PHILIPPINERURALDEVELOPMENTPROJECT
EnterpriseDevelopment
Component
(I-REAP)
August2016
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
i
Contents
1Introduction.............................................................................................................................1
1.1RationaleandPurposeoftheManual..................................................................................1
1.2UseandUsersoftheManual...............................................................................................2
1.3ContentsoftheManual.......................................................................................................2
1.4ScopeandLimitations..........................................................................................................2
1.5DefinitionofTerms...............................................................................................................3
2ComponentDescriptionandObjectives..................................................................................5
2.1BackgroundoftheI-REAPComponent.................................................................................5
2.2I-REAPObjectives.................................................................................................................6
2.3I-REAPComponentGoals,Objectives,OutcomesandOutputs...........................................6
2.4I-REAPDesiredOutcomesandExpectedOutputs................................................................7
2.5I-REAPLinkagewithotherPRDPComponents.....................................................................7
2.6I-REAPOperationalStrategies..............................................................................................9
2.7I-REAPComponentScopeofInterventions..........................................................................9
2.8I-REAPPossibleProponentGroup......................................................................................10
2.9I-REAPSubprojectFinancingModalities...........................................................................12
3ImplementationFeatures.....................................................................................................13
3.1ImplementingAgencyandPartnerAgencies.....................................................................13
3.2ImplementationStructure..................................................................................................14
3.2.1NPCOI-REAP................................................................................................................14
3.2.2PSOI-REAP...................................................................................................................15
3.2.3TheRegionalProjectAdvisoryBoard(RPAB)...............................................................15
3.2.4RPCOI-REAP.................................................................................................................16
3.2.5P/C/MPMIU.................................................................................................................17
3.3CapabilityBuildingProgramforProjectImplementers......................................................18
4ImplementationProceduresandProcesses..........................................................................19
4.1Implementation Process of Subcomponent 3.1 (Rural Agri-fishery Enterprise and
ProductivityEnhancementSupport).......................................................................................19
4.1.1RequirementsforLGUI-REAPPartners......................................................................19
4.1.2RequirementsforProponentGroups.........................................................................19
4.1.3ImplementationProceduresandProcess…………………………………………………………………21
4.1.3.1Implementation of I-REAP Subprojects in Areas Affected by Natural Calamities and
Conflict….………………………………………………………………………………………………………………………35
4.1.4PrivateSectorPartnershipwiththeProponentGroup...............................................35
4.2GEFSupportedActivities....................................................................................................36
4.2.1Pre-Implementation....................................................................................................36
4.2.2ImplementationProcessforI-REAPSubcomponent3.2(Technologyand
InformationforEnterpriseandMarketDevelopment).......................................................48
4.3Post-Implementation.........................................................................................................52
4.3.1Post-ProjectDataCollectionandEstablishmentofTechnologyDatabase..................52
5FinancialManagement.........................................................................................................53
5.1FinancingMixforI-REAPComponent................................................................................53
5.2FundEstablishmentattheLGU..........................................................................................54
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
ii
5.3PRDPFundReleasestoLGU...............................................................................................54
5.4FundTransferfromtheLGUtothePG...............................................................................55
5.4.1RequirementsforFundRelease..................................................................................55
5.4.2LiquidationofFundsReleasedtoPG...........................................................................55
5.5NegativeListofFundsUtilization.......................................................................................56
5.6Provision of Working
Capital......................................……………………………………………………………………………………………56
5.7DisbursementProceduresforTechnologyandInformationforEnterpriseand
MarketDevelopment(Subcomponent3.2)............................................................................57
5.8BooksofAccountsandRecords.........................................................................................57
5.9FinancialReports................................................................................................................58
6ProcurementGuidelines.......................................................................................................58
6.1Scope..................................................................................................................................58
6.2ProcurementArrangementundertheI-REAPComponent................................................58
6.2.1LGU-ManagedProcurement........................................................................................59
6.2.2ProponentGroup(PG)-ManagedProcurement..........................................................59
7SocialandEnvironmentalSafeguards...................................................................................59
8GrievanceMechanism..........................................................................................................64
9Results-BasedMonitoringandEvaluation............................................................................66
9.1Introduction.......................................................................................................................66
9.2OverviewofthePRDPRBMEFramework...........................................................................66
9.3OperationalizingthePRDPRBMESystemfortheEnterprise
DevelopmentComponent………………………………………………………………………………………………70
9.3.1ProgressM&ESub-system…………………………………………………………….……..………………….70
9.3.1.1Scope…………………………………………………………………………………………….……………………70
9.3.1.2SubprojectProgressM&EInstrument………………………………………………….……………..70
9.3.1.3SubprjectProgressM&EProcedures………………………………………………….……………….70
9.3.1.3aRegistryoftheEnterpriseDevelopmentSubprojectProposal………….……………71
9.3.1.3bRegistry/ReportingthestatusoftheEnterpriseDevelopmentSubproject….…73
9.3.1.3b.1Registry/ReportingofStatusofSuproject)FromAttendanceto
WorkshoponBusinessPlanningtoProcurement)…....................................73
9.3.1.3b.2Registry/ReportingofStatusofSubprojectImplementation
(AfterProcurement)……………………………………………………………………………….75
9.4SubprojectResultsM&ESub-system……………………………………………………………………………...77
9.4.1SubprojectBaselineData…………………………………………………………………………………………..77
9.4.1aTimingoftheSurvey…………………………………………………………………………………………….78
9.4.1bMechanicsfortheConductofSurvey……………………………………………………………………78
9.4.2RegistryoftheSPProfileincludingtheSubprojectBaselinetothe
Web-basedM&ESystem……………………………………………………………………………………….....81
9.4.3ConductofRapidAppraisalofEmergingBenefits(RAEB)………………………………………….81
9.5ResultsM&E…………………………………………………………………………………………………………………..82
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
iii
ListofTables
Table2-1.SampleTargetProponentGroupsbyCommodity.......................................................11
Table4-1.EligibilityRequirementsforProponentGroupsbyAmountofSubproject..................20
Table4-1.A.DocumentaryRequirementsforthePGEquity.........................................................21
Table4-2SubprojectProcedures,Activities,Tools,OutputsandResponsibilityCenter .............22
Table4-3.FinancingMixforI-REAPFunding...............................................................................33
Table5-1.FinancingMixforI-REAPComponent..........................................................................53
Table5-2.FinancingMixforI-REAPProjects................................................................................57
Table6-1.ProcurementTimeline-CFAforGoods(I-REAP)...........................................................59
Table7-1.SummaryofPotentialSocialImpactsandRequiredDocumentsforMitigation.........60
Table7-2.SummaryofImpactScenariosonIPsandRequiredDocumentsforMitigation.........61
Table7-3.SummaryofThresholdLevels-PotentialI-REAPEnterpriseComponents..................62
Table9-1.IntermediateOutcomestobeAchievedUnderI-REAPComponent............................82
Table9-2.ProceduresforMonitoringandEvaluationofI-REAPIntermediateOutcomes............83
ListofFigures
Figure2-1.I-REAPComponentConceptualFramework..............................................................7
Figure2-2.Inter-ComponentLinkages.......................................................................................8
Figure2-3.VerticalCommodityLinkages ...................................................................................10
Figure4-1.ProcessFlowforI-REAPImplementation:Sub-component3.1(RuralAgri-fishery
EnterpriseandProductivityEnhancement) ................................................................................45
Figure4-2.ProcessFlowforI-REAPImplementation:Sub-component3.2(Technologyand
InformationforEnterpriseandMarketDevelopment)...............................................................51
Figure9-1ThePRDPRBMESchematicFramework ....................................................................69
Annexes
Annex1.A-SampleMenuofEnterprisestobeSupportedbyI-REAPSub-Component3.1:
RuralAgri-fisheryEnterpriseandProductivityEnhancement.....................................................85
Annex1.B-SampleofActivities/Sub-ProjectstobeSupportedbyI-REAPSubcomponent3.2
(TechnologyandInformationforEnterpriseandMarketDevelopmentSupport)......................87
Annex2.A-MenuofPossibleNRMOGIsPerCommodityValueChain........................................89
Annex2.B-GlobalEnvironmentFacility(GEF)SupportedActivities ........................................94
Annex3-NegativeListofSub-projectsNotEligibleforI-REAPFunding.......................................96
Annex4-ProspectivePartnerAgenciesbyCommodityGroupandbySupportServices.............97
Annex5–SampleTermsofReferencesfortheBusinessDevelopmentStaff.............................98
Annex6-SampleProductSegment/EnterprisePrioritizationProcessandScoringSheet .......106
Annex7-GuideQuestionforBusinessModelFormulation/InformationGathering................109
Annex8-SampleLetterofIntentoftheProponentGroup......................................................110
Annex9.A-SampleProponentGroup(PG)PrioritizationProcessandScoringSheetfor
MicroenterpriseSubprojects ...................................................................................................111
Annex9.B-SampleProponentGroup(PG)PrioritizationProcessandScoringSheet
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
iv
forSmallandMediumEnterpriseandUpgradingEnterprises...............................................112
Annex10-PGValidationProcessandScoringSheet...............................................................113
Annex11-GuideQuestionforBusinessPlanData/InformationGathering..............................120
Annex12-A-I-REAPBusinessPlanOutline..............................................................................130
Annex12-B-SubprojectProposalOutlineforMicro-EnterpriseSubprojects...........................132
Annex12-C-TemplateoftheEnterpriseGeneralProfile.........................................................134
Annex13-A-ChecklistofRequirementsforSmallandMediumEnterpriseSubproject...........138
Annex13-B-ChecklistofRequirementsforMicro-enterpriseSubproject...............................144
Annex14-GuideintheConductoftheParticipatoryResourceAssessment-ResourceandSocial
Assessment(PRA-RSA) ............................................................................................................150
Annex15-BusinessPlanReviewTrackingForm ....................................................................159
Annex16-I-REAPInitialEvaluationForm ..............................................................................160
Annex17-SampleBusinessPlanorSubprojectProposalAppraisalorEvaluationForm..........162
Annex18-A-SampleImplementationManagementAgreement(IMA)forSubprojectswith
EnterpriseDevelopmentOnly ...............................................................................................166
Annex18-B-SampleImplementationManagementAgreement(IMA)forSubprojectswith
EnterpriseDevelopmentandCivilWorks ................................................................................177
Annex19-SampleEnterpriseInvestmentAgreement(EA) ...................................................189
Annex20-SupplementalGuidelinesfortheImplementationofSmallI-REAPLivelihood
SubprojectinYolandaandEarthquakeAffectedAreas(Region6,7and8)ofthePhilippineRural
DevelopmentProject ............................................................................................................199
Annex21-SubprojectProposalOutline ...................................................................................202
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
1
1 Introduction
1.1 Rationale and Purpose of the Manual1
Agricultureaccountsfor35%ofthePhilippineeconomyandemploysabout50%ofthelabor
force.However,itscontributiontoGrossDomesticProduct(GDP)andtotalemploymenthas
declined. Formanyyears, thecountry’sagriculture sectorhasbeencharacterizedby low
farmer’s income, low rural employment, precarious food security, low agricultural
competitivenessandhighruralpovertyoverall. Increasingdemandsforagriculturaloutput
havealsoputpressureonnaturalresources.Unsustainablepracticestoimproveyieldshave
resulted in landdegradation,decreasingwateravailabilityandmarineresourcedepletion,
which have been exacerbated by climate change. Development efforts need to focus on
transformingthesectorintoonethatisnotonlyhighlyproductivebutalsoclimate-resilient,
environment-friendlyandsustainable.
ThePhilippineRuralDevelopmentProject (PRDP) isdesignedtoaddressthissituationand
contribute to achieving the national goals of inclusive growth, job creation and poverty
reduction.Itbuildsonexistingpolicyframeworks,principlesandlessonslearnedfrompast
programsoftheDepartmentofAgriculture(DA).ThePRDPisasix-year(2013-2018)initiative
envisioned to increase farmand fisheryproductivityand incomes in targetareas inall16
regionsofthecountry. Theprojectseekstoachievethisobjectivebyimprovingaccessof
farmers and other industry players to a strategic network of infrastructure, market
information and support services. Specific investments and interventions are to be
implemented under four central components of the project, namely: 1) Local Planning
(IPLAN);2)InfrastructureDevelopment(I-BUILD);3)EnterpriseDevelopment(I-REAP);and4)
ProjectSupport(I-SUPPORT).
Through I-REAP, PRDP will engage broad sections of the sector in the production of
marketablesurplusthroughinvestmentsinstrategicsegmentsofprioritycommodityvalue
chainsprioritizedunder theRegionalAgricultureandFisheryModernizationPlan (RAFMP)
andtheProvincialCommodityInvestmentPlans(PCIPs).I-REAPisalsodesignedtostrengthen
collaborationbetweentheDAandtheprovincialgovernments.Itwilladoptthefarm-to-table
service delivery strategy being pursued under the Agrikulturang Pilipino (AgriPinoy)
framework.ItwillutilizetheBureauofSoilandWaterManagement’s(BSWM)vulnerability
and suitability assessment (VSA)methodology and results and the participatory resource
assessment (PRA) that will be conducted as bases for incorporating climate resiliency
strategies.
The implementationof the I-REAPcomponent,and thePRDPasawhole, involves several
institutionalpartnersattheregional,provincial,municipalandbarangaylevels.Theseinclude
severalnationalgovernmentagenciesandtheentirelocalgovernmentunit(LGU)community
inthecountry.Italsoinvolveslocalcommunities,households,people’sorganizations,non-
governmentorganizations,privatesector,academicinstitutionsandothercivilsocietysector.
ToensuretheI-REAPcomponent’seffectiveandefficientimplementation,includingthatof
1ThissectioncontainsinformationtakenfromthePRDPFeasibilityStudyMainReport.
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
2
theactivitiestobesupportedbytheGlobalEnvironmentFacility(GEF),itisimportantthat
thestakeholders,mostespeciallytheprojectimplementers,gainsharedunderstandingofits
operatingmechanisms.ThismanualthusaimstoensureacommonunderstandingoftheI-
REAPcomponentbyallstakeholders.
1.2 Use and Users of the Manual
Thismanualseekstoprovideacomprehensiveandstep-by-stepguidefortheimplementation
ofI-REAPactivities–fromtheselectionofenterpriseproponents,enterpriseplanningand
implementation, to themonitoringof theenterprises’progress and theevaluationof the
immediateandfinalimpactsoftheenterprises.Italsoclarifiesrolesandrelationshipsamong
implementers and prescribes measures to control the quality of outputs and to ensure
optimumuseofprojectresources.
Thismanualwasprepared for theuseof thepersonnel of theDA (the executing agency,
includingitsattachedagenciescriticalintheI-REAPimplementationaswellasotherpartner-
agencies,namely:DepartmentofEnvironmentandNaturalResources(DENR),Department
of Trade and Industry (DTI), Department of Science and Technology (DOST), National
CommissiononIndigenousPeople(NCIP),andtheLGUsfromtheprovincialandmunicipal
levels;theregionalandotherlocalunitsoftheparticipatingnationalagencies,participating
schools,collegesanduniversities,participatingnon-governmentorganizations(NGOs),and
the partner producer group organizations, private sector and other stakeholders. Any
proposedchangestothemanualasaresultofexperiencesinthefieldandlessonslearned
willbeadoptedandincorporatedinsubsequenteditionsofthemanual.
1.3 Contents of the Manual
Themanualcontainsthefollowingmajorparts:I-REAPcomponentdescriptionandobjectives,
which summarizes thecomponents’ interventions, theexpectedoutputsand someof the
major activities; the general conditions for implementation, which discusses the
implementingagencyandimplementationpoliciesthatprovidethepolicyframeworkforthe
component and its interventions; the implementation structure which describes the
administrativeframeworkandfinancialoperationsofthecomponent;the implementation
proceduresatthepre-implementation,implementationandpost-implementationphasesof
thecomponent;financialmanagementto includereleaseoffundstoProvincialLGU(LGU)
and proponent groups (PG); the procurement process for goods, works and services in
support to enterprises; social and environmental safeguards (SES); and results-based
monitoringandevaluation(RBME).
1.4 Scope and Limitations
ThismanualcontainsonlytheimplementationguidelinesoftheI-REAPcomponentandits
GEF-supported activities at the project management level. Specific guidelines for the
operation of the I-REAP supported enterprises will be contained in the Implementation
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
3
ManagementAgreement (IMA),Enterprise InvestmentAgreement (EA), andother related
documents.
1.5 Definition of Terms
Thefollowingoperationaltermswillbeusedonthismanualforclarityandmutualreference;
thusthesewillbedefinedasfollows:
BusinessPlan–referstothesubprojectproposalordocumentthatwillbethebasisfor
financing the proposed enterprise. The business plan should have a description of the
enterprise, its composition, products and services; market analysis; competitor
assessment;marketingplan;operationalplan including technical assumptions, facilities
andequipment,processflowandorganizationandmanagement;financialplanincluding
discussiononcapital investmentrequirements;andfinancialplanincludinganalysisand
financialratiostodeterminethetechnical,marketandfinancialviabilityofthesubproject
orenterprise.
BusinessModeling – refers to theactivity thatwill beundertakenby the LGUand the
ProponentGroupwiththeassistanceoftheRPCOwhereinthebusinessconceptforthe
proposed enterprise will be drawn. The businessmodel should answer the questions,
“What, Who, How”. What are the products/services of the enterprise? Who are the
suppliersandbuyers?Whataretheproblemsbeingaddressedandopportunitiesbeing
pursued?Whatistheuniquesellingpropositionoftheenterprise?Whoaretheenterprise
partners?Whatarethecostsinvolvedandrevenuestobegenerated?Howthefarmers
willbenefitfromtheenterprise.
Enterprise–referstothesubprojectdrawnfromthePCIPthatwillbefundedbythePRDP
IREAP.Itisthebusinessventurethatwillbeundertakenbytheproponentgrouporcluster
ofproponentgroups.
Enterprise Investment Agreement (EA) – is an agreement between the LGU and the
ProponentGroup/LeadProponent(andtheclusterofproponents).TheEAindicatestheroles
andresponsibilitiesoftheLGUandPGintheimplementationandoperationoftheenterprise
asidentifiedintheBusinessPlan.Itshallalsoidentifytheprovisionsinthefundreleasesand
procurementofgoods,worksandequipmentthatwillbeusedbytheenterprise.
EnterpriseProjectFund(EPF)-referstotheenterprisecostconsistingoftheloanproceeds,
theGOPcounterpartandtheLGUcounterpartwhichwillfinancethegoods,smallworksand
operationalcostsoftheenterpriseasrequiredinthebusinessplan.
EnterpriseSupportFund–referstotheI-REAPprogramfundconsistingoftheloanproceeds
andtheGOPcounterpartintendedtofinanceactivitiestobefundedunderSubcomponent
3.2insupporttothecommodityvaluechainsuchastraining,crossvisits,provisionofmarket
information,marketlinkageandpromotion,technologydevelopment,technodemoandthe
like.
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
4
ImplementationManagementAgreement(IMA)–isanagreementamongPSO,RPCOand
LGUthatspellsouttheimplementationarrangementsforallI-REAPsubprojects/enterprises
withinagivenperiodincludingthescheduleoffundreleasesandliquidations.
LeadProponent–isthemajorpartneroftheLGUintheenterpriseandwillserveasthemain
I-REAPsubprojectproponent,inthecaseofclusterofproponentgroups.
Micro,smallandmediumscaleenterprises–thesearethesubprojectsthatwillbefunded
by PRDP I-REAP Sub-component 3.1 with costs falling under the following categories:
Micro: not more than Php3,000,000; Small: Php3,000,001 - Php15,000,000; Medium:
Php15,000,001 – Php50,000,000. This amount include the costs of the enterprise
operation,equipment,facilitiesandcivilworks,netofPGequity.
ProgramContract–anagreementamongthePSOand/orRPCOandthepartneragencyor
entitythatcoverstheengagementofthepartneragencytoprovidetechnicalandsupport
servicesrelatedtotechnology,informationandproductandmarketdevelopmentsupport.
Thelistoftechnologysupportservicesshallsupportthecommodityvaluechain.
ProponentGroup-refersmainlytotheproducergroups(suchasfarmers/fishersgroups,
cooperatives,associations,RIC)engagedinthecommodityvaluechainandhavealegal
personality. Proponent group could also include micro, small and medium-scale
enterprises (i.e.agri-processors, consolidators,exporters,etc.)whoarewilling toassist
producer groups in vertical clusteringor joint business planning, and forge contract or
formalmarketingarrangementwithproducergroups.
Provincial Commodity Investment Plan (PCIP) – is a strategic plan that rationalizes the
interventionswithin the various segments of the value chain of commodities that are of
significancetotheprovinceandthatwillcontributetothenationalgoalsoftheagriculture
andfisherysector.Itis3-yearrollingconsensusplanbetweentheDAandLGUbasedonthe
valuechainanalysesofthesecommoditiesconductedwithstrongparticipationofthevarious
stakeholders.ThePCIPwillbethebasisinidentifyingpossibleenterprisesinwhichaprovince
decidestomakeapackageofinvestmentsthattheDAwillprovideassistance,withadequate
counterpartfromtheLGU.
Start-up Enterprises – refers to financing of I-REAP subproject that is a new business
undertakingoftheselectedproponentgroup.Thiswillalsofinanceproposedsubprojectsof
PGsthatfallwithinLevelIandLevelIIofthevaluechainladder.Thetotalenterpriseproject
costthatwillbeprovidedshallnotexceedPhP15Million.
TotalEnterpriseProjectCost–isthetotalcostoftheI-REAPsubprojectthatwillbefunded
bytheLoanProceeds,GOPcounterpart,LGUcounterpartincludingthecostofthecivilworks
component,netofPGequity.
TotalInvestmentCost- isthetotalamountofthebusinessplanwhichincludecostofthe
enterpriseoperation,equipment,facilities,civilworksandPGequityincashand/orinkind.
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
5
Upgrading/ExpansionofEnterprises–financingofI-REAPsubprojectthataimstoexpandor
upgradeexistingbusinessactivityofthePG.Expansionandupgradingcouldbeintermsof
equipment,facilitiesandproductlines(suchasdevelopmentofnewproducts,development
ofnewmarketsorincreaseinproductioncapacityofthePG).Someexamplesinclude:aPG
withexistingbusinessonflavoredmilkprocessingwillbeproposingsubprojectforPRDPon
cheeseandyoghurtprocessing;existingPGproducinggeonetwillexpandingoperationby
buyingwholenutfromcoconutfarmerstoproducecopraandusethehusktoincreasevolume
of production of geonets; existing PGproducing cassava granuleswill increase volumeof
production by expanding source of raw materials thru increase in farmer members and
consolidating volume of output of other cooperatives or associations thru enterprise
clustering. The total enterprise project cost thatwill be provided shall not exceed PhP50
Million.
2. Component Description and Objectives
2.1 Background of the I-REAP Component2
The conceptualization of PRDP and the I-REAP component, in particular, considered the
experiences, lessons and approaches drawn fromDA’s implementation of twoMindanao
RuralDevelopmentProjects(MRDP1&MRDP2).Such lessons includefeasible institutional
arrangements with LGUs and community-based approaches to ensure that project
interventionsareresponsivetotheneedsofLGUsandstakeholders.
UnderpinningPRDP’sapproachisbuildingastrongerpartnershipandengagementbetween
theDA(atthenationalandregionallevels),andthevariousdevelopmentstakeholdersatthe
local level (e.g., LGUs, farmers and fishers, private sector, academe, etc.) in investing in
prioritycommodityvaluechains.AllRegionalFieldUnits(RFUs)willundergotheprocessof
enhancingtheirregionalAFMPsthatidentifyhowregionalplanswillcontributetoachieving
nationalAFMPgoals.Thisisdesignedtoensurebettercongruenceinthesectorinvestments
beingfinancedatthelocallevelswhilefulfillingthenationalAFMPtargets.
TheLGUswillbesupportedinbuildingtheircapacitiestoidentifyandinvestininfrastructure
andsupportservicesneededtodeveloppriorityvaluechainsandamoremarket-oriented
agricultureandfisherysectorintheirareas.Complementingthis,communityentrepreneurial
activitieswouldbesupportedtohelpproducergroupsraiseincomesthroughbetterlinkages
andaccess tomarkets.Thisapproachhasalreadybeenpilot testedandadopted in those
regionsandLGUsimplementingMRDP2.WhileMRDP2wasdesignedtosupportcommunity
livelihoodactivities, thefocusofPRDPI-REAPComponentwouldbemoreonbuildingand
supportingagriculturalandfisheries-basedenterprises.OneofthekeyfeaturesofI-REAPis
theintegrationofnaturalresourcemanagement(NRM)intheenterprises.Therewillalsobe
2PRDPFeasibilityStudyMainReport
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
6
agreaterfocusinensuringamoresystematicprovisionoftechnologyandmarketsupport
servicesforallenterprises.
2.2 I-REAP Objectives
The general objective of the I-REAP component is to strengthen and develop viable agri-
fishery based enterprises through efficient value chains of key agricultural and fishery
productsintargetedprogramareas3.Itsspecificobjectivesareasfollows:
a. Toincreaseproductivityandmarketabilityofagricultureandfisheryproductsthrough
increasedaccesstoinformationandsupportservices;
b. Toincreasefarmandfisheryhouseholdincomesthroughengagementinvalue-adding
activities;and
c. Toimprovetheprotectionandconservationofthenaturalresourcebaseofidentified
enterprisesthroughalternativelivelihoodsandsupportfacilities.
2.3 I-REAP Component Goals, Objectives, Outcomes and Outputs4
Thecontributionof the I-REAPcomponenttotheoverallPRDPgoalof increasing farmers’
incomeandmarketablesurplusintheagri-fisherysectoristostrengthenanddevelopviable
agri-fisherybasedenterprisesthroughefficientvaluechainsofkeyagriculturalandfishery
productsintargetedprojectareas.
Toachievetheobjectiveofcreatingaclimateresilientandadaptivestrategyforenhancing
thevaluechainneedsoftheprioritycommodity,GEFsupportwouldbeprovidedintarget
areas in Central Philippines. TheGlobal EnvironmentObjective (GEO) of theGEF support
wouldbetocontributetotheconservationofbiodiversityandstrengtheningthecoastaland
marine resources base in targeted project areas. This would be achieved through (i)
enhancing institutional and planning capacities of LGUs and communities, (ii) providing
support to Marine Protected Areas (MPAs) in particular areas of global biodiversity
significanceandselectfisheryco-managementarrangements,and(iii)sharingofknowledge
and best practices. By integrating the GEF support with the institutional reforms being
“rolled–out” under the PRDP, the mainstreaming of innovations and best practices for
sustainableecosystemmanagementwouldbeenhanced.
3PRDPFeasibilityStudyVolume3:I-REAPComponent4PRDPFeasibilityStudyVolume3:I-REAPComponent
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
7
2.4 I-REAP Desired Outcomes and Expected Outputs
The goal or intended impact of I-REAP is increased farmer’s income in agri-fishery sector
(Figure 2-1). The desired outcomes are: a) increased producer groups operating viable
enterprises;b)enhancedproducergroups’productivitythroughformalizedarrangementsfor
marketingand/ortechnicalservices;andc)increasedproducerandfishergroups’resilience
toclimatechangeandadverseweatherconditions.
I-REAPactivitiescanbecategorizedintotwosub-components:1)ruralagri-fisheryenterprise
andproductivityenhancementand2)technologyandinformationforenterpriseandmarket
development).Theexpectedoutputsforsub-component1are:1)enterprisesupgraded,up-
scaledorestablishedattheappropriatecommodityvaluechainsegment,2)productionand
market support facilities established, and 3) LGU investments in the agri-fishery sector
increased.Ontheotherhand,outputsforsub-component2are:1)capacityoffarmerand
fishergroupsenhancedinadoptingappropriateproductivityenhancementtechnologies,2)
technologyextensionandbusinessdevelopmentservicedeliverystandardizedtosuitpriority
commodities;3)capacityofproducerandfishergroupstomanageandoperateagri-fishery
enterpriseenhanced;and4)farmtomarketlinksestablished.
Figure2-1.I-REAPComponentConceptualFramework
(BasedontheLogicalFramework)
2.5 I-REAP Linkage with other PRDP Components
Althougheachmajorinvestmentcomponent–I-PLAN,I-REAP,andI-BUILD–haveseparate
and distinct objectives, they are all designed to contribute to the accomplishment of the
project’s development objective. Thus, it is imperative that component processes and
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
8
outputs are in sync with each other (See Figure 2-2). Ensuring this synchronicity and
articulating the common element and the thread that ties key features across each
componentisthePCIP.Thismainlycontainsthestrategicareasofproductsegmentsinthe
valuechainof theprioritycommoditiesof theprovincesthatcouldbesupportedunder I-
REAPandI-BUILD.ThedevelopmentofthePCIPistheprimaryresponsibilityoftheI-PLAN
component, but with substantial contributions from the I-REAP and I-BUILD components
duringthePCIPdevelopmentprocess.
SpecificallyfortheI-REAPcomponent,assistancetoI-PLAN’sPCIPprocedureswillinvolvethe
applicationofthevalue-chainanalysisandfocusingontheproperapplicationofthecriteria
foridentifyingthepriorityenterprisesthatwillbeincludedinthePCIPforpotentialfunding
underI-REAP’sSubcomponent3.1.I-REAP’sworkingrelationshipwiththeI-BUILDcomponent
is linked with the infrastructure investments supporting the priority enterprises, also
containedinthePCIP.
I-SUPPORTisprogrammedtoprovidethestrategicadministrative,logistical,andoperational
assistancetothevariouscomponentsinimplementingtheiractivities.
Figure2-2.Inter-ComponentLinkages
PROJECTDEVELOPMENTOBJECTIVE
PRDPaimstoincreaseruralincomeandenhancefarmandfisheryproductivityintargetprogramareas.
PROVINCIALCOMMODITYINVESTMENTPLAN
I-REAP
Supportverticalclustering,joint
businessplanningandinvestmentsoftheproponentsgroupsengagedinenterpriseswithinthe
priorityvaluechainbasedon
thePCIP
I-BUILD
Infrastructuresupporttoenterprisesbasedonthe
PCIP
I-PLAN
Supporttoimprovingtheagricultureandfisheryplanningprocessusingscience-basedapproaches
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
9
2.6 I-REAP Operational Strategies5
Inconsonancewiththeabovementionedpoliciesandprojects,thefollowingkeystrategies
willguidetheimplementationoftheI-REAPcomponent:
• Broad-basedandinclusiveenterprisedevelopmentthroughclusteringofproponents
which engages farmer and fisher groups in surplus generation and value-adding
activities;
• Graduatedmarketaccesstomatchproductioncapacitiesandmarketrequirements
throughjointbusinessplanning;
• Value chain-determined product segments and interventions for enterprise
engagement;
• Equityinvestmentstobeputupbythegovernmentwiththeprivatesector;
• Farm-to-table service delivery, i.e., interventions and investments to improve
efficiencyofvaluechainsfromproductiontotheendconsumer;
• Integrationofnaturalresourcemanagementintocommunityenterpriseprojectsto
ensuresustainabilityofinvestments,preservethenaturalresourcebaseanddevelop
climate-resiliententerprises;
• InstitutionalizationoftechnicalsupportservicesinDARegionalFieldUnitsaimedat
improving productivity, market linkages and entrepreneurship skills among
participatingproducergroups;and
• Localownershipandsynergisticpartnership.Oneofthelessonslearnedfromprevious
ruraldevelopmentprojectssuchastheMRDP, InfrastructureforRuralProductivity
Enhancement Sector (InFRES), Agrarian Reform Community Development Project
(ARCDP2),etc.isthecriticalroleplayedbyLGUsinimplementingruraldevelopment
projects. I-REAPproject interventions/componentsshouldhaveaclear linkto local
economic development priorities and agenda to ensure local ownership and
community“buy-ins”.
2.7 I-REAP Component Scope of Interventions6
This component would support the development, implementation and sustainability of
agricultural, livestock or fishery-based entrepreneurial activities, based on the analysis of
priorityvaluechainsbeingsupportedunderAFMPs,andasreflectedinthePCIPs.Thetypes
ofinterventiontobesupportedwouldneedtobetailoredtothelevelofdevelopmentand
capacityoftheproducers.Annex1.Ashowsthesamplemenuofenterprisestobesupported
byI-REAPSub-component3.1whileAnnex1.Bpresentsthesampleofactivities/sub-projects
tobesupportedby I-REAPSub-component3.2. Annex2.Apresentsthemenuofpossible
NRMOn-the-GroundInvestment(OGIs)percommodityvaluechain.Annex2.Bcontainsthe
GEFsupportedactivitiesandAnnex3containsthenegativelistofenterprisesoractivitiesthat
cannotbesupportedbyI-REAP.
5PRDPFeasibilityStudyVolume3:I-REAPComponent6PRDPFeasibilityStudyVolume3:I-REAPComponent
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
10
Forplanningpurposes,threelevelscouldbeconsidered,assummarizedinFigure2-3,with
verticallinkagebetweenproponentsofenterprisesthroughclustering,whichwouldinvolve
forward,andbackwardcontracting/arrangements.Theverticalconvergenceofproponents
engagedinenterprisesidentifiedatdifferentlevelsoftheagri-fisherydevelopmentladderis
guidedbytheproperconductandresultofthevaluechainanalysis.Thevaluechainanalysis
shouldshowattheveryleastthecriticalsegment(s)intheproductflowchartthatrequire
supportthatwilldetermineappropriateclusteringofproponents in identifiedenterprises.
Small farmers and fishers who have the capacity to produce marketable surplus will be
capacitatedthroughclusteringorintegratingwithmoreorganizedgroups.Producersgroup
couldalsobeclusteredorintegratedwithmarketstoachievefullmarketintegration.
Figure2-3.VerticalCommodityLinkages
2.8 I-REAP Possible Proponent Group
ThepossibleproponentgroupsforI-REAPenterprisesarethefollowing:
a. Existingproducergroupswithmembersproducingcommoditieswhichareincludedin
thepriorityvaluechainsandhavepotentialtoincreasetheirmarketablesurplus;
b. Smallholder(farmersandfishers)groupswhichhavepotentialtoproducemarketable
surplus and demonstrate willingness to voluntarily adopt clustering with other
groupsandforgecontractsorformalmarketingagreementswithbuyersorprivate
intermediaries;
Commonservicefacilities,post -harvestfacilities,home-basedprocessing,feedmixingfacility,fishcages,plantingmaterialnurseries,NRMOGIs,GISinstruments,bancas,surveytools,etc.
Level2EnablingFarmtoMarketLinkages
Vertic
al
Com
modit
y
Linka
ge
Level1BuildingFoodSecurityandMarketableSurplus
Packinghouses,haulingequipment,consolidationcenters,multi -specieshatcheries,pasteurizingplants,drying,millingfacilities,livestockauctionmarkets,etc.
Level3Fullmarketintegration
Incubationforfood
Processing,vaporheattreatmentforexportcommodities,tripleAslaughterhouses,testingcenter,laboratories,etc
Clustering
ofproponentgroupsengaged
inenterprise
Clustering
ofproponentgroups
engagedinenterprises
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
11
c. Producergroupsorclusterofgrowers shouldbeeitheroperationaland/or showa
willingness to undergo capacity building on enterprise development and
management;and
d. Micro,small-andmedium-scaleprocessors,consolidators,exporters,etc.,whowould
bewillingtoassistproducergroupsinverticalclusteringorjointbusinessplanning,
andforgecontractorformalmarketingagreementswithsuchproducergroups.Joint
business planning and investments of the producer groups and agro-processors,
wouldbesupportedifitwouldresultinincreasedengagementoftheproducergroups
invalue-addingactivities.
Farmersandfisherswhoarenotmembersofanyorganizationoperating inthepriority
commodityvaluechainmustjointheproponentgroups(PG)forthemtobeeligibleinthe
I-REAPsupportedenterpriseseitherasmemberofthePGorassuppliertotheenterprise.
SampletargetproponentgroupsbycommodityareshowninTable2-1.
Table2-1.SampleTargetProponentGroupsbyCommodity
Commodity SampleTargetProponentGroups7
Cereals Riceandcorngrowersorganizedinto
• Farmersassociation(FAs)
• Irrigatorsassociation(IAs)
• Agrarianreformbeneficiariesassociations(ARBAs)
• Primarycooperatives
• Upland rice and corn cultivators especially IPs (with CADTs/CADCs) and upland
migrantsettlers
Root
Crops/Tubers
(Sweet
Potato,
Cassava)
• Localsweetpotato,cassavaandotherrootcropsgrowersassociation
• IPs(withCADTs/CADCs)anduplandmigrantsettlers
Vegetables • Localvegetablesgrowersassociation
• IPs(withCADTs/CADCs)anduplandmigrantsettlers
• Organicproducersassociation
• Localvegetablesgrowersfederationorcommoditygroups
• Vegetableindustrycouncils(provinceandregion)
FruitCrops • Localfruitgrowersassociation
• IPs(withCADTs/CADCs)anduplandmigrantsettlers
• Fruitgrowersfederationorcommoditygroups
• Fruitindustrycouncils(provinceandregion)
Livestock • Localcattleraisersassociation
• Localhograisersassociation
• Localpoultryraisersassociation
• Goatraisersassociation
• IPs(withCADTs/CADCs)anduplandmigrantsettlers
• Cooperatives
Fishery
Subsector
• Fisherfolkassociations
• Cooperatives
7Targetproponentgroupsshouldincludewomen
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
12
2.9 I-REAP Subproject Financing Modalities
I-REAP Subproject financing modalities can be categorized into two: a) by amount of
subproject;andb)bynatureofbusinessundertaking.
A. ByAmountofSubproject
I-REAPenterprisescanbecategorizedintomicro,smallandmediumenterprises(MSMES).
AdoptingthedefinitionofMSMEsasdefinedinRA9501ortheMagnaCartaforMicro,
Small and Medium Enterprises the following are the type of I-REAP subprojects by
amount:
1. Micro-enterprisesubproject-notbemorethanPhP3,000,000
2. Smallenterprisesubproject-PhP3,000,001-PhP15,000,000
3. Mediumenterprisesubproject-PhP15,000,001–PhP50,000,000.
B. ByNatureofBusinessUndertaking
1. Restorationorrehabilitation–thesearesubprojectsthatcouldbeavailedinresponse
totheneedsofthefarmersandfisherswhowereaffectedbycalamitiesandconflicts.
Adeclarationof“StateofCalamity”bythelocalgovernmentunitand/oridentification
bytheNationalDisasterRiskReductionManagementCouncil (NDRRMC)willbethe
basisforthis.Ontheotherhand,thelistofmunicipalitiesandprovincesbyDILGwill
be the basis for the areas affected by conflicts or peace and order situation. A
certificationfromDILGshouldbesubmittedassupportingdocument.
Asageneralrule,all I-REAPsubprojectsshouldbebasedonVCAsandalignedwith
prioritiesofthePCIPs.
However, for micro-enterprise subprojects responding to restoration and
rehabilitationefforts,asdefinedinSection2.9B.1,thatarenotalignedwithVCAsand
PCIPs,amaximumof10%oftheLoanProceedsoruptoUS$9Millionmaybeusedand
allocatedfromthetotalI-REAPSub-component3.1funds.Themaximumamountper
subprojectthatcanbeproposedunderthiscategoryisPhP1Million,netofPGequity.
TheNPCOshallgiveclearancetothePSOfortheuseofthefunds.
2. GEFArea–thesearesubprojectsthatwereidentifiedtoprovideincomegenerating
activities to fisherfolk communities in support to the biodiversity conservation
activities in the identified marine protected areas. The maximum amount per
subprojectthatmaybeproposedforGEFareasisuptoPhP5Million,netofPGequity.
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
13
3. Start-up Enterprises – financing of I-REAP subproject that is a new business
undertakingoftheselectedproponentgroup.Theamountofsubprojectthatmaybe
proposedasstart-upshallnotexceedPhp15Million,netofPGequity.
4. Upgrading/Expansion of Enterprises – financing of I-REAP subproject that aims to
expandorupgradeexistingbusinessofthePG.Expansionandupgradingcouldbein
termsofequipment,facilitiesandproductlines(suchasdevelopmentofnewproducts,
development of newmarkets or increase in production capacity of the PG). Some
examples include: a PG with existing business on flavored milk processing will be
proposing subproject for PRDP on cheese and yoghurt processing; existing PG
producinggeonetwillexpandingoperationbybuyingwholenutfromcoconutfarmers
to produce copra and use the husk to increase volume of production of geonets;
existing PG producing cassava granules will increase volume of production by
expandingsourceofrawmaterialsthruincreaseinfarmermembersandconsolidating
volumeofoutputofothercooperativesorassociationsthruenterpriseclustering.
Insomeprovinces,theseenterprisesmayalsocoverLevelsI,IIandIIIasindicated
intheverticalcommodity linkages(seeFig.2-3,p.10).Themaximumamountof
subproject that may be proposed as upgrading/ expansion shall not exceed
PhP50Million,netofPGequity.
The over-all target of I-REAP is to upgrade existing micro enterprises to small
enterprises and build their assets from PhP3Million to PhP15Million. On
exceptionalcases,PRDPmayalsoselectandsupportsmall-scaleenterprisesand
upgrade/expandthemintomedium-scaleenterprises.
UndertheladderizedI-REAPinterventions,PGisexpectedtobecompetentfortheenterprise
itcanengagewith.Whilemanagingtheenterprise,itcanincreaseitseligibility,capabilityand
competencytoqualifyforthenexthigherlevelofenterprise.Forexample,aPGwasqualified
forthecassavaproduction.Aftersomeyears,itcanexpanditsoperationtoprocessinggiven
thatitsatisfiesthecriteriasetunderLevelIIwhileutilizingthefundsgeneratedintheinitial
projectinvestmentwithinfusionofadditionalcapital.
3. Implementation Features
3.1 Implementing Agency and Partner Agencies
TheDAwillbetheexecutingagencyofthePRDP.Itwillhave,aspartneragencies,relevant
DA-attached agencies e.g., Philippine Coconut Authority (PCA), National Dairy Authority
(NDA), BSWM, Philippine Center for Postharvest Development and Mechanization
(PHilMech),BureauofFisheriesandAquaticResources(BFAR),AgriculturalTrainingInstitute
(ATI),AgriculturalCreditandPolicyCouncil (ACPC),BureauofAgriculturalResearch (BAR),
etc.OtherpartneragenciesincludeDepartmentofAgrarianReform(DAR),DENR,DOST,DTI,
andDepartmentofInteriorandLocalGovernment(DILG),amongothers.
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
14
Annex4providesthelistofprospectivepartneragenciespersubsectororcommoditygroup
andthekindoftheassistancethattheycanprovideforenterprisedevelopment,including:
1) improving production and productivity including agricultural extension services, skills
development, provision of production inputs, equipment and facilities/infrastructures for
production and post-production activities, etc.; 2) improving producers’ and enterprises’
accesstofinancingintheformofcreditorgrantsaswellascropinsurance;3)provideaccess
toimprovedtechnologiesthroughresearchanddevelopment;and4)provisionofbusiness
supportanddevelopmentservices,particularlyintheareasofmarketing,networking,etc.
Partner agencies will serve as project collaborators and will primarily provide technical
supportandassistancetosupporttheenterprisesinthecommodityvaluechainwhichshall
executedthroughaProgramContract.
3.2 Implementation Structure
A PRDP National Project Coordinating Office (NPCO) at the DA Central Office will be
established and headed by the Undersecretary for Operations. Under this, four8Project
SupportOffices(PSOs)willbesetup,twoforLuzon(LuzonACluster-CAR,Regions1,2,3and
LuzonBClusterRegions4A,4B,5);oneforVisayasandoneforMindanao.I-REAPUnitswill
beconstitutedineachofthesePSOs.CarryingouttheI-REAPcomponentoperationsatthe
locallevelwillbetheI-REAPteamsintheRegionalProjectCoordinationOffice(RPCO)and
the Project Management and Implementation Unit at the provincial/city/municipal
(P/C/MPMIU)levels.ThefunctionsandstaffcomplementoftheI-REAPunitineachofthese
officesareasfollows:
3.2.1 NPCO I-REAP
a. ServeasoversightofPSOandRPCOI-REAPunits;
b. AssisttheI-PLANinthereviewofVCAsandPCIPs;
c. AssistintheorientationoftheI-REAPOperationsManual;
d. Preparetheannualandglobalworkplanforthecomponent;
e. ConductofcapabilitybuildingneedsofPSOs;PSOstoRPCOsandRPCOsto
P/C/MPMIUs
f. Coordinatetheeffective implementationofthe I-REAPcomponentactivitiesacross
thedifferentPSOI-REAP;
g. Assistintheconductofsiteandproponentgroupvalidation;
h. IssueNoObjectionLettertoallI-REAPsubprojectswithinthegiventhreshold;
i. Monitor the implementation of the enterprise implementation and operation
includingSEScompliance;
j. ProvideregularreportsontheoverallimplementationofI-REAPactivities;and
k. FacilitatesharingofbestpracticesacrossPSOs.
8NPCOwillalsofunctionasthePSOforLuzonBCluster(Regions4A,4Band5)
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
15
TheNPCO I-REAP isheadedby theAgribusinessandMarketingAssistanceService (AMAS)
Director. At the minimum, the NPCO I-REAP Team, will be composed of a Business
Development Specialists (BDS), EnterpriseDevelopment andMarketing Specialist (EDMS).
businessandenterprisedevelopmentstaffandprojectdevelopmentassociates.
3.2.2 PSO I-REAP
a. Coordinatetheeffective implementationofthe I-REAPcomponentactivitiesacross
thedifferentRPCOI-REAP;
b. Assist the RPCOs in facilitating collaboration activities of various stakeholders and
engagementofothersupportinstitutionsandagencies;
c. ProvidesupporttotheRPCOsinimprovingaccessoftheproponentgroupstoresearch
andtechnologyresources;
d. BuildthecapacityoftheRPCOI-REAPunitstafftoprovidetechnicalassistanceand
supportservicestotheLGUandthePG;
e. ProvidetechnicalassistanceandcoherenceacrossRPCOs;
f. FacilitatesharingofbestpracticesacrossRPCOs;
g. Conductsiteandproponentgroupvalidationandissueletterofconfirmationonthe
selectedproponentgroup;
h. Facilitate theconductof complianceand technical review toensure feasibilityand
viability of the business proposals, and check completeness, consistency and
correctnessofthedocumentsbeforeendorsementtoNPCO;
i. Review and approve through issuance of No Objection Letter all micro-enterprise
subprojectsandothertypesofsubprojectswithinthegiventhreshold;
j. ProvidetechnicalassistanceinthepreparationandfinalizationofIMAsandEAs;
k. Assist InfoACE Unit in the conduct of I-REAP information, education and
communication(IEC)activitiesinthecluster;
l. AssisttheRPCOinfacilitatingtheconductofworkshopfortheP/C/MPMIUandthe
PG in coming up with policy and implementing guidelines relating to the
implementationoftheenterprise;
m. MonitortheimplementationandenterpriseoperationoftheI-REAPsubprojectsand
coordinatewithSESUnit inconsolidatingsafeguardscomplianceandwithMandE
UnitonimpactmonitoringreportinthecoveredRPCOs;and
n. ProvideregularreportsontheoverallimplementationofI-REAPtoNPCO.
ThePSOwillbe ledby I-REAPComponentHeadcomplementedbythe followingtechnical
staff:BDS,EDMSandbusinessandenterprisedevelopmentstaff.
3.2.3 The Regional Project Advisory Board (RPAB)
The RPAB is the regional counterpart of the National Project Advisory Board. The
implementationtasksoftheRPABareto:
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
16
a. ReviewandapproveI-REAPbusinessplansanditscorrespondingworkandfinancial
planforfunding;
b. EnsurepolicydirectionsarecarriedoutintheplanningandimplementationofI-
REAPenterprisesintheregion;
c. EnsureoverallharmonizationofsupporttoI-REAPenterprisesfromcollaborating
NationalLineAgencies’(NLA)regionaloffices;and
d. Generate support for and participation in I-REAP implementation by LGUs, people
organizations(POs)andNGOs.
TheRPABwillbecreatedthroughaSpecialOrderfromtheOfficeoftheSecretaryoftheDA
andchairedbytheDARegionalExecutiveDirector.
3.2.4 RPCO I-REAP
TheChiefoftheMarketingAssistanceDivision(MAD)oftheDA-RFOswilltaketheleadrole
incoordinatingtheoverallimplementationoftheI-REAPComponentactivitiesattheregional
level.
TheRPCOI-REAPunitswillhavethefollowingfunctionsandresponsibilities:
a. AssisttheP/C/MPMIUinprioritizingenterprisestargetedforI-REAPfundingbasedon
thePCIPandpreparingbusinessmodelsorconceptthereof;
b. Assistintheconductofsiteandproponentgroupvalidation;
c. ProvidetechnicalassistancetotheP/C/MPMIUI-REAPTeaminpreparingthebusiness
plansincludingallrequireddocumentsandattachments,EAandIMA;
d. Conductcollaborativetechnicalreviewofbusinessplansincludingthecompleteset
ofattachments,withcommodityexpertswithinDAbureausandattachedagencies,
other government agencies, institutions and/or organizations ensuring alignment
withexistinggovernmentprojects;
e. Endorseappraisedbusinessplans,EAandIMAtoPSO;
f. FacilitatepreparationandfinalizationofIMAsandEAsandendorsetheIMAtothe
PSOforfundrelease;
g. FacilitatesubmissionandcomplianceinthedocumentsrelatedtoI-REAP;
h. MonitortheimplementationandoperationoftheI-REAPsubprojectsandcoordinate
withSESUnitinconsolidatingsafeguardscomplianceandwithMandEUnitonimpact
monitoringreportfromtheP/C/MPMIUinthecoveredLGUs;
i. EnsureSEScomplianceinenterpriseprioritizationandbusinessplanpreparationby
assistingPGandP/C/MPMIU in theconductofenvironmentalandsocial screening
andassessment,conductofcommunityconsultations,preparationofEnvironmental
and Social Management Plans (ESMPs) and Relocation Action Plans (RAPs), and
acquisitionanddocumentationofEnvironmentalComplianceCertificate(ECC),Right
ofWay (ROW)and IndigenousPeople (IP) consentandendorsement,whichever is
applicableandnecessary;
j. ProvideregularreportsontheoverallimplementationofI-REAPtoPSO;
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
17
k. Develop a system of popularizing technologies developed by DA and organize
technologyroadshowsintheprovincesasneeded;
l. Design and develop agri-fishery enterprise development information resource
system;
m. ConductcapabilitybuildingneedsofP/C/MPMIUsandPGs;
n. PreparetheannualworkplanandbudgetforI-REAP;
o. AssistInfoACEUnitintheconductI-REAPIECactivitiesintheregion;and
p. Develop partnership agreements with agencies involved in agri-fishery business
developmentservices,extension/researchserviceproviderssuchasthefollowing:
• Regional-basedStateorPrivatestateuniversitiesandcolleges(SUCs),NGOs,
theRegionalDevelopmentCouncil’sEconomicDevelopmentCommittee(RDC-
EDC),andtheDTIRegionalOfficeand;
• RelevantNLAsincludingattachedagencies.
TheRPCOI-REAPwillbecomplementedbyatleastfour(4)businessdevelopmentstaff/team
with the following specialization: finance, marketing, technical and organizational. The
finance staff for business developmentwill provide support in developing the enterprise
budget, financial analysis, financial management system, and other finance-related
requirements; themarketing staffwill assist the enterprise in developingmarketingplan,
linking with potential buyers and develop marketing communications for the enterprise
productsand/orservices;technicalstaffshallassistinidentifyingthetechnologyrequiredfor
theenterprise and its adaption and implementation aswell as identificationof livelihood
optionsforNRMandGEFsites;andtheinstitutionalandorganizationaldevelopmentstaff
shallassistindevelopingthebusinessstructurefortheenterprise,staffingrequirement,job
descriptionandqualificationandcapacitybuildingrequirementsfortheproponentgroupand
itsproducers. Theminimumqualification for the I-REAPRPCOstaff include the following:
collegegraduateof any course related toagriculture (e.g.BSAgriculture,BSFisheries,BS
Agricultural Economics, Agribusiness Management, Agricultural Engineering etc), and
accounting,managementandengineering courses. SeeAnnex5forthesampleTermsof
Reference for the business development staff/team. Additional technical staff may be
requestedbytheRPCOdependingonthenumberofapprovedsubprojectsandthetypeof
enterprises.
3.2.5 P/C/MPMIU
AnI-REAPProvincial/City/MunicipalTeamundertheP/C/MPMIUwillbeorganizedtoperform
thefollowingfunctions:
a. Serve as Component’s management and supervision team and focal point for
coordinationofallprovincialI-REAPimplementationactivities;
b. ParticipatewiththeI-PLANComponentasleadinthereviewandpreparationofthe
PCIP;
c. SpearheadinprioritizingenterprisestargetedforI-REAPfundingbasedonthePCIP;
d. Formulatebusinessmodelorframework;
e. Conductorientationofpotentialproponentgroupandselection;
f. Assisttheproponentinthebusinessplanpreparation;
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
18
g. PackagethebusinessplanforI-REAPfunding,theEAandtheIMA;
h. Review the compliance of the required documentary requirements (Checklist of
requirements and Tracking Form) before forwarding the same to the RPCO and
checklistshallbeattachedtothetransmittaltoRPCO.
i. Developpartnershipwithagencies thatcanrenderbusinessdevelopmentservices,
researchandextensionsuchasthefollowing:
• Provincial-basedStateorPrivateSUCs,NGOs,ProvincialDevelopment
Council’s(PDC)EDC,andtheDOSTandDTIRegional/ProvincialOfficeand;
• Otherrelevantprovincial-basedNLAsincludingattachedagencies.
j. MonitortheimplementationoftheI-REAPComponentintheprovince;
k. ProvideregularreportsontheoverallimplementationofI-REAPtoRPCO;
l. ConductI-REAPIECactivitiesintheprovince;and
m. Develop capacity building proposals to strengthen the capacities of the LGUs to
providetechnology,informationandenterprisedevelopmentsupporttoagri-fishery
sectorplayers.
The Provincial/City/Municipal Agricultural Officer (PAO) is recommended to be the
P/C/MPMIUI-REAPHead.ABusinessDevelopmentTeamshallbecreatedattheLGUlevel
whowillberesponsibleinassistingtheProponentGroupsinthepreparationofthebusiness
plans,compliancetoreviewsandrequirementsandfinalizationandpackagingofthebusiness
plansincludingtherequiredattachments.I-REAPTeam.
3.3 Capability Building Program for Project Implementers
Priortoandduringimplementation,technicalassistancewillbeprovidedtotheNPCO,PSO,
RPCO, P/C/MPMIU/LGUs and to the PG to develop knowledge, skills and attitudes of the
projectimplementersandbuildtheircapacitytoimplementthePRDPactivitiesparticularly
thoseunderI-REAP.
