AFCEA Industry Day - Installation Information Infrastructure Modernization Program (I3MP)
Information ExchangeMr. Brendan Burke
PdM I3MP3 April 2018
America’s Force of Decisive Action 2
UNCLASSIFIED
UNCLASSIFIED
Encouraging Exchange and Dialogue, Increasing the Value of Partnership
Innovations, Solutions, Lessons Learned and Good Ideas are Welcome
Recap of PdM I3MP FY17 approach since last Industry Day, and update on what we did and did not do on that list
Preview of projected FY19 actions
Purpose & Intent
America’s Force of Decisive Action 3
UNCLASSIFIED
UNCLASSIFIED
Organizational Overview
NETMOD-C Overview
ICS Overview
SCC Overview
HSMCC Overview
Revisit of FY17 Industry Day Objectives
IDIQs selected for each Product Line
Future Potential Opportunities
Questions
Agenda
UNCLASSIFIED//FOUO
UNCLASSIFIED//FOUO UNCLASSIFIED
America’s Force of Decisive Action 5
UNCLASSIFIED
UNCLASSIFIED
Product ManagerMr. Brendan Burke
Deputy Product Manager
Mr. Tom Olson
Assistant Product Manager
Mr. Alberto Dominguez
Assistant Product Manager
Mr. Kevin Chinn
Assistant Product ManagerMs. Toni Freeland
Installation Capability Sets
CONUS
Network Modernization
CONUSCommand Centers
I3MP Product Managers
America’s Force of Decisive Action 6
UNCLASSIFIED
UNCLASSIFIED
I3MP enables the Warfighter through information technology, infrastructure modernization, and lifecycle management of the Army’s CONUS Installation Campus Area (Voice, Video & Data) Networks,and Strategic Command Centers.
I3MP Capability Portfolio Overview
APM CONUSCONUS ICAN Modernization conducts full-scope voice, data, outside plant, and facility modernization projects to enhance delivery of IT services to Army customers.
APM CC
APM NETMOD-C
HSMCC is a suite of standardizedcapabilities utilized at Corps, Division and Theater Headquarters that allows expeditionary mission command during all operational phases.SCC provides core Command, Control, Communications, and Computers (C4) infrastructure for Joint, Coalition and Interagency C4 capabilities at Army and Army supported command centers (SOUTHCOM, AOC, ANMCC & JSOC).
NETMOD-C standardizes US Army Installation network architectures; and collapses more than 30 separate networks into a single Army network, enhancing network security.
18A modernizes premise wiring and supporting infrastructure to provide proper user accessibility and VoIP; modernizes telecommunication rooms to meet industry standards; implements a Wi-Fi solution; providesa more standard, documented and organized IT Infrastructure.
18A / WHCA Modernization
America’s Force of Decisive Action 7
UNCLASSIFIED
UNCLASSIFIED
NETMOD-C Video
Video URL: https://youtu.be/gYip7qqkycQ
America’s Force of Decisive Action 8
UNCLASSIFIED
UNCLASSIFIED
• Bandwidth should no longer be an issue when the Soldier needs new capability
• Upgrade Core Routers to 10Gb/s (capable of supporting 100 Gb/s)• 10 Gb/s across B/P/C/S: DISA router to End User Building (where possible)
• Reduce number of Entry/Exit points to NIPRNET• From 435 points in CONUS to less than 20 Globally• Enable capabilities such as VoIP and other UC Services
• Move to Single Network - Consolidate 30+ Army networks
• Standardize configuration of Army Installation Campus Area Networks
• Improve Content Management
• Move toward a Joint/Regional Network Management Construct
NETMOD-C Objectives
America’s Force of Decisive Action 9
UNCLASSIFIED
UNCLASSIFIED
PEO EIS Program Executive Office Enterprise Information Systems
I3C2 Installation Information Infrastructure Communications & Capabilities
I3MP Installation Information Infrastructure Modernization Program
