watercourses or
aquifers?
No No impoundment, damming, culverting,
realignment or other changes to the hydrology
of surface watercourses is proposed.
1.22 Stream crossings? No As such no river or drain is passing by the
project site.
1.23 Abstraction or transfers of water
form ground or surface waters?
Yes Total water requirement for the proposed
project activity will be 425 KLD including Fresh
water (286 KLD) and recycled water (139 KLD).
The water will be sourced from private water
tanker supply and Greater Noida Industrial
Development Authority.
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 9 J M Environet Pvt. Ltd.
If required ground water will be abstracted only
after getting prior permission from CGWA.
1.24 Changes in water bodies or the land
surface affecting drainage or run-off?
No There shall be no effect on Surface Drainage /
Runoff as the required land for the project is
with no any water body near the project site.
For collecting storm water, storm water
drainage network has been provided during the
design as per the guidelines. Adequate measures
will be taken to collect run off and suitable
garlanding drain as per the existing contours of
the plot will be developed.
1.25 Transport of personnel or materials
for construction, operation or
decommissioning?
Yes Transport of personnel/material during the
construction and operation of the project shall
be envisaged. Construction material shall be
transport through trucks /lories During the
operational phase sufficient parking space will
be provided for the vehicles like scooters, cars
and bus.
1.26 Long-term dismantling or
decommissioning or restoration
works?
No This is a new construction of Building project,
hence no Long-term dismantling or
decommissioning or restoration works.
1.27 Ongoing activity during
decommissioning which could have
an impact on the environment?
No Not Applicable, as this is a new construction of
Building project.
1.28 Influx of people to an area in either
temporarily or permanently?
Yes During construction phase All the workers
employed / hired will be from nearby areas.
Hence, there will be minor influx of people in
the area. Temporarily local labours will visit the
site during the construction phase.
During operation phase in 857 D.U. plus 86
Servant Units there will influx of 6327 persons
(Residents 3942 + 2385 Visitor) persons will be
involved in the project.
1.29 Introduction of alien species? No There will not be Introduction of alien species as
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 10 J M Environet Pvt. Ltd.
this is a building construction Group Housing
project in which all the trees and plants that are
proposed to be planted are native to the area.
1.30 Loss of native species or genetic
diversity?
No There will no loss of native species or genetic
diversity as the site is vacant and avoid any
major plant/Tree species. Although no such case
is reported from the area so far. As
environmental disturbance is not much and it is
not likely in future also.
1.31 Any other actions? None None, no other actions will be required except
mentioned above.
2222.... Use of Natural resources for construction or operation of the Project (such as land, water, Use of Natural resources for construction or operation of the Project (such as land, water, Use of Natural resources for construction or operation of the Project (such as land, water, Use of Natural resources for construction or operation of the Project (such as land, water,
materials or energy, especially any resourcmaterials or energy, especially any resourcmaterials or energy, especially any resourcmaterials or energy, especially any resources which are nones which are nones which are nones which are non----renewable or in short supply):renewable or in short supply):renewable or in short supply):renewable or in short supply):
S. S. S. S.
No.No.No.No.
Information/Information/Information/Information/ checklist confirmationchecklist confirmationchecklist confirmationchecklist confirmation Yes/ Yes/ Yes/ Yes/
NoNoNoNo
Details thereof (with approximate quantities Details thereof (with approximate quantities Details thereof (with approximate quantities Details thereof (with approximate quantities
/rates, wherever possible) with source of /rates, wherever possible) with source of /rates, wherever possible) with source of /rates, wherever possible) with source of
information datainformation datainformation datainformation data
2.1 Land especially undeveloped or
agricultural land (ha)
No The land involve in project is undeveloped land
which is given on lease /allotted by GNIDA. The
total land area of the project is 2.0 Hect. (20000
Sqm/4.94 Arces). The area earmarked for
residential land use purpose as per master plan of
the area. The area around the project site is
under rapid development.