Capabilitybuildingprogramwouldincludebutnotlimitedtothefollowingareas:
• Businessplanpreparation;
• ParticipatoryResourceAppraisal-ResourcesandSocialAssessment(PRA-RSA)
• Financialmanagement (includingestablishmentof theCFTrustAccount, simplified
financialandmanagementsystem,developmentand installationof theaccounting
system,auditandfinancialmonitoringandcontractadministration);
• Enterprisedevelopment;
• Organizationaldevelopment;
• Marketingmanagement;
• Procurement,
• Socialandenvironmentsafeguards;
• Projectmonitoringandevaluation;
• Contractmanagement;and
• Simplebookkeepingandaccounting
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
19
ThePSOtogetherwiththeRPCOwilldevelopcapability-buildingprogramsandundertakethe
conductoftheseactivitieswhichwillbefacilitatedandcoordinatedbytheP/C/MPMIU.The
PSO and RPCO may tap other national and/or regional technical agencies, private and
governmentSUCs,andprivatesectorexperts toconductcapability-buildingprogramsand
undertake supportive monitoring visits, in order to ensure timely provision of training
assistanceresponsivetotherequirementsoftheI-REAPenterprises.Thefundthatwillbe
usedintheconductofthecapabilitybuildingactivitieswillcomefromI-REAPSub-Component
3.2.
4. Implementation Procedures and Processes
Thefollowingsectionspresenttheguidelines,activities,processes,andproceduresthatwill
beundertakenintheimplementationoftheI-REAPComponent
4.1 Implementation Process of Subcomponent 3.1 (Rural Agri-fishery
Enterprise and Productivity Enhancement Support)
4.1.1 Requirements for LGU I-REAP Partners
Ingeneral,subprojectswillbeimplementedbytheparticipatingprovincialLGUs.However,in
some instances, when the case warrants, municipal or component city may directly
implementsubprojectsprovidedthattheywillbeidentifiedtohavecriticalroleinthevalue
chainupgradingoftheprioritycommodities.Theirroleshouldbespecifiedintheresultsand
findingsoftheVCA,E-VSAandinthePCIP.TheparticipatingC/MLGUshallalsobewillingto
providethecounterpartfundfortheenterpriseandiswillingtobetheprocuringentityfor
worksandgoodstobeprocuredfortheenterprise.
AparticipatingLGUmustcomplywiththefollowingrequirementsinordertoparticipateand
submitsubprojectsunderI-REAPComponent:
a) MemorandumofAgreementbetweenDAandtheLGU
b) SealofGoodHousekeeping/FinancialHousekeepingissuedbyDILG
c) ApprovedPCIP
d) CertificateofLiquidationfromconcernedDA-RFOforthePRDPI-REAPsubproject
previouslyundertakenbytheLGU.
4.1.2 Requirements for Proponent Groups
ProponentGroup/swho signified interest to implementanenterprise/subproject through
submission of Letter of Intent to the LGU shall comply with the eligibility requirements
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
20
enumeratedinTable4-1.TheeligibilityrequirementsforthePGdependontheamountof
subprojecttobeproposed.
Table4-1.EligibilityRequirementsforProponentGroupsbyAmountofSubproject
RequirementsEnablingInstrumentsbyAmountofSubproject
MicroEnterprise SmallEnterprise MediumEnterprise
Legalpersonality Maybenewlyregisteredwith
CDA/SEC
CertificateofRegistration
(SEC/CDA/DOLE)
Profileoffarmermembersand
officers
Mustbeatleastregistered
foroneyearwith
CDA/SEC/DOLE
CertificateofRegistration
(SEC/CDA/DOLE)
Profileoffarmermembers
andofficers
Mustbeatleastregisteredforthree
yearswithCDA/SEC/DOLE
CertificationofRegistration
(SEC/CDA/DOLE)
Profileoffarmermembersand
officers
CertificateofCompliance
GoodStandingforCDA
registeredorCertificateof
noDerogatoryRecordfor
SECregisteredorCertificate
ofRegistrationforDOLE
registered
CertificateofComplianceGood
StandingforCDAregisteredor
CertificateofnoDerogatoryRecord
forSECregisteredorCertificateof
RegistrationforDOLEregistered
AuthenticatedorCertified
TrueCopyofArticlesof
Incorporation/Cooperation
and
CopyofBy-Laws
AuthenticatedorCertified
TrueCopyofArticlesof
Incorporation/Cooperation
andCopyofBy-Laws
AuthenticatedorCertifiedTrueCopy
ofArticlesofIncorporation/
CooperationandCopyofBy-Laws
Financialcapability PhotocopyofOfficialReceipt
(OR)foritsfinancial
transactions
PhotocopyofOfficialReceipt
(OR)foritsfinancial
transactions
AuditedFinancialReportsforthe
Last3Years
Organizational
capability
CertifiedTrueCopyofthe
Policies,Systemsand
Procedures(PSP)areinplace.
AccomplishmentReports
andphotographsofagri-
fisheryorrelatedprojects
undertakenforatleastone
year
AccomplishmentReportsand
photographsofagri-fisheryor
relatedprojectsundertakenforat
least3years
CertificatefromtheLGUor
DAthatOfficersand
membershaveattended
basicorganizationaltraining
andtechnicaltraining
requiredoftheirsubprojects.
LGUCertificationonthe
organizationalandtechnical
capabilityofthe
PG
LGUCertificationonthe
organizational,technicaland
financialcapabilityofthePG
AffidavitofDisclosure Aswornaffidavitofthe
SecretaryoftheNGO/POthat
noneofitsincorporators,
organizers,directors,or
officialsisanagentofor
relatedbyconsanguinityor
affinityuptothefourthcivil
degreetotheofficialsofthe
governmentagency
authorizedtoprocessand/or
approvetheproposal,the
MOAandthereleaseof
funds.
Swornaffidavitofthe
SecretaryoftheNGO/POthat
noneofitsofficersare
Aswornaffidavitofthe
SecretaryoftheNGO/PO
thatnoneofits
incorporators,organizers,
directors,orofficialsisan
agentoforrelatedby
consanguinityoraffinityup
tothefourthcivildegreeto
theofficialsofthe
governmentagency
authorizedtoprocessand/or
approvetheproposal,the
MOAandthereleaseof
funds.
Swornaffidavitofthe
SecretaryoftheNGO/PO
AswornaffidavitoftheSecretaryof
theNGO/POthatnoneofits
incorporators,organizers,directors,
orofficialsisanagentoforrelated
byconsanguinityoraffinityupto
thefourthcivildegreetothe
officialsofthegovernmentagency
authorizedtoprocessand/or
approvetheproposal,theMOAand
thereleaseoffunds.
SwornaffidavitoftheSecretaryof
theNGO/POthatnoneofits
officersareemployeesoftheDAor
theimplementingLGU.
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
21
employeesoftheDAorthe
implementingLGU.
thatnoneofitsofficersare
employeesoftheDAorthe
implementingLGU.
Liquidation LGUAccountantCertificate
thatthePGhasNo
UnliquidatedAccountorCash
AdvancewiththeLGU
LGUAccountantCertificate
thatthePGhasNo
UnliquidatedAccountor
CashAdvancewiththeLGU
LGUAccountantCertificatethatthe
PGhasNoUnliquidatedAccountor
CashAdvancewiththeLGU
20% equity
requirement
Equitycouldbeallin-kindor
anycombinationofcashorin-
kind
Equitycouldbeany
combinationofcashorin-
kind
Equitycouldbeanycombinationof
cashorin-kind
The followingaretherequireddocumentaryrequirements for theequityof thePGand its
members.
Table4-1.ADocumentaryRequirementsforthePGEquity
TypeofEquity Document Remarks
Cash Bankcertificateunderthenameofthe
PG
Actual amount of cash in bank or
availablecashonhandequivalenttothe
cashequitywillberequiredbasedonthe
WFPandProcPlan
Land Forownedland:
CertificateofLandTitle
Forleaseofland:
Dependingon the infrastructure to be
build(adaptedfromCOACircular2003-
007A):
• Lease Agreement with provision
forrenewaloroptiontopurchase
(Forprivateland)
o Wood–10yearsrenewablefor
another10years
o Mixed–20yearsrenewablefor
another10years
o Concrete–30yearsrenewable
foranother20years
• UsufructAgreementwithprovision
forrenewal(Forpublicland)
In case when the land was donated or
boughtbythePGandthetransferofland
titleisstillon-going,acopyoftheDeed
ofSaleandDeedofDonationmaysuffice
forthebusinessplanapproval
Landshouldhavenoencumbrances.
Landequity shouldbe valuedbasedon
assessedvalueofthelotareathatwillbe
usedfortheenterprise
Labor/Manpower List of workers with corresponding
wageorsalaryratesorPayroll
Listwill be required based on theWFP
andProcPlan
Equipment and
materials
Latestauditedfinancialstatements Shouldbevaluedbasedonbookedvalue
4.1.3 Implementation Procedures and Process
Pre-ImplementationProcess
ThePCIPpreparedunder I-PLANwith the involvementof I-BUILDand I-REAPwill identify
prioritycommodities,productsegments/enterprisesandselectkeystakeholdersthatcould
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
22
besupportedandfundedunderI-REAPineachprovince.SeeAnnex5ofI-PLANOperations
ManualforthecontentsofthePCIP.
ThePCIPisastrategicplanthatrationalizestheinterventionswithinthevarioussegmentsof
the value chain of commodities that are of significance to the province and that will
contributetothenationalgoalsoftheagricultureandfisherysector.Itisthree-yearrolling
consensus-basedplanbetweentheDAandLGUbasedonthevaluechainanalysesofthese
commoditiesconductedwithstrongparticipationofthevariousstakeholders.ThePCIPwill
bethebasisinidentifyingpossibleenterprisesinwhichaprovincedecidestomakeapackage
ofinvestmentsthattheDAwillprovideassistance,withadequatecounterpartfromtheLGU.
Thepre-implementationprocessshowingtheresponsibleentities/unitsandthestep-bystep
proceduresfortheimplementationofI-REAPenterprises/subprojectsisshowninTable4-2.
Table4-2.SubprojectProcedures,Activities,Tools,OutputsandResponsibilityCenter
Step Procedures/
ActivityWorking
DaysTools Input Output Responsibility
Center
1.EnterprisePrioritization
Prioritizationof
possible
enterprisesper
segmentas
identifiedinthe
PCIP
2 Annex6 VCA,PCIP,
EVSAEnterprisePrioritizationresult
Lead:P/C/MPMIUSupport:RPCO
2.Formulation
ofBusiness
Model/Framework
Workshopin
theformulationofBusinessModel
2
Annex7 VCA,PCIP,EVSAandEnterprise
Prioritization
BusinessModel,
Atleastonepage
descriptionof
thebusiness
modelor
subproject
Lead:P/C/MPMIUSupport:RPCO,
PSO
3ProponentGroupSelection
a.PGSelection 2 Annex9A;
Annex9BPriority,
enterprise,
Letterof
Intentfrom thepotentialPGs w/eligibilityrequirements
Ranking of
potentialPGs,NominatedPG
Lead:P/C/MPMIUSupport:RPCO
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
23
b.Validation 2 Validation
Form
(Annex10)
Rankingof
potentialPGs,Eligibilityrequirements
ofPGs
Validation
report/
Confirmation
letter
Lead:PSO
Support:NPCORPCO
4.Preparation
ofBPor
Subproject
Proposalinc
all
attachments
andrequirements
a.1.Business
planning
workshop
a.2.Conductof
environmental
andsocial
screeningof
proposed
subproject
a.3Conductof
sitevalidation
andgeotagging
activities
7 Data
Gathering
(Annex11);
Business
Plan
Outline
(Annex12-
A);
Subproject
Proposal
(Annex12-
B)
Businessplan
outline,VCA
DraftBP
including
attachmentsand
requirements
I-REAPInitial
EvaluationForm
Lead:RPCOP/C/MPMIU,PGSupport:PSO
b.Seriesof
business
planning
sessionsand
preparationof
attachments
and
requirements
55 Checklist
andtrackingform
(Annex13-
Aand13-B)
DraftBP RevisedBPincludingattachmentsand
requirements
(IBUILD, SES,
Procurement,
Finance,GGU,M
andE,I-PLAN,M
andE)
Lead:RPCO,
P/C/MPMIU,PGSupport:PSO
c.BusinessPlan
packaging10 Business
Plan
Review
Tracking
Form
(Annex15)
RevisedBP Letterendorsement
fromLGU
Lead:P/C/MPMIU,PGSupport:RPCO
5.SubprojectReviewandAppraisal
BPtechnical
revieww/
commodity/technical
experts
2 I-REAP
Initial
Evaluation
Form
(Annex16);
Business
Planor
Proposal
Appraisal(Annex17)
RevisedBP
endorsedby
LGU
Technical review
report,BPAppraisalsheet,
SESappraisal
report
Lead:RPCO
Technical
ReviewTeam
Support:PSO
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
24
6.ComplianceReview
Review ofBPsincluding
allattachment
oncomplianceto PRDP
requirementsandcomments
5 TechnicalReviewReport,BPAppraisalSheet,RevisedBP
Compliance
ReviewReport,EndorsementLettertoRPCO
Lead:PSO
Support:RPCO
7.RPAB Approvalofthe
BP1 Final
BusinessPlan
RPABResolution RPCO
8.Issuance
ofNOLConfirmation
ofprojectimplementation
leadingtoprocurement
5 FinalBP NOL Lead:Dependsonthe
thresholdPSO,
NPCO,WB
Theestimatedtotalnumberofworkingdaystocompletethewholeprocessfromenterprise
identification to NOL Issuance 93working days or approximately 4months. The detailed
proceduresarediscussedbelow.
Step1:IdentificationandPrioritizationofProductSegment/Enterprise
The priority interventions identified in the PCIP will be the basis in the identification of
possibleproductsegmentsorenterprises.Theidentifiedproductsegmentsorenterpriseswill
beprioritizedbytheP/C/MPMIUwithguidancefromtheRPCOusingthecriteriasetinAnnex
6todeterminetheenterprise(s)thatwillundergobusinessplanpreparation.Adraftbusiness
modelfortheproposedenterprisewillbepreparedbytheP/C/MPMIUwhichwillbethebasis
ininvitingpossibleProponentGroups.
The criteria thatwill be followed in the prioritization of product segment or selection of
enterprisesareasfollows:
1. Importanceoftheproductsegment/enterpriseinthelocaleconomy(30points)
o Numberofproducersintheprovinceinvolvedassuppliersofrawmaterialsof
theproductsegment/enterprise
o Percentage of municipalities in the province involved in producing the raw
materialsoftheproductsegment/enterprise
o Numberofjobstobegeneratedbytheproductsegment/enterprise
2. Marketpotential(30points)
o Potential for value-addition of the enterprise (in terms of the number of
productsegments)
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
25
o Strongdomesticand/or internationaldemandfortheproduct(availabilityof
local markets, percentage share to total exports of agricultural products,
percentagesharetototalimportsofagriculturalproductsasimportsubstitute)
o Identifiedindustrialorcommercialbuyerwithpotentialforsupply/marketing
contract
3. Resourcebase(20points)
o Percentageshareofthecommodity/rawmaterialstothetotalagriculturalarea
oftheprovince/totallivestockpopulation
o Percentage share of the commodity/raw materials to the total agricultural
volumeofproductionoftheprovince/totalfishcatch/totallivestocktraded
4. Environmentalimpact(10points)
o Impactoftheenterprisetotheenvironment(positive,neutralornegative)
5. Women’sparticipation(includingindigenouspeople(IP))(10points)
o Percentageofwomendirectlyandindirectlyparticipatingintheenterpriseand
along thevalue chainof theenterprise including the forwardandbackward
linkages
TheYear1subprojectsoftyphoonYolanda(Hainan)andtheareasaffectedbytherecent
earthquakeinBoholareexemptedfromthisstepbecauseoftheirexemptionfromVCA
andPCIPpreparation.Itisunderstoodthattheseareaswouldneedimmediatelivelihood
support and income augmenting activities. This exemptionwas further extended to
micro-enterprise subprojects that would fall under rehabilitation or restoration
subprojectsinareasaffectedbycalamityandconflicts.
Step2:BusinessModel/FrameworkFormulation
Once theproduct segment is selected, theP/C/MPMIUassistedbyRPCOwill formulatea
businessmodel. This istoensurethatcommodityfarmerswillbenefitfromtheproposed
enterprise.
The business model will be captured in 1 to 3 pages that will cover the hereunder key
questions:
1. Whatistheproductorservicesthatcouldbeofferedbytheenterprise?
2. WhoaretheUSERs(Farmers)orDIRECTBENEFICIARIESoftheenterprise?Whoare
theBUYERS?(identifiedmarket)
3. What is the problem and gaps that the enterprise will address? What are the
opportunitiesthattheenterprisewilltakeadvantageof?
4. Whatistheuniquesellingproposition?
5. Whoarethebusinesspartners?(horizontalandverticallinkages)
6. Whatarethecostsinvolved?
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
26
7. Whataretherevenuestobegeneratedofthebusiness?(comparisonbetweenwith
orwithoutPRDPinterventions)
8. Howcanthefarmersearnfromtheenterprise?
Dataneedsforthepreparationofbusinessmodel/frameworkarefromVCA,PCIP,Socio-
EconomicProfileofanLGUandothersourcesofdataandinformation.SeeAnnex7forthe
GuideinBusinessModelFormulation.
Step3:SelectionofProponentGroupandSubmissionofLetterofIntent
The P/C/MPMIU will send letter of invitation to possible proponent group (PG) on the
prioritizedenterprisewithbriefdescriptionofthedraftbusinessmodel.Aprojectorientation
onthecontentofthedraftbusinessmodelmaybepresentedtothepotentialPGs.Thelistof
PGwillcomefromthedirectoryofproducergroupsandgroupofindustryplayersidentified
inthevaluechainandincludedinthePCIP.
TheinterestedProponentGroupwillsubmitLetterofIntent(LOI)(templateinAnnex8)with
the statement of compliance on the eligibility criteria together with the eligibility
requirementsidentifiedinTable4-2A,totheP/C/MPMIUaddressedtotheGovernor.TheLOI
will serve as the PG’s expression ofwillingness to participate or undertake the proposed
enterprise.
Step3.A:SelectionofProponentGroup
ThepossiblePGs that submitted LOIwith completeeligibility requirements (basedon the
levelof intervention)willbeevaluatedbytheP/C/MPMIUwiththeguidanceoftheRPCO
usingthefollowingcriteria(Annex9-Aand9-B9).ThehighestrankingPGwillbeselectedas
theLeadProponentwiththepossibilityofworkingwithotherproponentsascluster.
ForMicroEnterpriseSubprojects
1. Atleast15ormorefarmer/fisherfolkcurrentlyproducingthecommodity(5points)
2. Opentoinvestmentsbyenterprisesoperatingwithinprioritycommodityvaluechains
identifiedinthePCIP(5points)
O Valueofinvestment/equityoffered
3. Readinesstoworkinverticalcluster(5points)(alllevelsofPGinterventions)
O Stakeholdersparticipationatvariousphasesofthemarketingchain
O Presenceoforganizedproducer’sgroupthatsuppliesrawmaterials
4. Performancebasedonpreviousorexistingcontractswithotherfundinginstitutions
(5points)
ForSmallandMediumEnterpriseSubprojects
9ForPGwithoutpreviousorexistingcontractwithotherfundinginstitutions,ratingforcriteria1to3shouldbe
pro-ratedtoreach20points(e.g.,criteria1=7points,criteria2=6points,criteria3=7points).
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
27
1. Engagesthemostnumberofproducers(5points)
O Noofparticipatingfarmersorproducers
2. Readinesstoworkinverticalcluster(5points)
O Stakeholdersparticipationatvariousphasesofthemarketingchain
O Presenceoforganizedproducer’sgroupthatsuppliesrawmaterials
3. Opentoinvestmentsbyenterprisesoperatingwithinprioritycommodityvaluechains
identifiedinthePCIP(5points)
O Valueofinvestment/equityoffered
4. Performancebasedonpreviousorexistingcontractswithotherfundinginstitutions(5
points)
ForSEC registeredassociationswhose registration isnon-stockornon-profitorganization,
they may be eligible to be the Lead Proponent Group provided that the Articles of
Incorporationstatethattheyaremandatedtoengageinincomegeneratingactivities.
Incasesofclusteringofproponents,aLeadProponentfromamongtheproponentgroups
mustbeidentifiedwhichwillserveastheleadfirmormainproponentoftheenterprise.The
LeadProponentwillbetheauthorizedrepresentativeofthemembersofthePGinsigning
theEAwiththeLGU.TheEAwillindicatetherolesandresponsibilitiesofthePG,theLead
ProponentandtheLGUasdiscussedinthejointbusinessplan.Itwillalsoindicatethefund
allocationanditsliquidationaswellastheidentificationoftheprocuringentityforgoodsand
worksthatwillbeneededintheenterprise.AsupplementalagreementbetweentheLead
ProponentandthemembersofthePGshouldbeattachedandformanintegralpartofthe
EA.
TheLeadProponentwillbedeterminedaccordingtothefollowingcriteria:
• Abletoprovidetherequiredequityof20%ofthetotalenterprisecost
• Acceptabletoallclustermembers;
• Broadnetworkwithinthecommoditysector;
• Accesstotechnicalandfinancialresources;and
• Proventrackrecordinmanaginganorganizationandanenterprise.
Insomecasesandatacertainextent,theLGUwillonlybeallowedtobeaproponentofan
enterpriseunderALLofthefollowingconditions:
• Absenceofprivate investment in theproposedenterprise inaprovincedue to
peaceandordersituationoritissituatedinremoteareas;
• Lackofcapableproducergrouptoundertaketheproposedenterpriseduetoits
nature i.e. highly integrated along the value chain that would affect themost
numberoffarmersandfishersinthearea;and
• WillingnessoftheLGUtoinvestonspecificenterprises.
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
28
Step3.B:ProponentGroupValidationandEvaluation
The PSO shall conduct site and PG validation after the P/C/MPMIU has identified the
enterpriseandPGwhowillimplementtheenterprise.ThePSOshallissuetheConfirmation
LetterwithrecommendationstotherespectiveRPCOscopyfurnishtheNPCO.RefertoAnnex
10ValidationandScoreSheet).
TheNPCOmayassistintheconductofsitevalidationandPGevaluationaftertheP/C/MPMIU
hasidentifiedtheenterpriseandthePGwhowillimplementtheenterprise.
Step4:BusinessPlanPreparationandFinalization
Step4.A.1:ConductofTraining/WorkshoponBusinessPlanning
UponselectionofenterpriseandPG,theRPCOwillarrangeameetingtobeattendedbythe
P/C/MPMIUandtherepresentativesofthePGtodiscussthefollowing:
• Data needs for the preparation of the business plan, process of gathering data,
sourcesofdata,andtaskingofwhowillgatherpertinentdata(SeeAnnex11)forGuide
QuestionsforBusinessPlanData/InformationGathering).
• Conduct of the PRA-RSA for the set of prioritized enterprises that have significant
dependence/relationswithnaturalresourcebase
• Finalize schedules of the data gathering activities, the conduct of the business
planningtraining/workshopandPRA-RSAtraining.
TheRPCOwiththeassistanceofthePSOwillfacilitatetheconductoftheBusinessPlanning
WorkshopandassistthePGandtheP/C/MPMIUinpreparingthebusinessplan.
The participants to the Business Planning Workshop will include but not limited to the
following:
• RepresentativesofthePG;
• P/C/MPMIUHeadandI-REAPHead;
• ConcernedLGUstaff(PPDO,OPAg,OPV,etc)
• MunicipalAgricultureOfficer(MAO)ofthemunicipalitywheretheenterprisewillbe
located;
• RPCOI-REAPHead
• AMADstaff;and
• Concernedunitsoragenciesorcommodityexperts
• Industryexperts/practitioners
Theoutputoftheworkshopwillbethedraftbusinessplan(SeeAnnex12-AfortheBusiness
PlanOutlineandAnnex12-BfortheSubprojectProposalformicroenterprises).Tomaximize
resourcesandenhancethelearningexperience,two(2)groupsofproponentsofenterprises,
asapplicable,willundergoaBusinessPlanningWorkshoptogether.
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
29
Atthispoint,subprojectbaselinedatashouldbegatheredofwhichinformationwillbeused
inthepreparationoftheSubprojectProfileincludingfarmersprofile.Thedatagatheringwill
bedonejointlybytheRPCOI-REAPandRPCOMandE.Thesubprojectprofilewillbeuploaded
intheweb-basedMISwhilethefarmersprofilewillbeattachedtothebusinessplan.Guide
ingatheringthebaselinedataispresentedinAnnex13.
During thepreparationof theBusinessPlan, the termsof thebusiness arrangement (e.g.
PartnershipAgreement, LeaseAgreement, LeasePurchaseAgreement, etc.), between the
LGUandtheProponentGroupwillbethoroughlydiscussedandtheagreedtermswillform
partoftheBusinessPlan(specificallyontheoperationalplanandthefinancialsectionsofthe
businessplan).
An enterprise with infrastructure component will be proposed under I-BUILD. It will be
requiredtohaveDetailedEngineeringDesign(DED)followingtheguidelinessetintheI-BUILD
Operations Manual and should conform to the Social and Environmental Safeguards
Framework of the project. Refer to the I-BUILD Operations Manual and Integrated
EnvironmentalandSocialSafeguardsFramework(IESSF)forthechecklistofrequirementsand
procedures.
Step4-A.2:ConductofParticipatoryResourcesAppraisal-ResourcesSurveyand
Assessment(PRA-RSA)forGEFAreasandSubprojectwithNRMInterventions
TheconductofPRA-RSAshouldbuildontheresultsoftheVCA.TheNRMinterventionsfor
theprioritycommodityshouldbeidentifiedinthePCIP.Anenterprisethatwillbeestablished
inGEFareasand/orisresource-basedshouldbesubjectedtoarapidPRA-RSAofwhichNRM
interventions will be included in the business plan. (See Annex 2.A for possible NRM
interventions)
AllsubprojectsidentifiedinGEFsitesshouldhavePRA-RSA.
Theconductofenterprise-basedrapidPRA-RSAwillbejointlyconductedbytheRPCOandthe
P/C/MPMIU.Preferably,thePRA-RSAwillbeledbytheRPCO’sNRMfocalperson,actively
supportedbythePSO’sNRMSpecialist.IfcapacitytodothePRA-RSAisnotpresentatthe
RPCOlevel,thePSOhastheoptiontoengagetheservicesofaconsultanttoaugmentthe
limitationsoftheRPCO.
Theactivitiesandoperational featuresof thePRDPPRA-RSA isa simplifiedandpurposive
adaptationoftheMRDP2PRA-RSAdesign.ForalltheGEFsites,inventoryandassessmentof
thecoastalresourceswillbeconducted.
TheguideintheconductofthePRA-RSAispresentedinAnnex15.
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
30
Step4.B:BusinessPlanningSessions
Within 55 days, the PG and the P/C/MPMIU will finalize the business plan and all its
attachmentsincludingDetailedEngineeringDesignfortheinfrastructurecomponentofthe
enterprise,SocialandEnvironmentalSafeguards(SES)document/s,asapplicable,Workand
FinancialPlan (WFP),ProcurementPlan (PP),geotagpicturesof theproposed I-REAPsub-
project and its location and other supporting documents or attachments as necessary.
(PleaserefertothefollowingOperationsManualandGuidelinesforguidance:Supplemental
Guidelines for I-REAP Civil Works, IESSF for I-REAP Subprojects, Geotagging of I-REAP
Subprojects,FinancialManagementandProcurementGuidelinesforI-REAPSubprojects).
Step4.C:BusinessPlanPackaging
The business plan, the WFP, PP, and DED and SES documents will be packaged by the
P/C/MPMIUandshouldbeapprovedbytheGovernor.Uponapprovalofthesedocuments,
the P/C/MPMIUwill prepare the Endorsement Letter to be signed by the Governor. The
P/C/MPMIUshallsubmitthebusinessplanandallitsattachmentsinsoftandhardcopyto
theRPCO.SeeAnnex14AforChecklistofRequirements
Step5:SubprojectReviewandAppraisal
Upon receiptof the completepackageof thebusinessplan includingall attachmentsand
documentary requirements with letter endorsement from the Local Chief Executive, the
RPCO will convene the Technical Review Committee which will be composed of
representatives from the different units and components of PRDP, commodity experts,
industryexpertsandpractitionersandothertechnicalexpertsasmaybedeemednecessary.
ATechnicalReviewReportshallbepreparedprovidingdetailsontheessentialelementsof
thebusinessplanandthefindingsoftheTechnicalReviewCommittee.Thebusinessplanwill
beevaluatedusingtheguidequestions inAnnex12andtheSubprojectAppraisalForm in
Annex13.Basedontheevaluation,thebusinessplanwillbereturnedtotheP/C/MPMIUand
thePGforrevisionandcompliancetofindings.ThedulyaccomplishedSubprojectAppraisal
Form(Annex15),checklistandrecommendationstorevisedbusinessplanshallbeforwarded
LGUforcompliancetothetechnicalReport.Abusinessplantrackingformshouldbeprepared
tokeeptrackofcommentsandcompliances(Annex16).
Step6:ComplianceReviewReport
ThePSOwillconductComplianceReviewonthesubmittedrevisedbusinessplanincludingall
attachmentstocheckitscompliancestoPRDPrequirementsandthecommentsandfindings
in the Technical Review. Depending on the review of the PSO, the business plan will be
returnedtotheRPCOforrevisionandcomplianceoftheP/C/MPMIUandthePG.However,
ifthereviewissatisfactory,therevisedbusinessplantogetherwiththeComplianceReview
ReportwillbeendorsedtotheRPCOfortheschedulingofRPABdeliberation.
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
31
Step7:RPABApproval
Uponapproval,theRPCOservingasthesecretariatoftheRPABwillpreparethe‘Noticeof
Approval’andtheRPABResolutiontobesenttotheP/C/MPMIU.Thiswillbethebasisfor
thepreparationoftheIMA.
A template for the preparation of the IMA is shown in Annex 17.A for subproject with
EnterpriseDevelopmentonlyand14.BforEnterpriseDevelopmentwithCivilWorks.
Step8:IssuanceofNOL
ThefollowingthresholdwillbefollowedfortheissuanceofNoObjectionLetter.
NOL1IssuingOffice Threshold
PSOLuzonA
Allsubprojectswithtotalenterpriseprojectcost
notmorethanUS$300,000.00
PSO (Luzon B and
Visayas)
LP+GOPamountofthetotalenterpriseproject
costnotexceedingPhP5Million
Mindanao Allsubprojectswithtotalenterpriseprojectcost
notmorethanUS$1Million
NPCO LP+GOPamountofthetotalenterpriseproject
costabovePhP5MillionbutbelowPhP15Million
Allfirstmicro-enterprisesubprojectpercluster
WorldBank LP+GOPamountofthetotalenterpriseproject
costPhP15Millionandabove
TheNPCOatanytime,dependingontheresultoftheperformancereviewevery6months,
lift the authority given to the PSOs in the issuance of NOL for start-up and upgrading/
expansionsubprojects.
Step9:SigningoftheIMAamongPSO,RPCOandLGUandthePreparationofEAbetween
theLGUandthePG
Step9.A:SigningoftheImplementationManagementAgreement(IMA)
UponissuanceofNOL,theRPCOwillprovidecopyoftheNOLandtheRPABResolutiontothe
LGU.TheP/C/MPMIUwillproceedtothefinalizationandsigningoftheIMAwhichwillbethe
basisinthepreparationoftheEA.OnlyoneIMAwillbepreparedforI-REAPsubproject.The
LGUwillprepareandendorsetheIMAtotheRPCO,whichwillthenendorsethesametothe
PSO, with the following documents: a) Sangguniang Panlalawigan/Panlungsod/Bayan
ResolutionAuthorizingtheLocalChiefExecutivetosigntheIMA;b)AppropriationOrdinance
for the LGU equity; c) Approved business plan; d) ApprovedDED and POW; e) Approved
ProcurementPlan;f)ApprovedWorkandFinancialPlan;ande)NOL.
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
32
TheLGUmayalsoincludeintheendorsementofthesignedIMA,therequestfortheissuance
ofCertificateastoAvailabilityofFund(CAF).
UponreceiptoftheIMAandtherequestforCAF,theRPCOwillreviewandsigntheIMAand
endorsethesametothePSO.
ThePSOwillreviewtheIMAandsignthesame.ThePSOwillalsoreviewtherequirementsfor
theissuanceofCAFandiffoundthedocumentsinorder,willprocesstheissuanceofCAF.
ThePSOthroughtheRPCOwillprovidethesignedIMAandtheCAFtotheLGU.
Step9.B:SigningoftheEnterpriseInvestmentAgreement(EA)
After finalizingand signing the IMA, thedraft EAwill be finalizedby theP/C/MPMIUand
endorsedtotheRPCOforreviewandapproval.SampleEAisshowninAnnex18.Uponreview
andapprovalof theRPCO,theEAwillbeforwardedtotheGovernor forhisapprovaland
signature.
Step10:ProcessingandReleaseoftheEPF
The PSOwill release the Enterprise Project Fund to the LGU at least two tranches or as
providedintheIMAbasedontherequirementsoftheenterpriseasstipulatedinthebusiness
plans,procurementplanandworkand financialplan (WFP).For the infrastructureorcivil
workscomponentoftheenterprise,thefundreleaseswillfollowtheI-BUILDprocess(Refer
toI-BUILDOperationsManualandFinancialManagementGuidelinesfortheprocedures).
Formicro-enterprise subprojectswithone-itemor single itemprocurement, fundmaybe
releasedtotheLGUusingonetrancheonly.TheWorkandFinancialPlanwillbethebasisin
thefundreleases.
TherequirementsforthereleaseoffundtotheLGUareasfollows:
a. RequirementforIssuanceofCertificateastoAvailabilityofFund(CAF)
1. Approved,signedandnotarizedIMAbetweenthePSOandLGU
b. ForInitialRelease
a. Approved,signedandnotarizedIMAbetweenthePSO,RPCOandLGU
b. AppropriationOrdinancefortheLGUequity
c. CAF
d. ApprovedProgramofWork,ProcurementPlanandWorkandFinancialPlan
e. LetterfromLCErequestingRPCOforthereleaseoffundsinaccordancewiththe
IMA
f. BankcertificationfortheopeningofaccountsofLoanand/orGrantProceedsand
GOPCounterpart
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
33
g. BankcertificationofLGUequityreflectingfulldeposit(100%)ofequityshareinthe
enterprise
h. EndorsementbyRPCOtothePSOontherequestofLGUforthereleaseoffunds
c. ForSucceedingandFinalRelease
a. LetterfromLCErequestingforthereleaseoffunds
b. SubmissionofSREfortheliquidationofatleast70%ofthepreviousrelease
c. Certifiedcopiesofsupportingdocuments
d. Geotaggedphotosofaccomplishments
e. ValidatedrequiredaccomplishmentreportasstatedintheIMAandEA
f. EndorsementfromRPCOtothePSOontherequestofLGUforthereleaseoffunds.
ThePSOuponprocessingofthefirsttranchewillissueacheckorletterofadviceandtransfer
thefundinthenameoftheLGUforPRDPSubProjectTrustAccountbasedontheoriginal
copy of Bank certification submitted by LGU. The LGU will issue its Official Receipt or
ConfirmationLetterorAcknowledgementReceiptwithinthree(3)daysuponconfirmation
thatfundshadbeencredited.
ThefinancingmixforI-REAPfundingisshowninTable4-3.
Table4-3.FinancingMixforI-REAPFunding
WB-Loan
Proceeds(LP)
GoP–DA GEF LGU
Counterpart
Total
Enterprise
Project
Cost
60% 20% 0 20%
Total
Enterprise
Project
Cost-GEF
0 0 80% 20%
ThetotalEPCisnetofthe20%PGequityfromthetotalinvestmentcost.ThePGequitymaybe
intheformofcashand/orinkindsuchasland,labor,equipmentandmaterials,amongothers.
Thelandequityshouldhavenoencumbrances.
IncaseofGEFidentifiedenterprise,thefinancingmixis80%oftotalEPC-GEFand20%from
the LGU as equity. Types of activities applicable for GEF financing would include
implementation support for improved conservation, technical training, awareness-raising,
andknowledgesharing.RefertoGuidelinesintheImplementationofGEF-fundedSubprojects
fortheproceduresandrequirements.
TheLGUshallprovidetherequired20%LGUcounterpart.
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
34
Step11:ReleaseofI-REAPfundfromtheLGUtothePG
TheLeadProponentwillopenaseparatebankaccount,preferablycurrentaccounttoany
governmentorcommercialbanks,butpreferablyLandBankofthePhilippines,fortheI-REAP
fund.TheLGUwillreleasethefundsbasedontheapprovedWFPasstatedintheEA,upon
submissionofthefollowingrequirements.
1 Approved,signedandnotarizedEAbetweentheLGUandthePG;
2 ApprovedWorkandFinancialPlan(WFP);
3 BankcertificationoftheBankAccountinthenameofPG;
4 DocumentshowingthatPGhasequityequivalenttotwentypercent(20%)ofthetotal
incrementalenterprisecost.Forcashequity,bankcertificationreflectingtheamount
ofequitydeposit.Incaseofequityinkind,suchasland,buildingorequipment,the
valuationshouldbebasedonbookvalue;
5 Certified photocopyof the PurchaseOrder/MarketingAgreement/Contract for the
releaseoftradingcapital,asappropriate.
Step12:ImplementationoftheProposedEnterprise
TheP/C/MPMIU in coordinationwith theRPCOwill conductpre-implementationmeeting
withPGanditsmembers
The PG will implement the enterprise as detailed in theWork and Financial Plan of the
approvedbusinessplan.
TheP/C/MPMIUwillconductregularmonthlymonitoringandreportingoftheprogressofthe
enterprise implementationtotheRPCO.TheRPCOwillprocessthereportandsubmit the
processeddatatothePSO.ThePSOwillconsolidatethereportssubmittedbythedifferent
RPCOandwillsubmittheprogressreporttotheNPCO.
Uponliquidationofthe70%ofthefundpreviouslydownloadedtothePG,itcanrequestthe
releaseofthesucceedingorfinaltranche.
Step13:SubmissionofCompletionReportbytheP/C/MPMIU
After the full release (100%) of the EPF to the LGU and the PG and completion of the
subproject implementationasstatedintheWFP,theP/C/MPMIUwillnotify inwritingthe
RPCOthatthesubprojecthasbeencompleted.TheRPCOwillmobilizetheJointInspection
TeamwhichshallbecomposedofrepresentativesfromthePSOandRPCOI-REAP,I-BUILD
(when there is civilworks),GGU,Procurement and SES to validate the completionof the
subproject.
Step14:TurnOveroftheCompletedSubprojecttothePG
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
35
Uponsubmissionof reportof the Joint InspectionTeamandwithsatisfactory remarkand
acceptanceof completedsubprojectby theRPCO, theLGUshall turnover thecompleted
subprojecttothePG.Theturnovershallincludeallgoodsandworksprocuredandfunded
byPRDP.ACertificateofTurnOverwillbeissuedbytheLGUtothePG.
4.1.3.1 Implementation of I-REAP Subprojects in Areas Affected by Natural
Calamities and Conflict
PRDPwouldpayspecialattentiontothoseareasaffectedbytoareasaffectedbyTyphoon
Yolanda(Haiyan)andtheearthquakeinBoholduringthefirstyearofprojectimplementation
(SeeAnnexAforthe list).Thetypesofenterprisesandinfrastructuretobesupportedare
flexibleintheseaffectedareassuchthatitwillspecificallytargetthegaps.Forexamplesmall-
scalefarmersandfisherswhohavelostproductiveassets(boats,coconuttrees,etc.,)coconut
nurserydevelopmentlinkedwithreplantingbygroupsofsmall-scalefarmersorboatbuilding
linked to fisheries or seaweed production, among others. Annex 20 provides for the
supplementalguidelinesintheimplementationofI-REAPsubprojectsintheaffectedareas.
I-REAPsubprojectsinareasaffectedbytyphoonHaiyanandtheearthquakeinBoholwere
eligible for support without necessarily being alignedwith PCIPs. This exemptionwas
furtherextendedtoaffectedfarmersandfishersofthesubsequentnaturaldisasterssuch
astyphoonLandoandNonain2015.
Itwasagreedthatallnewenterprisesubprojects,includingmicro-enterprisesshouldbe
basedonVCAsandalignedwithprioritiesofthePCIPs.However,formicro-enterprises
thathavealreadypassedRegionalProjectAdvisoryBoard(RPAB)Approval,processingcan
continue. In addition, recognizing the fact that PRDP has established considerable
capacity,robustmechanismsandproceduresthroughwhichtheDAcanrespondtofuture
declareddisastersandcalamities,amaximumofUS$9Million (10%)of theLoanFunds
allocatedtoSub-component3.1canbeused insuchcasesformicroenterprises (PhP1
Million below),without the need for their alignmentwith priorities established in the
PCIPs.
4.1.4 Private Sector Partnership with the Proponent Group
The P/C/MPMIU in its efforts to increase the integration of smallholder producers in
performing remunerative value chains may develop and implement productive alliances
between smallholders and the private sector aimed at improving market access of the
producersgroupinthearea.Inthiscase,theP/C/MPMIUwillinviteprivatesectorasbusiness
partnersinprovidingsupportservicestotheidentifiedproducersgroup.Thisistrueforvalue
chainor subprojects thatarehighly integrated suchas cacao, coffee,geonet,andpoultry
amongothers.Thecriteriaforselectingprivatesectorpartnercouldincludethefollowing:
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
36
• Committed to enter into marketing contract or buy back agreement with the
producersgroup
• Willundertaketechnologytransferontheprovidedgoodsand/orservices
• Financialandorganizationalcapabilitytoundertaketheproposedenterprise
• Established actual experience in undertaking or implementing the proposed
enterprise
ThebasisforinvitingoracceptingtheparticipationoftheprivatesectoristhePCIPproposed
interventions. Specifically private sectors are expected to complement the proposed
interventionswithnoexistingvaluechainplayersorstakeholders.Examplesincludeinvestors
orcompanieswillingtoputupprimaryorsecondaryprocessingfacilitiesandwouldrequire
localrawmaterials(e.g.fermentedcacaobeansasingredientforchocolate).Otherexamples
are companies thatwill add local investments in product or technology innovations (e.g.
coconutfiberasrawmaterialforrubberizedmat).
The private sector, with its available advance technology and who needs quality raw
materials,willforgeagreementwiththeLGUinbehalfoftheproponentgroup.Theprivate
sectorshouldalsobeidentifiedtohavecriticalroleinthecommodityvaluechainandcould
provide technical assistance to thePGsand serveasmarket /buyerof the rawmaterials
producebyfarmers.
PrivatesectorsinvitedbytheproponentLGUmustsubmitinvestmentproposalsbasedonthe
enterpriseidentifiedandthefollowingrequirements:
a. MustberegisteredunderPhilippineLawsforatleast5years(SECregistration
asstockcorporationwithCertificateofGoodStanding)
b. Musthaveequityinvestmentofatleast50%ofthetotalprojectcost
c. Proofoffinancialstabilitywiththreeyearsauditedfinancialreports
d. Companyprofile
e. Certification from government or non-government organizations on the
performanceoftheprojectscompletedorpartnershipwithindustrysectorfor
thepastthreeyears
TheP/C/MPMIUtogetherwithRPCOwillevaluatethesubmittedinvestmentproposalswith
considerationsontheconsistencytotheVCAfindingsandtheE-VSAresultforthelocationof
theproposedinvestments.TheproposalwillthenbesubmittedtothePSOforfurtherreview
onthecomplianceswithPRDPrequirementsandendorsethesametotheNPCOandWBfor
issuanceofNOL.
4.2 GEF Supported Activities
4.2.1 Pre-Implementation
Amorepurposivepre-implementationprocesswasconductedforidentifyingtheGEFsites.
Thisfeaturewasmainlytoensurethatthesiteshavebothsignificanceintermsofthepriority
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
37
commodity in the region and province, and the level of biodiversity. As part of the pre-
implementationprocess,theDAandDA-BFARcreatedalistofcandidatesitesthatarelisted
aspriorityconservationareas,andhavebeenidentifiedbyDA-BFARaskeymarineandcoastal
resourceproductionareas.Theinitiallistofcandidatesiteswerefurthertrimmeddownbased
onspecifictechnicalandoperationalconsiderations.
ThefollowingarethefinalGEFsitesforPRDP:
a. TayabasBayinQuezonProvince(Region4A),
b. GuimarasStrait,GuimarasProvince(Region6),
c. GuiuanCoast,EasternSamarProvince(Region8),
d. DanajonBank,BoholProvince(Region7),
e. Donsol-Ticao-BuriasPass,SorsogonandMasbateProvinces(Region5),
f. GreenIslandBay,PalawanProvince(Region4B).
All of these project sites have been listed as priority conservation areas in the National
BiodiversityStrategyandActionPlan(NBSAP)andfurtherlistedaskeymarinebiodiversity
areas by the International Union for Conservation of Nature (IUCN), Conservation
International(CI),andDENR.TheDA-BFARalsorecognizesthesesitesasmajorcoastaland
fisheryresourceareas.Theseareaspossessgloballythreatenedspeciesthatarecategorized
undertheIUCNRedListascriticallyendangered(CE),endangered(EN)orvulnerable(VU).
Threatstothesesixsitesrangefromunsustainablefarmingandfishingpracticesresultingin
soilerosionandsiltationofcoastalzones,illegalfishing,over-fishingandover-exploitationof
resources.Climatechangeisexpectedtocontributetothesethreatsandnegativeimpacts,
as coastalanduplandcommunitieshave limitedcopingandadaptationcapacities.Within
eachGEFtargetarea,theGEFfinancedactivitieswillbeconcentratedincloseproximityto
PRDPareaswherethereisacommodityvaluechaininordertobetterintegratesustainable
ecosystemmanagement.Hence,MPAswouldbeselectedforGEFfinancingbasedontheir
distance fromPRDPareas, theirglobalbiological significanceandwhere localdemand for
improvedmanagementeffectivenessishigh.
GEF supported activitieswould be integrated into the components of I-PLAN and I-REAP.
Identification of NRM and conservation activities in the GEF sites will follow the normal
prioritizingandplanningproceduresoftheI-REAPcomponent.Thus,thetypesofactivities
supportedateachGEFtargetareawouldbeadaptablebasedonregionalandlocalneeds,as
contained in the PCIP and specified in the business plan. The types of supportwould be
catalytic in terms of ensuring that biodiversity conservation and coastal resources co-
management arrangements are included in thedeterminationof interventionsneeded to
supportcommodityvaluechains.
Through theseGEF-supported activities,measureswill be taken to protect or restore the
componentsofbiodiversitythatcontributetoecosystemfunctioningandlocaldevelopment.
ThetypesofactivitiessupportedateachGEFtargetsitewillbeadaptablebasedonregional
andlocalneeds.Specificactivitieswillbeselectedatthesitelevelbasedontheinformation
generatedbytheVCA,PRA-RSA,andGEFTrackingTools.
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
38
Subcomponent3.1:Rural Agri-fishery Enterprise, Productivity and Sustainability
Enhancement
Thetypesofsupportavailabletoeachsitewillinclude:
1. EnhancementofTechnicalandOperationalCapacitiesofStakeholders-Trainingfor
smallholder farmer and fisher groups on natural resources management and
conservation strategies such as Participatory Resource Assessment (PRA) on
mangrove,sea-grassandcoralreefecosystemthatarecriticalhabitatstoendangered
marineorganisms;
2. Strategic Awareness Campaigns - These campaigns will focus on biodiversity
conservation,fisheriesmanagementandcoastalresourcemanagementissues;
3. Facilitating Stakeholders to Pursue Co-management Arrangements - Support for
facilitatingandbuildingpartnershipsbetweencommunity/producergroups,market
stakeholders,andlocalgovernments.Consultationsandorganizationaldevelopment
building activities will lead to co-management arrangements over key coastal
resources. These co-management arrangements will increase the likelihood for
sustainabilityandensureintegrativeattentiononconservationandproperresources
managementandutilization;
4. ConservationImplementationInvestments-Examplesofpotentialactivitiesinclude
coastal andmarinehabitat restoration; providing enhanced enforcement capacity;
equipmentandfinancingrequiredforenhanceMPAmanagement;
5. Coastal and Marine Ecosystem Management Implementation - Assisting with the
implementation of strengthened local policy frameworks for improving local
conservationofvitalresourcesinconjunctionwiththecommodityvaluechain.
Subcomponent3.2:TechnologyandInformationforEnterpriseandMarketDevelopment
ThisGEFsupportwillprovideknowledgeandexperiencesharingofgoodpracticesamong
stakeholders. This project will contribute to the IW: LEARN knowledge sharing platform
throughtheestablishmentofaprojectwebsitefollowingIW:LEARNguidelines,participation
intheGEFIWbiennialconferences,andsharingofexperienceswithatleasttwoExperience
Notes. Specificactivitieswill includeagro-forestry;nurseryestablishment;marinehabitat
restoration techniques for mangrove, seagrass and coral reefs, promotion of Sloping
Agricultural LandTechnology (SALT).Moreover,GoodAquaculturePractices (GAP)will be
appliedsuchasenhancementof seedqualityand improvementof stockingpractices,and
habitatmanagementandbio-security.
GEFActivitiesImplementation
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
39
TheimplementationofGEFsupportedactivitieswillfollowtheGuidelinesforImplementing
GEF-FundedSubprojects
PhilippineRuralDevelopmentProgramOperationsManual
I-REAPComponent
40
ThetotalareacoveredbytheMPAsinthetargetedsitesisabout14,000hectares.AlltheMPAswereestablishedthroughlocalgovernment
ordinancesfollowingtheproceduresundertheFisheriesCode(RA8550).AllMPAsareclassifiedasIUCNCategory-6MPAs(LocallyManaged
MPA).
Target
Sites
Municipalities TriggerSpecies Bio-
Geographic
Zone/LME
MPAs(overallMETT
score)
GEFSupportedActivities
Tayabas
Bay,
Quezon
R.4-A
Sariaya,
Lucena,Pitogo,
Unisan,
Agdangan,
Gen.
Luna,
Macalelon,
Mulanay,San
Francisco,
Catanauan,
Pagbilao,Padre
Burgos
Hawksbill Turtle
Eretmochelysimbricata(CR);
GreenSeaTurtleCheloniamydas
(EN);
Olive-ridley'sTurtle
Lepidochelysolivacea(EN);
Cantherellusnoumea(EN);
Catalaphylliajardinae(VU);
Gonioporaburgosi(VU)(EN)
TayabasBay • BahurangSilag
MarineSanctuary
(37%)
• SanRoqueReefFish
Sanctuary
(75%)
• PadreBurgosFish
Sanctuary(54%)
Component1.1
• PRA-SRA,VSA,VCA,METT,
MEAT,MSPandTNAas
preliminaryactivitiestocritically
assesstheprioritysitesand
subsequentlybeusedinregional
planningprocesses.
Component3.1.
• Enhancementoftechnicaland
operationalcapacitiesof
stakeholdersincludingconduct
ofParticipatoryResource
Assessment(PRA),onmangrove,
sea-grassandcoralreef
ecosystemthatarecritical
habitatsto
Ticao
Pass,
Masbate
and
Sorsogon,
R.5
PioDuran,Ligao;
Magallanes,
Bulan,Castilla,
Donsol,
Pilar(Sorsogon);
Monreal,San
Jacinto
(Masbate).
WhalesharkRhincodontypus(VU);
HammerheadSharks(VU);
Extensivemangrove,seagrassand
coralreefecosystem
Burias and Ticao
PassandSan
Bernardino
Strait
• ButagBayFish
Sanctuaryand
MarineReserve
(49%)
• PilarMarineFishery
Reserveand
Sanctuary(43%)
• MagallanesFishand
Marine
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
41
Sanctuary(20%)
• MatnogMarine
Reserve(27%)
• SanFernandoFish
Sanctuaryand
MarineReserve
(18%)
Southeast
Iloilo,
Guimaras
andIloilo,
Buenavista,
San Lorenzo,
Sibunag,
Jordan,Nueva
Valencia
HawksbillTurtle
Eretmochelysimbricata
(CR);
GreenSeaTurtleChelonia
Sulu Sea in the
South and
VisayanSeainthe
• PamanculanFish
Sanctuary(53%)
• LawiMarineResrve
andFish
Sanctuary(54%)
• ToyoReefFish
Sanctuary(54%)
R.6
(GuimarasIs.);
Dumangas,
Leganes,Iloilo,
Oton(Iloilo)
mydas(EN);
WhitefinTopeShark
Hemitriakisleucoperiptera(EN);
Camptostemonphilippinense
(EN);
White-spotted Guitarfish
Rhynchobatusaustraliae(VU);
DugongDugongdugon(VU);
Avicenniarumphiana(VU);
North ·TumalintinanPoint
FishSanctuary
(60%)
endangeredmarine
organisms;
• Strategic awareness campaigns
activitiesfocusedonbiodiversity
conservation,fisheries
managementandcoastalresource
managementissues;
• Facilitating Comanagement
arrangements and building
PhilippineRuralDevelopmentProgramOperationsManual
I-REAPComponent
42
partnerships, including
organizational
development
• Provision of conservation
implementationinvestmentssuch
as coastal and marine habitat
restoration and enforcement for
enhancingMPA
management;
• Strengthening local policy
frameworksfor
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
43
Green
Island,
Palawan
Region4-B
Roxas (Green
IslandBay),
HawksbillTurtle
Eretmochelysimbricata
(CR);
GiantClamTridacnagigas
(EN); GreenSea Turtle
Cheloniamydas(EN);
LoggerheadTurtle
Carettacaretta(EN);
HumpheadWrasse
Cheilinusundulatus(EN);
White-spotted Guitarfish
Rhynchobatusaustraliae (VU);
LeopardShark
Stegostomafasciatum(VU);
DugongDugongdugon(VU);
SuluSea • CaramayMPA(44%)
• JohnsonIslandMPA(45%)
• MalcampoMPA(56%)
• RizalMPA(57%)
• SanMiguelMPA(29%)
• TinitianMPA(38%)
• TumarbongMPA(79%)
Danajon
Bank,
Cebu,R.7,
Ubay, Pres. C.
Garcia, Jetafe,
Inabanga,
HumpheadWrasse
Cheilinusundulatus(EN);
Barbour's
CamotesSea • AguiningMarineSanctuary
(55%)
• AsinanReefFishSanctuary
(33%)
• BatasanMarineSanctuary
(76%)
PhilippineRuralDevelopmentProgramOperationsManual
I-REAPComponent
44
Buenavista,
Talibon, Clarin,
Tubigon, Calape,
Loon,BienUnido,
Trinidad,Banacon
Island
SeahorseHippocampusbarbouri
(VU);
HumpbackGrouper
Cromileptesaltivelis(VU);
Spotted
SeahorseHippocampuskuda
(VU);
Hippocampuscomes(VU);
H.spinossisimus(VU);
H.trimaculatus(VU);
Acroporaloisetteae(VU);
Acroporahoeksemai(VU);
Nemenzophylliasp.;
ChineseEgret
Egrettaeulophotes(EN).
• Bilang-bilanganmarineSanctuary
(69%)
• CatabanMarineSanctuary(65%)
• CuamingMarineSanctuary(83%)
• GuindacanMarineSanctuary
(35%)
• HambonganMarineSanctuary
(50%)
• HandumonMarineSanctuary
(54%)
• HingotananWestMarine
Sanctuary(65%)
• JandayanMarineSanctuary(29%)
• PangapasanMarineSanctuary
(29%)
• SidakanMarineSanctuary(79%)
• SinandiganMarineSanctuary
(71%)
improvinglocal
conservationofvital
resourcesinconjunction
withthecommodity
valuechain.