ISEC US Army Information Systems Engineering CommandCIO-G6 Headquarters Department of Army Chief Information Officer – G6
NETCOM Army Network Enterprise Technology Command
7th SC (T) 7th Signal Command (Theater)
93rd SB 93rd Signal Brigade
106th SB 106th Signal Brigade
CECOM Communications-Electronics Command
ACC-RI Army Contracting Center – Rock Island
DLA Defense Logistics Agency
DISA Defense Information Systems Agency
Partnerships and Stakeholders
America’s Force of Decisive Action 10
UNCLASSIFIED
UNCLASSIFIED
Implementation Strategy - Generic B/P/C/S
• Install timeline driven by:• # of EAS install teams• ASI approvals/building access
• Plan based on six (6) EAS install teams of two (2) personnel (~48 switches/night)
• Implementation plan validated at the JBSA Pilot location
Pre Coordination & Logical Survey
Physical Site Survey
EAS Switch Config & Installs
ACS / ADS Config & Installs EIP & Coordination
• Installation estimated at ~ 2 to 4 months• Highest requirement for manpower
Closeout & SAT
Shipping multi shipments as required
Repurposing
2 Months 3 Weeks 2 Months 1 - 2 Months
1-2 Weeks
2 - 4 Weeks
2 Weeks to TBD
1- 4 Months
PRE-INSTALLATION PHASE INSTALLATION PHASE
Facility Power Upgrades (TYAD)
PdM I3MP is Supported Organization 7th SC(T) is Supported Organization
ROC Drill
KICK-OFFMEETING
Implementation Strategy: Generic B/P/C/S
America’s Force of Decisive Action 11
UNCLASSIFIED
UNCLASSIFIED
ICS-MOD Video
Video URL: https://youtu.be/9ORtu1P3ATo
America’s Force of Decisive Action 12
UNCLASSIFIED
UNCLASSIFIED
OSP Defined: Connection via fiber optic cables to provide user/network connectivity between all required locations on b/p/c/s in support of tenant mission requirements and user needs.
OSP Connection Points: From Core/Area Nodes to End User Buildings (EUBs), and EUBs to other EUBs.
OSP Activities: I3MP OSP includes all typical commercial installations, including trenching, boring, direct buried cable, splicing, installation of maintenance and hand holes, installation of conduits and fiber optic cable.
Outside Plant (OSP) Capability
America’s Force of Decisive Action 13
UNCLASSIFIED
UNCLASSIFIED
Site Preparation: Physical environmental conditions (e.g., HVAC, humidity, structure) and the supporting and sustaining facilities systems (e.g., power, grounding, UPS, generators) for IT equipment.
Typical Prefabricated Communications Shelter, 400 to 1,200 square feet, includes the following features:
Site Preparation/Facilities Capability
America’s Force of Decisive Action 14
UNCLASSIFIED
UNCLASSIFIED
TDM Decommission-VoIP Infrastructure: TDM Decommission encompass the complete replacement of Army Installations Analog Telephone system and the integration of DISA’s AS-SIP Trunk for DSN and PSTN. Refers to LSCs or ESCs, Voice Gateways, End User Licenses, telephone instruments, power and cabling to provide voice telephony services.1. Session Controllers (CISCO CUCM, AVAYA CM6,
GENBAND or AVAYA 5300, others)
2. Voice Gateways converting legacy TDM to VOIP
3. Ancillary voice equipment - SBCs, Power, TMS, cabling.
Voice Terminology: Voice engineering refers to the cabling and equipment infrastructure installed within a communications facility to support voice communication. Typical voice communications facilities include Dial Central Offices (DCOs), Remote Switching Centers, main telecommunications rooms within buildings, as well as stand alone communications shelters or “huts” for remote switching units or voice gateways. In current Army locations it is a mixture of VOIP and legacy TDM.
