Post on 03-Apr-2018
transcript
7/28/2019 PTCC EHS Plan With Pages
1/22
E H S
4137 Ponte Street, Brgy. Sta. Cruz,Makati City, PhilippinesTel. No. (02) 519-6214Fax. No. (02) 890-2802
www.ptcerna.com
P.T. Cerna Construction Environmental Health & Safety Plan 1
7/28/2019 PTCC EHS Plan With Pages
2/22
E H S
TITLE PAGE
Section 1 GENERAL / ADMINISTRATIVE
1.1 Introduction 1
1.2 Company Safety Policy 1
1.3 Functions and Responsibilities 1
Section 2 CONSTRUCTION SAFETY PRACTICES
2.1 General Safe Practices 3
2.2 Barricades, Warning and Safety Signages 3
2.3 Regulatory Compliance 4
2.4 Claims 4
2.5 Safety Communication and Safety Management 4
2.6 Compressed Gas Cylinders 5
2.7 Concrete and Masonry Construction 5
2.8 Cranes, Hoist and Riggings 5
2.9 Control Measures 6
2.10 Emergency Notification Procedures 6
2.11 Excavation and Trenching 7
2.12 Housekeeping 9
2.13 Safety Equipment 9
2.14 Safety Orientation 11
2.15 Ladders and Scaffolds 11
TITLE PAGE
P.T. Cerna Construction Environmental Health & Safety Plan 2
7/28/2019 PTCC EHS Plan With Pages
3/22
E H S
2.16 Parking / Traffic 12
2.17 Pre-Job Briefings 13
2.18 Work Permit 13
2.19 Tools and Equipment Inspection Procedure 13
2.20 Tools and Equipment Inspection Procedure 14
Section 3 FIRE PREVENTION
3.1 General Fire Prevention 14
3.2 Fire Extinguisher Requirements for Active ConstructionSites
14
3.3 Hot Work Permit 15
3.4 Fire System Work / Red Tag Process 16
3.5 Welding, Cutting and Brazing 16
ENVIRONMENTAL HEALTH and SAFETY PLAN
P.T. Cerna Construction Environmental Health & Safety Plan 3
7/28/2019 PTCC EHS Plan With Pages
4/22
E H S
SECTION 1 GENERAL / ADMINISTRATIVE
1.1 INTRODUCTION
1.1.1 The Environmental Health and Safety (EHS) plan was establishedand developed to provide management and supervision guidelinesand roadmaps of the accident prevention program of the company.It outlines techniques and procedures which are essential for theprotection of the companys greatest asset its people.
1.1.2 The program was designed to encourage, promote and require thatEHS be integrated into all phases of the construction. Comply with;and enforce all programs, rules, regulations relevant to the workbeing performed.
1.1.3 The goal is to Perform all Work required by the Contract in a safe,healthy and
environment friendly manner.
1.1.4 Ensure the workers and subcontractor employees have a goodworking knowledge of
the companys environmental, health and safety (EHS) rules andprocedures along with those required by customer.
1.2 COMPANY SAFETY POLICY
1.2.1 To provide and maintain a safe and healthful working condition for itspeople.
1.2.2 To develop and maintain a vigorous Safety and Accident PreventionProgram to
avoid human suffering and financial losses.
1.2.3 To hold responsible every manager or supervisor who supervisesor directs the work
of others in assuring the safety of each employer under hissupervision.
1.2.4 To guide employees in maintaining safe and impose correspondingpenalty for
violations committed.
1.2.5 To give reward to employees, departments or projects who haveattained an
excellent safety record.
1.3 FUNCTIONS AND RESPONSIBILITIES
1.3.1 Safety Department
The Safety Department is responsible for:
P.T. Cerna Construction Environmental Health & Safety Plan 4
7/28/2019 PTCC EHS Plan With Pages
5/22
E H S
1.3.1.1 Developing, implementing and administering all aspects ofaccident prevention;
fire protection and prevention; first aid policies and proceduresand programs on all projects, offices and facilities.
1.3.1.2 Monitoring P.T. Cerna Corporation compliance with standardsand procedures promulgated by the Department of Labor, Bureauof Working Conditions, Health and Safety Division.
