T-76.115 Project ReviewT-76.115 Project Review
Agenda
Introduction (5 min) Skipped if all review attendees are familiar with the project
Project status (15 min) Achieving the goals of the iteration Project metrics
Work results (10 min) Presenting the iteration’s results Demo
Used work practices (5 min) Next iteration planning (5 min) Discussion
5 min 15min 10min 5min 5min
1
3
T-76.115 Project ReviewT-76.115 Project Review
Introduction to the project
Customer: Beconnected Finland Ltd. Produces IP-based video surveillance systems for international market Main product: ASAN = Automatic Surveillance and Alarming Network Customer representative: PhD Michael Samarin
Project team: Aino Lahdenperä, Maija Kangas, Outi Syysjoki, Janne Ojala, Antti Alestalo,
Juhani Nokela, Ville Vatén GOAL: Produce tools, which help Beconnected in their customer support
work and reduce costs through increased productivity Three tools will be created:
Watchdog – Automatic monitoring of network cameras HourLogger – Log support person’s work hours per customer/target LogAnalyzer – Search for error patterns from ASAN logs
Beconnected’s goals: Working software is the only thing that matters KISS – Concentrate on simplicity, maintainability, quality. No fancy features Very busy making business – we should bother them as little as possible Minimize costs – all costs should be covered by the attendance fee to SoberIT
5 min 15min 10min 5min 5min
3
4
T-76.115 Project ReviewT-76.115 Project Review
Overview of the problem domain
5 min 15min 10min 5min 5min
5
5
T-76.115 Project ReviewT-76.115 Project Review
Status of the iteration’s goals
Goal 1: Set up development environment OK, except servlet debugger still does not work
Goal 2: Watchdog core functionality We had a slight misroute on the way but are now on the right track Almost there but no QA performed.
Goal 3: Hourlogger core functionality OK, except only minor QA performed yet
Goal 4: LogAnalyzer architecture We have planned, but no official documents exist yet LogAnalyzer UI has not been planned yet
Goal 5: Requirements maintained and detail level increased OK
Goal 6: SEPA practices used and revised Not OK, Usability Tests postponed, No time for Design Patterns, Pair
Programming used slightly, Meeting practices used, but not revised. Goal 7: Quality Assurance plan
OK, but actual QA hasn’t started yet due to resources problems
5 min 15min 10min 5min 5min
7
6
T-76.115 Project ReviewT-76.115 Project Review
Status of the iteration’s deliverables
Project Plan Quality Assurance plan: problems due to Maija’s absense OK
Requirements document OK
Watchdog core functionality Almost there, demonstrated to Beconnected this morning
Watchdog technical specification Sent documentation to Beconnected, but is somewhat outdated
Hourlogger core functionality OK
Hourlogger technical specification OK, sent documentation to Beconnected
Test case document POSTPONED: QA activities have not been started yet
Agreement on legal rights to project deliverables NOT OK. We still don’t have a written contract about the legal rights to the
project deliverables with the customer.
5 min 15min 10min 5min 5min
9
7
T-76.115 Project ReviewT-76.115 Project Review
Realization of the tasks Major discrepancies
Architectural design of too complex system takes time…
Programming slower due to slow debugging cycle…
Development environment setup has really been pain in the ***.
A lot of miscellaneous project communication not budgeted
Not started: Systematic QA postponed
to I2 due to Maija’s absense and slower progress than expected
Still not much effort on SEPAs
5 min 15min 10min 5min 5min
11
8
T-76.115 Project ReviewT-76.115 Project Review
Realization of budget
Monthly allowance of € 100 for miscellaneous well justified project costs
October costs: € 1 for mailing the NDAs $ 43 for buying Core Servlets and JavaServer Pages, Vol. 1 from Amazon
November costs: € 22 for pizza and coke for long weekend coding session € 17.30 for pizza and coke for the final crunch coding session on Monday
5 min 15min 10min 5min 5min
12
9
T-76.115 Project ReviewT-76.115 Project Review
Working hours by person
Maija had to leave Finland and haven’t been able to work at all for the project
Ville had to write the QA plan and has also performed design, testing and development environment setup.
Aino’s figure is more than 38 hours… Work distribution among members has equalized since PP
Realized hours in this iteration
5 min 15min 10min 5min 5min
13
10
T-76.115 Project ReviewT-76.115 Project Review
Working hours by person
Shifted weight from the FD iteration to I2 iteration.