Component3.2.
· Knowledgegeneration
andsharingofbest
practicesthrough
websiteestablishment
ondifferent
technologiesused,
lessonslearnedand
experiences.
Guian
Coast,
Eastern
Samar,
R.8
Salcedo,Guiuan,
Gen. MacArthur,
Giporlos,Hernani,
Mercedes,
Quinapondan
HawksbillTurtle
Eretmochelysimbricata
(CR);
LeatherbackTurtle
Dermochelyscoriacea(CR);
Green Sea Turtle
Cheloniamydas(EN);
Smooth Giant Clam
Tridacnaderasa(VU);
PacificOcean • BagonbanuaMarineReserveand
Sanctuary(55%)
• BalangigaReefFishSanctuary
(33%)
• BaolIslandMarineReserveand
FishSanctuary(76%)
• BinabasalanIslandMarine
Sanctuary(69%)
• BolusaoFishSanctuary(65%)
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
45
Montiporasamarensis(VU)
• CanigaranFishSanctuary(83%)
• CabuohanFishSanctuary(35%)
• CanticanIslandSanctuary(50%)
• Can-usodFishSanctuary(54%)
• Guinob-anFishSanctuary(65%)
• LupakonandBilangbilangReefs
MarineSanctuary(29%)
• MaglutoReefFishSanctuary(29%)
• ManapagReefSanctuary(79%)
• MantampokIsletMarine
Sanctuary(71%)
• MaslogFishSanctuary(65%)
• MinonbonanReefMarine
Sanctuary(65%)
• MonbonFishSanctuary(63%)
• PanoloytoyonReefMarine
Sanctuary(57%)
PhilippineRuralDevelopmentProgramOperationsManual
I-REAPComponent
46
Figure4-1.ProcessFlowforI-REAPImplementation:Sub-component3.1(RuralAgri-fisheryEnterpriseandProductivityEnhancement)
PROPONENT P/C/MPMIU RPCO PSO RPAB NPCO WORLDBANK
Technical
ReviewReport
10.Compliance
Reviewand/orNOL
issuanceforall
micro-enterprise
subprojectsandall
othertypesofSPs
withinitsthreshold
(2workingdays)
1.ConductEnterprise
Prioritization(2working
days)
3.InvitePossiblePG
7.BusinessPlanning
WorkshopIncludingPRA-
RSAActivities,ifapplicable
(7workingdays)
5.ProponentGroup
Selection(2workingdays)
9.Subproject
Reviewand
Appraisal
(2 working
days)
11.RPAB
Approval(2
working
days)
Confirmation
Letter
12.NOL
Issuancefor
alltypesof
SPswith
grantamount
of(LP+GOP)
oftotal
enterprise
projectcost
abovePhp5
Mbutless
Php15M
(2working
days)
NOL
A PCIP
2.Business
Model/Framework
Formulation (2working
days)
8.BusinessPlan
Preparation,Review,
Revisions,and
Packaging(45
workingdays)
6.PG
Validation
(2working
days)
RPAB
Resolution
Compliance
Report NOL B
12.WBtoissue
NOLfor:First
Subprojectper
Clusterandall
othertypesof
SPwithgrant
amount
(LP+GOP)of
thetotal
enterprise
projectcost
Php15Mand
above(7
workingdays)
4.Submit
letterofIntent
andEligibility
Requirements
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
47
PROPONENT P/C/MPMIU RPCO PSO RPAB NPCO WORLDBANK
B
15.Review
andSignIMA
andprocess
CAF(2
workingdays)
PLGU/PG can
start preparatory
activities for
procurement of
goods/works
13. Finalization and
SigningofIMAbythe
Governor and
preparation for
request for CAF (5
workingdays)
17. Sign EA
(2working
days)
22.Implement
theSubproject
MonthlyProgressMonitoringand/orGeo-taggingofEnterpriseImplementation
14.Review
andSign
IMA(2
working
days)
21. Process and
Release First Tranche
toPG(5workingdays)
18.Submit to RPCO
RequestforReleaseof
First Tranche (3
workingdays)
16. Finalize and
Sign EA
(2workingdays)
19.EndorseRequestof
LGUforReleaseofFirst
Tranche (3 working
days)
SignedIMA
SignedIMAby
PSO
CAF
Issued
20.Processand
ReleaseFirst
Tranche(3working
days)
C
PhilippineRuralDevelopmentProgramOperationsManual
I-REAPComponent
48
ProponentPLGU/
PPMIURPCO RPAB PSO NPCO WORLDBANK
Process and Release
Succeeding Tranche
totheLGU(5working
days)
MonthlyProgressMonitoringand/orGeo-taggingofEnterpriseImplementation
Submit Liquidation
Report for First
Tranche and Request
for Succeeding
Tranche to PSO
through the RPCO (5
workingdays)
PG to Liquidate
First Tranche
and Submit
Request for
Release of
Succeeding
Tranche
Process and Release
Succeeding Tranche
tothePG(5working
days)
Continue
Subproject
Implementation
based on
Approved Work
andFinancialPlan
13. Submission of
Subproject
CompletionReportto
RPCO and Turn-Over
ofSubprojecttoPG
14. Inspection of Completed
SubprojectbytheRPCOandPSO
JointInspectionTeam
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
49
4.2.2 Implementation Process for I-REAP Subcomponent 3.2 (Technology
and Information for Enterprise and Market Development)
Thiscomponentwillbeavailedofonthebasisofaproposalstatingthetypeoftrainingand
consultancyservicesandthedesiredresultsoftheseactivities.Theproposalmayoriginate
fromtheRPCOs,PSOsandNPCO.ThiswouldcomplementtheenterprisesupportunderSub-
component3.1byassistingsmall-scaleproducergroupsacrossthecountrytoincreasetheir
productivityandincomesthroughimprovedtechnologicalandoperationalknowledge,along
withincreasedawarenessofmarketrequirements,opportunitiesandfacilitationofmarket
linkages.Aparticularfocuswouldbeonpromotingandfacilitating"demand-side"linkages
withagro-processors,marketingagents,exporters,etc.
Activitiestobesupported,primarilythroughtechnicalassistancewouldinclude:
(i) showcasingexperiencesgainedfrompreviousprojects in thePhilippinesandother
countriessupportingmarketdevelopmentandintegration;
(ii) trade facilitation through conduct of market matching, trial shipment of priority
productsfromproductionareastoidentifiedmarkets,andassistanceinpreparing
market contracts between producers, agro-processors, market agents, exporters,
etc.;
(iii) marketpromotionofqualityproductsthroughtradefairs,caravans,crossvisitsand
studytours;
(iv) assistance in aggregation of supply and improved handling/packaging and proper
labellingofpriorityproducts;
(v) fasterprocessingofregistrationandbusinesspermits;
(vi) partnershipandnetworkbuildingwithProducerandProcessingFederations;
(vii) Climate Field Schools providing weather-related production information to small
scaleproducers;
(viii) capability building inGAP,GMP,product standards, businessplanning, enterprise
management and operation including bookkeeping , internal control and cost
analysis;and
(ix) climate-smart agricultural and fisheries practices and technologies, such as crop
diversification,IPM,constructionofrainsheltersforcrops,anddripirrigation.
Newtechnologiesandapproacheswouldalsobeintroduced,incollaborationwithagencies
suchas theDOST, InternationalRiceResearch Institute (IRRI), andStateUniversities and
Colleges(SUCs),e.g.,promotionofprecisionagriculturedesignedtolinkclimateandweather
datasothatfarmersandfisherscanbebetter informedinmakingtimelyproductionand
marketingdecisions,varietalimprovement,etc.ThismaybecontractedbytheProvincewith
privateserviceproviders,e.g.,agro-processors,nursery/seed/fingerlingsuppliers,technical
andtrainingoutreachofStateUniversitiesorprivateorganizations.Itmayalsobeprovided
as appropriate through Program Agreements between the RPCO/PSO and specialized
DepartmentofAgricultureagencies.
50
ThedisbursementsaretobemadebyNPCO,PSOsandRPCOs.Approvalandsigningauthority
ofofficials,thenatureandamountofdisbursementsmustfollowtheapprovedWBGuidelines
of eligible expenditures and existing DA policies and procedures on approval of
disbursements.
ThestepbystepprocessinimplementingI-REAPSub-component3.2isshowninFigure4-2,
particularlyintheexecutionofaProgramContract.
Step1:IdentificationofTechnicalAssistanceRequirements/Interventions
BasedontheVCAand/orPCIP,theNPCO/PSO/RPCOshallidentifythecriticalinterventions
and technical assistance to support the enterprises or to support commodity value chain
upgrading.
Step2:PreparationofProjectProposal
Upon identificationofpartneragency, theconcernedunitNPCO/PSO/RPCOwillmeetand
discusswiththepartneragencytherequiredinterventionandwillcraftaprojectproposal
andthecorrespondingworkandfinancialplan.
ProjectproposalemanatingandforimplementationbytheRPCOshouldbesubmittedtothe
PSO for review and approval of funding. While the project proposal emanating and for
implementationby thePSOshouldbesubmitted to theNPCO for reviewandapprovalof
funding.ProjectproposalemanatingandforimplementationbytheNPCOwillbesubmitted
totheNationalProjectDirectorforapproval.
Step3:ApprovaloftheProjectProposal
ThePSO/NPCO,whicheverisappropriate,willreviewandapprovetheprojectproposaland
theworkandfinancialplan.Aletterofapprovaldulysignedbythedesignatedauthorityshall
beissuedtotherequestingparty.
Step4:PreparationofProgramContract
Theimplementingunit(NPCO/PSO/RPCO)willpreparetheProgramContractwiththepartner
agencyfortheimplementationofthetechnicalassistance.TheContractshouldprovidethe
project details, the deliverables of the contracting parties, timelines of activities, funding
requirementsandtheliquidationoffund.
Step5:DownloadFundtoPartnerAgency
UponsigningandnotarizationoftheProgramContract,theNPCO/PSO/RPCOwilldownload
thefundtothepartneragency.
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
51
Step6:ImplementationoftheActivitiesorTechnicalAssistance
Theactivitiesforrequiredtechnicalassistancewillbeimplementedbasedontheapproved
WFP. This could be jointly undertaken by the partner agency together with the
NPCO/PSO/RPCO.
Step7:ProjectMonitoringandReporting
NPCO/PSO/RPCOwillregularlymonitortheprogressoftheactivities.Thepartneragencywill
submit progress or accomplishment reports, the frequency of which is identified in the
ProgramContract.
Step8:ProjectCompletionandFundLiquidation
Upon completion of the activities based on the approvedWFP, the partner agencywill -
submitFinalReportorCompletionReporttogetherwiththefundliquidationreporttothe
NPCO/PSO/RPCO.
ActivitiesandsubprojectstobefundedunderSub-component3.2whichwillbeimplemented
solely by the NPCO/PSO/RPCO without executing a Program Contract with partner
implementingagencywillonlyneedasubmissionofWorkandFinancialPlandulysignedby
designatedauthorityandapprovedbytheNationalProjectDirector.
52
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
Figure4-2.ProcessFlowforI-REAPImplementation:Sub-component3.2(TechnologyandInformationforEnterprise
andMarketDevelopment)
NPCO/PSO/RPCOtoidentifyTechnicalAssistanceorInterventionsandPartnerAgency(SUC/OtherGovernmentAgencies/DABureaus/AAs/Units)
VCA/PCIP
CapabilityNeedAssessment
RPCOtoprepare
ProjectProposaland
WorkandFinancialPlan
(5workingdays)
NPCOReview
andApproval(5
workingdays)
YES
PreparationandSigningofProgramContractbytheImplementingUnit(NPCO/PSO/RPCO)andthePartnerAgency(30workingdays)
TransferEnterpriseSupportFundtoPartnerAgency(10workingdays)
ImplementationofActivitiesbasedontheProjectProposalandWorkandFinancialplan
NO
SubmissionofAccomplishmentandLiquidationReport
NPCO/PSOtoprepareProject
ProposalandWorkand
FinancialPlan(5working
days)
PSOReview
andApproval
(5working
days)
53
4.3 Post-Implementation
The head of the ProjectManagement Implementing Unit of the concerned LGU and the
proponent,aftercompletionofthe‘Project’implementationwillrequestfinalinspectionby
theRPCOJointInspectionTeam.”
4.3.1 Post-Project Data Collection and Establishment of Technology
Database
The Monitoring and Evaluation (M&E) unit of the P/C/MPMIU will collect post-project
implementationdata.ThedetailsondatacollectionarediscussedintheRBMEGuidelines.
ThePRDPthroughthePSOswillassisttheRegionalIntegratedAgriculturalResearchCenters
(RIARCs) in establishing and maintaining an Agriculture and Fishery Information and
Technology Database where LGU Agriculture Technicians can access downloadable
technologypackages to support future implementationofenterprise(s) in their respective
areas.
54
5. Financial Management
TheprincipalroleoftheLGUistoserveasthefundmanageroftheEPFandwillberesponsible
forthesuccessfulimplementationoftheI-REAPenterprisesintheprovince.
The total EPC will fund eligible enterprises of the PG including among others facilities,
equipment, inputs, and infrastructure needed by the enterprise. The total EPC does not
includethePGequityofat least20%(incashor inkind)ofthetotal investmentcost(See
Table5-1.).
Funds,equipmentorfacilitiestransferredtothePGforI-REAPenterprisewillbeconsidered
asinvestmentintheenterpriseandwillbegovernedbytheprovisionsoftheIMAandtheEA.
ThePGshalltakecareoftheoperationandmaintenanceofthesefacilities,equipmentand
infrastructure.
5.1 Financing Mix for I-REAP Component
EnterprisesundertheI-REAPSub-component3.1andGEFsupportedprojectswillbefinanced
following the financingmix presented below in Table 5-1 for enterprises proposed and
approvedbytheLGUforeachroundofI-REAPfundingcycle:
Table5-1.FinancingMixforI-REAPComponent
I-REAP
FinancingMix
WB-Loan
Proceeds(LP)
GoP–DA GEF LGU
Counterpart
Total
Enterprise
ProjectCost
(EPC)
60% 20% 0 20%
TotalEPC-GEF 0 0 80% 20%Note:ForPGimplementedenterprises,thefinancingmixaboveisnetof20%PGEquity(incrementalcostofthe
enterprise).PGequitymaybeintheformofcashorinkind.
TheinfrastructurecomponentoftheenterprisethatwereapprovedbytheRPABbeforeApril
28,2016will followthe financingmixstipulated in the I-BUILDOperationsManual.While
infrastructurecomponentoftheenterprisethatwereapprovedaftertheabovementioned
datewillbeincludedinthetotalenterpriseprojectcostandshallfollowtheI-REAPfinancing
mixstatedinTable5-1.
IncaseofGEFidentifiedenterprise,thefinancingmixis80%ofEPC-GEFand20%fromthe
LGUasequity.TypesofactivitiesapplicableforGEFfinancingwouldincludeimplementation
support for improved conservation, technical training, awareness-raising, and knowledge
sharing(Annex2.A).
55
5.2 Fund Establishment at the LGU
TheLGUisrequiredtoopenthree(3)separatetrustfundbankaccounts,preferablywiththe
LandBankofthePhilippines(LBP)oranyaccreditedgovernmentdepositorybanks,perfund
sourceforI-REAPimplementation.Thesaidaccountsmustbearthename:“PRDP-<Nameof
theProvince>-I-REAP/<FundSource>”.
TheLGUequitymustbeincludedintheenactedAppropriationOrdinancebytheSangguniang
Panlalawigan/Panlungsod/Bayan. Thetotalequity requirementmustbedepositedto the
PRDPTrustFundAccount–LGUEquityinthenameoftheprovincebeforereleaseoffunds
fromLPandGOPcounterpartsaretobemade.
5.3 PRDP Fund Releases to LGU
ThePSOwillreleasethecorrespondingfundstotheLGU,basedontheIMAsignedbetween
PSOandLGU.However,fundreleasestoLGUmustbeatleasttwotranchesdependingonthe
requirementoftheenterprisesasstipulatedintheapprovedWFP,businessplanandEA.In
casesofmicro-enterprisesubprojectsthatwouldrequireone-timeprocurementonly,release
ofthefundtotheLGUwillonlybedoneonce.Forinfrastructuretypeofinvestmentunder
theI-REAPcomponent,itwillfollowtheI-BUILDtrancherelease.
TherequirementsforthereleaseoftheLGUareasfollows:
A. ForInitialTrancheRelease
1. Approved, signed and notarized Implementation Management Agreement (IMA)
amongthePSO,RPCOandPLGU/CharteredCities
2. AppropriationOrdinancefortheLGUequity
3. CAF
4. ApprovedProgramofWork,ProcurementPlan,WorkandFinancialPlanandNOLfrom
theissuingoffice,asperthreshold
5. LetterfromLCErequestingRPCOforthereleaseoffundsinaccordancewiththeIMA
6. BankcertificationfortheopeningofaccountsofLoanand/orGrantProceedsandGOP
Counterpart
7. BankcertificationofLGUequityreflectingfulldeposit(100%)ofequityshareinthe
enterprise
8. EndorsementbyRPCOtothePSOontherequestofLGUforthereleaseoffunds
56
B. ForSucceedingandFinalTrancheRelease
1. LetterfromLCErequestingforthereleaseoffunds
2. SubmissionofSREfortheliquidationofatleast70%ofthepreviousrelease
3. Certifiedcopiesofsupportingdocuments
4. Geotaggedphotosofaccomplishment
4. ValidatedrequiredaccomplishmentreportasstatedintheIMAandEA
5. EndorsementfromRPCOtothePSOontherequestofLGUforthereleaseoffunds.
5.4 Fund Transfer from the LGU to the PG
5.4.1 Requirements for Fund Release
The PG will open a bank account preferably checking account with any
government/commercialbank,preferablywithLandbank,forfundsthatwillbedownloaded
bytheLGUfortheoperationoftheenterprise.
ReleaseoffundswillbebasedontheapprovedWFPattachedintheEA.Therequirements
forthereleaseoffundstothePGarethefollowing:
a. Approved,signedandnotarizedEAbetweentheLGUandthePG
b. ApprovedWFPbasedontheapprovedbusinessplan
c. BankcertificationofbankaccountinthenameofPG
d. Document showing that PG has equity equivalent to twenty percent (20%)
incrementalcostoftheenterprise.Forcashequity,bankcertificationreflectingthe
amount of equity deposit. In case of equity in kind, such as land, building or
equipment,thevaluationshouldbebasedonbookvalue.
5.4.2 Liquidation of Funds Released to PG
a. Fundutilizationreportindicatingthesummaryofexpensesandthestatusreportof
accomplishments,certifiedbytheAccountant,approvedbythePresident/Chairman
ofthePGandverifiedbytheinternalauditororequivalentofficialoftheLGU
b. Geo-taggedpicturesofimplementedenterprises
c. InspectionreportandcertificateofprojectcompletionissuedbytheLGUauthorized
representative
d. ProofofverificationbytheLGUofficialonthevalidityofthedocumentssubmittedby
thePG
e. OfficialReceipt(OR)issuedbythegrantingLGUacknowledgingreturnbythePGof
anyunutilized/excessamountofcashadvance.
f. List of equipment/ facilities/vehicles procured by the PG out of enterprise funds
indicatingitsbriefdescription,dateacquired,acquisitioncostandfinaldisposition
g. MonthlySREasLiquidationReport
57
5.5 Negative List of Funds Utilization
a. Moneymarketplacement,timedepositorotherformsofinvestment
b. Cashadvanceofanyofficialof thePGunless related to the implementationof
enterprise
c. Paymentofsalaries,honorariaoranyformofallowancesofthepersonnelofthe
LGU
d. Purchaseofsupplies,materials,equipmentandmotorvehiclesoftheLGU
e. Acquisition of assets of the PG, unless necessary for the execution of the
enterpriseandspecificallystipulatedintheEPF
f. Purchaseofweapons
g. Financingofpoliticalandreligiousactivities
h. Purchaseoffertilizer,pesticides,insecticidesandherbicides,asbestosandother
potentiallyanddangerousmaterialsandequipment
i. Chainsawsandexplosives
j. Financingofsawmills
k. Consumptionitemsorevents
l. Financingactivitiesthathaveanalternativepriorsourceofcommittedfunding
m. Financing labor and other costs that could be provided in-kind through the
membersoftheenterprise
n. Financingsalariesandwagesunless theenterprisepersonnel required ishighly
technicalorspecialized
o. Financingadministrativeexpensessuchasfuel,utilities,repairandmaintenance,
permitsandlicenses
p. Purchaseorrepairofvehiclesforgovernmentoffices
q. Salariedactivitiesthatemploychildrenunder16yearsofage
r. Financingactivitiesthatunfairlyexploitwomenormenatanyage
s. Useofmangroveorcoralreefsasbuildingmaterials
t. Purchaseoffishingboatsandotherrelatedequipmentunlessdirectlyrelatedor
neededintheenterprise
u. Purchaseofvehicleformonitoringpurposes
v. Constructionofenterprisesupportfacilitiesinprotectedareas
w. Useoffundsforpurchaseorcompensationofland
x. Constructionorrepairandbuyingofequipmentforgovernmentofficesandplaces
ofworship
y. Micro-financingactivities
z. Potablewatersystem
5.6 Provision of Working Capital
AllI-REAPsubprojectsshouldbesustainableandthePGshouldbeabletoshoulderpart
oftherecurringcostsoftheenterprise.However,aportionoftheinitialworkingcapital
maybeprovidedtothePGaspartofthesubprojectgrantforthefirstproductiononly,
58
nottoexceedPhP1Million.WorkingcapitalrequirementsforI-REAPsubprojectsmaybe
usedas roll-over fund for theoperationof theenterpriseexceptaspayment for fuel,
fertilizer, pesticide, insecticides and the like, labor expense, salaries and wages,
administrativeexpenses,utilities,repairandmaintenance,permitsandlicensesandother
coststhatcouldbeprovidedbythePGanditsmembersinkind.
Workingcapitalrequirementistheamountoffinancingabusinessenterpriseneedsto
carryoutitsday-to-dayactivities.Thisvarieswiththetypeofbusiness(e.g.production,
processing,trading)andtheproducts/servicesoffered,whichalsoaffecttosomeextent
theamountofinventoryheldandtheamountoftimeittakestopaythesuppliersandto
collectcashfromthebuyers.Theformulabelowcanbeusedincomputingthenetworking
capitalrequirement:
Networkingcapitalrequirement=AccountsReceivables+Inventory–AccountsPayable
5.7 Disbursement Procedures for Technology and Information for Enterprise
and Market Development (Sub component 3.2)
Activities/sub-projects proposed by the NPCO, PSO, RPCO and other partner agencies in
supporttoenterpriseswillbefinancedusingthefollowingfinancingmix:
Table5-2.FinancingMixforI-REAPProjects
I-REAPSub-
Component
3.2
LP GOP Total
FinancingMix 80% 20% 100%
The disbursements are to bemade by NPCO, PSOs and RPCOs as stated in the Program
ContractsignedbetweentheNPCO/PSO/RPCOandthepartneragency.Approvalandsigning
authorityofofficials,thenatureandamountofdisbursementsmustfollowtheapprovedWB
GuidelinesofeligibleexpendituresandexistingDApoliciesandproceduresonapprovalof
disbursements.
5.8 Books of Accounts and Records
TheBooksofAccountsandRecordsthatwillbeestablishedandmaintainedbytheLGUare
discussedindetailonChapter5oftheFinancialManagementGuidelines.
59
60
5.9 Financial Reports
The PG and LGU must submit monthly, quarterly and annual financial reports including
certified copies of supporting documents to the RPCO reflecting the receipts and
disbursementsoffunds.Therequiredreportsshouldbesubmittednotlaterthanthe5thday
oftheensuingmonthorquarter.
TherequiredfinancialreportstobesubmittedarepresentedinChapter6ofPRDPFinancial
ManagementGuidelines.
6. Procurement Guidelines
Procurement refers to the purchase of all the works, goods and services needed in the
establishmentandimplementationoftheenterprise.
ThePGortheLGUthruitsProcurementCommitteeorBidsandAwardsCommittee(BAC)will
beresponsibleintheprocurementprocessesunderthesupervisionoftheP/C/MPMIUand
theRPCO.
6.1 Scope
I-REAPprocurementisforworks,goodsandservicesidentifiedintheapprovedbusinessplans
andEA.ProcurementwillbeundertakenbythePGortheLGUfollowingtheproceduresas
definedintheWorldBankProcurementGuidelinesandtheProjectProcurementGuidelines.
6.2 Procurement Arrangement under the I-REAP Component
Upon approval of the proposed subproject (Business Plan, Work and Financial Plan,
Procurement Plan, Detailed Engineering Design, Program ofWork, O &M Plan, geo-
taggeddocumentsandthebiddingdocuments)thenoobjection1(NOL1)shallbeissued
whichsignalthestartoftheprocurementprocess.Theproposedsubprojectshallproceed
with the procurement of the packages described in the submitted prescribed
procurementplan.TheProcurementPlanshallbebasedfromtheapprovedWorkand
FinancialPlan.
Subprojects under I-REAP may compose various procurement packages considering the
natureofenterpriseproductivitydevelopment.
TwomodalitiesshallbeconsideredintheconductandmanagementofprocurementunderI-
REAP component; 1) LGU managed procurement; 2) Proponent Group (PG) managed
procurement;
61
6.2.1 LGU-managed procurement
TheLGUshallmanagetheprocurementofGoodsandWorksforcontractsunderthe
NCB and shopping method above US$200,000.00, including contract below said
thresholdwherethePGdoesnothavethecapacitytomanagetheprocurement.
6.2.2 PG-managed procurement
ThePGmaymanageprocurementofgoods,worksandservices.Thiswilldependon
the established procurement capacity of the PG of the Enterprise. The basic
requirement/capacity of the PG to manage the procurement within the allowed
threshold shall include formation (if no existing procurement committee) of
bidding/procurement committee, experience and knowledge on
procurement/purchasing,andshouldhaveattendedtheprocurementtrainingunder
thePRDP.
Composition of the Procurement Committee- with minimum of three member;
Chairmanandtwomembers.Ineligible:membersoftheBOD,GeneralManagerand
PresidentoftheAssociationtoauthorizetosigncontract,Accountant,Auditor.
Appropriate procurement arrangements should be made clear in the Enterprise
InvestmentAgreement(EA).
ThedetailedproceduresandrequirementsfortheprocurementofgoodsandworksforI-
REAPsubprojectwillbereferredtointheProcurementGuidelines.
7. Social and Environmental Safeguards
A Social and Environmental Safeguards Framework (SESF) was prepared for the PRDP to
ensurethatagriculturalandfisheries-basedentrepreneurialactivitiesundertheI-REAPare
environmentally and socially sound. The SES takes off from lessons gained from MRDP
implementation and integrates policy frameworks on land acquisition, rehabilitation and
resettlement, indigenouspeoples(IP),andenvironmentalmanagementthatareconsistent
withPhilippinelawsandWorldBanksafeguardpolicies(RefertotheGuidelinesonSocialand
EnvironmentalSafeguardsFramework(SESF)forPRDP).
TheSESFpromotesthesustainabilityofI-REAPenterprises,investmentsandsupportfacilities
through social acceptability, better social inclusion, and environmental management
initiativesduringenterpriseselectionuptoimplementation.Thissectionprovidesadetailed
guidetotheintegrationofSESFprovisionsinI-REAPmanagementandimplementation.
TheSESFprovidesthedetailsofthevarioussocialandenvironmentalimpactscenariosand
theappropriatemitigationmeasuresanchoredondocumentaryrequirements.Preparation
of the EIP for the proposed clusters of enterprises requires the inclusion of required
documentsasproofofcompliancetotheSESofthePRDP.Asearlyastheconceptionstage
62
and to be finalized during validation by RPCO, all proposals shall undergo mandatory
environmental and social screening using the form provided in the PRDP SESF to ensure
subproject eligibility for funding in terms of safeguards and also to determine the
environmental and social aspects and corresponding requirements for the subproject
preparation. Table 7-1 summarizes the different social impact scenarios to guide the
P/C/MPMIU and proponents as to the type of intervention or documentation needed to
establishsocialsafeguardcompliance.
Table7-1.SummaryofPotentialSocialImpactsandRequiredDocumentsforMitigation
PotentialSocial
Impact
Mitigation RequiredDocuments/
Attachments
Acquisitionofland
andROWJustcompensationthroughmutually
agreedcompensationscheme
consistentwiththeentitlementpolicy
oftheSESF
§ ESMP
§ DocumentationofCompensationExecution
Physicalandor
Economic
DisplacementofProjectAffectedPersons(PAP)
Note:Physical
displacementmeans
thePAPisuprooted
ortransferredfrom
hispresentdwelling.
Economic
displacementis
definedbelow.
Consultationwithandparticipationof
PAPsinplanningandimplementation
ofresettlementplans
Resettlementconsistentwiththe
entitlementpolicyoftheSESF
§ Documentationof
consultations(minutesofthe
meeting,attendancesheets)§ ResettlementActionPlan
withcomprehensive
inventory/survey§ Documentationof
CompensationExecution
Accessrestrictionto
resourcesJustcompensationoflostassetand
provisionoflivelihoodassistance
consistentwiththeentitlementpolicy
oftheSESF.Itshouldbenotedthatif
accessrestrictionconstitutelossof
morethan20%ofthelivelihood
sourceorincome,thePAPis
considered“economicallydisplaced”
andshouldbeprovidedwithaRAP
whichinvolvelivelihoodsupportor
restoration(seeabove).
§ ESMP§ Documentationof
CompensationExecution
Policyonlandacquisitionandresettlementadherestotheprinciplethatareasfortheuseof
prospectiveenterprisesarenotforcefullyacquiredandthatPAPsaretimelyconsultedand
justlycompensatedfortheinvoluntarylossesoflands,structures,cropsorotherproperties.
Thepolicyalsorequiresthatdisplacementleadstoassistedresettlementtoimprove,orat
leastmaintain,pre-projectlivingstandardsandincomeearningcapacity.Landandproperty
donationsareacceptedprovidedthatexecutionisvoluntaryandthedeedisdulynotarized
andannotatedbyanauthorizedagency.
63
SocialsafeguardsforIPsnecessitatefreeandpriorinformedconsultationwiththeIPgroups
and coordination with the NCIP (Table 7-2.). Ultimately, indication of broad community
support from IPs would reflect observance of cultural sensitivities associated with such
vulnerablegroups.
Table7-2.SummaryofImpactScenariosonIPsandRequiredDocumentsforMitigation
ImpactScenarioon
IndigenousPeople
Mitigation RequiredDocuments/
Attachments
Enterpriseswithcomponents
locatedwithindeclaredor
proposedIPAD
RA9178onestablishmentof
exemptionofotherbusiness
relatedrequirementsfor
BarangaySMEsand
AdministrativeOrder01series
of2006ofNCIPonthe
GuidelinesonfreePrior
InformedConsent(FPCI)
§ FPICforothertypeof
investmentsneedingsuch
document,MOAwithIP
Community§ CertificateofPre-Condition§ Documentationof
ConsultationProcesses§ESMP
ForenterprisesinsideADthatare
solicitedbyIPCommunityor
identifiedinADSDPP
ValidationbyNCIP § NCIPValidationReportor
NCIPCertificationaffirming
conditions§ ESMP
ForenterprisesinsideADthatwere
neithersolicitedbytheIPnor
identifiedintheirADSDPPbuttheIP
arethemselvestheprimary
beneficiaries
ValidationbyNCIP § NCIPCertificationaffirming
conditions§ ESMP
Enterprisesthatarewith
componentslocatedinareas
outsidedeclaredorproposedIPAD
buthavesignificantIPpopulation
andthemajorityoftheproponents
arenotIPmembers
Conductoffreeandprior
informedconsultationactivities
andsecuringbroadcommunity
support.Incorporation/
integrationofanIP
DevelopmentPlaninthe
businessplanforthepurpose
ofminimizingadverseimpacts,
ifany,totheIPcommunities
andensuringinclusionofthe
IPsinthebenefitsofthe
subproject.
§ DocumentationofFPIC
Consultation(IECmaterials,
attendancesheetsand
minutesofmeetings)§ IPCommunityEndorsement
orResolutionofSupport§ BusinessPlanshallinclude
assessment/analysisofthe
impactsoftheI-REAP
subprojecttotheIP
community;and§ IPDevelopmentPlan
EnterpriseinareasoutsideADbut
withsignificantIPpopulationand
themajorityoftheproponentsare
membersoftheIPcommunity
Nomeasuresneeded § EvidencethatIPmembers
constitutemajorityofthe
proponents
§ Evidenceofconsultation
conducted
§ IPcommunityendorsement
64
Potentialdamagetocultural
propertiesandresources*Avoidancethroughrelocation,
realignmentandredesignof
enterprisecomponent.
Forchancefindsordiscoveries
ofarchaeologicalartifacts,
immediatecoordinationwith
theNationalMuseumis
required
§BusinessplanandESMP
indicatingavoidance,relocation
orrealignmentoftheaffecting
subprojectactivity.Ifthe
subprojectinvolvesignificant
excavation,proponentis
requiredtoadoptthePRDP
ChanceFindProcedure
*Forinclusiontonegativelistofenterprises
Forenvironmentalsafeguards,thePhilippineEISSystemestablishedfourprojectcategories
that indicate themagnitude of potential impacts to the bio-physical and socio-economic
environment.Thecategorizationdeterminesthetypeofdocumentthatisneededtosecure
an Environmental Compliance Certificate (ECC). Category A is for Environmentally Critical
Projects (ECP)andwould requireanEnvironmental ImpactStatement (EIS).However, the
IREAP Component is not expected to support such undertakings, which include heavy
industries,resourceextractiveindustriesandmajorinfrastructureworks.
CategoryBProjectsareundertakingslocatedwithinEnvironmentallyCriticalAreas(ECA)and
would require an EIS, Initial Environmental Examination (IEE) Report or IEE Checklist
dependingonthesizeandscaleoftheproject.CategoryCisforenvironmentalmitigationor
enhancement projects, to include reforestation activities, artificial reef establishment,
embankmentandriverbanksstabilizationworks.CategoryDontheotherhand,isforprojects
thatareoutsidethecoverageofPEISSystemduetotheminimalnatureofenvironmental
impacts.BothCategoriesCandDprojectswouldnotrequireECCs.
While NRM OGIs of the I-REAP are classified as Category C and does not require ECCs,
prospective I-REAP enterprises are expected to fall under Categories B or D. Table 7-3
provides the threshold levels of enterprise components to guide the P/C/MPMIU and
Proponents with regard to compliance to the Philippine EIS System. For enterprise
componentsfallingunderCategoryD,anESMPmayberequiredbytheRPCOorPSO.
Table7-3.SummaryofThresholdLevels-PotentialI-REAPEnterpriseComponents
PossibleEnterpriseComponents
forI-REAP
Category
B D
Fishery/AquacultureProjects(inland-based,
e.g.,lakes,rivers,bays,etc.)>=1hectarebut<25hectares <1hectare
Fishery/AquacultureProjectsinwaterbodies
(coastalareas)>=1hectarebut<100hectares <1hectare
Compost/fertilizermaking >=15MTdailycapacityor
5,475MTannualcapacity<15MTdailycapacityor
5,475MTannual
capacity
65
Livestockprojects
Note:OnlyContractgrowingiscoveredby
thePhilippineEISSystem.Otherlivestock
projectsaredeemedtobeunderthe
jurisdictionoftheconcernedLGU
EIS: >= 100,000 heads
poultry/birdsOR>=1,000headspigs/goats
<10,000heads
poultry/birdsOR
<100headspigs/goatsIEE:>=10,000headsbut<100,000headspoultry/birds
OR>=100headsbut<1,000
headspigs/goats
Agriculturalplantation EIS:>=1,000hectares <100hectares
IEE:>=100hectaresbut<
1,000hectares
Agriculturalprocessingfacilities EIS:=>50,000MTannual
productioncapacity<5,000MTannual
productioncapacity
IEE:=>5,000MTbut<50,000
MTannualproductioncapacity
Fruitandvegetableprocessing EIS:>=500Kgdailyprocessing
capacity
IEE:<500Kgdailyprocessing
capacity
Processingofdairyproducts EIS:>=100,000L(liquid)OR>=100,000Kg(solid)monthly
productioncapacity
IEE:<100,000L(liquid)OR<
100,000Kg(solid)monthly
productioncapacity
Coconutprocessingplants EIS:>=25,000MTpermonth
productioncapacity
IEE:<25,000MTpermonth
productioncapacity
Animalproductsprocessing(fish/meat
processing,canning,slaughterhouses,etc.)EIS:>=10,000Kgdaily
productioncapacity<500Kgdaily
productioncapacity
IEE:>=500Kgbut<10,000Kg
dailyproductioncapacity
Othertypesoffood(andotherfood
byproducts,additives,etc.)processing
industries
EIS:>=50,000MTannual
productioncapacity(finishedproduct)
IEE:<50,000MTannual
productioncapacity(finishedproduct)
Leatherandrelatedindustries >=1MTrawhidesperday(or
25MTpermonth)<1.0MTperday(or25
MTpermonth)
Paperandplasticbasedproducts >=15,000MTannual
productioncapacity< 15,000 MT annual
productioncapacity
Commercialbuildingsandothersimilar
structuresincludingfoodpreservation(e.g.,
EIS:>=25,000squaremeters(gross/totalfloorareaincluding
parkingandotherareas)
<10,000squaremeters(gross/totalfloor
areaincluding
66
drying,freezing)andothermethodsaside
fromcanningIEE:>=10,000squaremeters
but<25,000squaremeters(gross/totalfloorareaincluding
parkingandotherareas)
parkingandother
areas)ORKiosk-typeormobilefast
foods
Storagefacilities,non-toxic/hazardous
materials>=10,000.0squaremeters
(gross/totalfloorarea)<10,000.0square
meters(gross/totalfloorareaincludingparking
andotherareas)
In the preparation of the business plan, the P/C/MPMIU will include a section on SES
considerations(i.e.adiscussiononthesocialandenvironmentalaspectsofthesubproject)
prior toendorsement to theRPCO. The sectionwill containdisclosure statementson the
statusoflandacquisition,applicabilityofdisplacement,presenceofIPsandenvironmental
screening and categorization of enterprise components. In cases where land acquisition,
resettlement, IP involvement, and/or Category B classification are applicable, respective
compliancedocumentswillbeattachedtotheEIPforreviewandclearanceoftheRPCOand
PSO. Compliance to the provisions of respective SES documents will form part of the
conditionalitiesstipulatedintheEAbetweentheP/C/MPMIUandProponent,aswellasthe
IMAbetweentheLGUandtheDA.
8. Grievance Mechanism
I-REAPsubprojectswillbecoveredbytheProject-wideGrievanceRedressMechanism(GRM)
systemtobeestablishedinallparticipatingLGUs.AllI-REAPsubprojectproposalsmustclearly
indicateadoptionof theGRMsystem.No I-REAPsubprojectwillbe implementedwithout
demonstrating that a function GRM has already been established and adequately
disseminatedwithinthesubprojectarea.
TheProjectGRMwillhavethefollowingelements:
1. Requirement. Each I-REAP subproject will have a system for airing and resolving
grievancesatthecommunitylevelsthatwillgenerallyconformtothisframework.
2. Objective. The objective of GrievanceMechanism is to provide stakeholders with
mechanism to voice out complaints at the subproject level and to provide the project
managementameanstohearandresolvecomplaintsonthesubproject.
3. GrievanceCommittee. The concernedLGU representativeplus two representatives
from civil society (e.g. leaders of local church/religious community and civil society
organization)tobeappointedbytheMayorwillconstitutetheGrievanceCommittee.
4. Secretariat to the Grievance Committee. The safeguards focal persons of the
P/C/MPMIUwillserveasthesecretariatoftheGrievanceCommittee.
67
5. Format of Complaint. Complaints will be written down either in the form of a
handwrittenortypewrittenletterorinaformofanemailmessage.Thefollowingminimum
information should be provided in the complaint: (a) Name of Subproject; (b) Name of
Community;(c)NameofMunicipality;(d)NameofProvince;(e)DetailsoftheComplaint;(f)
NameoftheComplainant;(g)AddressorContactInformationofComplainant.
6. Drop Boxes for Complaints. Complaints drop boxes (made of sturdymaterials and
securedwithalock)willbeinstalledinstrategicandconspicuousplaces,suchatthefollowing:
(a)attheprovincialcapitolhall/cityhalland/ormunicipalhall;(b)atcommunityhalls;and/or
(d) at the construction sites. The boxes will be duly labelled and provided with a brief
description of its purpose and a simple instruction for submitting complaints, including
submissionthroughemailifavailable.
7. Email Address for Complaints. Each P/C/MPMIU will, optionally and if technically
possible, maintain an email address account for complaints. The email address will be
registeredattheRPCOandPSOandcanbeaccessedbybothwhenneeded.Theemailaddress
name will be descriptive of the purpose of the address and easy to recall, for example:
8. Sending of Complaints. Letter complaints will be dropped at Drop Boxes for
Complaints.TheLetterwillbesignedbythecomplainantandwill indicatehis/hercontact
information. Email complaints should be sent from a valid address and should include
alternativecontactinformationsuchasatelephonenumber(oroptionallyahomeaddress)
thatcanbeverifiedandvalidated.Allcomplaintswillbeconsideredstrictlyconfidential.
9. CollectionofDropBoxesContentsandInitialScreening.ThecontentsoftheComplaint
DropBoxeswillbecollectedatleastonamonthlybasisbythesafeguardsfocalpersonsacting
assecretariattotheGrievanceCommittee.
10. CollectionofEmailMessagesandInitialScreening.EmailInboxesshouldbecleanedof
spamandinvalidmessageseveryweekandaprintoutofeachvalidemailmessagewillbe
compiledbythesafeguardsfocalpersonsactingassecretariattotheGrievanceCommittee.
11. ScreeningofComplaints.TheGrievanceCommitteewillbeconvenedwhenneededor
at least once a month and presented with the compiled complaints for the period. The
Grievance Committee will first determine the validity of each complaint. Anonymous
complaint or complaints using aliases may be accepted as long as adequate contact
informationand/orevidenceareprovidedthatcanbeverifiedorvalidatedbytheCommittee.
Forcomplaintsrulednotvalidornotrelevant,theGrievanceCommitteemaychoosetosend
areplytothecomplainantexplainingwhythecomplaints/issuesraisedisnotvalid.
12. Replyon theComplaints. Ifacomplaint isdeemedvalid, theGrievanceCommittee
shouldsendareplytothecomplainantinforminghim/heroftheactionsbeingundertaken
onthecomplaint ifany,and/orprovidinghim/herofanexplanationorclarificationofthe
issues,ifnecessary.
68
13. Resolution of the Complaints. The Grievance Committee will determine the
appropriateactionstobeundertakenonthecomplaints.TheGrievanceCommitteemay:(a)
address the complaints by itself if it is within its competence to do so; or, (b) refer the
complaints to the appropriate office who is competent to address/resolve the
issues/complaintsraised.
14. GrievanceReports.ThesafeguardsfocalpersonsoftheLGUactingassecretariatto
theGrievanceCommitteewillcompileallcomplaintsandmonitortheirstatusaswellasthe
actions undertaken by the committee. A semi-annual report on the grievances will be
preparedandsubmittedtotheirRPCOs.
9. Results-Based Monitoring and Evaluation (RBME) System for
Enterprise Development Component
9.1 Introduction
Thisdocumentdefinesthescope,responsibilitycenters,proceduresandinstruments
tobeusedinthemonitoringandevaluationoftheprogressofthePRDPEnterprise
DevelopmentComponent(I-REAP).Theinformationareexcerptedfromtherevised
Results-BasedM&EGuidelines10,whichwillbeendorsedtotheWorldBankforNo
Objection.
ItispreparedbytheNPCOM&EUnitasareferenceoftheNPCOI-REAPComponent
inupdatingtheI-REAPComponentOperationsManualSectiononthemonitoringand
evaluationoftheenterprisedevelopmentsubprojects.
9.2 Overview of the PRDP RBME Framework
The PRDP RBME schematic framework (see Figure 9-1) embarks on the Project’s
Results Framework andArrangement forMonitoring and is at playwith the three
aspectsofbuilding-uparesults-basedM&Esystem.Theseareenumeratedandbriefly
describedbelow.
a. Baseline information has been established through the conduct of the Baseline
Study11,whichwascompleted in2014. Itdescribes theconditions in the targeted
areasbefore the implementationof thePRDP. Thiswill allow theDA toassessor
measuretheproject’sresultsoreffectivenessbymid-temandend-ofproject.
10The RBME Guidelines secured No Objection from the World Bank in August 2014. The revision in the
GuidelinesismadetotakeintoaccounttheM&EprocessusingtheWeb-basedM&Esystemrecentlylaunched.11TheBaselineStudycompletedin2014didnotadequatelycapturetheappropriatebaselinedatafortheI-REAP
resultindicators.ASupplementalBaselineStudyfocusingontheI-REAPComponentshallbeundertakenthis
year.
69
b. Input-Process-OutputorProgressM&Eisaboutcontinuoustrackingandatthesame
timespearheading“efficiency”inimplementingthePRDP.Itsmainaimistobuilda
clearunderstandingwhetherornotinputs/resourcesandprocessundertakenasthe
project progresses translate to outputs the project needs to produce from each
component in order to achieve anticipated results (intermediate results by
component and PDOs). Findings shall be used to determine how inputs and/or
processcanbeadjustedorfactorsthatadverselyaffectitcanbeaddressedtoensure
thatproject’spacewillbeon-trackforthedesiredoutputsandresults.
c. ResultsM&Edelvesontrackingatspecificperiods(e.g.,annually,mid-termandend-
ofprogram) the “effectiveness”ofPRDP.Effectiveness shallbedeterminedat two
levelsnamelyProject-wideandSubprojectspecific.Thesearedescribedasfollows.
(i) Project-wide Level Results. By engaging a consulting service of a third
party, theevaluationat this level seeks tomeasureandunderstand the
Project’s performance in termsof achieving the intermediateoutcomes
envisagedfromtheimplementationofeachcomponentandachievement
of Project Development Objectives (PDOs). The latter shall provide
conclusionof the successor failureof theentire implementationof the
PRDP while the former shall facilitate evaluation of the success of the
implementationundereachcomponentoftheProject.TheProjectwide
levelevaluationisexecutedatthemidandendoftheProject.
A Midterm Evaluation Study shall be conducted in 2017 to measure
changesintheresultindicatorsfrombaseline(withoutPRDP)tothemid
of the Project implementation. This will determine how activities and
outputs delivered as of the half of the Project have become adequate,
relevant and sustainable towards achieving the intermediate outcomes
andthePDOsinthe2ndhalfontheProjectimplementation.
Thefindingsshallbeusedtoeithersustainimplementationapproachesor
potentially institute changes or modifications on any of the following
areas: (i) project design; (ii) result indicators, (iii) allocationof fundsby
component;(iv)operationsguidelines;(v)strategiesandactivities;(vi)DA
TopManagementpolicysupports;(vii)humanresources;and(viii)others
towardsthePDOs.
AProject-EndEvaluationStudyshallbeconductedin2021toconcludeor
assessthesuccessoftheProjectimplementationbycomponentandasa
whole.Theevaluationshallevolveontheextentimplementationofthe
Project translates to the desired changes in the result indicators. The
lessonsthatwillbeacquiredfromtheProjectimplementationexperience
shallbeutilizedbytheDAinimprovingthedesignandimplementationof
futureand/orotheron-goingsimilarProjects.
(ii) SubprojectLevelResults.Thisleveloftrackingresultsseekstodetermine
thesuccessofthesubprojectsthatwererealizedthroughtheRural
InfrastructureandEnterpriseDevelopmentComponentsoftheProject.
70
Thesuccessisdeterminedbymeasuringtheextentbywhichspecific
objectivesofthesubprojecthavebeenattained.
This serves as an intermediate evaluation activity that will facilitate
buildingknowledgeor feedback to thePRDPmanagementwhether the
desiredoutcomesandtheoveralldevelopmentobjectivesoftheProject
are likely or unlikely to be achieved given the situations and lessons
(positiveand/ornegative)emergingfromthecompletedsubprojects.As
theProjectprogressesthemanagementmayusethefindingsasbasesto
introduceadjustmentinhandlingthesubprojectstobemoresustainable.
71
Figure9-1:ThePRDPRBMESchematicFramework
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
72
9.3 Operationalizing the PRDP RBME System for the Enterprise Development
Component
9.3.1 Progress M&E Sub-system
9.3.1.1 Scope
Themonitoringoftheprogressoftheenterprisedevelopmentsubprojectsthatare
proposedby theproponent LGUs for financing under the EnterpriseDevelopment
ComponentshallstartfromtheperiodtheproponentLGUandtheproponentgroup
oftheproposedsubprojectattendedtheWorkshoponBusinessPlanpreparationand
shall end upon completion of the subproject as validated or confirmed by the
concerned PRDP Regional Project Coordination Office (RPCO) and Project Support
Office(PSO).
9.3.1.2 Subproject Progress M&E Instrument
TheM&Eontheprogressofthesubprojectinpassingthroughtheprescribedprocess
fromsubprojectdevelopmenttocompletionshallbedoneon-linethroughthePRDP
Web-basedM&ESystem.
EachsubprojectshallhaveaDataCaptureForm(DCF)intheWeb-BasedM&ESystem
whereprofile,progressincludingtheissues/concernsandmeasurestobeorbeing
undertaken shall be recorded. The DCF along with the Subproject Identification
Number(SPID)willbecreatedbythesystemoncethesubprojectisenteredinthe
system.ThedetailsoftheprocessofusingtheDCFisdiscussedbelow.
9.3.1.3 Subproject Progress M&E Procedures
TheRPCOshallberesponsibleforthemonitoringandreportingoftheprogressofeach
enterprisesubprojectintheWeb-basedM&ESystem.EachRPCOhasdesignatedfocal
personstoreporttheprogressofenterprisesubprojectsintheRegion.Thenamesof
the designated personnel to use the system to report the profile and status of
enterprisesubprojectsareindicatedinaMemorandumsignedbyUsec.EmersonU.
PaladdatedApril14,2016.Theuseofthesystem,however,isnotconfinedtothesaid
list.OtherpersonnelinvolvedintheoperationoftheI-REAPComponent(e.g.,heads
of the I-REAP Component, Business Development Specialist andOfficers) can also
accessandusethesystem.TheotherusersshallberegisteredbythebytheNPCO
M&Eunit.
Eachdesignatedstaffmusthavea“Username”and“Password”withcorresponding
accesslevelandscopeofusingthesystem.ThestepstousetheI-REAPComponent
ModuleofthePRDWeb-basedM&Esystemareasfollows.
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
73
9.3.1.3a Registry of the Enterprise Development Subproject Proposal
TheRPCOdesignatedstaffshallenteracertainsubprojectproposalinthesystemonce
the proponent LGU and enterprise group/s attended the Workshop on Business
Planning.Theregistryshallbemadeonthefirstworkingdayfollowingtheprovision
oftheWorkshoponBusinessPlanningtotheproponentLGUandenterprisegroups.
Theproceduresandthecorrespondingscreenshotstoregisterthesubprojectinthe
systemareillustratedbelow.
Step1:Access the PRDPWeb-based M&E System by simply typing in an internet
browser (preferably Google Chrome or Mozilla Firefox) the URL Address:
mis.daprdp.net
Step2:IntheUserEntryPage,entertheUsername(e-mailaddress)andPassword.
Foranewuser,thedefaultpasswordisprdpmis.Tochangeapassword,click“Change
Password”buttonatthetop(right)portion.Then,apop-upscreenwillappear.Enter
thedesiredpersonalpasswordandclick“Savenewpassword”button.
Step3Step3: In the SystemHome Page, click “I-REAP”menu tabs located at the
upperportion.
Step4:IntheDrop-downMenu,clickSubprojectSet-up.Then,theI-REAPSubproject
Set-uppagewillappear
1
2
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
74
Step5:SupplytheinformationrequiredintheI-REAPSubprojectSet-uppage.The
SubprojectID12willbeautomaticallycreated/assignedbythesystem.
Step6:After providing the required information, click button Save to register the
subprojectincludingitsIDnumberinthesystem.
Step7:Toexitormoveoutofthesystem,simplyclick“Logout”tab.
12TheSubprojectIDcannolongerbedeletedoralteredoncetheUsersavedentriesintheSubprojectSet-up
Page.ThesaidIDshallbecarriedbythesubprojectuptoitscompletion.
4
3
5
6
7
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
75
9.3.1.3b Registry / Reporting the status of the Enterprise Development
Subproject
Afterregistryofthesubprojectinthesystem,theRPCOdesignatedusercanalready
registerstatusofthesubproject.Theprogressormovementofthesubprojectfrom
attendance toWorkshop on Business Planning to the completion of Procurement
(IssuanceofNoticetoProceed)shallberegisteredrealtimeorwithinthedayacertain
processisrealized.Duringimplementation,theregistryofthephysicalprogressshall
bedonemonthlynotlaterthanendofthemonth.
Whileusereportingoftheprogressisprimarily lodgedattheRPCOs,thePSOsand
NPCO(particularlytheI-REAPComponent)arerequiredtoaccessthesystemtocheck
theinformationenteredbytheRPCOsandprovidecorrection,clarificationandother
informationasnecessary.ThestepstoregisterprogressinthesystemusingtheData
CaptureForm(DCF)areexplainedbelow.
9.3.1.3b.1 Registry / Reporting of Status of Subproject (From
Attendance to Workshop on Business Planning to Procurement)
Step1:Access the PRDPWeb-based M&E System by simply typing in an internet
browser (preferably Google Chrome or Mozilla Firefox) the URL Address:
mis.daprdp.net
Step2:IntheSystemUserEntryPage,enteryouUsernameandPassword.
Step3:IntheSystemHomePage,clickI-REAPmenutabslocatedattheupperportion.
Step4:In theDrop-downMenu, clickSubprojectList. Then, the listall subprojects
alreadyregisteredinthesystemthroughStep3.1.3awillappear.
1
2
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
76
Step5:ClickbuttonoftheSubprojectIDofthesubprojecttobeupdatedorprovided
withnewstatus.Then,sub-menus,willpop-uptoselectthesubjectofupdating.
Step6:To update the status, click “Physical Progress”Menu. The sub-drop down
menutoappearwilldependonthecurrentstatusofthesubproject.Forinstance,if
thesubprojectisinthepre-implementation(Development)stage(noNOL1yet),click
sub-dropdownmenu“Pre-Implementation”.Then,theDCFwillappear.
Step7:IntheDCF,putdateofrealizingorcompletingacertainprocess/milestoneto
reflectthecurrentstatusofthesubproject. Citethefactorsaffectingtheprogress
(positive/negative)ifanyandthecorrespondingrecommendations.Putremarksas
necessary.
43
56
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
77
9.3.1.3b.2 Registry/Reporting of Status of Subproject Implementation
(After Procurement)
Step1:RepeatSteps1to6illustratedabove.
Step2:In Step 6, click in the Sub-drop downmenu the “Implementation” button.
Then,subprojectpackages(ifany)willappear.
