Post on 28-Aug-2018
transcript
Transportation Concept Report
State Route 191 District 3
Date: June 2017
Disclaimer: The information and data contained in this document are for planning purposes only and should not be relied upon for final design of any project. Any information in this Transportation Concept Report (TCR) is subject to modification as conditions change and new information is obtained. Although planning information is dynamic and continually changing, the District 3 Office of System Planning Analysis, Modeling and Forecasting makes every effort to ensure the accuracy and timeliness of the information contained in the TCR. The information in the TCR does not constitute a standard, specification, or regulation, nor is it intended to address design policies and procedures.
California Department of Transportation Provide a safe, sustainable, integrated and efficient transportation system to
enhance California’s economy and livability
Marlon Flournoy Date Ray Zhang Date
District 3 Deputy Director Acting District 3 Director Planning and Local Assistance
Approvals:
STATE ROUTE 191 transportation concept report
Page 3
TABLE OF CONTENTS
About the Transportation Concept Report ............................................................................... 4
TCR Purpose………………………………………………………………………………………………………………………….5
Stakeholder Participation .......................................................................................................... 5
State and Local Responsibility .................................................................................................. 5
Strategic Management and Performance……………………………………………………………………………..5
State Route 191 Corridor Summary .......................................................................................... 6
State Route 191 Segmentation Map ......................................................................................... 7
Key Corridor Issues .................................................................................................................... 8
Economic Drivers and Traffic Generators .................................................................................. 8
System Characteristics, Concept Facility and Corridor Performance……………………………………10
State Route 191 Segment ........................................................................................................ 12
State Route 191 Segment 1 Summary………………………………………………………………………………….13
State Route 191 Segment 2 Summary…………………………………………………………………………………14
CALTRANS district 3
Page 4
ABOUT THE TRANSPORTATION CONCEPT REPORT
System Planning is the long-range transportation planning process for the California Department of Transportation (Caltrans). The System Planning process fulfills Caltrans’ statutory responsibility as owner/operator of the State Highway System (SHS) (Gov. Code §65086) by evaluating conditions and proposing enhancements to the SHS. Through System Planning, Caltrans focuses on developing an integrated multimodal transportation system that meets Caltrans’ goals of safety, mobility, delivery, stewardship, and service.
The System Planning process is primarily composed of four parts: the District System Management and Development Plan (DSMDP), the Transportation Concept Report (TCR), the Corridor System Management Plan (CSMP), and the DSMDP Project List. The district-wide DSMDP is a strategic policy and planning document that focuses on maintaining, operating, managing, and developing the transportation system. The TCR is a planning document that identifies the existing and future route conditions as well as future needs for each route on the SHS. The CSMP is a complex, multi-functional, multi-jurisdictional planning document that identifies future needs within corridors experiencing or expected to experience high levels of congestion. The CSMP serves as a TCR for segments covered by the CSMP. The District System Management Plan (DSMP) Project List is a list of partially programmed, planned and conceptual transportation projects used to recommend projects for funding.
District 3 System Planning continues its efforts to streamline and expedite short-range to long-range project needs by creating focused documents such as:
The District 3 State Highway Bicycle Facility Plan (SHBFP) is a comprehensive plan that identifies a vision and framework for bicycle facility improvements on the SHS in District 3. It provides information regarding bicycling on the SHS along with recommended changes to improve connectivity and convenience.
The Intelligent Transportation Systems and Operations Plan (ITS/Ops Plan) provides critical guidance to optimize the State Highway System within the District by identifying and managing ITS and other operational strategies that yield a high return on investment. The ITS/Ops Plan identifies an inventory of prioritized projects and a process for continuously updating the inventory.
The District 3 Goods Movement Study is a district-wide gap analysis of the district goods movement network, proposing methodologies to identify and prioritize freight projects. Findings and recommendations from this study will inform local, regional, and statewide planning efforts.
District 3 Complete Streets Plan assesses existing conditions and opportunities to identify, and implement complete streets enhancements to be included in transportation improvement projects on the SHS corridors.
These System Planning products are also intended as resources for stakeholders, regional, local and partner agencies, and the public. This TCR includes projects identified in the previously discussed focused documents. For more information and to access all System Planning products, please visit:
http://www.dot.ca.gov/dist3/departments/planning/systemplanning.htm.
STATE ROUTE 191 transportation concept report
Page 5
TCR PURPOSE
California’s State Highway System needs long range planning documents to guide the logical development of transportation systems as required by CA Gov. Code §65086 and as necessitated by the public, stakeholders, and system users. The purpose of the TCR is to evaluate current and projected conditions along the route and communicate the vision for the development of each route in each Caltrans District during a 20-year planning horizon. The TCR is developed with the goals of increasing safety, improving mobility, providing excellent stewardship, and meeting community and environmental needs along the corridor through integrated management of the transportation network, including the highway, transit, pedestrian, bicycle, freight, operational improvements and travel demand management components of the corridor.