1.3.1.3 Reviewing standards and regulations promulgated by theDOLE, Health and Safety Division and other government agencies,and formulating uniform interpretations and complianceprocedures which are disseminated to affected departments.
1.3.1.4 Providing technical liaison with construction engineering,procurement, medical and labor relations department.
1.3.1.5 Coordinating project safety, fire protection and first aidprograms within divisional organization.
1.3.1.6 Staffing project sites with safety personal and in some casesincluding security, medical and employee relations.
1.3.2 Department/Project Manager
1.3.2.1 Responsible for ensuring the establishment of safetyprograms which conforms to the Companys Environmental Healthand Safety Plan
1.3.2.2 Responsible for monitoring project/department safetyplanning and supervisory safety performance and implementingcorrective measures when required.
1.3.3 Superintendent/Supervisor
1.3.3.1 Responsible for ensuring safety planning and executingwork in compliance
with the Companys established safety procedures,Government Safety andHealth regulations, standard and procedures as well as clients
requirements.
1.3.4 On-Site Safety Representatives
1.3.4.1 Full-time On-Site Safety Representative (s) to help ensureadequate project
safety and health oversight. The On-Site SafetyRepresentative (s) shall have
appropriate knowledge and skills, to ensure job site safety.Basic qualifications
P.T. Cerna Construction Environmental Health & Safety Plan 5
7/28/2019 PTCC EHS Plan With Pages
6/22
E H S
shall be in accordance with Rule 1030 (Training of Personnelin Occupational
Safety and Health) of the Occupational Safety and HealthStandards of the
Philippines and Department of Labor and Employment Order#16.
SECTION 2 CONSTRUCTION SAFETY PRACTICES
2.1 GENERAL SAFE PRACTICES
2.1.1Check the area to determine what problem or hazards that exist.
2.1.2 Your activity may endanger fellow workers or nearby equipment
and materials. Take
necessary steps to safeguard them.
2.1.3 Review the requirements of each assigned job with your supervisor.
You will not be expected to do job which might result in injury to
yourself or others.
2.1.4 A safety rule can only be changed when life or property is in
immediate danger an
by permission of safety top management.
2.1.5 Be sure you understand emergency instructions. Anticipate what
you will do in case of an emergency. Above all, be calm.
2.1.6 Do not wear jewelries (rings, bracelets, or neck chains) on the job.
2.1.7 Report unsafe equipment, hazardous conditions and unsafe acts to
your supervisor.
2.1.8 Use safety equipment when it is specified for the job. Safety
equipment is available at the tool room.
2.1.9 Practice good housekeeping in your work area. Pick up your tools.
Do not leave materials and scarp where they will be hazardous to
others.
P.T. Cerna Construction Environmental Health & Safety Plan 6
7/28/2019 PTCC EHS Plan With Pages
7/22
E H S
2.1.10For your protection, obey all warning signs such as Keep Out No
Smoking, Eye Protection Required and Authorized Personnel
Only.
2.1.11Do not take shortcuts. Use appropriate ladders, ramps, stairways,
and paths.
2.1.12Do not use compressed air or oxygen to blow dust or dirt from
clothing or skin.
2.1.13Carbon tetrachloride must not be used for any purpose on the job.
2.1.14Adequate sanitary facilities are provided on the jobsite. Do not use
any other area.
2.1.15You must not engage in horseplay or roughhousing on the jobsite.
To do so may lead to injury.
2.1.16Failure to follow practices relating to your safety or that of fellow
employees or failure to safeguard equipment, tools or materials
properly may lead to your discharge.
2.2 BARRICADES, WARNINGS AND SAFETY SIGNAGES
2.2.1 We shall provide all necessary barricades, safety signs,stanchions, safety
cones or safety warning tape as required to isolate and protectunsafe work areas from workers, pedestrians or vehicle traffic.
2.2.2 Where caution (yellow) warning tape or yellow chain is used asbarricade material, signs denoting the hazard shall be secured tothe barricade. Employees are allowed to pass or cross caution tapeonly after assessing the hazards posted on the signage.Caution tape and signs shall be erected around all sides of thecontrolled area, and at each access point.
2.2.3 Adequate and safe passage shall be established for workers at theactive construction site to ensure effective separation betweenvehicular paths and walkways. Appropriate caution and warning signshall be installed at crossings and when necessary, a flagman mayalso be used to control the traffic flow.