Step3:Toregisterupdatesorstatusofimplementation,clickSPIDcorrespondingto
a package of the subproject to be provided with updates. Then click “Items
7
2
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
78
(Download)”button.OpentheMS-Excelfiledownloadedandsupplyupdates(e.g.,
itemsdelivered).
Step4:Toreflecttheprogressinthesystem,uploadtheMS-Excelfileprovidedwith
updates.ThisisdonebyclickingSPIDcorrespondingtoapackageofthesubproject
tobeprovidedwithupdates.Thenclick“UploadItems”button.SelecttheMS-Excel
filesavedinthecomputerandandclickUpload.
Whileusersof the I-REAPModuleof thesystemareat largestaff fromthe I-REAP
Component,theM&EUnitspersonnelattheRPCOs,PSOsandNPCOshallhavethe
overall responsibility to coordinate andensure efficient useof the system in their
3
4
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
79
respective offices and provide feedback using the information contained in the
system.Theirspecifictasksareasfollows.
(i) Monitor and coordinate compliance of the designated persons to report
progressthroughtheweb-basedM&Esystem.Shouldthedesignatedstafffor
certain circumstance cannot access or register progress in the system, the
RCPO M&E unit staff may register the progress based on the information
providedbytheI-REAPdesignateduser.
(ii) Monitor the quality of the information provided in the system (e.g., citing
reasons whenever delay in the progress is incurred as well as the
recommendationsand /oractionsbeingundertaken). TheNPCOM&EUnit
shall coordinate with the concerned user from the I-REAP Component to
providethedatalackingorneedtobeclarifiedinthesystem.
(iii) EvaluatetheprogressoftheI-REAPsubprojectsintheRegionusingthereports
or data sets that are automatically generated by the system. A feedback
containing an aggregate assessment on the status of I-REAP subprojects,
outstanding issues and concerns including measures being or need to be
undertakenshallbeprovidedtothemanagementandtheI-REAPComponent
asbasesforProjectsteeringandmakingdecisions.ApartfromtheMonthly
andQuarterlyProgressReports13regularlyproducedbytheM&Eunit,concise
weekly reports shall be prepared focusing on outstanding issues the
managementneedstobeawareof,inordertorelaydecisionsandinstructions
tooperatingunits.
9.4 Subproject Results M&E Sub-system
9.4.1 Subproject Baseline Data
The baseline data corresponding to the specific objectives of the proposed
enterprise development subproject needs to be established during the
preparationofthesubproject. Thisistofacilitatecomparisonofchangesinthe
conditionofbeneficiariesfromwithouttowithsubprojectperiods.
Thegatheringof thebaselineof thesubproject (e.g., incomesofhouseholdsof
membersoftheenterprise,numberofmembers(bysex),numberofIPandNon-
IPmembers,etc.)shallbedoneduringthepreparationofthesubprojectproposal
particularly in the period after identifying the final list of proponent groups to
benefitfromtheproposedsubproject.
13TheMonthlyReportisrequiredbytheDA-SPCMADtoformpartofitsconsolidatedreportsoftheDA
ForeignAssistedProjects(FAPs)beingsubmittedtotheOfficeoftheSecretaryandoversightagencies.
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
80
Inorder toensurecomplianceof theproponentLGUs, theSPProfileFormthat
includesbaselinedataofthesubprojectissetaspartoftherequirementsforthe
issuance of No Objection Letter (NOL) 114for the enterprise development
subprojects.
WhilesomeoftheinformationrequiredintheSPProfileformareavailableand
canbegatheredfromPGFarmersmasterlist,otherdataparticularlytheaverage
annualincomeofhouseholdsofmembersineachPG(brokendownaccordingto
source e,g, On-Farm, Off-Farm and Non-Farm) and others, can be obtained
throughasurveywiththePGmembers.Theproceduresforthesurveyincluding
the necessary collaboration between the Project and the Proponent LGUs and
Groupsareexplainedinthesucceedingparts.
9.4.1a Timing of the Survey
The survey for the profile of members of PGs to benefit from the enterprise
developmentSPshallbeundertakenonceaProponentLGUhasidentifiedtheLead
andClusterPGstomanagetheSPbasedontheProjectprescribedPGselection
criteria.Thismeansthatideally,suchsurveyisnecessarytobecompletedbefore
acertainProponentLGU (withPGs) isasked toparticipate in theWorkshopon
Business Plan Preparation. This will ensure that an LGU and PGs have the
necessary data to complete filling out of the SP Profile form during the said
workshop.
Alternatively, a Proponent LGU (with PGs) may be required to attend the
WorkshoponBusinessPlanPreparationthoughsuchsurveyisnotyetundertaken
/completed.Thisistopreventabsenceofthesurveyfromcausingdelayinthe
technicalassistancetoaProponentLGUandPGsontheformulationofBusiness
Plansof theproposedSPs. Under thisoption, the fillingoutofSPProfileForm
duringtheworkshopwillstillcommencetocoverdatathatarenotdependenton
survey(e.g.numberofmaleandfemalemembers,IPandNon-IPmembers,etc.).
ThesurveyamongmemberstocompletetheSPProfileFormwillbeundertaken
whiledevelopingtheSPBusinessPlan.Itisnecessarythatthesubprojectprofile,
whichincludebaselinedata,becompletedpriortopresentationofthesubproject
forRPABapproval.
9.4.1b Mechanics for the Conduct of Survey
TheconductofsurveyfortheprofilingofPGmembersshallbeundertakenbythe
Proponent LGUs and PGs with guidance from the concerned Regional Project
Coordination Office (RPCO) through its I-REAP component andM&E unit with
14IssuanceofNOL1servesasanapprovalforthegrantoffinancialassistancetotheProponentLGUs
in supporting PGs operating the enterprise development subprojects. Upon securing NOL 1, a
ProponentLGUandProponentGroupscanproceedwiththeprocurementprocessforthedeliveryof
theitemsindicatedintheEnterpriseBusinessPlanapprovedbytheProject
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
81
supportfromthePSOandNPCOasnecessary.Thespecificstepsareenumerated
andbrieflydescribedintheTablebelow.
Steps(ActionsRequired) ResponsibilityCenter
1. Orient theProponentLGUandPGsofficersonthe
conduct of survey by using a “Survey
Questionnaire”.Thisentailsclarificationaboutthe
specific data required in the survey aswell as the
manner questionswould have to be asked by the
interviewer for the respondents. This activity shall
beconductedpreferablyintheSPareaaccessibleto
thetargetrespondents.
RPCO M&E staff with I-
REAPComponentstaff
2. ActualsurveyofPGsmembers(LeadandCluster
Groups).TheRPCOthroughthecollaborativeeffortsoftheI-REAPComponentandM&EUnit
shallbeaccountabletoundertakethesurvey.The
RPCOmaytakeassistancefromtheproponentLGU
andproponentgroup/sasmaybedeemed
necessaryincompletingthesaidtask.Thesurveyshallcoverthedirecthouseholdbeneficiarieslisted
ineachPG.AStratifiedRandomSamplingmethod
shallbeemployedtosavetimeandresourcesin
theconductofsurvey.Forconvenienceandto
speeduptheactivity,thesurveyisrecommended
tobeheldinstrategicplaceswherePGmembers
canbegatheredforthesurveyactivityinsteadof
house-to-housesurveythatwouldbetimeand
resourceintensive.
TheRPCOstafffromtheI-REAPandM&Egroups
shallbepresentduringthefirstdayoftheactual
survey to check on the process and quality
(completenessandappropriateness)ofthedata
gathered. The duration of the survey will
dependonthenumberofmembersofPGs.
ThesuggestedrespondentsfromeachPG(Lead
and Cluster) to be covered by the Stratified
RandomSamplingSurvey shall come from the
totalhouseholdsdirectlybenefiting(members)
from the enterprise. The survey sampling
shouldbebasedonthefollowing:
No. of
Households
(Members
of the PG)
Proponent Group (PG)
Composition
with
1-3
PGs
with
4-6
PGs
with 7
or
more
PGs
20 & below 100% (total enumeration)
21-50 50% 40% 30%
51-100 30% 25% 20%
100 & above 10% 10% 10%
RPCO M&E and I-REAP
staff
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
82
Note:theno.ofPGwillincludeboththelead
andclustergroup/s(ifany)
As there are I-REAP subprojects that are
comprisedofanumberofclustergroupsaside
from that of the proponent lead group, the
sampling method has been designed in a
manner that the PG will not have too much
difficulty inaccomplishingthedesirednumber
ofrespondents.
The final list of respondents shall be selected
randomlybasedonthemasterlistofmembers
ofeachPG.Forinstance,ifaparticularPGhas
100 members in their masterlist, the 10%
samplesizeequivalentto10respondentsshall
be selected as those placed in the 10th, 20
th,
30th,40
th,50
th,60
th,70
th,80
th,90
th,and100
thin
themasterlistofmembers.
3. QualityCheck(Validation).Thecontentor
responsestothesurveyquestionnairesneedtobe
assessedbeforecapturingthemtobepartofthe
PGProfileForm.
RPCOM&E/I-REAPstaff
PhilippineRuralDevelopmentProjectOperationsManual
I-REAPComponent
83
9.4.2 Registry of the SP Profile Including the Subproject Baseline to
the Web-based M&E System
Theentryofthesubprojectprofileincludingthebaselinedataarethesubjectsof
the registry of the subproject in the system after the proponent LGU and
enterprise group attended theWorkshop on Business Planning as explained in
Section 3.1.3a. The system allows registry of the contents profile in batches
includingthedataonincome,andothersrequiredtobeuploadedinthesystem
usingthesystemgeneratedMS-Excelspreadsheets.Theregistryofinformation
shouldbecompletedwhilethepreparationoftheBusinessPlanofthesubproject
isunderway.Thus,subprojectprofileshouldbecompletedanduploadedtothe
PRDPWeb-sitebeforeendorsementofthesubprojectforapprovalbytheRPAB.
9.4.3 Conduct of Rapid Appraisal of Emerging Benefits (RAEB)
Atleastsix(6)monthsafterthecompletionofthesubproject,theRPCOM&EUnit,
EconGroupand I-REAPComponentwithsupport fromthePSOandNPCOshall
conductaRAEBthatwillseektogaugeandunderstandtheemergingbenefitsor
success of the enterprise subprojects that have improved operation through
investmentsprovidedbythePRDPI-REAPComponent. Inparticular,changesin
income,increasenumberofmembersespeciallywomen,employmentgenerated
andothersocio-economicbenefitsshallbeassessed.Thedetailsoftheprocess
andinstrumentsfortheconductoftheRAEBareprovidedintheFrameworkfor
theConductofRAEBdiscussedintheRBMEGuidelines.
84
9.5 Results M&E
AswithI-BUILD,monitoringandevaluationofintermediateoutcomesexpectedfromI-REAP
ComponentwillbepartoftheProjectMid-TermandEnd-of-ProjectEvaluationStudiestobe
conducted by end of Year 3 and Year 6 respectively as specified in the PRDP Results
Framework.TheDAmayengagethesamefirmorexternalgroupthatconductedthebaseline
study or other firm / group asmay be deemed necessary. The specific result indicators
expected to be achieved in implementing the I-REAP Component contributing the
developmentobjectivesoftheprojectareshowninTable9-5below.
Table9-1.IntermediateOutcomestoBeAchievedUnderI-REAPComponent
RESULT
INDICATORS
UNITOF
MEASUREMENT
DATACOLLECTIONMECHANISMRESPONSIBILITY
FORDATA
COLLECTION
DESCRIPTION
(INDICATOR)INSTRUMENTS FREQUENCY/
SCHEDULE
IncreasedProducerGroups(includingsmall
holders)
participatingin
verticallylinked
commodityvalue
chainclusters
%increasein
numberofgroups
operatingviable
enterprises
SamplingSurvey Year3toYear6
RFUsincoordinationwithP/C/MPMIUs
Viable
Smallholder
enterprises
following good
business
practices e.g.,
institutionalized
financial and
auditing system
and enterprises
operating
beyond
breakevent
point
%increasein
numberofwomendirectlybenefiting
fromenterprise
development
SamplingSurvey Year3toYear6
Producer
productivity
enhancedthrough
formalized
arrangementsfor
marketingand/or
technicalservices
Numberof
formalized
arrangements
between
enterpriseswithin
commodityvalue
chains
SamplingSurvey Year3toYear6
Contractualand
formalized
arrangements
formarketingof
produceand/or
provisionof
technical
services
Increasedproducer
groupsandfishers’
resilienceto
climatechangeand
adverseweather
conditions
%usingclimate
smart
technologies
SamplingSurvey Year3toYear6
Producergroups
&fishershave
awareness,
accessanduse
ofclimate-smart
technologies
85
Table9-1.IntermediateOutcomestoBeAchievedUnderI-REAPComponent
RESULTINDICATORSUNITOF
MEASUREMENT
DATACOLLECTION
MECHANISM RESPONSIBILITY
FORDATA
COLLECTION
DESCRIPTION
(INDICATOR)INSTRUMENTS FREQUENCY
/SCHEDULE
Productivityinglobally
significantbiodiversity
sitesenhancedthrough
improvedresourcemanagement,biodiversityconservation,
co-management
arrangements,and
knowledgesharing
%increasein
fishstocksin
targetareas
PSOto
contract
resource
inventory
assessment
surveyin
collaboration
withRFUs
Year3to
Year6 Fishdensity,
diversity,and
biomass
increaseddueto
improvedmanagementandprotectionin
targetareas
In the event DA as executing agency desires to track I-REAP results (along with I-BUILD
results)inYears4and5orapartfromtheMid-TermandEnd-of-Project,asamplingsurvey
maybe conducted following the same techniqueused inbaseline andmid-term studies.
Thus, field interviewersneedtobehired inOctoberoftheyeartodosurveyfortracking
IREAPresultsinprojecttargetedareas.SeealsoTable9-9-6forthestepstodetermineand
evaluate status of achieving intermediate outcomes from the I-REAP Component. The
informationwillformpartofRF10(ResultsTrackingMatrix)attachedintheRBMEGuideline
asAnnex39.FurtherdiscussionsareprovidedintheRBMEGuideline.
Table9-2.ProceduresforMonitoringandEvaluationofI-REAPIntermediateOutcomes
ACTORS ACTIVITIES SCHEDULE/FREQUENCY
RPCOsin
coordinationwith
P/C/MPMIUs.
Step1:Conductsurveyamongprojectareasusing
thesamemethodologyappliedinBaselineStudy
(e.g.,stratifiedrandomsamplingwithpercentof
universetobecoveredbythesurvey;usinga
questionnaire).Thefieldinterviewerscitedin
Table9(tobeengagedinOctober)willalsodo
surveyfor–REAPresults.
November(everyyear)
RPCOMISand
M&EOfficer
Step2:Dataprocessing(tabulation),andanalysis. 1stwk.OfDecember(annual,
fromY3toY6
PSO Step2:Reportingofresults(regionalbycluster)
duringProject-wideAssessment.
PartofDay1oftheTwo-day
Workshoptobeconducted
every3rdweekofDecember
fromY3toY6.
SPCMADMIS
Officerassigned
inPRDP
Step 3: Register I-REAP results in PRDP Results
Database.
1stworkingdayaftertheYear-
EndAssessment.
SPCMADM&E
Specialistfor
PRDP
Step4:IntegrateI-REAPresultsinthePRDPAnnual
PerformanceReport.
Preparation/Finalizationof
AnnualPerformanceReport
untilendofJanuaryofthe
succeedingyear
86
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
85
Annex1.A-SampleMenuofEnterprisestobeSupportedbyI-REAPSub-Component
3.1:RuralAgri-fisheryEnterpriseandProductivityEnhancement
ProductionandProductivityEnhancement
• Cropssubsector
o vermicastproduction
o organicfertilizerproduction
o establishmentofnurseries
o operationofacommonservicefacilityforproductionlikethreshers,tractors,
farmimplements,etc
• Livestocksubsector
O livestockimprovement(throughartificialinseminationfacilitydevelopment)
o establishmentsofmultiplierfarms
o community-basedfeedmixingfacility
• Fisherysubsector
O community–based planting materials production facility development for
seaweeds
o community-basedfingerlingproductionfacilitydevelopment
o fishcagesfacilitydevelopment
o aquaculturefacilitydevelopment
PostharvestandProcessingFacilities
• Crops
O establishmentofriceandcornmillswiththeattendantdryingandwarehouse
facilityforcereals
o establishment of Cassava drying, chipping and granulizing facility with
marketingservice(securedsupplycontracts)
o Vapor heat Treatment and hotwater treatment facilitywith the attendant
packing/packaginghouses)
o establishment of common service facilities for drying (both solar and
mechanical)forpalay,corn,coffee,cacao,copra,etc.
o Developmentofcommonservicepostharvestfacilities(thresher,cornsheller,
communitywarehouseforcereals,etc.)
o Establishmentofprocessingfacilitiesinpartnershipwithacollege/university
thatoffersfoodtechnologycourses
o Establishmentofconsolidationandpacking/packaginghouses
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
86
MarketingFacilities
o establishmentofauctionmarketfacilitywiththeattendantweighingscalesand
theholdingpensforlargeanimalsincludingtheauctionmarketsystem
o establishmentofslaughterhousesanddressingplants
o establishmentoftradingposts/centerswithancillaryfacilitiesandequipmentsuch
as minimal processing facility, cold storage facility, transport facility, weighing
scales,plasticcrates,etc
NRMOn-the-GroundInvestments(OGIs)asaProductivityEnhancementMeasure
toidentifiedprioritycommodities
• OGIs includeactual establishmentand/orenhancementof fish sanctuaries and
Marine Protected Areas (MPAs) and artificial coral reef systems, mangrove
reforestation/rehabilitation,andaqua-silvicultureforcoastalareas
• agro-forestrytosupportsustainablefarmingonslopingland,andreforestationto
rehabilitatedegradedlandsinuplandareas
• stream bank stabilization/ rehabilitation using structural, vegetative, bio-
engineeringdesigns,oracombinationofallthreetypestoreducesoilerosionand
excessiverunoff
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
87
Annex1.B-SampleofActivities/Sub-ProjectstobeSupportedbyI-REAPSubcomponent
3.2:TechnologyandInformationforEnterpriseandMarketDevelopmentSupport
ResearchandDevelopmentandExtensionSystem
• Varietalimprovementthroughtissueculture
• Technology enhancement through breeder stocks production and distribution
facility
• Developmentofclimate-smarttechnologies
• Establishmentofextensionnetworkattheprovincial leveltoprovideextension
deliverysystemtoenterprises(e.g.,SUCs,ATI,NGOs,privatesector)
• Establishmentofclimate-smartfieldschools
• Selectionanddevelopmentoffarmer-scientists(oneforeachprioritycommodity)
tobepartnersoftheacademeinappliedResearchandDevelopment
• Development of information tools that producers’ groups and farmer
entrepreneurscanusetopreserveandenhancetheiroperations(e.g.matrixof
commodityandsupportingprogramsandfinancialresources,FarmerInformation
andTechnologySystem,etc.)
• Establishmentofresearchanddevelopmentcenterandtechnologyincubation
CapacityBuildingorTraining
• TrainingonGAP,GMP,HACCP,bio-control
• Trainingonproductstandards
• Useofexistingagro-meteorologicalweatherstations(AWS)forcropschedulingof
cropcycles,etc.
• Climate-smarttechnology
• Facilitatingaccesstocredit,guaranteeandinsurancefacilities
• BusinessPlanning,enterprisedevelopmentandmanagement
• Establishment of Business Development Service (e.g., training on enterprise
management,bookkeeping,internalcontrol,costanalysis,financialmanagement,
etc.)
MarketDevelopmentServices
• Promotionofclusteringapproachthroughpartnershipandnetworkbuilding
• Establishment of an LGU-based one-stop action center or Agri-fishery Business
ProcessingandLicensingCenter(ABPLC)
• Trialshipmentofpriorityproductsfromspecificsourcestoidentifiedmarkets
• Marketpromotionthroughtradefairs,caravans,crossvisits,studytours
• Tradefacilitationthroughconductofmarketmatchingorlinkageactivities
• Shelf-lifetestingofprioritycommodities/products
• Enhancementofpackagingandlabelingofpriorityproducts
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
88
• Support towardsproductaccreditation toenhancemarketaccess (e.g.,organic
certification,halalcertification,etc)
• Operationalization of national and regional marketing umbrella to assist the
enterprises in facilitating linkages with other agri-fishery stakeholders in the
prioritycommodityvaluechains
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
89
Annex2.A-MenuofPossibleNRMOGIsPerCommodityValueChain
Below is the tablepresenting the indicative listofNRM interventionsbasedon the resultsof
eithertheFullorRapidPRA-RSA.Thelistalsopresentsthetechnicaljustificationsforthepotential
investments.
Value
Chain
Commodity
On-the-Ground
Investments
(OGI)
TechnicalJustificationofOGI
COASTAL
Fishand
other
fishery
species
1.Fish
Sanctuary/
Marine
ProtectedArea
(i)Alldestructivepracticessuchasuseoffinenets,dynamite/cyanide
fishing,etc.areprohibited/controlledespeciallyinstrictprotection
zonesandallowscontrolofotherhumanactivities,includingaccess,in
ordertoprotecttheecosystemwithinthespecificsitethereby
increasingfishproduction.
(ii)Coralreefsprovidefood,livelihood,recreation,protectionfrom
erosion,andextremelyhighlevelsofbiodiversity.Damagedcoralreef
areaswhenrehabilitatedincreasesfishspeciesandfishcatch,
improvesturtlebreedinggroundsanddivingspotsforecotourism.
(iii)Seagrassbedslikewiserehabilitatedandtheseareimportant
habitatsforunderwaterlifesuchasjuvenilefishes,adultrabbitfish,
andcommerciallyimportantspeciesofshrimps,prawns,crabs,sea
urchinsandseacucumbers.Theseprovidetheintermediatebuffer
necessaryforcoralreefstoprotectcoastsfromstrongwavesand
surges.Seagrasshabitatsalsoserveasthefeedinggroundforthe
highlyendangereddugongandmarineturtles.
TheestablishmentofFishSanctuaries/MPAshavebeenknowntobe
aneffectivetoolforconservingfishstock,preservingbiodiversityand
increasingfishproduction.
2.Mangrove
Rehabilitation/
Reforestation
(i)Carbondensityvaluesarecomparablyhighinuplandcarbonsinks
thaninmangrovecarbonsinks.Nevertheless,bothcarbonsinks,
assumingtheirfullyrestoredcondition,cansequesterrelativelyvast
amountsofcarbon.
(ii)Mangroveforests,asadistinctecosysteminitself,providethe
transitionbetweenterrestrialandcoastal/marineecosystems.
Mangrovesprotectthecoastsfromstorms,erosionandfloodsand
likewisescreenoutdebrisfrominlandareas.Theyareimportant
spawninggroundsandfeedingsitesformanycommerciallyimportant
fishspecies.
(SEEMOREUNDERREFORESTATIONINGENERAL)
3.Artificial
CoralReefs
Coralreefssupportassemblagesoflivingcoralsandothermarine
organisms,includingfish,mollusks,marineworms,crustaceans,algae
andsponges.However,climatechange,destructiveandunsustainable
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
90
Value
Chain
Commodity
On-the-Ground
Investments
(OGI)
TechnicalJustificationofOGI
fishingandrecreationalpractices,unwarrantedcoastaldevelopment
andpollutionhaveseverelydegradedcoralreefsystems.Asaremedy,
artificialcoralreefsareplacedinareasawayfromnaturalreefs,
providingaframeworkfornewhardbottomcommunitiestodevelop.
Artificialreefsusematerialsthatmimicnaturalreefsystemssuchas
concreteandlimestone.Itsbenefitsincludeprovidingfood,shelter,
protection,andspawningareasforfishandmarinelife,andrelieving
userpressurefromnaturalreefsbyprovidingalternativerecreational
areas.
4.
Aquasilviculture
(forfishpens,
shrimpand
crabpens)
Aqua-silvicultureisacoastalmanagementstrategythatallowslow-
densitycultureoffish,shrimpsandcrabsinintertidalforestsor
swampswithoutclearingthemangroves,andwhennecessary,even
rehabilitatesdenudedareas.Thisensuresthelong-termcontinuityof
essentialecologicfunctions,andthehealthandproductivityof
forestedecosystems,insupportoftheagriculturalproductivityofthe
enterprise.
(Seemangroverehabilitation/reforestationaboveforother
justifications.)
UPLAND
Cereals,
Rootcrops,
Tubers,
Vegetables,
Fruitcrops,
Livestock,
Poultry
5.
Reforestation
(i)Climatechangeisconsideredasoneofthemostpressing
environmentalissuesofourdaybecauseexpertsbelievethatitcarries
alongharmfuleffectsbothontheenvironmentandthehuman
population.Tomitigateclimatechange,degradedareasneedtobe
rehabilitatedsinceforestecosystemscanassimilatecarbondioxidevia
photosynthesisandstorecarboninbiomassandinsoil.
(ii)Carbondensityvaluesarecomparably1highinuplandcarbonsinks
thaninmangrovecarbonsinks.Nevertheless,bothcarbonsinks,
assumingtheirfullyrestoredcondition,cansequesterrelativelyvast
amountsofcarbon.
(iii)Reforestationisanapproachtomitigatingclimatechange2by
capturingcarbondioxide(CO2)fromlargepointsourcessuchaspower
plantsandsubsequentlystoringitawaysafelyinsteadofreleasingit
intotheatmosphere.Theconceptofcarbonsinkthusworksasa“giant
filter”.Carbondioxidemaybeincorporatedintoforestsandforestsoils
bytreesandotherplants.Plantsabsorbandstorecarbondioxidefrom
12006.CollegeofForestryandNaturalResources,UPLBasheadedbyDr.RodelLascoandDr.JohnPulhin.
2BBC:Treesonlycooltheplanetiftheyareplantedin
the tropics. News Release: Models show growing
moreforests intemperateregionscouldcontribute
toglobalwarming.DecCMBC-2er5,2005NR-05-12-
04, Website of Lawrence Livermore National
Laboratory
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
91
Value
Chain
Commodity
On-the-Ground
Investments
(OGI)
TechnicalJustificationofOGI
theatmosphereandreleaseoxygenintotheatmosphere.Ayoung
forest,composedofgrowingtrees,absorbscarbondioxideandactsas
asink.Forestsarecarbonstores,andbecomecarbondioxidesinks
whentheirdensityorareaincreases.Tropicalreforestationcan
mitigateglobalwarminguntilallavailablelandhasbeenreforested
withmatureforests.Agriculturalproductionwillbenefitgreatlyif
climatechangeeffectsaremitigated.
(iv)Carbonsinksalsoaidinnaturalwaterfiltering,whichprotectsand
preservesthewaterqualityinthearea,acriticalresourceinmost
agriculturalactivities.Thecarbonsinkabsorbsexcessnitratesand
phosphates,andreducestheleveloforganicpollution.
(v)Theforestvegetationplaysanimportantroleinthecapture,
storageandtransportofprecipitationthatfallsinawatershed.Any
alterationintheseprocesses,bywayofchangesinlanduseswithinthe
forestlands,willalterwaterqualitywhereinareductionofthefiltering
processandincreasedrunoffofwaterandsedimentcanoccur
(Waterlines2001).Thisfilteringprocessiscrucialinensuringthe
correctquantityandqualityofwater,acriticalresourceinagricultural
production.
(vi)BasedonPRDPsafeguards,designshouldtakenoteofthe
following:
- Provisionofprotectionmeasuresagainstforestfires(firelines,fire
breaks,look-outtowers)andattackofpestanddiseases
- Plantingalongcontourlinesspeciallyonerodibleandslopingareas
- Strategiclocationofbunkhouses,permanentnurseriesandsatellite
nurseries.Shouldconsideraccessibilityandadequatewatersupply.
- Availabilityofwatersupply
- Multipletreespeciestominimizeinfestation
- Useofindigenousornativeforesttreespeciestoensure
sustainabilityandconservethecountry’sbiodiversity
- Plantingofspeciesbyblocksforeasyidentification
- Roadsandtrailsystemforaccessibilityespeciallyduringtransportof
seedlingsfromnurserytotheplantingsite
6.Agroforestry
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
92
Value
Chain
Commodity
On-the-Ground
Investments
(OGI)
TechnicalJustificationofOGI
reducesoilerosioninslopingareasincludeterracing,vegetative
coverandstrategicallyplantedtrees.
(iii)Increaseslandutilizationofareasundercoconutsthatareusually
unproductivedespiteitshugepotential.
(iv)Rubbermaytakefivetosevenyearsbeforeitcanbetappedofits
latexbutinthelongterm,itcouldbeagoodsourceofincome
especiallythatthebuyingpriceforrubberisnoticeablyhighat
present.
(iv)Multipleperennialandcashcropsplantedinbetweentherowsof
oldcoconutsincreaseslandutilizationofareasundercoconutsthat
areusuallyunproductivedespiteitshugepotential.Italso
showcasesproperagriculturalpractices.
(v)Intercroppingthatleavescropresiduesinthefieldtodecompose
resultstoabeneficialeffectonthesoilthrougheffectsofrun-off
andsoilerosion.Moreplantsresulttomoreoxygeninthe
surroundingsandmorefreshair.
(vi)Othersoilandwaterconservationmeasuresthatallowfarmersto
effectivelymanagesoilfertilityandproductivityinthelong-term.
Theseincludetheuseoflocallyavailableorganicnutrients,suchas
livestockmanure,andhouseholdwaste,andnitrogen-fixingtrees
andshrubs.
(vii)IntegratedPestManagementthatencouragescropprotection
throughcontinuousobservationoffieldconditionsbyfarmers,and
increasedawarenessbyfarmersoftheagri-ecologicallinkages
amonginsects,animals,plantsandhumans.Thisincludesan
assessmentandpracticalapplicationofthefarmers'detailed
knowledgeofthebiologicalandecologicalmake-upofplant
diseases.Inmostcases,pestsarecontrolledthroughthedirect
actionofthepests'naturalenemies.Somemethodsincludeinter-
croppingwithplantsthatarehoststobeneficialinsects,usingplants
withinsecticideproperties,andbacterialandviralpesticides.Also,
theless-toxicchemicalpesticidesasidentifiedbytheFertilizerand
PesticideAuthority(FPA)areused.(CARE2012)
(viii)BasedonPRDPsafeguards,designshould:
- ConformtotheIndigenousKnowledgeSystemsparticularlyofIPsin
caseswherethereareIPs
- Sequentialplantingoftreecropsandshort-rotationcrops
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
93
Value
Chain
Commodity
On-the-Ground
Investments
(OGI)
TechnicalJustificationofOGI
- Providesoilandwaterconservationthroughestablishmentof
vegetativestripsalongcontourlinesand/orhedgerows
- Alleycroppinginslopingorerodibleareas
- AvailofAgroforestrysystemthatareeitheragro-silvi-pastoralor
aqua-agro-silvi-pastoral
- Selectspeciesforhedgerows(multi-purposeplantspecies),shrubs
andfast-growingtreespecies,andagriculturalcrops
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
94
Annex2.B-GlobalEnvironmentFacility(GEF)SupportedActivities
Thetypesofsupportavailabletoeachsitewillinclude:
a) Conservation Implementation Investments. Examples of potential activities
include mangrove and marine habitat restoration; providing enhanced
enforcement capacity; equipment and financing required for enhance MPA
management.
b) CoastalandMarineEcosystemManagementImplementation:Assistingwiththe
implementation of strengthened local policy frameworks for improving local
conservationofvitalresourcesinconjunctionwiththecommodityvaluechain;
c) TechnicalandOperationalCapacitiesofStakeholdersEnhancement:Trainingfor
smallholder farmer and fisher groups on natural resources management and
conservation strategies such as Participatory Resource Assessment (PRA) on
mangrove, sea-grass and coral reef ecosystem that are critical habitats to
endangeredmarineorganisms;
i. Strategic Awareness Campaigns: These campaigns would focus on
biodiversityconservationandcoastalresourcemanagementissues;
ii. Facilitating Stakeholders to Pursue Co-management Arrangements.
Support for facilitating and building partnerships between
community/producer groups, market stakeholders, and local
governments. Consultations and organizational development building
activities will lead to co-management arrangements over key coastal
resources. These co-management arrangements will increase the
likelihood for sustainability and ensure integrative attention on
conservationandproperresourcesmanagement;and
iii. KnowledgeGenerationandSharing:Supportknowledgeandexperience
sharingof goodpracticesamong stakeholders. ThroughGEF’s IW-Learn
Program,attention to factorsaffecting largemarineecosystems (LMEs)
willbestrengthenedthroughstructurallearningandinformationsharing
amongstakeholders.
Specific activities could include agro-forestry; nursery establishment; promotion of
Sloping Agricultural Land Technology (SALT); others. Moreover, Good Aquaculture
Practices(GAP)willbeappliedsuchasenhancementofseedqualityandimprovementof
stockingpractices,andhabitatmanagementandbio-security.
In certain cases, where anMPA does not already exist close to PDRP areas, the GEF
financing could assist with the MPA establishment as long as significant community
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
95
supportexists.Aswell,theremightalsobecaseswherefisheriesco-managementoutside
oftheMPAboundarieswouldbethemostbeneficialforlocalsmallholderproducersand
therefore,GEFfinancingwouldbeallocatedaccordingly.
GEF financed activitieswould focus on improvedMPAmanagement plans, fishery co-
management plans and incorporating measures to conserve and sustainably use
biodiversityinpolicyandregulatoryframeworksattheregionalandprovinciallevels.As
well in select cases, these activities can finance the planning of newMPAs and their
subsequentmanagementplans.EnhancedMPAandfisheriesco-managementplanning
wouldaidinreversingthemismanagementofmanyofthesekeybiodiversityandcoastal
resources.
Overall,theexpectedimprovementsasadirectresultfromtheGEFfinancingsupportwill
bethefollowing:(a)theinformationbaseresultingfrominnovativetechnicalassessment
tools (VCA-VSA-PRA/RSA); (b) transparency; (c) stakeholder ownership; and (d)
sustainability of gains and benefits. It is expected that through these interventions,
marketablesurplusproductivityinthetargetsiteswillincreaseby20%byprojectend.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
96
Annex3-NegativeListofSub-projectsNotEligibleforI-REAPFunding
ThefollowinglistsofsubprojectsareNOTeligibleforI-REAPfunding:
a. Moneymarketplacement,timedepositorotherformsofinvestment
b. Cash advance of any official of the PG unless related to the implementation of
enterprise
c. Paymentofsalaries,honorariaoranyformofallowancesofthepersonnelofthe
LGU
d. Purchaseofsupplies,materials,equipmentandmotorvehiclesoftheLGU
e. AcquisitionofassetsofthePG,unlessnecessaryfortheexecutionoftheenterprise
andspecificallystipulatedintheEPF
f. Purchaseofweapons
g. Financingofpoliticalandreligiousactivities
h. Purchase of fertilizer, pesticides, insecticides and herbicides, asbestos and other
potentiallyanddangerousmaterialsandequipment
i. Chainsawsandexplosives
j. Financingofsawmills
k. Consumptionitemsorevents
l. Financingactivitiesthathaveanalternativepriorsourceofcommittedfunding
m. Financinglaborandothercoststhatcouldbeprovidedin-kindthroughthemembers
oftheenterprise
n. Financing salaries and wages unless the enterprise personnel required is highly
technicalorspecialized
o. Financing administrative expenses such as fuel, utilities, repair and maintenance,
permitsandlicenses
p. Purchaseorrepairofvehiclesforgovernmentoffices
q. Salariedactivitiesthatemploychildrenunder16yearsofage
r. Financingactivitiesthatunfairlyexploitwomenormenatanyage
s. Useofmangroveorcoralreefsasbuildingmaterials
t. Purchase of fishing boats and other related equipment unless directly related or
neededintheenterprise
u. Purchaseofvehicleformonitoringpurposes
v. Constructionofenterprisesupportfacilitiesinprotectedareas
w. Useoffundsforpurchaseorcompensationofland
x. Constructionorrepairandbuyingofequipmentforgovernmentofficesandplacesof
worship
y. Micro-financingactivities
z. Potablewatersystem
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
97
Annex4-ProspectivePartnerAgenciesbyCommodityGroupandbySupportServices
Commodity
Group
Production/ProductivityFinancing
Researchand
Development
BusinessSupportand
Development
Crops DAAttachedAgencies
(PCA3,BPI4,BSWM5,ATI6,
FIDA7,PHilMech3,and
PhilRice4);DABanner
Programs(Rice,
Corn,HVCDP5)
ACPC6,
AMCFP7,
Quedancor8
Window,
DBP9,ACEF10
DOST-
PCAARRD11,
UPLB12,
SUCs13
BAR14,
PHilMech,
DTI15anditsSmalland
MediumEnterpriseCore
Group[BSMED16,SBGFC17,
PTTC18,PDCC19,CITC20,
BDT]21,PHilMech,ATI,
CDA22
Livestock DAAttachedAgencies
[LDC23,PCC24,BAI25,
NDA26,andNMIS]27,
ATI
MLDLP28,
Quedancor,
DBP,ACEF,
ACPC
DOST-
PCAARRD,
UPLB,SUCs,
BAR,
PHilMech
DTIanditsSMECoreGroup
[BSMED,SBGFC,PTTC,
PDDC,CITC,BDT]
PADCC,PhilMech,ATI
Fishery DAandAttached
Agencies[BFAR29,
PFDA]30
SEAFDEC31
ATI
ACPC,
AMCFP,
Quedancor
Window,
DBP,ACEF
DOST-
PCAARRD,
NFRDI32,
SUCs,
PHilMech,
SEAFDEC
DTIanditsSMECoreGroup
[BSMED,SBGFC,PTTC,
PDDC,CITC,BDT]
PDCC,PHilMech,SEAFDEC,
ATI
3 PCA–PhilippineCoconutAuthority
4 BPI–BureauofPlantIndustry
5 BSWM–BureauofSoilsandWaterManagement
6 ATI–AgriculturalTrainingInstitute
7 FIDA-FiberIndustryDevelopmentAuthority
3PHilMech–PhilippineCenterforPostharvestDevelopmentandMechanization4PhilRice–PhilippineRiceResearchInstitute5HVCDP–HighValueCropsDevelopmentProgram6ACPC-AgriculturalCreditPolicyCouncil7AMCFP-Agro-industryModernizationCreditandFinancingProgram8Quedancor–QuedanandRuralCreditGuaranteeCorporation9DBP–DevelopmentBankofthePhilippines10ACEF–AgricultureCompetitivenessEnhancementFund
11DOST-PCAARRD–DepartmentofScienceandTechnology-PhilippineCouncilforAgriculture,Forestry,Aquaticand
NaturalResourcesResearchandDevelopment12UPLB–UniversityofthePhilippinesLosBaños
13SUCs–StateUniversitiesandColleges
14BAR–BureauofAgriculturalResearch
15DTI–DepartmentofTradeandIndustry
16BSMED-BureauofSMEDevelopment
17SBGFC-SmallBusinessGuaranteeandFinanceCorporation
18PTTC–PhilippineTradeandTrainingCenter
19PDDC–ProductDevelopmentandDesignCenter
20CITC–CottageIndustriesandTechnologicalCenter
21BDT–BureauofDomesticTrade
22CooperativeDevelopmentAuthority
23LDC-LivestockDevelopmentCouncil
24PCC–PhilippineCarabaoCenter
25BAI–BureauofAnimalIndustry
26NDA–NationalDairyAuthority
27NMIS–NationalMeatInspectionService
28MLDLP–Multi-livestockDevelopmentLoanProgram
29BFAR–BureauofFisheriesandAquaticresources,PFDA–PhilippineFishDevelopmentAuthority
30PFDA–PhilippineFishDevelopmentAuthority
31SEAFDEC–SouthEastAsianFisheriesDevelopmentCenter
32NFRDI–NationalFisheriesResearchandDevelopmentInstitute
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
98
Annex5-SampleTermsofReferencesfortheBusinessDevelopmentStaff
TERMSOFREFERENCE
BusinessDevelopmentStaff(Finance)
Rationale/Background
TheGovernmentofthePhilippines(GOP)hasobtainedaloanfromtheInternationalBankfor
Reconstruction and Development - World Bank (IBRD-WB), amounting to FIVE HUNDRED
MILLION DOLLARS (US$500,000,000) for the purpose of financing the ‘Philippine Rural
DevelopmentProgram(PRDP)tosupporttheGovernment’sefforttoreducepovertyamongthe
ruralcommunitiesinthecountry.
ThePRDPisasix-year(2015-2021)initiativeenvisionedtoincreasefarmandfisheryproductivity
andincomesintargetareasinall16regionsofthecountry.Theprogramseekstoachievethis
objectiveby improvingaccessof farmersandother industryplayerstoastrategicnetworkof
infrastructure,marketinformationandsupportservices.Specificinvestmentsandinterventions
are tobe implementedunder fourcentral componentsof theprogram,namely:1) Localand
National Level Planning (I-PLAN); 2) Infrastructure Development (I-BUILD); 3) Enterprise
Development(I-REAP);and4)ProjectImplementationSupport(I-SUPPORT).
I-REAP activities can be categorized into two sub-components namely; Rural Agri fishery
EnterpriseandProductivityEnhancement;andTechnologyandInformationforEnterpriseand
Market Development. This component will support the development, implementation and
sustainabilityofagricultural,livestockorfishery-basedentrepreneurialactivities,basedonthe
analysis priority commodity value chains being supported under the Regional Agricultural
Fisheries and Modernization Plans (RAFMPs) and as reflected the Provincial Commodity
InvestmentPlans(PCIPs).Itwillengagetheengagebroadsectionsofthesectorintheproduction
ofmarketable surplus throughvertical clustering, jointbusinessplanningand investmentsby
proponentgroupsengagedinruralagri-fisheryenterprises.
Itistargetedthataround1,500proponentgroupsconsistingmostlyofproducergroupsincluding
smallproducersandfisheriesassociationsengagedinenterpriseswillbeassistedoverthesix-
yeardurationoftheproject.Atpresent,thereareonly138enterprisespipelinedforI-REAPof
which 11 has been issued No Objection Letter by World Bank and the National Project
CoordinationOffice(NPCO).
ScopeofServicestobeRendered
Themain role of the BusinessDevelopment Staff on Finance is to take the lead in providing
technicalassistancethroughcoachingandmentoringoftheRPCO(forPSOposition)LGUandthe
Proponent Groups (for RPCO position) in all financial management related concerns of the
enterprise.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
99
TasksandResponsibilities
1. IdentifytogetherwiththeLGUandthePGtherequiredinvestmentrequirementsforthe
proposedenterprise
2. Assistinthepreparationoftheenterprisebudget
3. Assistinthepreparationoftheenterprisefinancialstatements
4. Preparetherequiredfinancialanalysisandfinancialratios
5. Set-uptheenterprisefinancialmanagementsystemandcascadethistotheLGUsandthe
PGs
6. Assist the LGU and the PG in complying the comments and recommendations of the
businessplanreviewers
7. Assist the Component Head in the validation and selection of proponent groups and
enterprisebusinessmodel
8. Performotherdutiesthatmayberequiredfromtimetotime
QualificationRequirements
AcademicQualification
At least a Bachelor’s degree in Accountancy, Business Administration major in Finance,
Agribusiness,AgriculturalEconomics,andotherrelatedfields
Experience
Atleasttwo(2)years’experienceinanyorcombinationofthefollowing:financialmanagement,
accounting, bookkeeping, financial audit, business planpreparation, project proposalwriting,
projectdevelopment
Knowledge,SkillsandAbilities
1. Skillinusingfinancialanalysisusingcomputerprograms/softwares;2. Stronganalyticalandoperationalknowledgeofagribusiness3. Considerableknowledgeonagricultureandfisherycommodities4. Understanding of business procedures including business financing, human
resources,IT,operationsandsalesandmarketingfinancingoptionsforbusinessstart-upsandbusinessexpansions;
5. Stronginterpersonalskills;
6. Abilitytocommunicateeffectivelyinoralandinwriting,workindependentlyandaspart
of the team, and work effectively with co-workers, partner agencies and the private
sector;
7. AdvancedproficiencyinMSword,excel,andpowerpoint
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
100
TERMSOFREFERENCE
BusinessDevelopmentStaff(Marketing)
Rationale/Background
TheGovernmentofthePhilippines(GOP)hasobtainedaloanfromtheInternationalBankfor
Reconstruction and Development - World Bank (IBRD-WB), amounting to FIVE HUNDRED
MILLION DOLLARS__ (US$500,000,000) for the purpose of financing the ‘Philippine Rural
DevelopmentProgram(PRDP)tosupporttheGovernment’sefforttoreducepovertyamongthe
ruralcommunitiesinthecountry.
ThePRDPisasix-year(2015-2021)initiativeenvisionedtoincreasefarmandfisheryproductivity
andincomesintargetareasinall16regionsofthecountry.Theprogramseekstoachievethis
objectiveby improvingaccessof farmersandother industryplayerstoastrategicnetworkof
infrastructure,marketinformationandsupportservices.Specificinvestmentsandinterventions
are tobe implementedunder fourcentral componentsof theprogram,namely:1) Localand
National Level Planning (I-PLAN); 2) Infrastructure Development (I-BUILD); 3) Enterprise
Development(I-REAP);and4)ProjectImplementationSupport(I-SUPPORT).
I-REAP activities can be categorized into two sub-components namely; Rural Agri fishery
EnterpriseandProductivityEnhancement;andTechnologyandInformationforEnterpriseand
Market Development. This component will support the development, implementation and
sustainabilityofagricultural,livestockorfishery-basedentrepreneurialactivities,basedonthe
analysis priority commodity value chains being supported under the Regional Agricultural
Fisheries and Modernization Plans (RAFMPs) and as reflected the Provincial Commodity
InvestmentPlans(PCIPs).Itwillengagetheengagebroadsectionsofthesectorintheproduction
ofmarketable surplus throughvertical clustering, jointbusinessplanningand investmentsby
proponentgroupsengagedinruralagri-fisheryenterprises.
Itistargetedthataround1,500proponentgroupsconsistingmostlyofproducergroupsincluding
smallproducersandfisheriesassociationsengagedinenterpriseswillbeassistedoverthesix-
yeardurationoftheproject.Atpresent,thereareonly138enterprisespipelinedforI-REAPof
which 11 has been issued No Objection Letter by World Bank and the National Project
CoordinationOffice(NPCO).
ScopeofServicestobeRendered
ThemainroleoftheBusinessDevelopmentStaffonMarketingistotaketheleadinproviding
technicalassistancethroughcoachingandmentoringoftheRPCO(forPSOposition)LGUandthe
ProponentGroups(forRPCOposition)indevelopingthemarketingstrategiesandplansofthe
enterprise.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
101
TasksandResponsibilities
1. IdentifytogetherwiththeLGUandthePGthecompetitorsandassistinthepreparation
of the competitors assessment to include buying and selling practices, pricing and
promotionsstrategies
2. Conduct target buyers profiling to include information on total demand and potential
demandfortheenterprise
3. Assistinthepreparationoftheenterprisemarketingplanusingthedifferentmarketing
mix(product,price,place,promotion)andidentifycorrespondingbudget
4. Facilitatemarketlinkageoftheenterprisewithpotentialortargetbuyers
5. Preparepurchaseagreementwith farmersuppliersandmarketingagreementwiththe
buyers
6. Assist the LGU and the PG in complying the comments and recommendations of the
businessplanreviewers
7. Assist the Component Head in the validation and selection of proponent groups and
enterprisebusinessmodel
8. Performotherdutiesthatmayberequiredfromtimetotime
QualificationRequirements
AcademicQualification
At least a Bachelor’s degree in Agribusiness, Agricultural Economics, Business Administration
majorinMarketing,Agriculture,andotherrelatedfields
Experience
Atleasttwo(2)years’experienceinanyorcombinationofthefollowing:marketdevelopment,
product development, preparation of marketing plan, business plan preparation, project
proposalwriting,projectdevelopment
Knowledge,SkillsandAbilities
1. Considerableknowledgeinmarketingagri-fisherybasedcommodities2. Analyticalandoperationalknowledgeofagribusiness3. Understanding of business procedures including business financing, human
resources,IT,operationsandsalesandmarketingfinancingoptionsforbusinessstart-upsandbusinessexpansions
4. Stronginterpersonalskills
5. Abilitytocommunicateeffectivelyinoralandinwriting,workindependentlyandaspart
oftheteam,andworkeffectivelywithco-workers,partneragenciesandtheprivatesector
6. AdvancedproficiencyinMSword,excel,andpowerpoint
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
102
TERMSOFREFERENCE
BusinessDevelopmentStaff(Operations)
Rationale/Background
TheGovernmentofthePhilippines(GOP)hasobtainedaloanfromtheInternationalBankfor
Reconstruction and Development - World Bank (IBRD-WB), amounting to FIVE HUNDRED
MILLION DOLLARS__ (US$500,000,000) for the purpose of financing the ‘Philippine Rural
DevelopmentProgram(PRDP)‘tosupporttheGovernment’sefforttoreducepovertyamongthe
ruralcommunitiesinthecountry.
ThePRDPisasix-year(2015-2021)initiativeenvisionedtoincreasefarmandfisheryproductivity
andincomesintargetareasinall16regionsofthecountry.Theprogramseekstoachievethis
objectiveby improvingaccessof farmersandother industryplayerstoastrategicnetworkof
infrastructure,marketinformationandsupportservices.Specificinvestmentsandinterventions
are tobe implementedunder fourcentral componentsof theprogram,namely:1) Localand
National Level Planning (I-PLAN); 2) Infrastructure Development (I-BUILD); 3) Enterprise
Development(I-REAP);and4)ProjectImplementationSupport(I-SUPPORT).
I-REAP activities can be categorized into two sub-components namely; Rural Agri fishery
EnterpriseandProductivityEnhancement;andTechnologyandInformationforEnterpriseand
Market Development. This component will support the development, implementation and
sustainabilityofagricultural,livestockorfishery-basedentrepreneurialactivities,basedonthe
analysis priority commodity value chains being supported under the Regional Agricultural
Fisheries and Modernization Plans (RAFMPs) and as reflected the Provincial Commodity
InvestmentPlans(PCIPs).Itwillengagetheengagebroadsectionsofthesectorintheproduction
ofmarketable surplus throughvertical clustering, jointbusinessplanningand investmentsby
proponentgroupsengagedinruralagri-fisheryenterprises.
Itistargetedthataround1,500proponentgroupsconsistingmostlyofproducergroupsincluding
smallproducersandfisheriesassociationsengagedinenterpriseswillbeassistedoverthesix-
yeardurationoftheproject.Atpresent,thereareonly138enterprisespipelinedforI-REAPof
which 11 has been issued No Objection Letter by World Bank and the National Project
CoordinationOffice(NPCO).
ScopeofServicestobeRendered
ThemainroleoftheBusinessDevelopmentStaffonOperationsistotaketheleadinproviding
technicalassistancethroughcoachingandmentoringoftheRPCO(forPSOposition)LGUandthe
Proponent Groups (for RPCO position) in preparing the operational plan and technical
requirementsoftheenterprise.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
103
TasksandResponsibilities
1. IdentifytogetherwiththeLGUandthePGthetechnologyrequiredfortheenterpriseand
itsadaptionandimplementationaswellasidentificationoflivelihoodoptionsforNRM
andGEFsites
2. Provide guidance in operations planning from identifying the inputs/raw material
ingredients, the process, technology, the output, product or services and the
correspondingbudgetorexpenses
3. Identifyandassessexistingtechnology/iesthatcouldbeadaptedbytheenterprise
4. Assistintheidentificationoftechnologyorequipmentspecificationsappropriateforthe
enterprise
5. Work closely with the I-BUILD in the preparation of the DED and POW for the
infrastructurecomponentoftheenterprise
6. Prepareprocessandoperationalflowoftheenterprise
7. Ensure compliance of enterprise to food safety standards (GAP, GAHP, GAFP, GMP,
HACCP,etc)
8. Assist the LGU and the PG in complying the comments and recommendations of the
businessplanreviewers
9. Assist the Component Head in the validation and selection of proponent groups and
enterprisebusinessmodel
10. Performotherdutiesthatmayberequiredfromtimetotime
QualificationRequirements
AcademicQualification
At leastaBachelor’sdegree inAgriculture,AgriculturalEngineering,Agribusiness,Agricultural
Economics,FoodScience,FoodTechnology,BusinessAdministration,andotherrelatedfields
Experience
Atleasttwo(2)years’experienceinanyorcombinationofthefollowing:farming,manufacturing,
processing, product development, production planning,business plan preparation, project
proposalwriting,projectdevelopment
Knowledge,SkillsandAbilities
1. Considerable knowledge in production and processing of agri-fishery based
commodities2. Analyticalandoperationalknowledgeofagribusiness3. Understanding of business procedures including business financing, human
resources,IT,operationsandsalesandmarketingfinancingoptionsforbusinessstart-upsandbusinessexpansions
4. Stronginterpersonalskills
5. Abilitytocommunicateeffectivelyinoralandinwriting,workindependentlyandaspart
oftheteam,andworkeffectivelywithco-workers,partneragenciesandtheprivatesector
6. AdvancedproficiencyinMSword,excel,andpowerpoint
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
104
TERMSOFREFERENCE
BusinessDevelopmentStaff(OrganizationalManagement)
I. Rationale/Background
TheGovernmentofthePhilippines(GOP)hasobtainedaloanfromtheInternationalBankfor
Reconstruction and Development - World Bank (IBRD-WB), amounting to FIVE HUNDRED
MILLION DOLLARS__ (US$500,000,000) for the purpose of financing the ‘Philippine Rural
DevelopmentProgram(PRDP)‘tosupporttheGovernment’sefforttoreducepovertyamongthe
ruralcommunitiesinthecountry.
ThePRDPisasix-year(2015-2021)initiativeenvisionedtoincreasefarmandfisheryproductivity
andincomesintargetareasinall16regionsofthecountry.Theprogramseekstoachievethis
objectiveby improvingaccessof farmersandother industryplayerstoastrategicnetworkof
infrastructure,marketinformationandsupportservices.Specificinvestmentsandinterventions
are tobe implementedunder fourcentral componentsof theprogram,namely:1) Localand
National Level Planning (I-PLAN); 2) Infrastructure Development (I-BUILD); 3) Enterprise
Development(I-REAP);and4)ProjectImplementationSupport(I-SUPPORT).
I-REAP activities can be categorized into two sub-components namely; Rural Agri fishery
EnterpriseandProductivityEnhancement;andTechnologyandInformationforEnterpriseand
Market Development. This component will support the development, implementation and
sustainabilityofagricultural,livestockorfishery-basedentrepreneurialactivities,basedonthe
analysis priority commodity value chains being supported under the Regional Agricultural
Fisheries and Modernization Plans (RAFMPs) and as reflected the Provincial Commodity
InvestmentPlans(PCIPs).Itwillengagetheengagebroadsectionsofthesectorintheproduction
ofmarketable surplus throughvertical clustering, jointbusinessplanningand investmentsby
proponentgroupsengagedinruralagri-fisheryenterprises.
Itistargetedthataround1,500proponentgroupsconsistingmostlyofproducergroupsincluding
smallproducersandfisheriesassociationsengagedinenterpriseswillbeassistedoverthesix-
yeardurationoftheproject.Atpresent,thereareonly138enterprisespipelinedforI-REAPof
which 11 has been issued No Objection Letter by World Bank and the National Project
CoordinationOffice(NPCO).