STAKEHOLDER PARTICIPATION
Stakeholder participation was sought throughout the development of the TCR for State Route 191. Outreach efforts involved internal and external stakeholders, and regional and local agencies. During the initial information resource gathering for the TCR, stakeholders were contacted for initial input related to their particular specializations, and to verify data sources used and data accuracy. As the document was finalized, stakeholders were asked to review the document for comments, edits, and for consistency with the intent of existing plans, policies, and procedures. Written comments were received and incorporated into the final document. The process of including and working closely with stakeholders adds value to the TCR, allows for outside input, provides an opportunity for ideas to be reflected in the document, increases credibility, and helps strengthen public support and trust.
STATE AND LOCAL RESPONSIBILITY
Improvements to the SHS are the responsibility of both Caltrans and local agencies. Developments that add cumulative impacts to this route and the regional SHS may necessitate that local jurisdictions provide nexus based, proportional fair-share funding for future multi-modal transportation improvements. Developments or local circulation changes that will have significant traffic impacts to the mobility should provide improvements to mitigate those impacts.
STRATEGIC MANAGEMENT AND PERFORMANCE
The Department’s Strategic Management Plan is the road map of Caltrans’ role, expectations, and activities; and includes performance measures to bring about transparency, accountability, sustainability, and innovation. The Plan highlights the Department goals which are: Safety and Health, Stewardship and Efficiency, Sustainability, Livability and Economy, System Performance, and Organizational Excellence.
CALTRANS district 3
Page 6
STATE ROUTE 191 CORRIDOR SUMMARY
State Route (SR) 191, also called “Clark Road,” is a south to north undivided 2-lane highway in Butte County.
SR 191 is 11.39 miles in length, and connects SR 70 (PM 0.0) to its northern terminus at the Pearson Road
intersection in the Town of Paradise, where it then becomes a local road (PM 11.39). The route is divided
into two segments: Segment 1, which is from SR 70 to the Town of Paradise city limits (PM 9.49), and
Segment 2, which is from the Town of Paradise city limits to the Pearson Road intersection. According to
Federal Highway Administration (FHWA) approved California Road System (CRS) maps, Segment 1 is a rural
minor arterial, while Segment 2 is an urban principal arterial. SR 191 is the main road Paradise and Magalia
residents depend on to access to the City of Oroville to the south, as well as the Cities of Marysville, Yuba
City, and Sacramento.
SR 191 is the urban principal arterial that serves the Towns of Paradise and Magalia. The Town of Paradise is
approximately 12 miles east of the City of Chico and 80 miles north of Sacramento. The Town of Paradise is
currently developing a “Southeast Paradise Specific Plan,” which proposes approximately 200 new homes and
some commercial development between SR 191 and Durham-Pentz Road, which may affect circulation patterns
and highway performance.
District 3 has established concept level of service (LOS) standards for the State Highway System within district
boundaries - LOS D for route segments in rural areas and LOS E for route segments in urban areas. SR 191 will
meet these thresholds over the next 20 years based on currently adopted plans. If new plans allowing growth
and development are adopted that propose more development near the route, such as the “Southeast
Paradise Specific Plan,” then forecasted performance data will need to be reevaluated.
SR 191 is primarily used for local trips within the Town of Paradise and regional trips, rather than for
interregional travel. SR 191 is considered by Caltrans as a route eligible for relinquishment to the local
agencies it passes through. There currently is no discussion to relinquish SR 191 to the Town of Paradise and
the County of Butte, but the option remains available to these agencies to acquire SR 191 if they wish to own,
operate, and maintain the route at some point in the future.
CALTRANS district 3
Page 8
KEY CORRIDOR ISSUES
There is currently no formal bicycle facility classification on SR 191, and bicyclists are permitted to use it.
Shoulder widths are generally sufficient for bicyclists; however, in the mountainous portions of SR 191
there is limited right of way, and shoulders are narrow or they are non-existent, which requires bicyclists
and vehicles to share the road. A Class II bike lane on SR 191 is planned between Durham Pentz Rd. and
SR 70.
Incomplete sidewalks are common in downtown Paradise, which will be addressed when the SR 191
widening project is implemented.
Economic Drivers and Traffic Generators
Transit options exist for travelers between Paradise and Oroville on Route 191, operated by Butte
Regional Transit. The route provides a morning and an evening trip for commuters from Paradise to
Oroville and back.
There are limited rail options in the region. The only operational rail line is the Coast Starlight, operated
by Amtrak, which travels through the City of Chico.
