Post on 31-Aug-2020
transcript
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 1
SSI Performance & Earned Value Management Tools ............................................................................................................ 2
Overview ............................................................................................................................................................................. 2
Common Definitions Used in Earned Value Management .................................................................................................. 2
Project Setup for SSI Earned Value Management Reporting .................................................................................................. 3
Minimum Setup Requirements for EVM using SSI Tools.................................................................................................... 3
Recommended Setup for EVM using SSI Tools .................................................................................................................. 3
Post Project Data to the SSI Project Performance Database ................................................................................................ 6
Adding Subsequent Reporting Periods to the Database ..................................................................................................... 11
Importing Actual Values .................................................................................................................................................... 15
Using Earned Value Reports .............................................................................................................................................. 22
Example Project for Demonstrations and Exercise Browse to: http://ssitools.com/classfiles/EVM
Right-click ExampleProject(EVM).mpp and save to
c:\ssi_tools
Right-click ExampleProject(EVMApril).mpp and save
to c:\ssi_tools
Right-click ImportedActualValues2015.xlsx and save to
c:\ssi_tools\EVM (Make this folder if it does not exist
on your system)
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 2
SSI Performance & Earned Value Management Tools
Overview
Structured Solutions Performance and Earned Value Tools includes built-in Earned Value reporting
using project data. Data showing the Plan Value (aka PV or BCWS), the Earned Value (aka EV or
BCWP) and Actual Value (aka AV or ACWP) can be determined by Task Days, Task Work or Task
Cost.
When Using Task Days as the EV Unit of Measure, SSI Tools reports the days of work
scheduled through a reporting period vs. days of work performed (using the Baseline Duration as
the basis) and the actual days taken to perform tasks in the schedule.
When Using Task Work as the EV Unit of Measure, SSI Tools reports the hours of work
scheduled through a reporting period vs. hours performed (using the Baseline Hours as the
basis). The Actual Value for work hours can be taken from Microsoft Project or it can be
imported and held outside Microsoft Project. Work hours can be reported at the Work Package
level or rolled up to the Work Package Parent level.
When Using Task Cost as the EV Unit of Measure, SSI Tools reports cost values scheduled
through a reporting period vs. cost performance (using the Baseline Duration as the basis).
Actual costs can be taken from Microsoft Project or imported and held outside Microsoft Project.
Costs can be reported at a Work Package level or rolled up to the Work Package’s Parent level.
For those needing to use a formal Earned Value Management System, SSI Tools includes data
generators for Deltek MPM and Cobra. SSI’s Cobra and MPM interface tools make import/transaction
files that include WBS, Planned Value, Earned Value, and Estimates to Complete.
Common Definitions Used in Earned Value Management
Baseline: The “Planned Value” of the duration, start, finish and resource assignment values (if any) for
a project. The Baseline is usually formally controlled in a project and does not change unless a formal
change control review has been conducted and the change to the baseline has been approved. Terms and
acronym used to describe the baseline include: Baseline, Budget, Planned Value (or PV), Budget Cost of
Work Scheduled (or BCWS) and Budget at Complete (BAC).
Performance: The amount of progress taken on a task. Progress can be shown as a percent of the total
task duration (% Complete), the percent of the total work or cost (Work % Complete) or as a percent of
the Baselined duration, work or cost (% of Baseline Earned or “Earned Value”). Terms and acronym
used to describe Performance include: Earned Value, Budgeted Cost of Work Performed (EV, BCWP –
when taken as a percent of the Baseline), % Complete, Work % Complete, and Physical % Complete.
Actual Values: The actual number of days, hours or cost taken to perform a task or a portion of a task.
With the exception of Actual Days to perform a task, Actual Values are often captured at a “rolled-up”
level meaning that its value is not recorded on a task by task level. Rolled-up values are often captured
for a collection of tasks having something in common such as their performing organization or position
in the Work Breakdown Structure of a project. Terms and acronym used to describe Actual Values
include: Actual Cost (AC), Actual Cost of Work Performed (ACWP) or Actual Value (AV).