ScopeofServicestobeRendered
ThemainroleoftheBusinessDevelopmentStaffonOrganizationalManagementistotakethe
lead in providing technical assistance through coaching andmentoring of the RPCO (for PSO
position)LGUandtheProponentGroups(forRPCOposition)inpreparingtheorganizationaland
managementrequirementsoftheenterprise.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
105
TasksandResponsibilities
1. IdentifytogetherwiththeLGUandthePGtheappropriateorganizationalandbusiness
structurefortheenterprise
2. Assistinpreparingtheorganizationalandmanagementplanfortheenterpriseincluding
the required operations and administrative staff with corresponding job descriptions,
qualificationsandremunerations
3. Identify the business capability requirements of the proponent groups including the
operationsandmanagementstaff
4. ForGEFareas,facilitateorganizationoffarmersandfisherfolk
5. LinkwithconcernedDAagenciesi.e.ATIandothergovernmentagenciesi.e.CDA,DOLE,
DTI for the provision of capability building or training to proponent groups and its
members
6. Ensurecomplianceofenterprisetolaborlawandoccupationalsafety
7. Assist the LGU and the PG in complying the comments and recommendations of the
businessplanreviewers
8. Assist the Component Head in the validation and selection of proponent groups and
enterprisebusinessmodel
9. Performotherdutiesthatmayberequiredfromtimetotime
QualificationRequirements
AcademicQualification
At least a Bachelor’s degree in Agriculture, Agribusiness, Agricultural Economics, Business
Administration,andotherrelatedfields
Experience
Atleasttwo(2)yearsexperienceinanyorcombinationofthefollowing:organizationaldiagnosis,
strategicplanning,communityorganizing
Knowledge,SkillsandAbilities
1. Considerable knowledge in business procedures including business financing,
human resources, IT, operations and sales andmarketing financing options forbusinessstart-upsandbusinessexpansions
2. Analyticalandoperationalknowledgeofagribusiness
3. Stronginterpersonalskills
4. Abilitytocommunicateeffectivelyinoralandinwriting,workindependentlyandaspart
oftheteam,andworkeffectivelywithco-workers,partneragenciesandtheprivatesector
5. AdvancedproficiencyinMSword,excel,andpowerpoint
:
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
106
Annex6-SampleProductSegment/EnterprisePrioritizationProcess
andScoringSheet
Theproductsegment/enterprisewillbeassessedandprioritizedbasedonthefollowing
criteriaandscoringsheet:
No. Criteria Indicator RankingGuide Score
1 Importance
oftheproductsegment/
enterpriseinthelocal
economy
(30POINTS)
• No.ofproducers
involvedassuppliersof
rawmaterials(Source:
BASdata,provincial
data)–10POINTS
• No.ofmunicipalities
involvedinproducing
therawmaterials
(Source:provincialdata)
–10POINTS
• No.ofjobs(directand
indirect)tobe
generated(basedon
DTI/NEDAjob
coefficient)–10
POINTS
HIGH–Top3intheprovince(8-
10POINTS)
MEDIUM–Top5intheprovince
(5-7POINTS)
LOW–outsidetheTop5 inthe
province(1-4POINTS)
HIGH-80%-100%ofthe
municipalitiesintheprovinceare
producingtherawmaterials(8-
10POINTS)
MEDIUM-50%-70% ofthe
municipalitiesintheprovinceare
producingtherawmaterials(5-7
POINTS)
LOW- below 50% ofthe
municipalitiesintheprovince
areproducingtherawmaterials
(1-4
POINTS)
HIGH – Top 3 among the
identified enterprises in the
province(8-10POINTS)
MEDIUM – Top 5 among the
identified enterprises in the
province(5-7POINTS)
LOW–belowtheTop5among
theidentifiedenterprisesinthe
province(1-4POINTS)
2 Market
Potential(30
POINTS)
• Potential for value
addition (based on the
no. of product
segments)–10POINTS
• Strongdomesticand/or
internationaldemand
fortheproduct
(Sources:NSOimport
andexportvolume,
marketstudies,
stakeholders’
consultations,I-PLAN
prioritizationinterms
HIGH–5productsandabove
(8-10POINTS)
MEDIUM–3to4products(5-7
POINTS)
LOW–1to2products(1-4
POINTS)
HIGH–Top3(8-10POINTS)
MEDIUM–Top5(5-7POINTS)
LOW–belowtheTop5(1-4
POINTS)
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
107
ofmarketsize,growth
&potentialandeaseof
entry)–10POINTS
• Identifiedindustrialor
commercialbuyerwith
potentialfor
supply/marketing
contract(basedon
VCA/PCIP)–10POINTS
HIGH–morethantwoknown
localindustrialandcommercial
buyers with potential for
supplyandmarketingcontract
andpresenceofexporttraders
ofthecommodityinthelocality
(8-10POINTS)
MEDIUM –less than two local
and industrial buyers with
potential for supply and
marketing contract and
presence of export traders of
the commodity in the locality
(5-7POINTS)
LOW –No known industrial or
commercialbuyerandexport
traders(1-4POINTS)
3 Resourcebase(20
POINTS)
• Productionarea(10
POINTS)
• Productionvolume(10
POINTS)
HIGH – 40% and above of
agriculture area planted/total
livestock population/ total
aquaculturearea(8-10POINTS)
MEDIUM – 20%-39%
agriculture area planted/ total
livestock population/ total
aquaculturearea(5-7POINTS)
LOW – below 20% agriculture
area planted/ total livestock
population/ total aquaculture
area(1-4POINTS)
HIGH–40%andaboveshareof
agricultural production
volume/totallivestocktraded/
totalfishcatch
(8-10POINTS)
MEDIUM – 20%-39% share of
agricultural production
volume/totallivestocktraded/
totalfishcatch
(5-7POINTS)
LOW–below20%belowthe
shareofagriculturalproduction
volume/totallivestocktraded/
totalfishcatch(1-4POINTS)
4 EnvironmentalImpact
(10POINTS)
• WithPositiveImpact
• Neutral
• NegativeImpact
10POINTS
5POINTS
0POINT
5 Women’s
participation(10
POINTS)
Percentageofwomen
directly&indirectly
participatinginthe
enterprise
HIGH–40%andaboveofthose
who are engaged in the
enterprise are women (8-10
POINTS)
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
108
MEDIUM – 20%-39% of those
who are engaged in the
enterprise are women (5-7
POINTS)
LOW–below20%ofthosewho
areengagedintheenterprise
arewomen(1-4POINTS)
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
109
Annex7-GuideQuestionforBusinessModelFormulation/InformationGathering
No. Questions SourceofData/GuideforInformation
Gathering
1WhatIsthePRODUCT/SERVICESofthe
enterprise?
• Marketing-4P’s
Product , Price, Place,
Promotion
2
WhoaretheUSERs(Farmers/Direct
Beneficiaries)?WhoaretheBUYERS(Identified
Market)?
• VCA/IndustryPlayers/LocalSourcesfor
BaselineData
• ConsiderBackwardand
ForwardIntegration
• ShowconnectionfromSOURCEofRAW
Matstowards
DestinationofFinishProduct
• IdentificationofIndustry
Players
3
Whatisthe“problem”thattheenterprisewill
Address?
Whatisthe“opportunity”thattheenterprisewill
takeadvantageof?
• VCA/PCIP/LocalSourcesforBaselineData
4 WhatistheUniqueSellingProposition(USP)?
• Marketing-convincingtargetclientsto
patronizeyourproductortoswitchbrand
• HowwillyoudelivertheUSP?
• ProductionPlan-identificationofResources
Requirements:Materials,Manpower,
Methods,Machineries,Money
5 WhoaretheBusinessPartners?• IdentificationofHorizontalandVertical
Linkages
6 WhataretheCostsInvolved?
• ProductionCost
• BasisofCostsandAssumptions
7 Whataretherevenues?
• CompareRevenues
• RevenuestobegeneratedwithoutPRDP
investmentvswithPRDPinvestment
8 HowcantheFARMERSearnfromtheenterprise?
• Showhowcandirectbeneficiariesearn
fromtheproposal
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
110
Annex8-SampleLetterofIntentoftheProponentGroup
DearGovernor_________________:
WewouldliketosignifyourintentiontoparticipateasProponentGroupfortheimplementation
oftheruralenterprisesidentifiedandprioritizedundertheProvincialCommodityInvestmentPlan
tobesupportedbytheDepartmentofAgriculture-PhilippineRuralDevelopmentProgram(PRDP).
The _____________________________________ (name of organization) is registered under
_________________________________(nameofagency)andhasbeeninexistencesince
__________(month/date/year).Wehave___________(numberofproducers)whoareinvolved
in
____________________________, _________________, and__________________
(crops/livestock/fisheries cultivated/grown/catch). Our organization has experience in
implementing various agriculture and fishery based projects namely, __________________,
_____________________,and___________________________(specifyprojects).Wearewilling
toprovide20%counterpart,incashand/orinkind,ontheincrementaltotalprojectcostofthe
enterprise.
Wehaveattachedhereinthedocumentaryrequirementsasaproofofourintention.
Thankyouandwearehopingforyourconsideration.
Trulyyours,
President/Chairperson
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
111
Annex9-A-SampleProponentGroup(PG)PrioritizationProcessandScoringSheet
forMicro-enterpriseSubprojects
BelowisthescoringsheetorrankingguideforprioritizingthePG.
No. Criteria Indicator RankingGuide Score
1 Atleast15ormore
farmers/fisherfolks
currentlyproducing
thecommodity–5
POINTS
• Stakeholdersparticipationat
variousphasesofthe
marketingchain
• Presenceoforganized
producer’sgroupthatsupplies
rawmaterials
HIGH(5POINTS)
MEDIUM(3-4
POINTS)
LOW(1-2POINTS)
2 Opentoinvestments
byenterprises
operatingwithin
prioritycommodity
valuechainsidentified
inthePCIP–5POINTS
• Valueofinvestment/equity
offered
HIGH(5POINTS)
MEDIUM(3-4
POINTS)
LOW(1-2POINTS)
3 Readinesstoworkin
verticalcluster(all
levelsofPG
interventions)–5
POINTS
• No.ofparticipatingfarmersor
producers
HIGH(5POINTS)
MEDIUM(3-4
POINTS)
LOW(1-2POINTS)
4 Performancebased
onpreviousor
existingcontracts
withotherfunding
institutions33–5
POINTS
(NOTE:Appliesonly
toPGwithprevious
existingcontract
withgovernment)
• Performance in previous or
existing contracts with
government
HIGH(5POINTS)
MEDIUM(3-4
POINTS)
LOW(1-2POINTS)
33ForthosePGwithoutpreviousorexistingcontractwithgovernment,ratingforcriteria1to3shouldbe
proratedtoreach20points(e.g.,criteria1=7points,criteria2=6points,criteria3=7points).
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
112
Annex9-B-SampleProponentGroup(PG)PrioritizationProcessandScoringSheet
forSmallandMediumEnterpriseandUpgradingEnterprises
TheprospectivePGwillbeprioritizedbasedonthefollowingcriteria:
• Readinesstoworkinverticalcluster;
• Open to investments and provide equity (in cash or in kind) by enterprises
operatingwithinprioritycommodityvaluechainsidentifiedinthePCIP;
• Engagesthemostnumberofproducers;and
• Nodisqualificationsbasedonpreviousorexistingcontractswithgovernment
BelowisthescoringsheetorrankingguideforprioritizingthePG.
No. Criteria Indicator RankingGuide Score
1 Readinesstoworkin
verticalcluster–5
POINTS
• Stakeholdersparticipation
atvariousphasesofthe
marketingchain
• Presence of organized
producer’sgroupthatsupplies
rawmaterials
HIGH(5POINTS)
MEDIUM(3-4
POINTS)
LOW(1-2POINTS)
2 Open to investment and
provideequity(incashor
inkind)–5POINTS
• Valueofinvestment/equity
offered
HIGH(5POINTS)
MEDIUM(3-4
POINTS)
LOW(1-2POINTS)
3 Engages the most
numberofproducers–5
POINTS
• No.ofparticipatingfarmersor
producers
HIGH(5POINTS)
MEDIUM(3-4
POINTS)
LOW(1-2POINTS)
4 Performanceon
previousorexisting
contractswith
government34–
5POINTS
(NOTE:Appliesonlyto
PGwithprevious
existingcontractwith
government)
• Performanceinpreviousor
existingcontractswith
government
HIGH(5POINTS)
MEDIUM(3-4
POINTS)
LOW(1-2POINTS)
34ForthosePGwithoutpreviousorexistingcontractwithgovernment,ratingforcriteria1to3shouldbe
proratedtoreach20points(e.g.,criteria1=7points,criteria2=6points,criteria3=7points).
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
113
Annex10-PGValidationProcessandScoringSheet
A. Rationale:
ThevalidationoftheselectedproponentgroupbytheNPCO/PSO/RPCOIREAPisconductedtoverifythe
“strategicfit”betweenprioritizedenterprise/sorproductsegment/sandselectedproponentgroup(PG)or
leadproponentgroup,iffromclusteredproducergroups.Thevalidationisdoneon-sitetoappreciatethe
processundertakenbythePPMIUwiththeassistanceoftheRegionalProjectCoordinatingOffice(RPCO)in
applyingthecriteriainselectingthepriorityenterprisesand(Annex6)andproponentgroup(Annexes7and
8).
B. Requirements:
Tofacilitatethevalidation,theP/C/MPMIU-PLGUisrequestedtopreparethefollowing:
1. Provide in advance the official minutes of meeting in selecting the priority enterprise/s or product
segment/s with completed Annex 6 – Product Segment/ Enterprise Prioritization Process & Scoring
Sheet;Theminutesshouldbedirectandsimpleindicatingthedateofmeeting,attendees,resolutionsor
resultsofmeetingandsummaryofdiscussionsandsignedbythesecretaryandpresidingofficer;
2. MakeavailablethehardcopiesoftheapprovedPCIPincludingVCAandEVSAwhicharethelogicalbases
inidentifyingthepriorityenterprises;
3. Provideinadvancetheofficialminutesofmeetinginselectingtheproponentgrouporleadproponent
group,iffromclusteredproducergroupswithcompletedAnnexes7–LetterofIntentand8–Proponent
GroupPrioritizationProcessandScoringSheet;Theminutesshouldbedirectandsimpleindicatingthe
dateofmeeting,attendees,resolutionsorresultsofmeetingandsummaryofdiscussionsandsignedby
thesecretaryandpresidingofficer;
4. Theon-sitevalidationwillproceedwiththepresenceofbothofficialminutesofmeeting;
5. TheP/C/MPMIUorRPCOor bothwill prepare thenecessary logistical arrangement– transportation
vehicle,boardandlodgingandconferencevenueforintroductoryandclosingmeetings;
6. ThereshallbeatleastonerepresentativefromthePPMIU,RPCO,PSOandNPCOIREAPwhoareprepared
totravelorwalklongdistancesandifneededstayovernightindesignatedaccommodationinthenearby
TownProper,ProvinceorRegion;
C. ValidationProcess/Activity
1. In the introductory meeting, the participants will introduce their name and designation and the
NPCO/PSO IREAPStaff /Representativeexplain the rationaleof theactivity, requirementsandsite
validation;
2. TheP/C/MPMIUorRPCOwillprovideandexplaintheofficialminutesofthemeetingswithcomplete
annexes6,7and8includingthedocuments:PCIP,VCAandEVSAduringorbeforetheintroductory
meeting;
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
114
3. TheNPCO/PSOIREAPStaff/Representativewillthensuggesttheitineraryofthesitevalidationgiving
importancetotheselectedPGthentothenextrankingPGuntilthelast;
4. Theintroductorymeetingshouldbeheldnotmorethantwohoursandproceedimmediatelytothe
sitesuponagreeingontheitinerary;
5. TheNPCO/PSOIREAPStaff/RepresentativewillfocusitsvalidationorassessmentoftheselectedPG
based on provided information (Annex 7 Letter of Intent with statement of compliance and its
attachments)andmayaskquestionstogathermissingoradditionalinformationwithorwithoutthe
presenceofPPMIUorRPCOorRepresentative;
6. Asmuchaspossible,thesitevalidationperPGshouldnotgobeyondtwohoursexcludingtraveltoand
fromthesiteandthiscanbeachievediftheofficersandmembersofthePGaregatheredintheiroffice
orinpre-agreedmeetingplace;
7. ThePGvalidationisnotadatagatheringactivityandispresumedthatthePPMIUwiththeassistance
ofRPCOandPSOhaddoneenoughpreparation;
8. TheNPCO IREAP Staffwill then thank the visited PG andmay explain the nature of the validation
activitybeforeproceedingtothenextsite;TheP/C/MPMIUorRPCOorPSOStaffwillbetaskedto
answerquestionsrelatedtoPRDPorto
9. Duringorafterthesitevalidation,theNPCOIREAPStaff/Representativewillcompletethevalidation
reportandfinalizeitduringtheclosingmeeting;
10. UponfavorableassessmentoftheselectedPG,NPCOIREAPwillthenissuethe“No
ObjectionLetter”withtheinstructiontoproceedwiththebusinessplanpreparation;Otherwise,thePPMIU
willbeprovidedwithsetofrecommendations
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
115
D. PGValidationScoringSheet
BasicInformation:
ProponentGroup:
OfficeAddress:
Location(Town/Province/Region):
PriorityCommodity(BasedonEVSA):
TitleofVCAReport
PCIPEndorsedbyPLGUGovernor:
Prioritized Enterprise or
ProductSegment:
Validationconductedby;
Dateconducted:
Accompanyingpersons:
1.NPCOIREAPStaff:
2.PSOIREAPStaff:
3.RPCOIREAPStaff:
4.P/C/MPMIUIREAPStaff:
5.Otherstaff
Recommendation:
o Forapproval
o IssuanceofNoObjectionLetter,seedraftNOL
o IssuanceofNoObjectionLetterafterresolvingthefollowingconditions:
1.
2.
3.
o Fordisapprovalduetothefollowingsummaryofnon-compliances
1.
2.
3.
4.
5.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
116
E. Detailsofobservationsduringvalidationactivity
PartI:Annex6:EnterprisePrioritizationProcessandScoreSheet
Arethefollowingrequirementscomplied
basedonAnnex6?
Answer
(Yes,No,NA–
Notapplicable)
Describe answers or explain (If yes, mention
supporting document; if no, provide date on
when it can be complied; If not applicable,
explainwhy?)
A. Are the enterprise subproject
interventions in the PCIP based on the
VCAandEVSAReports?
o Yes o Checked PCIP, VCA &EVSA
consistency;
o NotimetocheckthePCIP,VCA&EVSA
andreliedonfeedback;
o Others:
o No o NoVCAReportforthecommodity;
o NoEVSAdonefortheProvince;
o Others:
o NA o ProvinceisaffectedwithTyphoon
Hainan
o ProvinceisaffectedwithBohol
earthquake
B. Are the enterprise subproject
interventions identified per segment of
thevaluechain?
o Yes Whichsegment
o Input;
o Farming;
o Processing;
o Marketing
o No Whichsegment
o Input;
o Farming;
o Processing;
o Marketing
o NA
C.Istherankingofenterprisesubproject
interventions based on established
criteriaandindicatorsinAnnex6?
o Yes
o No
o NA
D.DidtheP/C/MPMIUidentifyandrank
theenterprisesubprojectinterventions?
o Yes IdentifyPPMIU in-charge and
members
o No
o NA
E.Onthedifferentsetofcriteria,arethe
indicators provided correct and the
scoringconsistent?
1.Importance of product
segment/enterpriseinthelocalo Yes o Indicatorscomplete&correct
o Scoringconsistent
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
117
economy(#ofproducers;#of
Municipalities;and#ofjobs)o No o Indicatorsincomplete&incorrect
o Scoringinconsistent
o NA
2. Marketpotential(Potential
valueaddition;Strongproduct
demandIdentified buyer/swith
contract;hasidentifiedindustrialor
commercialbuyerwithpotentialfor
supply/marketingcontract
o Yes o Indicatorscomplete&correct
o Scoringconsistent
o No o Indicatorsincomplete&incorrect
o Scoringinconsistent
o NA
3. Resourcebase(productionarea,hectares;productionvolume)
o Yes o Indicatorscomplete&correct
o Scoringconsistent
o No o Indicatorsincomplete&incorrect
o Scoringinconsistent
o NA
4. Environmentalimpact(positive,
neutral,negative)
o Yes o Indicatorscomplete&correct
o Scoringconsistent
o No o Indicatorsincomplete&incorrect
o Scoringinconsistent
o NA
5. Women’sparticipation
(Percentageofwomendirectly/
indirectlyparticipating)
o Yes o Indicatorscomplete&correct
o Scoringconsistent
o No o Indicatorsincomplete&incorrect
o Scoringinconsistent
o NA
PartII:Annex8:QualificationofSelectedProponentGroup
Arethefollowingrequirementscomplied? Answer
(Yes,No,NA
– Not
applicable)
Describeanswersorexplain
(If yes,mentionsupporting
document; if no, provide
date on when it can be
complied; Ifnotapplicable,
explainwhy?)
A.DidtheP/C/MPMIUnotifythedifferentvaluechainplayers
or stakeholders to submit a letter of intentwith compliance
statementontherequirements?
o Yes Check date of notice by
PPMIU
o No Cannotbecorrected
anymore
o NA When there is no
proponent due to peace
andorder
situation
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
118
B.Table4-1:DidtherespectivePGsubmittheirletterofintent
withcompliancestatement?
o Yes
o No
o NA
PartII:QualificationofSelectedProponentGroup
Arethefollowingrequirementscomplied(RefertoTable4-2of
I-REAPOperationsManual)?
Answer(Yes,No,
NA-Not
applicable)
Describe answers or
explain (If yes, mention
supporting document; if
no,providedateonwhen
itcanbecomplied;Ifnot
applicable,explainwhy?)
1. Is the selected PG legal registered with SEC, CDA, DTI or
DOLE?
o Yes Provideregistration
detailsanddate.
o No
o NA
AuthenticatedorCertifiedTrueCopyofArticlesof
Incorporation/CooperationandCopyofBy-Laws
o Yes
o No
o NA
CertificateofComplianceGood
StandingforCDAregisteredorCertificateofnoDerogatory
RecordforSECregisteredorCertificateofRegistrationfor
DOLEregistered
o Yes
o No
o NA
2.LatestAuditedFinancialStatement(atleast3years)or
PhotocopyofOfficialReceipt(OR)foritsfinancialtransactions
o Yes
o No
o NA
3.AccomplishmentReportsandphotographsofagri-fisheryor
relatedprojectsundertakenforatleast3years
o Yes
o No
o NA
4.20%equity o Yes
o No
o NA
5.LGUAccountantCertificateofNoUnliquidatedAccountwith
theLGU
o Yes
o No
o NA
7. LGU Certification on the organizational, technical and
financialcapabilityofthePG
o Yes
o No
o NA
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
119
8.AswornaffidavitoftheSecretaryoftheNGO/POthatnone
ofitsincorporators,organizers,directors,orofficialsisanagent
oforrelatedbyconsanguinityoraffinityuptothefourthcivil
degreetotheofficialsofthegovernmentagencyauthorizedto
processand/orapprovetheproposal,theMOAandtherelease
offunds.,ornoneofitsofficialsormembersareemployeesof
theDAor the implementing LGU.Relationshipof thisnature
shallautomaticallydisqualifytheNGO/POfrombeinggranted
thefund
o Yes
o No
o NA
PartIII:Annex9Aand9B:PGSelectionProcessandRanking
Arethefollowingrequirementscomplied? Answer
(Yes, No, NA –
Notapplicable)
Describeanswersorexplain (If yes,mention
supportingdocument; ifno,providedateon
when it can be complied; If not applicable,
explainwhy?)
1. Readinesstoworkinverticalcluster:
1.1 Stakeholdersparticipationinthe
valuechain
1.2 Presenceoforganizedproducer
groupsthat
suppliesrawmaterials
o Yes o Indicatorscomplete&correct
o Scoringconsistent
o No o Indicatorsincomplete&incorrect
o Scoringinconsistent
o NA
2.Opentoinvestmentandprovideequity o Yes o Indicatorscomplete&correct
o Scoringconsistent
o No o Indicatorsincomplete&incorrect
o Scoringinconsistent
o NA
3.Engagesmostnumberofproducers
3.1#ofparticipatingfarmerso Yes o Indicatorscomplete&correct
o Scoringconsistent
o No o Indicatorsincomplete&incorrect
o Scoringinconsistent
o NA
4. Performance in previous or existing
contractswithgovernment
o Yes o Indicatorscomplete&correct
o Scoringconsistent
o No o Indicatorsincomplete&incorrect
o Scoringinconsistent
o NA
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
120
Annex11-GuideQuestionforBusinessPlanData/InformationGathering
I. DESCRIPTIONOFTHEBUSINESSENTERPRISE
[Sourcesofdataand info: industrystudies,valuechainstudies, roadmapsof thecommoditywherethe
enterprisewillbeengaged]
ELEMENTS DESCRIPTION
1.Opportunityforthe
enterpriseandit’s
products
• Howtheproposedenterprisewillmakemoney?Whatistheunique
sellingpropositionoftheenterprise?
• What are the potential profit and the important impact of the
enterprise?
2.BusinessOverview • Whatisthehistoryofthebusinessanditsprimarystrength?
• WhatistheprofileoftheProponentGroupintermsof:
-Ownershipandstructure,thenatureofbusiness,general
productsandservices,numberofyearsinthebusiness,customer
channelsandcustomersize,financialperformanceintermsof
salesrevenue,creditratingandfundsources,industrypositionin
termsofrankandmarketshare,valuesandprinciples.
• Whatisthecompositionoftheenterpriseandtheirrolesinthe
business(incasesofclustering).Whataretheprofileofeachof
themembersoftheenterprisecluster?
3.Productandservices • Enumeratetheproductsandservicestobeofferedandbriefly
describeeach.
4. Supportofthe
enterprisetothecommodity
valuechainupgrading
• Whatis/arethespecificsegment/softhevaluechainwhichthe
enterprisebelongs?
• Whatis/aretheconstraint/sorgap/swhichtheenterpriseaims
toaddressaswellastheopportunitiesthatmayhelpin
developingorupgradingthevaluechain?
• Whatis/aretheoverallcontributionoftheenterprisetothe
developmentofthecommodityorindustry?
II.MARKETANALYSIS
a)MarketCharacteristics(Briefindustryprofileandoutlook)
• Whatisthegeneralsituationoftheindustry?Attheinternationallevel?Nationallevel?
Locallevel?
• Whatisitsmarketsizeandpotential?Volumetraded?Demand-supplysituation?
• Whatarethetrendsandoutlookoftheindustry?Isitgrowing/declining/stableovertime?
Whatistheprospectfortheindustry?Isitgrowing/decling/stable?
• What is the state of themarket or industry? Is it new/emerging? Is it competitive or
difficulttopenetrate?Isitmatureorstable?
• Howdoestheindustryormarketstructurelookslike?
• What are the general characteristics and behavior of the players (sellers) and the
customers(buyers)intermsofpurchasingandsellingbehavior,beliefsandopinions?
• What is thepositionof thesesellersandbuyers in themarket?Whataretheirmarket
share?Howmuchofthismarketsharedoyouwanttoobtain?
• What are the factors affecting the market? (social, technological, environmental,
economic,government,regulation.Political,etc.)
• Whenareyourpeaksalesmonths?LowSalesMonths?
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
121
b)TargetConsumer/CustomerProfile(Thisshouldclearlyhelptheenterpriseanalyzeitsbusiness
directions)
• WhoorwhatisyourtargetMarket?
a. Individuals?
b. Companies(small,medium,large)
c. Institutions?
d. GovernmentAgencies?
e. Exportmarket?
• Whatarecharacteristicsandbehaviorsofyourtargetcostumers?Howdotheynormally
purchasethiskindofproduct?
• Whatbenefitsaretheylookingfor?
• Howwillyouidentifyyourmarket?(Questionnaire?Survey?Others?)
• What is the size of your Market? (Identify indicators of size, Population, per capita
consumption,etc).Wherearethey?
III. COMPETITORASSESSMENT (Competitorsarefirmsthatare inthespaceofyourprimarytarget
segment.Discussionmaybefocusedontop3competitors)
a) KeyCompetitors(Canbeillustratedthroughtable,piechart,graph,etc)
• WhoaretheindustryplayersintheMunicipal?Provincial?Regionallevel?
• Whoarethecompetitors?
• WhatistheirMarketShare
• Whataretheirpricingtrends/system?
• Wherearetheyselling
• Whatistheirdistributionsystem?
• Whatportionofthetargetmarkethavetheycaptured?
• Whatparthavetheymissed?Why?
• Anynewproducts?
• Whereisyourcompetitionlocated?
• Woulditbenefityoutobeinthesamelocation?Why?
b) Relationshipwithcustomers
• Isyourcustomerbuyingfromyourcompetition?Why?
• Whyshouldthecustomerswitchfromyourcompetitiontobuyfromyou?
• Howhaveyoudealtwithcompetition?
• Doyouknowthecompetition’squality,service,andlocation?
• Doyouknowtheirstrengthsandweaknesses?
• What are your strengths and weaknesses (in terms of products, production system,
financial,location,etc)
• Whatisyourcompetition’srelationshipwithitscustomer?
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
122
IV.MARKETINGPLAN(Discussherethemarketingobjectivesandtargetsintermsofsalesvolume,income
andprofitmargin.Outlinethestrategybydefiningthe4Psofmarketing)
Elements Description Remarks
1.Product a. Whatexactlydoyousell?PhysicalDescriptionofeachproduct.
b. Whatareitscomponentparts?Packaging,andotherparts,etc.
c. What is its purpose- (Staple food? Drinks/ beverage? Food
Supplement?Pasalubongitem/Souvenir,officefurnishing,etc.?)
d. Isitanitemthatisanecessityorisitaluxuryitem?
e. Whydocustomerswantit?
f. What makes your product unique and why is it superior or
unique?
g. Possiblenewusageof theproduct. Trends in themarket.New
products.
Technology - (Any product or servicemust take into account the
technology surrounding it. It is important to note where is it in
today'ssituationandcapabilities,andwhatplanshavebeenmade
forchangestothatsituation)
• Whatistheproduct'stechnologicallife?
• Isitstateoftheart?
• Whatistheplantoadapttochangesintechnologyand
trends?
• Howwillglobalization/freetradeaffectyourproducts
(suppliesandprocessing)
• Howistheproductmade?
• Willanyproductionbesub-contracted?Whatmethodswill
youuse?
• Areyouplanningtoproduceinternally?
• Istheproductaninputtosomeoneelse'sproduct?
• Doyoudependontheothercompanyforyoursurvival?
j.Supplies/Suppliers–
• Whatmaterialsandcomponentsarerequiredfor
production?Namethecriticalparts
• Who/whatarethesourcesofsupplyfortheseparts?
• Doyouhavealternativesuppliers?Whatistheleadtime?
• Areyoursuppliersreliable?
k.NaturalResourceBase
• What istheproduct’snaturalresourcebase?Whatarethe
natural resources needed to develop and produce the
product?
l.ProductDevelopment
• Whendidyoudevelopyourproduct?
• Howwasitdeveloped?
• Wheredidyoudoyourresearch?
• Didyouhaveanyguidance?
• Didyourresearchrequireyoutoutilizeanyinstrumentation,
chemicals,components,etc.?
Get the
descriptionfromwhat
youhavewrittenand
presentedin
PartIIIofthisguide
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
123
• Hasyourproductundergoneanystresstests,safetytests
andotherreliabilitytests(shelflife)?
• Haveyoutestedtheproductinthemarketplace?(Test
market?)
h. Whathavebeenthemajorproblemsandsetbacks?Howdidyou
resolvethem?
2.Price Whenpricing, yourbestpricewillbe somewhere ina "range"of
possiblepricesratherthanoneexactnumber.Thisrangeofprices
hasanupperlimitandalowerlimitwhichyoucandetermine.
a. Determinetheupperlimitbyusingthefollowingfactors:
• Thepriceconsumersarewillingtopayforyourproduct.
• Yourcapacitytoproduce(productivity)
• Thenumberofcompetitors'goodsavailabletoconsumers
andtheirprices.
b. Determineyourlowerlimitpricebyusingthefollowingfactors:
• Yourcostofproductionorcost-volumerelationship
• Competitivereactions
• Capacitytoproduce
• Ensuringthateverybodyinthedistributionchain(including
oneself)canmaketheirusualmark-uponcost.
c. ProductCosting
• Materials - Get quotes of price of material at different
volume/quantities
• Manufacturing Costs -What is your direct labor cost for
eachproductdesign?Assembling?Packing?Whatareyour
fixedcosts?Machinecosts,designcosts,etc.
• Overhead-Thisincludescoststhatarenotrelatedtosales
or production volume. They include office expense (e.g.
officesupplies)insurance,wagesandsalaries,utilities,rent
andothermiscellaneouscosts.
• Transportation and shipping - Identify your choices- By
jeep, tricycle, bus, plane, ship cargo or combination of
these.
• Sales Expense - How will your product be distributed?
(sales representatives, distributors, wholesaler, or on
commission)
• Otherhiddencosts-Salesreturnandallowances
• Isthecustomerpricesensitive?Whatdiscountsshouldbe
offeredtotradecustomers?
• Howwillyourpricecomparewithyourcompetitors?
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
124
3.Place a.Locationwhereyourcustomerpurchasetheproduct
• Whoare your customers/consumers andwherewill you
findthem?Describethem(majorityofcustomers)interms
ofbasicdemographicdata:male/female,students,young
professional,sectorstheybelong,incomebracket,etc.
• Wheredoyourcustomersbuytheproduct?Howdothey
normallypurchasethiskindofproduct?Whatbenefitsare
theylookingfor?
• Doyouneedasalesforce?Howwillyoupositionthem?
b. Fromthecustomerprofileanalysis,identifytheplace
whereyouwillsell:
• Province/Town/City
• Wet Market/ Supermarket/ Grocery Stores/ Sari-sari
storesandtherequirementstosellinthatplace.
c. Whydidyouchoosethelocation?
• Factors to consider in Location selection for Trading/
Manufacturing:
-Transportationcosts
-Availability of services(banking,
communication,utilities,etc)
-potentialforexpansion
4.Promotion Again from the customer profile analysis, identify how you will
promoteyourproductintermsofdistributionpolicies(creditpolicy,
delivery policy, pricing policy, policy on returned merchandise,
volumesalesdiscounts,etc.)Advertisingplan.
• When and where can you get across your marketing
messagestoyourtargetmarket?Whatmarketingactivities
doyouneedtodotocommunicateyourvalueproposition?
• Identify the activities, frequency and the budgetary
requirement
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
125
V.OPERATIONALPLAN
ELEMENTS
DESCRIPTION
1.Ownershipand
management
• Describetheownersoftheenterprise
• Describethemanagementteam
• IllustratetheOrganizationalChart
• Describethepersonnelrequirementorstaffingpatternandtheresponsibilitiesof
eachstaff.Givejobdescriptions.
• Whoistheprincipal/keypeopleinvolvedinthebusiness?
• Whatassetsdotheypossess?
2.Resourcesand
Production
• Whataretheproductionmethods,theprocessandtheinputsrequiredforeach
process,andstaffing?
• Illustratetheprocessflow(majorstepstoperformfromrawmaterialsourcingto
deliveryofproductstoyourtargetcustomers).
• What is theoperationalprocessand inputrequirements.Thiscanbepresented in
tabular format (process steps,descriptionof the step,where itoccurs-geographic
and/or physical location, expected inputs required in terms of materials, tools,
equipment,toperformthestep,expectedoutput/result,whowillperformthisstep?
• WhatisyourcapacityandlevelofProduction?Intermsofunits,inPesos?
• Whataretheproductioncycles?Whatisyourbreak-evenpoint?
• Whataretheactivitiesandcostsneededtoaddressfactorsaffectingthesupplyand
qualityofinputs’naturalresourcebase?
• Whatarethecoststomanagewastesandotherpossiblenegativeenvironmental
impacts?
3.Facilitiesand
Equipment• Describetheneededfacilitiesandequipment(existingandproposed)ofthe
enterprise.Whatistheinputandoutputcapacity?Howmuchwillbethe
estimatedcostsperoperations?
• Whatisyourequipmentset-upandfacilitylay-out?Bothproductionandoffice
equipmentandlay-out.
• Whenwillyourequireyourequipment?
4.Operations • Whataretheoperationalschedulesandproceduresoftheenterprise?
• Whatsystemhaveyoudevelopedforqualitycontrol?Whatareyourprofitsby
product/service
• Whatareyourproductioncontrolprocedures?
• Inventorycontrol
• Howmuchinventoryfinishedandrawmaterialswillyouhavetomaintain?
• Haveyoudevelopedasystemofschedulingproductionusingdatesandnumbers?
• Whatistheshelflifeoftheproduct?
• Indicateorcreateoperationsschedule(plantingandharvesting,production
schedule,deliveryschedule)
5. Complianceto
localandnational
regulations
• Whataretheexistingbusinesspermitsandlicensesneededtooperatethe
enterprise?
• Whataretheaccreditationandcertificationsystemsthattheenterprisewillgo
throughtoproduceandselltheproduct?
VI.SOCIALANDENVIRONMENTALSAFEGUARDS
A. SocialSafeguardAspect
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
126
1. SubprojectBeneficiaries
Who are the beneficiaries of the subproject? What is their socioeconomic status? Have they been
consulted?Describe theconsultationprocess (indicatedate, locationandattendeesofmeetings).Have
theyaccepted theproposedproject?Whatare their concernsand inputs?Describe theminutesof the
meetings if any?Are thewomen represented in these consultations (describe attendanceofwomen)?
Whataretheirconcerns/inputs(describeanyparticularinputsfromwomen,ifany)?
ProjectBeneficiaries:IncludediscussiononGrievanceRedressMechanismofthesubproject.Pleasereferto
GrievanceRedressMechanismFramework in the IESSF for referenceandmakesure that the subproject
beneficiariesarewellinformedregardingthesubjectmatter.
2. Indigenous CulturalCommunity/Indigenous Peoples (ICC/IP)– Is the project located inside an
ancestraldomain?Iftheprojectisnotsituatedinsideanyancestraldomain,isitgoingtoaffectanyextant
IP/ICCcommunityoraretherebeneficiarieswhoaremembersoftheIP/ICCcommunity?Whatparticular
IP/ICCcommunityisinvolved?Whatistheirsocioeconomicstatusascomparedtothemainstreamgroup?
DidtheIP/ICCcommunitysolicitthesubprojectthemselves?Iftheydidnotsolicittheproject,havethey
beenconsultedandhavetheygiventheirendorsementoftheproject?Describetheconsultationprocess
thus far conducted. Indicate date, location and attendees of meetings. Describe the minutes of the
meetingsifany.Whataretheirconcernsandinputs?
Notethat:IftheProjectisinsideanyancestraldomain,orifthereareanyintactICC/IPcommunitytobe
affectedbytheproject,eitherofthefollowingshouldbesecured:i.Certificatefromthelocaltribalchieftain,
orfromthelocaltribalcouncilorfromNCIPthattheprojectispartoftheICC-IP’sdevelopmentplanoris
partoftheirAncestralDomainSustainableDevelopmentandProtectionPlan(ADSDPP);ii.Certificatefrom
thelocaltribalchieftainthattheprojectissolicitedbytheICC-IPthemselves;or,iii.Anendorsement(e.g.in
a formofaResolution) from ICC/IP community togetherwithevidenceof consultations conducted (e.g.
minutesofmeetingsandlistofattendees,issuesandconcernsraisedandhowtheywereaddressed).
3. Site andRight-of-Way acquisition–What is the ownership status of the proposed site or right-of-way?
Describethesiterequirementintermsofarea(sq.m),landtenure,andexistinglanduse.Describetheright-
of-wayrequirementsintermsofwidth,thetypes,ownershipoflandsandexistinglanduseofthelandsto
betraversedbythesubprojects.
Notethat:IfanylandsorROWneedtobeacquiredbytheLGUorthebeneficiarycommunity,thefollowing
arethedocumentaryshouldbesecured:
• Ifthelandispublicland,aSpecialLandUsePermit(SLUP)orleasefromDENRii.IfthelandisownedbyLGU,
evidenceofLGUownershipsuchasTitleiii.IfthelandistobepurchasedbytheLGUfromprivateowner(s),
evidenceofpurchasebytheLGUsuchasDeedsofSaleorTCTsiv.Iflandisdonatedbyprivateowners,
DeedofDonationandannotationofthepropertyattheRegistryofDeeds
• IfthesubprojectisinsideAncestralDomainorifnotinside,itadverselyaffectsanextantIP/ICCcommunity
who are not themselves beneficiaries of the subprojects, then an FPIC/CP should be secured under the
auspicesoftheNCIP.
4. Damagetostandingcrops,housesand/orproperties–Willtheconstructionoftheprojectresulttoany
cropand/orproperties?Describeandtrytoquantifythepotentialdamage.
Note that (potential) damage to cropsand/orproperties/assets shouldbe inventoriedand suitable
compensationschemesshouldbeworkedoutthroughconsultationwiththeownersofthecropsand
properties(e.g.throughaMOAortheEntitlementSurveyForm).Compensationofdamagesfollowing
theagreedschemesshouldbebasedonactualdamageorloss.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
127
5. Physicaldisplacementofpersons–Willtheproposedsubprojectresultintherelocationofhouses?How
manyhouseswillberelocated?Describetheconditionsoftheaffectedhousesandproperties.Whatarethe
socioeconomicconditionsoftheaffectedhouseholds?
6. Economicdisplacementofpersons–Willtheproposedsubprojectresultinthelossoflivelihoodorreduced
accessoffamiliestotheirtraditionallivelihoodsources?Notethatlossoflivelihoodmayresultfrom:lossof
asignificantportionofthehousehold’sfarmland,lossofbusinesssuchasduetolossofvendingstalls,etc.
Describethenatureoflossifany.
Notethatifthereisphysicaloreconomicdisplacementofpersons,aResettlementPlanshallbeprepared
B. EnvironmentalAssessment
1. Naturalhabitat–Describetheprojectsite(i.e.,thelandstobetraversedbytheproposedroad,theactual
siteofthePWSorstructure,etc.)intermsoflanduse,vegetation,wildlife,presenceofwaterecosystems,
endangeredandotherimportantspecies.Howaretheygoingtobeimpactedbytheproject?Istheproject
sitewithinanofficiallydeclaredorproposedprotectedareaofnaturalhabitat?
Note that: PRDP loan should not be used to fund subprojects involving civil works that encroach into
ProtectedAreasofnaturalhabitatsuchasareasdeclaredasNaturalParksunderNIPAS,exceptforNRM
subprojectsthatareallowedasperprovisionsoftheNIPASlawofBufferZone,orMultipleUseZone,and
thelawcreatingtheNaturalPark.
2. PhysicalCulturalResources–Arethereanystructure,monumentsorPhysicalCulturalResources(as
definedbelow)onsitethatwillbeaffectedbythesubproject?Describetheculturalandhistorical
significanceofthestructure/s,ifany.Describetheimpactoftheprojecttothestructure/s.Istheproject
sitepartofanimportantnaturalfeatureorlandscape?Howwilltheprojectchangeorimpactthe
landscape?Istheprojectareaapotentialarchaeologicalsite?Iftherearenosuchstructuresor
monumentsorPhysicalCulturalResourcestobeaffected,theassessmentshouldclearlysayso.
Notethat:TheWorldBankPolicyonPhysicalCulturalResourcesrequiresthatphysicalculturalresources
likelytobeaffectedbytheprojectshouldbeidentifiedandtheproject’spotentialimpactsontheseresources
beassessedasanintegralpartoftheEA.Culturalresourcesaredefinedasmovableorimmovableobjects,
sites, structures, groups of structures, and natural features and landscapes that have archaeological,
paleontological,historical,architectural,religious,aesthetic,orotherculturalsignificance.
Whentheprojectislikelytohaveadverseimpactsonphysicalculturalresources,appropriatemeasuresfor
avoidingormitigatingtheseimpactsshallbeidentifiedintheEA.Thesemeasuresmayrangefromfullsite
protectiontoselectivemitigation,includingsalvageanddocumentation,incaseswhereaportionorallof
thephysicalculturalresourcesmaybelost.
Physical/CulturalResources:IncludediscussiononArchaeologicalandPaleontologicalchancefindsduring
implementationoftheproject.PleaseseeAnnexH-2ofChanceFindsProcedureintheIESSFforreference.
3. HazardsandRiskAssessment (DrainageSituations,ErosionandFloodingPotential) - For theBusiness
Plan,includebriefdiscussiononthestatusoftheIPMprogramontheproductionsite.Additionally,include
discussion on solid and liquid waste management of the production and enterprise of the proposed
subproject.IncludeabriefdiscussiononthestatusoftheDAIPMProgram(KASAKALIKASAN)intheroad’s
influencearea.ThediscussionshouldincludeaquickassessmentofadequacyoftheeffortbyDAandrate
ofadoptionamongfarmersoftheIPMintheareaandbasedontheassessment,anactionplantointroduce
and/orfurthersupportKASAKALIKASANeffortsinthearea.Makesuretoreflectthemitigationmeasures
intheESMP.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
128
VII. FINANCIALPLAN
ELEMENTS DESCRIPTION
1. SourcesofFunds • Describeandhowmuchistheinvestmentrequirementforthe
enterprise
• Whereandhowwillthefundstosupporttheinvestmentrequirement
besourced?
2. FinancialProjections • Indicatefinancialassumptionstocomputerevenueandcoststreamsof
theenterprise
• Presentfinancialschedules(costschedule,salesschedule,etc)
• Presentfinancialforecasts
- Monthlyincomestatement(Year1)
- Monthlycashflow(Year1)
- Monthlybalancesheet(Year1)
- Incomestatement,cashflowandbalancesheetannualprojections
fromYear2toYear10
- Others,asnecessary
3. FinancialAnalysis Computethefinancialratios:NPV,FIRR,BCR,Paybackperiod,Breakeven
analysisperproduct
4. SensitivityAnalysis Computeanddiscusstheresultsofsubjectingtheenterpriseintodifferent
financialrisksandcases:
- 10%increaseincosts
- 10%decreaseinrevenue
- 10%increaseincostsand10%decreaseinrevenue
- 15%increaseincosts
- 15%decreaseinrevenue
5. Recordingsystem Howarefinancialtransactionsgoingtoberecordedandkept?
Whataretheinternalcontrolmechanismsthatwillbeemployedbythe
enterprise?
VIII. ECONOMICIMPACT(Describetheeconomicimpactofbenefitsthatthecommunitywillgenerateasa
resultoftheenterprise)
ELEMENTS DESCRIPTION
1. IncreaseFarmers
Income
• Describehowtheincomeoffarmerswillbeaffected?Comparethe
incomeoffarmersbeforeandaftertheProject.
•
2. Employment
Generation
• Istheenterprisegoingtoprovideemploymentopportunitiestothe
community?
• Howmaywillbeemployed?
• Providecomparisononthenumberofpeopleemployedbeforeand
aftertheProject
3. OtherEconomic
Impact
• DiscussothertargetedorpotentialimpactoftheProject
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
129
IX. SUSTAINABILITYMECHANISM
• Howistheenterprisegoingtosustainitsoperation?Describethesustainabilityplanfortheenterprisein
termsofthefollowing:
- Expandingoperation(couldeitherbeintermsofexpandingsourceofrawmaterialsand/or
increasingenterpriseoutput/capacity,upgradingfacilitiesandequipment,etc)
- Expandingmembership
- Utilizationofnetincomeorprofit(howwilltheincomebeused?)
• Whataretherequiredtechnicalassistancetoensurecontinuousoperation.Thetechnicalassistancecould
beforthefarmersand/ortheenterpriseitself.Whowillprovidethetechnicalassistance?Whatisthenature
oftheassistanceandthecostsinvolved?(Thiscouldbeprovidedintabularformat)
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
130
Annex12-A–I-REAPBusinessPlanOutline
SECTION DESCRIPTION
EnterpriseGeneral
Profile(SEEANNEX
12C)
Onepage‘CoverSheet’thatpresentsthefollowing:(i)titleofthesubproject/enterprise;(ii)
locationofthesubproject;(iii)ProponentGroup/LeadProponent;iv)nameandtelephone
numberofthecontactpersonorleadfirmthatwillrepresenttheclusterofbusiness
enterprises;(v)thecompositionoftheclusterofenterprises;targetmarketswith
correspondingvolume;(vi)summarytableofsubproject’sinvestmentrequirementby
componentandbysourceoffund(vii)roleoftheenterpriseinvaluechainupgrading;(viii)
enterpriseobjectivesbriefdescriptionofthesubproject;(ix)economicbenefits;(x)financial
indicators;and(xi)SummaryDataSheetwhichcontainstheMandEparameters
ExecutiveSummary Amaximumoftwo-pagebriefpresentingthefollowingkeypoints:(i)rationaleforthe
proposedsubproject,itscontributiontovaluechainupgradingandtofarmers/fishers
income;(ii)descriptionofthebusinessenterprise(missionstatement/goals/objectives;(iii),
experiencesandcurrentstateoftheenterprise;(iv)operationalplan;(v)economicbenefits;
and(v)resultsofthefinancialanalysis
1.Descriptionof
theBusiness
Enterprise
Discussiononthefollowing:(i)opportunityfortheenterprise/PGanditsproducts(howthe
proposedenterprisewillmakemoney,theproductanditsvalue),shouldrelatetothevalue
chainupgrading;(ii)objectivesoftheenterprise;(iii)businessoverview(summaryofthe
currentstateorexistingprojects/accomplishmentsoftheenterprise/PG,typeofbusiness
enterprise(registration),compositionoftheclusterofenterprises,expansionorstart-up,and
historyofthebusinessanditsprimarystrengths);(ivproductandservices(general
descriptionoftheproductsandservices)offered/undertaken;and(v)roleoftheenterprise
invaluechainupgrading/supporttocommodityvaluechainupgrading(constraints/
opportunitiesidentifiedintheVCA,prioritizationinthePCIP(discussthespecificsegment(s)
ofthevaluechaininwhichtheenterprisebelong;constraint(s)orgap(s)whichtheenterprise
aimstoaddressaswellastheopportunitiesthatmayhelpindevelopingorupgradingthe
valuechain,ifany;over-allcontributionoftheenterprisetothedevelopmentofthe
commodity)
2.MarketAnalysis Topicsinclude(i)marketcharacteristics(briefindustryprofile,industryoutlook,newproduct
development,markettrendsandcompetition);(ii)marketstructure(numberofsellersand
itsgeneralcharacteristicsandbehavior,numberofbuyersanditsgeneralcharacteristicsand
behavior,horizontalandverticalrelationships,priceandcoststructure);(iii)customer
analysis(description,characteristicsandbehaviorofcustomers,location,channelsof
distribution,operationsandpractices,volumerequirementsandspecifications,horizontal
andverticalrelationships;and(iii)supplyanddemandanalysis(supplyanddemandgap).
3.Competitor
Assessment
Discusstheprofileofthecompetitorsfocusingonthefollowingindicators:(i)descriptionand
product/servicefeaturesofidentifiedcompetitor;(ii)geographiclocationandareaof
influence;(iii)channelsofdistribution;(v)relationshipwithsuppliers/buyers;(v)marketing
strategies(price,product,place,positioning,promotion);(vi)marketshare;and(vii)financial
strength/costposition
4.MarketingPlan Discussthe4PsofMarketingfocusingonthefollowing:(i)product(productuses,attributes
andfunctionalbenefits,qualitycontrols/services,standards,developmentandtechnological
trends);(ii)pricingstrategies(basisforpricing,howisthepricegoingtobeestablished;what
isthedifferencefromcompetitors);(iii)place(describehowtheproduct/servicewillbe
distributedandwhatgeographicalarea);and(iv)promotion.
5.OperationalPlan Describesthefollowing:(i)ownershipandmanagement(includingorganizationalstructure);
(ii)resourcesandproduction(productionmethods-theprocessandtheinputsrequiredfor
eachprocess,andstaffing);(iii)facilitiesandequipment,fulldescriptionandspecificationsof
thefacilitiesandequipmentneededintheoperationoftheenterpriseandthelocation,esp
ofthecivilworks(includingsourcesandestimatedcosts);(iv)operations(operational
schedulesandprocedures);(v)implementationplan(ganttchartofactivities);and
compliancetolocalandnationalregulations(businesspermits,license,etc.)
6.Socialand
Environmental
Assessment
Discussthefollowing:(i)SocialSafeguards–subprojectbeneficiaries,indigienous
community,siteandrightofwayacquisition,damagetostandingcrops/house/properties,
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
131
SECTION DESCRIPTION
physicaldisplacementofpersons,economicdisplacementofpersons(ii)Environmental
Assessment–naturalhabitat,physical-culturalresources,hazardandriskassessment
7.FinancialPlan Coversthefollowing:(i)Investmentrequirementbycomponentandbyfundsource(identify
and discuss the detailed investment requirement by subproject component, identify fund
source–fixedassetsandoperatingexpenses(variableandfixedcosts));(ii)financialanalysis
(settingofassumptions–productionschedule,salesschedule,costsschedule,etc,compute
formonthlyincomestatementandmonthlycashflowforthe1stYearofoperation,financial
projectionsfor10years(incomestatement,cashflow,balancesheet,computeanddiscuss
financialindicators–NPV,FIRR,BCR,ROI,Paybackperiod,break-evenanalysis);(iii)risksand
Sensitivity Analysis (discuss the risks and uncertainties that may be experienced by the
enterpriseincludingthemitigatingmeasures–environmental,organization,operationaland
social, compute sensitivity scenarios: a)10% increase in cost; b)10% decrease in revenue;
c)10% increase in cost and10%decrease in revenue; d) 15% increase in cost; ande) 15%
decreaseinrevenue);and(iv)financial
recordingandmanagementsystem(discussrecordkeepingandfinancialmanagement
systemthatwillbeadoptedbytheenterprise)
8.Socio-Economic
Benefits
Discussiononthefutureplansoftheenterprise,howistheincomegoingtoutilize(i)
Increaseinfarmersincome(comparisonbeforeandafterPRDPcomputedforthe10-year
period,numberoffarmersinvolved;(ii)employmentgeneration(comparisonbeforeand
afterPRDP;(iii)Otherpotentialbenefits
9.Sustainability
Mechanism
Discussiononthefollowing:(i)futureplansofthePGontheoperationsoftheenterprise
(howwilltheincomegeneratedfromthesubprojectbegoingtobeutilized,anyplanson
expansion;and(ii)provisionoftechnicalassistance/support(whenwillthePGanditscluster
membersincludingthefarmersmembersgettheneededtechnicalsupport,howwillitbe
availed;whowillprovideit;whatmechanism,sourceoffundforthetechnicalsupport.
