Calumet County Courthouse Emergency
Generator andElectrical Equipment
Replacement
Electric service = 600 kilowatts
Facility demand = 560 kilowatts
Generator capacity = 180 kilowatts
Emergency generator is only capable of powering emergency lights and selected loads, not including air conditioning and critical jail loads
Existing Capacities
Location of Existing Equipment
Existing Generator Room
Existing Electric Service Room
Add capacity to enable operation of the entire facility in the event of power outage or other emergency
Add redundancy to ensure that critical systems and processes remain operational in the event of power outage or other emergency
Replacement of existing service panel boards and generator due to age, condition, and capacity
Replacement of existing overhead electric service due to condition
Project Goals
Electric service = 600 kilowatts◦ Expandable to 2000 kilowatts to accommodate future
growth
Facility demand = 560 kilowatts
Generator capacity
◦ Base Bid generator capacity = 350 kilowatts This generator can power all systems except air conditioning
◦ Alternate Bid No. 1 generator capacity = 350 kilowatts Additional generator can power air conditioning and provides
redundancy for the first generator
◦ Provisions for future generator = 350 kilowatts To accommodate future growth
Proposed Capacities
Location of Proposed Equipment
Initial Budgeting: 2010
Design Phase: November 2012-February 2013
Bidding Phase: March 2013
Construction Milestones:◦ May 31, 2013: Underground work complete to
accommodate parking and road repaving.◦ September 12, 2013: Construction complete.
Project Schedule
Original and Revised Budgetary Estimates
Alternate Bid No. 1: add a second 350 kilowatt generator and associated wiring
Alternate Bid No. 2: replace the existing service entrance service panel board labeled ‘MDP’ with new panel board labeled ‘MDB’
2010 Budgetary Estimate 90% Design Budgetary Estimate Lowest Bid Totals
Construction: $450,000 Base Bid: $458,000 Base Bid: $598,980
Engineering: $25,000 Alt #1 Bid: $105,000 Alt #1 Bid: $126,699
Utility Fees: $10,000 Alt #2 Bid: $41,750 Alt #2 Bid: $32,020
Contingency: $65,000 Engineering: $25,000 Engineering: $25,000
Utility Fees: $25,000 Utility Fees: $25,000
Contingency: $50,000 Contingency: $50,000
Total: $550,000 Total: $704,750 Total: $857,699
7 out of 12 contractors did not submit a bid due to being too busy to do the work
Remaining 5 contractors bid in line with existing 2013 competitive pricing
Economy and associated workload has improved for contractors since 2010
Factors Contributing to Difference Between 2010 and 2013 Estimates
Evaluation of bids identified the lowest responsible bidder to be Altmeyer Electric.
On March 25th, Engineer recommended award of the Base Bid and Alternate Bid No. 2 to the committee. Additional funds should be budgeted for future years for the work under Alternate Bid No. 1.
The committee decided to pursue additional funding at this time to include Alternate Bid No. 1 in the project.
Recommendations