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 3
Current Schedule: The current value of the duration, start, finish and resource assignment values (if
any) for a project. The Current Schedule is usually not formally controlled and reflects actual
performance to date plus current projections for future tasks and associated resource needs. The Current
Schedule changes at the end of each reporting cycle and is used to yield the estimate to complete the
project and its key program events. Terms and acronym used to describe the Current Schedule include:
Estimate to Complete (ETC), current plan or current schedule.
Variances: The difference between the current schedule and the baseline is known as the Cumulative
Variance. The difference between the current schedule and the schedule at the end of the prior reporting
period is known as the Current Period Variance. Terms and acronym used to describe Variances
include: Variance at Complete (VAC), Schedule Variance (SV), Cost Variance (CV) and Variance
Analysis Reports (VAR).
Estimate at Complete: Equal to Remaining value of duration, work and cost, plus the actual values of
the same to date. EAC is the acronym commonly used for Estimate at Complete.
Project Setup for SSI Earned Value Management Reporting
SSI Earned Value Management Tools (EVM) enables the maximum benefit from EVM accounting and reporting with
minimal burden and cost of implementation. Minimum and our Suggested setup requirement for a project reporting Earned
Value are as follows:
Minimum Setup Requirements for EVM using SSI Tools
1. Add Work Package IDs to tasks in the schedule. Tasks having Work Package IDs will be
known as Work Packages. A Work Package ID is a unique code given to a task/activity in the
schedule that represents work that will be performed in a project. You can use any convention
you like for Work Package IDs (A, B, C, 1, 2, 3, A1, A2, A3 and so on).
2. Post project data to the SSI EVM system at the end of one reporting period. This enables
Cumulative Earned Value Reporting from the data in a Microsoft Project plan.
Recommended Setup for EVM using SSI Tools
1. Use Intuitive Work Package IDs and Work Package Parent IDs to enable summarizing of like
or common collections of Work Packages. As an example, use a convention for Work Package
IDs such as “A.01”, “A.02”, and “A.03” and give these three Work Packages the Work Package
Parent ID of “A”. Another common collection of Work Packages could be given “B.01”,
“B.02” and “B.03” for their Work Package ID and “B” as the Work Package Parent ID.
2. Post project data to the SSI EVM system from the last two reporting periods. This enables
Cumulative and Current Period Earned Value Reporting from the data in a Microsoft Project
plan.
3. Add the name or the organization name of the Performing and/or Responsible entity for each
Work Package.
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 4
Steps Description / Image
Pick Text or Outline Code Fields in Microsoft
Project and enter values for:
Work Package ID
Work Package Parent ID
Performing Manager / Organization
Responsible Manager / Organization
Practice – On your own
1. Open Microsoft Project and open the project
named ExampleProject(EVM).mpp
2. Insert Text1, Text3, Text4 and Text5 in the
Gantt chart table by right-clicking on any
column title in the table and selecting Insert
Column.
Right-click Insert columns
Project 2003 - 2007 Toolbar
Project 2010 -2013 tools from SSI Analysis Tools menu
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 5
3. Right-click on each of the added columns and
select Customize Fields
4. Rename Text1, Text3, Text4 and Text5 to
match the example shown to the right
5. Add the Values shown to the right for WP
Parent, WP ID, Performing Manager and
Responsible Manager in lines 15 – 25 (if not
already there)
6. Scroll through the rest of the sections of the
example project and see the values that have
already been entered in the same text fields.
7. The Project now contains the following values
for tasks/activities
Work Package ID (Using Text1)
Work Package Parent ID (Using Text2)
Performing Manager (Using Text4)
Responsible Manager (Using Text5)
Notice that WP Parent (Work Package Parent ID)
and WP ID (Work Package ID) are only needed on
tasks. It is not necessary to add these to
Summaries or Zero Duration Milestones as
summaries and milestones do not have Planned
Value or Earned Value
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 6
Post Project Data to the SSI Project Performance Database
The Project Performance Database captures Planned Value, Earned Value and the Estimate to
Complete from the current Microsoft Project schedule from one or more reporting periods. The Actual
Value for EVM Work and Cost can come directly from the project or it can be imported from an
external source.