Nearby airports include the Paradise Skypark Airport, Chico Municipal Airport to the west, and Oroville Municipal Airport to the south.
CALTRANS district 3
Page 10
SYSTEM CHARACTERISTICS, CONCEPT FACILITY, AND CORRIDOR PERFORMANCE
Notes/Definitions
Level of Service (LOS) - A measure of traffic density conditions, with “A” representing the least amount of density and “F” the most congested conditions. For the above peak hour LOS, A and B are not needed to provide good conditions.
LOS A – Free Flowing Conditions. LOS B – Speeds at or near free-flow speed, but presence of other users begins to be noticeable. LOS C – Speeds at or near free-flow speed, but freedom to maneuver is noticeably restricted. LOS D – Speeds begin to decline slightly with increasing flow; freedom to maneuver is more restricted. LOS E – Operating conditions at or near roadway capacity. Even minor disruptions to the traffic stream can cause delay. LOS F – Breakdown in vehicle flow. Queues form quickly behind point in the roadway where the arrival flow rate temporarily exceeds the departure rate.
Seg-men
t County
Existing Facility (BY)* Concept Facility- Build Facility (HY)*
Post Miles (Begin/End)
Facility Type
General Purpose
Lanes
Lane Miles
Centerline Miles
Designated Lane
Facility Type
General Purpose
Lanes
Lane Miles
Centerline Miles
Designated
1 BUT
0.0/10.08 C 2 20.16 10.08 - C 2 20.16 10.08
2 10.08/11.386 C 2 2.612 1.306 - C 2 2.612 1.306
PEAK HOUR TRAFFIC DATA
Seg-men
t County
Post Miles (Begin/End)
Volume Directional Split Volume/Capacity (V/C)
BY No Build
(HY) Build (HY)
BY No Build (HY) Build (HY)
BY No Build
(HY) Build (HY)
1
BUT
0.0/10.08 650 1138 1138 60% 60% 60% 0.26 0.45 0.45
2 10.08/11.386 920 1242 1242 58% 58% 58% 0.36 0.48 0.48
STATE ROUTE 191 transportation concept report
Page 11
Facility Type Codes; C = Conventional Highway; E = Expressway; F = Freeway; HOV = High Occupancy Vehicle lanes; Aux = Auxiliary lanes.
Concept Facility -The future roadway with improvements needed in the next 20 years. If LOS “F”, no further degradation of service from existing “F” is acceptable, as indicated by delay performance measurement.
20-Year LOS (No Build) - The LOS that would be expected at 20 years with no improvements.
20-Year Concept LOS - The minimum acceptable LOS over the next 20 years.
Ultimate Facility - The future roadway with improvements needed beyond a 20 year timeframe.
Average Annual Daily Traffic (AADT) -The average number of vehicles per day in both directions.
Peak Directional Split -The percentage of total traffic in the heaviest traveled direction during the peak hour.
Volume over Capacity (V/C ) - The volume of traffic in the Peak Hour compared to the capacity of the roadway.
Vehicle Miles Travel (VMT) - VMT is a report that estimates the number of vehicle miles that motorists traveled on California State Highways.
Build Facility (HY)* Concept Facility Ultimate
Facility- (HY)* Average Daily Traffic (ADT) Level of Service (LOS)
Vehicle Miles Traveled (VMT)
Centerline Designated Lane
General Purpose Lane/Facility Type (project to achieve LOS-
ultimate concept)
Base Year (BY)
No Build Horizon
Year
Build (HY)
BY No Build
(HY) Build (HY)
Ultimate Concept
BY No Build
(HY) Build (HY)
- 2C 6,100 10,675 10,675 D E E D 57,213 100,122 100,122
- 2C 9,500 12,825 12,825 E E E D 8,522 11,505 11,505
TRUCK TRAFFIC DATA
VMT
Build (HY) BY No Build (HY) Build (HY)
Average Annual Daily Truck Traffic
(AADTT) (BY)
Total Trucks (% of
AADT) (BY)
5+ Axle AADTT
(BY)
5+ Axle Total
Truck (% of AADT)
(BY)
6,470 11,323 11,323 423 4.50% 103 1.10%
813 1,098 1,098 423 4.50% 103 1.10%
CALTRANS district 3
Page 12
STATE ROUTE 191 SEGMENT
The following pages includes a map and summary of State Route 191 segment.
Segment summaries provide a segment overview including route designations, traffic analysis data, existing Transportation Management System (TMS) elements, bicycle and pedestrian access, and freight and airport facilities. Information that covers more than three segments is described in the corridor summary. Needed improvement projects for each segment is also discussed and listed in one of three categories—Planned, Programmed, or Conceptual.