10.Annexes AnnexA–WorkandFinancialPlan
AnnexB-ProcurementPlan
AnnexC–PRA-RSA(forGEFsitesandNRMrelatedenterprisesonly)
AnnexD–DetailedEngineeringDesign(DED)(inc.facilitiesandequipmenttechnicalplan)
AnnexE–ProgramofWorks(POW)(inc.constructionSchedule(barchart/s-curve)forthe
facilitiesandequipment)
11Attachments Seechecklistofrequirementsfortheattachments(Annex13-A)
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
132
Annex12-B–SUBPROJECTPROPOSALOUTLINEFORMICRO-ENTERPRISESUBPROJECTS
SECTION DESCRIPTION
EnterpriseGeneral
Profile(SEEANNEX
12C)
Onepage‘CoverSheet’thatpresentsthefollowing:(i)titleofthesubproject/enterprise;(ii)locationof
thesubproject;(iii)ProponentGroup/LeadProponent;iv)nameandtelephonenumberofthecontact
personorleadfirmthatwillrepresenttheclusterofbusinessenterprises;(v)thecompositionofthe
clusterofenterprises;targetmarketswithcorrespondingvolume;(vi)summarytableofsubproject’s
investmentrequirementbycomponentandbysourceoffund(vii)roleoftheenterpriseinvaluechain
upgrading;(viii)enterpriseobjectivesbriefdescriptionofthesubproject;(ix)economicbenefits;(x)
financialindicators;and(xi)SummaryDataSheetwhichcontainstheMandEparameters
ExecutiveSummary Amaximumoftwo-pagebriefpresentingthefollowingkeypoints:(i)rationalefortheproposed
subproject,itscontributiontovaluechainupgradingandtofarmers/fishersincomeordamagecaused
bythecalamityorconflictandobjectivesoftheenterprise;(ii)briefdescriptionoftheproponent,
targetmarket,managementandownershipoftheenterprise,operationalplan;(iii),resultoffinancial
analysis;(iv)economicbenefits;and(v)sustainabilitymechanism
1.ProjectRationale Discussiononthefollowing:(i)backgroundorjustificationfortheproposal;(ii)objectivesofthe
enterprise;(iii)businessoverview(summaryofthecurrentstateorexistingprojects/accomplishments
oftheenterprise/PG,typeofbusinessenterprise(registration),compositionoftheclusterof
enterprises(ifany),expansionorstart-up,andhistoryofthebusinessanditsprimarystrengths);and(v)
roleoftheenterpriseinvaluechainupgrading/supporttocommodityvaluechainupgrading(discuss
thespecificsegment(s)ofthevaluechaininwhichtheenterprisebelong;constraint(s)orgap(s)which
theenterpriseaimstoaddressaswellastheopportunitiesthatmayhelpindevelopingorupgrading
thevaluechain,ifany;over-allcontributionoftheenterprisetothedevelopmentofthecommodity)
MarketStudy Discussiononthefollowing:(i)productdescription-discussthekindofproducttobeproducedbythe
projectincludingquantitytobesold,qualitystandards/specifications;(ii)targetmarket/buyerincluding
volume requirement and marketing arrangements; (iii) supply and demand situation discuss the
availability of supply, major producing municipalities, volume and hectarage, discuss the market
demand,majorbuyers,andvolumerequirements;(iv)Marketingstrategies-discusshowthePGintend
tomarketitsproductincludingtheformofproducttobesold,thepackagingtobeused,brand(ifany),
pricingstrategy for theproduct,placeofdistributionandhowwill theproductarriveat theplaceof
distribution (mode of transportation used), picked-up or delivered, frequency of selling, and the
promotionalactivitiesthatwillbeundertakentomaketheproductknowntothetargetconsumers
OperationalPlan 2. Discussthefollowing:(i)OwnershipandManagement-howthesubprojectwillbemanagedincluding
organizationalstructure,projectmanagementanditsrolesandfunctions;capabilityofthePOtohandle
theproject;doesthestaffhavethenecessaryskills;trainingneeds;numberofpersonnelneededforthe
projectimplementationandoperation;includewhentheorganizationwillberegisteredtoCDAorSEC,
if not yet registered); (ii) production and operational process - (discuss how the project will be
operationalized, provide process flow, resources needed); (iii) facilities and equipment - discuss the
facilitiesandequipmentrequiredincludingspecificationsandcapacity;forcivilworksorinfrastructure
describewhere itwill be located, access to road network, technical design or specifications; include
wheretosourcethefacilitiesandequipmentandestimatedcostsbyfundsource)
4.Socialand
Environmental
Assessment
3. Discussthefollowing:(i)SocialSafeguards–subprojectbeneficiaries,indigienouscommunity,siteand
rightofwayacquisition,damagetostandingcrops/house/properties,physicaldisplacementofpersons,
economic displacement of persons (ii) Environmental Assessment – natural habitat, physical-cultural
resources,hazardandriskassessment
FinancialPlan Presentanddiscussthefollowing:(i)financialassumptionsusedincomputingtheinvestment/project
cost,salesandexpenses;(ii)Investment/ProjectCost(indetailsincludingfixedcapital,workingcapital
andpre-operatingexpenses);(iii)Financialassumptions-productionScheduleandsalesschedule(at
leastone-yearperiodforrestoration/rehabilitationsubprojectoratleast3-yearperiodforothermicro-
enterprisesubprojects);(iv)FinancialProjections-monthlyincomestatementandcashflowforYear1,
atleastoneyearIncomeStatement(forrestoration/rehabilitationsubprojectofatleast3yearsannual
income statement, balance sheet and cash flow; (v) Financial ratio– compute for ROI (for one year
projectiononly);FIRR;NPV;BCR;PaybackPeriod
6. Socio-Economic
Benefits
Discussiononthefutureplansoftheenterprise,howistheincomegoingtoutilize(i)Increaseinfarmers
income (comparison before and after PRDP computed for the 10-year period, number of farmers
involved;(ii)employmentgeneration(comparisonbeforeandafterPRDP;(iii)Otherpotentialbenefits
7. SustainabilityMechanism
Discussiononthefollowing:(i)futureplansofthePGontheoperationsoftheenterprise(howwillthe
incomegeneratedfromthesubprojectbegoingtobeutilized,anyplansonexpansion;and(ii)provision
of technical assistance/support (when will the PG and its cluster members including the farmers
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
133
SECTION DESCRIPTION
membersgettheneededtechnicalsupport,howwillitbeavailed;whowillprovideit;whatmechanism,
sourceoffundforthetechnicalsupport.
8. Annexes AnnexA–WorkandFinancialPlan
AnnexB-ProcurementPlan
AnnexC–PRA-RSA(forGEFsitesandNRMrelatedenterprisesonly)
AnnexD–DetailedEngineeringDesign(DED)(inc.facilitiesandequipmenttechnicalplan)
AnnexE–ProgramofWorks (POW) (inc.constructionSchedule (barchart/s-curve) for the
facilitiesandequipment)
9. Attachments Seechecklistofrequirementsfortheattachments(Annex13-B)
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
134
Annex12C–TEMPLATEOFTHEENTERPRISEGENERALPROFILE
SubprojectTitle
SubprojectIDNo.
Location
LeadProponentGroup
ClusterMembers Listdownallcoops/associationsthatareincludedinthesubproject
FinancingModalityBasedonthe
AmountofSubproject
Indicateifmicro,small,mediumsubproject
TypeofPGUndertaking Indicateifstart-up,upgradingorexpansion,GEFarea,rehabilitation/
restoration
NatureofExpansion/Upgrading(for
SPsundertheexpansion/upgrading
Category)
Increasehectarage
Acquisitionofnewequipment
Renovationofexistingbuilding
etc
Commodity/Product(s)/Service(s)
VolumeofProduction
(totalproductionoftheenterprise)
ExistingVolume(Unit):
TargetVolume(Unit):
Product VolumeofProduction(Unit)
Existing(Y0) Y1 Y10
TargetMarket/s Indicatenameofbuyer,volumetobesold(existingand/ortarget
volume)andarrangements
Target
Buyer
(Specify)
Existing
Volsold
(Unit)
Target
Vol
sold
(Unit)
Frequency
ofdelivery
Payment
Terms
Marketing
Arrangements
TotalInvestmentCost/Amountofthe
BusinessPlan
InTabularFormbrokendownbyfundsourceandspecificinvestment
requirements
Detailed
Items
LP GOP LGU PGEquity
Cash Kind
Enterprise
Operation
(specify)
CivilWorks
(specify)
Total
Investment
Cost
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
135
SupporttoCommodityValueChain
Upgrading
BriefdescriptionoftheVCAsegmentbeingsupportedorstrengthenedby
theproposedenterprisecitingVCAfindingsonconstraints/gapsand
opportunities
BriefDescriptionoftheSubproject Brieflydiscusswhatthesubprojectintendstodo(descriptionofthe
businessmodel)
EnterpriseorSubprojectObjectives:
Enumeratethegeneraland/orspecificobjectivesofthesubproject
1.
2.
3.
NewWaysofDoingThings/
Innovations
DescribehowthePRDPinterventionwillimprovethewayofdoingthings
ofthePGanditsmembersintermsoftechnology,practices,processes,
etc
Socio-EconomicBenefits:
A. No.ofDirectIndividual
Beneficiaries(specifynumberper
PG)
Note:PGmeanstheaffiliate
coop/association.Applicableonlyfor
clusteringofproponents
B. No.ofHouseholdBeneficiaries
EmploymentGeneration
PG
Cluster
Member
No.ofIP No.ofNon-
IP
TotalNo.of
Individual
Beneficiaries
Male F M F
(Nameof
PG)
(Nameof
PG)
Total
PGCluster
Member
No.of
IP
No.of
Non-
IP
TotalNo.of
HH
Beneficiaries
(Nameof
PG)
(Nameof
PG)
Total
JobTitle/
Position
NumberofEmployees
Existing New/Additional Increment
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
136
InvestmentCostperBeneficiary (Computedasthetotalcostofinvestmentdividedbythetotalnumberof
directindividualbeneficiaries)
TargetIncreaseinFarmersIncome
Numberof
Farmers
Involved
AverageAnnualFarmers
Income(PhP)
Total
Incremental
Income(PhP)
BeforePRDP AfterPRDP
FinancialAnalysis
NetIncomeoftheEnterprise:
FinancialRatios:
Break-evenAnalysis(foreach
product):
ExistingNetIncome(Baseline):
ProjectedAverageNetIncome:
FIRR:PaybackPeriod:
ROI:Benefit-CostRatio:
BEVolume(unit):BEPrice(PhP):BESales(PhP):
TechnicalSupportAgencies
Indicateagenciesthatwillprovidetechnicalsupport/assistance,natureof
assistance,costsinvolvedandarrangements
Agency Natureof
Technical
Assistance
Estimated
Cost
SourceofFunding
DurationofProjectImplementation:
TargetStartDate:(targetdateforthefirstNOL2)
TargetCompletionDate:
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
137
SubprojectSummaryData/MonitoringSheet(Thissummarydatasheetshouldshowtheindicatorsthatwouldbe
usefulinmeasuringtheimpactofthesubprojectorPRDPinterventions.TheimpactshouldindicatetheProject
DevelopmentObjectivesandthesub-projectspecificobjectives)
Parameters Baseline Year1 Year2 Year3 Year4 Year5 Year6 Year7 Year8 Year9 Year10
Farmers
income
HHincome
Marketable
surplus
Incomeof
enterprise
No.of
women
engaged
Employment
generated
Coopor
Association
membership
(indicate
otherSP
indicators)
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
138
Annex13-A–CHECKLISTOFREQUIREMENTSFOR
SMALLANDMEDIUMENTERPRISESUBPROJECT
SUB-PROJECTTITLE:
LOCATION:
PROPONENTGROUP:
TOTALINVESTMENTREQUIREMENT:
ENTERPRISEPROJECTFUND:
INFRASTRUCTURECOST:
PGEQUITY:
CHECKEDBY:
DATECHECKED:
I.EligibilityRequirementsoftheProponentGroupATTACHED
REMARKSYES NO
1.LetterofIntent
2.CertificateofRegistration
3.CertificateofGoodStanding
4. Latest Audited Financial Report in the last 3 years (for medium
enterprisesubproject)orPhotocopyoftheOfficialReceipt(OR)(For
SmallEnterprisesubprojects
5.PLGUEvaluationon theFinancialandOrganizationalCapabilityof
theProponent
6. Accomplishment Reports and Photographs of the Projects
UndertakenintheLast3yearsonAgri-FisheryorSimilarProjects(for
medium enterprise subproject) or Accomplishment reports and
photographsofagri-fisheryorrelatedprojectsundertakenforatleast
oneyearofoperation(ForSmallEnterprisesubproject)
7.ProofofEquity(Cash-BankCertificate);LandTitle/LeaseContract/
DeedofDonation,etc(asapplicable)
8.CertificateofNoUnliquidatedAccountwithPLGU
9.CertifiedtruecopyoftheArticlesofIncorporation/Cooperationand
bylaws
10.AswornaffidavitoftheSecretaryoftheNGO/POthatnoneofits
incorporators,organizers,directors,orofficialsisanagentoforrelated
byconsanguinityoraffinityuptothefourthcivildegreetotheofficials
ofthegovernmentagencyauthorizedtoprocessand/orapprovethe
proposal,theMOAandthereleaseoffunds.
11.SwornAffidavitof theSecretaryof theNGO/PO thatnoneof its
officialsareemployeesoftheDAortheimplementingLGU.
Republic of the Philippines Department of Agriculture PHILIPPINE RURAL DEVELOPMENT PROJECT
National Project Coordination Office 4
th Floor, DA Building, Elliptical Road, Diliman
Quezon City 1100, Philippines
FORM1
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
139
II.BusinessPlanRequirementsATTACHED
REMARKSYES NO
1.ValueChainAnalysis(VCA)
2.ApprovedPCIP
3.Form2A–BusinessPlanTrackingForm
4.Annex6-EnterprisePrioritizationresult(DulysignedbyPPMIUI-
REAPHead)
5.Annex9-ProponentGroupSelectionresult(DulysignedbyPPMIU
I-REAPHead)
6.Annex15-I-REAPInitialEvaluationForm(EvaluatedbyRPCOI-
REAPStaff,verifiedbyRPCOI-REAPHead,endorsedbyRPCO
AlternateFocalandnotedbyRPCOProjectDirector)
7.Annex16-BusinessPlanAppraisalorEvaluationForm(usingI-REAP
Scoresheet)–signed
8.TechnicalandEvaluationReviewReportdulysignedbythe
TechnicalReviewTeam
9.ProponentGroupProfile
10.FarmersProfile
11.PRA-RSA(forGEFsitesandNRMrelatedenterprisesonly)
12.SupplyContractwithparticipatingfarmers
13.MarketingContractwithbuyers
III.ForInfrastructureComponent(PleasecheckAnnexB:Review
ChecklistforBuildingsoftheI-REAPTechnicalGuidelinesfordetails
perrequirement)
ATTACHED REMARKS
YES NO
1.DetailedEngineeringDesign–signedbytheGovernor
a.Coversheet
b.IndexofDrawings
c.DetailsofArchitecturalDrawings
i.Title/SignatoryBlock
ii.VicinityMap/LocationPlan
iii.SiteDevelopmentPlan
iv.Perspective,drawnatanyconvenientscale
v.FloorPlan(s)
vi.Elevations,atleastfour(4)
vii.Sections,atleasttwo(2)
viii.CeilingPlan(s)
ix.RoofPlan
x.Details,intheformofplans,elevations/sections(min.
scaleof1:50)
xi.ScheduleofDoorsandWindows
xii.ScheduleofFinishes(ingraphicform)
d.DetailsofStructuralDrawings
i.FoundationPlan
ii.FloorFramingPlan(s)
iii.RoofFramingPlan
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
140
iv.Schedule/DetailsofFootings/Columns/Girders/
Beams/Slabs
v.DetailsofTrusses/ConnectionsorDetailsofShear
Walls/ElevatorShaft
vi.DetailsofStair(s)
vii.StructuralDesignAnalysis/Computations
e.DetailsofPlumbingDrawings
i.LocationPlanandSiteDevelopmentPlan
ii.PlumbingPlans
iii.IsometricDrawings
iv.DetailofSepticTank,SedimentationTank,ifany
v.DetailofCatchBasins
vi.DetailofElevatedWaterTank,ifany
vii.LegendandGeneralNotes
f.DetailsofElectricalDrawings
i.LocationPlanandSiteDevelopmentPlan
ii.LegendofSymbols
iii.GeneralNotesand/orSpecifications
iv.PlanforPower
v.PlansforLightingandReceptacleOutlets
vi.PlansforFireDetectionandAlarmCircuits
vii.FireAlarmRiserDiagram
viii.ScheduleofLoads
ix.OneLineDiagram
x.OtherDetails
xi.PlansforLightningProtection
xii.PlansandSpecificationsforIndoororOutdoor
Substation
xiii.Title/SignatoryBlock
xiv.DesignAnalysis
xv.TechnicalSpecifications
xvi.DetailedQuantityEstimates
g.DetailsofMechanicalDrawings
i.LegendofSymbols
ii.GeneralNotesand/orSpecifications
iii.PlansforAirConditioningandVentilationSystems
iv.PlansforWaterPumpingSystem
v.PlansforFireSuppressionSystem
vi.PlansforElevator
vii.PlansforGeneratingSets
viii.OtherDetails
ix.OtherPlans
x.Title/SignatoryBlock
xi.DesignAnalysis
xii.TechnicalSpecifications
xiii.DetailedQuantityEstimates
h.DetailsofElectronicsDrawings
i.LocationPlanandSiteDevelopmentPlan
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
141
ii.LegendorSymbols
iii.GeneralNotesorSpecifications
iv.PlansforAuxiliary/CommunicationSystems
v.AuxiliaryCommunicationRiserDiagrams
vi.OtherDetails
vii.Title/SignatoryBlock
viii.DesignAnalysis
ix.TechnicalSpecifications
x.DetailedQuantityEstimates
2.ProgramofWorks(POW)–signedbytheGovernor
IV.SocialEnvironmentalSafeguard(SES)Requirements(LargeScale
Enterprise)
ATTACHED REMARKS
YES NO
1.Dulysigned(byPPMIU,PSO,andRPCO)AnnexA-2SESScreening
Form
2.SA/EAoftheBusinessPlan
a. Consultation/s: Minutes, attendance and photos during all
consultations (project beneficiaries meeting, PAPs consultation,
FPICorbroadbasedconsultation,TribalChieftainCertification)
b. Executive Order with Grievance Redress Mechanism Point
PersonorCommitteeanddiscussionintheBP(2015andbeyond)
for the LGUs. For PGs, a Grievance Point person should be
identified.
c.LetterofRequests:DENRforECCandcuttingpermit;PCAfor
cuttingpermit;NCIPforCertificateofPre-Condition;ElectricCoop
for transferof electricposts (whatever is applicable) ForNOL2,
permits/certifications should already be secured and attached
accordingly.
d.AnnexH-1IP/ICCPlan(refertoPRDP’sIESSFforguidanceon
whentheIPPlanisrequired)
3. Duly signed ESMP attachedwithAnnexH-2Archaeological and
Paleontological Chance Finds (Templates have been provided
dependingontheCategoryoftheEnterprise)
4.SiteAcquisitionDocumentssuchas:
a.Form1–EntitlementSurveyofAffectedPersons
b.Form2–InventoryofEntitlementSurveyofAffectedPersons
c.Proofofownership(TitleorDeedofSaleofthesite,Deedof
SaleorTransferCertificateTitle/TCT)
d. Notarized Waiver/Quit Claims and/or Notarized Deed of
Donations
e. Contract of Lease for 50 years and subject for renewal or
option tobuy.ContractofUsufruct for25yearsand subject for
renewal.
f. Rehabilitation/Relocation/Resettlement Action Plan and
Agreement between Proponent LGU and PAPs if with
Resettlement
g.AgreementbetweenthePAPsandLGUforthecompensation
oftheirproperties
5.DisclosureofSESDocumentsbythePSO–SESUnit(SA/EAofthe
BP;IEE/EIA;ECC;DulysignedESMP)
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
142
6.SocialInclusivenessScoringSheetforPGSeekingI-REAPFunding
V.GeomappingandGovernanceUnit(GGU)RequirementsATTACHED
REMARKSYES NO
CommunityLivelihood/EnterpriseSubproject
1.PlacemarkofLocalGovernmentOffice(i.e.Capitol,Municipal
Hall,Barangayhall)wherethesubprojectisunderitsjurisdiction
2.DigitizedtrackofthenearestroutefromLocalGovernment
Officetotheproposedsubprojectsite
3.Officelocationoftheproponentgroup
4.OfficelocationofClusterGroup/Coop/organizationoffice
5.Placemarkwhereitisapplicable,dependingonthebusiness
plan:
a.Locationoflocalmajortargetmarkets(withintheprovince);
b.Locationofnon-localmajortargetmarkets(excluding
overseas);
c.Locationofmajorcompetitors;
d.Locationof(existing&proposed)garage(haulingtruck,farm
tractor,deliveryvan);
e.Locationofexisting&proposedDock(motorizedbanca,
module,fishcage);
f.OtherRelated/SimilarStructurewiththesamelineof
business(existing&proposed);
6.ProposedConstructionsiteofPermanentStructures(i.e
processingplant,warehouse,dryeretc.)
a)Geotaggedphotos(atleastfourgeotaggedphotoofsiteand
existingpermanentstructure)oftheproposedsite;
b)Digitizedpolygonofthevicinityorsitedevelopment;
7.SourceLocationofRawMaterial
Raw material source location determines the availability and
sufficiency of raw material to supplied/processed in the propose
business enterprise. The following are the classificationwhere it is
applicabletobusinessplan;
a.1)CommodityPolygon(digitized;atleast50%ofthetotal
commodityareaasstatedinthebusinessplan)or100%ifthe
proposalincludeproductionsupport
a.2)Minimumoffour(4)geotaggedphoto(commodity)isrequired
perparticipatingcluster.
b. Farm Animal (carabaos, cows, goat, hog, chicken)
Placemark/marker;
c. Farmmachinery target user (ie. Tractor rental/services for
landpreparation);(polygon)
7.Placemark&geotaggedphotos(KMZ)submittedtoRPCO-GGU
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
143
VI.ProcurementRequirementsATTACHED REMARKS
YES NO
1. Procurement Plan – at least signed by the PG, and PPMIU BAC,
however,onthefinalsubmissionthedocumentmustbesignedbythe
Governor
2.Completespecifications–goods
3.PhilippineBiddingDocumentsforworks/infrastructure(electronic
ordigitalcopy)
4.PhilippineBiddingDocumentsforgoodsusingNCBasmodeof
Procurement(electronicordigitalcopy)
VII.FinanceRequirementsATTACHED REMARKS
YES NO
1.MemorandumofAgreement(MOA)betweenDAandLGU
2.RPABResolution
3. SP Resolution Authorizing the LCE to sign IMA, Appropriation
Ordinance,Contracttoprovidefundsandothers.
4. Local Finance Committee (LFC) certificate of the LGU equity/
AppropriationOrdinance
5.WorkandFinancialPlan(WFP)–signedbyPG,PPMIUandGovernor
VIII.M&ERequirementsATTACHED REMARKS
YES NO
1.SubprojectProfile–signed
2.DataCaptureForm–signed
FinalBusinessPlanshouldbesubmittedinsoftbindwithattachmentsinringbindwithe-copyinCD
format.Finalbusinessplanwithcompleteattachmentsshouldbepreparedin5copiestobe
distributedasfollows:1)PGcopy;2)LGUcopy;3)1RPCOcopy;4)PSOcopy;5)NPCOcopy;6)WB
copy(onlyifWBwillissuetheNOL)
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
144
Annex13-B–CHECKLISTOFREQUIREMENTSFORMICRO-ENTERPRISESUBPROJECT
SUB-PROJECTTITLE:LOCATION:
PROPONENTGROUP:
TOTALINVESTMENTREQUIREMENT:
ENTERPRISEPROJECTFUND:
INFRASTRUCTURECOST:
PGEQUITY:
CHECKEDBY:
DATECHECKED:
I.EligibilityRequirementsoftheProponentGroupATTACHED
REMARKSYES NO
1.LetterofIntent
2.CertificateofRegistration
3.CertificateofGoodStanding
4. PhotocopyofOfficialReceipt
5. Certified true copy of the policies, systems and procedures/
CertifiedtruecopyoftheArticlesofIncorporation/Cooperationandby
laws
6.ProofofEquity(Cash-BankCertificate);LandTitle/LeaseContract/
DeedofDonation,etc(asapplicable)
7.CertificateofNoUnliquidatedAccountwithPLGU
8.AswornaffidavitoftheSecretaryoftheNGO/POthatnoneof its
incorporators,organizers,directors,orofficialsisanagentoforrelated
byconsanguinityoraffinityuptothefourthcivildegreetotheofficials
ofthegovernmentagencyauthorizedtoprocessand/orapprovethe
proposal,theMOAandthereleaseoffunds
9. Sworn Affidavit of the Secretary of the NGO/PO that none of its
officialsareemployeesoftheDAortheimplementingLGU.
II.BusinessPlanRequirementsATTACHED
REMARKSYES NO
1.ValueChainAnalysis(VCA)
2.ApprovedPCIP
3.Form2A–BusinessPlanTrackingForm
4.Annex6-EnterprisePrioritizationresult(DulysignedbyPPMIUI-
REAPHead)
5.Annex9-ProponentGroupSelectionresult(DulysignedbyPPMIU
I-REAPHead)
Republic of the Philippines Department of Agriculture
PHILIPPINE RURAL DEVELOPMENT PROJECT National Project Coordination Office 4
th Floor, DA Building, Elliptical Road, Diliman
Quezon City 1100, Philippines
FORM1
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
145
6.Annex15-I-REAPInitialEvaluationForm(EvaluatedbyRPCOI-
REAPStaff,verifiedbyRPCOI-REAPHead,endorsedbyRPCO
AlternateFocalandnotedbyRPCOProjectDirector)
7.Annex16-BusinessPlanAppraisalorEvaluationForm(usingI-REAP
Scoresheet)–signed
8.TechnicalandEvaluationReviewReportdulysignedbythe
TechnicalReviewTeam
9.ProponentGroupProfile
10.FarmersProfile
11.PRA-RSA(forGEFsitesandNRMrelatedenterprisesonly)
12.SupplyContractwithparticipatingfarmers
13.MarketingContractwithbuyers
III.ForInfrastructureComponent(PleasecheckAnnexB:Review
ChecklistforBuildingsoftheI-REAPTechnicalGuidelinesfordetails
perrequirement)
ATTACHED REMARKS
YES NO
1.DetailedEngineeringDesign–signedbytheGovernor
a.Coversheet
b.IndexofDrawings
c.DetailsofArchitecturalDrawings
i.Title/SignatoryBlock
ii.VicinityMap/LocationPlan
iii.SiteDevelopmentPlan
iv.Perspective,drawnatanyconvenientscale
v.FloorPlan(s)
vi.Elevations,atleastfour(4)
vii.Sections,atleasttwo(2)
viii.CeilingPlan(s)
ix.RoofPlan
x.Details,intheformofplans,elevations/sections(min.
scaleof1:50)
xi.ScheduleofDoorsandWindows
xii.ScheduleofFinishes(ingraphicform)
d.DetailsofStructuralDrawings
i.FoundationPlan
ii.FloorFramingPlan(s)
iii.RoofFramingPlan
iv.Schedule/DetailsofFootings/Columns/Girders/
Beams/Slabs
v.DetailsofTrusses/ConnectionsorDetailsofShear
Walls/ElevatorShaft
vi.DetailsofStair(s)
vii.StructuralDesignAnalysis/Computations
e.DetailsofPlumbingDrawings
i.LocationPlanandSiteDevelopmentPlan
ii.PlumbingPlans
iii.IsometricDrawings
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
146
iv.DetailofSepticTank,SedimentationTank,ifany
v.DetailofCatchBasins
vi.DetailofElevatedWaterTank,ifany
vii.LegendandGeneralNotes
f.DetailsofElectricalDrawings
i.LocationPlanandSiteDevelopmentPlan
ii.LegendofSymbols
iii.GeneralNotesand/orSpecifications
iv.PlanforPower
v.PlansforLightingandReceptacleOutlets
vi.PlansforFireDetectionandAlarmCircuits
vii.FireAlarmRiserDiagram
viii.ScheduleofLoads
ix.OneLineDiagram
x.OtherDetails
xi.PlansforLightningProtection
xii.PlansandSpecificationsforIndoororOutdoor
Substation
xiii.Title/SignatoryBlock
xiv.DesignAnalysis
xv.TechnicalSpecifications
xvi.DetailedQuantityEstimates
g.DetailsofMechanicalDrawings
i.LegendofSymbols
ii.GeneralNotesand/orSpecifications
iii.PlansforAirConditioningandVentilationSystems
iv.PlansforWaterPumpingSystem
v.PlansforFireSuppressionSystem
vi.PlansforElevator
vii.PlansforGeneratingSets
viii.OtherDetails
ix.OtherPlans
x.Title/SignatoryBlock
xi.DesignAnalysis
xii.TechnicalSpecifications
xiii.DetailedQuantityEstimates
h.DetailsofElectronicsDrawings
i.LocationPlanandSiteDevelopmentPlan
ii.LegendorSymbols
iii.GeneralNotesorSpecifications
iv.PlansforAuxiliary/CommunicationSystems
v.AuxiliaryCommunicationRiserDiagrams
vi.OtherDetails
vii.Title/SignatoryBlock
viii.DesignAnalysis
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
147
ix.TechnicalSpecifications
x.DetailedQuantityEstimates
2.ProgramofWorks(POW)–signedbytheGovernor
IV.SocialEnvironmentalSafeguard(SES)Requirements(Large
ScaleEnterprise)
ATTACHED REMARKS
YES NO
1.Dulysigned(byPPMIU,PSO,andRPCO)AnnexA-2SESScreening
Form
2.SA/EAoftheBusinessPlan
a. Consultation/s:Minutes, attendance andphotos during all
consultations (project beneficiariesmeeting, PAPs consultation,
FPICorbroadbasedconsultation,TribalChieftainCertification)
b. ExecutiveOrderwith Grievance RedressMechanism Point
PersonorCommitteeanddiscussionintheBP(2015andbeyond)
for the LGUs. For PGs, a Grievance Point person should be
identified.
c.LetterofRequests:DENRforECCandcuttingpermit;PCAfor
cuttingpermit;NCIPforCertificateofPre-Condition;ElectricCoop
fortransferofelectricposts(whateverisapplicable)ForNOL2,
permits/certifications should already be secured and attached
accordingly.
d.AnnexH-1IP/ICCPlan(refertoPRDP’sIESSFforguidanceon
whentheIPPlanisrequired)
3.DulysignedESMPattachedwithAnnexH-2Archaeologicaland
Paleontological Chance Finds (Templates have been provided
dependingontheCategoryoftheEnterprise)
4.SiteAcquisitionDocumentssuchas:
a.Form1–EntitlementSurveyofAffectedPersons
b.Form2–InventoryofEntitlementSurveyofAffectedPersons
c.Proofofownership(TitleorDeedofSaleofthesite,Deedof
SaleorTransferCertificateTitle/TCT)
d. Notarized Waiver/Quit Claims and/or Notarized Deed of
Donations
e. Contract of Lease for 50 years and subject for renewal or
optiontobuy.ContractofUsufructfor25yearsandsubjectfor
renewal.
f. Rehabilitation/Relocation/Resettlement Action Plan and
Agreement between Proponent LGU and PAPs if with
Resettlement
g.AgreementbetweenthePAPsandLGUforthecompensation
oftheirproperties
5.DisclosureofSESDocumentsbythePSO–SESUnit(SA/EAofthe
BP;IEE/EIA;ECC;DulysignedESMP)
6.SocialInclusivenessScoringSheetforPGSeekingI-REAPFunding
V.GeomappingandGovernanceUnit(GGU)RequirementsATTACHED REMARKS
YES NO
CommunityLivelihood/EnterpriseSubproject
1.PlacemarkofLocalGovernmentOffice(i.e.Capitol,Municipal
Hall,Barangayhall)wherethesubprojectisunderitsjurisdiction
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
148
2.DigitizedtrackofthenearestroutefromLocalGovernment
Officetotheproposedsubprojectsite
3.Officelocationoftheproponentgroup
4.OfficelocationofClusterGroup/Coop/organizationoffice
5.Placemarkwhereitisapplicable,dependingonthebusiness
plan:
a.Locationoflocalmajortargetmarkets(withintheprovince);
b.Locationofnon-localmajortargetmarkets(excluding
overseas);
c.Locationofmajorcompetitors;
d.Locationof(existing&proposed)garage(haulingtruck,farm
tractor,deliveryvan);
e.Locationofexisting&proposedDock(motorizedbanca,
module,fishcage);
f.OtherRelated/SimilarStructurewiththesamelineof
business(existing&proposed);
6.ProposedConstructionsiteofPermanentStructures(i.e
processingplant,warehouse,dryeretc.)
a)Geotaggedphotos(atleastfourgeotaggedphotoofsiteand
existingpermanentstructure)oftheproposedsite;
b)Digitizedpolygonofthevicinityorsitedevelopment;
7.SourceLocationofRawMaterial
Raw material source location determines the availability and
sufficiency of raw material to supplied/processed in the propose
business enterprise. The following are the classificationwhere it is
applicabletobusinessplan;
a.1)CommodityPolygon(digitized;atleast50%ofthetotal
commodityareaasstatedinthebusinessplan)or100%ifthe
proposalincludeproductionsupport
a.2) Minimum of four (4) geotagged photo (commodity) is
requiredperparticipatingcluster.
b. Farm Animal (carabaos, cows, goat, hog, chicken)
Placemark/marker;
c. Farmmachinery target user (ie. Tractor rental/services for
landpreparation);(polygon)
7.Placemark&geotaggedphotos(KMZ)submittedtoRPCO-GGU
VI.ProcurementRequirementsATTACHED REMARKS
YES NO
1. Procurement Plan – at least signed by the PG, and PPMIU BAC,
however,onthefinalsubmissionthedocumentmustbesignedbythe
Governor
2.Completespecifications-goods
3.PhilippineBiddingDocumentsforworks/infrastructure(electronic
ordigitalcopy)
4.PhilippineBiddingDocumentsforgoodsusingNCBasmodeof
Procurement(electronicordigitalcopy)
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
149
VII.FinanceRequirementsATTACHED REMARKS
YES NO
1.MemorandumofAgreement(MOA)betweenDAandLGU
2.RPABResolution
3. SP Resolution Authorizing the LCE to sign IMA, Appropriation
Ordinance,Contracttoprovidefundsandothers.
4. Local Finance Committee (LFC) certificate of the LGU equity/
AppropriationOrdinance
5.WorkandFinancialPlan(WFP)–signedbyPG,PPMIUandGovernor
VIII.M&ERequirementsATTACHED REMARKS
YES NO
1.SubprojectProfile–signed
2.DataCaptureForm–signed
FinalSubprojectProposalshouldbesubmittedinsoftbindwithattachmentsinringbindwithe-copy
inCDformat.Finalbusinessplanwithcompleteattachmentsshouldbepreparedin5copiestobe
distributedasfollows:1)PGcopy;2)LGUcopy;3)1RPCOcopy;4)PSOcopy;5)NPCOcopy
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
150
Annex14.GUIDEINTHECONDUCTOFTHEPARTICIPATORYRESOURCEASSESSMENT–
RESOURCESANDSOCIALASSESSMENT(PRA-RSA)
Background
ThePhilippineruraleconomyhasbeencharacterizedformanyyearsbythelowincomelevelsofprimary
producers,lowlevelsofruralemployment,lackoffoodsecurity,weakagriculturalcompetitivenessandan
overallhighlevelofruralpoverty.Theunderlyingreasonsfortherelativelypoorperformanceofthesector
havebeenextensivelystudied35.Amongthefactorsaffectingthesectorarepoorlydevelopedinfrastructure
andlimitedproductionareas.
Beyondtheseinstitutionalissues,thePhilippinesmustalsocontendwiththecontinuingdegradationofits
naturalresourcesandlossofbiodiversity.Ithasexperiencedoneofthehighestbiodiversitylossratesinthe
worldwith 284 species considered endangered. Likewise, coastal andmarine resources continue to be
degraded,withlessthan3%ofthecoralreefsstillinexcellentconditionandonly5%ofmangrovecover
considered to be “old growth”. Although the Philippines has established approximately 1,300 marine
protectedareas(MPAs),unfortunatelyonly10to15%aremanagedproperly.Around50%oftheseMPAs
arelessthan10hectaresintotalarea;hence,only2%ofthecountry’smarineareaisunderanyformof
protection.Theinadequacyoftechnicalandhumanresourcecapabilitiesalongwiththelackofsustainable
managementofcoastalandmarineareashasgreatlyreducedthehealthoflocalfisheriesandecosystem
services.
Compounding the environmental degradation is the damage caused by frequent destructive weather
conditions,whichoverthepastdecadehaveresultedinlossesaveragingUS$500millionannually.Losses
havebeenmostsevereintheagriculturesectorandonthelivesofthoseaffected,forwhomitcantake
severalyearstorecover.WiththePhilippinesbeingrankedhighamongthemajorglobalclimatehotspots,
sealevelrise,temperatureincrease,changesinrainfallpatternsandincreasingfrequencyandintensityof
extremeweathereventscanalsobeexpected.
ResultsfromtheCoastalandMarineBiodiversityConservation(CMBC)component,implementedunderthe
first phaseof theMindanaoRuralDevelopmentProgram (MRDP-1), provided valuable experiences and
lessons,suchastheneedtoundertakealandscape/ecosystemapproachtoensuresustainableconservation
andmanagementofthecoastalresources.ExperiencesinCMBC1showthatsiltationandsedimentation,
brought about by destructive agricultural land utilization in the upland and forest areas, threaten the
conditionandrecoveryofcoralreefs,mangrovesandseagrassbeds.
Byintegratinguplanddevelopmentwithcoastalresourcesmanagementasanoverallapproachofnatural
resources management, there is potential for broader and sustainable impact on the income of
communitiesandoverallimprovementintheirqualityoflives.
ForthesecondphaseofMRDP2,interventionsincoastalresourcesmanagementincorporatedthelessons
from CMBC1 and was scaled up to include sustainable land management in the uplands, where land
degradationaffectsthebiodiversityandproductivityofcoastalareas,andexpandedtoothersiteswhere
such upland-lowland coastal linkages are evident. An integrative ecosystem/watershed management
approachwasutilizedandimplementedin35municipalitieswherelocalNRMbenefitsandmultipleglobal
environmental benefits could be generated from sustainable landmanagement and in selected critical
biodiversity-richsites’municipalities.
The NRM and GEF activities underMRDP2 also featured key institutional partnerships at the regional,
provincial,municipalandbarangaylevels.Theseincludedseveralnationalgovernmentagenciesandthe
35WorldBankAnalyticalandAdvisoryAssistanceforAgricultureandRuralDevelopmentinthePhilippines(Agriculturalproductivity
andAgribusiness);aSynthesisPaper(2011).
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
151
entire LGU communities, households, people’s organizations, non-government organizations, academic
institutionsandothercivilsocietysectorsinMindanao.
ToensurethatNRMisfullyandsuccessfullyintegratedinthebroadervaluechainoftheprioritycommodity
underPRDPitisimportantthatthestakeholders,mostspeciallytheprojectimplementers,gainashared
understanding of its operating mechanisms through participatory and demand-driven approaches and
strategies.
Rationale
The implementation of the NRM interventions within the commodity value-chain, a fundamental
operational and strategic feature of the Philippine Rural Development Program (PRDP) requires the
understandingof the current statusof theproducts’natural resourcebaseand the factorsaffecting its
conditionandsustainability.
Communities settled within and around the target coastal and watershed areas are the immediate
beneficiariesorusersofthenaturalresources.However,theyandtheirpracticesarealsothemajorcauses
thatresultinthedegradationanddestructionoftheuplandandcoastalecosystems,theresourcebasefrom
whichtheprioritycommoditiesrelyupon.Itisthereforeimportanttoinvolvethecommunitiesorresource
usersintheidentificationofproblems,formulation,implementationandmonitoringofanydevelopmental
effortthatwilladdressenhancementandsustainingtheintegrityofthecriticalandrelevantecosystems.
It isthus importanttoconducta landscapecharacterizationbothforthecoastalanduplandecosystems
throughaParticipatoryResourceAppraisal-ResourceandSocialAssessment(PRA-RSA)thatwouldfocuson
thecurrentsituationoftheenvironmentandnaturalresources.Theprocessshouldbeconsultative,multi-
sectoral and multidisciplinary that would ensure participation and cooperation among the different
stakeholdersthat includeNGOs,POsandcommunities,LGU,RPCO,andsupportfromlocalandnational
agencies.Theapproachwouldalsominimizeorganizationalproblemsbecausestakeholdersareinvolvedin
allstagesofproblemidentificationandproject identificationandplanning.Theprocessalsoemphasizes
thatthedifferentcommunitiesarenotonlyresourceusersbutkeydecisionmakersasfarasthehealthand
well-beingoftheirimmediateenvironmentandsustainableuseofthenaturalresourcesareconcerned.
The conduct of PRA-RSA activities therefore would generate appropriate data and information on
biophysicalfeatures,demography,socio-economicandpoliticalcharacteristicsandthecurrentstatusofthe
environmentandnaturalresourceswithemphasisonthewatershedarea.Theactivityalsowouldgenerate
appropriateinterventionstrategiesforlandscapeenhancementandrehabilitationandlivelihoodactivities
that would be sustainable and which will either support sustainable resource utilization or draw the
communitiesawayfrompracticesthataredestructivetotheenvironment.
Objectives
TheprimaryobjectiveofPRA-RSAistoassessthestatusoftheprioritycommodities’naturalresourcesbase
throughaparticipative,consultative,multi-sectoralandmultidisciplinaryprocess.
Specifically,thePRA-RSAwillseektoachievethefollowing:
• Measure,analyzeandestablishrelevantinformationonforestland,upland,lowland,settlements/
built-up,freshwaterandcoastalecosystemsbothqualitativelyandquantitativelywithinthemajor
watershedarea(s).
• Identifyandestablishthecurrentandpotentialenvironmentandnaturalresourcesmanagement
issues,problems,concernsthatneedtobeaddressed.
• Identify strength,weaknesses,opportunitiesand threats thatpertain to the current statusand
sustainabilityofthenaturalresources;
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
152
• Identifypractices,sourcesoflivelihoodsandothereconomicactivitiesandexaminetheextentto
whichcommunitiesdependonnaturalresourcesfortheirsustenanceandday-to-dayhousehold
requirements.
• IdentifyandassesspastandcurrentNRMefforts.
• AssessthecapacityofthestakeholdersandbeneficiariestoundertakeNRMinterventionactivities.
• Providerecommendationspertainingtotheconservation,protectionandenhancementofnatural
criticaltotheprioritycommodity.
Modalities
UnderPRDP,PRA-RSAwillbedoneintwomodalities.Thefirstmodalityisacomprehensiveandtechnically
detailedPRA-RSAdesignadaptingfromtheMRDP2’sPRA-RSAframework. Inthismodality,thePRA-RSA
will coverboth thebroadanddetailedassessmentof theecosystemsdirectly relevant to the identified
marineprotectedareas(MPAs)withintheselectedGEFsites.Bothterrestrialandcoastalresourceswillbe
surveyedandanalyzedwithrespecttotheircondition,management,andutilization.Therewillbespecial
emphasisonthefactorsaffectingbiodiversityconservationandimprovingmanagementeffectiveness.The
PRA-RSAwillprovidethekeytechnicalbaselineinformationcomplementingtheresultsoftheMETTand
MEAT for each of the GEF sites. This modality will be coordinated and facilitated through the I-PLAN
component.
Thesecondmodalityistherapidandpurposiveapproach.Thismodalityisenterprise-based,asopposedto
theecosystems-basedorientationofthefirstmodality.Thepurposeofthisapproachistodeterminethe
relationshipbetweentheprioritizedcommodityandthenaturalresourcebase.Thedeterminationofthis
relationship,alongwithunderstandingthethreatsandopportunities thatrelatetothenatural resource
base,willaidinassessingtheneededNRMinterventionsthatareexpectedtocontributetoensuringquality
and sustained inputs within the commodity value-chain. This modality will mainly employ simple
participatory rural assessment methods such as community mapping, focus group discussions, ocular
inspections,andkeyinformantinterviews,amongothers.ThismodalitywillmainlybedoneintheI-REAP
component.TherapidPRA-RSAwillbepartoftheformulationoftheBusinessPlan.
ProceduresandProcesses
FortheFullPRA-RSAmodality,activitieswillbemainlyconductedbyqualifiedspecialists(entitiescantake
theformofaconsultancyfirm,academicinstitution,orcivilsocietyorganization).Throughacontract,the
servicesoftheentityarespecifiedaswellasthelevelsofsupervisionandexpecteddeliverables.TheFull
PRA-RSAfortheGEFsitesisexpectedtocovernotmorethan90days,inclusiveofstakeholderconsultation,
mapgeneration,andreportwriting.
TheRapidPRA-RSA for identifiedpriority commoditieswillbeundertakenby thedesignatedNRMfocal
personintheRPCOassistedbylocaltechniciansfromDA,BFAR,DENR,andBSWM.Thismodalityshould
not takemore than10days. The tablebelow shows, in a summary and indicative format, the relevant
featuresofeachofthePRA-RSAmodality.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
Rapid
PRA-RSA
I-REAP Toassessthecondition
ofthenaturalresource
base of the priority
commodityand
provide
recommendationsfor
addressing
threats andconcerns
regardingthe
management
of the
resource
base
Depending on the priority commodity,
theactivitiesfortherapidPRA-RSAareasfollows.
Coastal
• MeetingwiththeLGUandtheMPAmanagersto
reviewofMPAplansandbudget
• Conductassessmentofrelevantecosystemand
habitat(e.g.,mangroves,coralreefs,etc.)
• Inventoryofrelevantresourcebase
• Identifyandagreeonproposedinterventions
Terrestrial
• MeetingwiththeLGUandthePOtoreviewofCLUP
andFLUPandbudget
• Conductofsitevisitsurveyandassessment(e.g.,
forests,riverbanks,watersourcesandsystems,etc.)
• Identifyandagreeonproposedinterventions
FGD, KII, secondary
datareview,
community
mapping, SWOT
analysis,Institutions
Mapping, Issues
Tree/Web
Mapping, GIS
(Geo-mappingand
Geo-tagging)
RPCO in
coordination
and with assistance
from
BFAR, BSWM,and
DENR
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
GuideQuestionsforFocusGroupDiscussionsandKeyInformantInterviewsinRapidPRA-RSA36
MAJORAREAS TERRESTRIAL COASTAL
Institutional • Whatorganizationorgroupisdirectlyandactivelyinvolvedinthemanagementoftheresources?
• Howmanymembersarethereintheorganization?Wherearetheyfrom?Whoarethemembers?Whereisthis
organizationlocated?
• Istheorganizationregisteredoraccredited?
• Ifso,whenwasitaccreditedorregistered?
• Ifnot,whyisitnotregisteredoraccredited?
• Whoassistedintheestablishmentanddevelopmentoftheorganization?
• Doestheorganizationhavefinancialresources?
• Ifso,howmuchofitsbudgetisallocatedforthemanagementoftheresources?
• Whatactivitiesarebeingsupportedbythisbudget?
• Ifthereisnofinancialresourceorbudget,wheredoestheorganizationgetfinancialsupport?
• Doestheorganizationhavepoliciesandprogramsrelevanttothemanagementoftheresources?Whatarethey?
• Hastheorganizationbeenarecipientofaprojectoriscurrentlyundertakingaprojectdirectlyrelevanttothe
managementoftheresources?
• Arethereotherorganizationsassistingthemanagersoftheresources?
Governance • Isthemunicipalorprovinciallocalgovernmentactivelyinvolvedinthemanagementoftheresources?
• Doesthemunicipalorprovinciallocalgovernmenthaveanypolicies,programsorprojectsdirectlyrelevanttothe
managementoftheresources?
• Ifso,howmuchisbeingallocatedfortheproject/program?WhointheLGUisdirectlyresponsible?Whatactivities
weredone?
• Ifnot,why?
• DoestheLGUhaveaMunicipalorprovincialENRO?
• Ifnone,whointheLGUisresponsibleforaddressingenvironmentalornaturalresourcesmanagement
• HastheLGUbeenarecipientorbeneficiaryofaprojectthatrelatestothemanagementoftheresources?
36Theprimaryrespondentsaremembersorrepresentativesoftheorganizationoftheresourcemanagersandthelocalgovernmentunit.Thisinstrumentshould
becomplementedbyotherParticipatoryRuralAppraisal tools suchas secondarydata review,communitymapping, issues tree,SWOTanalysis, institutions
mapping,amongothers.Moreimportantly,thisapproachisintendedtobuildontheValueChainAnalysis.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
• Ifso,whenwasthis?Whatactivitiesweredone?Howmuchwasprovided?Howlongwastheproject?Whatwerethe
outputsandoutcomes?
• Havetherebeenanyapprehensionsandsanctionsagainstpeopleorgroupsdoingillegalresourceextractionactivities?
Ifso,howmanyinthelastyear?Wherearetheyfrom?Whatspecificillegalactivitiesweredone?
Technical • Hasanyassessment,surveyorinventorydoneontheresources?
• Ifyes,whodidthis?Whenwasthisdone?Whatweretheresults?Whatactivitiesweredoneasfollow-up?
• DotheresourcemanagementorganizationandLGUhavetheappropriatetechnicalcapacityandmanpowerto
properlymanagetheresources?
• Ifno,why?
• Ifyes,whattechnicalcapacitiesarepresent?
• DotheLGUandresourcemanagersundertakeregularmonitoringoftheresources?
• Ifyes,how?Ifno,why?
Biophysical • Whatarethevariouslanduseandvegetationcover
ofthearea?
• Whataretheapproximatesizes(inhectares)ofthese
features?
• Whatcropsarebeingplantedinagriculturalareas?
• Whatarethetreespeciesandplantcomposition
foundintheforest?
• Whatanimalscanbefoundintheforest?
• Whatmajorwatersystemsarefoundintheforest
(springs,waterfalls,rivers,etc.)?Whatfloraand
faunaarefoundinthesewatersystems?Arethese
watersystemsbeingfordomesticandagricultural
purposes?How?
• Whattenureinstrumentshavebeenprovidedforthe
useoftheareas(e.g.,PLAs,SIFMAs,CBFMAs,etc)?
• Whatresourceextractionactivitiesarebeingdonein
theforestareas?
• Arethereillegalresourceextractionactivitiesinthe
forestareas?
• Ifyes,whendidthesestarted?Whoaredoingthese?
Wherearetheyfrom?Whatarebeingextracted?
• Whatarethevariousmarineandcoastalfloraand
faunafoundinthearea?
• Wherearetheselocatedandfound?
• Whatistheapproximatesizeofthevariouscoastal
ecosystems(e.g.,coralreefs,seagrass,sandy,etc.)?
• Arethereanyareasdesignatedforprotection,
conservationandmanagement?
• Ifyes,howbigaretheseareas?Whoismanaging?
Doesithaveatenureinstrument(e.g.,municipal
ordinance,barangayresolution,etc.)?Doesithavea
managementplan?Isitdelineated?Aretherezones
(e.g.,buffer,protection,etc.)?Whatactivitiesare
beingdomeinthearea(e.g.,enforcement,
monitoring,etc.)?Howmuchisbeingprovidedtodothese
activities?Ifnone,why?
• Whatextractionactivitiesarebeingdoneinthe
area?
• Whattypesofresourcesarebeingextracted?
• Whattypesofgearsarebeingused?
• Howbigaretheboats?
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
• Hastherebeenanypresenceofconflictwithregards
totheuseandmanagementoftheforestresources?
• If,yes,howwasthismanaged/resolved?
• Arethereanyproduction,recreation,andprotection
zonesintheforests?
• Ifyes,whodesignatedthese?Why?Whatarethe
sizesoftheseareas?Whatactivitiesarebeingdone
intheseareas?Howmuchisbeingprovidedtodo
theseactivities?
• Whatareasareproneorvulnerabletofloods,
erosion,landslides,andothergeophysicalevents?
Whathavebeenthedamages?
• Whatothernaturalrisksarepresent(e.g.,soilloss,
pest,watershortage,draught,etc.)?Whatactions
havebeendonetominimizetheserisks?
• Aretheseman-maderiskspresent(e.g.,industrial
waste,domesticpollution,landconversion,etc.)?
Whatarethesourcesoftheserisks?Whatisbeing
donetoaddressthese?
• Howmanyaretotallydependentontheextraction
oftheresources?
• Whatisthefrequencyofextraction?Howmuchis
beingextractedperoperation(e.g.,fishcatch)?
• Whatotherresourceuseispresent(e.g.,tourism,
research,etc.)?Whoaredoingthese?
• Whatarethenaturalandman-madethreatsto
theseresources(e.g.,illegalfishingpractices,
siltation,domesticpollution,overfishing,etc.)?
Whatactivitieshavebeenorbeingdonetoaddress
thesethreatsandrisks?Whoaredoingthese
activities?Whendidthesestart?Whatarethe
results?
Socio-Economic • Whatarethemainlivelihoodactivitiesofthepeople?
• Whataretheotherlivelihoodactivitiesthataugmentfamilyincome?
• WhataretheprogramsandprojectsoftheLGUtoassistcommunitiesintheirlivelihoodandincome?
Whendidthesehappen/start?Whatweretheresults?
• Aretheregroupsandnon-governmentorganizationsthatprovidelivelihoodassistance?Whatarethese?Whoare
thesegroups?Whatactivitiesweredone?Whendidthisstart?Whatweretheresults?
Cultural • ArethereanyIPcommunitieslivingadjacentorwithintheforestareas?
• Ifso,whatethno-linguisticgroupdotheybelongto?Howmanyarethey?Whatactivitiesdotheydorelevantto
resourcemanagementanduse?Dotheypracticetheirindigenoussystemsinusingandconservingtheresources?If
yes,how?Havethesesystemsbeensuccessful?
• Arethesegroupsassimilatedwiththemigrantcommunities?
• Ifso,towhatextentaretheyassimilated?
• Ifnot,aretheIPcommunitiesreceivingspecificassistanceintermsoflivelihoodsupportandprovisionofbasic
services?
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
157
SiteVisitandFieldObservationActivitiesforRapidPRA-RSA
Theocularobservationsandsitevisitsaremeanstovalidateandputintospatialcontexttheinformationgathered
fromthefocusgroupdiscussions(FGDs)andkeyinformantinterviews(KIIs).Theactivitiesareconsistentwith
ParticipatoryRuralAppraisalmethodologies.Thecoastalassessmentactivitiesaresimplifiedandadaptedfrom
the Participatory Coastal Resources Assessment (PCRA) Handbook. For both observations and coastal areas,
common activities are locating specific key points on amap and visits to themarket to determine types of
productsbeingextractedfromthelocality(cropsandfish).Theactivitiespresentedarebynomeanscomplete
and shouldonly serve as a guide and startingpoint for practitioners to explore andapplymore appropriate
approachestoachievetheexpectedanddesiredresult.