If the database contains data from one reporting period, only Cumulative Earned Value reporting is
possible. If data from two or more reporting periods is posted to the database each is stored separately.
This enables Current Period and Cumulative Earned Value Reporting since current period earned
value is always equal to current cumulative values minus the cumulative values at the end of the prior
period.
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 7
Steps Description / Image
Post Current Period Data into a new or existing Database
for reporting Earned Value
Click Performance Vs. Baseline on the Performance
And Earned Value group of the SSI Analysis Tools
ribbon in Microsoft Project
1. Connect to an existing database or make a new one by
entering a database name and location
Name and Location for Metrics Records and
Reporting Database can be a new value entered by
the user or it can map to an existing record set for
projects and reporting periods
Task Records Maintenance shows existing Project
and Periods in the Database. If necessary, use this
control to Delete All Task Records for the selected
project and reporting period
Enter a name and location for the database. If the database
does not exist, a new one will be created using the name and
location provided
2. Enter Project Unique Name or ID
Record sets in the Database are stored separately by
their Project Unique Name or ID and the reporting
period
Each Project should have its own Project Unique
Name or ID to prevent data from one project from
mixing with data from another project
Project Unique Name or ID is taken from the
Project’s Summary Title. Display the Project’s
Summary (Format menu / Summary Task) or select
Project Information from the File menu to view or
change the summary title
Double-click Project Status Date to open the Project
Information form and select a Status date for the
project
Name of Project and Reporting Period in Database
Note – The Project Status Date should match the Current
Period End Date in the section below
3. Select Reporting Periods and Intervals
Select one of the reporting intervals (Every Week, 2
Weeks, Month or User Defined Periods*)
Reporting Intervals and Current Period Start and End Date
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 8
Steps Description / Image
Current Reporting Period End Date is taken from the
Project’s Status date
Current Reporting Period Start Date is determined
by the reporting interval
*If User Defined Periods is selected, a list of custom
calendars is displayed. Select or create a Defined Periods
table and pick from the list of Reporting Periods if using
this option
Double-click Select a Defined Periods Table to see its
list of Periods, Start and End dates in a table
Select a Reporting Period to use its Period Start and
End date as the current period
The default System Location for Defined Periods is
the installation location for SSI Tools. That location
will contain sample Defined Periods record sets in a
folder named “TSV”. Another way to make your own
defined periods tables is by using Excel to open the
example files, edit them in Excel and save as a
Comma Separated Values file format with a name that
begins with “TSV”
Note –the Current Period End Date should match the
Project Status Date in the section above
4. Click Post Current Period Data
Post Task Data records information about tasks in the
schedule
Include Task Usage adds information about the
resources assigned to tasks, if they exist
Select All Tasks to post information about each tasks
in the active schedule or Selected Tasks to post data
for the tasks in the current selection
Data Exists Warning appears whenever data for the
project in the same period is found in the database
Replace All completely removes data for the period
and replaces with current records. Use this option if
significant changes have been made to the project
tasks and a complete new record set is desired
Replace Matching Records is a good option to use if
you are correcting just one or a few tasks in the
project and want to preserve all other records in the
reporting period
Select which tasks to post to the database.
Choose how to handle existing data if SSI Tools finds
records for the same project in the same reporting period
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 9
Steps Description / Image
Append is useful when you want to add more task to
the existing record set in the database
Cancel allows you to exit to posting operation and go
back to the previous form
Practice – On your own
1. Open Microsoft Project and open the project named
ExampleProject(EVM).mpp
2. Click Performance Vs. Baseline on the Performance
And Earned Value group of the SSI Analysis Tools
ribbon in Microsoft Project
3. Enter c:\SSI_Tools\Class_ExampleEVM.mdb as shown
below for the Name and Location for Metrics Records
and Reporting Database
Project 2003 - 2007 Toolbar
Project 2010 -2013 tools from SSI Analysis Tools menu
4. Set the Project Status Date to 3/31/2015 by double-
clicking Project Status Date and entering the status
date on the Project Information form
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 10
Steps Description / Image
5. Select User Defined Periods for the reporting interval
6. Use TSV_2015-4-4-5-FiscalCal.csv as the Defined
Periods Table 7. Select the period labeled 201503 which starts on
02/23/2015 and ends on 03/31/2015 for the reporting
period
8. Click Ok on the Select Defined Periods form
Example for Steps 6 - 8
Steps Description / Image
9. Post Current Period Data to the new database
10. Make an Earned Value report for the project
Complete the Project Earned Value Reporting form
as shown by the example to the right and click Make
EV Report
Click the Excel Icon or activate Excel to see the
Earned Value report created by SSI Tools
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 11
Does your report look like this?
