Special Considerations for Maintenance of the Sunshine Skyway Bridge · 2014-05-06 · •The...

Post on 08-Apr-2020

0 views 0 download

transcript

2014 NATIONAL BRIDGE PRESERVATION PARTNERSHIP CONFERENCE

James J. Jacobsen, P.E.

District Structures Maintenance Office

Tampa, Florida

1 April 24, 2014

Florida Department of

TRANSPORTATION

Special Considerations for Maintenance of the Sunshine Skyway Bridge

Presentation Outline

• Sunshine Skyway Bridge Overview

• Proactive Maintenance Program: Skyway Preservation Committee

• Post Tensioning Protection

• Improved Inspection and Maintenance Access

• Bridge Health Monitoring

• Strategy for a 100-year Bridge Life

April 24, 2014 2

Sunshine Skyway Bridge

April 24, 2014 3

Sunshine Skyway Bridge Location

April 24, 2014 4

Skyway Bridge History • In May 1980, a major ship impact caused the south

bound main span of the original bridge to collapse.

• A signature replacement bridge was envisioned.

• After a 5 year construction period, the bridge was opened to traffic in April 1987.

• The bridge was re-dedicated in 2005 as the “Bob Graham Sunshine Skyway Bridge” as the former Florida Governor had the vision to build this signature bridge.

• Owned and Maintained by the Florida Department of Transportation

• Asset Maintenance Contracted since 2004

April 24, 2014 5

Looking south

April 24, 2014 6

Looking North

April 24, 2014 7

MAIN SPAN UNIT

•Post-Tensioned Precast Segmental Box

•42 Continuous Stay Cables, 21 per Pylon

•Total Length: 4,000 ft

April 24, 2014 8

•Post-Tensioned Precast Segmental Boxes

•Post-Tensioned Precast Segmental Columns

• Length: 2,430 ft each

HIGH LEVEL

APPROACH HIGH LEVEL

APPROACH

April 24, 2014 9

LOW LEVEL TRESTLE SPANS

LOW LEVEL TRESTLE SPANS

Shldr.

Lane

Lane

Shldr.

Shldr.

Lane

Lane

Shldr.

Cast In Place Deck on Prestressed Concrete Beams

Total Length: 13,000 ft

April 24, 2014 10

High level approach

April 24, 2014 11

High Level Approach Column and Dolphin

April 24, 2014 12

Proactive Maintenance Program

• Major Challenge: Preserve the Investment

• Response: Skyway Preservation Committee

April 24, 2014 13

Total Cost Per Year to Maintain

April 24, 2014 14

Major Maintenance Challenges

•Corrosive Environment

•Three types of bridges in one

•Access for Maintenance

April 24, 2014 15

Skyway Preservation Committee

The Preservation Committee exists to provide a forum whereby a select group of specialists come together twice per year to discuss a wide variety of issues that affect the current and long term health of the Skyway Bridge.

April 24, 2014 16

Sample Skyway Preservation Committee Meeting Agenda Items

• Recently completed repair contracts

• Accelerometers on Stay Cables

• Remove Anchorage Covers

• Stay Cable Tension Testing

• Median Interior Maintenance

• Corrosion Prevention (water line and foundation)

April 24, 2014 17

Post Tensioning Protection

• Five Strategies: New Direction for Florida: PT Bridges (2002)

1. Enhanced PT system

2. Multiple tendon Paths

3. Fully grouted tendons

4. Water tight bridge

5. Multiple layer anchor protection

April 24, 2014 18

Where could water enter?

• Closure pour cracking

• PT anchor pour-backs

• Raised median

• Segment joints (dry and epoxy coated)

• Cracked Polyethylene Ducts

April 24, 2014 19

Where could water enter?

April 24, 2014 20

Sealing the Raised Median Barrier with Polyurea

April 24, 2014 21

Cable Stay / Median Barrier

April 24, 2014 22

Segmental Bridge Deck

April 24, 2014 23

2013 Deck Sealing Test Area Methyl Methacrylate

April 24, 2014 24

2013 Deck Sealing Test Area Methyl Methacrylate

April 24, 2014 25

Polyethylene Ducts

• All External PT ducts had been wrapped with heat shrink sleeves by 2006.

• Ongoing maintenance includes localized repairs by asset maintenance forces.

