Linaro Roadmap Overview
Mounir Bsaibes
Agenda
•Quarterly cycle •Roadmap •Implementation
Heavily based on: •https://wiki.linaro.org/Process/Roadmap by Kiko •http://video.google.com/a/linaro.org/#/Play/contentId=e6b907c7f6597a7e by Joey •Life cycle graphs by Ilias •http://wiki.linaro.org/Process/* by various Linaro contributors
Quarterly* Cycles
* A quarter starts at one Connect and ends at the beginning of next Connect, so a quarter does not span exactly 3 months, it may be more of less than 3 months.
Three major phases:
1.Requirements gathering
2.@Connect
3.Implementation
Requirements and Linaro Roadmap
•Requirements
•Can be proposed by the member companies, the TSC,
Technical Lead, Linaro management and Engineers
•Product Management Council (PMC)
•Requirements are submitted to the PMC
•The PMC works with engineering to understand the
requirements feasibility, sizing and when they can be
implemented.
•Place requirements on the roadmap
•Linaro Roadmap
•Holds high level requirements
•Spans 2+ years
•Implemented as Kaban board
Requirement Submission https://linaro.papyrs.com/
Requirement can arrive
any time
New requirements
normally wait till the start
of next Connect to begin
the implementation
Requirements in current
quarter do not normally
change
Anatomy of a Roadmap Card
Name
Task Id
Link to
Papyrs
requirement
Card Type
Sponsor
Priority
Size: small,
medium or
epic
Tags:
components
affected
Linaro Roadmap: General View
Covers only
major
initiatives
Spans 2+
years
Actual plan
of
deliverables,
not a list of
possibilities
Linaro Roadmap: Card Life Cycle View
Draft Accepted Planned Ready Delivered
Normal Flow
Card Lifecycle: Planning Phase
Source by Ilias: https://wiki.linaro.org/Internal/People/IliasBiris?action=AttachFile&do=view&target=PlanningPhaseProcess.graphml
Card Lifecyle: Connect & Implementation Phase
Source by Ilias: https://wiki.linaro.org/Internal/People/IliasBiris?action=AttachFile&do=view&target=ImplementationPhaseProcess-v2.graphml
@ Connect
Implementation
Card
Ready
Implementation
Blueprint3
Blueprint1
Blueprint2
Milestone
12.01
Milestone
12.02
Milestone
12.03
Backlog
Launchpad Project Series 2012
Blueprint1
Blueprint2
Blueprint3
Card
Delivered
Card Lifecycle: End of Quarter Phase
Source by Ilias: https://wiki.linaro.org/Internal/People/IliasBiris?action=AttachFile&do=view&target=EndOfQuarterPhaseProcess.graphml
Tracking http://status.linaro.org/
http://status.linaro.org/11.11/roadmap-card-GWG2011-BENCHMARK-DASHBOARD.html
QUESTIONS
?
Backup
MB board example https://mb.kanbantool.com/boards/9855-trial1