Adding Subsequent Reporting Periods to the Database
Whenever a Project Performance and Earned Value Reporting database contains two or more record
sets from the same project, additional reporting options can be selected for Earned Value reports. The
database keeps separate record sets for each project and for each project’s reporting periods. Having
two or more record sets enables current period as well as cumulative earned value reporting and the
Baseline data from the current and prior periods can be inspected for changes.
Cumulative and Current Period EV shows planned value, earned value and actual value in the current
period by subtracting cumulative values from the prior period from cumulative values in the current
period.
Make Change Log compares data from the prior reporting period to data from the current reporting
period and finds Added Work Packages, Deleted Work Packages and Changes to the Baseline Start
date, Finish Date and Baseline Resource Assignment values. Adds, Deletes and Changes are recorded in
a change log Excel worksheet that is included with an Earned Value report.
Practice – On your own
Add a second reporting period to the same database. A summary of the steps taken in this section are as follows:
Advance the Reporting Period End Date to 04/26/2015
Status all tasks through the new status date
Add a new Work Package, Delete an Existing Work Package and Change the Baseline for another Work Package
Post Task and Task Usage for All Tasks to the database created in the prior steps
Make an Earned Value report that shows Cumulative and Current Period EV with a Change Log (showing baseline
changes from one period to the next)
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 12
Steps Description / Image
1. Using the project from the last exercise, advance the
Reporting Period End Date to 04/26/2015
Select Project Information from the Project menu
Change the Status date to 4/26/2015 and click Ok
2. Status all tasks through the new status date
Find tasks occurring prior to the Status date requiring
updates using
Tip – use SSI Analysis Tools / Schedule Integrity
Audits to find these tasks using the Invalid Status audit
If using Project 2010 or 2013, mark these task as being
on track using Microsoft Project’s Mark on Track tool
on the Task menu
If using Project 2003 or 2007, mark these task as being
on track using Microsoft Project’s Update as
Scheduled tool on the Tracking toolbar. Or use
Tracking / Update Project from the Tools menu as
shown below
Update as Scheduled on Tracking Toolbar
Update Project from Tools / Tracking
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 13
Steps Description / Image
3. Add a new Work Package, Delete an Existing Work
Package and Change the Baseline for another Work
Package
Select row 37 and change its WP ID (Text1) to
WP2.8.X. SSI Tools will identify this as a New Work
Package since its value did not exist in the prior
reporting period. At the same time, SSI Tools will no
longer find WP2.8 in the current record set so it will
identify it as a Deleted Work Package
Select rows 56 – 57 and reset their baseline by selecting
Set Baseline from the Project menu (Project 2010 -
2013 users) or Set Baseline from Tools / Tracking if
using Project 2003 – 2007
Be careful to Set Baseline for Selected tasks (rather
than for the Entire project) by carefully completing the
form as shown by the example to the right
This step demonstrates how Changes logs are created by
SSI Tools. If a Change log is added to an Earned Value
report it will appear in the reports Excel workbook as a
separate worksheet named ChangeLog.
Set Baseline for Selected tasks only
4. Post Task and Task Usage for All Tasks to the database
Click Performance Vs. Baseline on the Performance
And Earned Value group of the SSI Analysis Tools
ribbon in Microsoft Project
Make sure all the selections on Project Performance
and Earned Value Reporting are as shown to the right
– then Click Post Current Period Data
Post Data for the Period ending 04/26/2015
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 14
Steps Description / Image
5. Make an Earned Value report that shows Cumulative
and Current Period EV with a Change Log (showing
baseline changes from one period to the next)
Click the Earned Value button on Project Performance
and Earned Value Reporting
Select the options named Get Cumulative & Current
Period EV, Make Pivot Table in Report and Make
Change Log on the form named Project Earned Value
Reporting (see the example to the right)
Click the Excel Icon or activate Excel to see the Earned
Value report created by SSI Tools
Does your report look like this?
