List of Priority External Loans and Grants (DRPPHLN) 2009 Ministry of National Development Planning/ National Development Planning Agency
Transcript

LLiisstt ooff PPrriioorriittyy

EExxtteerrnnaall LLooaannss aanndd GGrraannttss

((DDRRPPPPHHLLNN)) 22000099

MMiinniissttrryy ooff NNaattiioonnaall DDeevveellooppmmeenntt PPllaannnniinngg//

NNaattiioonnaall DDeevveellooppmmeenntt PPllaannnniinngg AAggeennccyy

‐  i  ‐ 

Foreword  

 

    The Government of Indonesia has compiled the annual List of Planned Priority 

External Loans and Grants for 2009 known as DRPPHLN, also known as the Green Book. 

The Green Book is one of the planning documents in the process of planning projects that 

are funded by external loans/grants. 

    The Green Book contains the list of proposed projects that are eligible for being 

funded by external  loans and/or grants. Thereby,  the projects  in  the Green Book are  the 

projects  that  are  contained  in  the  DRPHLN‐JM,  that  have  already  met  most  of  the 

readiness  criteria  and  that  have  already  obtained  the  indicated  commitment  from  the 

prospective development partners.  

    The  2009 Green Book  contains  127 proposed projects  in  the  total  amount of 

USD 6.7 billion, consisting of 56 projects assistance in the total amount of USD 6.39 billion 

and 71  technical assistance  in  the amount of USD 0.31 billion. These proposals originate 

from ministries/government  agencies  (106  projects),  regional  governments  (2  projects), 

and state‐owned enterprises (19 projects).  

    With the publication of the 2009 Green Book,  it  is expected that the planning 

and management  of  projects  that  are  funded  by  external  loans  and/or  grants,  become 

more effective and efficient, to optimally benefit national development and to increase the 

welfare of the people. 

 

State Minister for National Development Planning/ 

Chairman of the National Development Planning Agency, 

 

 

Paskah Suzetta 

 

   

- iii -

LIST OF PROJECT ASSISTANCE

Indonesian Maritime Safety and Security Agency

1. The Development of Command Center Base on Global Maritime Distress

Safety System (GMDSS) ..................................................................................................................3

2. The Establishment and Operation of the Indonesia Maritime

Surveillance Satellite System ........................................................................................................5

National Disaster Management Agency (NDMA)

3. Procurement of Equipment for Emergency and Post Disaster Phase .......................................9

Statistics Indonesia Agency (BPS)

4. Statistical Capacity Building Program (STATCAP) for Indonesia...........................................13

National Search and Rescue (SAR) Agency (BASARNAS)

5. Procurement of Search and Rescue Aircraft Project ..................................................................17

Ministry of Home Affairs

6. Development and Implementation of Population Administration

Information System (SIAK)...........................................................................................................21

7. PNPM Mandiri Rural.....................................................................................................................23

Ministry of Justice and Human Rights

8. Development of Automation System (Information Technology of

Intellectual Property Rights).........................................................................................................27

Ministry of Marine Affairs and Fisheries

9. Development of the Inspection Boat System for Indonesian Fisheries

(Phase I) ...........................................................................................................................................31

Ministry of Health

10. Strengthening of Teaching Hospitals in Indonesia....................................................................35

List of Project Assistance

- iv -

Ministry of Public Works

Directorate General of Highways

11. Bridge Construction Project for Regional Development in West Nusa

Tenggara (Phase II)........................................................................................................................ 39

12. Padang By Pass Capacity Expansion .......................................................................................... 41

Directorate General of Human Settlements

13. Climate Friendly and Sustainable City Development (Eco City), Phase:

Solid Waste Improvement Management .................................................................................... 43

14. Metropolitan Sanitation Management and Health Project....................................................... 45

15. National Program for Community Empowerment in Urban Area (PNPM

Mandiri - Perkotaan) ..................................................................................................................... 47

16. Regional Solid Waste Development for Maminasata, South Sulawesi................................... 49

17. Rural Infrastructure Support (RIS) PNPM Phase 2 ................................................................... 51

Directorate General of Water of Water Resources

18. The Construction of Transfer Water Inter Basin of Cibutarua – Cilaki –

Cisangkuy....................................................................................................................................... 53

Ministry of National Education

19. Development of Medical Research Center and Teaching Hospital ........................................ 57

20. Human Resources for Health Education Quality Improvement............................................. 59

21. Life Skills Education for Employment and Entrepreneurship (LSE3) .................................... 61

22. Sustainable Economic Supported by Improving Technical and Vocational

Education........................................................................................................................................ 63

23. The Quality Improvement of Padjadjaran University .............................................................. 65

Ministry of Transportation

Directorate General of Sea Transportation

24. Indonesia Ship Reporting System................................................................................................ 71

25. Vessel Traffic Services (VTS) System .......................................................................................... 73

Directorate General of Civil Aviation

26. Procurement of Airport Rescue and Fire Fighting Equipment................................................ 75

List of Project Assistance

- v -

Directorate General of Railway

27. Procurement of Railway Track Construction and Maintenance Machinery ..........................77

28. Procurement of 1000 km Track Material and 200 Units Turn Out...........................................78

29. Procurement of Locomotives Diesel Electric ..............................................................................80

Ministry of Industry

30. Development of Leather Industries .............................................................................................85

Ministry of Agricultural

31. Prevention and Control of Avian Influenza in the Veterinary Sector .....................................89

Ministry of Manpower and Transmigration

32. Revitalization of Vocational Training Center .............................................................................93

Indonesian National Police

33. Integrated Trunking Radio Communication for Indonesian National Police........................99

34. National Criminal Information Center for Indonesian National Police

Phase II ..........................................................................................................................................101

Indonesian Institute of Science

35. Animal Husbandry Technology and Practice Improvement to Accelerate

Meat and Milk Production (Meat-Milk Pro).............................................................................105

National Resilience Institute

36. Strengthening the Capacity Building Program of National Resilience

Institute..........................................................................................................................................111

Local Government of Nanggroe Aceh Darussalam Province

37. Seulawah Geothermal Working Area Infrastructure ..............................................................115

Local Government of Riau Province

38. Southern Pekanbaru Water Supply Project ..............................................................................119

List of Project Assistance

- vi -

PT. PERTAMINA

39. Ulubelu Unit 3 & 4 (2x55 MW)................................................................................................... 123

State Electricity Company (PT. PLN)

40. Bakaru II Hydro-Electric Power Plant (HEPP) [2 x 63 mW] .................................................. 127

41. Construction for Java - Sumatera Interconnection 500 kV Line (HVDC) -

Phase I ........................................................................................................................................... 129

42. Engineering Services and Construction of the Kamojang - 6 Geothermal

Plant (60 MW) .............................................................................................................................. 131

43. Engineering Services and Construction of the Lumut Balai Geothermal

Plant (2 x 55 MW) ........................................................................................................................ 132

44. Enterprise Resource Planning (ERP) Outside Java Bali.......................................................... 133

45. Java-Bali Electricity Distribution Performance Improvement ............................................... 135

46. Java-Bali Submarine Cable 150 kV Circuit 3 & 4 ..................................................................... 136

47. Kusan Hydro Electric Power Plant 63 MW.............................................................................. 138

48. Lahendong IV GEOPP (1 x 20 mW) .......................................................................................... 140

49. Lombok Steam Coal Power Plant (2x25 MW).......................................................................... 142

50. Muara Tawar Add on Block 2, 3, 4 CCPP (825 - 1200 MW) ................................................... 143

51. Parit Baru Coal Fueled Steam Power Plant (2x50 MW).......................................................... 145

52. Rehabilitation and Modernization of Paiton Small Power Producer (SPP)

1&2 (2x400 MW)........................................................................................................................... 147

53. Rehabilitation and Modernization of Saguling Hydro Electric Power Plan

(HEPP 4 x 178 MW) ..................................................................................................................... 148

54. Scattered Transmission and Sub-Station in Indonesia............................................................ 149

55. Sembalun GEOPP, Lombok (2 x 10 MW) ................................................................................. 152

56. Upper Cisokan Pumped Storage HEPP (1000 MW)................................................................ 154

- vii -

LIST OF TECHNICAL ASSISTANCE

Investment Coordinating Board

1. Investment Promotion Policy Advisor ......................................................................................159

2. Strengthening Institution Capacity for Sustainable and Competitive Investment

Climate...........................................................................................................................................160

National Disaster Management Agency (BNPB)

3. Disaster Information Sharing System for Emergency Response............................................163

4. Disaster Risk Reduction Based Rehabilitation – Reconstruction (DRR-RR).........................164

Statistics Indonesia Agency (BPS)

5. Capacity Building on Dissemination and Use of Small Area Statistics for 2010

Population Census in Indonesia.................................................................................................169

Ministry of Religious Affair

6. Supporting Islamic Leadership through Islamic Institutions of Higher Education

(SILE) .............................................................................................................................................173

Ministry of Home Affairs

7. Aceh Government Transition Programme (AGTP) .................................................................177

8. Disaster Risk Reduction in Development (DRR – A) ..............................................................179

9. PNPM Green Kecamatan Development Program ...................................................................182

10. Nias Island Transition Programme (NITP)...............................................................................184

Ministry of Forestry

11. Forestry Sector Climate Change Related Program (Reducing Emission from

Deforestation and Degradation (REDD))..................................................................................189

Ministry of Marine Affairs and Fisheries

12. Arafuru and Timor Seas Ecosystem Action Programme (ATSEA) .......................................193

13. Assistance for SMEs in Fish and Shrimp Industry ..................................................................195

14. Capacity Building in Fisheries and Aquaculture .....................................................................197

15. Sustainable Indonesia Fisheries Product Competitiveness ....................................................200

16. Value Capture Fisheries ..............................................................................................................202

Ministry of Finance

17. Capacity Building of Regulatory Compliance and Human Resources for the

Capital Market..............................................................................................................................207

18. Fostering Knowledge Partnership to Strengthen Indonesia's Financial Early

Warning System ...........................................................................................................................209

19. Support for Local Government Finance and Governance Reform (LGFGR) II....................211

List of Technical Assistance

- viii -

Ministry of Communication and Information Technology

20. Extending Telecommunications in Rural Indonesia............................................................... 215

Ministry of Public Works

Agency for Research and Development

21. Identification of Ecopolis Component in Term of Rethinking Principles of Urban

Development in Indonesia ......................................................................................................... 219

22. Development of Green Housing Model with Minimizing CO2 Emission as a

Control Micro Climate Change.................................................................................................. 221

Directorate General for Highways

23. Capacity Building for Public-Private Partnership (PPP) Operation ..................................... 223

24. Road Policy Advisor ................................................................................................................... 224

Directorate General of Human Settlement

25. Capacity Development of 3R and Domestic Solid Waste Management System................. 225

26. Flood Management in Selected River Basins, PFR1................................................................ 227

27. Policy Advisor for Irrigation Management.............................................................................. 229

Directorate General for Water Resources

28. Technical Assistance for Capacity Building in Water Sector ................................................. 230

Ministry of National Education

29. Basic Education Sector Programme .......................................................................................... 233

30. Enhancement of Global Carbon Sequestration Potential from Indonesian Tropical

Forest (Phase II) ........................................................................................................................... 235

31. Higher Education Policy Advisor ............................................................................................. 237

32. Higher Education Training on Developing Education Content for Mobile Learning........ 238

33. Long-term Training (C/P of PREDICT) .................................................................................... 239

34. Polytechnics Education Development Sector Project ............................................................. 240

Ministry of Trade

35. The Project on Service Improvement of NAFED as a Major Trade Promotion

Organization in Indonesia.......................................................................................................... 245

36. Trade and Support Programme II ............................................................................................. 246

List of Technical Assistance

- ix -

Ministry of Transportation

Directorate General of Land Transportation

37. Integrated Public Transportation Master Plan for the Bandung Metropolitan Area ..........251

38. Program for Improvement of Transport System in Medium-Sized Cities ...........................253

39. Port Security Management Project (Phase II) ...........................................................................254

40. Strengthening Maritime Safety and Security Especially for Anti Piracy and Anti

Maritime Terrorism......................................................................................................................256

Directorate General of Civil Aviation

41. Introduction of New CNS/ATM System ...................................................................................257

42. Project for Improvement on Aviation Safety Policy ................................................................258

43. Project for Strengthening Capacity on Ensuring Safe and Efficient Aircraft

Operations.....................................................................................................................................260

Directorate General of Railways

44. Bandung Urban Railway Transport Development, Electrification Padalarang -

Cicalengka Line (Phase I: Engineering Services) .....................................................................261

Ministry of Industry

45. SME Human Resources Development under Economic Crisis..............................................265

Ministry of Agriculture

46. Immediate Support for Improving Resilience of Agriculture Based Livelihood and

Enhanced Food Security Response in East Nusa Tenggara (NTT) Province .......................269

47. Improvement of Countermeasure on the Productive Diseases of Dairy Cattle...................272

48. Livestock Development Policy Advisor....................................................................................274

49. Standardization and Quality Control for Horticulture Production of Indonesia ................275

50. Strategy for Improving the Rice Post Harvest System in Indonesia......................................277

Commission for Supervision of Business Competition

51. Competition for Competition Policy (Phase II) ........................................................................281

Indonesian Institute of Sciences

52. Establishing Research Laboratory for Energy, Environment, and Natural

Substances .....................................................................................................................................285

Ministry of Cooperatives and Small and Medium Enterprises

53. Sustainable SMEs Growth through Improved Services and Competitiveness ....................289

List of Technical Assistance

- x -

Ministry of Environment

54. Indonesian Training Course for Co-Benefits Approach in Japan ......................................... 293

Ministry of Women Empowerment

55. Strengthening Indonesia’s National Mechanism to Enhance State Effectiveness in

Promoting Women’s Right and Gender Equality ................................................................... 297

Ministry of Administrative Reform

56. Capacity Building for Public Officials for Government Innovation in Indonesia

Stage II .......................................................................................................................................... 301

Ministry of National Development Planning/ National Development Planning

Agency (BAPPENAS)

57. Support to Aid for Development Effectiveness Secretariat (A4DES) ................................... 305

58. Aid Information Management System (AIMS) ....................................................................... 307

59. Articulate Governance and Local Development (AGI) .......................................................... 309

60. Decentralization Support Facility (DSF)................................................................................... 312

61. Delivery Improvement and Local Governance (DIALOG).................................................... 314

62. Formulation of the National Medium Term Development Plan on Decentralization

and Functional Assignment Reform ......................................................................................... 316

63. Monitoring and Evaluation System .......................................................................................... 318

64. Planning and Budgeting Reform............................................................................................... 320

65. Long-term Finance Security for National Backbone Infrastructure Development ............. 322

66. Provincial Governance Support Programme (PGSP) ............................................................. 324

67. Strengthening Knowledge Management for Effective Project Planning and

Implementation. .......................................................................................................................... 327

68. Support to Bappenas in Mainstreaming Climate Change Issue into Development

Plan................................................................................................................................................ 329

69. Support to PNPM Mandiri......................................................................................................... 331

70. Supporting Medium Term Geothermal Development Plan and Accelerated

Investment in Geothermal Sector .............................................................................................. 333

State Electricity Company (PT. PLN)

71. Java-Bali Crossing Interconnecting 500kv................................................................................ 337

PROJECT ASSISTANCE

P-1

Indonesian Maritime Safety and

Security Agency

P-3

GB ID : GBP1-07-10601-0800-09-072001

1. Project Title : The Development of Command Center Base on Global Maritime

Distress Safety System (GMDSS)

2. Project Type : Project Assistance

3. Executing Agency : Indonesian Maritime Safety and Security (BAKORKAMLA)

4. Implementing Agency : Indonesian Maritime Safety and Security

5. Duration : 24 months

6. Location : DKI Jakarta

7. Objectives

The development of maritime surveillance integration is aimed for enhancing capability of

maritime surveillance, safety and control system in Indonesia throughout:

a. Upgrading National Picture Compilation (NPC) command center of Bakorkamla;

b. Collecting rescue signal from shipwreck via regional coast station at Bakorkamla’s NPC

Command Center in Jakarta;

c. Commanding the strategic operation for immediate rescue action;

d. More effective utilization of national facilities/property (communication system etc);

e. Formulating regulation on more effective and efficient rescue operations;

f. Development of human resources capability on handling the integrated maritime safety

handling in Indonesia

8. Scope of Projects

The development of the integrated maritime surveillance system consist of maritime intelligence

such as detecting and monitoring of all vessels in certain area, protecting marine resources,

detecting of piracy, and take an action against piracy, detect and monitoring illegal fishing,

illegal immigration, monitoring activity of foreign state port and execute certain action , detect

and monitor oil spill and ships discharge, also take on action against marine distress or ships

wreck situation.

