Shielding of Route Goward Status – 25 June 2013

Post on 22-Feb-2016

18 views 0 download

description

Shielding of Route Goward Status – 25 June 2013. Main works of Route Goward will be completed end of June 2013 (1st layer blacktop on june 28th) Finishing works : Metalworks – in july 2013 2 nd layer of blacktop and parking – after Septum 16 works. - PowerPoint PPT Presentation

transcript

Shielding of Route Goward Status – 25 June 2013

• Main works of Route Goward will be completed end of June 2013 (1st layer blacktop on june 28th)

• Finishing works: – Metalworks – in july 2013– 2nd layer of blacktop and parking – after Septum 16 works

Temporary road

Retaining wallPiling works

Some pictures of the works:

Slab reinforcement

Formwork for the slab

Biocofra

Concreting

Road works

Backfilling

Shielding of Septum 16 Status – 25 June 2013

• Adjudication of the works on 19 June 2013

• June-July 2013 - Preparatory works

– « Sondages » – Felling of trees– Removal of the barrier closing access to the PS – Removal of the street lighting– Setting out of the works– Worksite installation– Information campaign for users and TSO

• July 2013 – Earthworks

• September 2013 - Piling works

«Sondages»

Worksite installations:

Parking route Gowardshared with CV

Concrete batching plant(to be confirmed)

Temporary spoil dump

Access to building 561 (RP)

«Passage pieton» closed

Provisional ScheduleExpected in July 2013!

Thank you for your attentionAny questions?