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 15
Does the sheet named ChangeLog look like this?
Importing Actual Values
When using Task Work or Task Cost as the Earned Value Unit of Measure, you can override Microsoft Project’s actual
values by Importing Cumulative Actual Values from an Excel worksheet. You can import values for each Work Package
or you can import values at the Work Package Parent level. The simple format for a worksheet contains imported values is
as follows:
Work Package or Work Package Parent ID
Resource Name
Resource Type (Labor, Material, Travel, Other Direct Cost for example)
Cumulative Work amount
Cumulative Cost amount
Below is an example of a worksheet in excel containing Actual values for a project
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 16
Steps Description / Image
1. Click Performance Vs. Baseline on the Performance
And Earned Value group of the SSI Analysis Tools
ribbon in Microsoft Project
2. Select Task Work or Task Cost as the Earned Value
Unit of Measure and Imported Cumulative Actual
Values as the EV Actuals (AC) or ACWP option 3. Click Import Cumulative Actual Values
4. Select the Name and Location of a Excel workbook
containing actual values
5. Select the name of the Worksheet to Use in the selected
workbook
6. Look at the Worksheet Preview and map the columns
in the worksheet to the following key values for Earned
Value reporting:
Column with Matching Work Package Id (If you
don’t match at the Work Package level, you can set
this value to None)
Column with Matching Work Package Parent
(Rollup) Id
Column with Resource Name
Column with Resource Type
Column with Work Value
Column with Cost Value 7. Select the reporting period for cumulative values using
the drop-down list next to “Actual Values are for
Reporting Period Ending”
8. Click Import Actual Values
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 17
When using Imported Actual Values that are rolled-up to the Work Package Parent level an Earned Value report will show
zero in the Tot AV or Cur_AV column. In this case, SSI Tools adds a new Work Package named WP-Imp-Act at the
Work Package Parent level. Since no actual values exist for Work Packages, you will only be able to perform analysis of
Cost Variances (CV) at the Parent level.
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 18
Practice – On your own
Import actual work values into the Performance and Earned Value reporting database
Steps Description / Image
1. Click Performance Vs. Baseline on the Performance
And Earned Value group of the SSI Analysis Tools
ribbon in Microsoft Project
2. Click Earned Value on the Project Performance And
Earned Value Reporting form
3. Select Imported Cumulative Actual Values
4. Click the button named Import Cumulative Action
Values
Step 3
Step 4
5. Select the Excel Workbook with Actual Values named
“ImportedActualValues2015.xlsx”
6. Select “April2015” for Worksheet to Use
Look at the Worksheet Preview and map the columns in
the worksheet to the following key values for Earned
Value reporting: (See Example to the right)
Column with Matching Work Package Id = None
Column with Matching Work Package Parent (Rollup)
Id = WP ID Parent
Column with Resource Name = Resource Name
Column with Resource Type = Resource Type
Column with Work Value = Work
Column with Cost Value = Cost
Actual Values are for Reporting Period Ending =
4/26/2015 5:00:00 PM
7. Click Import Actual Values
8. Close the form named Import Actual Values when done
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 19
9. Use the settings shown to the right and click Make EV
Report using data through 4/26/2015
Does your report look like this?
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 20
10. Remove Task Name from the Pivot Table and Replace
it with Res_Name (Resource Name)
Click inside the Pivot table and select Field List from
the Analyze menu in Excel
Change the Rows in the Pivot table by replacing
TaskName with Res_Name
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 21
Does your report look like this?
Do the same as above but replace Res_Name with Res_Type
SSI Analysis Tools Training
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 22
Using Earned Value Reports
Click the button named See Example & Description on the Project Earned Value Reporting form to see
useful tips and explanations of SSI Tools reports.
Earned Value Pivot Table Report Example & PV and EV Projections Chart