9. Activities

Activities Implementation

Locations

Project

Implementation Units

a. Study (for regulation and technology

assessment)

b. Coordination with other related agencies

c. Training

d. Procurement

e. Operation and maintenance

Indonesia and

Overseas

Secretariat of

Indonesian Maritime

Security Coordinating

Board

P-4

GB ID : GBP1-07-10601-0800-09-072001

10. Funding Source

Implementing Agency Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Secretariat of Indonesian

Maritime Security

Coordinating Board

18,000 - 18,000 Japan

(JICA)

Total 18,000 - 18,000

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

10,000 8,000 18,000

12. Funding Allocations

Categories (US $ 000)

Detail of Activities Services

Construct-

ions Goods Trainings Others

a. Study 3,000

b. Coordination with other

agencies

3,000

c. Training 2,000

d. Procurement 7,000

e. Operation and maintenance 3,000

Total 6,000 7,000 2,000 3,000

13. Project References :

BB 2006 - 2009 ID: P1-07-10601-0202-072001

P-5

GB ID : GBP1-07-10601-0900-072003

1. Project Title : The Establishment and Operation of the Indonesia Maritime

Surveillance Satellite System

2. Project Type : Project Assistance

3. Executing Agency : Indonesian Maritime Safety and Security (BAKORKAMLA)

4. Implementing Agency : Indonesian Maritime Safety and Security

5. Duration : 36 months

6. Location : Nation Wide

7. Objectives

The establishment of Indonesia Maritime surveillance satellite system are purpose of:

a. to improve security in Indonesian waters so as to prevent and handle smuggling, drug-

trafficking, illegal immigration, ship crimes and illegal fishing.

b. to acquire data/information about possible natural distress that would seriously disturb

security and safety of various activities on Indonesian waters.

c. to enhance the individual capabilities of Indonesian fishermen, by providing access to

data/information on potential locations of fishes in the sea.

8. Scope of Projects

a. Increasing the Indonesian capabilities particularly in satellite technology and related

technologies.

b. growing faster satellite industry and related industries in Indonesia.

c. helping Indonesian fishermen in funding fishes to harvest in the Indonesian waters.

9. Activities

Activities Implementation

Locations

Project

Implementation

Units

The first stage (The first year)

a. Project preparation

The second stage (The second and third years)

a. Procurement of and manufacturing

subsystems/component of the Surveillance Satellite

system

b. Assembly, integration and test of the Surveillance

Satellite system

c. Launch of the Surveillance Satellite system.

Indonesia Indonesian

Maritime

Security

Coordinating

Board

P-6

GB ID : GBP1-07-10601-0900-072003

10. Funding Source

Implementing Agency Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Secretariat of Indonesian

Maritime Security

Coordinating Board

5,300 407 5,707 China/Korea

Total 5,300 407 5,707

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

707 3,000 2,000 5,707

12. Funding Allocations

Categories (US $ 000)

Detail of Activities Services

Construct-

ions Goods Trainings Others

a. Organizing education and

training of Indonesian

scientist and engineers

1,000

b. Strengthening institutional

capability of Bakorkamla

1,000

c. Empowerment of life

quality of coastal people

400

d. Provision of support for

Universities and research

and technologies institution

of Indonesia in Mastering

satellite technology

300

e. Consultant services 2,600

f. Others 407

Total 2,600 1,000 1,300 807

13. Project References :

BB 2006 - 2009 ID: P1-07-10601-0202-072003

P-7

National Disaster Management Agency

(NDMA)

P-9

GB ID : GBP1-03-10301-0800-09-077004

1. Project Title : Procurement of Equipment for Emergency and Post Disaster Phase

2. Project Type : Project Assistance

3. Executing Agency : National Disaster Management Agency (NDMA)

4. Implementing Agency : National Disaster Management Agency

5. Duration : 48 months

6. Location : Nation Wide

7. Objectives

a. To improve the NDMA staff capabilities in handling the emergency and post disaster phase

b. To improve clean water supplies for the communities in the region that affected by

disasters.

8. Scope of Projects

Procurement of equipment for emergency and post disaster phase in form the mobile water

purification unit, car handling, mobile command center.

9. Activities

Activities Implementation Locations Project Implementation Units

a. Need Assessment

b. Procurement of equipment

c. Training

d. Monitoring and evaluation

Central and Province NDMA

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

NDMA 10,000 - 10,000 Hungary

Total 10,000 - 10,000

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

1,500 3,500 3,500 1,500 10,000

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Need Assessment 780

b. Procurement of equipment 400 1,400 7,280

c. Training

d. Monitoring and evaluation 140

Total 1,180 1,400 7,280 140

13. Project References :

BB 2006 - 2009 ID: P1-03-10301-0302-077004

P-11

Statistics Indonesia Agency (BPS)

P-13

GB ID : GBP1-03-05401-0800-09-074009

1. Project Title : Statistical Capacity Building Program (STATCAP) for Indonesia

2. Project Type : Project Assistance

3. Executing Agency : Statistics Indonesia Agency (BPS)

4. Implementing Agency : Statistics Indonesia Agency

5. Duration : 60 months

6. Location : Nation Wide

7. Objectives

a. To improve the accuracy of statistics produced by BPS;

b. To improve data consistency between collections;

c. To improve the confidence of users in the statistics produced by BPS;

d. To improve the productivity of BPS staff through better information and communication

technology;

e. To improve the skills and professionals of BPS staff.

8. Scope of Projects

a. Improvement of data collection, compilation and dissemination.

b. Investment in ICT infrastructure and information management.

c. Human resource capacity development.

d. Project management and administration support.

9. Activities

Activities Implementation

Locations

Project

Implementation Units

a. Improving Statistical Quality

b. Analysis, Quality Assurance and

Methodological Innovations

c. Dissemination, User Engagement and

Communication Strategy

d. Data Warehouse Development and Network

Improvement

e. Application of Geospatial Technology

f. Corporate Information Systems Management

g. Upgrading of ICT Capabilities in Selected

Model BPS Field Offices

h. Technical Training on Human Resource

Capacity Development

i. Building Professional Excellence

j. Project Management and Administration

Support

Nation Wide Statistical Indonesia

Agency (BPS)

P-14

GB ID : GBP1-03-05401-0800-09-074009

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

BPS 45,000 8,635 53,635 World Bank

Total 45,000 8,635 53,635

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

9,409.5 9,663.0 11,028.8 13,147.2 10,386.5 53,635

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Improving Statistical Quality 6,824.2 - 630.5 746.0 1,160.4

b. Analysis, Quality Assurance

and Methodological

Innovations

1,624.5 - - - 927.5

c. Data warehouse

development and network

improvement

85.0 - - 38.7 21-

d. Data Warehouse

Development and Network

Improvement

2,762.8 - 18,057.0 267.9 -

e. Application of Geospatial

Technology

463.4 - 4,030 328.9 -

f. Corporate Information

Systems Management

735.0 - - - -

g. Upgrading of ICT

Capabilities in Selected

Model BPS Field Offices

1,865.7 - 1,000 - -

h. Technical Training on

Human Resource Capacity

Development

1,024.4 - - 4,375.0 -

i. Building Professional

Excellence

832.0 - 466.7 - 663.5

j. Project Management and

Administration Support

- - - - 3,376.0

Total 16,217.0 - 24,184.2 5,756.4 6,337.4

13. Project References :

BB 2006 - 2009 ID: P1-03-05401-1104-074009

P-15

National Search and Rescue (SAR) Agency

(BASARNAS)

P-17

GB ID : GBP1-03-02200-0800-09-066331-07

1. Project Title : Procurement of Search and Rescue Aircraft Project

2. Project Type : Project Assistance

3. Executing Agency : National Search and Rescue Agency (BASARNAS)

4. Implementing Agency : National Search and Rescue Agency

5. Duration : 24 months

6. Location : DKI Jakarta

7. Objectives

a. To improve BASARNAS capability to response and carry out the save and rescue operations

for flight and shipping accidents with a sufficient equipments.

b. To strengthen the skill and capability of the rescue team in operating the helicopter for the

rescue operation.

8. Scope of Projects

a. Procurement 4 (four) units helicopter medium range

b. Procurement spare part of the helicopters

c. Development and training for technicians and crew;

9. Activities

Activities Implementation Locations Project Implementation Units

a. Procurement of helicopter

b. Procurement spare part of

the helicopters

c. Development and training

for technician and crew

DKI Jakarta BASARNAS

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

BASARNAS 42,500 7,500 50,000 Commercial Loan

Total 42,500 7,500 50,000

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

20,000 30,000 50,000

P-18

GB ID : GBP1-03-02200-0800-09-066331-07

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Procurement of helicopter 48,000

b. Procurement spare part of

the helicopters

440 1,100

c. Development and training

for technician and crew

460

Total 440 49,100 460

13. Project References :

BB 2006 - 2009 ID: P1-03-02200-0302-066331-07

P-19

Ministry of Home Affairs

P-21

GB ID : GBP1-06-01000-0900-067060-07-09

1. Project Title : Development and Implementation of Population Administration

Information System (SIAK)

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Home Affair

4. Implementing Agency : Ministry of Home Affair

5. Duration : 60 months

6. Location : DKI Jakarta

7. Objectives

a. To develop a comprehensive, accurate, updated and secure national population database (at

districts/cities, provinces and national level).

b. Availability of the software and hardware as well as the infrastructures and facilities

supporting the SIAK operations;

c. To build a network system to facilitate population administration information management

and integrate every working unit.

d. To develop a customized software application to provide a complete and accurate platform

for population information management.

e. To distribute accurately and quickly citizens’ data and information to related Central and

Local Government Institutions as well as the related stakeholders linked to the MoHA

network.

f. To design and implement a flexible and expandable system to foresee the increasing

workload and be able to keep up to the technology development.

g. To provide a true technology transfer towards MoHA officials in order to guarantee the

project sustainability.

h. Increased technical knowledge and skills of the staff in charge of operating the population

administration services at the national, provincial and district/city levels;

i. Completion of the process of socialization as well as operation of the SIAK in population

registration, civil registry and population administration information management in all

regions in Indonesia.

8. Scope of Projects

a. Detailed project planning

b. User requirement analysis

c. Design and implementation of network infrastructure (WAN & LAN)

d. Supply, installation and configuration of all hardware equipment, system software and

peripherals

e. Analysis, design, development, testing and installation of the required software application

programs

f. System initialization

g. Training program

h. Project management

i. Technical support, maintenance and warranty program

P-22

GB ID : GBP1-06-01000-0900-067060-07

9. Activities

Activities Implementati

on Locations

Project

Implementation Units

a. Detailed project planning

b. User requirement analysis

c. Design and implementation of network

infrastructure (WAN & LAN)

d. Supply, installation and configuration

e. Analysis, design, development, testing and

installation

f. System initialization

g. Training program

h. Project management

i. Technical support, maintenance and warranty

program

Nation Wide Ministry of Home

Affairs

10. Funding Source

Implementing Agency Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Ministry of Home Affair 250,000 25,000 275,000 China

Total 250,000 25,000 275,000

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

35,000 65,000 75,000 65,000 35,000 275,000

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

SIAK system application 4,300

Population database 51,820

System back-up 11,000

Data services 14,730

Input data 200

Data recording & document

services

180,845

Training 7,215

Miscellaneous 4,890

Total 206,575 56,120 7,215 5,090

13. Project References :

BB 2006-2009 ID No: P1-06-01000-0103-067060-07

P-23

GB ID : GBP1-01-01005- 0901-073011-09

1. Project Title : PNPM Mandiri Rural

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Home Affair

4. Implementing Agency : Directorate General of Community Empowerment – Ministry of

Home Affair

5. Duration : 60 months

6. Location : All Provinces in Indonesia

7. Objectives

To empower Indonesia’s diverse rural communities to be actively participated in development

through identifying their own needs and how to fulfill them with the resources they have in

order to improve their welfare.

8. Scope of Projects

a. To promote community participation in development planning and management.

b. To fill infrastructure gap as well as to promote more efficient delivery of services to the rural

communities

c. To develop local government capacities in the formulation and implementation of pro-poor

policies and approaches.

9. Activities

Activities Implementation Locations Project Implementation Units

a. Provision of block grant to

the community

Local governments at Central

and districts level

b. Community Empowerment

and provision of facilitators

All sub-district

Local governments at Central

and provincial level

c. Local government capacity

building

All level (central, province,

districts, sub districts)

Local governments at Central

level

10. Funding Source

Implementing Agency Foreign Funding

(US $ 000)

Local Funding

(,US $ 000)

Total of Funding

(US $ 000) Remarks

Directorate General of

Community

Empowerment, MoHA

168,300 168,300 World

Bank

Total 168,300 168,300

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

16,000 33,660 33,660 33,660 51,320 168,300

P-24

GB ID : GBP1-01-01005- 0901-073011-09

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Community Empowerment

and provision of facilitators

129,454

b. Local government capacity

building

38,846

Total 129,454 38,846

13. Project References :

BB 2006-2009 ID No: P1-01-01005-1190-073011-09

P-25

Ministry of Justice and Human Rights

P-27

GB ID : GBP1-06-01307-0900-072012

1. Project Title : Development of Automation System (Information Technology of

Intellectual Property Rights)

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Justice and Human Rights

4. Implementing Agency : Directorate General of Intellectual Property Rights (DGIPR), Ministry

of Justice and Human Rights (MOJH)

5. Duration : 36 months

6. Location : DKI Jakarta

7. Objectives

The project aims to enable Intellectual Property offices to replace paper-based processes with

highly efficient and convenient electronic transactions, and benefit more citizens as well as the

DGIPR. The Project will be expected to save applicants’ time, money and opportunity cost in a

large way. Especially, it will help applicant’s Intellectual Property Rights to be protected much

faster through shortening the register period.

8. Scope of Projects

a. Consulting Services

b. Preparation for Paperless

1) System Business Process Reengineering on DGIPR and main office of MOJH

2) System analysis and Development

3) Hardware installation for application system

4) Software installation for hardware and application system

5) Network construction

6) Establish IT equipment for training MOJH and DGIPR staff

7) Office automation equipment

c. Foundation for Online Services

1) Application System Development and Implementation

2) Software installation: preparation software

d. Paperless IP Administration

1) Application system development and implementation

2) Software installation: enhancement software

3) Training external user (applicant, attorney)

P-28

GB ID : GBP1-06-01307-0900-072012

9. Activities

Activities Implementation

Locations Project Implementation Units

a. Consulting Services

b. Preparation for Paperless

c. Foundation for Online Services

d. Paperless IP Administration

DKI Jakarta DGIPR, MOJH

10. Funding Source

Implementing Agency Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

DGIPR 33,000 6,088 39,088 Korea

(EDCF)

Total 33,045 3,225 36,270

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

11,270 15,000 10,000 36,270

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. System Construction 17,210 10,000 430

b. Digitalization of Legacy

Data

1,100

c. Training 900

d. Consulting Service 1,120

e. Operation &

Maintenance

510

f. Contingency 2,000

g. Tax 3,000

Total 19,940 10,000 900 5,430

13. Project References :

BB 2006-2009 ID No: T1-06-01307-0409-072012

P-29

Ministry of Marine Affairs and Fisheries

P-31

GB-ID : GBP1-04-03200-0800-09-065102-07

1. Project Title : Development of the Inspection Boat System for Indonesian

Fisheries (Phase I)

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Marine Affairs and Fisheries

4. Implementing Agency : Directorate General for Marine and Fisheries Resources

Surveillance and Controlling, Ministry of Marine Affairs and

Fisheries

5. Duration : 24 months

6. Location : Nation Wide

7. Objectives

a. To establish the facilities and infrastructures for surveillance and control of marine resources

and fisheries;

b. To optimize surveillance and control of marine resources and fisheries;

c. To improve endeavor of combating Illegal, Unreported, and Unregulated (IUU) fishing

effectively.