Coastal
1. Locatethefollowingkeystructuresandbiophysicalfeaturesonamap
a. Marineprotectedareas
b. Coralreefs
c. Mangroves
d. Seagrass
e. Hatchingareas
f. Portsandfishlandings
g. Publicmarket
h. Wastesources
2. Byboattravelandsitevisit
a. Assesstheconditionofthemangrovesfollowingusingvegetationtype,vegetativehealthand
densityasindicators(poor,fair,good,excellent);asimpleandshortline-transectmethodmay
beused
b. Identifyvarietyofanimalslocatedinthemangrovenotingitssize,specie,anddistribution
c. Noteareaswhereextractionactivitiesordestructionfromnaturalforcesarehappening
d. Notewheremanagementactivitiesarebeingdone(e.g.,rehabilitation,protection,etc.)
e. Notethesourcesofwaste,sedimentationandsiltationandtheits level/degree(none, light,
heavy,severe)
3. Bydivingorsnorkelling
a. AssesstheconditionofthecoralreeforidentifiedMPA/FSusingcoralspecies/coraldiversity,
coralcover/density,distribution,andphysicalcondition(damagedfrodynamiteandcyanide
fishing, bleaching, crown of thorns infestation, etc.) as indicators (bad, fair, good, and
excellent);linetransectorquadranttechniquescanbeusedforthispurpose
b. IdentifythemarinelifefoundinthecoralreefsoridentifiedMPA/FSnotingspecietypes,size,
andnumber/population(density),onecanemployfishvisualcensustechnique.
Terrestrial
1. Locatethefollowingkeystructuresandbiophysicalfeaturesonamap
a. Majorandmicrowatersheds
b. Vegetationtypesandlanduse
c. Residentialandbuilt-upareas
d. Extractionareas(timberandNTFP)
e. Watersourcesandsprings
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
158
f. Riversandtributaries
g. Irrigationcanals
h. Agriculturalareas
i. Industrialandcommercialinfrastructures
j. Roads
2. Bysitevisit(inagriculturalareas,forests,watersources,etc.)
a. Assesstheconditionoftheforestsusingvegetationtype,size,anddistributionas indicators
(poor,fair,good,excellent);simplelinetransectsmethodcanbedone
b. Locate areas under stress (fromman-made and natural activities) and determine extent of
damage(typeandmethodofextraction,forcescausingdamage,extentofdamage,etc.)
c. Identifyanimalsfoundintheareanotingspecie,size,location,andpopulation
d. Identifycropslocatedintheareaanddetermineextentandfrequencyofplantingactivities
e. Determinethesoiltypeandslopeofthearea,especiallyintheuplandareas
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
159
Annex15-BUSINESSPLANREVIEWTRACKINGFORM
SUB-PROJECTTITLE:LOCATION:
PROPONENTGROUP:
TOTALINVESTMENTREQUIREMENT:
ENTERPRISEPROJECTFUND:
INFRASTRUCTURECOST:
PGEQUITY:
REVIEWEDBY:
DATEREVIEWED:
UNIT COMMENTS/FINDINGS RECOMMENDATIONS
Republic of the Philippines Department of Agriculture PHILIPPINE RURAL DEVELOPMENT PROJECT National Project Coordination Office
4th
Floor, DA Building, Elliptical Road, Diliman Quezon City 1100, Philippines
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
160
Annex16-I-REAPINITIALEVALUATIONFORM
I. Proponent’sProfile
NameofProponent:_____________________________________________________________
Commodityline:_____________________Productform:_____________________________
Natureofbusiness:[]1stlevelproduction[]processing[]trading[]others_____________
OfficeAddress:_________________________________________________________________
ContactPerson:_________________________________Designation:_____________________
ContactNumber:_______________________Email:___________________________________
Registrations:[]SEC []CDA[]DOLE[]Mayor‘sPermit[]FDA
[]Others(listall)_________________________________________________
NetAssets(asof201_)_______________TotalEnterpriseProjectCost:___________________
FinancingMode:[]Micro-enterprise []Smallenterprise []Mediumenterprise
[]Restoration/Rehabilitation(calamityorconflictarea)
[]GEFarea[]Start-upEnterprise[]Upgrading/ExpansionofEnterprises
II.EvaluatingthePGeligibility
Criteria Yes No Remarks
Completenessofsubmittedeligibilitydocuments (indicate docs
submitted and
lackingdocs)
Actorinthecommodityvaluechain (indicaterole)
Producer group/ Smallholder groups/ MSME processor, consolidator,
exporter
Operational
(indicateexisting
businessactivities)
Willing toadopt clusteringor jointbusinessplanningwithothergroups
and forge contracts or formal marketing agreements with buyers or
privateintermediaries
(indicatewhether
verticalor
horizontal
integration)
III.Evaluatingproposalsagainstnegativelistoffundutilization
Negativelistoffundutilization Yes No
Moneymarketplacement,time-depositorotherformsofinvestment
CashadvanceofanyofficialofthePGunlessrelatedtotheimplementationofenterprise
Paymentofsalaries,honorariaoranyformofallowancesofthepersonnelofLGU
Purchaseofsupplies,materials,equipmentandmotorvehiclesoftheLGU
Acquisition of assets of the PG, unless necessary for the execution of the enterprise and
specificallystipulatedintheEPF
Purchaseofweapons
Financingofpoliticalandreligiousactivities
Purchaseofchemicalfertilizers,pesticides, insecticidesandherbicides,asbestosandother
potentiallydangerousanddangerousmaterialsandequipment
Financingofsawmills
Consumptionitemsorevents
Financingofactivitiesthathaveanalternativepriorsourceofcommittedfunding
Purchaseorrepairofvehiclesforgovernmentoffices
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
161
Salariedactivitiesthatemploychildrenunder16yearsofage
Financingactivitiesthatunfairlyexploitwomenormenatanyage
Useofmangroveorcoralreefsasbuildingmaterials
Purchaseoffishingboatsandotherrelatedequipmentunlessdirectlyrelatedorneededin
theenterprise
Constructionofenterprisesupportfacilitiesinprotectedareas
Useoffundsforpurchaseorcompensationofland
Constructionorrepairandbuyingofequipmentforgovernmentofficesandplacesofworship
Micro-financingactivities
Financinglaborandfuelexpenses
FinancingothercoststhatcouldbeprovidedbythePGinkind
Financingsalariesandwages,utilities,repairandmaintenance,permitsandlicenses
Potablewatersystem
IV.Evaluatingtheproposal’sobjectivesandimpacts
PRDPObjective Yes No Remarks/Explain
To increase productivity and marketability of agriculture
andfisheryproducts
(indicate target increase
inproductionvolumeand
sales volume of the
enterprise)
Toincreasefarmandfisheryhouseholdincomes
(indicate target increase
in income of farmer-
beneficiaries)
To improve the protection and conservation of the natural
resourcebaseofidentifiedenterprises
(indicate NRM activities
speciallyforGEFsites)
V.Evaluatingtheproposal’sbenefitsandoutcomes
PotentialImpact Remarks(includetargetgroupsandnumbers)
Farmer/Fishersbenefitted
Formalizedmarketingarrangements
FormalizedTechnicalarrangements
Benefitstotheenvironment
Improvedresiliencytoclimatechangeand
adverseweathercondition
Evaluatedby:_____________________ Verifiedby:___________________
(RPCOI-REAPStaff) (RPCOI-REAPHead)
Endorsedby:____________________ Notedby:_______________________
(RPCODeputyProjectDirector) (RPCOProjectDirector)
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
162
Annex17-SampleBusinessPlanorSubprojectProposalAppraisalorEvaluationForm
BusinessPlanEvaluationForm
PartI.GeneralInformation Tobefilled-upbytheTechnicalReviewTeam
Nameofenterprise:
Address:
Contactperson:
Product/s:
BriefDescriptionoftheEnterprise
EnterpriseProjectFund(EPF):PhP
TotalcounterpartofProponentGroup:PhP
InfrastructureCost:PhP
TargetstartingDateofOperation:
DateBusinessPlanwasReceived:
DateBusinessPlanwasEvaluated:
Name/Position/OfficeofRegionalTechnicalReviewTeam:
1.
2.
3.
4.
5.
PartII.ChecklistofRequirements YesorNo?(specify) IfYes,checkifinfois
correct,ifNo,request
formissingdata
1. Are the eligibility requirementdocuments completely
submitted?
2. Are the required documents and attachments
submitted?(SEECHECKLISTOFREQTS–ANNEX13OF
THEOM)
A. BusinessPlanAttachments
B. I-BUILDRequirements
C. SESDocumentaryRequirements
D. GGURequirements
E. ProcurementRequirements
F. FinanceRequirements
G. MandERequirements
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
163
Instructions:Ratethecontentofthebusinessplanfrom1-5with1asthelowestand5asthehighest.
COMPONENT/PARAMETERS RATING/SCORE
A. MARKETINGASPECT(20%) 1 2 3 4 5
1. Basisforthesalesprojectionsoundandinformationreliable
2. Buyersidentifiedandhassecuredcommitment(marketingagreement,
PO,etc)
3. Marketingstrategiessoundandwell-defined?
- Product’suniquesellingpropositionwelldefined
- Basisforpricingsoundandreliable
- Subproject location strategically located from themarket (market
accessibility)
- StrategiestocommunicateUSPoftheproducttotargetcustomers
welldefined
- Distributionnetworkorchannelestablished
4. Characteristicsoftargetmarketwelldiscussed
5. Competitorsidentifiedandwell-defined
- Profile,characteristicsandpracticesdiscussed
- Financialstrengthandpositionidentified
ScoreorPoints
B. OPERATIONSASPECT(20%)
1. Production methods and processes well-presented and discussed in
detail
2. Productionschedules
3. Technical assumptions well-presented (procedures, conversions,
recoveries,etc)
4. Required inputs, facilities and equipment are well defined and met
includingspecifications,volumeandcapacity
5. Suppliersofrawmaterialsidentifiedandsecuredcommitmenttosupply
6. Facilityandequipmentlay-outwell-definedandmatchedwiththesize
ofthebusinessoperation
7. Productionqualitycontrolsystemsinplaced
ScoreorPoints
C. ORGANIZATIONANDMANAGEMENTASPECT(20%)
1. Ownership and management of the enterprise clearly defined and
discussed
2. Organization and management plan depicts a level of skill and
experienceforasuccessfuloperationoftheenterprise
- Allmanagersandemployeeshaveexperienceinthebusiness
- Thegroup/entityhasalegalstructure
3. Organizationalchartandstaffingrequirementmatchedtheoperational
planoftheenterprise
4. Job description, duties and responsibilities of themanagers and staff
clearlystated
5. Profitdistributionschemeclearlypresentedanddiscussed
6. Internalcontrolmeasuresdefinedandin-placed
ScoreorPoints
D. FINANCIALASPECT(20%)
1. Financialassumptionsaresoundandrealisticandsourcesofrevenues
andcostsproperlyidentified
2. Presentationoffinancialstatements(BalanceSheet,IncomeStatement)
correct and in order according to general accounting standards and
principles
3. Financialprojectionsreflecttheproductionandmarketingplans
4. Financialratioanalysispresentedandpassedstandardcriteria
- FinancialInternalRateofReturn(FIRR)>15%
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
164
- Benefit-CostRatio(BCR)>1
5. Financialandnon-financialrisksdefinedandtakenintoaccount
ScoreorPoints
E. STAKEHOLDERPARTICIPATIONANDSOCIALBENEFITS(10%)
1. Contributiontoincreaseinfarmers’income
2. Sustainableemployment/ impactto localemployment(fromseasonal
toregular-salaryisequivalenttominimumwageormore)
3. Participationofsmallholderfarmersorfishers
4. Opportunitiesorparticipationofwomen
5. Opportunitiesorparticipationofindigenouspeople
6. Environmentalimpactandclimateresiliency
ScoreorPoints
F. SUSTAINABILITYMECHANISM(10%)
1. Clearlydefinedfutureplansorsustainabilityplan
2. Definedroleinthecommodityupgradingorvaluechaindevelopment
3. Planforexpansionorupgrading
4. Strategytomitigaterisksanduncertaintieswell-presented
5. Over-allstrategiescancontributetotheviabilityoftheenterprise
ScoreorPoints
COMPUTATION:
1. Get thePercentile Scorebyadding the total scoresper componentdividedby themaximumscore
possibleforthatcomponent.
2. MultiplythePercentilescoretotheAssignedPercentagePoint.
3. GettheActualScorebymultiplyingthePercentileScoreby100.
BUSINESSPLANAPPRAISAL/EVALUATIONSUMMARY:
Components
Assigned
Percentage
Point
Maximum
Scoreor
Points
SampleBPScore
fromtheTechnical
ReviewTeam
Percentile
ScoreSampleActual
score
C B A (A/B) ((A/B)*C)*100
1.Marketing 20% 25 20 0.8 16.00
2.Operations 20% 35 20 0.57 11.43
3. Organizationand
Management 20% 30 15 0.50 10.00
4.Financial 20% 25 20 0.80 16.00
5.Stakeholders
Participation&Social
Benefits10% 30 25 0.83 8.33
6. Sustainability
Mechanism10% 25 18 0.72 7.20
TOTAL
79.75
Minimum
PassingScore
70
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
165
REVIEWEDBY(TECHNICALREVIEWTEAM):
NAME OFFICE SIGNATURE
RECOMMENDINGAPPROVAL: APPROVEDBY:
_________________________ ______________________
I-REAPComponentHead,RPCO RPCOProjectDirector
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
166
Annex18-ASampleImplementationManagementAgreementfor
SubprojectswithEnterpriseDevelopmentOnly
IMANumber-PSO__________(RPCO)-2015(Year)-02(Month)-001(Number)
PrescribedFormat(27February2015)
RepublicofthePhilippines
DepartmentofAgriculture
PHILIPPINERURALDEVELOPMENTPROJECT(PRDP)
ProjectSupportOffice–________
IMPLEMENTATIONMANAGEMENTAGREEMENT
EnterpriseDevelopment
This Agreement ismade and entered into this ____ day of _____ 2014, at ___________, Philippines, by and
between:
TheDepartmentofAgriculture,anExecutiveDepartmentoftheRepublicofthePhilippines,withprincipaladdress
at Elliptical Road, Diliman, Quezon City, represented herein byDirector _______________________, Project
Director,ProjectSupportOffice–________________hereinafterreferredtoastheDA;and
TheProvince/City/Municipalityof__________________,apoliticalsubdivisionoftheRepublicofthePhilippines,
with principal address at______________________________, ________________ represented by Hon.
_________________________________Governor/Mayor,hereinafterreferredtoastheLGU;
-WITNESSETH-
WHEREAS,RepublicActNo.8435,otherwiseknownastheAgricultureandFisheriesModernizationAct(AFMA)of
1997 sets out the Government’s policies in the agriculture sector in attaining equitable distribution of
opportunities, incomeandwealth,expandingproductivity,andsustaining increase inproductionofgoodsand
servicestherebyraisingthequalityoflifeofthepeople,especiallytheunderprivileged;
WHEREAS,theDAgivesforemostconsiderationtopovertyalleviationandsocialequitythroughthedevelopment
and implementationofprojectsandprojects thatprovide thepoorsectorsof thecommunityespecially those
engaged insubsistenceagriculturewithequitableaccesstoresources, incomeopportunities,supportservices,
andmost especially rural infrastructures particularly in areas where productivity is low and the incidence of
povertyishigh;
WHEREAS, the Government of the Philippines (GOP) has obtained a loan from the International Bank for
ReconstructionandDevelopment-WorldBank(IBRD-WB)withIBRDLoanNo.8421PHamountingtoU.S.Dollar
FIVEHUNDREDONEMILLION TWOHUNDRED FIFTY THOUSANDONLY (US$501,250,000) for the purpose of
financingthePhilippineRuralDevelopmentProject(PRDP)tosupporttheGovernment’sefforttoreducepoverty
amongtheruralcommunitiesofeightyone(81)provincesinthecountry;
WHEREAS, all fundsconcerning the implementationof Subcomponent3.1: RuralAgri-fisheryEnterpriseand
ProductivityEnhancement(EnterpriseProjectFund)underComponent3:EnterpriseDevelopmentofPRDPwill
becoursedthroughandmaintainedbytheProjectSupportOffice(PSO)andwillbemadeavailabletoparticipating
LocalGovernmentUnits(LGUs);
WHEREAS, theDA’sfunctionsrelativetotheProjectaredonethroughitsNationalProjectCoordinationOffice
(NPCO)andtheconcernedProjectSupportOffice(PSO)andRegionalProjectCoordinationOffice(RPCO);
WHEREAS, the PLGUmanifested its interest to participate in the Project, and forwarded to theDApertinent
documentaryrequirementsforitsproposedsubproject;
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
167
WHEREAS, the _________________________________ has issued a No Objection Letter (NOL) 1 on
____________________________,whichisthebasisofthisImplementationManagementAgreement(IMA);
WHEREAS, theLGUandtheDAcommittedtoperformactionsassetout inthis ImplementationManagement
Agreement (IMA) hereinafter referred to as the Agreement to ensure the successful implementation of the
subproject,andthusachievetheProject’sdesiredobjectives;
WHEREAS, the LGU through Sangguniang Panlalawigan/Panlungsod/Pambayan Resolution No._______ dated
________authorizedtheGovernor/MayortosignthisAgreementandcommittheLGUtotheprovisionstherein;
NOW,THEREFORE,forandinconsiderationoftheforegoingpremises,thepartiestheretoagreeasfollows:
ARTICLEI–PURPOSEOFTHEAGREEMENT
Sec1.01 TheAgreementsetsoutthecommitmentsoftheDepartmentofAgricultureunderthePhilippine
RuralDevelopmentProject(PRDP)andtheLGUforimplementingtheSubproject.
ARTICLEII-DEFINITIONOFTERMS
Sec2.01 UnlessthisAgreementotherwiserequires,thetermsoracronymusedinthisAgreementshallhave
definitionsandmeaningsassetoutinSchedule1(DefinitionofTerms).
ARTICLEIII-SUBPROJECTDESCRIPTIONANDCOSTESTIMATES
Sec3.01 ThesubprojectcoveredbythisAgreementisthe_________________________________under
Subcomponent3.1:RuralAgri-fishery Enterprise andProductivity Enhancement (Enterprise
Project Funds) of Component 3: Enterprise Development described in detail in Schedule 2
(DescriptionofSubproject)hereof(hereinafterreferredtoasthe“Subproject”).
Sec3.02 TheEnterprisecostisestimatedat__________________________(_____)netofProponent
Groupequityof__________________________________(___)thebreakdownofwhichisset
forthinSchedule3(EstimatedSubprojectCostfortheEnterprise).
Sec3.03 Anyincreaseordecreaseinthecostbutnotbeyondtheapprovedsubprojectcoststatedinthis
AgreementshallfollowtheapprovedfinancingmixanddoesnotrequireamendmenttoIMA.
IncasethesubprojectcostexceedstheamountstatedintheIMA,thePLGU/PGwillprovidethe
additionalcost.
ThecostofBusinessPlanandallothercostofthesubprojectshallalsobefortheaccountofthe
LGU/PG.
Sec3.04 TheDAwillprovidetotheparticipatingLGUsasgrantequivalentto60%fromtheLoanProceeds
and 20% from the Government of the Philippines (GOP) Counterpart Fund or 80% of the
approved Enterprise cost, while the LGU Equity will be 20% as provided under Schedule 3
(EstimatedSubprojectCost).
TheProponentGroupwillcontributeanamountequaltoatleast20%(cashorinkind)tothe
Enterpriseasincrementalenterprisecost.
Sec3.05 The DA shall make available from the Loan Proceeds the amount of
__________________________(Php_________)andGOPCounterpartFundsintheamountof
___________________(Php__________)asfinancialassistancetotheLGUintheformofGrant
subjecttothetermsandconditionsofthisAgreement.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
168
Sec3.06 TheLGUequityshallbe_____________________(Php____________)oftheSubprojectcostto
beusedexclusivelyfortheenterprise.
Sec3.07 The Grant shall be allocated in accordance with the provisions of this Agreement, for
expendituresincurredinrespectoftheapprovedcostsoftheSubprojectcomponentsdescribed
andreferredtoinSchedule3and4(TentativeDisbursementSchedule)ofthisAgreement.
ARTICLEIV–SUBPROJECTACCOUNTANDRECORDS
Sec4.01 TheLGUshall:
a) Upon signing of this Agreement, establish and maintain in a bank acceptable to the
GovernmentoneSubprojectTrustAccounteachfor:
(i) fundswithdrawnfromtheDA(Grant)fortheLoanProceedfromIBRD-WBtofinance
partsoftheSubproject;
(ii) fundswithdrawnfromtheDA(Grant)fortheGOPCounterpartFundsfromthe
GOPtofinancepartsofthesubproject;and
(iii) fundsforEquityoftheLGUfortheSubproject.
Asubsidiaryledgershallbemaintainedforeachoftheabovecited trustaccounts
(Grant/Equity) forproperaccounting,record-keepingandmonitoringoftransactions
andtofacilitatethepreparationoffinancialreports.
b) Maintainafinancialmanagementsystemandpreparesfinancialstatementinaccordance
withconsistentlyappliedaccountingstandardsacceptabletotheBank,bothinamanner
adequatetoreflecttheoperationsandfinancialconditionoftheParticipatingPLGU,
includingtheoperations,resourcesandexpendituresrelatedtotheProject,includingthe
recoveryofallcosts,forcarryingouttheSub-projectoranypartthereof;
c) EstablishandmaintainseparateaccountsandbooksfortheSubproject,reflectingall
expendituresandonwithdrawalsrequestedandreceivedfromtheDAonthebasisofthe
StatementofReceiptsandExpenditures(SRE).Maintainrecordsadequatetoreflect,in
accordancewithconsistentlysoundaccountingpractices,theoperations,resources,and
expenditures,includingtherecoveryofallcosts,forcarryingouttheSubprojectoranypart
thereof;
d) DisbursethefundsinaccordancewiththeSubprojectcomponentstowhichtheGrant
wereprovidedaspresentedinSchedule2a,2band3thereof;
e) Retain,untilten(10)yearsaftertheClosingDate,allrecords,pertainingtoormentionedin
Subsections(a)to(c)ofthisSection(includingcontracts,orders,invoices,bills,receiptsand
otherdocuments)evidencingtheexpendituresandpaymentsontheaccountsofthe
Subproject,andenabletheDA’srepresentativestoexaminesuchrecords;
f) HaveitsfinancialstatementsfortheProjectreferredtoaboveauditedbyIndependent
auditors(CommissiononAudit)acceptabletotheBank,inaccordancewithconsistently
appliedauditingstandardsacceptabletotheBank.Eachauditofthesefinancialstatements
shallcovertheperiodofone(1)calendaryearoftheparticipatingPLGU;
g) FurnishtheDAthrutheNPCOand/orPSOassoonasavailable,butnotlaterthantwo
months,anoriginalcopyofthereportsofsuchaudits,ofsuchscopeandinsuchdetailas
theNPCOandPSOshallreasonablyrequest,includingwithoutlimitationstotheforegoing,
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
169
aseparateopinionbytheauditor“ascontainedinanauditcertificate”inrespecttothe
expendituresandrecordsreferredtoinSubsection(b)ofthisSectionastowhetheronthe
basisoftheSRE,theGrantwithdrawnhavebeenusedforthepurposesforwhichtheywere
provided;and
h) FurnishtheNPCOandPSOsuchotherinformationconcerningthesaidseparateaccounts,
recordsandexpendituresandtheauditthereofasNPCOandPSOmayreasonablyrequest
fromtimetotime.
ARTICLEV–SUBPROJECTEXECUTION
Sec5.01 ThePLGUshallstarttheimplementationoftheSubproject,basedontheschedulepresentedin
Schedule5(ProjectImplementationPlan)hereof,immediatelyfromthedateoftheeffectivity
ofthisAgreement.
Sec5.02 UponapprovalofthisAgreementandincompliancewiththeadditionalconditionsreferredto
inSection9.02ofthisAgreement,theDA-PSOwillreleaseorcausethereleaseofGranttothe
PLGU in accordance with Schedules 6 (Schedule of Release of Funds) and 7 (Schedule of
RequirementsfortheReleaseofFunds)ofthisAgreement.
Sec5.03 ThePLGUshallpassanordinanceappropriatingthePLGUEquityfortheSubproject,anddeposit
theseintheaccountsreferredtoinSection4.01Subsection(a)intheamountofandonsuch
datesspecifiedinSchedule3ofthisAgreement,suchfundsaretobewithdrawnanddisbursed
against theclaimsof thecontractors/creditors inaccordancewith the samescheduleof this
Agreement.
Sec5.04 TheDAthroughtheNPCOand/orPSOand/orRPCOshall:
a) Monitor,supervise,andevaluatethePLGUintheimplementationofitsSubprojectandits
compliancewiththeobligationsunderthisAgreement;
b) Assistinthereviewoftheprocurementofgoods,services,andequipmentaswellasthe
works/outputsofconsultants/contractors/suppliers,and
c) EnsurethattheSubprojectisimplementedinaccordancewiththeprovisionsofthis
Agreement,relevantlaws,rulesandregulations,andprofessionalandtechnicalstandards.
Sec5.05. ThePLGUshallalso:
a) CarryoutanenvironmentalscreeningfortheproposedSubprojectinaccordancewith
theprovisionsoftheEnvironmentalSocialSafeguardsFramework(ESSF)(includingthe
EMFG);
b) Priortothecommencementofanyinstallationofequipment,facilitiesorservicestobe
rendered,prepare,holdconsultationsonanddiscloseanEnvironmentalSocial
managementPlan(ESMP),satisfactorytothebank;
c) CarryouttheSub-projectinaccordancewiththeESMP;
d) Notamend,suspend,orabrogateanyoftheprovisionsoftheESMPwithoutprior
approvalofthebank;
e) IntheeventanenvironmentalcompliancecertificateisrequiredunderthePhilippine
Lawsorregulations,suchcertificatehasbeenobtainedfromDENRoritsinstrumentality
attheregionallevelinrespectoftheactivitiesunderthesaidSub-project.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
170
Sec5.06. ThePLGUshall:
a) Maintain,throughouttheperiodofProjectimplementation,theorganization,
managementandresources,satisfactorytotheBank,forcarryingoutSub-projects;
b) Establish,priortothecarryingoutofanySubprojects,andthereaftermaintain,a
ProvincialProjectManagementandImplementationUnit(PPMIU)throughouttheperiod
ofProjectimplementation,withcomposition,termsofreference,staffingandother
resourcesacceptabletotheBank,toberesponsibleforsupportingproject
implementationactivities,preparingannualworkplansandbudgets,undertaking
monitoringandevaluationandoverallaccountingandfinancialmanagement;and
c) CarryouttheSubprojectswithduediligenceandefficiency,andinconformitywith
appropriateeconomic,financial,administrative,technical,andagriculturalpracticesand
soundsocialandenvironmentalstandards,assetforthintheOperationsManuals
preparedandadoptedbytheProject,andacceptabletotheBank,andprovidepromptly
asneeded,thefunds,facilities,servicesandotherresourcesrequiredtherefor.
d) Submitmonthly,quarterlyandannualfinancialandphysicalprogressreportsregularlyto
PSOthroughRPCOonorbeforeduedates;
e) ComplywithalltheprovisionsapplicableinthePRDPOperationsManualsandGuidelines
insubprojectimplementation.
Sec5.07. EachparticipatingPLGUshall:
a) Intheprocurementofgoods,equipmentandservices,thePLGUshallcomplywithPRDP
ProcurementManualandtheWorldBankProcurementGuidelinesandRepublicAct
No.9184,knownasthe“GovernmentProcurementReformAct,theiralliedstatutesand
theirrespectiveImplementingRulesandRegulations,andinaccordancewiththe
relevantprovisionsoftheLoanAgreementshallbesuppletoryincharacter;
b) Ensurethatsaidgoodsareinsuredagainsthazardsincidenttotheacquisition,
transportationanddeliverythereoftotheplaceofuseorinstallation,anyindemnity
thereundertobemadepayableinacurrencyfreelyusablebythepurchaserthereofto
replaceorrepairsuchgoods;and
c) Ensurethatsaidgoods,equipment,facilitiesandservicesincludedintheprojectare
utilizedexclusivelyforthepurposeofcarryingouttheProject.
ARTICLEVI-MONITORING,REPORTINGANDEVALUATION
Sec6.01 The PLGU, through the P/MPMIU, shall comply with the procedures and guidelines for
monitoringandreportingasprescribedbythePRDP.
Sec6.02 TheDAshall,onbehalfofNPCO,PSOandRPCO,undertakeoverallmonitoringandevaluationof
theperformanceofthePLGUincarryingoutthetasks,responsibilitiesandobligationssetforth
inthisAgreement.
Sec6.03 ThePLGUshallenabletheWB,NPCO,PSOandRPCOtomonitor,examineallgoods,facilities,
sitesandequipment included intheProject, theoperationthereof,andanyrelevantrecords
and documents. The findings of themonitoring team shall be forwarded to the NPCO, PSO
and/orRPCODirectors,copiesofwhichshouldbefurnishedtothePLGU.
Sec6.04 StatusreportssuchasStatementofExpenditures(SRE),StatementofSourcesandApplication
of Funds (SSAF), financial statements (Trial Balance, Cash Flow Statement and Bank
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
171
ReconciliationStatement)attachedasSchedule8(FormatofFinancialReportsandStatements)
andMonthlyProgressReporton theSubproject shallbe forwardedby thePLGU to thePSO
throughRPCOonorbeforethe5thdayoftheensuingmonthinsuchdetailsandfrequencyas
mayreasonablyberequestedsubjecttovalidationbythePSOand/orRPCO.
Sec6.05 ThePLGUshall:
a) Maintainpoliciesandproceduresadequatetoenableittomonitorandevaluateonan
ongoingbasis,inaccordancewiththeperformanceindicatorsintheLoanAgreement,
theircarryingoutoftheSub-projects;and
b) Prepare,underthetermsofreferencesatisfactorytotheBank,asemi-annualreport
summarizingtheresultsofthemonitoringandevaluationactivitiesperformedonprogress
achievedincarryingouttheSub-projectsduringtheprecedingcalendarsemesterand
settingoutthemeasuresrecommendedtoduringthenextsemi-annualperiodfollowing
suchdateandfurnishthesametoRPCO/PSO/NPCOtoenablethemtoconsolidateand
submittheinformationtotheBank.
Sec6.06 ThePLGUshallallowtheWB,NPCO,PSOandRPCOtoconductauditinspectionandreviewof
financialaccountingrecords.
Sec6.07 IntheeventthattheperformanceofthePLGUfallsshortoftheagreedobjectives,targetsor
projects,thePLGUshallnotifytheNPCO,PSOandRPCOinwritingwithinfifteen(15)calendar
days from the receipt of the latest monthly accomplishment report, so that necessary
adjustments,modificationsoramendmentswillbemadeortobemadeinaccordancewiththe
provisionsofthisAgreementwithoutprejudicetotheremediesavailabletotheDA.
ARTICLEVII-OTHERCOVENANTS
Sec7.01 All national and local taxes, duties, fees, levies and other government impositions on the
SubprojectshallbefortheaccountofthePLGU.
Sec7.02 ThePLGUshallberesponsibleforbankchargesandotherexpensesassociatedwithremittances
toandfromtheSubprojectTrustAccountestablishedbythePLGUinaccordancewithSection
4.01,paragraph(a)i–iiiofthisAgreement.
Sec7.03 TheNPCO,PSOandRPCOshallmaintainamonitoringandrecordsystemreflectingallthefunds
releasedandtheexpendituresmadefortheexecutionoftheSubproject.
Sec7.04 ThePLGUwarrantsthattheSangguniangPanlalawiganhaspassedaresolution,asshown in
Schedule9(SangguniangPanlalawiganResolutionNo.___)that:
a) AuthorizetheLocalChiefExecutive(LCE)toenterintocontractswiththewinningbidders
forconsultancy,procurementofgoods/equipmentandotheragreementsrequiredtobe
donetoputthisAgreementIntofulleffect,and
b) Commitsresourcesandlogisticalsupportfortheeffectiveimplementationofthe
Subproject
Sec7.05 ThePLGUshallsubmittheSub-projectCompletionReportnotlaterthansix(6)monthsafterthe
lastpaymentwasmadebythePLGUtothecontractorand/ortotheproponentgroup.
Sec7.06 Upon the issuanceof theCertificateofCompletion, thePLGUshall turn-over the structures,
facilitiesandequipmentprovidedfortheSubprojectandshallcausetheProponentGroupto
operateandmaintain,orcausetobeoperatedandmaintainedproperly,thestructures,systems
andfacilitiesinstalledorestablishedundertheSubprojectandshallpassaResolutionproviding
forthefunds,facilities,servicesandotherresourcesrequiredforthepurposeforthenextten
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
172
(10)yearsaftersubprojectcompletion.TheDA-RFOshallbecopyfurnishedwiththecopyofthe
Resolutionformonitoringpurposes.
Sec7.07 a) AnynoticeorrequestrequiredorpermittedtobegivenormadeinthisAgreementshall
be inwritingandshallbedeemed tohavebeendulygivenormadewhendelivered to
NPCOorPSO;theOfficeoftheLCE,incaseofthePLGU,orsuchotheraddresswhichthe
Partiesheretomayspecifyinwriting.
b) Anyactionrequiredorpermittedtobetaken,andanydocumentrequiredorpermittedto
beexecutedunderthisAgreement,onbehalfoftheDA,maybetakenorexecutedbythe
PSOProjectDirectororhisauthorizedrepresentative.
c) Anyactionrequiredorpermittedtobetaken,andanydocumentrequiredorpermittedto
beexecutedunderthisAgreement,onbehalfofthePLGU,maybetakenorexecutedby
the LCE except those expressly reserved in this Agreement to be taken by the PLGU’s
SanggunianPanlalawigan.
Sec7.08 Bymutualconsent,thisAgreementoranypartthereofmaybechanged,modified,revisedand
amendedorsupplementedforthepurposeofeffectiveimplementationandmanagementofthe
Subproject. Allotherpartiesconcernedshallbenotified/informedofsuchchanges,revisions
andamendments.
Sec7.09 All disputes or controversies between the parties arising out of or in connection with this
AgreementwhichisnotsettledbetweenthepartiesshallbeelevatedinitiallytotheDA.
Sec7.10 Notarial feesandexpenses incidentaltotheprocessingofthisdocumentshallbechargeable
againstthePLGUfunds.
ARTICLEVIII-REMEDIES
Sec8.01 TheDAshallsuspendthesubsequentreleasesoftheGrantifanyofthefollowingoccurs:
a) ThePLGUhasnoorinsufficientequityfortheSubproject;
b) UnsatisfactoryperformanceofthePLGUintheimplementationandexecutionofthe
Sub-project.(Thereisunsatisfactoryperformanceifthereisdelayinthedelivery,
complianceorinstallationofmorethanseven(7)calendardaysforgoodsorequipment
procuredlocallyorfortyfive(45)calendardaysincaseofgoodsorequipmenttobe
procuredabroad,savetheexistingapprovedextensionorsuspensionofdeliveryor
installationorcompliance,ofgoods,services,equipmentandfacilitiesbythewinning
bidder/contractor/consultant/supplier.)
c) AtanytimetheNPCO,PSOorRPCOdetermines,duringtheconductofreviewand
monitoringactivities,thattheprocurementofanycontracttobefinancedbyGrantis
inconsistentwiththeproceduressetforthorreferredtobytheapplicableManualsand
GuidelinesofthePRDPandinreferencewiththeWBandGOPguidelines;and
d) Extraordinaryconditionssuchasforcemajeure,fortuitousevents,andthelikewhich
shallmakeitnecessarytosuspendtheimplementationoftheSubproject.
Sec8.02 TheDA,atitsownsoleoption,reservestherighttoliftsuchsuspensionfortheresumptionof
releasesofGrantfortheSubprojectofthePLGU.
Sec8.03 Upon the recommendationofNPCOorPSO, the concernedRegional ProjectAdvisoryBoard
(RPAB)shallcanceltheIMAifanyofthefollowingoccur:
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
173
a) Non-complianceorviolationbythePLGUofanyprovisionsofthisAgreement;
b) TheNPCOand/orPSOfoundout,withrespecttoanycontracttobefinancedbythe
Grant,thatcorruptorfraudulentpracticesasprovidedforunderR.A.3019orotherwise
knownasAnti-GraftandCorruptpracticesActwereengagedinbyrepresentativesofthe
PLGUorabeneficiaryoftheGrantduringtheprocurementandexecutionofsuch
contract,withoutthePLGUhavingtakentimelyandappropriateactionsatisfactorytothe
NPCOand/orPSOtoremedythesituation;
c) Atanytime,whentheextentoftheeventsmentionedinSection8.01(d)escalatesthat
shallmakeitimprobablefortheSubprojecttocontinuetobecarriedout;and
d) UpontherequestofthePLGU.
Sec8.04 InsuchcasethattheSubprojectispartiallyorfullycancelledduetothefaultofthePLGUasin
Section8.01Sub-sections(a),(b),and(c)thefollowingprovisionsshallapply:
a) ThePLGUshallbeobligedtoreturntoDAtheunexpendedand/orunliquidatedbalanceof
thereleasedGrantoftheSubprojectwithinonemonthfromthedateofreceiptofthe
noticeofcancellationofIMA,and
b) TheamountofGrantutilizedshallberefundedtoDAwithinthree(3)monthsfromthe
dateofreceiptofcancellationofIMA.
Sec8.05 IncaseofcancellationofIMAduetoforcemajeure,asstatedinSection8.01(d),theamount
disbursed and paid for the actual accomplishment of the subproject may not be returned
however,anyunexpendedand/orunliquidatedbalanceshouldbereturnednotlaterthantwo
(2)monthsfromthereceiptofthenoticeofapprovalofcancellationofIMA.
Sec8.06 IncaseofcancellationupontherequestofPLGUasstatedinSection8.03(d),thetotalamount
ofgrantreleasedshouldbereturnedwithintwo(2)monthsafterreceiptofnoticeofapproval
ofthecancellation.
Sec8.07 ThePLGUswho’sIMAwerecancelledbutdidnotrefundorreturnthegrantfundsinfulltoDA
willnotbeconsideredforon-goingandfutureprojectsandprojectsofthedepartment.
Sec8.08 Failure to complywith theOperationalPlan: Should thePLGU fail toproperlyoperate the
subprojectand/orprovidenecessarybudgetallocationsasperOperationalPlaninSchedule10
(OperationalPlan)andassessmentcriteria,DAshallreviewitsoptiontodeny/withholdsimilar
assistanceinthefutureuntilsuchtimethatitisconvincedthatareconsiderationonthematter
shouldbeeffected.
ARTICLEIX-EFFECTIVITY
Sec9.01 ComplianceofPreconditionsbythePLGUfortheeffectivityofthisAgreement:
a) ASangguniangPanlalawiganResolutionandAppropriationOrdinancehasbeenpassed
committinglogisticalandfundingsupporttothePLGUandtheSubproject,particularly
withrespecttotheequitycontributionandoperationsandmaintenanceofcompletedor
installedstructures,systemsandfacilities.
Sec9.02 ThisAgreementshallbecomeeffectiveuponsigningofthepartiesconcernedandcompliance
bythePLGUoftheadditionalpreconditionsforeffectivenessreferredtoinSection9.01ofthis
Agreement and shall subsist and remain in full force and effect ten (10) years after the
subprojecthasbeenturnedoverandatsuchtimethepartiesheretoshallbemutuallyreleased
fromallobligationshereunder.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
174
INWITNESSWHEREOF,theParties,havecausedthisImplementationManagementAgreementtobesignedin
________,Philippinesonthis____dayof_____________.
By:By:
__________________________________________________________________________________
ProjectDirectorGovernor
ProjectSupportOffice(PSO)–_______
By:
____________________________________
Director
RegionalProjectCoordinationOffice(RPCO)________
WITNESSES:
___________________________________ _______________________________
PRDPFocalPerson–RPCO____ProvincialAccountant/Treasurer
_________________________________________________________________________
ProjectAccountant–PSO______SPMember,FinanceCommittee
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
175
ACKNOWLEDGMENT
REPUBLICOFTHEPHILIPPINES)
_____________________________)S.S.
Before me this __________ day of ___________________ 2014, at _____________________ personally
appeared:
Name CompetentEvidenceofIdentityPlaceandDateIssued
____________________________________________________________________________________________
____________________________________________________________________________________________
Known to me and to me known to be the same persons who executed the foregoing agreement and they
acknowledged to be the same is of their own free and voluntary act and deed and those of the offices they
represent.
WITNESSMYHANDANDSEALonthedateandattheplacefirstwrittenabove.
NOTARYPUBLIC
UntilDecember31,2015
PTRNo.____________
DocNo________
PageNo________
BookNo._______
Seriesof2015_____
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
176
SCHEDULES
Schedule1 - DefinitionofTerms
Schedule2 - DescriptionofSubproject
Schedule3 - EstimatedSubprojectCostforEnterprise
Schedule4 - TentativeDisbursementSchedule
Schedule5 - ProjectImplementationPlan
Schedule6 - ScheduleofReleaseofFunds
Schedule7 - ScheduleofRequirementsfortheReleaseofFunds
Schedule8 - FormatofFinancialReportsandStatements
a) StatementofReceiptsAndExpenditures(SRE)
b) StatementofSourcesandApplicationofFunds(SSAF)
c) TrialBalance
d) BalanceSheet
e) CashFlowStatement
Schedule9 - SangguniangPanlalawigan(SP)Resolution
– Resolution Authorizing the Provincial Governor to
Execute and Enter into an IMA and Approving the
AppropriationfortheLGUEquityoftheSubprojectCost
Schedule10 - OperationalPlan
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
177
Annex18-BSampleImplementationManagementAgreementforSubprojectswith
EnterpriseDevelopmentandCivilWorks
IMANumber-PSO___________(RPCO)_________(Year)_______-(Month)-________(Number)
PrescribedFormat(27February2015)
RepublicofthePhilippines
DepartmentofAgriculture
PHILIPPINERURALDEVELOPMENTPROJECT(PRDP)
ProjectSupportOffice–__________
IMPLEMENTATIONMANAGEMENTAGREEMENT
EnterpriseDevelopmentwithCivilWorks
This Agreement ismade and entered into this ____ day of _____ 2014, at ___________, Philippines, by and
between:
TheDepartmentofAgriculture,anExecutiveDepartmentoftheRepublicofthePhilippines,withprincipaladdress
at Elliptical Road, Diliman, Quezon City, represented herein by Director _____________________________,
ProjectDirector,ProjectSupportOffice–________________________________hereinafterreferredtoastheDA;and
TheProvinceof__________________, apolitical subdivisionof theRepublicof thePhilippines,withprincipal
address at Provincial Capitol Building, _______________, ________________ represented by Hon.
_________________________________Governor,hereinafterreferredtoasthePLGU;
-WITNESSETH-
WHEREAS,RepublicActNo.8435,otherwiseknownastheAgricultureandFisheriesModernizationAct(AFMA)of
1997 sets out the Government’s policies in the agriculture sector in attaining equitable distribution of
opportunities, incomeandwealth,expandingproductivity,andsustaining increase inproductionofgoodsand
servicestherebyraisingthequalityoflifeofthepeople,especiallytheunderprivileged;
WHEREAS,theDAgivesforemostconsiderationtopovertyalleviationandsocialequitythroughthedevelopment
and implementationofprojectsandprojects thatprovide thepoorsectorsof thecommunityespecially those
engaged insubsistenceagriculturewithequitableaccesstoresources, incomeopportunities,supportservices,
andmost especially rural infrastructures particularly in areas where productivity is low and the incidence of
povertyishigh;
WHEREAS, the Government of the Philippines (GOP) has obtained a loan from the International Bank for
ReconstructionandDevelopment-WorldBank(IBRD-WB)withIBRDLoanNo.8421PHamountingtoU.S.Dollar
FIVEHUNDREDONEMILLION TWOHUNDRED FIFTY THOUSANDONLY (US$501,250,000) for the purpose of
financingthePhilippineRuralDevelopmentProject(PRDP)tosupporttheGovernment’sefforttoreducepoverty
amongtheruralcommunitiesofeightyone(81)provincesinthecountry;
WHEREAS, all fundsconcerning the implementationof Subcomponent3.1: RuralAgri-fisheryEnterpriseand
ProductivityEnhancement(EnterpriseProjectFund)underComponent3:EnterpriseDevelopment(I-REAP)of
PRDPwillbecoursedthroughandmaintainedbytheProjectSupportOffice(PSO)andwillbemadeavailableto
participatingLocalGovernmentUnits(LGUs);
WHEREAS, theDA’sfunctionsrelativetotheProjectaredonethrough itsNationalProjectCoordinationOffice
(NPCO)andtheconcernedProjectSupportOffice(PSO)andRegionalProjectCoordinationOffice(RPCO);
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
178
WHEREAS, the PLGUmanifested its interest to participate in the Project, and forwarded to theDApertinent
documentaryrequirementsforitsproposedsubproject;
WHEREAS, the _____________________________ has issued a No Objection Letter (NOL) 1 on
______________________,whichisthebasisofthisImplementationManagementAgreement(IMA);
WHEREAS,thePLGUandtheDAcommittedtoperformactionsassetoutinthisImplementationManagement
Agreement (IMA) hereinafter referred to as the Agreement to ensure the successful implementation of the
subproject,andthusachievetheProject’sdesiredobjectives;
WHEREAS,thePLGUthroughSangguniangPanlalawiganResolutionNo._______dated________authorizedthe
GovernortosignthisAgreementandcommitthePLGUtotheprovisionstherein;
NOW,THEREFORE,forandinconsiderationoftheforegoingpremises,thepartiestheretoagreeasfollows:
ARTICLEI–PURPOSEOFTHEAGREEMENT
Sec1.01 TheAgreementsetsoutthecommitmentsoftheDepartmentofAgricultureunderthePhilippine
RuralDevelopmentProject(PRDP)andthePLGUforimplementingtheSubproject.
ARTICLEII-DEFINITIONOFTERMS
Sec2.01 UnlessthisAgreementotherwiserequires,thetermsoracronymusedinthisAgreementshallhave
definitionsandmeaningsassetoutinSchedule1(DefinitionofTerms).
ARTICLEIII-SUBPROJECTDESCRIPTIONANDCOSTESTIMATES
Sec3.01 ThesubprojectcoveredbythisAgreementisthe_________________________________under
the Enterprise Development Component described in detail in Schedule 2 (Description of
Subproject)hereof(hereinafterreferredtoasthe“Subproject”).
Sec3.02 The Subproject cost is estimated at PESOS ________________________________ (Php
___________)thebreakdownofwhichissetforthinSchedule3(EstimatedSubprojectCost).
Sec3.03 The portion of Civil Works in the subproject is estimated at PESOS
_______________________________(Php___________)thebreakdownofwhichissetforthin
Schedule3A(EstimatedSubprojectCostfortheCivilWorks).
Sec 3.04 a) The DA shall make available from the Loan Proceeds eighty percent (80%) or PESOS
___________________________ (Php_____________) and ten percent (10%) from GOP
Counterpart or PESOS _________________ (Php _________) from the cost of Civil Works
portion in the subproject under the Infrastructure Development Component as financial
assistancetotheLGUintheformofGrantsubjecttothetermsandconditionsofthisAgreement.
b)TheLGUequityshallbetenpercent(10%)orPESOS________________(Php_________)ofthe
CivilWorksportionoftheSubprojecttobeusedexclusivelyforcivilworks.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
179
Sec3.05 The portion of the Enterprise cost in the subproject is estimated at PESOS
__________________________(Php_____)thebreakdownofwhichissetforthinSchedule3B
(EstimatedSubprojectCostfortheEnterprise).
Sec 3.06 a) The DA shall make available from the Loan Proceeds sixty percent (60%) or PESOS
___________________________ (Php_____________) and from GOP Counterpart is twenty
percent (20%) or PESOS ______________________________from the cost of the Enterprise
portioninthesubprojectundertheEnterpriseDevelopmentComponentasfinancialassistance
totheLGUintheformofGrantsubjecttothetermsandconditionsofthisAgreement.
b)TheLGUequityshallbetwentypercent(20%)orPESOS________________(Php_________)
oftheEnterpriseportionoftheSubprojecttobeusedexclusivelyfortheenterprise.
c) TheProponentGroupwillcontributeanamountequaltoatleast20%(cashorinkind)tothe
Enterpriseasincrementalenterprisecost.
Sec3.07 Anyincreaseordecreaseinthecostbutnotbeyondtheapprovedsubprojectcoststatedinthis
AgreementshallfollowtheapprovedfinancingmixanddoesnotrequireamendmenttoIMA.In
case the subproject costexceeds theamount stated in the IMA, thePLGU/PGwillprovide the
additionalcost.ThecostofBusinessPlanandallothercostofthesubprojectshallalsobeforthe
accountofthePLGU/PG.
Sec3.08 TheGrantshallbeallocatedinaccordancewiththeprovisionsofthisAgreement,forexpenditures
incurredinrespectoftheapprovedcostsoftheSubprojectcomponentsdescribedandreferredto
inSchedule3and4(TentativeDisbursementSchedule)ofthisAgreement.
ARTICLEIV–SUBPROJECTACCOUNTANDRECORDS
Sec4.01 ThePLGUshall:
a) Upon signing of this Agreement, establish and maintain in a bank acceptable to the
GovernmentoneSubprojectTrustAccounteachfor:
(i) fundswithdrawnfromtheDA(Grant)fortheLoanProceedfromIBRD-WBtofinance
partsoftheSubproject;
(ii) fundswithdrawnfromtheDA(Grant)fortheGOPCounterpartFundsfromthe
GOPtofinancepartsofthesubproject;and
(iii) fundsforEquityofthePLGUfortheSubproject.
A subsidiary ledger shall bemaintained for each of the above cited trust accounts
(Grant/Equity)forproperaccounting,record-keepingandmonitoringoftransactionsandto
facilitatethepreparationoffinancialreports.
b) Maintainafinancialmanagementsystemandpreparesfinancialstatementinaccordance
withconsistentlyappliedaccountingstandardsacceptabletotheBank,bothinamanner
adequate to reflect the operations and financial condition of the Participating PLGU,
includingtheoperations,resourcesandexpendituresrelatedtotheProject,includingthe
recoveryofallcosts,forcarryingouttheSub-projectoranypartthereof;
c) Establish and maintain separate accounts and books for the Subproject, reflecting all
expendituresandonwithdrawalsrequestedandreceivedfromtheDAonthebasisofthe
Statement of Receipts and Expenditures (SRE).Maintain records adequate to reflect, in
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
180
accordancewithconsistently soundaccountingpractices, theoperations, resources,and
expenditures,includingtherecoveryofallcosts,forcarryingouttheSubprojectoranypart
thereof;
d) DisbursethefundsinaccordancewiththeSubprojectcomponentstowhichtheGrantwere
providedaspresentedinSchedule2a,2band3thereof;
e) Retain,untilten(10)yearsaftertheClosingDate,allrecords,pertainingtoormentioned
inSubsections(a)to(c)ofthisSection(includingcontracts,orders,invoices,bills,receipts
andotherdocuments)evidencingtheexpendituresandpaymentsontheaccountsofthe
Subproject,andenabletheDA’srepresentativestoexaminesuchrecords;
f) Have its financial statements for theProject referred to above auditedby Independent
auditors (CommissiononAudit) acceptable to theBank, in accordancewith consistently
appliedauditingstandardsacceptabletotheBank.Eachauditofthesefinancialstatements
shallcovertheperiodofone(1)calendaryearoftheparticipatingPLGU;
g) Furnish theDA thru theNPCOand/or PSOas soon as available, but not later than two
months,anoriginalcopyofthereportsofsuchaudits,ofsuchscopeandinsuchdetailas
theNPCOandPSOshallreasonablyrequest,includingwithoutlimitationstotheforegoing,
aseparateopinionbytheauditor“ascontained inanauditcertificate” inrespecttothe
expendituresandrecordsreferredtoinSubsection(b)ofthisSectionastowhetheronthe
basisoftheSRE,theGrantwithdrawnhavebeenusedforthepurposesforwhichtheywere
provided;and
h) FurnishtheNPCOandPSOsuchotherinformationconcerningthesaidseparateaccounts,
recordsandexpendituresandtheauditthereofasNPCOandPSOmayreasonablyrequest
fromtimetotime.
ARTICLEV–SUBPROJECTEXECUTION
Sec5.01 ThePLGUshallstarttheimplementationoftheSubproject,basedontheschedulepresentedin
Schedule5(ProjectImplementationPlan)hereof,immediatelyfromthedateoftheeffectivity
ofthisAgreement.
Sec5.02 UponapprovalofthisAgreementandincompliancewiththeadditionalconditionsreferredto
inSection9.02ofthisAgreement,theDA-PSOwillreleaseorcausethereleaseofGranttothe
PLGU in accordance with Schedules 6 (Schedule of Release of Funds) and 7 (Schedule of
RequirementsfortheReleaseofFunds)ofthisAgreement.
Sec5.03 ThePLGUshallpassanordinanceappropriatingthePLGUEquityfortheSubproject,anddeposit
theseintheaccountsreferredtoinSection4.01Subsection(a)intheamountofandonsuch
datesspecifiedinSchedule3ofthisAgreement,suchfundsaretobewithdrawnanddisbursed
against theclaimsof thecontractors/creditors inaccordancewith the samescheduleof this
Agreement.
Sec5.04 TheDAthroughtheNPCOand/orPSOand/orRPCOshall:
a) Monitor,supervise,andevaluatethePLGUintheimplementationofitsSubprojectandits
compliancewiththeobligationsunderthisAgreement;
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
181
b) Assistinthereviewoftheprocurementofgoods,services,andequipmentaswellasthe
works/outputsofconsultants/contractors/suppliers,and
c) Ensure that the Subproject is implemented in accordance with the provisions of this
Agreement,relevantlaws,rulesandregulations,andprofessionalandtechnicalstandards.
Sec5.05. ThePLGUshallalso:
a) CarryoutanenvironmentalscreeningfortheproposedSubprojectinaccordancewiththe
provisionsoftheEnvironmentalSocialSafeguardsFramework(ESSF)(includingtheEMFG);
b) Prior tothecommencementofany installationofequipment, facilitiesorservicestobe
rendered, prepare, hold consultations on and disclose an Environmental Social
managementPlan(ESMP),satisfactorytothebank;
c) CarryouttheSub-projectinaccordancewiththeESMP;
d) Notamend,suspend,orabrogateanyoftheprovisionsoftheESMPwithoutpriorapproval
ofthebank;
e) IntheeventanenvironmentalcompliancecertificateisrequiredunderthePhilippineLaws
orregulations,suchcertificatehasbeenobtainedfromDENRoritsinstrumentalityatthe
regionallevelinrespectoftheactivitiesunderthesaidSub-project.
Sec5.06. ThePLGUshall:
a) Maintain, throughout the period of Project implementation, the organization,
managementandresources,satisfactorytotheBank,forcarryingoutSub-projects;
b) Establish,priortothecarryingoutofanySubprojects,andthereaftermaintain,aProvincial
ProjectManagementandImplementationUnit(PPMIU)throughouttheperiodofProject
implementation, with composition, terms of reference, staffing and other resources
acceptabletotheBank,toberesponsibleforsupportingprojectimplementationactivities,
preparing annual work plans and budgets, undertaking monitoring and evaluation and
overallaccountingandfinancialmanagement;and
c) Carry out the Subprojects with due diligence and efficiency, and in conformity with
appropriateeconomic, financial,administrative, technical,andagriculturalpracticesand
sound social and environmental standards, as set forth in the Operations Manuals
preparedandadoptedbytheProject,andacceptabletotheBank,andprovidepromptlyas
needed,thefunds,facilities,servicesandotherresourcesrequiredtherefor.
d) Submitmonthly,quarterlyandannualfinancialandphysicalprogressreportsregularlyto
PSOthroughRPCOonorbeforeduedates;
e) ComplywithalltheprovisionsapplicableinthePRDPOperationsManualsandGuidelines
insubprojectimplementation.