2.2 Water (expected source &
competing users) unit: KLD
Yes During Construction phase water requirement
will be 35 KLD to 60 KLD, which will be source
through hired water Tankers arrange by
contractor.
During Operation phase total water requirement
for the proposed project activity will be 425 KLD
which includes Fresh water (286 KLD) and
recycled water (139 KLD).
The water will be sourced from Hired Private
Water Tankers supplying water from safe zone.
Waste water will be treated in STP. Dual
Plumbing system has been proposed for recycling
the treated water for flushing, horticulture
purpose.
2.3 Minerals (MT) Yes Sand and stone aggregates will be used as
Construction material.
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 11 J M Environet Pvt. Ltd.
2.4 Construction material–stone,
aggregates, sand / soil (expected
source – MT)
Yes Usual construction materials will be utilized like
Cements, Bricks, Sand, Iron rods, Fly ash based
products, etc.
Source: Steel and cement will be procured from
authorized vendors. Sand & aggregate will be
procured from local material suppliers.
2.5 Forests and timber (source – MT) Yes Timber required will be taken from nearby
markets.
2.6 Energy including electricity and fuels
(source, competing users) Unit: fuel
(MT), energy (MW)
Yes The power RequirementThe power RequirementThe power RequirementThe power Requirement for the proposed for the proposed for the proposed for the proposed
projectprojectprojectproject::::----
TTTTotal connected loadotal connected loadotal connected loadotal connected load - 6809.60 KW
Demand LoadDemand LoadDemand LoadDemand Load - 3662.30 KW.
Source of electricitySource of electricitySource of electricitySource of electricity: State Electricity board.
3 DG Sets of total capacity 2520 KVA (2X1010
KVA + 1X500 KVA DG Sets) Heat Exchanger
Type will be installed for power back up in case
of power failure.
2.7 Any other natural resources (use
appropriate standard units)
No Not applicable, not any natural resources will be
required except mentioned above.
3. 3. 3. 3. Use, storage, transport, Use, storage, transport, Use, storage, transport, Use, storage, transport, handling or production of substances or materials, which could be handling or production of substances or materials, which could be handling or production of substances or materials, which could be handling or production of substances or materials, which could be
harmful to human health or the environment or raise concerns about actual or perceived risks to harmful to human health or the environment or raise concerns about actual or perceived risks to harmful to human health or the environment or raise concerns about actual or perceived risks to harmful to human health or the environment or raise concerns about actual or perceived risks to
human health.human health.human health.human health.
S. S. S. S.
No.No.No.No.
Information/Checklist confirmationInformation/Checklist confirmationInformation/Checklist confirmationInformation/Checklist confirmation Yes/Yes/Yes/Yes/
NoNoNoNo
Details thereof (with approximDetails thereof (with approximDetails thereof (with approximDetails thereof (with approximate quantities/ate quantities/ate quantities/ate quantities/
rates, wherever possible) with source of rates, wherever possible) with source of rates, wherever possible) with source of rates, wherever possible) with source of
information datainformation datainformation datainformation data
3.1 Use of substances or materials,
which are hazardous (as per MSIHC
rules) to human health or the
environment (flora, fauna, and
water supplies)
No The project is a Building project and hence, no
storage of hazardous chemicals (as per MSIHC
rules) will be done, except HSD required to run
D.G. sets, for which the quantity stored will
be below the threshold limit specified in the
MSIHC rules. Necessary permission will be
obtained from the Explosives Dept.
3.2 Changes in occurrence of disease or
affect disease vectors (e.g. insect or
water borne diseases)
No Suitable drainage and waste management
measures will be adopted in both the
Construction and Operational Phase, which will
restrict stagnation of water or accumulation of
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 12 J M Environet Pvt. Ltd.
waste. This will effectively restrict the
reproduction and growth of disease vectors.
3.3 Affect the welfare of people e.g. by
changing living conditions?
