The PSA DISS Test Facility · The DISS Project: experimental results DISS The high...

Post on 30-Sep-2020

2 views 0 download

transcript

DISSThe PSA DISS Test Facility

Actual Configuration of the PSA DISS Test Facility

550 m

Water

(40 - 108 bar)(30 - 100 bar)

Superheated Steam

0º-2º-4º 0º-2º-4º 0º-2º-4º0º-2º-4º 0º-2º-4º 0º-2º-4º 0º to 8º

25 m

0º-2º-4º0º-2º-4º

B.O.P.

Recirculation

50 mInjectionSystem

Special Test Collector (25 m)

1 2 3 4 5 6 7 8 9 10 11

NorthSouth

AA

Solar Collectors

To be implemented in a next phaseTo be implemented in a next phase

DISS

Aerial View of the PSA DISS Test Facility

The PSA DISS Test Facility

Row of collectors

BOP building

DISSThe PSA DISS Test Facility

Technical Characteristics of the PSA DISS Test Facility

No. of parabolic-trough modules 40Module aperture/length: 5.76 m /12 mNo. of solar collectors 11 Total row length: 550 mInclination of the tracking axis: 0º,2º,4º,6º,8º

Orientation: North-SouthAbsorber pipe inner/outer diameter: 50/70 mmMass flow per row (once-through

configuration) 1 kg/s

Max. recirculation rate: 4Max. outlet steam temperat./pressure: 400ºC/100 bar

DISSThe DISS Project: experimental results

➟ The high pressure/temperature ball joints are performing very well. No problem has been found so far.

➟ The circunferential temperature gradient at the absorber pipes of the boiling section is less than 20ºC for I= 950W/m2 and a flow of 0,8 kg/s, while the temperature gradient at the steam

superheated section is of about 40ºC for a steam flow of 0,5 kg/s (see Results I and II)

➟ The pressure drops at both the boiling and the steam superheating sections in the solar field are much smaller than theoretically predicted by simulation models.

➟ The water recirculation pump has repeatedly failed at high pressures (>60 bar). After one year, the pump manufacturer (National Oil Well) is still trying to solve the problem.

➟ The test facility has been operated for more than 1000 hours. Saturated steam at 100bar and superheated steam at 60bar/375ºC have been produced in Recirculation mode.

➟ The steam pressure at the solar field outlet is rather stable, even with great solar radiation transients (see Results III and IV for 30 and 60 bar)

➟ The new local control unit developed by CIEMAT for sun tracking is performing very well

DISSThe DISS Project: experimental results (I)

09:30 10:00 10:30 11:00 11:30 12:00 12:30 13:00 13:30 14:00 14:30 15:00 15:300

20406080

100120140160180200

Maximum ∆T allowed

Temperature gradients BOILING SECTION (Collector 5) ∆T SOLDERED Thermocouples (TEMI118D) ∆T NOT SOLDERED Thermocouples (TEMI119D)

∆Tem

pera

ture

(ºC

)

Local time

09:30 10:00 10:30 11:00 11:30 12:00 12:30 13:00 13:30 14:00 14:30 15:00 15:300

100200300400500600700800900

10001100

Date: 8th June 2000

Direct solar radiation

Sola

r Rad

iatio

n (W

/m2 )

Local time

03691215182124273033

Outlet pressure

Pressure (bar)

0.00.20.40.60.81.01.21.41.61.82.0

Inlet water flow

Flow (kg/s)

DISSThe DISS Project: experimental results (I)

09:30 10:00 10:30 11:00 11:30 12:00 12:30 13:00 13:30 14:00 14:30 15:00 15:300

20

40

60

80

100

120Changes of valves to put collectors10&11 as Superheating Section

Mixture of water&steam

Maximum ∆T allowed

Temperature gradients SUPERHEATING SECTION (Collector 11) ∆T SOLDERED Thermocouples (TEMI142D) ∆T NOT SOLDERED Thermocouples (TEMI143D)

∆Tem

pera

ture

(ºC

)

Local time

09:30 10:00 10:30 11:00 11:30 12:00 12:30 13:00 13:30 14:00 14:30 15:00 15:300

100200300400500600700800900

10001100

Date: 8th June 2000

Direct solar radiation

Sola

r Rad

iatio

n (W

/m2 )

Local time

03691215182124273033

Outlet pressure

Pressure (bar)

0.0

0.3

0.6

0.9

1.2

1.5

1.8 Outlet steam flow

Flow (kg/s)

DISSThe DISS Project: experimental results (III)

10:30 11:00 11:30 12:00 12:30 13:00 13:30 14:00 14:30 15:00 15:30048

1216202428323640

Outlet pressure

Pres

sure

(bar

)

Local time

0.00.10.20.30.40.50.60.70.80.91.0

Outlet steam flow

Flow (kg/s)

10:30 11:00 11:30 12:00 12:30 13:00 13:30 14:00 14:30 15:00 15:300

100200300400500600700800900

1000Date: 1st June 2000

Direct solar radiationSo

lar R

adia

tion

(W/m

2 )

Local time

DISSThe DISS Project: experimental results (IV)

10:30 11:00 11:30 12:00 12:30 13:00 13:300

10

20

30

40

50

60

70

80 Outlet pressure

Pres

sure

(bar

)

Local time

0.0

0.2

0.4

0.6

0.8

1.0

1.2

1.4

1.6

Mixture of water and steam

Change of valves to put collectors10 & 11 as Superheating Section

Outlet steam flow

Flow (kg/s)

10:30 11:00 11:30 12:00 12:30 13:00 13:300

100200300400500600700800900

10001100

Date: 9th June 2000

Direct solar radiation

Sola

r Rad

iatio

n (W

/m2 )

Local time

DISSDISS test facility: water recirculation pump

detail of a damaged plunger damaged graphite sealings

DISSThe PSA DISS Test Facility

Ball-joints installed at the DISS collectors

South end pylon

Absorber pipe

North end pylon

Absorber pipe

Mirrors

Mirrors