8. Scope of Projects

In order to achieve the above mentioned object, the activities of the project will be focused on the

following:

a. Survey, analysis data and information relating to the project;

b. Development of 4 (four) units Inspection Boat type A (size 57-60 meters);

c. Supervisor;

d. Training;

e. Technology transfer to local shipyard

f. Project administration

9. Activities

Activities Implementation

Locations

Project

Implementation

Units

a. Survey, analysis data and information

b. Development of 12 units inspection boats type A

c. Supervisor

d. Training

e. Technology transfer to local shipyard

f. Project administration

DKI Jakarta Directorate of

Surveillance Facility

and Infrastructure

P-32

GB-ID : GBP1-04-03200-0800-09-065102-07

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Directorate

General for Marine

and Fisheries

Resources

Surveillance and

Controlling

77,000 10,000 87,000 Commercial

Loan

Total 77,000 10,000 87,000

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

30,000 57,000 87,000

12. Funding Allocations

Categories (US $ 000)

Detail of Activities Services

Construct

-ions Goods Trainings Others

a. Survey, analysis data and information 700

b. Development of 12 units inspection

boats type A 500 72,400 500

c. Supervisor 200

d. Training 300

e. Technology transfer to local shipyard 200

f. Project administration 200 200 1,800

g. Miscellaneous 10,000

Total 1,600 72,400 700 500 11,800

13. Project References :

BB 2006 - 2009 ID: P1-04-03200-0504-065102-07

P-33

Ministry of Health

P-35

GB-ID : GBP1-05-02400-0700-08-09-061124

1. Project Title : Strengthening of Teaching Hospitals in Indonesia

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Health

4. Implementing Agency : Directorate General for Medical Care (DGMC), Ministry of

Health

5. Duration : 36 months

6. Locations :

a. Dr.Zainoel Abidin Hospital, Aceh,

b. H. Adam Malik Hospital, Medan,

c. Dr. Mohammad Hoesin Hospital,

Palembang,

d. RSAB Harapan Kita, Jakarta,

e. Jantung Harapan Kita Hospital, Jakarta,

f. Persahabatan Hospital, Jakarta,

g. Dr. Ciptomangunkusumo Hospital,

Jakarta,

h. Dr. Soeradji Tirtonegoro Hospital,

Klaten,

i. Sanglah Hospital, Denpasar,

j. Dr. Prof. R.D. Kandou Hospital,

Manado,

k. Andi Makkasau Hospital, Pare-Pare

7. Objectives

To strengthen the operating theaters and intensive care units in 11 teaching hospitals units that

provides quality care in the region.

8. Scope of Projects

The scope of the project is to provide adequate medical equipment and train doctors for

improving targeted hospitals in Indonesia. The scope consists of the following:

a. procurement of equipment and materials, installation of the equipment and materials,

testing and commissioning

b. trainings;

c. operations and maintenances;

9. Activities

Activities Implementation

Locations

Project

Implementation Units

a. Procurement of medical equipment,

installation, testing and commissioning

b. Training

c. Operation and maintenance;

11 teaching

hospitals

Ministry of Health

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

DGMC 14,000 3,500 17,500 Finland

Total 14,000 3,500 17,500

P-36

GB-ID : GBP1-05-02400-0700-08-09-061124

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

10,000 4,000 3,500 17,500

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Procurements of

Medical Equipment

12,600

b. Renovation of

Hospital Facilities

3,500

c. Trainings program 560

d. Maintenances 840

Total 840 3,500 12,600 560

13. Project References :

BB 2006 – 2009 ID No: P-05-02400-0703-061124

P-37

Ministry of Public Works

P-39

Directorate General of Highways

GB-ID : GBP1-03-03300-0700-09-066205

1. Project Title : Bridge Construction Project for Regional Development in West Nusa

Tenggara (Phase II)

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Public Works

4. Implementing Agency : Directorate General of Highways, Ministry of Public Works

5. Duration : 48 months

6. Location : West Nusa Tenggara Province

7. Objectives

The improvement of the Sejorong Lunyuk section is aimed to provide fundamental

transportation infrastructure, to ensure smooth and efficient road network, to relieve local

people from inconvenience and difficulty in daily life, and to enhance socio-economic activities

of the local communities.

The Sejorong-Lunyuk section plays an important role not only as a lifeline road for the

inhabitants including those migrating from Lombok and Bali islands in accordance with the

transmigration programs but also as a transport route of agriculture products in Sekongkang,

Jereweh and Lunyuk Sub districts to Benete Port which is a sea port to send agricultural

products directly to Bali and Jakarta.

8. Scope of Projects

The objective of this project is to facilitate the improvement of Sejorong-Lunyuk section of the

South Ring Road in Sumbawa Island by constructing 30 bridges located on the eastern side of

the section.

9. Activities

Activities Implementation Locations Project Implementation Units

a. Civil works

b. Consulting services

West Nusa Tenggara

Province

Directorate General of Highways

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Directorate General

of Highways 19,660 2,949 22,609 Japan (JICA)

Total 19,660 2,949 22,609

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

4,000 7,000 7,000 4,609 22,609

P-40

GB ID : GBP1-03-03300-0700-09-066205

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Civil works 20,349

b. Consulting services 2,260

Total 2,260 20,349

13. Project References :

BB 2006 - 2009 ID: P-03-03300-0408-066205

P-41

GB-ID : GBP1-03-03304-0800-09-076020-08

1. Project Title : Padang By Pass Capacity Expansion

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Public Works

4. Implementing Agency : Directorate General of Highways, Ministry of Public Works

5. Duration : 24 months

6. Location : Padang, West Sumatera Province

7. Objectives

a. To anticipate regional development along with operation of Minangkabau International

Airport and Bingkuang Regional Terminal and Teluk Bayur Port Development Plan.

b. To accommodate the traffic growth in Padang.

c. To accelerate social and economic activity

d. To provide evacuation line that is easy, safe, and fat in order to anticipate the emergency

condition due to natural disasters.

e. To provide a better accessibility for the road user to reach Padang City.

f. To provide additional 2 lanes of the existing 2 lanes two ways carriage

8. Scope of Projects

a. Improving roads capacity through road capacity improvement from two lanes two ways

road two lanes and for ways road;

b. Constructing the Duku Fly Over;

c. Road improvement of 27 km length.

9. Activities

Activities Implementation Locations Project Implementation Units

a. Civil works

b. Consulting services

Padang Directorate General of

Highways

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Directorate General

of Highways

58,000 6,800 64,800 Korea

(EDCF)

Total 58,000 6,800 64,800

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

30,000 34,800 64,800

P-42

GB-ID : GBP1-03-03304-0800-09-076020-08

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Civil works 58,320

Consulting Services 6,480

Total 6,480 58,320

13. Project References

BB 2006 - 2009 ID: P1-03-03304-0407-076020-08

P-43

Directorate General of Human Settlements

GB-ID : GBP1-05-03305-0900-096001

1. Project Title : Climate Friendly and Sustainable City Development (Eco City),

Phase: Solid Waste Improvement Management

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Public Works

4. Implementing Agency : Directorate General of Human Settlement, Ministry of Public Works

5. Duration : 48 months

6. Location : Kota Pekalongan, Kota Surabaya, Kota Semarang, Kota Malang, Kota

Surakarta, Kota Palembang, Kota Mataram, KotaBukit Tinggi, Kota

Serdang Bedagai, Kota Bitung, Kota Amuntai

7. Objectives

a. To improve performance of final disposal site in Pekalongan, Surakarta, Yogyakarta and

Surabaya.

b. To capture and process biogas from final disposal site.

c. To improve environmental condition.

d. To optimize the existing performance of Final Disposal Site for achieving Clean

Development Mechanism (CDM).

8. Scope of Projects

a. Evaluate the performance of Final Disposal Site in selected cities

b. Evaluate the pollution condition.

c. Conduct social/public campaign

d. Determine the appropriate and cost-effective system, considering

e. The existing capacity.

f. Prepare Feasibility Study and Detailed Engineering Design (DED)

g. Prepare financing scheme

h. Rehabilitation of Final Disposal Site according to FS and DED

9. Activities

Activities Implementation

Locations

Project Implementation

Units

a. Evaluate the performance of Final

Disposal Site in selected cities

b. Evaluate the pollution condition.

c. Conduct social/public campaign

d. Determine the appropriate and cost-

effective system, considering

e. The existing capacity.

f. Prepare Feasibility Study and Detailed

Engineering Design (DED)

g. Prepare financing scheme

h. Rehabilitation of Final Disposal Site

according to FS and DED

Selected cities Directorate General of

Human Settlement,

Ministry of Public Works

P-44

GB-ID : GBP1-05-03305-0900-096001

10. Funding Source

Implementing Agency Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Directorate General of

Human Settlement,

Ministry of Public

Works

68,600 7,000 75,600 Germany

Total 68,600 7,000 75,600

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

15,000 25,000 25,000 10,600 75.600

12. Funding Allocations

Categories (US $ 000)

Detail of Activities Services

Construct

-ions Goods Trainings Others

Feasibility Studies & DED 5,600

Final Disposal Site Rehabilitation 70,000

Total 5,600 70,000

13. Project References :

BB 2006 - 2009 ID: P1-05-03305-0501-096001

P-45

GB-ID : GBP1-03-03300-0900-066219

1. Project Title : Metropolitan Sanitation Management and Health Project

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Public Works

4. Implementing Agency : a. Directorate General of Human Settlement, Ministry of Public

Works

b. Government of Yogyakarta City

c. Government of Medan City

d. Government of Makassar City

5. Duration : 60 months

6. Location : Yogyakarta, dan Medan

7. Objectives

a. Reduction healthy risk reduction, particularly for urban low income community

b. Reduction water pollution

c. Increasing quality and pollution of urban environment

d. Overcome institutional constraints which affect sanitation sector

8. Scope of Projects

a. Implementing city sanitation strategies

b. Improving stakeholder’s awareness regarding sanitation

9. Activities

Activities Implementation Locations Project Implementation Units

a. Build sanitation

infrastructure based on city

sanitation strategies

b. Implementation subproject

appraisal report (SPARSs)

c. Give support and

intitutional development

programs addressing sector

reform, governance, and

public awarenes

Yogyakarta, and Medan Directorate General of

Human Settlement

10. Funding Source

Implementing Agency Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

a. Government of

Medan city

22,500 6,000 28,500

b. Government of

Yogyakarta city

12,500 14,000 26,500

ADB

Total 35,000 20,000 55,000

P-46

GB-ID : GBP1-03-03300-0900-066219

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

5,000 15,000 15,000 10,000 10,000 55,000

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Development of sanitation

infrastructure and implementing

supporting activities to maintain

the facilities

10,000 30,000 10,000 4,000 1,000

Total 10,000 30,000 10,000 4,000 1,000

13. Project References :

BB 2006 - 2009 ID: P-03-03300-0502-066219

P-47

GB-ID : GBP1-01-03305-0901-076031-09

1. Project Title : National Program for Community Empowerment in Urban Area

(PNPM Mandiri - Perkotaan)

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Public Works

4. Implementing Agencies : Directorate General of Human Settlement, Ministry of Public

Works

5. Duration : 36 months

6. Location : All Provinces

7. Objectives

To empower Indonesia’s diverse urban communities that is capable to overcome local poverty

problems.

8. Scope of Projects

a. To promote community participation in development planning and management to

overcome poverty problem.

b. To increase the capacity of the local governments.

c. To promote harmonization and synergy with other community empowerment programs to

optimize poverty alleviation.

9. Activities

Activities Implementation

Locations

Project Implementation

Units

a. Community development block grant All sub-district Central and districts level

b. Community & local government

capacity building

All districts and sub-

district

Central and provincial

level

c. Technical support for the

implementation

Central, provinces, &

districts

Central level

10. Funding Source

Implementing

Agencies

Foreign Funding

(US $ 000)

Counterpart

Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Directorate General of

Human Settlements

34,880 34,880 World Bank

Total 34,880 34,880

P-48

GB-ID : GBP1-01-03305-0901-076031-09

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

4,880 10,000 20,000 34,880

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Community & local

government capacity

building

22,700

b. Technical support for the

implementation

12,180

Total 22,700 12,180

13. Project References :

BB 2006 - 2009 ID: P1-01-03305-1190-076031-09

P-49

GB-ID : GBP1-03-03305-0800-09-076032

1. Project Title : Regional Solid Waste Development for Maminasata, South Sulawesi

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Public Works

4. Implementing

Agencies

: a. Directorate General of Human Settlement, Ministry of Public Works

b. Local Government of Gowa, South Sulawesi

5. Duration : 60 months

6. Location : Kab. Gowa, South Sulawesi

7. Objectives

a. To construct a regional solid waste infrastructure in accordance with the required national

technical standard;

b. To have better environment by managing the final disposal sites as sanitary landfill;

c. To have better quality solid waste management.

8. Scope of Projects

Only the first phase in the sanitary landfill construction and the procurement of heavy

equipment were considered, included:

a. Collection

b. Transfer station in Makassar

c. Transportation

d. Access road

e. Supporting facilities

f. Recycling plants

g. Sanitary landfill

h. Compensation facilities for community

9. Activities

Activities Implementation

Locations

Project Implementation

Units

a. Sorting plant

b. Composting plant

c. Sanitary Landfill (phase 1)

d. Heavy equipment (phase 1)

e. Access road

f. Supporting facilities

g. Land acquisition

h. Compensation facilities

i. Transfer station

j. Transportation vehicles

k. Consulting service

Maminasata, South

Sulawesi Province

� Directorate General of

Human Settlement and

Local Governments

P-50

GB-ID : GBP1-03-03305-0800-09-076032

10. Funding Source

Implementing Agencies

Foreign

Funding

(US $ 000)

Counterpart

Funding

(US $ 000)

Total of

Funding

(US $ 000)

Remarks

Directorate General of Human

Settlements, Ministry of Public Works 40,470 4,047 44,517

Japan

(JICA)

Total 40,470 4,047 44,517

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

1,200 5,000 13,317 15,000 10,000 44,517

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Construction 31,700

b. Equipment procurement 3,100

c. Consulting 5,700

d. Contingency 4,017

Total 5,700 31,700 3,100 4,017

13. Project References :

BB 2006 - 2009 ID: P1-03-03305-0502-076032

P-51

GB-ID : GBP1-01-03305-0902-076031-09

1. Project Title : Rural Infrastructure Support (RIS) PNPM Phase 2

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Public Works

4. Implementing Agencies : Directorate General of Human Settlement, Ministry of Public

Works

5. Duration : 60 months

6. Location : Provinces Covered by RIS – PNPM

7. Objectives

To empower Indonesia’s diverse rural communities to be actively participated in development

through identifying their own needs and how to fulfill them with the resources they have to

improve their welfare.

8. Scope of Projects

a. To promote community participation in development planning and management.

b. To fill the gap of infrastructure in general and rural infrastructure in particular as well as to

promote more efficient delivery of services to the rural communities

9. Activities

Activities Implementation Locations Project Implementation

Units

a. Block grant for rural

infrastructure improvement

Rural Central and districts level

b. Community facilitation and

mobilization

Sub-district and rural Central and provincial

level

c. Audit, studies, & surveys All level (central, province,

districts, & sub-districts)

Central level

10. Funding Source

Implementing

Agencies

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Directorate General of

Human Settlements

90,000 90,000 ADB

Total 90,000 90,000

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

30,000 20,000 25,000 10,000 5,000 90,000

P-52

GB-ID : GBP1-01-03305-0902-076031-09

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Block grant for rural & social

infrastructure improvement 35,000 20,000 5,000

b. Community facilitation and

mobilization 28,550

c. Audit, studies, & surveys 1,500

Total 30,000 35,000 20,000 5,000

13. Project References :

BB 2006 - 2009 ID: P1-01-03305-1190-076031-09

P-53

Directorate General of Water of Water Resources

GB-ID : GBP1-03-03300-0900-066268

1. Project Title : The Construction of Transfer Water Inter Basin of Cibutarua – Cilaki –

Cisangkuy

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Public Works

4. Implementing Agency : Directorate General of Water of Water Resources (DGWR), Ministry of

Public Works

5. Duration : 48 months

6. Location : West Java

7. Objectives

The objective of the project is utilization of water resources in DAS Cibutarua to increase raw

water supply from 600 l/sec to 1400 l/sec. on Bandung Regency, and also guarantee of irrigation

water supply in Garut Regency.