No No use, storage, transport, handling or
production of any harmful product will be
envisaged from the project. Thus no major
adverse impacts on the human health/
environment are envisaged.
Moreover this project will help in increasing
socio-economic standards of the local people. It
will generate employment. Thus, the project is
supposed to have major beneficial impacts.
3.4 Vulnerable groups of people who
could be affected by the project e.g.
hospital patients, children, the
elderly etc.,
No No effect is envisaged due to this project.
3.5 Any other causes None Not applicable, as there not any other risk will be
developed except mentioned above.
4.4.4.4. Production of solid wastes during construction or operation or decommissioning (MT/month)Production of solid wastes during construction or operation or decommissioning (MT/month)Production of solid wastes during construction or operation or decommissioning (MT/month)Production of solid wastes during construction or operation or decommissioning (MT/month)
S. No.S. No.S. No.S. No. Information/Checklist confirmationInformation/Checklist confirmationInformation/Checklist confirmationInformation/Checklist confirmation Yes/ Yes/ Yes/ Yes/
NoNoNoNo
Details thereoDetails thereoDetails thereoDetails thereof (with approximate f (with approximate f (with approximate f (with approximate
quantities/rates, wherever possible) with source quantities/rates, wherever possible) with source quantities/rates, wherever possible) with source quantities/rates, wherever possible) with source
of information dataof information dataof information dataof information data
4.1 Spoil, overburden or mine wastes No No spoil, overburden or mine waste will be
generated in this case. However excavated earth
material will be generated during digging of
foundations and Basement .The approx quantity
of earth material will be 9700 Cu.m. Same shall
use in site development levelling and gardening/
Horticulture activities.
4.2 Municipal waste (domestic and or
commercial wastes)
Yes Approximately 2370.15 kg/day of solid waste
will be generated from the project activity; these
will be collected from designated locations and
segregated into inorganic and organic wastes.
Organic waste converter will be installed at site &
Organic biodegradable waste will be composted
in the composter with in project site.
The inorganic non-biodegradable wastes will be
segregated and sold to Authorized vendors for
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 13 J M Environet Pvt. Ltd.
recycling as per MSW rules, 2016. The sludge
generated from STP will be used as manures in
horticulture after decomposition or it would be
composted in composter
4.3 Hazardous wastes (as per
Hazardous Waste Management
Rules)
No NO hazardous waste will be generated from the
site as this is a building construction project. Only
used spent oil would be generated from
operation of D.G. sets. Spent Oil from D.G. sets
will be carefully stored in High Density Polythene
(HDPE) drums in isolated covered facility. This
spent oil will be handed over to some authorized
processor. Suitable care will be taken so that spills
/ leaks of spent oil from storage could be
avoided.
The used oil generated from DG set will be
disposed off as per H.W. (M & H) Rules, 2016.
4.4 Other industrial process wastes No Not applicable, as this is a Building project thus
there will not be any production of industrial
waste during construction or operation.
4.5 Surplus product No Not applicable, as this is a New Building project.
4.6 Sewage sludge or other sludge from
effluent treatment
Yes The Sewage sludge (10-15 kg/day) will generate
from the project STP which shall be
processed/dried through filter press and
composited in organic waste composter and will
be used as manures in horticulture /plantations
4.7 Construction or demolition wastes Yes Construction waste generation will be limited
to the construction phase only and will be
limited to project site only. The same will be
managed as per New C&D Rules-2016. Material
will be reused for levelling, backfilling and site
preparation and road construction after manual
segregation. Unusable and excess construction
debris will be disposed at designated places in
tune with the local norms. Some quantity of
construction debris will be used for road
construction site development activities.
The excavated earth material (i.e.97000 Cu.m)
shall be utilized at site for the purpose of back
filling, green area development, and other site
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 14 J M Environet Pvt. Ltd.
development activities and rest excess soil will be
disposed in low laying site /areas.
4.8 Redundant machinery or equipment No No Redundant machinery or equipment is
involved.