2.2.4 The walkways shall meet the applicable safety standards, includingbut not limited to proper barricade and floor/ground demarcation.
2.2.5 All barricading/signage will be removed after work is complete andhazard is
eliminated.
P.T. Cerna Construction Environmental Health & Safety Plan 7
7/28/2019 PTCC EHS Plan With Pages
8/22
E H S
2.3 REGULATORY COMPLIANCE
2.3.1 Ensure compliance with all applicable laws and regulations of any
governmental entity or sovereign authority that pertain toenvironmental, health and safety standards and / or work practices.
This will include developing and implementing appropriate job-specific EHS programs.
2.3.2 Correction of unsafe work practices, conditions, and regulatoryviolations committed by the personnel.
2.3.3 Report the conditions or practices found on site that could result inserious injury, property damage, or environmental damage
2.4 CLAIMS
2.4.1 Settlement of rightful claims from municipalities or private ownersfor road damage caused by trucks or heavy equipment drivers toand from the job sites by third-party property, by Contractor,subcontractors or suppliers, or employees of any of them. IfContractor fails to settle such claims promptly, customer shall havethe right to settle the claims and withhold the amount paid pluscustomer costs and expenses from Contractors payments under theContract.
2.5. SAFETY COMMUNICATION AND SAFETY MANAGEMENT
2.5.1 The Project Manager shall attend weekly construction operationsmeetings (or as
otherwise defined) with Project Management to review all siterelated incidents and issues and ensure site communication.
2.5.2 All workers are required to attend a daily safety meeting led bytheir safety group leader or foreman (tool box meetings) and aperiodic mass safety meeting (as scheduled).
2.5.3 All contractors will establish a means for distributing written safetymaterial as defined by the site (safety bulletins, site updates,
lessons learned, etc.).
2.5.4 Contractor management is to verify compliance with EHSrequirements by conducting site inspections and audits by SafetyManagement By Walking Around.
2.5.4.1 At minimum, a weekly walk around will be conductedby the project
management to reinforce correct behavior and coaching tomodify unwanted behavior.
2.5.4.2 At least one walk will be recorded weekly.
P.T. Cerna Construction Environmental Health & Safety Plan 8
7/28/2019 PTCC EHS Plan With Pages
9/22
E H S
2.6 COMPRESSED GAS CYLINDERS
2.6.1 Cylinders will be stored in designated places where they willnot be damaged by passing or falling objects.
2.6.2 Storage facilities will be designated as a non-smoking area andposted with the
names of the gases to be stored.
2.6.3 Outside storage of cylinders must be protected from adverseweather conditions.
2.6.4 The person responsible for handling, transporting orconnecting/using the cylinder must check the identity of the gas by
reading the label. If necessary, review the MSDS concerningpotential hazards.
2.6.5 All cylinders must be removed from trucks prior to use, exceptthose specially mounted for cutting and heating torches (e.g.welding trucks).
2.6.6 Cylinders will never be taken inside tanks or vessels where work isto be performed. Gas lines will be removed from space when work isnot in progress.
2.6.7 Oxygen/acetylene cutting/heating torches will have check valves onthe torch body.
2.7 CONCRETE AND MASONRY CONSTRUCTION
10.1 Shall ensure that mixing machine is in good condition and all
the moving components such as pulleys are properly guarded.
2.8 CRANES, HOIST AND RIGGINGS
2.8.1 All crane work must be pre-planned to ensure the safety of the
process. It is the responsibility of the contractor and/or craneequipment supplier to ensure any crane used on an Intel siteis in safe working condition. Documentation must be suppliedwith the crane and reviewed by project management prior toany work.
2.8.2 Documentation required:
2.8.2.1 The crane has been inspected and maintained inaccordance with the
manufacturers specifications, OSHA and ASME B.30
standards or local equivalent.
P.T. Cerna Construction Environmental Health & Safety Plan 9
7/28/2019 PTCC EHS Plan With Pages
10/22
E H S
2.8.2.2 The crane complies with all applicable regulatory orspecial requirements of the site.
2.8.2.3 Cranes will be equipped with an anti-two-blockingdevice.
2.8.2.4 Operators manual must be available in the cab of thecrane.
2.8.2.5 The crane has a current annual inspection by a personqualified to inspect
and certify cranes.