A Conceptual improvement or action is a project that is needed to maintain mobility or serve multimodal
users, but is not currently included in a fiscally constrained plan and is not currently programmed.
Conceptual projects are all fiscally unconstrained projects derived from documents such as local and
regional General Plans, and Caltrans System Planning Documents.
A Planned improvement or action is a project in a long-term fiscally constrained plan such as an approved Regional Transportation or Metropolitan Transportation Plan (RTP or MTP), Capital Improvement Plan, or measure.
A Programmed improvement or action is a project listed in a near-term programming document identifying funding amounts by year, such as the State Transportation Improvement Program (STIP) or the State Highway Operations and Protection Program (SHOPP).
The segment map will provide information on the segment location and locations of improvement projects (planned, programmed, and conceptual). The called-out project identification numbers corresponds to the Project Table under the Segment Summary Information section.
STATE ROUTE 191 transportation concept report
Page 13
Segment 1 (P.M. 0.00/10.08) begins at SR 191/SR70 intersection to Easy Street. It is a 2-lane rural minor arterial, with no plans for expansion. The segment serves Butte College, the region’s community college, and Paradise Skypark Airport, a private airport popular for skydiving.
This segment is currently operating at LOS D, and projected to decline to LOS E by 2035.
The project listed below on Table 2 is currently in construction. Once completed, this project will improve traffic operations for motorists. It will update the roadway to current standards by increasing the curve radii, widening the shoulders to 8 feet, and improve the vertical profile grade. Additionally, the project will improve the clear recovery zone by removing obstacles and flattening slopes close to the travelled way.
State Route 191 Segment 1 Summary
TABLE 1: SR 191 SEGMENT 1 ROUTE DESIGNATIONS AND CHARACTERISTICS
Freeway & Expressway
National Highway System
Strategic Highway Network
Scenic Highway
Interregional Road System
High Emphasis
Focus Route
Federal Functional
Classification
Highway Freight
Network
Truck Designation
Bicycle and Pedestrian Access
N0 Yes No No No No No Major Arterial No Terminal Access
Highway open-shoulder varies
Segment 1 Map (P.M. 0.00/10.08) SR
191/ SR 70 intersection to Easy Street
TABLE 2: SR 191 SEGMENT 1 Projects
Project #
Strategies (Description) PM Location Lead Agen-
cy Source*
Objective (Purpose)
Total Cost Estimate* (x
$1,000)
Proposed Completion
Year*
Project Cate-gory
1 Realign curves and widen shoulders
BUT 191, 6.8/8.6
Near Paradise from 1.9 miles north of Clear Creek Bridge to Airport Road.
CT 2015 10-year
SHOPP System Man-
agement $30,200 2018 Programmed
CALTRANS district 3
Page 14
State Route 191 Segment 2 Summary
Segment 2 (P.M. 9.49/11.39) begins at the Town of Paradise city limits, where it becomes an urban principal arterial.
This segment operates at LOS E, and projected to remain LOS E by 2035.
There are planned or programmed projects along this segment.
TABLE 3: SR 191 SEGMENT 2 ROUTE DESIGNATIONS AND CHARACTERISTICS
Freeway & Expressway
National Highway System
Strategic Highway Network
Scenic Highway
Interregional Road System
High Emphasis
Focus Route
Federal Functional
Classification
Highway Freight
Network
Truck Designation
Bicycle and Pedestrian Access
N0 Yes No No No No No Major Arterial No Terminal Access
Highway open-shoulder varies
Segment 2 Map (PM 10.08/11.386) Easy Street to Para-
dise Pearson Road
TABLE 4: SR 191 SEGMENT 2 Projects
Project #
Strategies (Description) PM Location Lead Agen-
cy Source*
Objective (Purpose)
Total Cost Estimate* (x
$1,000)
Proposed Completion
Year*
Project Cate-gory
3 Construct Class II Bike Lane
BUT 191, 9.49/11.39
SR 191 in Paradise Town limits to Pearson Rd.
CT 2011 SHBFP Complete
Streets $960 2035 Conceptual
4 Intersection modification BUT 191,
11.14/11.14 SR 191 in Paradise at Buschmann Rd.
CT BCAG 2012 MTP/SCS
System Man-agement
$2,000 2035 Conceptual
DISTRICT 3
California Department of Transportation
For questions and concerns about this Transportation Concept Report, please contact:
Caltrans District 3 Division of Planning and Local Assistance Office of System Planning Analysis, Modeling and Forecasting Branch 703 B Street, Marysville, CA 95901 Email: susan.zanchi@dot.ca.gov
Phone: (530) 741-4199For further Transportation Concept Report information, please visit:
Caltrans District 3 Website:
http://www.dot.ca.gov/dist3/departments/planning
(Select System Planning, then Transportation Concept Reports)