4.9 Contaminated soils or other
materials
No No Contaminated soils or other materials are
involved.
4.10 Agricultural wastes No Not applicable, as this is a New construction
project of building thus there will not be any
Agriculture Wastes produced during construction
or operation phase.
4.11 Other solid wastes No Not applicable, as there not any other solid
waste produces except mentioned above.
5.5.5.5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)
S. S. S. S.
No.No.No.No.
InfoInfoInfoInformation/Checklist confirmationrmation/Checklist confirmationrmation/Checklist confirmationrmation/Checklist confirmation Yes/ Yes/ Yes/ Yes/
NoNoNoNo
Details thereof (with approximate quantities/Details thereof (with approximate quantities/Details thereof (with approximate quantities/Details thereof (with approximate quantities/
rates, wherever possible) with source of rates, wherever possible) with source of rates, wherever possible) with source of rates, wherever possible) with source of
information datainformation datainformation datainformation data
5.1 Emissions from combustion of fossil
fuels from stationary or mobile
sources
No This is not applicable as this is Building
construction project .There will not be any
emissions from combustion of fossil fuels in the
project.
There will be minor/minimum emission of PM,
SOX & NOX through operation of DG sets only
which will be operate during power failure
only.
5.2 Emissions from production processes No Not applicable, as this is a Building project and
there is not any production process.
5.3 Emissions from materials handling
including storage or transport
Yes Dust may arise due to the materials handling
during the construction phase which will be
restricted to the construction phase and
construction site only.
Dust emission will be prevented by regular
sprinkling of water and by providing tarpaulin
covers.
5.4 Emissions from construction activities
including plant and equipment
Yes Dust emission will be restricted to construction
phase and construction site only. The dust
emitted will be of negligible amount and will be
generated due to movement of the equipments.
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 15 J M Environet Pvt. Ltd.
Suitable preventive measures will be taken.
5.5 Dust or odours from handling of
materials including construction
materials, sewage and waste
Yes There is chance of dust emission during the
construction phase which will be prevented by
the sprinkling of water and covering the raw
material by tarpaulin cover. Better sanitation
facilities will be provided to workers so that
there will be no odour generation.
5.6 Emissions from incineration of waste No Not applicable, as this is a Building project and
there will not be any incineration of wastes. As
entire waste generated from the project shall be
manage and dispose as per new waste
management Rules 2016.
5.7 Emissions from burning of waste in
open air (e.g. slash materials,
construction debris)
No Open burning of biomass / other material will
be prohibited. As entire waste generated from
the project shall be manage and dispose as per
new waste management Rules 2016.
5.8 Emissions from any other sources No Not applicable, no other actions will be
required except mentioned above.
6666 Generation of Noise andGeneration of Noise andGeneration of Noise andGeneration of Noise and Vibration, and Emissions of Light and Heat:Vibration, and Emissions of Light and Heat:Vibration, and Emissions of Light and Heat:Vibration, and Emissions of Light and Heat:
S. S. S. S.
No.No.No.No.
Information/Checklist confirmationInformation/Checklist confirmationInformation/Checklist confirmationInformation/Checklist confirmation Yes/ Yes/ Yes/ Yes/
NoNoNoNo
Details thereof (with approximate quantities/Details thereof (with approximate quantities/Details thereof (with approximate quantities/Details thereof (with approximate quantities/
rates, wherever possible) with source of rates, wherever possible) with source of rates, wherever possible) with source of rates, wherever possible) with source of
information data with source of information information data with source of information information data with source of information information data with source of information
datadatadatadata
6.1 From operation of equipment e.g.
engines, ventilation plant, crushers
No Not applicable, as this is Building Construction
project no process operation involved in this
project, However during the operation phase of
this Group Housing project, the noise emission is
caused only due to DG sets installed for backup
power supply. As the DG sets will be placed in
an acoustic enclosure, hence the noise generated
meets the ambient standard as per MoEF norms.