8. Scope of Projects

The construction of transfer water inter basin Cibutarua-Cilaki Project, West Java is divided into:

Phase 1, Cibutarua Dam construction and tunnel of transfer inter basin

Phase 2, Santoso Dam construction

9. Activities

Activities Implementation

Locations

Project

Implementation Units

a. Phase 1, Cibutarua Dam construction and

tunnel of transfer inter basin

b. Phase 2, Santosa Dam construction

West Java DGWR

10. Funding Source

Implementing

Agencies

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

DGWR 63,750 20,250 84,000 IDB

Total 63,750 20,250 84,000

11. Disbursement Plan

Disbursement Plan (US $ 000) Total

1st 2nd 3rd 4th 5th

16,800 25,200 25,200 16,800 84,000

P-54

GB-ID : GBP1-03-03300-0900-066268

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Dam construction 84,000

Total 84,000

13. Project References :

BB 2006 - 2009 ID: P-03-03300-0404-066268

P-55

Ministry of National Education

P-57

GB-ID : GBP1-05-02300-0900-061289

1. Project Title : Development of Medical Research Center and Teaching Hospital

2. Project Type : Project Assistance

3. Executing Agency : Ministry of National Education

4. Implementing Agency : University of Indonesia (UI), University of Andalas (UNAND),

University of Sebelas Maret (UNS)

5. Duration : 48 months

6. Location : Jakarta, Padang, Surakarta

7. Objectives

The Development of Medical Educational Research Center and Two University Hospitals has

stated the following strategic objectives:

a. Medical Education

1) To develop center of excellent in medicine

2) To improve effective and efficient curriculum and clinical education system integrated

with modern medical technology to provide excellent quality, professional, competence

graduates that fulfill international standard

3) To create education process that fulfill the international standard based on advance

research and fastening other medical faculty.

4) To provide facilities for undergraduate, graduate and post graduate medical students to

get experiences in the comprehensive clinical medical practices

5) To improve education, research and medical services through collaboration with

Information and Communication Technology (ICT) implementation

6) To assist other medical schools to meet the national standard

b. Medical Research

1) To develop center of excellent in medicine

2) To improve adequate facilities for performing research in medical science to improve

education and service

3) To assess medical science and technology

c. Medical Services

1) To develop centre of excellent in medicine

2) To develop an excellent quality of health care with evidence based medicine approach.

3) To support the health referral system from surrounding hospitals and community

health centers

4) To provide the community, especially coming from the lower economic level with the

more easily accessible health care facilities and high quality medical services.

5) To provide outdoor hospital in anticipating earthquake, tsunami and other natural

disasters

8. Scope of Projects

The scope of the project is aimed to cover the following activities:

a. Civil Works

b. Procurements of equipment

c. Curriculum Development and Training

d. Consultancy

P-58

GB-ID : GBP1-05-02300-0900-061289

9. Activities

Activities Implementation

Locations

Project Implementation

Units

a. Civil Works

• Research and education Tower

• University Hospital

b. Procurement of Equipment

c. Curriculum Development

d. Consultancy

Jakarta, Padang,

Surakarta

UI, Jakarta

UNAND, Padang; UNS,

Surakarta

UI, Jakarta; UNAND,

Padang; UNS, Surakarta

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

UI –Jakarta,

UNAND-Padang,

UNS-Surakarta.

101,567 28,220 129,787 IDB

Total 101,567 28,220 129,787

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

12,133 17,212 52,760 47,682 129,787

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Civil works 57,199

b. Procurement of

Equipment

28,896

c. Consultancy 4,694

d. Project Management

Organization

1,349

e. Curriculum development 28,220

f. Financial Auditing 150

g. Review/Familiarization 45

h. Others (Contingency) 9,234

Total 4,844 57,199 28,896 38,848

13. Project References :

a. BB 2006 - 2009 ID: P-05-02300-1006-061289

b. BB 2006 - 2009 ID: P-05-02300-1006-061292

c. BB 2006 - 2009 ID: P-05-02300-1006-061294

P-59

GB-ID : GBP1-05-02311-0900-071053

1. Project Title : Human Resources for Health Education Quality Improvement

2. Project Type : Project Assistance

3. Executing Agency : Ministry of National Education

4. Implementing Agency : Directorate General of Higher Education, Ministry of National

Education

5. Duration : 60 months

6. Location : Nation Wide

7. Objectives

The project aims at improving the quality of health higher education institution to fulfill the

demand for better quality health providers.

8. Scope of Projects

Improving the quality of health higher education institution

9. Activities

Activities Implementation

Locations

Project

Implementation

Units

a. Competitive grants to health education institutions

to improve the quality of the institutions and the

programs in alignment with national standards

b. Technical assistance, training, and workshop to

improve the implementation of higher education

school accreditation system

c. Procurement of goods and civil works, applied

research, training, and workshop at the central level

to strengthen monitoring and evaluation of quality

of health higher education

d. Training, workshop, and technical assistance at the

central level to strengthen the delivery of education

curriculum

e. Studies, technical assistance, and workshop to

develop human resources of health production

policies to meet demands for health care

Nation Wide Ministry of

National

Education

P-60

GB-ID : GBP1-05-02311-0900-071053

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Ministry of National

Education &

Ministry of Health

77,822 8,855 86,677 World Bank

Total 77,822 8,855 86,677

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

5,530 22,887 37,788 18,847 1,624 86,677

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Strengthening the

accreditation of

Health Higher

Education Institutions

7,148

b. Assuring Standard of

Education Quality

through Certification

of Graduates

12,870

c. Improving School

Quality through

Result-based

61,379

d. Project Management

and Evaluation

5,280

Total 20,018 66,659

13. Project References :

BB 2006 - 2009 ID: P1-05-02311-0705-071053

P-61

GB-ID : GBP1-05-02305-0900-081015

1. Project Title : Life Skills Education for Employment and Entrepreneurship (LSE3)

2. Project Type : Project Assistance

3. Executing Agency : Ministry of National Education

4. Implementing Agency : Ministry of National Education

5. Duration : 60 months

6. Location : Nation Wide

7. Objectives

To contribute in youth unemployment reduction through entrepreneurship and skills

enhancement provided by Non Formal Education (NFE) program. Specifically, LSE3 aims to:

a. Improve market-oriented program of NFE

b. Improve capacity building of NFE institutions

c. Develop financial access scheme for youth entrepreneurs

d. Establish labor market Management Information System (MIS) for a sustainable youth

employment program

8. Scope of Projects

Unemployment reduction through entrepreneurship and skills enhancement

9. Activities

Activities Implementation

Locations

Project

Implementation Units

a. Improve ‘link and match’ between youth and

job market

b. Strengthen equivalency education reform post

literacy education

c. Revitalize youth entrepreneurship

d. Improve program management, monitoring,

and evaluation

Nation Wide Ministry of National

Education

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Ministry of

National

Education

50,000 (loan)

43,000 (grant)

5,000 98,000 World Bank

Total 93,000 5,000 98,000

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

9,800 19,600 29,400 29,400 9,800 98,000

P-62

GB-ID : GBP1-05-02305-0900-081015

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Life skills education 3,000 9,000 27,100

b. Institutional

strengthening and

quality assurance

1,700 7,800

c. Program

management,

integration, and

sustainability

5,200 1,200

d. Grant to LSE3 Project 43,000

Total 8,200 11,900 77,900

13. Project References :

BB 2006 – 2009 ID: P1-05-02305-1004-081015

P-63

GB-ID : GBP1-05-02305-0900-071054

1. Project Title : Sustainable Economic Supported by Improving Technical and

Vocational Education

2. Project Type : Project Assistance

3. Executing Agency : Ministry of National Education

4. Implementing Agency : a. Directorate General of Management of Primary and Secondary

Education, Ministry of National Education

b. Ministry of Industry

c. Ministry of Manpower and Transmigration

5. Duration : 36 months

6. Location : Bandung, West Java

7. Objectives

a. To improve quality of vocational graduates through skill-approach learning in response to

labor market demand;

b. To improve the quality and relevance of vocational school with International benchmark

graduates to produce skilled and adaptable workers;

c. To improve of quality of standards of Technical and Vocational Education and Training

(TVET);

d. To increase the participation of vocational school graduates in industries including as

entrepreneurs;

e. To enhance the capability and facility of selected vocational schools in Ministry of Industry;

f. To improve selected training center (BLK) in Ministry of Manpower and Transmigration.

8. Scope of Projects

a. Coherent strategies for quality TVET and access agreed and monitored by all stakeholders.

b. Access to, and use of, better labor market information for TVET planning and

implementation improved.

c. Access to (self-) employment-relevant competencies as part of lifelong learning broadened.

d. Standard-based national assessment and certification system enhanced and recognized by

private sector

9. Activities

Activities Implementation Locations Project Implementation Units

Civil works, equipment,

consultant, and training of

operational equipment

Several province Ministry of Education

P-64

GB-ID : GBP1-05-02305-0900-071054

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Ministry of National

Education

31,000 (loan)

4,500 (grant)

15,000 50,500 Germany

Total 35,500 15,000 50,500

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

15,150 25,250 10,100 50,500

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Procurement of

equipment

30,456

b. Rehabilitation/

construction of

infrastructure

2,177

c. Consulting services 4,109

d. Programme management

supervision

2,177

e. Others 11,581

Total 4,109 2,177 30,456 13,758

13. Project References :

BB 2006 - 2009 ID: P1-05-02305-1004-071054

P-65

GB-ID : GBP1-05-02300-0700-09-061300

1. Project Title : The Quality Improvement of Padjadjaran University

2. Project Type : Project Assistance

3. Executing Agency : Ministry of National Education

4. Implementing Agency : Padjadjaran University

5. Duration : 36 months

6. Location : Bandung, West Java

7. Objectives

General objective:

To reduce the widespread poverty through the enhancement of the intellectual level and the

community welfare through the quality improvement of the Padjajaran University (UNPAD)

graduates by providing greater community access to the campus facilities and improving the

supporting campus facilities for Tri Dharma activities.

Specific objectives

a. Enhancing the intellectual level and community welfare:

1) To make UNPAD to have a community welfare concern and having an entrepreneurial

attitude in order to assist the enhancement of the intellectual community, the

implementation of regional autonomy and the creation of new job opportunities in

Indonesia;

2) To enlarge the community accesses to various campus facilities as part of the

community empowerment through appropriate knowledge and upgrading of their

skills;

3) To improve the supporting campus facilities and the quality of Tri Dharma activities in

the framework for preparation for higher education autonomy;

4) To provide jobs for the surrounding community during the project implementation

period;

5) To provide facilities for supporting UNPAD program, to increase the quality of the

graduates in order to be able to compete in the national and international human

resources, which in parallel to support the establishment of Padjadjaran University as

an one of the biggest public university in Indonesia.

b. Ensure quality through improvement of campus facilities and infrastructure:

1) Providing advanced laboratory equipment, audiovisual equipment, furniture and books

in order to implement the advanced, effective and efficient learning process;

2) Providing fellowship and training program for the teaching staff of medical, dental,

nursing, economic, fisheries and marine sciences, and agriculture industrial technology;

3) Providing technical assistance for the medical, dental, nursing, economic, fisheries and

marine sciences, and agriculture industrial technology.

8. Scope of Projects

Increased UNPAD community welfare and improvement of campus facilities and

infrastructures.

P-66

GB-ID : GBP1-05-02300-0700-09-061300

9. Activities

Activities Implementation

Locations

Project Implementation

Units

a. Construction of building

� DED consultant

� Project management and supervision

consultant

� Civil work & infrastructure

b. Equipment

c. Furniture and fixture

d. PMU

e. Academic (curriculum) development

f. Training development:

� Consultant service

� Training implementation

g. Auditing

h. Start-up workshop

Bandung, West

Java

Padjadjaran University

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Ministry of National

Education

25,000 9,000 34,000 IDB

Total 25,000 9,000 34,000

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

4,000 16,000 14,000 34,000

P-67

GB-ID : GBP1-05-02300-0700-09-061300

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Procurement of equipment 6,500

b. Construction of

infrastructure

16,000

c. Consulting 1,050

d. Academic Curriculum

Development Program

and Training

8,750

e. PMU, start up workshop

and auditing

1,700

Total 1,050 16,000 6,500 8,750 1,700

13. Project References :

BB 2006 - 2009 ID: P-05-02300-1006-061300

P-69

Ministry of Transportation

P-71

Directorate General of Sea Transportation

GB-ID : GBP1-03-02200-0800-09-066337-07

1. Project Title : Indonesia Ship Reporting System

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Transportation

4. Implementing Agency : Directorate General of Sea Transportation, Ministry of

Transportation

5. Duration : 48 months

6. Location : Nation Wide

7. Objectives

A Ship Reporting System and VTS (Vessel Traffic System) should provides up to date

information on the movements of vessels in order to give a quick and maximum assistance by

participating vessels to a vessel which may be in distress, and in order to facilitate a quick SAR

operation in case of missing of a participating vessel.

8. Scope of Projects

a. Establish report station

Report receiving station (receiving station) will be setup the major cost station 1st, 2nd and

3rd

b. Establish report sub centers

Report sub centers (sub centers) will be setup nine (9) of 1st class and nine (9) of 2nd class

coast stations

c. Establish ship reporting center

Ship reporting center will be setup at transmitting site of Jakarta coast station Tj. Priok

d. Establish data transmission line

Telecommunication line for report transmission on land is as follows

1) center to sub center: Internet/existing HF

2) sub center to 3rd class station : existing HF

e. Establish VTS station in Sunda and Lombok Straits

9. Activities

Activities Implementation

Locations

Project

Implementation Units

a. Design and Supervision

b. Equipment and Software Procurement

c. Installation and Activity

d. Training

e. Equipment Delivery

Nation Wide Directorate General of

Sea Transportation

P-72

GB-ID : GBP1-03-02200-0800-09-066337-07

10. Funding Source

Implementing Agency Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Directorate General of Sea

Transportation

17,504 2,891 20,395 Denmark

Total 17,504 2,891 20,395

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

5,000 5,000 5,395 5,000 20,355

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Design and

Supervision

468

b. Equipment and

Software Procurement

2,547 16,912

c. Training 468

Total 468 2,547 16,912 468

13. Project References :

BB 2006 - 2009 ID: P1-03-02200-0408-066337-07

P-73

GB-ID : GBP1-03-02204-0900-086023

1. Project Title : Vessel Traffic Services (VTS) System

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Transportation

4. Implementing Agency : Directorate General of Sea Transportation, Ministry of Transportation

5. Duration : 48 months

6. Location : Nation Wide

7. Objectives

To establish of VTS System it will contribute to:

a. Monitor the maritime traffic, the maritime area and the traffic lanes

b. Improve the security of the traffic

c. Improve the efficiency of vessel movements

d. Protect the environment

e. Surveillance, detection and tracking of vessels

f. Provision of general information to vessels

g. Provision of specific information to assist ships for navigation

h. Monitoring and analyzing risks of collision and grounding

i. Assisting vessels requiring special attention

j. Anticipating and assisting vessels arriving and departing port areas

8. Scope of Projects

Mayor system composition of Vessel Traffic Services (VTS) System is Radar System, Radar

Tracking, Multifunction Console, VHF Radio System and Transmission Link.

It will be set up at:

a. Tanjung Medang in Rupat Island;

b. Tanjung Parit in Bengkalis Island;

c. Jantan in Karimun Island;

d. Dangas in Batam Island;

e. Tanjung Berakit in Bintan Island;

f. Sabang, Sigli, Lhokseumawe, UG Peureuteam, Tg Tamiang, Belawan, Berhala Island, and

Jemur Island.