April 24, 2014 26

Localized Heat Shrink Duct Wrap Repair

April 24, 2014 27

Special Inspection of Post Tension Systems

• The Post Tension System is a critical item to inspect and ensure proper performance

• Voids and segregated grout must be detected and corrected to ensure maximum life of post tensioning system

• Special inspection methods are needed beyond the routine visual inspection

April 24, 2014 28

Typical External Tendon Cross Section

High Density

Polyethylene Duct

Strand

Cement grout

April 24, 2014 29

Post Tensioned Tendon Inspection State of the Art

• No single test method is able to effectively inspect and detect tendon voids and corrosion

• Current methods can be expensive and time consuming: Main Magnetic Flux

• Several methods may need to be combined to get better results

• The FDOT is supporting new development in non destructive testing

April 24, 2014 30

Cable Stay Repainting

April 24, 2014 31

Cable Stay Repainting

April 24, 2014 32

High Level Approach Bearing Inspection

April 24, 2014 33

High Level Approach Maintenance

April 24, 2014

Transition Pier from Single to Dual Box Sections

Typical High Level Approach

34

Sealing Column Caps

April 24, 2014 35

Pier Cap Sealing Complete

April 24, 2014 36

Wind Driven Rain Under Segments

April 24, 2014 37

Improved Inspection and Maintenance Access

April 24, 2014 38

Rappelling Tower

April 24, 2014 39

Bore scope Inspection of Stay Saddles

April 24, 2014

Check for corrosion and coating condition 40

Suspended Scaffolding

April 24, 2014 41

April 24, 2014

Inspection of Stay Cables using High Lift

42

Inspection of Stay Cables using High Lift

April 24, 2014 43

Inspection of Stay Cables Using High Lift

April 24, 2014 44

New Access Hatches in Median

April 24, 2014 45

Inspection Inside Median Barrier

April 24, 2014 46

Sunshine Skyway Health Monitoring • Integrated methods of

monitoring bridge condition properties

April 24, 2014 47

Outline • Need for Monitoring

• Existing Monitoring System

• Structural Health Monitoring Goals

April 24, 2014 48

Structural Health Monitoring (SHM)

• Why Monitor the Skyway?

– Vital to regional and multimodal transportation

– Help ensure 100 year design life is met

– Detect problems between visual inspections

– Post hurricane or impact evaluation

– Provide live weather conditions for Traffic Management

April 24, 2014 49

Current Monitoring System

• Global Positioning System (GPS) Receivers

• Automatic Total Stations

• Weather Stations

• Analytical Model

April 24, 2014 50

GPS System

GPS Sensors:

– Leica GPRX 1200+RS500 Receivers

– Post-processed accuracy of 1 centimeter in x and y planes

April 24, 2014 51

GPS Receiver Locations

April 24, 2014 52

Automatic Total Stations

• Leica TCA2003 ATS on Dolphin 101

• Leica TM30 on Dolphin 104

• Accuracy to 1 millimeter

• Redundancy for GPS

April 24, 2014 53

ATS Prism on Tower

April 24, 2014 54

ATS Lines of Sight

April 24, 2014 55

Weather Station

• Weather Sensors

– Wind Speed/Direction

– Temperature/Humidity

– Barometric Pressure

– Internet-connected with live web-cams

– Rain Gauge

April 24, 2014 56

Weather Station Website

• Tabular and graphical data available

• Website updated every 15 minutes

April 24, 2014 57

Structural Health Monitoring (SHM) Goals:

• Design verification (with analytical model)

• Establish normal movement

• Extreme event monitoring

• Deterioration/settlement detection

April 24, 2014 58

Design Verification – Theoretical estimation of time-dependent stay

forces to compare with empirical test results

– Calibration/verification of GPS/ATS readings

April 24, 2014 59

Analytical Model

• Time-dependent frame analysis model

• MIDAS Civil software used

• Main model P6S (106) to P6N (117)

April 24, 2014 60

Wind Analysis Graphical Results

1.37 ft

1.01 ft

April 24, 2014 61

Normal Operating Parameters

April 24, 2014 62

Extreme Event Monitoring • Hurricane effects

• Ship Impact

• Wind/rain cable vibration

April 24, 2014 63

Future Goals

• Fully calibrated analytical model

• Establish thresholds of movement

• Additional permanent sensors

– Strain measurements

– Stay vibration measurements

– Thermal measurements

• Automated alerts

April 24, 2014 64

Strategy for a 100 year Bridge Life:

• Continue a “Preventive” focused inspection and maintenance program

• Continue the "Skyway Preservation Committee” to sustain the vision for a 100 year life for the bridge

• Give special attention to long term Corrosion Prevention

April 24, 2014 65

Questions?

April 24, 2014 66

Thank you for participating

Florida Department of Transportation District Structures Maintenance Office

Tampa, Florida

67 April 24, 2014

NATIONAL BRIDGE PRESERVATION PARTNERSHIP CONFERENCE

Special Considerations for Maintenance of the Sunshine Skyway Bridge