6.2 From industrial or similar processes. No Not Applicable
6.3 From construction or demolition Yes The machinery used for the construction activity
will be of high standard and of reputed make
and according to the international standards.
These standards themselves take care of noise
pollution control/vibration control and air
emission control. Hence insignificant impacts due
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 16 J M Environet Pvt. Ltd.
to construction machinery are envisaged. Apart
from this the construction activity will be carried
out in day time only.
During the operation phase of the project, the
noise emission is caused only due to DG sets
installed for backup power supply. As the DG
sets will be placed in an acoustic enclosure, hence
the noise generated meets the ambient standard
as per MoEF norms.
Due to the various construction activities, there
will be short-term noise impacts in the immediate
vicinity of the project site. The construction
activities will include the following noise
generating activities: Operation of DG sets,
concreting & mixing, Excavation for foundation
and grading of the site, Construction plant and
heavy vehicle movement, Construction of
structures and facilities.
6.4 From blasting or piling No No blasting or mechanized piling will be done in
construction phase.
6.5 From construction or operational
traffic
Yes Some noise will be generated from vehicular
movement in the construction and operational
phase. Every possible provision will be taken up
to avoid/minimize traffic chaos. During
construction phase noise will be generated due
to excavation machineries, movement of heavy
vehicles like trucks. In Operational phase major
source of noise is D.G. set which will operate in
case of power failure.
Noise level will be reduce by putting
Screens/Barricades at Construction site.
Increase in noise and vibration due to traffic of
project site will be marginal. Hence noise and
vibration due to traffic is not anticipated on the
project site. This will be minimized by plantation
along the roadside.
6.6 From lighting or cooling systems No Not envisaged.
6.7 From any other sources No There will be no other sources for noise &
vibration generation except the mentioned
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 17 J M Environet Pvt. Ltd.
above.
7. 7. 7. 7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, Risks of contamination of land or water from releases of pollutants into the ground or into sewers, Risks of contamination of land or water from releases of pollutants into the ground or into sewers, Risks of contamination of land or water from releases of pollutants into the ground or into sewers,
surface waters, groundwater, coastal waters or the sea:surface waters, groundwater, coastal waters or the sea:surface waters, groundwater, coastal waters or the sea:surface waters, groundwater, coastal waters or the sea:
S. S. S. S.
No.No.No.No.
Information/Checklist confirmationInformation/Checklist confirmationInformation/Checklist confirmationInformation/Checklist confirmation Yes/ Yes/ Yes/ Yes/
NoNoNoNo
Details thereof (with approximate quantities/Details thereof (with approximate quantities/Details thereof (with approximate quantities/Details thereof (with approximate quantities/
rates, wherever possible) with source of rates, wherever possible) with source of rates, wherever possible) with source of rates, wherever possible) with source of
information datainformation datainformation datainformation data
7.1 From handling, storage, use or
spillage of hazardous materials
No Not applicable as no handling, storage, use or
spillage of hazardous material in the project only
Used spent oil from D.G. Sets will be generated
and same will be handled with care, it will be
stored in HDPE drums and provided to authorize
vendor. Hence, no risk of contamination is
envisaged.
7.2 From discharge of sewage or other
effluents to water or the land
(expected mode and place of
discharge)
No The waste water generated from the project will
be reused for flushing of toilets and green area
development and rest excess treated will drain to
municipal sewer line after prior permission from
concern authority for further treatment in CETP.
Therefore there will not be any contamination of
land and water due to project.
7.3 By deposition of pollutants emitted
to air into the land or into water.
No There will not be any deposition of pollutants
emitted to air into the land or into water due to
project as this is building construction project.
Air emissions will be generated due to increased
vehicular movement and occasional use of D.G.
set for which effective measures will be taken like
sufficient greenbelt development and use of low
sulphur diesel in D.G. sets etc. So, there would
not be any deposition of pollutants emitted to
air, land or water.
