Post on 29-Oct-2019
transcript
GSPublisherVersion 0.0.100.100
ARCHITECTS PROJECT DETAILSContent :Client: Project title:GeConsult
Office No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: Grant No.:
KIS069REHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES
JUBALANDSTATE OFSOMALIA
ARCHITECTURALDRAWINGS
IOM/SSI
REHABILITATION OF LUUQ LOCALADMINISTRATION OFFICES
GRANT NO.: - KIS062
GSPublisherVersion 0.0.100.100
ARCHITECTS PROJECT DETAILSContent :Client: Project title:GeConsult
Office No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: Grant No.:
KIS069REHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES
JUBALANDSTATE OFSOMALIA
ARCHITECTURALDRAWINGS
IOM/SSI
REHABILITATION OF LUUQ LOCALADMINISTRATION OFFICES
GRANT NO.: - KIS062SHEET NO. CONTENTS
COVER SHEET
INDEX SHEET
GPS COORDINATES
FLOOR PLAN
ELEVATIONS
SECTIONS
ELECTRICAL LIGHTING
ELECTRICAL POWER
SCHEDULES
ANALYSIS SHEETS
3 DIMENSIONAL PROJECTIONS
01
03
02
04
05
E-01
E-02
AS-01 to AS-03
3D-01 to 3D-05
GSPublisherVersion 0.0.100.100
Client: Project title:
ARCHITECTSGeConsultOffice No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
PROJECT DETAILS Drawing Tittle:
Drawn by: Sheet No. Scale:
Revision No.
Checked & Approved by:
Date:
Hassan Abdisamad
July 2017
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: --
A. KaranjaJUBALANDSTATE OFSOMALIA
IOM/SSIREHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES - KIS069
GPS COORDINATES
01 N/A
ARCHITECTURAL DRAWINGS
3.79214N 42.54418E
GSPublisherVersion 0.0.100.100
Client: Project title:
ARCHITECTSGeConsultOffice No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
PROJECT DETAILS Drawing Tittle:
Drawn by: Sheet No. Scale:
Revision No.
Checked & Approved by:
Date:
Hassan Abdisamad
July 2017
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: --
A. KaranjaJUBALANDSTATE OFSOMALIA
IOM/SSIREHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES - KIS069
1 2 3 4 5 6 7 8 9 10 11 12 13
A
B
C
D
E
F
1,500 900 1,200 900 1,850 600360
600 850 900 1,700 900 1,450 900 595
5,650 4,450 5,100
15,200
650 900 1,450 900 3,440 600360
600 1,850 900 1,200 900 1,450
5,100 2,300 2,150 5,650
15,200
1,500 750 850 750 1,000 1,300 1,000 750 850 750 1,500
1,900 2,500 1,950 2,300 1,850
11,000
1,500 900 1,200 900 1,750 600450
600450
600450
600 1,300 900 1,200 900 1,200 900 700
5,650 4,450 5,100 1,90017,100
310900 1,550 900 1,250 900 1,250 600
430600
430600
430600 1,850 900 1,200 900 1,450
1,850 5,100 2,300 2,150 5,650
2,950 1,300 3,000
7,2502,500 1,950 2,300
900
900
9003,000
2,300
3,28
0
2,300
3,000
2,300
3,28
0
2,300
1,30085
090
01,
295 2,1
85
2,505
3,410
2,505
2,115
850
900
1,34
5
2,81
5
2,81
5
900
1,34
890
01,
102
3,10
01,
300
3,10
01,
005
900
1,25
290
01,
243
3,35
02,
400
1,90
02,
700
5,30
0
16,1
50
17,050
3,35
02,
400
1,90
02,
700
5,30
0
16,1
50
1,34
890
01,
102
3,10
01,
300
3,10
01,
005
900
1,25
290
01,
243
CORRIDOR
MEETING HALLOFFICE 01
STORE
OFFICE 02 OFFICE 03 OFFICE 04
ROOM1
ROOM2
ROOM5
ROOM4
EXPOSTALROOM
CO
RRID
OR
STORE
CORRIDOR
ROOM3
CORRIDOR
E-01
E-02
E-03
E-04
FLOOR PLAN
02 1:120
ARCHITECTURAL DRAWINGS
GSPublisherVersion 0.0.100.100
Client: Project title:
ARCHITECTSGeConsultOffice No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
PROJECT DETAILS Drawing Tittle:
Drawn by: Sheet No. Scale:
Revision No.