TDM Decommission-DISA AS-SIP Trunk
Local Session Controllers
DISA VSIP Services
Legacy (TDM) Equipment
America’s Force of Decisive Action 15
UNCLASSIFIED
UNCLASSIFIED
CC-MOD Video
Video URL: https://youtu.be/gYip7qqkycQ
America’s Force of Decisive Action 16
UNCLASSIFIED
UNCLASSIFIED
Strategic Command CentersHome Station Mission Command Centers
APM Command Centers
America’s Force of Decisive Action 17
UNCLASSIFIED
UNCLASSIFIED
Depicts only Command Centers where Army is the Executive Agent with Automated Data Processing Equipment (ADPE) funding.
ANMCC-R:Joint Staff, J3 and 114th SIG BN
SOUTHCOM:J6, Office of the CIO and 525th SIG
CO
Joint Special Operations Command
J-6
Army Operation Center-Pentagon
G-3/5/7 and ITA
Army Strategic Command Centers
America’s Force of Decisive Action 18
UNCLASSIFIED
UNCLASSIFIED
HSMCC Sites
HSMCC Sites• 4th ID, Fort Carson, CO• 25th ID, Schofield Bks, HI• 1st ID, Fort Riley, KS• 3rd ID, Fort Stewart, GA• I Corps, JBLM, WA• 28th ID (ARNG), Harrisburg, PA• 38th ID ( ARNG) Indianapolis, IN• 7th ID, JBLM, WA• 34th ID (ARNG) St. Paul, MN• 40th ID ( ARNG) Los Alamitos, CA• 35th ID (ARNG), Fort Leavenworth, KS• 42nd ID ( ARNG) Troy, NY• 10th MTN, Fort Drum, NY• XVIII ABN, Fort Bragg, NC• 1st AD, Fort Bliss, TX• 2nd ID (Korea), Camp Humphries, ROK• 20th CBRNE, APG, MD• 36th ID (ARNG) Austin, TX• 32nd AAMDC, Fort Bliss, TX• 82nd ABN, Fort Bragg, NC• III Corps, Fort Hood, TX• 101st ABN Fort Campbell, KY• 1st CAV, Fort Hood, TX• 29th ID (ARNG), Fort Belvoir, VA• USARAF (Italy), Vicenza, Italy• 8th Army (Korea), Camp Humphries, ROK
America’s Force of Decisive Action 19
UNCLASSIFIED
UNCLASSIFIED
• Vision:• This Industry Day presents an opportunity for I3MP to provide a
transparent open discussion of current contract support requirements and future opportunities that are planned for the near future
• Notional information is provided for long term opportunities for general planning purposes
• Overall IDIQ Contract Methodology:
• Selection of an existing IDIQ vehicle with sufficient scope, flexibility, ceiling and period of performance to meet the entire procurement activity
• Tasks will be developed within the singular identified IDIQ, and structured to meet specific requirements within the program
Intent was that we could rapidly execute single smaller task orders for each site.
PdM I3MP FY17 Industry Day Vision
America’s Force of Decisive Action 20
UNCLASSIFIED
UNCLASSIFIED
IDIQ selection• NETMOD-C
• N/A
• OSP• Connections 2
• TDM/VOIP • Connections 2
• SCC• TBD
• HSMCC• GSA Alliant - LB
Lessons learned:We have not been able to rapidly execute single tasks orders,
and are moving to a more Capability Set Based approach using the above IDIQs
America’s Force of Decisive Action 21
UNCLASSIFIED
UNCLASSIFIED
FY17-18….. What We Did/Didn’t Do
Potential Project at FY17 Industry Day FY18 actions Contract vehicle Status
Ft Gordon - OSP Ft Gordon: OSP Directed ANC AwardedYuma Proving Ground - OSP Deferred – FY19Pine Bluff Arsenal - OSP deferredSunny Point Military - OSP deferredOcean Terminal - OSP deferred
McAlester AAP -OSP deferred
Corpus Christi Army Depot - OSP deferred
Soto Cano OSP ANC Awaiting approval from SBA
Ft Hood - VOIP Ft Hood: TDM DCOM Connections II RFP released 16 Feb 18
JBLM - VOIP JBLM: TDM DCOM Connections II RFP planned released 10 May 18
Fort Bliss Garrison - VOIP Awarded in FY17, option exercised in FY18 CTS Awarded
Fort Sill -VOIP Deferred – FY19Joint Base San Antonio - VOIP deferredFort Bragg - VOIP deferredFort Benning-VOIP deferredAOC – SCC AOC- SCC NAVAIRJSOC – SCC JSOC-SCC TAO/ CHESS Buy
HSMCC – 14 sites over 3 years HSMCC 9 sites over 3 years GSA Alliant - LB In source selection, Award soon
FY 20 or beyond
FY 20 or beyond
America’s Force of Decisive Action 22
UNCLASSIFIED
UNCLASSIFIED
Current/Future Requirements• SETA/PMO support
• Enterprise Information Technology Services (EITS) is the contract vehicle being utilized in support of I3MP, I3C2 selected key staff, and is supporting the start up of Defensive Cyber Operations.
