Qatar Petroleum Procedure

Post on 16-Apr-2017

303 views 2 download

transcript

Qatar Petroleum Procedure

DESIGN & CONSTRUCT

NEW ORBITAL HIGHWAY AND TRUCK ROUTE (P023)

Contract 3: Orbital Highway Mesaieed to Salwa Road

PROJECT ID: IA 12/13 C 062 ST

26 October 2015

Date: 25/10/2015 Page 1 of 37

QP Pipe Protection Procedures

Removal of QP Pipeline bund wall

Date: 25/10/2015 Page 2 of 37

QP Pipe Protection Procedures

Date: 25/10/2015 Page 3 of 37

QP Pipe Protection Procedures

Trench Excavation close to pipeline

Excavation of hard rock material

Date: 25/10/2015 Page 4 of 37

QP Pipe Protection Procedures

Date: 25/10/2015 Page 5 of 37

QP Pipe Protection Procedures

Excavation and installation of support pedestal

Date: 25/10/2015 Page 6 of 37

QP Pipe Protection Procedures

Trimming of excavation in preparation for foundation installation

Date: 25/10/2015 Page 7 of 37

QP Pipe Protection Procedures

Excavated formation/foundation level

Date: 25/10/2015 Page 8 of 37

QP Pipe Protection Procedures

Steel plates will be set prior to installation of arch segment

Date: 25/10/2015 Page 9 of 37

QP Pipe Protection Procedures

Restricted zone during element lifting

Date: 25/10/2015 Page 10 of 37

QP Pipe Protection Procedures

Arch Elements transported on flatbed trailer

Date: 25/10/2015 Page 11 of 37

QP Pipe Protection Procedures

Off-Loading Arch elements using Lifting beam

Date: 25/10/2015 Page 12 of 37

QP Pipe Protection Procedures

Storage of Arch Elements on Firm Ground and Proper Dunnage

Date: 25/10/2015 Page 13 of 37

QP Pipe Protection Procedures

Marks on footing keyway

Date: 25/10/2015 Page 14 of 37

QP Pipe Protection Procedures

Marks on unit side face for fast alignment

Date: 25/10/2015 Page 15 of 37

QP Pipe Protection Procedures

Turning of Arch element with Side Brackets

Date: 25/10/2015 Page 16 of 37

QP Pipe Protection Procedures

Installation of steel bracket on the segment

Date: 25/10/2015 Page 17 of 37

QP Pipe Protection Procedures

First arch unit staggered by half width

Date: 25/10/2015 Page 18 of 37

QP Pipe Protection Procedures

Total Station Survey Check of Crown Alignment

Date: 25/10/2015 Page 19 of 37

QP Pipe Protection Procedures

Element in Footing Keyway (Unit position adjustment using hardwood wedges)

Date: 25/10/2015 Page 20 of 37

QP Pipe Protection Procedures

STEP 4

RELEASE CRANE B. CRANE A CONTINUES PLACING UNIT

Erection Sequence of the Elements (units)

Date: 25/10/2015 Page 21 of 37

QP Pipe Protection Procedures

Grouting Foundation Keyway

Date: 25/10/2015 Page 22 of 37

QP Pipe Protection Procedures

Fig. A. Backfill Material zones Fig. B. Backfill material grain size

Date: 25/10/2015 Page 23 of 37

QP Pipe Protection Procedures

Up to existing slope or final grade

Or minimum one span

Max

Backfill placement levels - Max. Differential height < 0.50 m

Date: 25/10/2015 Page 24 of 37

QP Pipe Protection Procedures

Crown Beam Reinforcement Prepared According to Approved Drawings

Date: 25/10/2015 Page 25 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Date: 25/10/2015 Page 26 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Date: 25/10/2015 Page 27 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Date: 25/10/2015 Page 28 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Date: 25/10/2015 Page 29 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Date: 25/10/2015 Page 30 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Date: 25/10/2015 Page 31 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Date: 25/10/2015 Page 32 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Date: 25/10/2015 Page 33 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Date: 25/10/2015 Page 34 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Date: 25/10/2015 Page 35 of 37

QP Pipe Protection Procedures

QP Pipe line protection structure - QP Arch Erection

Date: 25/10/2015 Page 36 of 37

QP Pipe Protection Procedures

Minimum fill cover before heavy plant can cross the arch

Date: 25/10/2015 Page 37 of 37

QP Pipe Protection Procedures

Table 1 — Earthworks Compaction criteria