Checked & Approved by:
Date:
Hassan Abdisamad
July 2017
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: --
A. KaranjaJUBALANDSTATE OFSOMALIA
IOM/SSIREHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES - KIS069
1 2 3 4 5 6 7 8 9 10 11 12 13
13 12 11 10 9 8 7 6 5 4 3 2 1
A B C D E EE D C B A
5,650 4,450 5,100 1,900 2,500 1,950 2,300 1,850 5,100 2,300 2,150 5,650
150
150
3,80
020
0
970
1,33
030
045
075
0
900 900
1,50
01,
500
800
600 600
150
150
2,10
020
075
075
0
1,200
900
970
1,33
030
045
075
0
1,50
01,
500
800
150
150
2,53
726
3 600
400
750 7501,300
750 750
900 900
600 600
900 900
450
700
900
200
1,0001,60
020
020
0
700
900
200
1,000
5,650 2,150 2,300 5,100 1,850 2,300 1,950 2,500 1,900 5,100 4,450 5,650
150
150 97
31,
330
297
450
750
200 70
090
020
0
1,000
900 900
600 600 600 600
1,50
01,
500
800
900 900
700
900
200
1,0001,60
020
020
0
3,350 2,400 1,900 2,700
150
150
3,80
020
0
1,60
020
020
0
1,50
01,
500
800
900
150
150
2,50
0
1,300
900
1,33
030
045
0
2,700 1,900 2,400 3,350
150
150 97
01,
330
1,50
020
01,
600
200
200
900 900
150
150
2,50
01,
300
1,300
900
1,30
030
045
0
ELEVATION-01
ELEVATION-02 ELEVATION-04
ELEVATION-03
ELEVATIONS
03 1:120
ARCHITECTURAL DRAWINGS
GSPublisherVersion 0.0.100.100
Client: Project title:
ARCHITECTSGeConsultOffice No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
PROJECT DETAILS Drawing Tittle:
Drawn by: Sheet No. Scale:
Revision No.
Checked & Approved by:
Date:
Hassan Abdisamad
July 2017
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: --
A. KaranjaJUBALANDSTATE OFSOMALIA
IOM/SSIREHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES - KIS069
1 2 3 4 5 6 7 8 9 10 11 12 13
5,650 4,450 5,100 1,900 2,500 1,950 2,300 1,850 5,100 2,300 2,150 5,650
900 900
300
3,80
020
0 700
900
200
709 1,000 904
1,00
01,
300
300
450
1,00
01,
300
300
450
750
2,10
01,
660
200
1,60
020
020
0
900
FOUNDATION SPECIFICATION-150mm thick slab laid on app.dpm and blinding
-on a b.r.c mesh-600x200mm deep R.C strip foundation to S.E's details
-depth to be determined on site-hardcore fill consolidated at 300mm level
250mm thick concrete beamto S.E's details
500mm thick masonry rubble wallplastered and painted to approval
200mm R.C. Slab with 25mmthick protective cement andsand screed, laid to falltowards drains.
Hardwood pannel timber doors
SECTION-01
G.L
Floor level
Floor level
+4,100
+300
SECTION
04 1:120
ARCHITECTURAL DRAWINGS
GSPublisherVersion 0.0.100.100
Client: Project title:
ARCHITECTSGeConsultOffice No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
PROJECT DETAILS Drawing Tittle:
Drawn by: Sheet No. Scale:
Revision No.
Checked & Approved by:
Date:
Hassan Abdisamad
July 2017
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: --
A. KaranjaJUBALANDSTATE OFSOMALIA
IOM/SSIREHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES - KIS069
4FT Flourescent Light
Point Light
Twin Sockets with Switch
Consumer Unit
Power outlet circuit
Lighting circuit
Lighting mains
3 gang 1 way switch
LEGEND
Power mains to CU
Main Distribution Board
Floodlights
Corridor
Meeting hall
Office 01 Office 02Office 03
Office 04
CorridorCorridor
Store Store
ELECTRICAL LIGHTING
E-01 --
ELECTRICAL DRAWINGS
GSPublisherVersion 0.0.100.100
Client: Project title:
ARCHITECTSGeConsultOffice No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
PROJECT DETAILS Drawing Tittle:
Drawn by: Sheet No. Scale:
Revision No.