9. Activities

Activities Implementation Locations Project Implementation Units

a. Design and Supervision

b. Equipment Procurement

c. Installation

d. Training

Nationwide Directorate of Navigation

P-74

GB-ID : GBP1-03-02204-0900-086023

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Directorate of

Navigation

14,048 1,093 15,141 Norway

Total 14,048 1,093 15,141

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

5,141 10,000 15,141

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Design and Supervision 700

b. Equipment Procurement 13,441

c. Installation 300

d. Training 700

Total 700 300 13,441 700

13. Project References :

BB 2006-2009 ID No: P1-03-02204-0408-086023

P-75

Directorate General of Civil Aviation

GB-ID : GBP1-03-02200-0700-08-09-066353

1. Project Title : Procurement of Airport Rescue and Fire Fighting Equipment

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Transportation

4. Implementing Agency : Directorate General of Civil Aviation, Ministry of Transportation

5. Duration : 24 months

6. Location : 29 Airports in Indonesia

7. Objectives

a. To complete rescue and Fire Fighting Equipment through procurement of new fire fighting

vehicles

b. Replacement the old system to support aviation safety

8. Scope of Projects

a. Procurement of equipment

b. Training

9. Activities

Activities Implementation Locations

Project

Implementati

on Units

a. Delivery of that equipment from

originating country to Indonesia

b. Supervision and commissioning

c. Factory Acceptance Test

d. Factory Raining for operator and

maintenance technician

e. Local/on site training

Sampit, Bengkulu, Waingapu, Ende,

Kendari, Gorontalo, Luwuk, Nabire,

Wamena, Manokwari, Jayapura,

Sorong, Merauke, Tambolaka,

Pangkalan Bun, Alor, Singkep,

Lampung, Cilacap, Bima, Saumlaki,

Sintang, Sibolga, Ruteng, Budiarto,

Sangir Talaud, Poso, Maumere , and

Atambua

Directorate

General of

Civil Aviation

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Directorate General

of Civil Aviation

28,700 3,000 31,700 Netherland

Total 28,700 3,000 31,700

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

6,340 25,360 31,700

P-76

GB-ID : GBP1-03-02200-0700-08-09-066353

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Procurement of

equipment

30,115

b. Services 793

c. Training 792

Total 793 30,115 792

13. Project References :

BB 2006 - 2009 ID: P-03-02200-0302-066353

P-77

Directorate General of Railway

GB-ID : GBP1-03-02200-0800-08-066363

1. Project Title : Procurement of Railway Track Construction and Maintenance Machinery

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Transportation

4. Implementing Agency : Directorate General of Railway, Ministry of Transportation

5. Duration : 72 months

6. Location : Java Island

7. Objectives

To increase the reliability of track by procurement of railway track construction and

maintenance machinery.

8. Scope of Projects

a. Procurement of goods

b. Consulting services

9. Activities

Activities Implementation Locations Project Implementation Units

a. Procurement of goods

b. Consulting services

Java Island Directorate General of Railway

10. Funding Source

Implementing Agency Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Directorate General of

Railway

51,200 6,080 57,280 Germany

(KfW)

Total 51,200 6,080 57,280

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th 6th Total

5,000 10,000 12,500 12,500 10,000 7,280 57,280

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Consulting services 5,000 1,080

b. Procurement of goods 51,200

Total 5,000 51,200 1,080

13. Project References :

BB 2006 - 2009 ID: P-03-02200-0408-066363

P-78

GB-ID : GBP1-03-02200-0800-09-066360

1. Project Title : Procurement of 1000 km Track Material and 200 Units Turn Out

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Transportation

4. Implementing Agency : Directorate General of Railway, Ministry of Transportation

5. Duration : 36 months

6. Location : Java and Sumatera

7. Objectives

a. To increase the service level to user

b. To support maintenance mechanism track and improvement of the track maintenance

quality and to prolong the used of the track and also automatically will increase safety.

c. To anticipate the increasing capacity due to the signaling and double tracking project

d. To support standard maintenance by using the mechanism maintenance equipment to catch

up the standard requirement

8. Scope of Projects

a. Procurement of 1500 Km Track Material, type UIC-54

b. Procurement of 360 units Turn Out

9. Activities

Activities Implementation

Locations

Project Implementation

Units

a. Procurement of 1500 Km Track Material,

type UIC-54

b. Procurement of 360 units Turn Out

Java and Sumatera Directorate General of

Railway

10. Funding Source

Implementing Agency Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Directorate General of

Railway

102,000 19,500 121,500 China

Total 102,000 19,500 121,500

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

65,750 27,875 27,875 121,500

P-79

GB-ID : GBP1-03-02200-0408-066360

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Procurement of 1500

Km Track Material,

type UIC-54

88,720

b. Procurement of 360

units Turn Out

13,280

c. Others 19,500

Total 102,000 19,500

13. Project References :

BB 2006 - 2009 ID: P-03-02200-0408-066360

P-80

GB-ID : GBP1-06-04800-0900-062519-07

1. Project Title : Procurement of Locomotives Diesel Electric

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Transportation

4. Implementing Agency : Directorate General for Railways, Ministry of Transportation

5. Duration 39 months

6. Location : Java Island

7. Objectives

a. Availability of electric diesel locomotives for transportation of passengers and freight

especially in Java island;

b. Implementation of locomotives ready for operation, instead of old and damaged types of

locomotives;

c. Fulfill the requirement of passengers and goods demand by railway especially during

holiday seasons, such as new year, and for coal transportation

8. Scope of Projects

PT. Kereta Api (KA), Persero (Railway Corporation) has four separated railway networks,

namely in Java, North Sumatera, West Sumatera and South Sumatera. This project is focused on

the Java network. PT. KA (Persero) network on Java Island has an overall length of 4.726 km of

which 3.672 km is operational. This has a gauge of 1.067 mm and connects all the major cities

across the length and breadth of Java Island. PT. KA (Persero) handles a substantial proportion

of passenger traffic and freight traffic.

The main power for carrying out the above traffic is provided by diesel electric and diesel

hydraulic locomotives and to a limited extent is carried by diesel hydraulic rail cars and electric

multiple unit trains for suburban traffic. The major portion of the traffic and the important

traffic is carried out by diesel electric locomotives. As such the focus of this project is on diesel

electric locomotives DC/DC type BB-202, CC-201, CC-203 and the latest AC/DC CC-204 and also

CC-202 type. There are in all 421 units diesel locomotives of PT. KAI.

The total numbers of operationally ready medium locomotives are 347 units of which 74 units

are aged above 30 years with the following details:

a. condition 50% - 60% : 24 units

b. condition less than 50% : 50 units.

9. Activities

Activities Implementation Locations Project Implementation Units

Procurement of 30 units

locomotives diesel electric

Java Island Directorate General for

Railways, Ministry of

Transportation

P-81

GB-ID : GBP1-06-04800-0900-062519-07

10. Funding Source

Implementing Agency Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Directorate General for

Railways, Ministry of

Transportation

51,000 - 51,000 China/

Export

Credit

Total 51,000 - 51,000

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

10,200 15,300 20,400 5,100 51,000

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Procurement of 30 units

locomotives diesel electric 51,000

Total 51,000

13. Project References :

BB 2006-2009 ID No: P1-06-04800-0101-062519-07

P-83

Ministry of Industry

P-85

GB-ID : GBP1-02-01900-0700-09-064382

1. Project Title : Development of Leather Industries

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Industry

4. Implementing Agency : a. Ministry of Industry

b. Indonesian Footwear Service Centre, Sidoarjo

5. Duration : 36 months

6. Location : Sidoarjo, East Java

7. Objectives

To establish Indonesian Footwear and Service Center (IFSC) which shall supply capacity

building, carrying out the activities:

a. training & education;

b. testing, quality control & certification;

c. technology transfer & technical assistance;

d. design improvement; and

e. Research and Development.

8. Scope of Projects

a. Machineries procurement

b. Training

c. Consultation

9. Activities

Activities Implementation

Locations

Project

Implementation Units

a. Establishment IFSC & appoint management Sidoarjo, East Java

b. Training Italia & Indonesia

c. Consultation Services Sidoarjo, East Java

Directorate General of

Small and Medium

Industries

10. Funding Source

Implementing Agency Foreign Funding

(US $ 000)

Local Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Ministry of Industry 7,150 1,495 8,645 Italy

Total 7,150 1,495 8,645

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

700 3,000 4,945 8,645

P-86

GB-ID : GBP1-02-01900-0700-09-064382

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Establishment IFSC &

appoint management

4,460

b. Training 1,495

c. Consultation Services 2,690

Total 2,690 4,460 1,495

13. Project References :

BB 2006 - 2009 ID: T-02-01900-0407-064382

P-87

Ministry of Agricultural

P-89

GB-ID : GBP1-05-02400-0901-061130

1. Project Title : Prevention and Control of Avian Influenza in the Veterinary Sector

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Agricultural

4. Implementing Agency : Directorate General of Livestock Services, Ministry of Agricultural

5. Duration : 36 months

6. Location : - National Veterinary Drugs Assay Laboratorium (NVDAL)

Gunung Sindur, Bogor, West Java

- Disease Investigation Centre (DIC) Banjar Baru, South

Kalimantan

7. Objectives

To contribute to the national and global strategy of highly pathogenic Avian Influenza control

and to reduce the threat of human pandemic

8. Scope of Projects

a. Determine detailed spesifications on BS-3 capacity required

b. Develop site plan for BSL-3 facility

c. Detailed design for BSL-3 facility

d. Define equipment requuired

e. Recruit and train staff

f. Build BSL-3 facility

g. Install required equipment

h. Commission BSL-3 facility

9. Activities

Activities Implementation

Locations

Project

Implementation Units

a. Construction of BSL-3

b. Equipment for BSL-3

c. Training activities

d. Consulting services

e. Technical contingencies

NVDAL Gunung

Sindur

f. Upgrading DIC DIC Banjar Baru,

South Kalimantan

NVDAL Gunung

Sindur

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Directorate General

of Livestock Services

3,900 390 4,290 Germany

Total 3,900 390 4,290

P-90

GB-ID : GBP1-05-02400-0901-061130

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

1,000 1,820 1,470 4,290

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. Construction of BSL-3 2,000

b. Equipment for BSL-3 650

c. Training activities 515

d. Consulting services 400

e. Technical contingencies 300

f. Upgrading DIC 425

Total 400 2,000 1,075 515 300

13. Project References :

BB 2006 - 2009 ID: T-05-02400-0703-061130

P-91

Ministry of Manpower and

Transmigration

P-93

GB-ID : GBP1-02-2613-0900-073081

1. Project Title : Revitalization of Vocational Training Center

2. Project Type : Project Assistance

3. Executing Agency : Ministry of Manpower and Transmigration

4. Implementing Agency : Directorate General of Training and Productivity Development,

Ministry of Manpower and Transmigration (MOMT)

5. Duration : 36 months

6. Location : DKI Jakarta (central government) and 11 VTCs in NAD (Banda

Aceh), Sumatera Utara (Medan), Banten (Serang), Jawa Barat

(Bekasi and Bandung), Jawa Tengah (Surakarta and Semarang),

Kalimantan Timur (Samarinda), Sulawesi Selatan (Makassar),

Maluku Utara (Ternate), Papua Barat (Sorong)

7. Objectives

Improving the capacity of 11 central-government-owned Vocational Training Centers (VTCs) in

producing competent workers through revitalization program.

8. Scope of Projects

a. Formulating program and activity plans for three years implementation;

b. Improving equipment of existing vocational trainings;

c. Providing equipment for new vocational trainings;

d. Improving the quality (capacity building) and quantity of VTCs’ management and

instructors (upgrading and new);

e. Providing equipment for Mobile Training Units in selected vocational training.

9. Activities

Activities Implementation

Locations

Project

Implementation Units

Phase 1: Preparation

1. Project implementation planning

2. Project management planning

3. Requirement guidance of consultant

4. Workshop on identifying priority activities

5. Inviting appropriate consultant

6. Bidding preparation

Phase 2: Implementation

1. Selection of participants of training for

instructors

2. Formulation of training equipment for

bidding

3. Training of instructors (basic training)

4. International bidding for training

equipment

DKI Jakarta Ministry of Manpower

and Transmigration

P-94

GB-ID : GBP1-02-2613-0900-073081

Activities Implementation

Locations

Project

Implementation Units

5. Distribution and installation of training

equipment

6. Familiarization of training equipment

7. Instructors training for the new equipment

Phase 3: Monitoring and Evaluation

1. Monitoring and evaluation

11 VTCs

2. Reporting DKI Jakarta

Ministry of Manpower

and Transmigration

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Ministry of

Manpower and

Transmigration

32,500 8,125 40,625 IDB

Total 32,500 8,125 40,625

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

6,094 16,250 18,281 40,625

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Phase 1: Preparation

a. Project implementation

planning

250

b. Project management

planning

250

c. Requirement guidance of

consultant

1,000

d. Workshop on identifying

priority activities

500

e. Inviting appropriate

consultant

2,000

f. Bidding preparation 500

P-95

GB-ID : GBP1-02-2613-0900-073081

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Phase 2: Implementation

a. Selection of participants of

training for instructors

250

b. Formulation of training

equipment for bidding

250

c. Training of instructors (basic

training)

4,500

d. International bidding for

training equipment

500

e. Procurement of equipment 28,775

f. Distribution and installation

of training equipment

500

g. Familiarization of training

equipment

500

h. Instructors training for the

new equipment

500

Phase 3: Monitoring and Evaluation

a. Monitoring and evaluation 250

b. Reporting 100

Total 5,350 30,275 4,500 500

13. Project References :

BB 2006 - 2009 ID: P1-02-2613-0402-073081

P-97

Indonesian National Police

P-99

GB-ID : GBP1-07-06000-0800-09-062437

1. Project Title : Integrated Trunking Radio Communication for Indonesian

National Police

2. Project Type : Project Assistance

3. Executing Agency : Indonesian National Police

4. Implementing Agency : Indonesian National Police

5. Duration : 12 months

6. Location : West Kalimantan, Central Kalimantan, South Kalimantan, and East

Kalimantan

7. Objectives

To build up an integrated Indonesian National Police radio operational communication network

especially in big cities as the centers of an organized crime network.

8. Scope of Projects

The increasing criminal trend in Indonesia is happening in the big cities which need specific

equipment for police communication. Prototype radio communication for big cities should

comply with the operational needs of the Indonesian National Police.

The main priority is to build the Indonesian National Police radio communication which has the

capability to support activities of the Indonesian National Police, and to strengthen the

Indonesian National Police long distance communication network by enhancing its command,

coordination, communication, and information.

9. Activities

Activities Implementation Locations

Project

Implementation

Units

Building radio communication

network

West Kalimantan, Central

Kalimantan, South Kalimantan,

and East Kalimantan

Indonesian National

Police

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Indonesian National

Police

71,000 12,500 83,500 Korea

(EDCF)

Total 71,000 12,500 83,500

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

83,500 83,500

P-100

GB-ID : GBP1-07-06000-0800-09-062437

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Building radio communication

network

1,000 5,000 75,500 1,500 500

Total 1,000 5,000 75,500 1,500 500

13. Project References :

BB 2006 - 2009 ID: P-07-06000-0301-062437

P-101

GB-ID : GBP1-07-06000-0900-062432

1. Project Title : National Criminal Information Center for Indonesian National

Police Phase II

2. Project Type : Project Assistance

3. Executing Agency : Indonesian National Police

4. Implementing Agency : Indonesian National Police

5. Duration : 36 months

6. Location : Nation Wide

7. Objectives

a. Providing National Crime Information System accessible by Criminal Justice System and

public.

b. To help Indonesian National Police and related department to prevent crime, by supplying

fast, reliable and accurate crime data.

c. To support Indonesian National Police in its cooperation with international police

organization in preventing and processing crime in its new dimension, such as organized

crime and crime between country.

8. Scope of Projects

In order to process crime information fastly and as accurately as possible, an information

technology that is composed of modern on-line computerized system is required. Therefore, to

obtain reliable criminal data, a center of crime information is needed to support Indonesian

National Police in cooperation with other related department in Criminal Justice System.

