Mo-99 Topical MeetingMontreal, September 2017

Jayne Senior

Reliable & Timely Mo-99 Supply Globally

Agenda

1. ANM Project Background

2. ANM Design & Capacity

3. ANM Construction & Commissioning Status

ANM Project Background

ANSTO Nuclear Medicine – ANM

ANSTO Nuclear Medicine

Operated as a subsidiary of

ANSTO

One product-Mo-99

Scalable domestic and worldwide

supply

Full lifecycle consideration

Mo-99 Facility ANM

Synroc Waste PlantSyMo

TWO PARTS

ANSTO Nuclear Medicine Project

Synroc Waste Plant“SyMo”

Mo-99 Plant“ANM”

OPAL

Lucas Heights Location

ANM Design & Capacity

Mo-99 PlantANM

Synroc Waste PlantSyMo

TWO PARTS

3,500 6 day Ci per week

LEU fuel & LEU targets

Base Digestion process

Proven, reliable technology

Low emissions (Xe-133)

Integrated preparation and testing labs

Hot Isostatic Press technology

320 cans produced per year

Integrated with Mo-99 facility

Treats Intermediate Level Liquid Waste

Waste volume reduction by 90%

Immobilised waste form

ANSTO Nuclear Medicine Project

Integrated Mo-99 Production Cycle

OPAL Irradiation Plate TransportPlate Target

Generator Production Chemical Separation ANM

ANM Mo-99 production process

Plates DissolutionFiltering

and separation

Purification Conditioning Mo-99 Patient

Waste streams

World best safety features

New production efficiencies throughout

State of art hot cell design

Separate hot cells for each process step

Radiation shielding

In-cell equipment back-up

Best practice hot cell transfer system

Extensive emission control

systems

ANM – Capacity and Flexibility

0

10

20

30

40

50

60

70

80

90

weekend rest of week

World Demand Profile9000 6-Day Ci

% Demand

0

10

20

30

40

50

60

70

80

90

weekend rest of week

ANM Supply Profile3500 6-Day Ci

% Supply

Capacity Increase TimingProjection of 6-Day Ci Production/Week

2016 2017 2018

0

500

1000

1500

2000

2500

3000

3500

4000

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

Current Facility4 Runs x 8 Plates

Current Facility5 Runs x 12 Plates

ANM10 Runs x 12 Plates

Construction & Comissioning Status

16

Before

After……

Front Entrance

Ramp to Front Entrance

Side Access

Production Cell Face

Hydrogen Cell face

Dissolution Cell Control Panel

Waste Handling Cells

Rear of Hot Cells

Rear of Hot Cells

Basement Gas Tanks

Basement Iodine Filters

Plant Room

QC Intermediate Sample Test Lab

QC Intermediate Sample Test Lab

Process Preparation Room

Mo-99 Facility MilestonesOperation licence submission to ARPANSA

Public consultation

Construction complete

Commissioningunderway

Activecommissioning and operation

APRIL2017

JUNE2017

JULY2017

November2017

Subject toARPANSA licence

COMMISSIONING ACTIVECOMMISSIONING

ANM Commissioning MilestonesDesign

Qualification(DQ)

TGA /ARPANSA Licences

Instrumentation Qualification

(IQ)

Low & High Activity Runs

Finish 18 November

Product Qualification

(PQ)

Facility Services Complete

In Cell Process

Equipment Finish 26 October

Operational Qualification

(OQ)

AuditsEnd

October/Early

November

Facility Services Complete

In Cell Process

Equipment Commenced

Complete

Product Validation

Supply Customer Validation SamplesStart 20

November

Current Operations and ANM Transition

0

2

4

6

8

10

54

32

10

0

1

2

3

4

5

6

7

8

9

10

0 + (5) 2 + (4) 4 + (3) 6 + (2) 8 + (1) 10 + (0)

Planned Scale up of ANM + Reduction in Current Operations

Number of runs per week in ANM + (Number of runs per week in B54)

Current FacilityFull Capacity (Now)

Current FacilityShut-Down (Q3 2018)

Mo-99 Topical MeetingMontreal, September 2017

Jayne Senior

Reliable & Timely Mo-99 Supply Globally