7.4 From any other sources No There will be no other sources which can
contaminate land & water resources.
7.5 Is there a risk of long term build up
of pollutants in the environment
from these sources?
No Not applicable in this project as it is a building
construction project, in which construction
activities will be confined to limited time period
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 18 J M Environet Pvt. Ltd.
only and even.
Likelihood of such an event is not foreseen till
now in the area and suitable measures will be
adopted to control and reduce emission, so that
there will be no such risk in the coming future.
8.8.8.8. Risk of accidents during constrRisk of accidents during constrRisk of accidents during constrRisk of accidents during construction or operation of the Project, which could affect human health uction or operation of the Project, which could affect human health uction or operation of the Project, which could affect human health uction or operation of the Project, which could affect human health
or the environmentor the environmentor the environmentor the environment
S. S. S. S.
No.No.No.No.
Information/Checklist confirmationInformation/Checklist confirmationInformation/Checklist confirmationInformation/Checklist confirmation Yes/ Yes/ Yes/ Yes/
NoNoNoNo
Details thereof (with approximate quantities/Details thereof (with approximate quantities/Details thereof (with approximate quantities/Details thereof (with approximate quantities/
rates, wherever possible) with source of rates, wherever possible) with source of rates, wherever possible) with source of rates, wherever possible) with source of
information datainformation datainformation datainformation data
8.1 From explosions, spillages, fires etc
from storage, handling, use or
production of hazardous substances
No The entire building shall be designed as per
N.B.C. guidelines of India pertaining to fire
hazards. They will apply good construction
safety practices at the project. All precautionary
measures will be adopted and use of protective
footwear and helmet will be mandatory.
However, to meet out the minor incidences and
accidents first aid measures at site will be
provided.
Fire safety measures include Fire extinguishers,
Water tanks, Yard hydrants, hose reels,
automatic detection system, illuminated Exit
signs, sprinkler system and compartmentalisation
etc.
There are very little chances of explosion,
spillages and fire. There will be provision of
personal protective equipment as required
under the health & safety norms for the
workers during the time of construction
activities. Over and above awareness and
training will be provided to all the supervisors
dealing with construction workers during the
construction activity.
As such no hazardous product or substances will
be stored within project site and also no
industrial or process activity is involved in the
project hence chances of chemical hazards and
accidents are minimal. However, there will be
suitable fire fighting measures will be provided
to reduce chances of fire-accidents.
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 19 J M Environet Pvt. Ltd.
8.2 From any other causes No No other causes are involved except the
mentioned above.
8.3 Could the project be affected by
natural disasters causing
environmental damage (e.g. Floods,
earthquakes, landslides, cloudburst
etc)?
No No cases are reported so far and chances are
minimal. The site is selected carefully keeping in
view all the factors to avoid any environmental
damage due to natural disasters. The project
area falls in Zone-IV of seismic Zoning Map of
India. The seismic factors have been
appropriately incorporated in the civil designs
for the proposed Construction Project
9.9.9.9. Factors which should be considered (such as consequential development) which could lead to Factors which should be considered (such as consequential development) which could lead to Factors which should be considered (such as consequential development) which could lead to Factors which should be considered (such as consequential development) which could lead to
environmenenvironmenenvironmenenvironmental effects or the potential for cumulative impacts with other existing or planned tal effects or the potential for cumulative impacts with other existing or planned tal effects or the potential for cumulative impacts with other existing or planned tal effects or the potential for cumulative impacts with other existing or planned
activities in the localityactivities in the localityactivities in the localityactivities in the locality
S. S. S. S.
No.No.No.No.
