Nuclear Generation Development and Construction
TVA’s Integrated Project Delivery for Nuclear Projects
The Challenges of Transitioning to Long Term Major Nuclear Plant Construction
Mark J. Hellstern, CAPT USN (ret)General Manager, NGDC Oversight
Nuclear Generation Development and Construction
TVA’s Integrated Project DeliveryNuclear Generation Development and
Construction (NGDC) Genesis and Development
• Late 2007: Established NGDC and a small oversight group• April 2009 Self-Assessment: need for a project process
standardization, formal governance and oversight, risk management, and process improvement.
• Late Summer 2009: INPO cited a strength in the designation of NGDC to provide major construction activity separate from Nuclear Power Group Operations
• November 2009: TVA stands up a Project Management Peer Team to standardize Fleet project management.
• FY 2010/11: NGDC Project Manual implementation, Project management software integration, key performance indicator development, and piloting initiatives
Nuclear Generation Development and Construction
• Five year project• Budget of $2.5 Billion• Current staffing – 2,623• Licensing process on schedule
Watts Bar Unit 2 - 2012
NGDC Projects
Nuclear Generation Development and Construction
• S-COLA for AP1000 • Construction permits reinstated• Preservation of assets
Bellefonte Current Status
NGDC Projects
Nuclear Generation Development and Construction
NGDC Strategic Projects
• Several Strategic Outage Projects to include:– Watts Bar Re-rack– Sequoyah Steam Generator replacement– Browns Ferry Extended Power Uprate (EPU)– License renewal– Modular Reactors, etc.
Nuclear Generation Development and Construction
Integrated Project Team Manual
• Standardization of TVA’s project processes incorporating benchmarking of industry best practices. 42 processes.
• Benchmarked NASA, U.S. Navy, CURT, CII, APQC, state DOTs, and other utilities
• Incorporates regulatory, environmental, TVA, and business unit policies, procedures, and processes
• Stresses team building, process improvement, self-assessment, integration, and accountability
• Signed out in April 2010. Being piloted on Bellefonte and Watt’s Bar rerack projects.
Nuclear Generation Development and Construction
Safety & Environment
People
Performance Improvement
Work ManagementWork Management
Project Management
Project Management
Nuclear Generation Development and Construction
NGDC Oversight
• Standard Governance and Oversight procedures• Blocking and Tackling:
• Robust, intrusive Quality Assurance Oversight• Project Assurance (cost, schedule, scope) assessments
based on INPO assessment process: data analysis, observations, interviews
• Knowledge/Risk Mgt with project approval process tied to risk plans. Business Planning.
• Implement Knowledge Capture process with push/pull of knowledge for present and future projects
Nuclear Generation Development and Construction
NGDC Project Management Integration FY 10 Initiatives
• Pilot of the Project Manual on Bellefonte/Watt’s Bar Rerack projects.• Successful implementation of behavior-based NGDC safety programs• Incorporating Primavera 6 in Bellefonte as a pilot for a Fleet solution.• Implement a mature Risk and Opportunity Management• Key Performance Indicators, which roll-up for senior management into
INPO’s nine principles of construction excellence.• Approving a pilot for a wireless site at Bellefonte with electronic
configuration management and work flow tools• Approval for a Fleet Knowledge Management System
Nuclear Generation Development and Construction
eFMSProject Portfolio
Powerplant - Fleet
Document Mgmt (BSL)
Work PeopleHRIS
elance
ATIS
Collaboration Tools (Sharepoint/Outlook)
ConfigurationMgt
Maximo
RiskMgt
System SchedulePrimavera 6
EstimatingSystem
Fleet Solution
eWorkplace
PerformanceKPIs/Dashboards
Knowledge
Mgt System
Fleet Solution
ContractsCompliance
Compliance
Project Management Integration System (PMIS)
Cost Processor/EVMS
Project Management
Conceptual Design
Nuclear Generation Development and Construction
Challenges
• Cultural resistance to change management• Requires consistent Senior Management focus and
support for change implementation and funding• Mature work force• Accurate metrics• Changes required in owner-contractor relationships• Develop a self-critical culture focused on process• Not a self-learning organization … yet• Lack of historic knowledge management
Nuclear Generation Development and Construction
Long Term NGDC Goals
• Standardized TVA Fleet project management processes
• Nuclear construction conducted using BIM and extensive modular construction processes
• Target a 48 mon new nuclear construction schedule
• Target $$/kW overnight cost for new nuclear construction
• Cradle-to-grave electronic configuration management