9. Activities

Activities Implementation Locations Project Implementation Units

Provide Brain Ware,

Software Programming,

and Develop Network

System

DKI Jakarta Indonesian National Police

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Indonesian National

Police

20,000 3,500 23,500 Korea

(EDCF)

Total 20,000 3,500 23,500

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

10,500 6,500 6,500 23,500

P-102

GB-ID : GBP1-07-06000-0900-062432

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Provide Brain Ware, Software

Programming, and Develop

Network System

2,500 16,000 3,500 1,500

Total 2,500 16,000 3,500 1,500

13. Project References :

BB 2006 - 2009 ID: P-07-06000-0301-062432

P-103

Indonesian Institute of Science

P-105

GB-ID : GBP1-04-07900-0700-08-09-065451

1. Project Title : Animal Husbandry Technology and Practice Improvement to

Accelerate Meat and Milk Production (Meat-Milk Pro)

2. Project Type : Project Assistance

3. Executing Agency : Indonesian Institute of Science (LIPI)

4. Implementing Agency : Research Centre for Biotechnology, Indonesian Institute of Science

5. Duration : 36 months

6. Location : Cibinong Science Centre, West Java, South Sulawesi, and West

Sumatera

7. Objectives

The objective of the project is to promote animal husbandry as a pillar industry of Indonesia’s

rural economy. For this reason, the project is dedicated to build research infrastructure and

facilities. The project is also aimed to build incubator facilities as a vehicle to accelerate

dissemination of science and technology based innovation to the public.

The project is aimed to build information system as clearing house for beef and dairy cattle

activities, and to support the development of science and science base technology on livestock to

boost innovation and accelerate beef and dairy cattle business and other related industry.

Through the accomplishment of this objective, LIPI, by herself and through the collaboration

with other research institutes, universities and stake holders should be able to promote various

research programmers, accumulate basic knowledge, create technology, and improve the

affectivity and efficiency of beef and dairy cattle business. It is expected that LIPI will

continuously facilitate the improvement of the efficiency and affectivity of beef and dairy cattle

industry and facilitate the creation of a new technology.

8. Scope of Projects

a. Capacity Building

Problems in the beef and dairy cattle industry development include those related to major

input sides of the industry i.e.

1) Infrastructure of science and technology of the livestock sub-sector,

2) Human resources development, Information technology

3) Management of the services. Those three components are interconnected and contribute

to the success as well as the failure of the whole livestock industries development.

b. Intermediary mechanism institution

Problems in the intermediary mechanism of livestock industry development are very much

related to adoption of technology, such as through incubator a technology system, which

covers:

1) Institutional networking in the livestock development,

2) Working mechanism, partnership and information flow among responsible institutions

3) Adoption of the technology (Technical service team, production team, demonstration

farm).

P-106

GB-ID : GBP1-04-07900-0700-08-09-065451

c. Transformation Science and Technology

Problems in the transformation of science and technology system, particularly in livestock

development, are very much related to production systems which basically consist of:

1) Post harvest production technology,

2) Marketing and capital management

3) Institutional supports.

9. Activities

Activities Implementation

Locations Project Implementation Units

a. Research and

Development (Science

and technology centre),

incubator technology

Cibinong

Science Centre,

Bogor, West

Java

� Research Centre for Biotechnology, Indonesian

Institute of Science

� Bogor Agriculture University

b. Dairy Plant Incubator West Java � Provincial Livestock Services of West Java

� Padjadjaran University

� Indonesian Agricultural Technology Assessment

and Development Institute

� Provincial Assessment Institute of Agricultural

Technology

c. Beef Plant Incubator South Sulawesi � Provincial Livestock Services of South Sulawesi

� Hasanuddin University

� Provincial Assessment Institute of Agricultural

Technology

d. Beef Plant Incubator West Sumatera � Provincial Livestock Services of West Sumatera

� Andalas University

� Provincial Assessment Institute of Agricultural

Technology

10. Funding Source

Implementing Agencies

Foreign

Funding

(US $ 000)

Counterpart

Funding

(US $ 000)

Total of

Funding

(US $ 000)

Re -

marks

� Research Centre for Biotechnology,

Indonesian Institute of Science

� Bogor Agriculture University

13,116 1,792 14,908

� Provincial Livestock Services of West Java

� Padjadjaran University

� Indonesian Agricultural Technology

Assessment and Development Institute

� Provincial Assessment Institute of

Agricultural Technology

2,864 2,864

Spain

P-107

GB-ID : GBP1-04-07900-0700-08-09-065451

Implementing Agencies

Foreign

Funding

(US $ 000)

Counterpart

Funding

(US $ 000)

Total of

Funding

(US $ 000)

Remarks

� Provincial Livestock Services of

South Sulawesi

� Hasanuddin University

� Provincial Assessment Institute of

Agricultural Technology

1,521 1,521

� Provincial Livestock Services of West

Sumatera

� Andalas University

� Provincial Assessment Institute of

Agricultural Technology

2,252 2,252

Spain

Total 19,753 1,792 21,545

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

6,139 9,841 5,565 21,545

12. Funding Allocations

Categories (US $ 000)

Detail of Activities Services

Construct

-ions Goods Trainings Others

a. Research and Development

Infrastructure Facilities (Science

and technology centre), incubator

technology

1,096 18,083

b. Human Resource Development 1,674

c. Program Development and

Dissemination 444

d. Administration 248

Total 444 1,096 18,083 1,674 248

13. Project References :

BB 2006 - 2009 ID: P-04-07900-0407-065451

P-109

National Resilience Institute

P-111

GB-ID : GBP1-07-06400-0700-08-09-062454

1. Project Title : Strengthening the Capacity Building Program of National

Resilience Institute

2. Project Type : Project Assistance

3. Executing Agency : National Resilience Institute

4. Implementing Agency : National Resilience Institute

5. Duration : 24 months

6. Location : DKI Jakarta

7. Objectives

The objectives of the project is to support National Resilience Institute short, middle, and long

term program implementation, especially to support assessment and education program.

8. Scope of Projects

The scope of the project are strengthening and reengineering in the organization, system and

recruitment procedure, curriculum, leveraging the capacity of the human resources, assessment

process, and the infrastructure of information.

9. Activities

Activities Implementation

Locations

Project

Implementation Units

a. Planning and analyzing of the information

policy and system

b. Redesign, reconstruction and

reimplementation of system software,

development tools and application software

c. Redevelopment and rehabilitation of

information network infrastructure

d. Procurement and construction of hardware

and network equipment supply

e. Maintenance services (update content,

troubleshooting and system monitoring)

f. Developing and upgrading of the centralized

database system

g. Evaluation and audit of information system

and policy

h. Socialization and training for system user,

administrator and supporter

DKI Jakarta National Resilience

Institute

P-112

GB-ID : GBP1-07-06400-0700-08-09-062454

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

National Resilience

Institute

9,000 2,000 11,000 Spain

Total 9,000 2,000 11,000

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

7,250 3,750 11,000

12. Funding Allocations

Categories (US $ 000)

Detail of Activities Services

Construct

-ions Goods

Train

ings Others

a. Planning and analyzing of the

information policy and system

242

b. Redesign, reconstruction and

reimplementation of system software,

development tools and application

software

2,684

c. Redevelopment and rehabilitation of

information network infrastructure

935

d. Procurement and construction of

hardware and network equipment

supply

3,124

e. Maintenance services (update content,

troubleshooting and system

monitoring)

957

f. Developing and upgrading of the

centralized database system

892

g. Evaluation and audit of information

system and policy

1,089

h. Socialization and training for system

user, administrator and supporter

858

i. Freight and Insurance 209

Total 5,874 4,059 858 209

13. Project References :

BB 2006 - 2009 ID: P-07-06400-0202-062454

P-113

Local Government of Nanggroe Aceh

Darussalam Province

P-115

GB-ID : GBP2-03-00600-0900-076102-09

1. Project Title : Seulawah Geothermal Working Area Infrastructure

2. Project Type : Project Assistance

3. Executing Agency : Local Government of Nanggroe Aceh Darussalam (NAD) Province

4. Implementing Agency : Local Government of Nanggroe Aceh Darussalam Province (NAD)

5. Duration : 60 months

6. Location : Seulawah, Aceh Besar Regency, NAD Province

7. Objectives

a. Acceleration of Geothermal potential development for geothermal power plant in Seulawah

Agam, NAD Province

b. Increase of electricity supply in NAD Province by using the available renewable energy

c. Reduce the dependency on fossil fuel based energy resources

d. Reduce the environmental disturbance by the use of low or no emission renewable energy

e. Support the implementation of the Government Geothermal Road Map program

f. Increase the prosperity of the Indonesian people in general and especially for the Aceh

people

8. Scope of Projects

a. Exploration drilling

b. Feasibility Study

c. Exploitation

d. Utilization and power plant construction

e. Other related activities, e.g.: build transmission until the interconnection point of electricity,

infrastructure, etc.

9. Activities

Activities Implementation

Locations

Project

Implementation Units

a. Exploration Drilling

b. Feasibility study

c. Exploitation

d. Utilization and power plant construction

Seulawah, Aceh

Besar Regency

Local Government of

NAD Province

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Government of

NAD Province

81,900 76,500 158,400 Germany

Total 81,900 76,500 158,400

P-116

GB-ID : GBP2-03-00600-0900-076102-09

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

9,000 11,500 52,400 65,000 20,500 158,400

12. Funding Allocations

Categories (US $ 000)

Detail of Activities Services

Construct

-ions Goods Trainings Others

Seulawah Geothermal Working Area

Infrastructure

158,400

Total 158,400

13. Project References :

BB 2006 – 2009 ID: P2-03-00600-0407-076102-09

P-117

Local Government of Riau Province

P-119

GB-ID : GBP2-03-03301-0700-08-09-067493

1. Project Title : Southern Pekanbaru Water Supply Project

2. Project Type : Project Assistance

3. Executing Agency : Local Government of Riau Province

4. Implementing Agency : Local Government of Riau Province

5. Duration : 24 months

6. Location : Pekanbaru, Riau

7. Objectives

a. To increase water supply services coverage up to 60% in 2015

b. To have better environment by managing the final disposal sites as sanitary landfill

c. To provide water supply with capacity 500 l/s for southern Pekanbaru area (Pekanbaru City

and Kampar Regency)

8. Scope of Projects

To build new water supply system to cover southern Pekanbaru area

9. Activities

Activities Implementation

Locations

Project

Implementation Units

a. To build Water Treatment Plant with

capacity 500 l/s

b. To build transmission, distribution network,

reticulation and house connection to cover

southern Pekanbaru area separated from

existing PDAM services area, and part of

Kampar district adjacent to South

Pekanbaru

c. The raw water will be taken from Kampar

River

d. To increase the appointed Human Resource

Development (HRD) to manage the new

system

e. Detail Design Engineering (DED) &

supervision for construction works

Pekanbaru City

and Kampar

Regency, Riau

Province

Local Government of

Riau Province

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

Local Government

of Riau Province

27,143 4,475 31,618 Denmark

Total 27,143 4,475 31,618

P-120

GB-ID : GBP2-03-03301-0700-08-09-067493

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

13,250 18,368 31,618

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

a. New connections 4,458

b. Project preparation 467

c. DED 443

d. Supervision 338

e. Land acquisition 1,181

f. General cost 443

g. Intake building works 1,425

h. Processing installation 6,185

i. Transmission and

distribution network

15,222

j. Office services 108

k. Construction tax 1,347

l. Others 91

Total 781 27,290 3,547

13. Project References :

BB 2006 - 2009 ID: P-03-03301-0603-067493

P-121

PT. PERTAMINA

P-123

GB-ID : GBP3-03-02004-0900-086038-09

1. Project Title : Ulubelu Unit 3 & 4 (2x55 MW)

2. Project Type : Project Assistance

3. Executing Agency : PT. PERTAMINA (Persero)

4. Implementing Agency : PT. PERTAMINA (Persero)

5. Duration : 48 months

6. Location : Lampung Province

7. Objectives

a. To supply the electric power at the capacity of 2x55MW.

b. To increase the geothermal contribution to the national energy mix

8. Scope of Projects

a. Preparation of well pad, road, and cellar

b. Exploration and development drillings

c. Engineering design, procurements, and construction of the power plants

d. Construction of Steam gathering system (production facility) and power plant facility

e. Power plant commissioning

9. Activities

Activities Implementation

Locations

Project

Implementation Units

a. Preparation of well pad, road, and cellar

b. Exploration and development drillings

c. Engineering design, procurements, and

construction of the power plants

d. Construction of Steam gathering system

(production facility) and power plant facility

e. Power plant commissioning

Lampung

Province

PT. PERTAMINA

(Persero)

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart

Funding

(US $ 000)

Total of

Funding

(US $ 000)

Remarks

PT. PERTAMINA 295,400 - 295,400 Japan (JICA)

Total 295,400 - 295,400

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

29,540 88,620 103,390 73,850 295,400

P-124

GB-ID : GBP3-03-02004-0900-086038-09

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Ulubelu Unit 3 & 4 (2x55 MW) 295,400

Total 295,400

13. Project References :

BB 2006 - 2009 ID: P3-03-02004-0405-086038-09

P-125

State Electricity Company

(PT. PLN)

P-127

GB-ID : GBP3-03-02004-0900-076127

1. Project Title : Bakaru II Hydro-Electric Power Plant (HEPP) [2 x 63 mW]

2. Project Type : Project Assistance

3. Executing Agency : State Electricity Company (PT. PLN)

4. Implementing Agency : State Electricity Company (PT. PLN)

5. Duration : 72 months

6. Location : South Sulawesi Province

7. Objectives

a. To reclaim original capacity of Bakaru I

b. To solve the sedimentation problem of Bakaru dam

c. To maintain the reservoir capacity at million cubic meter

d. To add capacity of peaking unit by 126 MW in South Sulawesi system

e. To increase value of water discharge of Bakaru Hydro Power by operating the power plant

as a peaking unit

8. Scope of Projects

a. Stage I :

1) Sedimentation countermeasure

2) Rehabilitation dam and turbine of Bakaru I HEPP

3) Engineering services for Bakaru II HEPP

b. Stage II :

1) Construction of Bakaru II HEPP

2) Engineering services for construction supervision

9. Activities

Activities Implementation

Locations

Project

Implementation Units

a. Stage I :

• Sedimentation countermeasure

• Rehabilitation dam and turbine of Bakaru

I HEPP

• Engineering services for Bakaru II HEPP

b. Stage II :

• Construction of Bakaru II HEPP

• Engineering services for construction

supervision

South Sulawesi PT PLN (Persero)

Pikitring Sulmapa

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

PT. PLN 133,232 36,738 169,970 Japan (JICA)

Total 133,232 36,738 169,970

P-128

GB-ID : GBP3-03-02004-0900-076127

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th 6th Total

43,000 20,000 35,000 36,000 19,500 16,470 169,970

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

HEPP construction 169,970

Total 169,970

13. Project References :

BB 2006 - 2009 ID: P3-03-02004-0405-076127

P-129

GB-ID : GBP3-03-02004-0900-096003

1. Project Title : Construction for Java - Sumatera Interconnection 500 kV Line

(HVDC) - Phase I

2. Project Type : Project Assistance

3. Executing Agency : State Electricity Company (PT. PLN)

4. Implementing Agency : State Electricity Company (PT. PLN)

5. Duration : 24 months

6. Location : Java and Sumatera Island

7. Objectives

a. To utilize untradeable low rank coal in South Sumatera

b. To evacuate power from mine mouth power plants to load centers in Java

c. To increase the reliability of Java-Bali System and Sumatera system

d. To share reserve capacity between Java-Bali and Sumatera

e. To reduce production cost of Java-Bali and Sumatera system

8. Scope of Projects

Construction of:

a. 500 kV AC Overhead line (OHL) = 272 km

b. 500 kV DC Overhead line (OHL) = 494 km

c. HVDC submarine cables = 40 km

d. HVDC inverter and converter station = 3000 MW

e. 275 kV overhead line (OHL) = 167 km

9. Activities

Activities Implementation

Locations

Project

Implementation Units

Construction of:

a. 500 kV AC Overhead line (OHL)

b. 500 kV DC Overhead line (OHL)

c. HVDC submarine cables

d. HVDC inverter and converter

e. 275 kV overhead line (OHL)

Java and

Sumatera Island

PT PLN

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

PT. PLN 400,000 - 400,000 Japan (JICA)

Total 400,000 - 400,000

P-130

GB-ID : GBP3-03-02004-0900-096003

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

200,000 200,000 400,000

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Construction for Java -

Sumatera Interconnection 500

kV Line (HVDC) - Phase I

400,000

Total 400,000

13. Project References :

BB 2006 - 2009 ID: P3-03-02004-0405-096003

 