2.8.2.6 Logs for daily, weekly, monthly and annual inspections
are available in the crane cab for inspection.
2.8.2.7 The operator must have a current crane safety-trainingcard or documentation verifying the operators qualificationsto operate this specific type of crane. The crane operator willbe licensed by the local authority having jurisdiction.
2.8.2.8 Written safe crane operating procedures are availablein the cab of the crane. These are to be written by thecontractor. The operators manual may not be used in lieu ofseparate safety procedures.
2.9 CONTROL MEASURES
2.9.1 A control measures was establish to protect employees under theircontrol from
exposure to hazards, including but not limited to chemical, healthand physical hazards present at the work location.
2.10 EMERGENCY NOTIFICATION PROCEDURES
2.10.1 If such facility emergency alarm notification system will be
activated in the event ofan emergency (such as an evacuation or fire), followed by verbalexplanation of the emergency over facilitys public address system,contractor must have the presence of mind.
2.10.2We shall be responsible for accounting the number of employeesand must
immediately report any missing persons for monitoring.
2.10.3We shall oblige to follow the Emergency Response and ContingencyPlan of the company as described by the site orientation.
2.11 EXCAVATION AND TRENCHING
P.T. Cerna Construction Environmental Health & Safety Plan10
7/28/2019 PTCC EHS Plan With Pages
11/22
E H S
2.11.1Definition of Terms:
2.11.1.1 Excavation - defined as any man-made cut, cavity,trench or depression in an earth surface formed byearth removal.
2.11.1.2 Trench - defined as a narrow excavation ( in relation toits length) made below the surface of the ground.
2.11.2To prevent injury and property damage during excavation work,make adequate protective measures part of the job. Study pre-excavation conditions (superimposed loads, soil structure,hydrostatic pressure and the like) in order to evaluate changes thatmight occur, or situations that might develop and in order to planthe job ahead: One major hazard in excavation work is the presenceof underground facilities, such as utility lines (water, electricity, gasor telephone), tanks, process piping and sewers. If this dug into,undercut, or damaged in anyway, there may be injury or death toworkmen and interruption of service, contamination of water,disruption of processes and expensive delays.
2.11.2.1 Before any attempt is made to excavate, check public
utilities for
locations of underground or electric lines.
2.11.2.2 No shovel, dragline or other digging should be left in
place.
2.11.2.3 Establish a proximity limit for machine operations and
complete the
excavation by hand digging.
2.11.3When hand excavation is being done, worker must be warned
about driving picks, paving breakers, or other powered tools
through the envelope of buried facilities.2.11.4If necessary to dig near to or under the tank, it is either install
shoring or excavate of stable slope away from the outermost
edge of the tank supports, size shoring members to handle any
superimposed loads. Keep the excavated area free of water a
partially filled tank could be floated out of the ground.
2.11.5Whenever an open excavation must be made within or adjacent
to a building and lower than wall or column footings and
machinery or equipment foundations, the job should be handled
P.T. Cerna Construction Environmental Health & Safety Plan11
7/28/2019 PTCC EHS Plan With Pages
12/22
E H S
by qualified personnel to make a thorough study on the amount
and strength of shoring required before work is begun.
2.11.6Carefully study the nature of the soil, hydrostatic pressure, super-
imposed loads (both static and line), and other factors.
2.11.7Determine the need for sheet piling, shoring and bracing.
2.11.8Excavated materials should be placed at least 24 inches from the
side of the excavation unless toeboards or other effective
barricades have been installed to prevent fall back.
2.11.9When the excavation must remain open for the duration of the
construction work, barricades, fences, horses and warning signs
are necessary. The work area should be guarded by flares,
lanterns or flashlights at night.
2.11.10 A trench 4 feet or more deeps should be provided with
ladders to facilitate trench should be more than 25 feet apart and
the ladders extend from the bottom of the trench to at least 3 feet
above the ground surface.
2.11.11 In hand excavated trenches, wooden cleats should be spiked
or bolted to join the ends of braces to stringers to prevent thebraces from being knocked out of place.
