Sums: Operations Scheduling
Type 1 - Scheduling n jobs on one machine
Priority Rules for Job sequencing:
1. FCFS (First-come, first-served) orders are run in the order they arrive in the department.2. SOT (Shortest operating time.)Run the job with the shortest completion time first, next shortest second and
so on. It is also referred to as SPT (Shortest processing time).
3. EDD (earliest Due date first) Run the job with earliest due date first.4. STR (Slack time remaining) Orders with shortest slack time remaining (STR) are run first.
STR = Time remaining before due date Remaining processing time.
5. STR/OP (slack time remaining per operation). Orders with the shortest slack time per number of operationsare run first.
STR/OP = STR/ Number of remaining operations
6. CR (Critical ratio) this is calculated as the difference between the due date & the current date divided by thenumber of work days remaining. Orders with smallest CR are run first.
7. LCFS (Last-come, first-served). As orders arrive they are placed on top of the stack the operator usuallypicks up the order on top to run first.
8. Random order or Whim. The supervisor or operators usually select whichever job they feel like running.Sum: 1
Job ( in order of
Arrival)
Processing Time
(Days)
Due Date
A 3 5
B 4 6
C 2 7
D 6 9
E 1 2
Solution:
Method :1 First Come First Serve ( FCFS )
Job Seq.
Processing
Time
(Days)
Due Date
(Days
Hence)
Flow Time
Late by
(Comparing
Due date with
Flow time )
A 3 5 0 + 3 = 3 0
7/31/2019 Sums Print OperationsScheduling
2/14
2 | P a g e
B 4 6 3 + 4 = 7 1
C 2 7 7 + 2 = 9 2
D 6 9 9 + 6 = 15 6
E 1 2 15 + 1 = 16 14
Total
Flow Time /
Late by
50 23
Average Flow
Time
/ Late by
10 divide 5 23 divide 5
10 4.6
Method :2 Shortest Operating Time ( SOT )
Job Seq.
Processing
Time
(Days)
Due Date
(Days
Hence)
Flow Time
Late by
(Comparing
Due date with
Flow time )
E 1 2 0 + 1 = 1 0
C 2 7 1 + 2 = 3 0
A 3 5 3 +3 = 6 1
B 4 6 6 + 4 = 10 4
D 6 9 10 + 6 = 16 7
Total
Flow Time /
Late by
36 12
Average FlowTime
/ Late by
36 divide 5 12 divide 57.2 2.4
Method :3 Earliest Due Date ( EDD )
Job Seq.
Processing
Time
(Days)
Due Date
(Days
Hence)
Flow Time
Late by
(Comparing
Due date with
Flow time )
E 1 2 0 + 1 = 1 0
A 3 5 1 + 3 = 4 0
B 4 6 4+ 4 = 8 2
C 2 7 8 + 2 = 10 3
D 6 9 10 + 6 = 16 7
7/31/2019 Sums Print OperationsScheduling
3/14
3 | P a g e
Total
Flow Time /
Late by
39 12
Average Flow
Time
/ Late by
39 divide 5 12 divide 5
7.8 2.4
Method :4 Last Come First Serve ( LCFS )
Job Seq.
Processing
Time
(Days)
Due Date
(Days
Hence)
Flow Time
Late by
(Comparing
Due date with
Flow time )
E 1 2 0+1 = 1 0
D 6 9 6+1 = 7 0
C 2 7 7 + 2 = 9 2
B 4 6 9 + 4 = 13 7A 3 5 13+ 3 = 16 11
Total
Flow Time /
Late by
46 20
Average Flow
Time
/ Late by
46 divide 5 20 divide 5
9.2 4
Method :5 Slack Time Remaining Per Operation ( STR )
Calculation of Slack
Job ( in order of
Arrival)
Processing
Time
(Days)
Due Date
STR
= DD - PT
A 3 5 2
B 4 6 2
C 2 7 5D 6 9 3
E 1 2 1
Note : Orders with shortest slack time run first
7/31/2019 Sums Print OperationsScheduling
4/14
4 | P a g e
Job Seq.