• POP Base Year is May 2016 – May 2017 and 2 one-year options (with 6 month additional option)
• Completion of all option periods (May 2019 or Nov 2019)• Planned to be part of consolidated DCATS contract
• NETMOD-C• SEI replacement contract required to start NETMOD-C sites in FY19
• Plan to include SIPR and NIPR upgrades• Awaiting SIPR architecture approval• Awaiting decision on what next round of NETMOD-C will entail• Plan to utilize similar construct to current contract• Will be competed, which contact vehicle is still TBD
• Hardware Contracts• World Wide Buy 3 expires 21 Jun 2019• Routers order expires 15 Mar 2020• Any unplanned actions will likely be accomplished via Reverse Auction
America’s Force of Decisive Action 23
UNCLASSIFIED
UNCLASSIFIED
Current/Future Requirements• OSP Capability Set
• Capability set structure similar to P2E efforts• Base award likely Yuma Providing Grounds• Three year, multiple sites• Planned to compete on Connections 2
• TDM Capability Set• Capability set structure similar to P2E efforts• Base award planned for Ft Riley• Three year, multiple sites• Planned to compete on Connections 2
• SCC Capability Set• Capability set structure similar to P2E efforts• Base award likely• Three year, multiple sites• Base Contract to be used still TBD
• HSMCC• No additional procurements planned
America’s Force of Decisive Action 24
UNCLASSIFIED
UNCLASSIFIED
Notional OSP Projects by Year
FY19 FY20
*Yuma PG, AZ Letterkenny AD, PA
Ft McCoy, WI Presidio of Monterey, CA
Ft Bliss, TX (Ph 1 of 2) Fort Irwin / NTC, CAUS Army Combat Spt Tng Ctr & Camp Parks, CA SDDC, Charleston, SC
Soldier's System Center, MA SDDC, Jacksonville, FL
Camp Merrill, GA Ft Polk, LA
* Base award site
America’s Force of Decisive Action 25
UNCLASSIFIED
UNCLASSIFIED
Notional TDM DECOM Projects by Year
FY19 FY20Ft Gordon, GA Ft Benning, GA
*Ft Riley, KS Aberdeen Proving Ground, MD
Ft Sill, OK Holston AAP, TN
Ft Stewart, GA Ft Jackson, SC
Yuma PG, AZ Redstone Arsenal, AL
Camp Merrill, GA
* Base award site
America’s Force of Decisive Action 26
UNCLASSIFIED
UNCLASSIFIED
Thoughts for Industry• Role of OEM and Prime Contractor
• Know the difference, and appreciate the roles
• Remember I3MP goal is to deliver capability• Good enough now probably is better than a perfect later• But don’t let us do stupid
• Feedback on RFI• Getting a little better, but still post award/RFP release seems to be a large
uptick in information that would have been helpful during RFI
• Honest timeline assessments for RFPs• Reverse Auctions
• Pros and Cons
America’s Force of Decisive Action 27
UNCLASSIFIED
UNCLASSIFIED
Questions