Information /Information /Information /Information / Checklist confirmChecklist confirmChecklist confirmChecklist confirmaaaationtiontiontion Yes/ Yes/ Yes/ Yes/
NoNoNoNo
Details theDetails theDetails theDetails therererereof of of of ((((wwwwiiiitttth apph apph apph apprrrroximate qoximate qoximate qoximate quauauauantitiesntitiesntitiesntities ////
rrrraaaates, tes, tes, tes, wwwwhehehehererererevvvver possible)er possible)er possible)er possible) wwwwiiiithththth source source source source oooof f f f
informinforminforminformation dation dation dation daaaatatatata
9.1 Lead to development of supporting
utilities, ancillary development or
development stimulated by the
project which could have impact on
the environment e.g.
Yes The project activity will have positive impact on
the ancillary infrastructure like roads, markets,
conventional shops, public health amenities, and
conveyance facilities in the area.
•Supporting infrastructure (roads,
power supply, waste or waste water
treatment, etc.)
Yes The project will have positive impact on the
ancillary infrastructure like roads, markets,
public health, amenities, conveyance facilities
etc. in the area.
• housing development No Not applicable
• extractive industries No Not applicable
• supply industries No Not applicable
• other No Not applicable
9.2 Lead to after-use of the site, which
could have an impact on the
environment
No Not applicable
9.3 Set a precedent for later developments Yes Negligible impact is envisaged on air, noise and
aesthetic parameters due to the proposed
project. A beautiful after use scenario, which is
likely to increase aesthetics of the area &
greenery, May set precedence for subsequent
entrepreneurs who venture such projects.
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 20 J M Environet Pvt. Ltd.
9.4 Have cumulative effects due to
proximity to other existing or
planned projects with similar effects
No The proposed project is a Building project. A
better-planned and executed project has to yield
better result individually.
(III)(III)(III)(III) Environmental SensitivityEnvironmental SensitivityEnvironmental SensitivityEnvironmental Sensitivity
S. S. S. S.
No.No.No.No.
AreasAreasAreasAreas Name/ Name/ Name/ Name/
IdentityIdentityIdentityIdentity
Aerial distance (within 15 km.) Aerial distance (within 15 km.) Aerial distance (within 15 km.) Aerial distance (within 15 km.)
Proposed projecProposed projecProposed projecProposed project location boundaryt location boundaryt location boundaryt location boundary
1 Areas protected under international
conventions, national or local legislation
for their ecological, landscape, cultural or
other related value
Okhla Wild
Life Bird
Santuary
Surajpur
Wetland
and Reserve
• Okhla Wild Life Bird SantuaryOkhla Wild Life Bird SantuaryOkhla Wild Life Bird SantuaryOkhla Wild Life Bird Santuary
located at 12 kms from the
project site in SW direction.
• Surajpur Wetland and Reserve Surajpur Wetland and Reserve Surajpur Wetland and Reserve Surajpur Wetland and Reserve
Forest is located at the distance
of approx. 8 kms in SE
direction
2 Areas which are important or sensitive for
ecological reasons - Wetlands,
watercourses or other water bodies,
coastal zone, biospheres, mountains,
forests
Hinden
River
Yamuna
River
• Approx. 3Approx. 3Approx. 3Approx. 3 km in W direction km in W direction km in W direction km in W direction
of the project site approx.
• Approx. Approx. Approx. Approx. 11111111 km in km in km in km in SSSSWWWW direction direction direction direction
from project site approx.
3 Areas used by protected, important or
sensitive species of flora or fauna for
breeding, nesting, foraging, resting, over
wintering, migration
None
Not located within 15 km of the
project location.
4 Inland, coastal, marine or underground
waters
None Not located within 15 km of the
project location.
5 State, National boundaries Delhi State
border
Approx. 13 km in West direction from
project site.
6 Routes or facilities used by the public for
access to recreation or other tourist,
pilgrim areas
Greater
Noida Link
Road
Greater Noida Link Road located at a
distance of approx. 2.0 km in E
direction from project site
7 Defence installations None Not located within 15.0 km of the
proposed project location.
8 Densely populated or built-up area Noida The Project site is located in
Development Authority premises of
Greater Noida Industrial Development
Authority. The site is surrounded by
moderately populated built up area.