It’ll be interesting to see can Maija gain on us her lost hours in I1
Realized hours in this iteration Plan in the beginning of this iteration
Latest plan (realized hours, updates up and down)
5 min 15min 10min 5min 5min
14
11
T-76.115 Project ReviewT-76.115 Project Review
Quality metrics
Full controlled QA has not started yet Concentration on the architecture and core functionality Only minimal error handling implemented currently
I1 I2 FD TotalReported 11 11Closed 4 4Open 7
Bug metrics
Blockers Critical Major Normal Minor Trivial Enhancement
Total
Total open 0 0 0 1 2 1 3 7This iteration reported
0 0 0 1 2 1 3 7
5 min 15min 10min 5min 5min
15
12
T-76.115 Project ReviewT-76.115 Project Review
Quality assessment
Functional area Coverage Quality Comments
Requirements Document
2 Improving all the time
Project Plan 2 Has been reviewed
Development Environment
2 Works and has been used
Watchdog 0 Core functionality almost ready, not tested
HourLogger 1 Core functionality ready and tested quickly
SEPA documents 1 Only the minimal stuff exists yet
Legend
Coverage:
0 = nothing
1 = we looked at it
2 = we checked all functions
3 = it’s tested
Quality:
= quality is good
= not sure
= quality is bad 5 min 15min 10min 5min 5min
16
13
T-76.115 Project ReviewT-76.115 Project Review
Software size in Lines of Code (LOC)
Concentrated on architecture and core functionality Not all the lines here are actual live code Code refactoring needed
PP I1 I2 FD
Watchdog java classes 0 2910
Watchdog JSPs 0 970
HourLogger JSPs 0 851
LogAnalyzer JSPs 0 0
Testing and example JSPs 0 201
Utils 0 1882
Other 0 134
Total (NCLOC + COM) 0 6948
5 min 15min 10min 5min 5min
17
14
T-76.115 Project ReviewT-76.115 Project Review
Risks
Risks Maija’s absense affects our QA activities => forced to postpone most of it to I2 Development environment
An old computer running in Ville’s wardrobe Work is highly dependent on working Trinet and Aalto
Also needed for the demo in the project review NDA is very strict
We can not publish something critical to the course We may publish something that breaches the NDA
Busy schedules among group members Potential communication problems Quality problems among team member deliverables
5 min 15min 10min 5min 5min
19
15
T-76.115 Project ReviewT-76.115 Project Review
Changes to the project
Iteration 1 was turned into prototyping and architecture implementation QA was postponed to I2-FD due to Maija’s absence More critical to get the functionality working than QA at this point
Small changes to requirements Natural process of refining customer needs and finding out new requirements
5 min 15min 10min 5min 5min
20
16
T-76.115 Project ReviewT-76.115 Project Review
Results of the iteration
Watchdog demonstration
HourLogger demonstration
5 min 15min 10min 5min 5min
20
17
T-76.115 Project ReviewT-76.115 Project Review
Watchdog
Watchdog Monitors status of network camera on predefined intervals Alarms when malfunction occurs Records historical data of network camera statuses and erases old data
Architecture We were building too complex system and wasted time Now everything seems to be on the right track…
Implemented functionality Background process: Fetches images from cameras and analyzes them Camera list: Lists cameras and their current and past status Camera info: Basic functionality is there, easy to expand Configuration
User is able to change some parameters Not all parameters implemented yet
Not implemented Alarms and their configuration
QA has not started yet due to Maija’s absense
5 min 15min 10min 5min 5min
22
18
T-76.115 Project ReviewT-76.115 Project Review
Demonstration
Watchdog We’ll show you how background process works (by breaking up cameras!) You’ll see the main view of the system and camera info view Camera IPs have been censored to protect customer IP
5 min 15min 10min 5min 5min
27
19
T-76.115 Project ReviewT-76.115 Project Review
HourLogger
HourLogger Logs technician's work hours per customer, per target and per work type Produces reports of the recorded work tasks
Architecture This is not rocket science More focus will be paid on the usability
Implemented functionality Input work tasks and types Overview of worktypes Usability tuning still needed. This will be continued in I2
Not implemented Reports, Exporting, Customer/target management
Only minimal QA performed All problems found have been easily fixed
5 min 15min 10min 5min 5min
28
20
T-76.115 Project ReviewT-76.115 Project Review
Demonstration
HourLogger Inserting a new performed check Showing the overview of performed checks per customer and target
5 min 15min 10min 5min 5min
30
21
T-76.115 Project ReviewT-76.115 Project Review
Used work practices
Time reporting in Trapoli Still difficulties in time logging: dividing working hours and usability
Development server in Ville’s clothes closet Problems with Trinet… Long development cycle Difficult debugging
Meetings Worked well, but still scheduling problems among group members
Risk management Risks have been managed, but not documented very well…
Requirements elicitation and analysis Continued with the same style than in PP phase
Group working sessions Group architectural design sessions Group user interface design sessions Group coding sessions with a couple of pair programmin sessions
Coding convention Not complete Nobody has completely followed the guidelines
5 min 15min 10min 5min 5min
35
22
T-76.115 Project ReviewT-76.115 Project Review
Iteration I2 Goals
Generic goals: Quality Assurance really started now Code refactoring needed Coding convention, commenting, documenting improved
Watchdog & HourLogger & LogAnalyzer goals Minimum requirements functionality ready and fully tested Test installation in customer’s test environment Usability tests performed with customer representative with actual work tasks
SEPA goals: Pair programming sessions on most critical use cases Usability tests performed for all deliverables Design patterns used in refactoring Meeting practices are reviewed and improved
Iteration I2 divided to two sub-iterations Three weeks development, then installation to customers environment One week for customers internal testing and commenting One week for applying customer’s feedback back into the products