2.11.12 All excavations and trenches shall have valid excavationpermits and should bemarked with warnings tapes at the end of each day and any time
during the day when work is not being performed in them for anextended period.
2.11.13 Excavations and trenches with a depth of 4 feet or more isalways considered as Confined Space.
2.11.13 Checklist For Safe Trenching
2.11.14 Before you dig, check:
2.11.14.2 Soil conditions
2.11.14.3 Nearness on buildings, utilities, heavily traffic highwaysand
any other sources of vibration.
2.11.14.4 For ground that has been previously disturbed
2.11.14.5 Closeness of streams, old sewers, under-ground cables
andconduits.
P.T. Cerna Construction Environmental Health & Safety Plan12
7/28/2019 PTCC EHS Plan With Pages
13/22
E H S
2.11.14.6 Equipment, personal protective equipment, shoring
materials, signs, barricades, lights, machinery, etc.
2.11.15 While you dig, watch for:
2.11.15.2 Changing ground conditions, particularly after rainfall
2.11.15.3 Low condition or gaseous condition in the trench
2.11.15.4 Adequacy and condition of shoring and sloping as job
progresses.
2.11.15.5 The way in and the way out of excavation
2.11.15.6 Changes in vehicle traffic patterns, keep tracks awayfrom
trench walls
2.11.15.7 That excavated material is more than 60 cms. Awayfrom
edges of the trench.
2.11.15.8 Positioning of heavy equipment or pipe
2.11.15.9 Proper positioning and adequacy of cross bracing orjacks to
prevent shoring from moving
2.11.15.10 That men know safe and proper procedures and they
do not
endanger themselves by ignoring these checks.
2.12 HOUSEKEEPING
2.12.1 Work areas shall be kept clean, free of debris, trippinghazards, etc. at all times.
2.12.2 Use of a vacuum cleaner/system to immediately remove any debris
or dust generated when operating cutting or grinding equipment orwhen performing other dirt or particle generating activities.
2.12.3 Work areas shall not be left without a full, comprehensive clean up.No materials will be left that could present a trip or other hazard. Ifmaterials need to be left, appropriate hazard identification systemsmust be employed (barricades, signage, etc.).
2.12.4 Materials are not to be left loose in racks or unsecured.
2.12.5 Adequate containers shall be provided for collection and separationof waste and trash. Waste shall be disposed of at frequent and
regular intervals.
P.T. Cerna Construction Environmental Health & Safety Plan13
7/28/2019 PTCC EHS Plan With Pages
14/22
E H S
2.13 SAFETY EQUIPMENT
2.13.1 Appropriate personal protective equipment (PPE) is issued forthe specific person
(e.g., steel-toed shoes and prescription safety glasses with sideshields) and appropriate general use PPE (e.g., hearing protectionand non-prescription safety glasses) and PPE for site specifichazards (e.g., respirators and laser eye protection).Work areas shall be kept clean, free of debris, tripping hazards, etc.
at all times.
2.13.2 Ensure that the workers/personnels have receivedtraining on the
proper use, inspection, storage and care for all PPE as requiredfor their work.
2.13.3 Head and Scalp
a. Employees working in areas where there is a possible danger ofhead injury fromimpact, or from falling or flying objects, or from electrical shockand burns, shall be protected by protective helmets.
b. Hardhats are to be worn in all construction areas unlessotherwise communicated or posted. No class C or metallichardhats are allowed on Intel sites.
c. Before each use, hardhats must be inspected for cracks, signs ofimpact or rough treatment and wear that might reduce thedegree of safety originally provided. If signs of excess wear exist,it must be discarded.
d. Hardhat suspensions must never be altered.
e. Hardhats are to be worn with the bill to the front (not backwards).
2.13.4 Eye and Face
a. Prior to work in any area with potential exposure to hazardousmaterials/chemicals, the nearest eyewash will be identified andcommunicated to all.
b. All workers must wear approved eye protection at all times insites posted.
c. Special eye hazard work areas (such as welding, torch work, etc.)will be identified in pre-task plans and appropriate eye protectionprovided.
P.T. Cerna Construction Environmental Health & Safety Plan14
7/28/2019 PTCC EHS Plan With Pages
15/22
E H S
d. Goggles will be worn if the potential for fine particles or chemicalhazards exists.Goggles will also be worn for overhead protection from
particles/dust.