P‐131  

 GB‐ID : GBP3‐03‐02004‐0900‐066505 

1. Project Title  :  Engineering Services and Construction of the Kamojang ‐ 6 Geothermal Plant (60 MW) 

2. Project Type  :  Project Assistance 3. Executing Agency  :  State Electricity Company (PT. PLN) 4. Implementing Agency  :  State Electricity Company (PT. PLN) 5. Duration  :  36 months 6. Location  :  West Java Province  7. Objectives 

a. Undertake engineering design and tender document for EPC contracts b. Undertake power generating facilities construction c. Undertake transmission/distribution construction lines 

 8. Scope of Projects  

a. Preparation detail design and tender document for EPC contracts. b. Construction 

 9. Activities 

Activities Implementation 

Locations Project 

Implementation Units 

Engineering Services and Construction of the Kamojang ‐ 6 Geothermal Plant (60 MW) 

West Java  PT PLN (Persero) 

 10. Funding Source 

Implementing Agency 

Foreign Funding(US $ 000) 

Counterpart Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

PT. PLN  51,000  9,600  60,600  JICA/ ADB/ World Bank 

Total  51,000  9,600  60,600    11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

15,000  25,000  20,600      60,600  12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions  Goods  Trainings  Others 

Construction of Geothermal Plant    60,600       

Total    60,600        13. Project References : 

BB 2006 ‐ 2009 ID: P‐03‐02004‐0405‐066505 

 

P‐132 

 GB‐ID : GBP3‐03‐02004‐0900‐066506 

1. Project Title  :  Engineering Services and Construction of the Lumut Balai Geothermal Plant (2 x 55 MW) 

2. Project Type  :  Project Assistance 3. Executing Agency  :  State Electricity Company (PT. PLN) 4. Implementing Agency  :  State Electricity Company (PT. PLN) 5. Duration  :  36 months 6. Location  :  South Sumatera  7. Objectives 

a. Undertake  engineering  design  and  tender  document  for  Engineering  Procurement  and Construction (EPC) contracts 

b. Undertake power generating facilities construction c. Undertake transmission/distribution construction lines 

 8. Scope of Projects  

a. Preparation detail design and tender document for EPC contracts. b. Construction 

 9. Activities 

Activities Implementation 

Locations Project 

Implementation Units Engineering Services and Construction of the Lumut Balai Geothermal Plant (2 x 55 MW) 

South Sumatera  PT PLN (Persero) 

 10. Funding Source 

Implementing Agency 

Foreign Funding(US $ 000) 

Counterpart Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

PT. PLN  120,700  21,300  142,000  JICA/ ADB/ World Bank 

Total  120,700  21,300  142,000    11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

32,000  60,000  50,000      142,000  12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions  Goods  Trainings  Others Construction of Geothermal Plant    142,000       

Total    142,000        13. Project References : 

BB 2006 ‐ 2009 ID: P‐03‐02004‐0405‐066506 

P-133

GB-ID : GBP3-03-02002-0900-086039

1. Project Title : Enterprise Resource Planning (ERP) Outside Java Bali

2. Project Type : Project Assistance

3. Executing Agency : State Electricity Company (PT. PLN)

4. Implementing Agency : State Electricity Company (PT. PLN)

5. Duration : 24 months

6. Location : Nation Wide - Outside Java-Bali

7. Objectives

a. Standardization of business process, material codes and IT infrastructure

b. Support of PT. PLN Good Corporate Governance (GCG) with transparency and control

c. Timeliness and accuracy of PT. PLN financial reports

d. Increase workforce efficiency and productivity

e. Potential annual saving

f. Better management decision making

g. Improved financial management

h. Faster and more accurate transactions

8. Scope of Projects

a. Implementation of Enterprise Resource Planning (ERP) in all business units outside Java

b. Business units: 7 PLN Wilayah (Disco), 2 pembangkitan (Genco) dan 1 Transmission

(Transco) :

1) PLN wilayah NAD, PLN wilayah Sumut, PLN Wilayah Sumbar

2) PLN wilayah Riau, PLN wilayah Bangka Belitung

3) PLN wilayah Lampung, PLN wilayah Sumatera Selatan, Jambi dan Bengkulu

4) PLN Pembangkit Sumbagut, PLN Pembangkit Sumbagsel

5) PLN P3B Sumatera

c. Number of ERP Users : 1248

d. Number of employees : 9,600

e. ERP modules :

1) Financial Management

2) Material Management

3) Human Resource Management

9. Activities

Activities Implementation

Locations

Project Implementation

Units

Enterprise Resource Planning

(ERP) Outside Java - Bali

South Kalimantan PT PLN (Persero)

Pikitring Kalimantan

P-134

GB-ID : GBP3-03-02002-0900-086039

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

PT. PLN 30,000 - 30,000 World

Bank

Total 30,000 - 30,000

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

12,000 18,000 30,000

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Total Project 1,500 9,000 19,350 150

Total 1,500 9,000 19,350 150

13. Project References :

BB 2006 - 2009 ID: P3-03-02002-0405-086039

P-135

GB-ID : GBP3-03-02004-0900-066513-07-08

1. Project Title : Java-Bali Electricity Distribution Performance Improvement

2. Project Type : Project Assistance

3. Executing Agency : State Electricity Company (PT. PLN)

4. Implementing Agency : State Electricity Company (PT. PLN)

5. Duration : 24 months

6. Location : Java and Bali

7. Objectives

a. To decrease network losses.

b. To improve power reliability and quality

8. Scope of Projects

a. System reconfiguration

b. Re-constructing 20 kV lines

c. Installation of capacitors

d. Consulting services

9. Activities

Activities Implementation Locations Project Implementation Units

a. System reconfiguration

b. Re-constructing 20 kV lines

c. Installation of capacitors

d. Consulting services

Java and Bali PT PLN (Persero)

Distribution in Java and Bali

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

PT. PLN 100,000 15,000 115,000 ADB

Total 100,000 15,000 115,000

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

69,000 46,000 115,000

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Java – Bali Distribution 5,750 34,500 74,175 575

Total 5,750 34,500 74,175 575

13. Project References :

BB 2006 - 2009 ID: P3-03-02004-0405-066513-07-08

P-136

GB-ID : GBP3-03-02005-0900-086040

1. Project Title : Java-Bali Submarine Cable 150 kV Circuit 3 & 4

2. Project Type : Project Assistance

3. Executing Agency : State Electricity Company (PT. PLN)

4. Implementing Agency : State Electricity Company (PT. PLN)

5. Duration : 24 months

6. Location : East Java and Bali

7. Objectives

a. To prevent short term power shortages in Bali;

b. To increase supply capacity from Java to Bali;

c. To increase reserve margin in Bali; and

d. To reduce production cost in Bali.

8. Scope of Projects

a. 2 circuits of 150 kV submarine cables @ 100 MW = 4 km route

b. Rock dumping (to provide mechanical protection against strong Seadrift, anchors)

c. 150 kV overhead line in Java and Bali 2 circuits = 10 km route

9. Activities

Activities Implementation

Locations

Project

Implementation Units

a. 2 circuits of 150 kV submarine cables @ 100

MW = 4 km route

b. Rock dumping (to provide mechanical

protection against strong seadrift, anchors)

c. 150 kV overhead line in Java and Bali 2

circuits = 10 km route

East Java and Bali PT PLN (Persero)

Pikitring JBN

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

PT. PLN 55,560 6,170 61,730 Export Credit

Total 55,560 6,170 61,730

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

24,690 37,040 61,730

P-137

GB-ID : GBP3-03-02005-0900-086040

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Java – Bali submarine cable

150 kV circuits 3 & 4

3,086 18,519 39,816 309

Total 3,086 18,519 39,816 309

13. Project References :

BB 2006 - 2009 ID: P3-03-02005-0405-086040

P-138

GB-ID : GBP3-03-02004-0800-09-076129

1. Project Title : Kusan Hydro Electric Power Plant 63 MW

2. Project Type : Project Assistance

3. Executing Agency : State Electricity Company (PT. PLN)

4. Implementing Agency : State Electricity Company (PT. PLN)

5. Duration : 60 months

6. Location : South Kalimantan

7. Objectives

a. To provide peaking generation in South Kalimantan

b. To utilize renewable energy resources

8. Scope of Projects

a. Preparation of Tender Document

b. Procurement of Equipment

c. Engineering, design and Supervision

d. Construction and installation

e. Testing and commissioning

9. Activities

Activities Implementation

Locations

Project Implementation

Units

a. Preparation of Tender Document

b. Procurement of Equipment

c. Engineering, design and Supervision

d. Construction and installation

e. Testing and commissioning

South Kalimantan PT PLN (Persero)

Pikitring Kalimantan

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

PT. PLN 95,500 16,860 112,360 Japan (JICA)

Total 95,500 16,860 112,360

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

11,236 16,854 39,326 33,708 11,236 112,360

P-139

GB-ID : GBP3-03-02004-0800-09-076129

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Kusan – 3 Hydro Power

Plant Project (1x63MW)

7,500 44,700 96,100 700

Total 7,500 44,700 96,100 700

13. Project References :

BB 2006 - 2009 ID: P3-03-02004-0405-076129

P-140

GB-ID : GBP3-03-02006-0900-086041

1. Project Title : Lahendong IV GEOPP (1 x 20 mW)

2. Project Type : Project Assistance

3. Executing Agency : State Electricity Company (PT. PLN)

4. Implementing Agency : State Electricity Company (PT. PLN)

5. Duration : 36 months

6. Location : North Sulawesi

7. Objectives

a. To fulfill electric power requirement in North Sulawesi System;

b. To reduce high production cost; and

c. To anticipate delayed operation of Independent Power Producer (IPP) projects in the area.

8. Scope of Projects

a. Preparation Detail Design and Tender Document for Engineering Procurement, and

Construction (EPC) Contracts;

b. Engineering construction supervision; and

c. Construction

9. Activities

Activities Implementation

Locations Project Implementation Units

a. Preparation Detail Design and Tender

Document for Engineering

Procurement, and Construction (EPC)

Contracts;

b. Engineering construction supervision;

c. Construction

North Sulawesi PT PLN (Persero)

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

PT. PLN 32,730 5,780 38,510 ADB

Total 32,730 5,780 38,510

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

9,000 24,510 15,000 38,510

P-141

GB-ID : GBP3-03-02006-0900-086041

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Construction of Geothermal

Plant

38,510

Total 38,510

13. Project References :

BB 2006 - 2009 ID: P3-03-02006-0405-086041

P-142

GB-ID : GBP3-03-02004-0900-076131-08

1. Project Title : Lombok Steam Coal Power Plant (2x25 MW)

2. Project Type : Project Assistance

3. Executing Agency : State Electricity Company (PT. PLN)

4. Implementing Agency : State Electricity Company (PT. PLN)

5. Duration : 36 months

6. Location : Teluk Endog, West Nusa Tenggara

7. Objectives

a. To meet the increasing demand in Lombok

b. To reduce oil consumption

8. Scope of Projects

a. Engineering Services and Construction Supervision

b. Procurement of Equipment

c. Construction and Installation

9. Activities

Activities Implementation Locations Project Implementation

Units

a. Engineering Services and

Construction Supervision

b. Procurement of Equipment

c. Construction and Installation

Lombok Island PT PLN (Persero)

Pikitring JBN

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

PT. PLN 75,000 7,500 82,500 Korea

(EDCF)

Total 75,000 7,500 82,500

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

18,000 25,500 39,000 82,500

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Lombok Steam Coal Power

Plant (2x25 MW)

4,125 24,750 53,212.5 0,5 412

Total 4,125 24,750 53,212.5 0,5 412

13. Project References :

BB 2006 - 2009 ID: P3-03-02004-0405-076131-08

P-143

GB-ID : GBP3-03-02006-0900-086042

1. Project Title : Muara Tawar Add on Block 2, 3, 4 CCPP (825 - 1200 MW)

2. Project Type : Project Assistance

3. Executing Agency : State Electricity Company (PT. PLN)

4. Implementing Agency : State Electricity Company (PT. PLN)

5. Duration : 30 months

6. Location : Bekasi, West Java Province

7. Objectives

a. To increase capacity of supply by 1200 MW which close the load center in Jakarta

b. To improve the efficiency, reliability and availability of power supply

c. To utilize existing asset (existing GT foundation, auxiliary system/common facilities)

8. Scope of Projects

a. Basic Design

b. Preparation of tender document

c. Procurement of equipment

d. Engineering, design and supervision

e. Construction and installation

f. Testing and commissioning

9. Activities

Activities Implementation Locations Project Implementation

Units

a. Basic Design

b. Preparation of tender document

c. Procurement of equipment

d. Engineering, design and

supervision

e. Construction and installation

f. Testing and commissioning

West Java Province PT PLN (Persero)

Pikitring JBN

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

PT. PLN 850,000 150,000 1,000,000 Export

Credit

Total 850,000 150,000 1,000,000

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

150,000 700,000 150,000 1,000,000

P-144

GB-ID : GBP3-03-02006-0900-086042

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Muara Tawar Power Plant

Construction

50,000 300,000 645,000 5,000

Total 50,000 300,000 645,000 5,000

13. Project References :

BB 2006 - 2009 ID: P3-03-02006-0405-086042

P-145

GB-ID : GBP3-03-02004-0900-066514-08

1. Project Title : Parit Baru Coal Fueled Steam Power Plant (2x50 MW)

2. Project Type : Project Assistance

3. Executing Agency : State Electricity Company (PT. PLN)

4. Implementing Agency : State Electricity Company (PT. PLN)

5. Duration : 36 months

6. Location : Pontianak, West Kalimantan

7. Objectives

a. To meet the increasing demand in West Kalimantan system

b. To strengthen Electric Power System in West Kalimantan system

c. To reduce oil consumption

8. Scope of Projects

a. Engineering services and Construction Supervision

b. Procurement of Equipment

c. Construction and Installation

9. Activities

Activities Implementation

Locations

Project

Implementation Units

a. Engineering services and Construction

Supervision

b. Procurement of Equipment

c. Construction and Installation

West Kalimantan PT. PLN

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

PT. PLN 132,860 23,450 156,310 China

Total 132,860 23,450 156,310

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

36,000 49,310 71,000 156,310

P-146

GB-ID : GBP3-03-02004-0900-066514-08

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Parit Baru Steam Power Plant

construction

7,820 46,920 100,878 782

Total 7,820 46,920 100,878 782

13. Project References :

BB 2006 - 2009 ID: P3-03-02004-0405-066514-08

P-147

GB-ID : GBP3-03-02004-0900-066514

1. Project Title : Rehabilitation and Modernization of Paiton Small Power Producer

(SPP) 1&2 (2x400 MW)

2. Project Type : Project Assistance

3. Executing Agency : State Electricity Company (PT. PLN)

4. Implementing Agency : State Electricity Company (PT. PLN)

5. Duration : 24 months

6. Location : Probolinggo, East Java

7. Objectives

To increase power plant reliability and efficiency

8. Scope of Projects

a. Replacement of turbine blades, diaphragms, packing and turbine peripherals

b. Replacement of boiler pulverizes

c. Machining of turbine outer casing

d. Life time assessment of turbine and generator

9. Activities

Activities Implementation

Locations

Project

Implementation Units

a. Replacement of turbine blades, diaphragms,

packing and turbine peripherals

b. Replacement of boiler pulverizes

c. Machining of turbine outer casing

d. Life time assessment of turbine and generator

Probolinggo,

East Java

PT PLN (Persero)

Pikitring JBN

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

PT. PLN 41,100 7,250 48,350 Export Credit

Total 41,100 7,250 48,350

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

19,340 29,010 48,350

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Power Plant Rehabilitation 2,418 14,505 31,186 242

Total 2,418 14,505 31,186 242

13. Project References :

BB 2006 - 2009 ID: P-03-02004-0405-066514

P-148

GB-ID : GBP3-03-02004-0900-086044

1. Project Title : Rehabilitation and Modernization of Saguling Hydro Electric

Power Plan (HEPP 4 x 178 MW)

