UC Davis Sacramento Campus Past, Present and Future presentation... · 10/5/2016 1 Mark Romney,...

Post on 14-Jul-2020

0 views 0 download

transcript

10/5/2016

1

Mark Romney, Senior Facilities PlannerJoel Swift, AIA, LEED AP

Facilities Planning & Development

October 08, 2016

UC Davis Sacramento CampusPast, Present and Future

UCD Health System – Sacramento’s Academic Medical Center

10/5/2016

2

The UC Davis Health System includes…

10/5/2016

3

Innovative, Collaborative Research

UC Davis Health Facilities

10/5/2016

4

Recent Projects

UC Davis - the Sacramento Campus

UCD Medical Center -Main Hospital

UCD School of Medicine

UCD Betty Irene Moore School of Nursing

10/5/2016

5

UCD Sacramento Campus - Today

UCD Sacramento Campus - History

10/5/2016

6

Adaptive Reuse of Historic Resources Institute for

Regenerative Cures– State Fair Hall reused

for Biomedical Research

Governor’s Hall– State Fair Hall in

consideration for uses supporting UCDHS and the community

Research Projects

STEM CELL INDUSTRY PARTNER (SCIP)

PODS-1,500-2,340 RSF & INCLUDE:

•PRIVATE TECH/LAB SPACE + ACCESS TO SHARED WET LAB & UNIVERSITY’S CORE LAB SERVICES

•PRIVATE OFFICE, ACCESS TO CONFERENCE, COLLABORATION & GATHERING SPACES

10/5/2016

7

Research Projects

Main Hospital

Former County Hospital

Seismic deficiencies buried in structure

Must vacate by 2020

10/5/2016

8

North-South Wing

1928 & 1950

East Wing1965

University Tower

1982

Davis Tower

1999

Surgery and Emergency Services Pavilion

2010

UCD Medical Center – Main Hospital

2010 Long Range Development Plan

10/5/2016

9

Current Major Capital Projects

ASB RenovationsCompletion: 2016

DemolitionCompletion: 2022

Children’s Surgery Center

Completion: 2018

Other Seismic Projects

Completion: 2018 Betty Irene Moore Hall

Completion: 2017

North AdditionCompletion: 2018

Seismic Phase V

Demolish North-South

New Skin on West side of East Wing

Landscape between Colonial and Stockton Blvd

Start in 2020

10/5/2016

10

North Addition Office Building

North Addition

Office Building

Move-in 2019

North Addition Office Building

10/5/2016

11

Children’s Surgery Center

• 6 Operating Rooms• 1 Special Procedure Room• 24 PACU Beds (12 pre and 12

post)

Future North

Addition Site

East Wing

North South Wing

University Tower

Davis Tower

PavilionPavilion

Children’s Surgery

(existing) Children’s Surgery

(open 2018)

Children’s Surgery Center

10/5/2016

12

ASB School of Nursing Renovations

Betty Irene Moore Hall

10/5/2016

13

Planning Efforts

Potential Projects

Bed TowerReplaces East Wing150-300 Beds

Outpatient ClinicsClinical Departments TBD

10/5/2016

14

Potential Infrastructure Projects

Biomedical Research2010 Plan – 500,000 additional GSFUse of existing historic buildingsOther Initiatives

Health Sciences SchoolsRelocation of functions from Hospital,Future of Medicine & NursingAddition of Public Health and others

Research & Education Zone

10/5/2016

15

Thank you! Joel Swift, AIA, LEED AP

Director of Facilities Planning & Development