2.13.5 Body
a. Where chemical hazards (corrosives, etc.) are present,appropriate protection will be provided. The protection providedmust be chosen to be resistant to the hazards and chemicalproperties as presented by the work. Reusable clothing must bedecontaminated prior to storage.
b. For hazard specific protection, such as for protection forelectrical hazards, referto the appropriate procedure as provided in this manual.
c. When welding, the neck and face will be suitably protected fromarc burns.
d. For all construction sites, workers shall be required to wear longpants and shirtswith sleeves. Project management will approve exceptions.
2.13.6 Hand
a. Protective gloves may be worn for hand protection in the cleanrooms when hands are exposed to hazards described by thisprocedure.
b. Different exposures require the use of different types of gloves.Evaluate each situation to ensure which is the appropriate typeof hand protection to use.
2.14 SAFETY ORIENTATION
2.14.1 Ensure all of its employees and subcontractors have the
proper training with regardto environmental, health, and safety orientation prior to startingwork.
2.15 LADDERS AND SCAFFOLDS
2.15.1 Ladders
2.15.1.1 Anytime a worker is working and is exposed to a fall hazardover 6 vertical
feet, as measured from the sole of their shoe, personal fallprotection will be used.
2.15.1.2 Exception:
P.T. Cerna Construction Environmental Health & Safety Plan15
7/28/2019 PTCC EHS Plan With Pages
16/22
E H S
i. Maintain at least three points of contact with the ladder atall times;
ii. Maintains center of body between the ladders verticalsupports;
iii. Co-worker supports the ladder or it is secured frommovement; and
iv. Faces the front of the ladder.
2.15.2 General Portable Ladder Requirements
2.15.2.1 Ladders must not be placed in front of doors openingtoward the ladder unless door is blocked, open, locked andposted or guarded.
2.15.2.2Ladders shall be capable of supporting the following loadswithout failure:
i. Each self-supporting portable ladder: At least four timesthe maximum intended load, except that each extra-heavy-duty type 1A metal or plastic ladder shall sustain atleast 3.3 times the maximum intended load.
2.15.2.3 Only one person on ladder at a time.
2..15.2.4 Only fiberglass ladders are allowed. No wood or metalladders.
When storing, ladders must be laid on their side orsecured with a chain, cable or approved storage devicewhen stored upright.
2.15.2.5 Manufacturers information must be on the side of theladder.
2.15.2.6 Post and/or secure area with cones or barrier tape tokeep area separate from other workers.
2.15.2.7 Carry tools or equipment in tool belts or bags, handedup or down to
different levels or lifted by a mechanical hoist.
i. A signage system will be used to communicate thestatus of the ladder.
2.15.3 Scaffolds
2.15.3.1 Each scaffold and scaffold component shall becapable of supporting, without failure, its own
P.T. Cerna Construction Environmental Health & Safety Plan16
7/28/2019 PTCC EHS Plan With Pages
17/22
E H S
weight and at least 4 times the maximumintended load applied or transmitted to it (6times for suspension scaffolding).
2.15.3.2 All scaffolds/work access platforms must beinstalled by
qualified persons.
2.15.3.3 Before starting work on a scaffold, inspectvisually to
determine that:
i. Handrails, mid-rails, toe-boards, anddecking are in place.
ii. All wheels are locked on movablescaffolds.
iii. Locking pins are in place at each joint.
2.15.4Do not change or remove scaffold members unlessauthorized.
2.15.5No one is allowed to ride on a rolling scaffold when it is beingmoved unless
approved by EHS. Remove or secure all tools and material onthe deck before moving.
2.15.6Guard rails, including top and mid rails, and toe-boards mustbe installed onall open sides and on ends of scaffolds and platforms morethan 10 feet above the ground or lower surface.
2.16 PARKING / TRAFFIC
2.16.1All traffic rules shall be obeyed while on the premises includingstop signs, parking restrictions, pedestrian crosswalks, and postedspeed limits. Deliveries of materials, tools and/or equipment shall becoordinated with Project Manager. After the delivery is made to the
job site, the delivery vehicle shall be parked in the designatedparking area or shall exit the job site.
2.17 PRE-JOB BRIEFINGS
2.17.1Conduct pre-job briefings (toolbox talk / safety talks) withemployees undertheir control prior to work each day. Additional job briefings shall beheld if significant changes occur during the course of the work thatmight affect the safety of the employees based on the Permit ToWork System.
P.T. Cerna Construction Environmental Health & Safety Plan17
7/28/2019 PTCC EHS Plan With Pages
18/22
E H S
2.18 WORK PERMIT
2.18.1Prior to commencing any activity at the site, the Contractor shallensure that valid permits are issued and other clearances acquiredas stipulated in the Permit to Work System. These include but notlimited to the following:
2.18.2Safe Work Permit2.18.3Building Entry Permit2.18.4Hot Work Permit2.18.5Excavation Permit2.18.6Fire Safety Permit2.18.7Confined Space Entry
2.19 TOOLS AND EQUIPMENT INSPECTIONPROCEDURE
2.19.1 Ensure all PPE, Safety Equipment /Devices, Hand Tools, PowerTools, Compressed Gas Cylinders, Heavy Equipment, LiftingEquipment & Accessories and other Small Equipment & Deviceshave passed the inspection prior to use at facilities. A logbook shallmaintained by the respective department authorized to conduct theinspection.
2.19.2Equipment that failed in the inspection shall not be utilized and
immediately removed from the site.
2.19.3With the assistance of Project Manager, we shall bring theequipment and/or certifications to the following for inspection and/orverification:
1. Safety and Health- PPE and Safety Equipment & Devices- Third Party and other certifications
2. Mechanical Maintenance- Mechanical Hand Tools and Small Equipment / Devices
- Compressed Gas Cylinders
3. Electrical Maintenance- Electrical Hand Tools and Small Equipment / Devices- Power Tools
4. Maintenance Support- Lifting Equipment & Accessories- Scaffolding Materials- Heavy Equipment
2.20 TOOLS AND EQUIPMENT INSPECTION PROCEDURE
P.T. Cerna Construction Environmental Health & Safety Plan18
7/28/2019 PTCC EHS Plan With Pages
19/22
E H S
2.20.1 Ensure all PPE, Safety Equipment /Devices, Hand Tools, PowerTools, Compressed
Gas Cylinders, Heavy Equipment, Lifting Equipment & Accessoriesand other Small Equipment & Devices have passed the inspectionprior to use at facilities. A logbook shall maintained by therespective department authorized to conduct the inspection.
SECTION 3 FIRE PREVENTION
3.1 GENERAL FIRE PREVENTION
3.1.1 Smoke only in designated areas. Extinguish matches tobacco
products and placethem in approved containers.
3.1.2. Minimize the amount of flammable liquids/gases in the work area toa single work
shift supply.
3.1.3 Close containers of flammable liquids when not in use. Report spillsand any indication of excessive flammable vapor/gas concentrationsimmediately.
3.1.4 Obtain the necessary permits when performing hot work or disabling
fire protection systems.
3.1.5 Make sure materials and equipment do not block the access toextinguishers and fire protection hoses, hydrants, and standpipes.
3.1.6 Ensure materials are kept at least 18 inches (0.5 meter) fromsprinkler heads.
3.1.7 Attempt to extinguish small fires (trash can size) only if trained todo so. If trained to extinguish fires, familiarize yourself with thelocation of fire extinguishers in the area.
3.2 FIRE EXTINGUISHER REQUIREMENTS FOR ACTIVE CONSTRUCTIONSITES
3.2.1. Active construction projects shall have portable fire extinguishersprovided until the permanent buildings fire extinguishers areinstalled.
3.2.2 Extinguishers shall be provided in buildings under constructiononce one of the following conditions exists:
P.T. Cerna Construction Environmental Health & Safety Plan19
7/28/2019 PTCC EHS Plan With Pages
20/22
E H S
3.2.2.1 a second story or roof has been installed though notnecessarily completed - over the foundation;
3.2.2.2 the exterior walls have been erected and closed in.
3.2.2.3 The portable fire extinguishers shall be dry or wetchemical, and shall be rated for Ordinary Hazard Occupancy.
3.2.2.4. Each portable fire extinguisher shall have a minimum2A:20B:C rating, and
shall be spaced on an interval not to exceed 3,000 squarefeet (280 square meters) per extinguisher.