Sec5.07. EachparticipatingPLGUshall:
a) Intheprocurementofgoods,equipmentandservices,thePLGUshallcomplywithPRDP
Procurement Manual and the World Bank Procurement Guidelines and Republic Act
No.9184, knownas the “GovernmentProcurementReformAct, their allied statutes and
theirrespectiveImplementingRulesandRegulations,andinaccordancewiththerelevant
provisionsoftheLoanAgreementshallbesuppletoryincharacter;
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
182
b) Ensure that said goods are insured against hazards incident to the acquisition,
transportation and delivery thereof to the place of use or installation, any indemnity
thereunder tobemadepayable in a currency freelyusableby thepurchaser thereof to
replaceorrepairsuchgoods;and
c) Ensurethatsaidgoods,equipment,facilitiesandservicesincludedintheprojectareutilized
exclusivelyforthepurposeofcarryingouttheProject.
ARTICLEVI-MONITORING,REPORTINGANDEVALUATION
Sec6.01 The PLGU, through the P/MPMIU, shall comply with the procedures and guidelines for
monitoringandreportingasprescribedbythePRDP.
Sec6.02 TheDAshall,onbehalfofNPCO,PSOandRPCO,undertakeoverallmonitoringandevaluationof
theperformanceofthePLGUincarryingoutthetasks,responsibilitiesandobligationssetforth
inthisAgreement.
Sec6.03 ThePLGUshallenabletheWB,NPCO,PSOandRPCOtomonitor,examineallgoods,facilities,
sitesandequipment included intheProject, theoperationthereof,andanyrelevantrecords
and documents. The findings of themonitoring team shall be forwarded to the NPCO, PSO
and/orRPCODirectors,copiesofwhichshouldbefurnishedtothePLGU.
Sec6.04 StatusreportssuchasStatementofExpenditures(SRE),StatementofSourcesandApplication
of Funds (SSAF), financial statements (Trial Balance, Cash Flow Statement and Bank
ReconciliationStatement)attachedasSchedule8(FormatofFinancialReportsandStatements)
andMonthlyProgressReporton theSubproject shallbe forwardedby thePLGU to thePSO
throughRPCOonorbeforethe5thdayoftheensuingmonthinsuchdetailsandfrequencyas
mayreasonablyberequestedsubjecttovalidationbythePSOand/orRPCO.
Sec6.05 ThePLGUshall:
a) Maintainpolicies andproceduresadequate toenable it tomonitor andevaluateon an
ongoingbasis,inaccordancewiththeperformanceindicatorsintheLoanAgreement,their
carryingoutoftheSub-projects;and
b) Prepare, under the terms of reference satisfactory to the Bank, a semi-annual report
summarizingtheresultsofthemonitoringandevaluationactivitiesperformedonprogress
achieved in carrying out the Sub-projects during the preceding calendar semester and
settingoutthemeasuresrecommendedtoduringthenextsemi-annualperiodfollowing
suchdate and furnish the same toRPCO/PSO/NPCO to enable them to consolidate and
submittheinformationtotheBank.
Sec6.06 ThePLGUshallallowtheWB,NPCO,PSOandRPCOtoconductauditinspectionandreviewof
financialaccountingrecords.
Sec6.07 IntheeventthattheperformanceofthePLGUfallsshortoftheagreedobjectives,targetsor
projects,thePLGUshallnotifytheNPCO,PSOandRPCOinwritingwithinfifteen(15)calendar
days from the receipt of the latest monthly accomplishment report, so that necessary
adjustments,modificationsoramendmentswillbemadeortobemadeinaccordancewiththe
provisionsofthisAgreementwithoutprejudicetotheremediesavailabletotheDA.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
183
ARTICLEVII-OTHERCOVENANTS
Sec7.01 All national and local taxes, duties, fees, levies and other government impositions on the
SubprojectshallbefortheaccountofthePLGUandtheProponentGroupwhowillconsequently
implementtheSubproject.
Sec7.02 ThePLGUshallberesponsibleforbankchargesandotherexpensesassociatedwithremittances
toandfromtheSubprojectTrustAccountestablishedbythePLGUinaccordancewithSection
4.01,paragraph(a)i–iiiofthisAgreement.
Sec7.03 TheNPCO,PSOandRPCOshallmaintainamonitoringandrecordsystemreflectingallthefunds
releasedandtheexpendituresmadefortheexecutionoftheSubproject.
Sec7.04 ThePLGUwarrantsthattheSangguniangPanlalawiganhaspassedaresolution,asshown in
Schedule9(SangguniangPanlalawiganResolutionNo.___)that:
a) AuthorizetheLocalChiefExecutive(LCE)toenterintocontractswiththewinningbidders
forconsultancy,procurementofgoods/equipmentandotheragreementsrequiredtobe
donetoputthisAgreementintofulleffect,and
b) Commits resources and logistical support for the effective implementation of the
Subproject
Sec7.05 ThePLGUshallsubmittheSub-projectCompletionReportnotlaterthansix(6)monthsafterthe
lastpaymentwasmadebythePLGUtothecontractorand/ortotheproponentgroup.
Sec7.06 Upon the issuanceof theCertificateofCompletion, thePLGU shall turn-over the structures,
facilitiesandequipmentprovidedfortheSubprojectandshallcausetheProponentGroupto
operateandmaintain,orcausetobeoperatedandmaintainedproperly,thestructures,systems
andfacilitiesinstalledorestablishedundertheSubprojectandshallpassaResolutionproviding
forthefunds,facilities,servicesandotherresourcesrequiredforthepurposeforthenextten
(10)yearsaftersubprojectcompletion.TheDA-RFOshallbecopyfurnishedwiththecopyofthe
Resolutionformonitoringpurposes.
Sec7.07 a) AnynoticeorrequestrequiredorpermittedtobegivenormadeinthisAgreementshall
be inwritingandshallbedeemed tohavebeendulygivenormadewhendelivered to
NPCOorPSO;theOfficeoftheLCE,incaseofthePLGU,orsuchotheraddresswhichthe
Partiesheretomayspecifyinwriting.
b) Anyactionrequiredorpermittedtobetaken,andanydocumentrequiredorpermittedto
beexecutedunderthisAgreement,onbehalfoftheDA,maybetakenorexecutedbythe
PSOProjectDirectororhisauthorizedrepresentative.
c) Anyactionrequiredorpermittedtobetaken,andanydocumentrequiredorpermittedto
beexecutedunderthisAgreement,onbehalfofthePLGU,maybetakenorexecutedby
the LCE except those expressly reserved in this Agreement to be taken by the PLGU’s
SanggunianPanlalawigan.
Sec7.08 Bymutualconsent,thisAgreementoranypartthereofmaybechanged,modified,revisedand
amendedorsupplementedforthepurposeofeffectiveimplementationandmanagementofthe
Subproject. Allotherpartiesconcernedshallbenotified/informedofsuchchanges,revisions
andamendments.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
184
Sec7.09 All disputes or controversies between the parties arising out of or in connection with this
AgreementwhichisnotsettledbetweenthepartiesshallbeelevatedinitiallytotheDA.
Sec7.10 Notarial feesandexpenses incidental totheprocessingofthisdocumentshallbechargeable
againstthePLGUfunds.
ARTICLEVIII-REMEDIES
Sec8.01 TheDAshallsuspendthesubsequentreleasesoftheGrantifanyofthefollowingoccurs:
a) ThePLGUhasnoorinsufficientequityfortheSubproject;
b) UnsatisfactoryperformanceofthePLGUintheimplementationandexecutionoftheSub-
project.(Thereisunsatisfactoryperformanceifthereisdelayinthedelivery,complianceor
installationofmorethanseven(7)calendardaysforgoodsorequipmentprocuredlocally
orfortyfive(45)calendardaysincaseofgoodsorequipmenttobeprocuredabroad,save
theexistingapprovedextensionorsuspensionofdeliveryorinstallationorcompliance,of
goods, services, equipment and facilities by the winning
bidder/contractor/consultant/supplier.)
c) At any time theNPCO,PSOorRPCOdetermines, during the conduct of reviewand
monitoring activities, that the procurement of any contract to be financed by Grant is
inconsistentwith theprocedures set forthor referred toby theapplicableManualsand
GuidelinesofthePRDPandinreferencewiththeWBandGOPguidelines;and
d) Extraordinaryconditionssuchasforcemajeure,fortuitousevents,andthelikewhichshall
makeitnecessarytosuspendtheimplementationoftheSubproject.
Sec8.02 TheDA,atitsownsoleoption,reservestherighttoliftsuchsuspensionfortheresumptionof
releasesofGrantfortheSubprojectofthePLGU.
Sec8.03 Upon the recommendationofNPCOorPSO, the concernedRegional ProjectAdvisoryBoard
(RPAB)shallcanceltheIMAifanyofthefollowingoccur:
(i) Non-complianceorviolationbythePLGUofanyprovisionsofthisAgreement;
(ii) TheNPCOand/orPSOfoundout,withrespecttoanycontracttobefinancedbytheGrant,
thatcorruptorfraudulentpracticesasprovidedforunderR.A.3019orotherwiseknownas
Anti-GraftandCorruptpracticesActwereengagedinbyrepresentativesofthePLGUora
beneficiaryoftheGrantduringtheprocurementandexecutionofsuchcontract,without
thePLGUhavingtakentimelyandappropriateactionsatisfactorytotheNPCOand/orPSO
toremedythesituation;
(iii) Atanytime,whentheextentoftheeventsmentionedinSection8.01(d)escalatesthat
shallmakeitimprobablefortheSubprojecttocontinuetobecarriedout;and
(iv) UpontherequestofthePLGU.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
185
Sec8.04 InsuchcasethattheSubprojectispartiallyorfullycancelledduetothefaultofthePLGUasin
Section8.01Sub-sections(a),(b),and(c)thefollowingprovisionsshallapply:
a) ThePLGUshallbeobligedtoreturntoDAtheunexpendedand/orunliquidatedbalanceof
thereleasedGrantoftheSubprojectwithinonemonthfromthedateofreceiptofthenotice
ofcancellationofIMA,and
b) TheamountofGrantutilizedshallberefundedtoDAwithinthree(3)monthsfromthe
dateofreceiptofcancellationofIMA.
Sec8.05 IncaseofcancellationofIMAduetoforcemajeure,asstatedinSection8.01(d),theamount
disbursed and paid for the actual accomplishment of the subproject may not be returned
however,anyunexpendedand/orunliquidatedbalanceshouldbereturnednotlaterthantwo
(2)monthsfromthereceiptofthenoticeofapprovalofcancellationofIMA.
Sec8.06 IncaseofcancellationupontherequestofPLGUasstatedinSection8.03(d),thetotalamount
ofgrantreleasedshouldbereturnedwithintwo(2)monthsafterreceiptofnoticeofapproval
ofthecancellation.
Sec8.07 ThePLGUswho’sIMAwerecancelledbutdidnotrefundorreturnthegrantfundsinfulltoDA
willnotbeconsideredforon-goingandfutureprojectsandprojectsofthedepartment.
Sec8.08 FailuretocomplywiththeOperationalPlan:ShouldthePLGUfailtoensurethatthesubproject
isproperlyimplementedbythePGasstatedintheOperationalPlaninSchedule10(Operational
Plan)andassessmentcriteria,DAshallreviewitsoptiontodeny/withholdsimilarassistancein
thefutureuntilsuchtimethatitisconvincedthatareconsiderationonthemattershouldbe
effected.
ARTICLEIX-EFFECTIVITY
Sec9.01 ComplianceofPreconditionsbythePLGUfortheeffectivityofthisAgreement:
ASangguniangPanlalawiganResolutionandAppropriationOrdinancehasbeenpassedcommittinglogisticaland
fundingsupporttothePLGUandtheSubproject,particularlywithrespecttotheequitycontribution
Sec9.02 ThisAgreementshallbecomeeffectiveuponsigningofthepartiesconcernedandcompliance
bythePLGUoftheadditionalpreconditionsforeffectivenessreferredtoinSection9.01ofthis
Agreement and shall subsist and remain in full force and effect ten (10) years after the
subprojecthasbeenturnedoverandatsuchtimethepartiesheretoshallbemutuallyreleased
fromallobligationshereunder.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
186
INWITNESSWHEREOF,theParties,havecausedthisImplementationManagementAgreementtobesignedin
________,Philippinesonthis____dayof_____________.
By:By:
__________________________________________________________________________________
ProjectDirectorGovernor
ProjectSupportOffice(PSO)–_______
By:
____________________________________
Director
RegionalProjectCoordinationOffice(RPCO)________
WITNESSES:
___________________________________ ______________________________________
PRDPFocalPerson–RPCO____ProvincialAccountant/Treasurer
_________________________________________________________________________
ProjectAccountant–PSO______SPMember,FinanceCommittee
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
187
ACKNOWLEDGMENT
REPUBLICOFTHEPHILIPPINES)
_____________________________)S.S.
Beforemethis__________dayof___________________2014,at_____________________personally
appeared:
Name CompetentEvidenceofIdentity PlaceandDateIssued
___________________________________________________________________________________________
____________________________________________________________________________________________
Known to me and to me known to be the same persons who executed the foregoing agreement and they
acknowledged to be the same is of their own free and voluntary act and deed and those of the offices they
represent.
WITNESSMYHANDANDSEALonthedateandattheplacefirstwrittenabove.
NOTARYPUBLIC
UntilDecember31,2014
PTRNo.____________
DocNo________
PageNo________
BookNo._______
Seriesof2014_____
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
188
SCHEDULES
Schedule1 - DefinitionofTerms
Schedule2 - DescriptionofSubproject
Schedule3 - EstimatedTotalSubprojectCost
Schedule3A - EstimatedSubprojectCostforCivilWorks
Schedule3B - EstimatedSubprojectCostforEnterprise
Schedule4 - TentativeDisbursementSchedule
Schedule5 - ProjectImplementationPlan
Schedule6 - ScheduleofReleaseofFunds–Consolidated
Schedule6A - ScheduleofReleaseofFunds–CivilWorks
Schedule6B - ScheduleofReleaseofFunds–Enterprises
Schedule7 - ScheduleofRequirementsfortheReleaseofFunds
Schedule8 - FormatofFinancialReportsandStatements
a.) StatementofReceiptsAndExpenditures(SRE)
b.) StatementofSourcesandApplicationofFunds(SSAF)
c.) TrialBalance
d.) BalanceSheet
e.) CashFlowStatement
Schedule9 - SangguniangPanlalawigan(SP)Resolution–Resolution
AuthorizingtheProvincialGovernortoExecuteand
Enter into an IMA and Approving the Appropriation for the LGU
EquityoftheSubprojectCost
Schedule10 - OperationalPlan
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
189
Annex19-SampleEnterpriseInvestmentAgreement(EA)
RepublicofthePhilippines
Provinceof_________________
PHILIPPINERURALDEVELOPMENTPROJECT
ENTERPRISEINVESTMENTAGREEMENT
KNOWALLMENBYTHESEPRESENTS:
THISAGREEMENTismadethis__________dayof___________,201_,byandbetweenthefollowing:
TheProvincialGovernmentof________________,aLocalGovernmentUnitoftheRepublicofthePhilippines,
with principal address at _____________________ represented herein by its Provincial Governor,
___________________,andhereinafterreferredtoasthe“PLGU”
and
The__________________________,adulyregisteredorganizationoftheRepublicofthePhilippines,underthe
_______________________, with office address at _________________________, represented herein by its
President________________,andhereinafterreferredtoasthe“PROPONENTGROUP”;
-WITNESSETH-
WHEREAS,theDAisimplementingthePhilippineRuralDevelopmentProject(PRDP)aimedatincreasingfarm
and fishery productivity and incomes in target areas in all 16 regions of the country by improving access of
farmers andother industry players to a strategic networkof infrastructure,market information and support
services;
WHEREAS,theEnterpriseDevelopmentComponent(I-REAP)ofPRDPintendstostrengthenanddevelopviable
agri-fisherybasedenterprisesthroughthedevelopmentofefficientvaluechainsofkeyagriculturalandfishery
productsintargetedprogramareas;
WHEREAS,allfundsconcerningtheimplementationoftheenterprisewillbecoursedthroughtheProjectSupport
Office(PSO)andwillbemadeavailabletoparticipatingprovincialLGUsandproponentgroups;
WHEREAS,theLocalGovernmentCoderationalizestheneedforupgradinglocalgovernmentcapabilitiesthrough
directprojectimplementationincollaborationwithNationalGovernmentAgencies(NGAs)andtheprivatesector;
WHEREAS,theLocalGovernmentCodeof1991extendsgenuineandmeaningfullocalautonomytotheLGUsto
enable themtoattain their fullestdevelopmentasself-reliantcommunitiesandtomakethemmoreeffective
partnersintheattainmentofnationalgoals;
WHEREAS,theLocalGovernmentCodeof1991devolvestheDAfunction-theprovisionofagriculturalsupport
services,agriculturalextensionandon-siteresearchservicesandfacilitiestotheLGUs;
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
190
WHEREAS, the Province of _________ identified __________(title of the proposed enterprise) as its priority
subprojectforPRDPasindicatedintheapprovedPCIP;
WHEREAS, theProponentGroup submittedprojectproposal entitled “________________________________”
with all the necessary documents to support the implementation of the subproject under the Enterprise
DevelopmentComponent;
WHEREAS, the proposal of _______________________ (title of the enterprise) was endorsed by PLGU and
approvedbyRegionalProjectAdvisoryBoard(RPAB)perRPABResolutionNo.dated_______________;
WHEREAS, the World Bank/NPCO/PSO has issued a No Objection Letter (NOL 1) on the business plan of
_________________ (title of the enterprise) dated _____________, amounting to Twelve Million Forty Two
Thousandand44/100Pesos(PhP12,042,000.44)netoftheProponentGroup’sequity;
NOWTHEREFORE,thepartiesheretoherebyagreeasfollows.
ARTICLEI
DEFINITIONOFTERMS
Sec.1.01 UnlessthisAgreementotherwiserequires,thetermsofacronymusedinthisAgreementshall
havedefinitionsandmeaningsassetoutinSchedule1(DefinitionofTerms).
ARTICLEII
SCOPEOFAGREEMENT
Sec.2.01 Thisagreementshallcovertheimplementationof________________(titleoftheenterprise),
referredas the“Enterprise” inaccordancewith theapprovedBusinessPlan tobe located in
_________________.
ARTICLEIII
SUBPROJECTDESCRIPTIONANDCOSTESTIMATES
Sec.3.01 Thesubprojectcoveredbythisagreementis_________________(titleoftheEnterprise),with
a total cost of ______________ excluding Proponent Group equity described in detail in
Schedule2(DescriptionofEnterprise).
Sec.3.02 TheEnterprisecostis__________________________(amountinwords)(Php______________)
netofcivilworksthebreakdownofwhichissetforthinSchedule3EstimatedSubprojectCost
for__________________(titleoftheenterprise)).
Sec.3.03 The PLGU shall make available from the Enterprise Fund eighty percent (80%) or
________________________________ (amount inwords) (Php______) under the Enterprise
DevelopmentComponentasfinancialassistancetotheProponentGroupintheformofGrant
subprojecttothetermsandconditionsofthisAgreement.
Sec.3.04 TheProponentGroupequityshallbeatleasttwentypercent(20%)ofthetotalEnterpriseCost
whichconsistsofcashequity intheamountof______________________________________
(amount in words) (Php____________) and equity in kind amounting to
_________________________ (amount inwords) (Php______) tobeusedexclusively for the
enterprise.
Sec.3.05 Anyincreaseinenterprisecostbutnotbeyondtheapprovedcostofbusinessplanshallfollow
theapprovedfinancingmixanddoesnotrequireamendmenttoEA.Incasethesubprojectcost
exceedstheamountstated,thePGwillprovideadditionalamount.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
191
Sec.3.06 The Grant shall be allocated in accordance with the provisions of this Agreement, for
expendituresincurredinrespectoftheapprovedcostsoftheEnterprisedescribedandreferred
toinaccordancewithAnnexA(WorkandFinancialPlan)andasprovidedinthesubmittedand
approvedAnnexB(ProcurementPlan)ofthisAgreement.
ARTICLEIV
SUBPROJECTACCOUNTANDRECORDS
Sec.4.01 ThePGshall:
a) UponsigningofthisAgreement,establishandmaintaincurrentaccountinaCommercial
BankacceptabletothePSOandtoPLGU;
b) Maintainafinancialmanagementsystemandpreparefinancialstatementinaccordance
withconsistentlyappliedaccountingstandardsacceptabletotheBank,bothinamanner
adequatetoreflecttheoperationsandfinancialconditionoftheParticipatingPG;
c) EstablishandmaintainaccountsandbooksfortheEnterprise,reflectingallexpenditures
andonwithdrawalsrequestedandreceivedfromthePLGUonthebasisoftheStatement
ofReceiptsandExpenditures(SRE);
d) DisbursethefundsinaccordancewiththeSubprojectcomponentstowhichtheGrantwere
providedaspresentedinSchedule4(TentativeDisbursementSchedule)thereof;
e) Retain,untilten(10)yearsaftertheClosingDate,allrecords,pertainingtoormentioned
inSubsections(a)to(c)ofthisSection(includingcontracts,orders,invoices,bills,receipts
andotherdocuments)evidencingtheexpendituresandpaymentsontheaccountsofthe
EnterpriseandenabletheDAandPLGUrepresentativestoexaminesuchrecords;
f) Have its financial statements for theProject referred toaboveauditedby independent
auditors acceptable to the Bank, NPCO, PSO and PLGU. Each audit of these financial
statementsshallcovertheperiodofone(1)calendaryearoftheparticipatingPG;
g) FurnishthePLGUthruthePPMIUassoonasavailable,butnotlaterthantwomonths,an
originalcopyofthereportsofsuchaudits,ofsuchscopeandinsuchdetailasthePLGU
shallreasonablyrequest;and
h) FurnishthePLGUsuchotherinformationconcerningthesaidseparateaccounts,records
andexpendituresandtheauditthereofasPLGUmayreasonablyrequestfromtimetotime.
ARTICLEV
DUTIESANDRESPONSIBILITIES
Sec5.01 ThePLGUthroughtheProvincialProgramManagementandImplementingUnit(PPMIU)shall
havethefollowingdutiesandresponsibilities:
a) MakeavailabletotheProponentGrouptheenterprisefundanditstimelyreleasesasper
approvedworkandfinancialplancorrespondingtothedetailedimplementationplanand
and/orprogramofworks;
b) ProvidetechnicalsupporttotheProponentGroupinallaspectsofenterprisedevelopment
includingconductofcapacitybuildinginterventions;
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
192
c) EnsurethatgoodsandworksareprocuredinaccordancetotheEnterpriseDevelopment
OperationsManualandProcurementGuidelinesofPRDP;
d) AssisttheProponentGroupininstallingfinancialrecordstofacilitateproperdisbursement
offunds,liquidationandrecordskeeping;
e) Assign a focal person to conduct periodic monitoring and evaluation of enterprise
implementationandoperationandprovideregularfeedbacktoProponentGroup;
f) Ensure adherence of the Proponent Group to PRDP processes as provided in the PRDP
EnterpriseDevelopmentOperationsManual;
g) Submit regularly the monitoring and evaluation reports to the RPCO as defined in the
Results-BasedMonitoringandEvaluation(RBME)GuidelinesforPRDP;and
h) Facilitate the turn-over to the Proponent Group of goods and works procured for the
enterpriseuponsubprojectcompletionthruaDeedofDonationandCertificateofTurn-
Over.
Sec5.02 TheProponentGroupshall:
a) Ensuresmoothimplementationoftheenterpriseaccordingtotheapprovedbusinessplan
anddetailedimplementationplanand/orprogramofworksandinadherencetosocialand
environmentalstandards;
b) Ensurebroadparticipationoffarmersandotherkeystakeholdersintheenterpriseactivities;
c) Undertakeoperationsandmaintenanceofthefacilitiesandotherpropertiesrelevanttothe
enterprise;
d) EnablethePLGUandotherentitiestoexaminegoodsandworksprocuredandtheoperation
thereofincludinganyrelevantrecordsanddocuments;
e) Implementcontinuouscapabilitybuildingandcapacityimprovementfortheenterpriseand
otherfarmersstakeholders;
f) All expenses that will be incurred in the enterprise implementation in excess of the
approvedenterprisefundshallbefullyassumedbytheProponentGroup.However,ifthe
actualcostincurredislowerthantheapprovedamount,theProponentGroupmayrequest
thePLGUtoreprogramthefundforsimilarprojectprovideditshallnotrequireadditional
fundsfromtheprovince;
g) Maintainfinancialrecordstoproperlydisburseandliquidateenterprisefunds;and
h) Submitrequiredphysicalandfinancial reportstothePLGU.Thesereportsshallbemade
accessibletoallPRDPimplementingunits.
ARTICLEVI
SUBPROJECTEXECUTION
Sec6.01 ThePGshall start the implementationof theEnterprise,basedon thepresentedSchedule5
(ImplementationPlan)andinaccordancewiththeapprovedbusinessplan,immediatelyfrom
thedateoftheeffectivityofthisAgreement.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
193
Sec6.02 UponapprovalofthisAgreement,thePLGUwillreleaseorcausethereleaseofGranttothePG
inaccordancewithSchedule6(ScheduleandRequirementsfortheReleaseofFunds)ofthis
Agreement.
Sec6.03 ThePLGUthroughthePPMIUshall:
(a) Monitor, supervise,andevaluate thePG in the implementationof itsEnterpriseand its
compliancewiththeobligationsunderthisAgreement;
(b) Assist theProponentGroup in the formationof a procurement committee as stated in
articleVIIISec.8.03ofthisAgreement;
(c) Assistinthereviewoftheprocurementofgoods,services,civilworksandequipmentas
wellastheworks/outputsofconsultants/contractors;
(d) IfthePGuponassessmentisnotcapableintheprocurementprocessofPRDP,thePLGU
shall, in behalf of the PG, shall procure the goods, services orworks necessary for the
implementationoftheenterprise;and
(e) Ensure that the Enterprise is implemented in accordance with the provisions of this
Agreement,relevantlaws,rulesandregulations,andprofessionalandtechnicalstandards.
Sec6.04 ThePGshall
(a) Submitmonthly,quarterlyandannualfinancialandphysicalprogressreportsregularlyto
PLGUthroughRPCOonorbeforeduedates.
(b) ComplywithalltheprovisionsapplicableinthePRDPOperationsManualsandGuidelines
insubprojectimplementation.
Sec6.05 Intheprocurementofinfrastructure,goods,suppliesandconsultancyservices,thePLGUshall
complywithWorld Bank ProcurementGuidelines and Republic Act No. 9184, known as the
“GovernmentProcurementReformAct”,theiralliedstatutesandtheirrespectiveImplementing
RulesandRegulations,andtheNEDAGuidelinesontheProcurementofConsultingServicesfor
GovernmentProjects(ImplementingRulesandRegulations)respectively.
ARTICLEVII
MONITORING,REPORTINGANDEVALUATION
Sec7.01 ThePLGU,throughthePPMIU,shallcomplywiththeproceduresandguidelinesformonitoring
andreportingasprescribedbythePRDP.
Sec7.02 ThePLGUshall,onbehalfofNPCO,PSOandRPCO,undertakeoverallmonitoringandevaluation
oftheperformanceofthePGincarryingoutthetasks,responsibilitiesandobligationssetforth
inthisAgreement.
Sec7.03 TheWB,NPCO,PSO,RPCOandPLGUshallaudit,monitorandevaluatetheprogressandstatus
oftheimplementationandmanagementoftheEnterprise.Thefindingsofthemonitoringteam
shallbeforwardedtotheNPCO,PSOand/orRPCODirectors,copiesofwhichshouldbefurnished
tothePLGUandPG.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
194
Sec7.04 StatusreportssuchasStatementofReceiptsandExpenditures(SRE),and/orMonthlyprogress
ReportontheSubprojectshallbeforwardedbythePGtothePLGUonorbeforethe5thdayof
theensuingmonth insuchdetailsand frequencyasmayreasonablybe requestedsubject to
validationbythePLGUandRPCO.
Sec7.05 ThePGshallallowtheWB,NPCO,PSO,RPCOandPLGUtoconductauditinspectionandreview
offinancialaccountingrecords.
Sec7.06 In theevent that theperformanceof thePG falls shortof theagreedobjectives, targetsor
programs,thePGshallnotifythePLGUinwritingofthenecessaryadjustments,modifications
or amendmentsmade or to bemade in accordancewith the provisions of this Agreement
withoutprejudicetotheremediesavailabletothePLGU.
ARTICLEVIII
OTHERCOVENANTS
Sec8.01 ThePGshallberesponsibleforbankchargesandotherexpensesassociatedwithremittancesto
andfromtheEnterpriseBankAccountestablishedbythePGinaccordancewiththisAgreement.
Sec8.02 ThePGshallmaintainamonitoringandrecordsystemreflectingallthefundsreleasedandthe
expendituresmadefortheexecutionoftheSubproject.
Sec8.03 The PG may manage procurement of goods, works and services. This will depend on the
established capacity of the PG. The basic requirement/capacity of the PG to manage the
procurementwithintheprescribedthresholdshallincludeformation(ifnoexistingprocurement
committee) of bidding/procurement committee, experience and knowledge on
procurement/purchasingandshouldhaveattendedtheprocurementtrainingunderthePRDP.
Sec8.04 ThePGshallsubmittheSubprojectCompletionReportnotlaterthanthree(3)monthsafterthe
dateofissuanceofCertificateofCompletiontotheLGU.
Sec8.05 UpontheissuanceoftheCertificateofCompletion,thePGshalloperateandmaintain,orcause
to be operated andmaintained properly, the structures, systems and facilities constructed,
installedorestablishedundertheEnterprise
Sec8.06 (a) AnynoticeorrequestrequiredorpermittedtobegivenormadeinthisAgreementshall
beinwritingandshallbedeemedtohavebeendulygivenormadewhendeliveredtoPG;
orsuchotheraddresswhichthePartiesheretomayspecifyinwriting.
(b)Anyactionrequiredorpermittedtobetaken,andanydocumentrequiredorpermittedto
beexecutedunderthisAgreement,onbehalfoftheLGU,maybetakenorexecutedbythe
LocalChiefExecutive(LCE)orhisauthorizedrepresentative.
(c) Anyactionrequiredorpermittedtobetaken,andanydocumentrequiredorpermittedto
beexecutedunderthisAgreement,onbehalfoftheLGU,maybetakenorexecutedbythe
LCEexceptthoseexpresslyreservedinthisAgreementtobetakenbytheLGU’sSanggunian
Panlalawigan.
Sec8.07 Bymutualconsent,thisAgreementoranypartthereofmaybechanged,modified,revisedand
amendedorsupplementedforthepurposeofeffectiveimplementationandmanagementofthe
Subproject. Allotherpartiesconcernedshallbenotified/informedofsuchchanges,revisions
andamendments.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
195
Sec8.08 All disputes or controversies between the parties arising out of or in connection with this
AgreementwhichisnotsettledbetweenthepartiesshallbeelevatedinitiallytotheDA-PRDP
RPCO_.
Sec8.09 Notarial feesandexpenses incidentaltotheprocessingofthisdocumentshallbechargeable
againstthePGfunds.
ARTICLEIX
REMEDIES
Sec9.01 ThePLGU,afteraccordingdueprocesstoPG,shallsuspendthesubsequentreleasesoftheGrant
ifanyofthefollowingoccurs:
(a) ThePGhasnoorinsufficientequityfortheSubproject;
(b) Unsatisfactory performanceof the PG in the implementation and execution of the Sub-
project;
(c) AtanytimetheNPCO,PSO,RPCOandPLGUdetermines,duringtheconductofreviewand
monitoring activities, that the procurement of any contract to be financed by Grant is
inconsistentwiththeproceduressetforthorreferredtobytheWBandGOP;and/or
(d) Extraordinaryconditionssuchasforcemajeure,fortuitousevents,andthelikewhichshall
makeitnecessarytosuspendtheimplementationoftheSubproject.
Sec9.02 TheLGU,atitsownsoleoption,reservestherighttoliftsuchsuspensionfortheresumptionof
releasesofGrantfortheSubprojectofthePG.
Sec9.03 Upon the recommendationof thePPMIU, theLCEshall cancel theEA ifanyof the following
occur:
(a) Non-complianceorviolationbythePGofanyprovisionsofthisAgreement;
(b) TheNPCO,PSO,RPCOand/orPLGUfoundout,withrespecttoanycontracttobefinanced
bytheGrant,thatcorruptorfraudulentpracticeswereengagedinbyrepresentativesofthe
PGorabeneficiaryoftheGrantduringtheprocurementandexecutionofsuchcontract,
withoutthePGhavingtakentimelyandappropriateactionsatisfactorytotheNPCO,PSO,
RPCOand/orPLGUtoremedythesituation;
(c) Atanytime,whentheextentoftheeventsmentionedinSection9.01(d)escalatesthatshall
makeitimprobablefortheSubprojecttocontinuetobecarriedout;and/or
(d) UpontherequestofthePG.
Sec9.04 InsuchcasethattheSubprojectissuspendedorcancelledduetothefaultofthePGasinSection
9.01Sub-sections(a),(b),and(c)thefollowingprovisionsshallapply:
(a) ThePGshallbeobligedtoreturntoPLGUtheunexpendedand/orunliquidatedbalanceof
thereleasedGrantoftheSubprojectwithinonemonthfromthedateofreceiptofthenotice
ofcancellationofEA.
(b) TheamountofGrantutilizedshallberefundedtoLGUwithinthree(3)monthsfromthe
dateofreceiptofcancellationofEA.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
196
Sec9.05 In caseof cancellationofEAdue to forcemajeure,as stated inSection9.01(d), theamount
disbursed and paid for the actual accomplishment of the subproject may not be returned
however,anyunexpendedand/orunliquidatedbalanceshouldbereturnednotlaterthantwo
(2)monthsfromthereceiptofthenoticeofapprovalofcancellationofEA.
Sec9.06 IncaseofcancellationupontherequestofPGasstatedinSection9.03(d),thetotalamountof
grantreleasedshouldbereturnedwithintwo(2)monthsafterreceiptofnoticeofapprovalof
thecancellation.
Sec9.07 ThePGswhoseEAwerecancelledbutdidnotrefundorreturnthegrantfundsinfulltoPLGU
will not be considered for on-going and future projects and programs of the DA and PLGU,
withoutprejudicetothefilingofcaseagainsttheresponsibleofficialsofPG.
Sec9.08 FailuretocomplywithOperationalPlan:ShouldthePGfailtoproperlyoperatetheenterprise
in accordancewithSchedule7 (Operational Plan) and assessment criteria for a continuous
periodofone(1)yearwithoutjustifiablecauseandwithintheten(10)yearperiodfromissuance
of Certificate of Completion, the PLGU shall have the right to recover ownership over the
facilitiesand/orequipmentwhicharecoveredbythisAgreementsubjecttoexistinglaws,rules
andregulations.
ARTICLEX
GENERALPROVISIONS
Sec.10.01 AmendmentsandEffectiveness.Thepartiesmay,bymutualagreement,amend,alter,ormodify
thisAgreementanytimeanaddendumsignedbybothparties.ThisAgreementshalltakeeffect
onthedateofsigningofbothparties,unlesssoonerterminatedbyeitherparty,providedfurther
thatsuchterminationwillnotprejudiceanyongoingsubproject
INWITNESSWHEREOF,thepartnershavedulyexecutedthisAgreementonthedayandyearsetforthhereinabove.
TheProvincialGovernment TheProponentGroup
of________________
___________________ ______________________________
Governor Position,(NameofthePG)
WITNESSES:
________________________ ______________________________
________________________ ______________________________
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
197
ACKNOWLEDGEMENT
RepublicofthePhilippines)
_____________________)S.S.
BEFORE ME, a Notary Public for and in _____________, this day of 201_, personally
appeared:
Name CompetentEvidenceofIdentity Date/PlaceofIssue
________________ __________________________ ________________
________________ __________________________ ________________
knowntomeandtomeknowntobesamepersonswhoexecutedtheforegoinginstrumentandthey
acknowledgedtometobethesamearetheirfreeandvoluntaryactanddeedandthatoftheparties
theyrepresent.
WITNESSMYHANDANDSEALonthedateandtheplacefirstabovewritten.
NOTARYPUBLIC
DocNo._____
PageNo.______
BookNo.______
Seriesof201_
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
198
LISTOFANNEXES
AnnexA – ApprovedWorkandFinancialPlan
AnnexB – ApprovedProcurementPlan
LISTOFSCHEDULES
Schedule1 – DefinitionofTerms
Schedule2 – DescriptionofEnterprise
Schedule3 – EstimatedSubprojectCostoftheEnterprise
Schedule4 – TentativeDisbursementSchedule
Schedule5 – ImplementationPlan
Schedule6 – ScheduleandRequirementsfortheReleaseofFunds
Schedule7 – OperationalPlan
Schedule8 – DocumentaryRequirementsfortheLiquidationofFundTransfer
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
199
Annex20-SUPPLEMENTALGUIDELINESFORTHEIMPLEMENTATIONOF
SMALLI-REAPLIVELIHOODSUBPROJECTINYOLANDAANDEARTHQUAKE
AFFECTEDAREAS(REGIONS6,7,8)OFTHEPHILIPPINERURALDEVELOPMENT
PROJECT
I. RATIONALE
ThePhilippineRuralDevelopmentProject(PRDP)isasix-year(2013-2018)initiativeenvisionedtoincreasefarm
andfisheryproductivityandincomesintargetareasinall16regionsofthecountry.Theprojectseekstoachieve
thisobjectivebyimprovingaccessoffarmersandotherindustryplayerstoastrategicnetworkofinfrastructure,
marketinformationandsupportservices.Specificinvestmentsandinterventionsaretobeimplementedunder
four central componentsof theproject,namely: 1) LocalPlanning (IPLAN);2) InfrastructureDevelopment (I-
BUILD);3)EnterpriseDevelopment(I-REAP);and4)ProjectSupport(I-SUPPORT).
AssupportedinWorldBank’sProjectAppraisalDocument,thefirstyearofprojectimplementationwouldpay
specialattentiontothoseareasaffectedbyTyphoonYolanda(Haiyan)andtheBoholearthquake(SeeAnnexA
forthelist).Thetypesofenterprisesandinfrastructuretobesupportedareflexibleintheseaffectedareassuch
that itwill specifically target thegaps.Forexamplesmall-scale farmersand fisherswhohave lostproductive
assets(boats,coconuttrees,etc.,)coconutnurserydevelopmentlinkedwithreplantingbygroupsofsmall-scale
farmersorboatbuildinglinkedtofisheriesorseaweedproduction,amongothers.
II. SCOPEANDCOVERAGE
TheguidelinescontainonlytheguidingprinciplesintheidentificationandapprovalofIREAPYear1subprojects
inareasaffectedbyTyphoonYolanda(Haiyan)andtheearthquakeinBohol.
Procedures and requirements in financing the subproject, downloading of funds, procurement process and
monitoringandevaluationshallfollowtheFinancialGuidelines,ProcurementGuidelinesandRBMEGuidelines,
respectively.
III. OBJECTIVES
Ingeneral,thisaimstoprovidesustainableincomegeneratingactivitiestofarmersandfisherswhoselivelihood
wereaffected.
Specifically,itaimsto:
1. Providefoodsecurityinterventionstoaffectedfarmersandfisherstorespondquicklytotheirbasicneeds;
2. BringbacklivelihoodofthefarmersandfishersdamagedbyTyphoonHaiyanandtheearthquakebygiving
neededinterventions;and
3. Augmentthe incomeofthefarmersandfishers inaffectedareasbyprovidingproductionandmarketing
support
IV. ELIGIBLESUBPROJECTS
Allagri-basedandagribusinesssubprojectsareeligible.However,focuswillbegiventoprojectsorenterprisesof
the farmersandfishers thatweredamagedoraffectedbyTyphoonHaiyanandtheearthquake inBoholand
those thatwillprovide immediate livelihood to farmersand fisherfolk.Subprojects thatwill complement the
livelihoodactivitiesreceivedbytheprojectbeneficiariesthroughtheRAYProgramandfromotherdonorsmay
alsoqualify.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
200
V. ELIGIBILITYREQUIREMENTSFORTHEPROPONENTGROUP
AProponentGroup(PG)isdefinedasorganizationoffarmersorfishersintheaffectedareaswhichmayormay
notberegisteredwithDOLE,CDAorSEC.
1. LetterofIntentaddressedtotheLGU
2. LGUEvaluationontheFinancialandOrganizationalCapabilityoftheProponentGroup
3. AswornaffidavitoftheSecretaryoftheNGO/POthatnoneofitsincorporators,organizers,directors,
orofficials is anagentofor relatedby consanguinityor affinityup to the fourth civil degree to the
officialsofthegovernmentimplementingagencyauthorizedtoprocessand/orapprovetheproposal,
theMOAandthereleaseoffunds.RelationshipofthisnatureshallautomaticallydisqualifytheNGO/PO
frombeinggrantedthefund
4. CertificateofNoUnliquidatedAccountwithLGUandDA.
5. Capacitytoprovideanequityorcounterpartofatleast20%incashand/orkindtothetotalenterprise
cost; Proof of Equity (Cash- BankCertificate); Land Title/ LeaseContract/DeedofDonation, etc (as
applicable)
VI. IMPLEMENTATIONPROCEDURES
1. IdentificationofSubproject
Identification of subproject will be based on the immediate need of the farmers and fishers whose
livelihoodhasbeendamagedandaffectedbytyphoonHaiyanandtheearthquake.Thesubprojectmay
also focusonestablishingmarketable surplus,production supportandcommonservice facilities.The
subprojectmayemanatedirectlyfromthepossibleproponentsorfromthelocalgovernmentunits.
2. ConductofSiteValidationandEvaluation
The Regional Project Coordination Office (RPCO) together with the P/M/CPMIU shall conduct site
validationandevaluationoftheproposedproponentgroup(PG).ThecriteriaforselectionofPGstated
inAnnex8oftheI-REAPOperationsManualmaybeusedinidentifyingthePGwhowillimplementthe
subproject.
3. PreparationofSubprojectProposal/BusinessPlan
After identification of subproject and the PG, the P/M/CPMIU will facilitate the preparation of the
subprojectproposalanddocumentaryattachments(SeeAnnexAfortheSubprojectProposalOutline).
TheP/M/CPMIUwill alsoassist thePG in complyingwithall thedocumentary requirementsofPRDP
includingrequirementsforinfrastructure(ifany)andSocialandEnvironmentalSafeguardsasstatedin
theI-BUILDOperationsManualandSESGuidelines,respectively.ThePGandthePPMIU/MPMIU/CPMIU
asthecasemaybeshouldhelpeachotherinthesubprojectproposalpreparation.
The subproject proposal including all its attachments should be approved by the Governor or
City/MunicipalMayor,asthecasemaybeandshallbeendorsedtotheRPCOforTechnicalReview.
4. ReviewandApprovalofSubprojects
a. RPCOTechnicalReview
TheRPCOuponreceiptofthesubprojectproposalandallitsattachmentsshallconveneaTechnical
ReviewCommitteewhichwillbecomposedofmembersfromRPCOI-REAP,commodityexpertfrom
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
201
concernedagencyorDAbannerprogramandexpertsfromothergovernmentagencyandtheprivate
sector.ThetechnicalevaluationwillbedoneusingtheI-REAPAppraisalForm(Annex13oftheI-
REAPOM).A technical reviewreportdulysignedby theRPCO I-REAPHeadandapprovedby the
RegionalExecutiveDirectororRPCOFocalPersonshallbepreparedbytheRPCOhighlightingtheir
findingsonthesubprojectproposal. Ifthereviewisfoundtobesatisfactoryordependingonthe
findingsoftheTechnicalReviewTeam,theRPCOshallendorsethesubprojectproposalincludingall
itsattachmentsandacopyofthesignedAppraisalFormandtechnicalreviewreporttothePSO.
ForinfrastructurecomponentoftheI-REAPsubproject,theDetailedEngineeringDesign(DED),Bill
ofMaterialsandProgramofWorksandothersupportingdocumentsshallbereviewedbyI-BUILD.
b. ComplianceReview
ThePSOshallconductComplianceReviewtothesubmittedsubprojectproposalanditsattachments.
ThePSOshallvalidateandconfirmthetechnicalreviewconductedbytheRPCOandthecompliance
of the subproject to the PRDP requirements. The PSO shall prepare Compliance Review Report
highlightingitsfindings.ItwillendorseitsfindingstotheRPCO.
c. RPABApproval
Subprojectswhichsatisfactorilypassedtechnicalreviewandcompliancereviewwillbeendorsedby
theRPCOtotheRPABforapproval.AnRPABResolutionwillbepreparedbytheRPCOwhichwillbe
the basis of approving the subproject and the preparation of the ImplementationManagement
Agreement(IMA).
5. IssuanceofNoObjection
LivelihoodsubprojectswillbeissuedNoObjectionLetterbythePSO.Proceduresandthresholdssetin
theI-REAPOperationsManualwillbefollowed.
6. SigningoftheImplementationManagementAgreement(IMA)
UponRPABApproval,thePSOshalldrafttheIMAwhichwillserveastheagreementbetweenthePSO,
RPCO and the P/M/C LGU in the implementation of the I-REAP subproject. A separate IMA shall be
preparedfortheenterpriseoperationandtheinfrastructurecomponentofthesubproject.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
202
Annex21-SUBPROJECTPROPOSALOUTLINE
SUBPROJECTPROFILE(2pagesmax)
Title (Indicateplace,productandenterpriseinterventioninthetitle)
Location (IndicateMunicipalitiescoveredintheenterpriseintervention)
Components (Indicateoneormoreenterprise interventionsbasedonenterpriseprioritization results
and describe briefly how each component will contribute to the development of the
industryandthegoalsofPRDP)
¨ InputProvision; ̈Production; ̈Postharvest; ̈Processing;
¨ Marketing/Trading
Products and/or
Services
(Indicateproduct/sform/commonnameandorservices,annualcapacityandseasonality,
ifapplicable)
Product/s:____________________
Service/s:_____________________
Annualcapacity:______________
Seasonality:___________________
Stageofenterprise/s ̈Start-up; ̈Expansion; ̈Upgrading
Name of the
ProponentGroup
(Indicate official name of proponent group as registered based on proponent group
selectionresults)
Contact Person /
Designation
Address
ContactNumbers Landline:
Fax:
Mobile:
E-mail:
BusinessRegistration ¨ CooperativeDevelopmentAuthority;YearRegistered:__________
¨ SecuritiesandExchangeCommission;YearRegistered:__________
¨ DepartmentofLabor&Employment;YearRegistered:__________
EnterpriseClustersorother
participatinggroups
Producers/Suppliers ( Indicate groups and their correspondingno. of producers, production area, estimated
yield,showseasonalityifapplicable)
TargetBuyers (Indicatebuyersandtheirrespectiveandvolumerequirementperseasonoryearincluding
marketingarrangementse.g.contract,P.O)
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
203
InvestmentCapitalRequirement
Components/
Line
Items(shouldbe
specific)Amount,PhP
FundSources(PhP)
LP(Cash)GOP
(Cash)
LGU
(Cash)
ProponentGroup
Cash In-Kind
NG–LGUCostSharing
FundSource
EnterpriseCost InfrastructureCost Livelihood
Proposal
Amount
(PhP)Amount(PhP)
Cost
Sharing
(%)
Amount
(PhP)
Cost
Sharing
(%)
LP 60 80
GOP 20 10
LGU 20 10
Total 100
PGEquity 20
TotalwithPG
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
204
EXECUTIVE SUMMARY (1-2-page summary of the sub-project proposal highlighting key points such as:
descriptionofthesubprojectanditscomponents,projectrationale,damagecausedbythetyphoon/earthquake,
briefdescriptionoftheproponent,targetmarket,managementandownershipoftheenterprise,operational
plan,financingrequirementincludingcostsharingandequityandfinancialreturns)
I.PROJECTRATIONALE
1. Focusingontheeffectofthetyphoon/earthquaketotheeconomicsituationofthebeneficiaries,discuss
indetailwhytheproject/enterpriseisbeingproposed.Whatisthepreviousstatusoftheorganization
(economicactivitiesundertaken)andthestatusofthefarmersbeforethecalamity,whatistheircurrent
statusandwhatistheexpectedimpactofthesubprojecttotheireconomicupliftment.
2. Discusstheprofileoftheproponent,theprojectsoractivitiesundertaken,organizationalstatus(newor
existing),reasonforselectingtheproponent,numberandprofileofitsmembers.
3. Statetheprojectobjectives(generalandspecific).
II.MARKETSTUDY
1. ProductDescription(discussthekindofproducttobeproducedbytheprojectincludingquantitytobe
sold,qualitystandards/specifications)
2. Discussthetargetmarket/buyer,thevolumerequirement,marketingarrangements
3. SupplyandDemandSituation(ifdataisavailable)
- discusstheavailabilityofsupply,majorproducingmunicipalities,volumeandhectarage
- discussthemarketdemand,majorbuyers,andvolumerequirements
4. MarketingStrategies(discusshowthePGintendtomarketitsproductincludingtheformofproductto
besold,thepackagingtobeused,brand(ifany),pricingstrategyfortheproduct,placeofdistribution
andhowwilltheproductarriveattheplaceofdistribution(modeoftransportationused),picked-upor
delivered, frequency of selling, and the promotional activities thatwill be undertaken tomake the
productknowntothetargetconsumers).
III.OPERATIONALPLAN
1. Ownership andManagement (discuss how the subproject will bemanaged including organizational
structure,projectmanagementanditsrolesandfunctions;capabilityofthePOtohandletheproject;
doesthestaffhavethenecessaryskills; trainingneeds;numberofpersonnelneededfortheproject
implementationandoperation;includewhentheorganizationwillberegisteredtoCDAorSEC,ifnot
yetregistered)
2. Production andOperationProcess (discusshow theprojectwill beoperationalized, provideprocess
flow,resourcesneeded)
3. Facilities and equipment (discuss the facilities and equipment required including specifications and
capacity; for civilworks or infrastructure describewhere itwill be located, access to roadnetwork,
technicaldesignorspecifications;includewheretosourcethefacilitiesandequipmentandestimated
costsbyfundsource)
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
205
IV. SOCIALANDENVIRONMENTALSAFEGUARDS
1.SocialSafeguardAspect
A.SubprojectBeneficiaries
Whoarethebeneficiariesofthesubproject?Whatistheirsocioeconomicstatus?Havetheybeenconsulted?
Describetheconsultationprocess(indicatedate,locationandattendeesofmeetings).Havetheyaccepted
theproposedproject?Whataretheirconcernsandinputs?Describetheminutesofthemeetingsifany?Are
the women represented in these consultations (describe attendance of women)? What are their
concerns/inputs (describeanyparticular inputs fromwomen, if any)? (Attachminutesof themeeting/s,
attendance,photosduringconsultation/s).
B.IndigenousCultural
Community/IndigenousPeoples(ICC/IP)–Istheprojectlocatedinsideanancestraldomain?Iftheprojectis
not situated insideanyancestral domain, is it going toaffect anyextant IP/ICC communityor are there
beneficiarieswhoaremembersoftheIP/ICCcommunity?WhatparticularIP/ICCcommunityis involved?
Whatistheirsocioeconomicstatusascomparedtothemainstreamgroup?DidtheIP/ICCcommunitysolicit
thesubprojectthemselves?Iftheydidnotsolicittheproject,havetheybeenconsultedandhavetheygiven
their endorsement of the project? Describe the consultation process thus far conducted. Indicate date,
locationandattendeesofmeetings.Describetheminutesofthemeetingsifany.Whataretheirconcerns
andinputs?
Notethat: IftheProject is insideanyancestraldomain,or ifthereareanyintactICC/IPcommunitytobe
affectedbytheproject,eitherofthefollowingshouldbesecured:
Certificatefromthelocaltribalchieftain,orfromthelocaltribalcouncilorfromNCIPthattheprojectispart
of the ICC-IP’s development plan or is part of their Ancestral Domain Sustainable Development and
ProtectionPlan(ADSDPP);
Certificate from the local tribal chieftain that the project is solicited by the ICC-IP themselves; or, An
endorsement(e.g.inaformofaResolution)fromICC/IPcommunitytogetherwithevidenceofconsultations
conducted(e.g.minutesofmeetingsandlistofattendees,issuesandconcernsraisedandhowtheywere
addressed).
C.StatusofLandOwnership
What istheownershipstatusoftheproposedsiteorproductionarea? Describethesiterequirement in
termsofarea(sq.m),landtenure,andexistinglanduse.
IfdocumentsorproofsoflandownershipwerelostintheYolandadisasterandsecuringnewdocumentswill
takealongtime,thensecureacertificatefromtheMunicipalAssessorsortheMayorcertifyingtheidentities
ofthePGmembersandstatusofownershipofthelottheywilluseforthesubproject.
IfthesubprojectisinsideAncestralDomainorifnotinside,itadverselyaffectsanextantIP/ICCcommunity
who are not themselves beneficiaries of the subprojects, then an FPIC/CP should be secured under the
auspicesoftheNCIP.
PhilippineRuralDevelopmentProjectI-REAPOperationsManualAnnexes
206
2.EnvironmentalSafeguardAspect
A.Naturalhabitat
Describetheprojectsite(i.e.,thelandstobetraversedbytheproposedroad,theactualsiteofthePWSor
structure,etc.) intermsof landuse,vegetation,wildlife,presenceofwaterecosystems,endangeredand
other importantspecies.Howaretheygoingtobeimpactedbytheproject?Istheprojectsitewithinan
officiallydeclaredorproposedprotectedareaofnaturalhabitat?
B.Hazards/RiskAssessment(DrainageSituations,ErosionandFloodingPotential)–describethedrainage
situations, erosion and flooding potential of the project site. How does it going to be impacted on the
proposedsubproject?
Note that: PRDP loan should not be used to fund subprojects involving civil works that encroach into
ProtectedAreasofnaturalhabitatsuchasareasdeclaredasNaturalParksunderNIPAS,exceptforNRM
subprojectsthatareallowedasperprovisionsoftheNIPASlawofBufferZone,orMultipleUseZone,andthe
lawcreatingtheNaturalPark.
C.SocialandEnvironmentalImpact(-attachtheESMP)
(Template forsubproject typewillbeprovidedtothePG.Wastemanagementanduseofpesticidesand
agrochemicalsorevenIPMwillbediscussedinthissection.Pleaseberemindedthatusageofanypesticide
willbechargedagainstthePGequity,andredlabeledpesticidearenotallowed)
V. FINANCIALASPECT
1.Indicatefinancialassumptionsusedincomputingtheinvestment/projectcost,salesandexpenses
2.Investment/ProjectCost(indetailsincludingfixedcapital,workingcapitalandpreoperatingexpenses)
3.ProductionSchedule(one-yearperiod)
4.ProductionCostsandReturns(one-cycle)
5.ProjectedSales(one-yearperiod)
6.ProjectedIncomeStatement(oneyearperiod)
7. FinancialAnalysis(returnoninvestment)