Checked & Approved by:
Date:
Hassan Abdisamad
July 2017
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: --
A. KaranjaJUBALANDSTATE OFSOMALIA
IOM/SSIREHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES - KIS069
4FT Flourescent Light
Point Light
Twin Sockets with Switch
Consumer Unit
Power outlet circuit
Lighting circuit
Lighting mains
3 gang 1 way switch
LEGEND
Power mains to CU
Main Distribution Board
Floodlights
OFFICE 04OFFICE 03OFFICE 02OFFICE 01 MEETING HALL
CORRIDOR
STORE
ROOM1
ROOM2
ROOM5
ROOM4
EXPOSTALROOM
CO
RRID
OR
STORE
CORRIDOR
ROOM3
CORRIDOR
ELECTRICAL POWER
E-02 --
ELECTRICAL DRAWINGS
GSPublisherVersion 0.0.100.100
Client: Project title:
ARCHITECTSGeConsultOffice No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
PROJECT DETAILS Drawing Tittle:
Drawn by: Sheet No. Scale:
Revision No.
Checked & Approved by:
Date:
Hassan Abdisamad
July 2017
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: --
A. KaranjaJUBALANDSTATE OFSOMALIA
IOM/SSIREHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES - KIS069
OFFICE 01
OFFICE 02
OFFICE 03
OFFICE 04
EX-POSTAL ROOM
ROOM 01
ROOM 02
ROOM 03
ROOM 04
ROOM 05
CORRIDORS
MEETING HALL
STORES
QTY AREA FLOOR FINISH SKIRTING WALL FINISH CEILING
34M2
34M2
40.6M2
40.6M2
1
1
1
1
1
1
1
1
1
1
1
1
2
10.6M2
10.6M2
4.2M2
4.2M2
3.6M2
3.6M2
55M2
35.5M2
8.5M2
300mm x 300mm Ceramic tiles f.f.
300mm x 300mm Ceramic tiles f.f.
300mm x 300mm Ceramic tiles f.f.
300mm x 300mm Ceramic tiles f.f.
300mm x 300mm Ceramic tiles f.f.
300mm x 300mm Ceramic tiles f.f.
300mm x 300mm Ceramic tiles f.f.
300mm x 300mm Ceramic tiles f.f.
300mm x 300mm Ceramic tiles f.f.
300mm x 300mm Ceramic tiles f.f.
300mm x 300mm Ceramic tiles f.f.
300mm x 300mm Ceramic tiles f.f.
300mm x 300mm Ceramic tiles f.f.
300mm x 300mm Ceramic tiles150mm (H)
300mm x 300mm Ceramic tiles150mm (H)
300mm x 300mm Ceramic tiles150mm (H)
300mm x 300mm Ceramic tiles150mm (H)
300mm x 300mm Ceramic tiles150mm (H)
300mm x 300mm Ceramic tiles150mm (H)
300mm x 300mm Ceramic tiles150mm (H)
300mm x 300mm Ceramic tiles150mm (H)
300mm x 300mm Ceramic tiles150mm (H)
300mm x 300mm Ceramic tiles150mm (H)
300mm x 300mm Ceramic tiles150mm (H)
300mm x 300mm Ceramic tiles150mm (H)
300mm x 300mm Ceramic tiles150mm (H)
Plaster & paint to approval Plaster & paint to approval
Plaster & paint to approval Plaster & paint to approval
Plaster & paint to approval Plaster & paint to approval
Plaster & paint to approval Plaster & paint to approval
Plaster & paint to approval Plaster & paint to approval
Plaster & paint to approval Plaster & paint to approval
Plaster & paint to approval Plaster & paint to approval
Plaster & paint to approval Plaster & paint to approval
Plaster & paint to approval Plaster & paint to approval
Plaster & paint to approval Plaster & paint to approval
Plaster & paint to approval Plaster & paint to approval
Plaster & paint to approval Plaster & paint to approval
Plaster & paint to approval Plaster & paint to approval
AREA SCHEDULES
05 N/A
ARCHITECTURAL DRAWINGS
GSPublisherVersion 0.0.100.100
Client: Project title:
ARCHITECTSGeConsultOffice No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
PROJECT DETAILS Drawing Tittle:
Drawn by: Sheet No. Scale:
Revision No.
Checked & Approved by:
Date:
Hassan Abdisamad
July 2017
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: --
A. KaranjaJUBALANDSTATE OFSOMALIA
IOM/SSIREHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES - KIS069
ANALYSIS SHEET 01
AS-01 --
ARCHITECTURAL DRAWINGS
WALLSAll eroded walls to be cleaned, filled with approved cement sand,plastered and paint with two coats to approval
The plinth at the base of the building to be cleaned, filled with approvedcement, plastered and painted to approval
GSPublisherVersion 0.0.100.100
Client: Project title:
ARCHITECTSGeConsultOffice No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
PROJECT DETAILS Drawing Tittle:
Drawn by: Sheet No. Scale:
Revision No.
