SAMRI MINE DIVISION

HINDALCO INDUSTRIES LIMITED

DIST.- BALRAMPUR-RAMANUJGANJ

(CHHATTISGARH)

2

LOCATION MAP OF OPERATIONAL AREA

Existing Mines

KUDAG

TATIJHARIA

3

LEASE AREA OF SAMRI LEASE

Samri lease area lies in Sarguja District of

Chhattisgarh State. It is at a distance of

117 km from district Head Quarter

Ambikapur.

•Latitude:- 23023’02”N to 23027’05”N

•Longitude:- 83053’50”E to 83057’59’E

4

ENVIRONMENT PERCEIVE – Samri Mines Division

Particulars Details

Elevation above MSL 1140m

Climatic Conditions

(as per IMD- Daltonganj)

1] Annual Mean Max Temp : 38.2o C

2] Annual Mean Min Temp : 14.4o C

3] Annual Total Mean Rainfall : 1118.2-mm

4] Predominant Wind Direction : NW

Land use* Raiyati Land, Govt Land and Forest Land

Hills/Valleys SAMRI Plateau

Ground Water Level 1085-88-m from MSL

Bauxite Bottom (av.) 1128-m from MSL

5

Lease Details – Samri Mines Division

Name of Mine Area (Hect.) Lease granted

on

Lease

extended Upto

SAMRI MINE 2146.746 24-06-1998 23-06-2048

TATIJHARIA

MINE 1218.762 25-06-1998 24-06-2048

KUDAG MINE 377.116 24-12-1996 23-12-2046

6

Overall View of Mined Out, Reclamation and Afforestation

Lease

Up to Nov'2016

Mined out (Hect.)

Reclamation (Hect.)

Afforestation

Area of Plantation

(Hect.)

No. of Plantation

Samri Lease 169.077 137.44 68.154 167211

Tatijharia Lease 104.745 89.666 32.06 78925

Kudag Lease 65.032 61.009 49.98 117570

Total 338.854 288.115 150.194 363706

7

Samri Mines Division

F.Y.( 2015-16)

NAME OF MINES MINED OUT AREA (Ha) RECLAIMED AREA (Ha)

Samri Mines

10.999

15.454

Tatijharia Mines 9.303 7.844

Kudag Mines

4.452

4.084

8

Samri Mines Division

F.Y.( 2015-16)

Lease Reclamation in FY- 2015-

16 (Hect.) ReclamationUp to Nov’2016(Hect.)

Samri Lease 15.454 137.44

Tatijharia Lease 7.844 89.666

Kudag Lease 4.084 61.009

Total 27.382 288.115

9

RECLAMATION WORK

10

LAYING OF TOP SOIL ON RECLAIMED LAND

11

RECLAIMED LAND

12

RECLAIMED LAND

13

RECLAIMED LAND

14

AFFORESTATION

Lease

Plantation

FY: 2016-17 Upto Nov'2016

Area

(Hect.) Nos. Area (Hect.) Nos.

Samri Lease 3.7 9110 68.154 167211

Tatijharia Lease 2.4 5950 32.06 78925

Kudag Lease 2.8 4390 49.98 117570

Total 8.9 19450 150.194 363706

15

Plantation

16

AFFORESTED AREA-NASPATI UNDER

SOCIAL FORESTARY

17

Cultivation of crop on reclaimed land

18

Cultivation of crop on reclaimed land

19

AFFORESTATION

20

AFFORESTATION

21

ASTHETIC BEAUTY

22

Samri Nursury

23

Samri Nursury

)

24

Samri Nursury

25

Nursery- Green House (3 Nos.)

26

Nursery- Green House

27

Water Reservoir – 5 Nos.

28

INFRASTRUCTURE DEVELOPMENT Water Harvesting

To recharge ground water harvesting

work has been constructed in Samri

operational area.

29

1. All three mines weighbridge are

operated by solar Power

2. Solar Power operated street Light in

mine and residential colony

3. Group VTC operated by

Solar power

4. Solar power operated drinking water

5. Solar Power Operated Lift irrigation at

Samri Nursury

Solar Power Infrastructure At Mines

30

INFRASTRUCTURE DEVELOPMENT Solar Power Infrastructure At Mines

31

ENVIRONMENT FRIENDLY HUTMENT

32