Processing Time
(Days)
Due Date
(Days Hence)
STR
= DD - PT
Flow
Time
Late by
(Comparing Du
date with Flow
time )
E 1 2 1 0 + 1 = 1 0
A 3 5 2 1 + 3 = 4 0
B 4 6 2 4 + 4 = 8 2
D 6 9 3 8 + 6 = 14 5
C 2 7 5
14 + 2 =
16 9
Total
Flow Time /
Late by
43 16
Average Flow
Time
/ Late by
43 divide
5 16 divide 5
8.6 3.2
7/31/2019 Sums Print OperationsScheduling
5/14
5 | P a g e
Type 2 Scheduling n jobs on two machines (Johnsons rule)
Johnsons Rule is:
1. From the list of unscheduled jobs, select the one with the shortest processing time in either work center.2. If the shortest time is at the first work center, do the job first in the schedule otherwise do the job last in the
schedule.
3. Remove the job assigned in Step 2 from the list of unscheduled jobs.4. Repeat steps 1,2 and 3 filling in the schedule from the front and the back until all jobs have been scheduled.
Sum: 1
Job Machine A
( Times in hours)
Machine B
( Times in hours)
J1 8 4
J2 6 7
J3 5 5
J4 7 4
J5 3 6
J6 9 8
Solution:
Optimum
Sequence
1 2 3 4 5 6
J5 J3 J2 J6 J4 J1
Choose the smallest time 3 hrs J5 ( on 1st Machine) so placed this job in the beginning; Next lowest time J1 or J4 4 hrs. Since tie choose J1 (earlier in numbering of jobs.) ( on 2 nd machine )
So place J1 end of sequence. And place J4 at the end (unfilled space)
Next lowest J3 5 hrs (same time on both machine so tie) choose 1st machine so place J3 frombeginning after J5.
J2 6 hrs (1st Machine) Place this job from the beginning of sequence. J6 in vacant place.Note:
When there is a tie in two stages for two different jobs. In this case, place the job with the smallest time inthe first stage as early as possible in the unfilled job sequence.
7/31/2019 Sums Print OperationsScheduling
6/14
6 | P a g e
Calculation: Cycle time / idle time Machine A & B
JobMachine A
( Times in hours)
Machine B
( Times in hours)
Max Time
Required
J1 8 4 8
J2 6 7 7
J3 5 5 5J4 7 4 7
J5 3 6 6
J6 9 8 9
Operation time
Machine A /B38 34
42
Idle time
machine A/B4 8
Determination of Cycle time & idle time of the two machines: Two methods that can be used:
1. Graphical method or Gantt chart method2. Tabular column method
Tabular Column method:
Job
Sequence
Machine A Machine B Idle time
OperationTime
OT
Time In
TI
Time out
TO
OperationTime
OT
TimeIn
TI
Time out
TOMachine A Machine B
J5 3 0 3 6 3 6 + 3 = 9 - 3
J3 5 3 5 + 3 = 8 5 9 9 + 5 = 14 - -
J2 6 8 14 7 14 21 - 2
J6 9 14 23 8 23 31 -
J4 7 23 30 4 31 34 - 3
J1 8 30 38 4 38 42 4 -
4 8
7/31/2019 Sums Print OperationsScheduling
7/14
7 | P a g e
Graphical method or Gantt chart method: - last page.
7/31/2019 Sums Print OperationsScheduling
8/14
8 | P a g e
Type 3 Scheduling a set of number of jobs on the same number of machines (n things
n destination) The Assignment method.
The assignment method is appropriate method in solving problems that have the following characteristics:
1.There are n things to be distributed to n destination2.Each thing must be assigned to one & only one destination.3.Only one criterion can be used (minimum cost, maximum profit, or minimum completion time etc...)
Steps:
Step : 1 Subtract the smallest number in each row from itself & all other numbers in that row. (There will
be at least 1 zero in each row.)