9 Areas occupied by sensitive man-made
land uses (hospitals, schools, places of
Yes There are number of major hospitals,
schools etc. There are numerous places
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 21 J M Environet Pvt. Ltd.
worship, community facilities) of worship and community within the
project influenced area.
10 Areas containing important, high quality
or scarce resources (Ground water
resources, surface resources, forestry,
agriculture, fisheries, tourism, minerals)
Yes Ground-water resources in the study
area are depleting at very fast rate and
are declared as scarce resource.
11 Areas already subjected to pollution or
environmental damage. (Those where
existing legal environmental standards
are exceeded)
No No Environmental damage reported
from the area so far. All parameters
of Air, Water, and Noise etc. will be
maintained within permissible limits
specified by SPCB / CPCB with
proper mitigation measures.
12 Areas susceptible to natural hazard which
could cause the project to present
Environmental problems (Earthquakes,
subsidence, landslides, erosion, flooding
or extreme or adverse climatic conditions)
None The area under study falls in Zone-
IV, according to the Indian Standard
Seismic Zoning Map. Suitable seismic
coefficients in horizontal and
vertical directions respectively, will
be adopted while designing the
structures to mitigate the seismic
impacts.
There are no possibilities of the
proposed project site getting flooded
as per records available.
(IV)(IV)(IV)(IV) Proposed Terms of Reference for EIA studiesProposed Terms of Reference for EIA studiesProposed Terms of Reference for EIA studiesProposed Terms of Reference for EIA studies:::: Not ApplicableNot ApplicableNot ApplicableNot Applicable
“I hereby given undertaking that the data and information given in the application and enclosures
are true to the best of my knowledge and belief and I am aware that if any part of the data and
information submitted is found to be false or misleading at any stage, the project will be rejected
and clearance give, if any to the project will be revoked at our risk and cost.”
Proposed Group Housing Project,
At Plot No. –GH-11A, Sector-01, Greater Noida, District Gautam Budh Nagar (U.P.) (Form Form Form Form –––– 1111))))
Project Proponent EIA Consultant
Enticement Infrastructure Pvt. Ltd. 22 J M Environet Pvt. Ltd.
Date:Date:Date:Date:
Place:Place:Place:Place:
Signature of the applicant
Mr. Himanshu Goyal
(Authorized Signatory)
Enticement Infrastructure Pvt. Ltd.Enticement Infrastructure Pvt. Ltd.Enticement Infrastructure Pvt. Ltd.Enticement Infrastructure Pvt. Ltd.
B1/105 , Tower 8,
Purvanchal Silver City 2, opp. Wipro, Pi 2,
Greater Noida, Uttar Pradesh -201306
NOTE:NOTE:NOTE:NOTE:
1. The projects involving clearance under Coastal Regulation Zone Notification, 1991 shall
submit with the application a C.R.Z map duly demarcated by one of the authorized agencies,
showing the project activities, w.r.t. C.R.Z (at the stage of TOR) and the recommendations of
the State Coastal Zone Management Authority (at the stage of EC). Simultaneous action shall
also be taken to obtain the requisite clearance under the provisions of the C.R.Z Notification,
1991 for the activities to be located in the CRZ.
2. The projects to be located within 10 km of the National Parks, Sanctuaries, Biosphere
Reserves, Migratory Corridors of Wild Animals, the project proponent shall submit the map
duly authenticated by Chief Wildlife Warden showing these features vis-a-vis the project
location and the recommendations or comments of the Chief Wildlife Warden "thereon (at
the stage of EC)."
3. All correspondence with the Ministry of Environment & Forests including submission "of
application for TOR/Environmental Clearance, subsequent clarifications, as may be required
from time to time, participation in the EAC Meeting on behalf of the project proponent shall
be made by the authorized signatory only. The authorized signatory should also submit a
document in support of his claim of being an authorized signatory for the specific project".