Checked & Approved by:
Date:
Hassan Abdisamad
July 2017
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: --
A. KaranjaJUBALANDSTATE OFSOMALIA
IOM/SSIREHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES - KIS069
ANALYSIS SHEET 02
AS-02 --
ARCHITECTURAL DRAWINGS
R.C.C. SLABCut and clear all dead shrubs from the surface of the building.Hack and demolish existing floor screed. Supply and fix an approved waterproof membrane. Hack and scratch the old plaster from the surface of slaband replaster again.
Provide 25mm thick protective cement and sand screed, laid to fall towardsdrains.
GSPublisherVersion 0.0.100.100
Client: Project title:
ARCHITECTSGeConsultOffice No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
PROJECT DETAILS Drawing Tittle:
Drawn by: Sheet No. Scale:
Revision No.
Checked & Approved by:
Date:
Hassan Abdisamad
July 2017
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: --
A. KaranjaJUBALANDSTATE OFSOMALIA
IOM/SSIREHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES - KIS069
ANALYSIS SHEET 03
AS-03 --
ARCHITECTURAL DRAWINGS
DOORS AND WINDOWSReplace the old wooden windows with aluminum casement windows asper schedules to fabricator's details.
Provide new hard wood panel timber doors
GSPublisherVersion 0.0.100.100
Client: Project title:
ARCHITECTSGeConsultOffice No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
PROJECT DETAILS Drawing Tittle:
Drawn by: Sheet No. Scale:
Revision No.
Checked & Approved by:
Date:
Hassan Abdisamad
July 2017
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: --
A. KaranjaJUBALANDSTATE OFSOMALIA
IOM/SSIREHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES - KIS069
3 DIMENSIONAL PROJECTION
3D-01 N/A
ARCHITECTURAL DRAWINGS
GSPublisherVersion 0.0.100.100
Client: Project title:
ARCHITECTSGeConsultOffice No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
PROJECT DETAILS Drawing Tittle:
Drawn by: Sheet No. Scale:
Revision No.
Checked & Approved by:
Date:
Hassan Abdisamad
July 2017
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: --
A. KaranjaJUBALANDSTATE OFSOMALIA
IOM/SSIREHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES - KIS069
3 DIMENSIONAL PROJECTION
3D-02 N/A
ARCHITECTURAL DRAWINGS
GSPublisherVersion 0.0.100.100
Client: Project title:
ARCHITECTSGeConsultOffice No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
PROJECT DETAILS Drawing Tittle:
Drawn by: Sheet No. Scale:
Revision No.
Checked & Approved by:
Date:
Hassan Abdisamad
July 2017
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: --
A. KaranjaJUBALANDSTATE OFSOMALIA
IOM/SSIREHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES - KIS069
3 DIMENSIONAL PROJECTION
3D-03 N/A
ARCHITECTURAL DRAWINGS
GSPublisherVersion 0.0.100.100
Client: Project title:
ARCHITECTSGeConsultOffice No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
PROJECT DETAILS Drawing Tittle:
Drawn by: Sheet No. Scale:
Revision No.
Checked & Approved by:
Date:
Hassan Abdisamad
July 2017
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: --
A. KaranjaJUBALANDSTATE OFSOMALIA
IOM/SSIREHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES - KIS069
3 DIMENSIONAL PROJECTION
3D-04 N/A
ARCHITECTURAL DRAWINGS
GSPublisherVersion 0.0.100.100
Client: Project title:
ARCHITECTSGeConsultOffice No. 529,5th Floor, 680 Hotel Building,Muindi Mbingu Street,Off Kenyatta Avenue.
PROJECT DETAILS Drawing Tittle:
Drawn by: Sheet No. Scale:
Revision No.
Checked & Approved by:
Date:
Hassan Abdisamad
July 2017
ARCHITECTURE & ENGINEERING CONSULTANTS
geconsulteam@gmail.comwww.geconsultarchitects.comP.O Box 103525 - 00101 Nairobi,KenyaTel:+254 724 008 839 / +254 725 178 875
Implementation Partner: --
A. KaranjaJUBALANDSTATE OFSOMALIA
IOM/SSIREHABILITATION OF
LUUQ LOCAL ADMINISTRATIONOFFICES - KIS069
3 DIMENSIONAL PROJECTION
3D-05 N/A
ARCHITECTURAL DRAWINGS