Step : 2 Subtract the smallest number in each column from itself & all other numbers in that column
(There will be at least 1 zero in each column.)
Step : 3 Determine if the minimum number of lines required to cover each zero is equal to n.
If so optimal solution has been found, because job machine assignments must be made at the zero
entries, & this test proves that this is possible.
If minimum number of lines required is less than n, go to step 4.
Step : 4 Draw the least possible number of lines through all the zeros.
Subtract the smallest number not covered by lines from itself & all other uncovered numbers &
add it to the number at each intersection of lines Repeat step 3.
7/31/2019 Sums Print OperationsScheduling
9/14
9 | P a g e
Sum: 17
Machine
1 2 3 4 5
Job
A 6 11 12 3 10
B 5 12 10 7 9
C 7 14 13 8 12
D 4 15 16 7 9
E 5 13 17 11 12
Solution:
Step: 1 Row reduction
Machine
1 2 3 4 5
JobA 3 8 9 0 7
B 0 7 5 2 4
C 0 7 6 1 5
D 0 11 12 3 5
E 0 8 12 6 7
7/31/2019 Sums Print OperationsScheduling
10/14
10 | P a g e
Step: 2 Column reduction
Machine
1 2 3 4 5
JobA 3 1 4 0 3
B 0 0 0 2 0
C 0 0 1 1 1
D 0 4 7 3 1
E 0 1 7 6 3
Step: 3 Minimum number of lines
Lines = 4 not equal to machines = 5
7/31/2019 Sums Print OperationsScheduling
11/14
11 | P a g e
Step: 4
Smallest uncovered number was 1.
So subtracting 1 from uncovered numbers and adding in to the number at each intersection of lines.
Optimum Solution:
Note:
Start assigning with line with 1 zero.
Delete row & column & carry out the same process for all jobs.
7/31/2019 Sums Print OperationsScheduling
12/14
12 | P a g e
Assign Cost
1st
- A 4 Rs3
4th - B 3 10
5th - C 2 14
3rd
- D 5 9
2nd
- E 1 5
Total Rs41
Type 4 - Consecutive days-off (Sums 4, 8, 9, 16)
Objective:Finding the schedule that minimizes the number of five-day workers with two consecutive days off.
Steps:
Step: 1 Assign the first worker to all of the days that require staffing.
Simply recopy the total requirement for each day.
Circle the two consecutive days with the lowest numbers, These will be considered for days off.
In case of ties:
Choose the days-off pair with the lowest requirement on an adjacent day.
If tie still remains choose the first of the available tied pairs.
Step: 2 For worker 2,Subtract 1 from each of the days not circled with positive number & enter this in the worker 2
row.
This indicates that 1 less worker is required on these days because the first worker has just been
assigned to them.
The 2 steps are repeated for the second worker third so forth until no more workers are required
to satisfy the schedule.
7/31/2019 Sums Print OperationsScheduling
13/14
13 | P a g e
Sum: 4
Jumbos restaurant is trying to create a consecutive-days-off schedule that uses the fewest workers. Use thefollowing information to create a 5 days on 2 days off schedule.
Day M Tu W Th F S Su
Requirements 2 2 1 3 3 4 2
Solution:
7/31/2019 Sums Print OperationsScheduling
14/14
14 | P a g e
Type 5 First-hour principle
The first-hour rule says that for the first hour we assign a number of workers equal to the requirement in
that period.
For each subsequent period assign the exact number of additional workers to meet the requirements.
When in a period one or more workers come to the end of their shifts add more workers only if they are
needed to meet the requirement.
Sum: 2
A hotel has to schedule its receptionist according to hourly loads. Mgt has identified the number of receptionist
needed to meet the hourly requirement which changes from day to day, Assume each receptionist works a 4
hour shift. Given the following requirement in a certain day use first-hour principle to find the personnel
schedule:
Period
8AM 9AM 10AM 11AM Noon 1PM 2PM 3PM 4PM 5PM 6PM 7PM
Requirement 2 3 5 8 8 6 5 8 8 6 4 3
Solution: