AZT-22AZT-221. Astroclimate of Dome1. Astroclimate of Dome2. Optical system2. Optical system3. Field corrector 20’ and 50’3. Field corrector 20’ and 50’4. Mechanical system4. Mechanical system5. Digital pointing and guiding5. Digital pointing and guiding6. Coating mirrors Al+SiO film6. Coating mirrors Al+SiO film
LOMOLOMO 1.5- 1.5-mm. . AZT22AZT22
Coating mirrorsCoating mirrors
• 1. Dismantling mirrors
• 2. Sending mirrors to LOMO
• 3. Coating mirrors (LOMO)
• 4. Assembling mirrors
• 5. Control optics• 5-6 people (Moscow, Kharkov, Tashkent, LOMO)
• 2-3 month of stop telescope• 20000-25000 $