3.2.2.5 Maximum travel distance to any fire extinguisher shall not
exceed 100 feet(30.5 meters).
3.2.2.6 Transition to providing fire extinguishers at permanentlocations andspacing
is not necessary until the building/rooms are completed andmeet room readiness requirements. All cabinets andmounting hardware for the permanent fire extinguishers shallbe marked as not in operation or equivalent, until thepermanent extinguishers have been installed.
3.3 HOT WORK PERMIT
3.3.1 A Non-Electrical Hot Work Permit and SIPP / CIPP (as specified byIntel or project site) are required any time work involves the use ofopen flame or spark producing equipment. This includes welding,cutting burning, grinding and or soldering operations.
3.3.2 Prior to commencing work, all work specific/area hazards must beunderstood and communicated and all appropriate permits will beobtained.
3.3.3 All appropriate permits will be posted in the area of the work.
3.3.4 All personnel in the surrounding work area must be properlywarned of the hazardous work area by the use of barricades orother communication means.
3.3.5 Prior to work, within 35 feet (~ 11 meter) of work area:
a. Flammable liquids, dust lint and oily deposits are to be removedb. Explosive atmosphere is eliminated or if not possible, monitoredc. Floors swept cleand. Combustible floors wet down, combustibles in the area removedor covered with
fire resistive protectione. Floor and wall openings covered
P.T. Cerna Construction Environmental Health & Safety Plan20
7/28/2019 PTCC EHS Plan With Pages
21/22
E H S
f. Fire resistive tarpaulins suspended beneath work
3.3.6 A fire watch will be employed while Non-Electrical Hot Work isongoing and for 60 minutes after with fire extinguishing equipmentimmediately available at the work area.
3.3.7 A fire watch must be present for one hour after completion of thework and 30 minute checks will be completed for four hours afterwork is completed.
3.3.8 All fire watch personnel will be trained in the use of the fireprotection equipment and fire watch duties.
3.3.9 Non-Electrical Hot Work will not be conducted in any area classifiedas a Class I, Division I or II area according to the current UniformFire Code. Contact your local safety representative or projectmanager for questions.
3.4 FIRE SYSTEM WORK/RED TAG PROCESS
3.4.1 Obtain the proper permits and approvals before conducting workthat could affect
facility fire detection and suppression systems.
3.4.2 Permits must be closed after work is completed. Permits areordinarily issued for oneshift only, approval must be granted if work will extend beyond theshift in which the permit was issued. Permits may not be modified;new permits must be approved.
3.4.3 Participants in fire system work must be trained to the level of theirresponsibilities (i.e., buddy, fire watcher).
3.4.4 Everyone working in the impaired area must be briefed on thehazards present and precautions to be taken.
3.4.5 All available sprinklers, fire hose systems and extinguishers will bein service and operable.
3.4.6 Additional safety measures must be taken when hot work orenergized electrical work is conducted in an area that has animpaired fire system.
3.5 WELDING, CUTTING AND BRAZING
3.5.1 Protection of the eyes, face, neck, and hands is required duringwelding.
P.T. Cerna Construction Environmental Health & Safety Plan21
7/28/2019 PTCC EHS Plan With Pages
22/22
E H S
3.5.2 Only natural fiber clothing may be worn on the upper bodyextremities. A leather apron or full body leathers is recommended.
3.5.3 Respiratory protection is not required for most welding jobs ifproper ventilation is provided.
3.5.4 Welding screens are required to protect adjacent workers fromexposure to non-ionizing radiation. Adjacent workers are required towear appropriate eye protection where screens are not feasible.Welders assistants and those working inside the screened in areamust wear appropriate eye protection.
3.5.5 When welding, cutting, burning, grinding, chipping, abrasive
blasting, rivet busting, or otherwise disturbing painted or coatedsurfaces, a pre-assessment will be required to determine if thesurfaces contain lead-based paint. If bulk sampling results for paintare positive for lead, OSHA Standard 29 CFR 1926.62 will befollowed.
3.5.6 Chlorinated solvents are prohibited from use in or adjacent to allwelding operations. Decomposition products such as phosgene canbe formed as a result of the reaction of these solvent vapors withthe radiation energy produced during welding