The MiniBooNE Horn

Post on 04-Jan-2016

42 views 0 download

Tags:

description

The MiniBooNE Horn. Ioanis Kourbanis For The MiniBooNE Collaboration. Outline. List of people Horn characteristics Horn Power Supply Horn Striplines Highlights of Horn Construction and Assembly Horn Testing Horn Changeover Future Plans. List of People. C. Anderson - PowerPoint PPT Presentation

transcript

NBI 14-19 March 2002

The MiniBooNE Horn

Ioanis Kourbanis

For

The MiniBooNE Collaboration

NBI 14-19 March 2002

Outline

List of people Horn characteristics Horn Power Supply Horn Striplines Highlights of Horn Construction and Assembly Horn Testing Horn Changeover Future Plans

NBI 14-19 March 2002

List of People• C. Anderson

• L. Bartotzek (Bartoszek Engineering)

• L. Bartelson

• L. Bugel

• C. Jensen

• H. Le

• B. Markel (Markel & Associates)

• J. Misek

• F. Nezrick

• H. Pfeffer

• R. Reilly

• D. Snee

• M. Sorel

• E. Zimmerman

NBI 14-19 March 2002

Horn Characteristics

We are using one horn with a narrow neck and a conical inner conductor (BNL Design) designed to run at a current of 170 KA.

The horn is made out of Al alloy 6061-T6 and is excited by a 143 sec current pulse. Keep the voltage at the PS below 10 KV (use solid state SCR’s

instead of thyristors) Reduce the current pulse width as much as possible to avoid

excessive heating of the horn . Keep the voltage at the horn as low as possible (small inductance).

The horn will operate at an average rep rate of 5 Hz. Total average power deposited in the horn is 2.4 KW.

NBI 14-19 March 2002

3-D Model of the Horn

NBI 14-19 March 2002

Horn Power Supply

The Power Supply consists of a Capacitor bank (1,344 F) discharged through an inductive load by an SCR switch. The system has a separate circuit for energy recovery.

The circuit is divided into 16 parallel capacitors, each with its own SCR switch.

NBI 14-19 March 2002

Horn PS Parameters

DESIGN OPERATION

Pulse Amplitude(KA)

250 170

Rep. Rate(Hz)

7.5 5.0

Circuit Inductance(microH)

1.78 1.33

Operating Voltage(kV)

9.5 5.4

Average Power(kW)

62 19

NBI 14-19 March 2002

Power Supply Schematic

NBI 14-19 March 2002

Power Supply View (Front)

NBI 14-19 March 2002

Power Supply View (Back)

NBI 14-19 March 2002

Horn Stripline Balanced design (odd number of conductors) to

minimize forces. The conductor spacing is 1 inch. Fluted alumina

insulators with a 2 inch creepage length were used to separate the conductors.

The test stripline piece, along with a clamped joint, were corona tested.

The inductance of the final stripline was measured to be 18.5 nH/m.

NBI 14-19 March 2002

View of the Long Stripline Section

NBI 14-19 March 2002

View of a Stripline Joint

NBI 14-19 March 2002

View of the Small Stripline Section

NBI 14-19 March 2002

Construction and Assembly Highlights

Forged Outer Conductor The water sprayers were vibration isolated from

the Horn Outer Conductor. Solid connections from the striplines to the Horn. The Horn Inner Conductor was welded at

Fermilab using a programmable TIG welding machine.

NBI 14-19 March 2002

Outer Conductor after Forging

NBI 14-19 March 2002

Outer Conductor after Machining

NBI 14-19 March 2002

Outer Conductor after Welding

NBI 14-19 March 2002

Water Manifolds

NBI 14-19 March 2002

Water Truss

NBI 14-19 March 2002

Water Truss and Water Manifolds

NBI 14-19 March 2002

Water Truss Bellows Detail

NBI 14-19 March 2002

Water Connection Detail

NBI 14-19 March 2002

Outer Conductor with Water Truss

NBI 14-19 March 2002

Water Drain Connection

NBI 14-19 March 2002

Water Nozzle Detail

NBI 14-19 March 2002

Twist Transitions

NBI 14-19 March 2002

Inner Conductor Before Welding

NBI 14-19 March 2002

Hand Scraping before Welding

NBI 14-19 March 2002

Welding Sample

NBI 14-19 March 2002

Large Weld

NBI 14-19 March 2002

Small Diameter Weld

NBI 14-19 March 2002

Inspecting the Small Diameter Weld

NBI 14-19 March 2002

Radiography of Weld

NBI 14-19 March 2002

Radiography of Large Weld

NBI 14-19 March 2002

Moving the Inner Conductor from The Welding Machine

NBI 14-19 March 2002

Inserting the Inner into the Outer Conductor

NBI 14-19 March 2002

Horn Testing

The horn was pulsed for the first time on 07/27/01. The horn test was completed on 02/12/02 after completing 11M pulses

at full current. We completed horn magnetic field measurements. Completed a series of vibration measurements. Things we were monitoring:

Total current Current in the four striplines feeding the horn Total voltage Cooling water supply and return temperatures Horn temperatures

NBI 14-19 March 2002

Overview of MI-8 Test Area

NBI 14-19 March 2002

Horn module overview

NBI 14-19 March 2002

Stripline Configuration at the TSB

NBI 14-19 March 2002

Current and Voltage Profiles

NBI 14-19 March 2002

Horn Magnetic Field Measurement

NBI 14-19 March 2002

Horn Temperature Profiles with Different Sprayer Configurations

NBI 14-19 March 2002

Correlation between Horn and Water Return Temperatures

NBI 14-19 March 2002

Horn Vibration Spectrum

NBI 14-19 March 2002

Horn Axial Displacement vs. Time

NBI 14-19 March 2002

Horn Changeover

The horn module is expected to be highly radioactive (30 Rad/hr at 2 ft).

In order to reduce the Radiation Exposure to under 100 mR/hr at 1 ft, the shielding requirement is 5” of steel on all sides.

Because of the crane lifting capacity, two separate coffins (an inner and an outer ) will be used.

The inner coffin has 1.5’’ thick walls except from the top cover and the front door (5” thick).

The outer coffin has 3.5” thick walls and is open at the top and the front.

NBI 14-19 March 2002

Horn Changeover (2)

The radioactive horn module will be stored inside the two coffins in the Target Service Building in the old Proton Line.

Four coffins (two inner and two outer coffins) will be needed for a changeover.

A detailed procedure outlining all the steps for a changeover has been written and reviewed.

Total estimated time for a changeover is 2 weeks.

NBI 14-19 March 2002

Inner Coffin

NBI 14-19 March 2002

Outer Coffin

NBI 14-19 March 2002

Initial Configuration

NBI 14-19 March 2002

Inner and Outer Coffins

NBI 14-19 March 2002

Open Inner Coffin Door

NBI 14-19 March 2002

Position the Coffins next to the Horn Module

NBI 14-19 March 2002

Pull the Horn Module in the Coffin

NBI 14-19 March 2002

Close Inner Coffin Door

NBI 14-19 March 2002

Future Plans

We have started disassembling the Power Supply and the Striplines.

The horn modules will be stored in the inner coffin. Plan to install the horn in the target pile on May 7. We estimate to be ready for a horn changeover test on May

15. We should be ready for beam on June 15. We have started ordering the large pieces for a spare horn.