2. Project Type : Project Assistance

3. Executing Agency : State Electricity Company (PT. PLN)

4. Implementing Agency : State Electricity Company (PT. PLN)

5. Duration : 24 months

6. Location : Bandung, West Java

7. Objectives

To increase power plant reliability

8. Scope of Projects

a. Replacement of turbine governor

b. Cooling system pipes coating

9. Activities

Activities Implementation

Locations Project Implementation Units

a. Replacement of turbine governor

b. Cooling system pipes coating

Bandung, West

Java

PT PLN (Persero) Pikitring JBN

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

PT. PLN 13,380 2,360 15,740 Export Credit

Total 13,380 2,360 15,740

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

6,296 9,444 15,740

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Rehabilitation and Modernization

of Saguling HEPP

787 4,722 10,152 79

Total 787 4,722 10,152 79

13. Project References :

BB 2006 - 2009 ID: P3-03-02004-0405-086044

P-149

GB-ID : GBP3-03-02004-0900-086045

1. Project Title : Scattered Transmission and Sub-Station in Indonesia

2. Project Type : Project Assistance

3. Executing Agency : State Electricity Company (PT. PLN)

4. Implementing Agency : State Electricity Company

5. Duration : 36 months

6. Location : West Java Province

7. Objectives

a. To meet the high growth of electricity demand in Indonesia

b. To increase reliability of supply in Indonesia

c. To increase the electricity efficiency

d. To reduce the consumption by replacing of fueled power plants with supply from the grid

e. To build 275 kV backbone in the Sumatera power system

8. Scope of Projects

World Bank:

a. Sumatera

1) GI 275/150 kV Lahat 500 MVA

2) GI 275/150 kV Lubuk Linggau 250 MVA

3) GI 275/150 kV Bangko 250 MVA

4) GI 275/150 kV Muara Bungo 250 MVA

5) GI 275/150 kV Kiliranjao 250 MVA

b. Jawa-Bali

1) IBT 500/150 kV Cibatu 500 MVA (Extension)

2) IBT 500/150 kV Depok 500 MVA (Extension)

3) IBT 500/150 kV Pedan 500 MVA (Extension)

4) IBT 500/150 kV Balaraja 500 MVA (Extension)

Export Credit

a. Sumatera

1) T/L 275 kV Payakumbuh – Garuda Sakti, 2 cct

2) T/L 150 kV Pasir Putih – Pangkalan Kerinci, 2 cct

3) T/L 150 kV Pangkalan Kerinci - Rengat, 2 cct

4) T/L 150 kV Rengat - Tembilahan, 2 cct

5) T/L 150 kV Dumai – Bagan Siapi-api, 2 cct

6) GI 275 kV Garuda Sakti 250 MVA

7) GI 275 kV Payakumbuh 500 MVA

8) GI 150 kV Pangkalan Kerinci 30 MVA

9) GI 150 kV Rengat 30 MVA

10) GI 150 kV Tembilahan 30 MVA

11) GI 150 kV Bagan Siapi-api 30 MVA

12) GI 150 kV Ext LB, Pasir Putih, Pangkalan Kerinci, Rengat Dumai

P-150

GB-ID : GBP3-03-02004-0900-086045

b. Jawa-Bali

1) T/L 500 kV Paiton - Grati, 3 rd cct

2) T/L 500 kV Tanjung Jati B – Pedan/Ungaran, 2 cct

3) T/L 500 kV Krian - Tandes, 2 cct

4) IBT 500/150 kV Krian 500 MVA (Extension)

5) GITET 500 kV Tandes dan IBT 500/150 kV 1x500 MVA (New)

9. Activities

Activities Implementation

Locations

Project

Implementation

Units

World Bank:

a. Sumatera

� GI 275/150 kV Lahat 500 MVA

� GI 275/150 kV Lubuk Linggau 250 MVA

� GI 275/150 kV Bangko 250 MVA

� GI 275/150 kV Muara Bungo 250 MVA

� GI 275/150 kV Kiliranjao 250 MVA

Sumatera

PT. PLN

b. Jawa-Bali

� IBT 500/150 kV Cibatu 500 MVA (Extension)

� IBT 500/150 kV Depok 500 MVA (Extension)

� IBT 500/150 kV Pedan 500 MVA (Extension)

� IBT 500/150 kV Balaraja 500 MVA (Extension)

Java – Bali PT. PLN

Export Credit

a. Sumatera

� T/L 275 kV Payakumbuh – Garuda Sakti, 2 cct

� T/L 150 kV Pasir Putih – Pangkalan Kerinci, 2 cct

� T/L 150 kV Pangkalan Kerinci - Rengat, 2 cct

� T/L 150 kV Rengat - Tembilahan, 2 cct

� T/L 150 kV Dumai – Bagan Siapi-api, 2 cct

� GI 275 kV Garuda Sakti 250 MVA

� GI 275 kV Payakumbuh 500 MVA

� GI 150 kV Pangkalan Kerinci 30 MVA

� GI 150 kV Rengat 30 MVA

� GI 150 kV Tembilahan 30 MVA

� GI 150 kV Bagan Siapi-api 30 MVA

� GI 150 kV Ext LB, Pasir Putih, Pangkalan Kerinci,

Rengat Dumai

Sumatera

PT. PLN

P-151

GB-ID : GBP3-03-02004-0900-086045

Activities Implementation

Locations

Project

Implementation

Units

b. Jawa-Bali

� T/L 500 kV Paiton - Grati, 3 rd cct

� T/L 500 kV Tanjung Jati B – Pedan/Ungaran, 2 cct

� T/L 500 kV Krian - Tandes, 2 cct

� IBT 500/150 kV Krian 500 MVA (Extension)

� GITET 500 kV Tandes dan IBT 500/150 kV 1x500

MVA (New)

Java – Bali PT. PLN

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

PT. PLN 500,000 - 500,000 Export Credit

and World

Bank

Total 500,000 - 500,000

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

176,800 295,000 84,000 500,000

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Scattered Transmission and Sub-

Station in Indonesia

27,800 166,700 358,500 2,800

Total 27,800 166,700 358,500 2,800

13. Project References :

BB 2006 - 2009 ID: P3-03-02004-0405-086045

 

P‐152 

 GB‐ID : GBP3‐03‐02004‐0900‐086046 

1. Project Title  :  Sembalun GEOPP, Lombok (2 x 10 MW) 2. Project Type  :  Project Assistance 3. Executing Agency  :  State Electricity Company (PT. PLN) 4. Implementing Agency  :  State Electricity Company (PT. PLN) 5. Duration  :  24 months 6. Location  :  Lombok Island  7. Objectives 

a. To fulfill electricity demand in Lombok  b. To reduce high operation cost in Lombok system 

 8. Scope of Projects  

a. Engineering  design  covering  plant  and  technical  drawings,  design  and  construction  of piping system, generating plant and transmission and  EPC contracts documentation 

b. Production drilling, piping system, generating facilities and transmission     c. Production well drilling d. Construction 

 9. Activities 

Activities Implementation 

Locations Project 

Implementation Units 

a. Engineering design covering plant and technical drawings, design and construction of piping system, generating plant and transmission and  EPC contracts documentation 

b. Production drilling, piping system, generating facilities and transmission     

c. Production Well Drilling d. Construction 

Lombok Island  PT PLN (Persero)  

 10. Funding Source 

Implementing Agency 

Foreign Funding (US $ 000) 

Counterpart Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

PT. PLN  40,460  7,140  47,600  JICA/ ADB/ World Bank 

Total  40,460  7,140  47,600    11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

20,600  27,000        47,600  

P-153

GB-ID : GBP3-03-02004-0900-086046

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Construction of Geothermal

Plant

47,600

Total

13. Project References :

BB 2006 - 2009 ID: P3-03-02004-0405-086046

P-154

GB-ID : GBP3-03-02004-0900-076134-08

1. Project Title : Upper Cisokan Pumped Storage HEPP (1000 MW)

2. Project Type : Project Assistance

3. Executing Agency : State Electricity Company (PT. PLN)

4. Implementing Agency : State Electricity Company

5. Duration : 52 months

6. Location : Cianjur dan Bandung, West Java

7. Objectives

a. To increase capacity of supply in Java – Bali system by 1000 MW

b. To provide a reliable of peaking unit in Java – Bali power system

c. To increase capacity factor of base load unit/steam coal power plants

d. To reduce cost of supply in Java – Bali system

8. Scope of Projects

a. Land Acquisition and Resettlement Action Plan (LARAP)

b. Design review, project review panel & construction supervision

c. Upper an lower dam

d. Waterways, underground PH and spillway

e. Hydraulic pump – turbine & auxiliary equipment

f. Generator – motor & electrical equipment

g. 500 kV transmission line

h. Hydraulic metal works

i. Access road

j. Base camp and facilities

9. Activities

Activities Implementation

Locations

Project

Implementation

Units

•••• LARAP

•••• Design review, project review panel &

construction supervision

•••• Upper an lower dam

•••• Waterways, underground PH and spillway

•••• Hydraulic pump – turbine & auxiliary equipment

•••• Generator – motor & electrical equipment

•••• 500 kV transmission line

•••• Hydraulic metal works

•••• Access road

•••• Base camp and facilities

Cianjur and

Bandung, West

Java

PT PLN (Persero)

Pikitring JBN

P-155

GB-ID : GBP3-03-02004-0900-076134-08

10. Funding Source

Implementing

Agency

Foreign Funding

(US $ 000)

Counterpart Funding

(US $ 000)

Total of Funding

(US $ 000) Remarks

PT. PLN 774,000 73,000 847,000 World

Bank

Total 774,000 73,000 847,000

11. Disbursement Plan

Disbursement Plan (US $ 000)

1st 2nd 3rd 4th 5th Total

84,700 169,400 254,100 254,100 84,700 847,000

12. Funding Allocations

Categories (US $ 000) Detail of Activities

Services Constructions Goods Trainings Others

Total project include study 847,000

Total 847,000

13. Project References :

BB 2006 - 2009 ID: P3-03-02004-0405-076134-08

 

 

      

    

TECHNICAL ASSISTANCE  

 

T ‐ 157 

 

Investment Coordinating Board 

 

 

T ‐ 159 

 GB ID :  GBT1‐02‐06500‐0700‐09‐064008 

1. Project Title  :  Investment Promotion Policy Advisor 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Investment Coordinating Board 

4. Implementing Agency  :  Investment Coordinating Board 

5. Duration  :  48 months 

6. Location  :  DKI Jakarta  7. Objectives 

a. Attracting more investment from overseas.  b. Improving the investment climate 

 8. Scope of Projects  

a. Expert for technical assistant on investment promotion policy. b. Financial support for all the expenses of project 

 9. Activities 

Activities Implementation 

Locations 

Project Implementation 

Units a.  Promoting regional capacity to Japan investors  b.  Improving Indonesia investment climate 

DKI Jakarta  Investment Coordinating Board 

 10. Funding Source 

Implementing Agency 

Foreign Funding (US $ 000) 

Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Investment Coordinating Board 

362  ‐  362  Japan (JICA) 

Total  362  ‐  362    11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

100  100  100  62    362  12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a.  Promoting regional capacity to 

overseas investors 162         

b.  Improving Indonesia investment climate 

200         

Total  362          13. Project References : 

BB 2006 – 2009 ID:T‐02‐06500‐0490‐064008  

 

T ‐ 160 

 GB ID :  GBT1‐05‐09004‐0902‐074058 1. Project Title  :  Strengthening Institution Capacity for Sustainable and Competitive 

Investment Climate 2. Project Type  :  Technical Assistance 3. Executing Agency  :  Investment Coordinating Board 4. Implementing Agency  :  Investment Coordinating Board 5. Duration  :  36 month 6. Location  :  DKI Jakarta  7. Objectives 

To  support  the  Government  of  Indonesia  in  creating  the  sustainable  and  competitive investment climate as mandate on the Investment Law Number 25 Year 2007 with a view to enhancing  the  investment  public  service  and  promotion  on  investment  in  both  local  and central government. 

 8. Scope of Projects  

Enhancing the investment planning capacity in both central and local government through the targeted and integrated promotion and strengthening the investment services. 

 9. Activities 

Activities  Implementation Locations Project Implementation 

Units a.  Strengthening investment services b.  Improving the promotion capacity

Jakarta and regions  Investment Coordinating Board 

 10. Funding Source 

Implementing Agency 

Foreign Funding (US $ 000) 

Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Investment Coordinating Board 

6,843  ‐  6,843  European Union 

Total  6.843    6.843    11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

2,562  2,140.5  2,140.5      6,843  12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services Constructions Goods Trainings  Others a.  Strengthening investment services 250  ‐  50  3,000  121.5 b.  Improving the promotion capacity 250  ‐  50  3,000  121.5 

Total  500  ‐  100  6,000  243.0  13. Project References : 

BB 2006 – 2009 ID: T1‐05‐09004‐0410‐074058 

 

T ‐ 161 

 

National Disaster Management Agency (BNPB) 

 

 

T ‐ 163 

 GB ID :  GBT1‐03‐11200‐0801‐09‐068006 1. Project Title  :  Disaster Information Sharing System for Emergency Response 2. Project Type  :  Technical Assistance 3. Executing Agency  :  National Disaster Management Agency (BNPB) 4. Implementing Agency  :  National Disaster Management Agency 5. Duration  :  6 months 6. Location  :  DKI Jakarta 

 7. Objectives 

To know needs of disaster  information system  for emergency response  in  form a hard ware and software for Crisis Centre in central and provincial level. 

 8. Scope of Projects  

Study for Crisis Centre in central level and Provincial Level (some districts as sampling).  9. Activities 

Activities Implementation 

Locations Project 

Implementation Units Re‐preparation and implementation for study, formulate for the result and recommendation, and reporting 

DKI Jakarta  BNPB 

 10. Funding Source 

Implementing Agency 

Foreign Funding (US $ 000) 

Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

BNPB  450  ‐  450  Japan (JICA) Total  450  ‐  450   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

450          450  12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions  Goods  Trainings  Others Re‐preparation and implementation for study, formulate for the result and recommendation, and reporting 

450         

Total  450          13. Project References : 

BB 2006 – 2009 ID: P‐03‐11200‐0302‐068006 

 

T ‐ 164 

 GB ID :  GBT1‐03‐11200‐0901‐068006 

1. Project Title  :  Disaster Risk Reduction Based Rehabilitation – Reconstruction (DRR‐RR) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  National Disaster Management Agency (BNPB) 

4. Implementing Agency  :  National Disaster Management Agency 

5. Duration  :  36 months 

6. Location  :  National wide 

 7. Objectives 

Strengthen  the  capacity  of GOI  national  and  local  government  agencies  to  coordinate  and implement gender sensitive, pre and post disaster recovery planning processes and practices based on disaster risk reduction principles. 

 8. Scope of Projects  

Rehabilitation  and  reconstruction  (recovery)  planning  takes  place  in  a  way  that  better considers the real needs of any given disaster affected community based on  a. the  pre‐disaster  establishment  of  adequate  information,  recovery  planning  and  needs 

analysis systems; b. pre‐established GOI inter‐agency working relationships to support recovery; and  c. identified underlying development  and governance related causes of disasters.  As  a  part  of  pre‐disaster  recovery  planning  and  post‐disaster  needs  assessments, ways  to counteract underlying causes of disasters must be considered and accounted  for as a part of recovery  programming  so  disaster  risk  reduction  becomes  a  normal  part  of  affected communities governance and development planning processes 

 9. Activities 

Activities Implementation 

Locations Project 

Implementation Units a.  Disaster risk reduction based rehabilitation 

and reconstruction guidelines strengthened, enacted and established 

b.  Institutional systems that support DRR guided recovery (rehabilitation and reconstruction) strengthened and established 

c.  Field application of DRR guided recovery (rehabilitation and reconstruction) practices, methodologies, guidelines and tools with feedback mechanism to the policy framework. 

National wide  BNPB 

 

 

T ‐ 165 

 GB ID :  GBT1‐03‐11200‐0901‐068006 

 10. Funding Source 

Implementing Agency 

Foreign Funding (US $ 000) 

Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

BNPB  1,500  ‐  1,500  UNDP 

Total  1,500  ‐  1,500   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

300  600  600      1,500 

 12. Funding Allocations  

Categories (US $ 000) Detail of Activities 

Services  Constructions  Goods  Trainings  Others 

Coordinate and implement gender sensitive, pre and post disaster 

1,500         

Total  1,500         

 13. Project References : 

BB 2006 – 2009 ID:P‐03‐11200‐0302‐068006 

 

T ‐ 167 

 

Statistics Indonesia Agency (BPS) 

 

 

T ‐ 169 

 GB ID :  GBT1‐06‐05500‐0801‐09‐068482 

1. Project Title  :  Capacity Building on Dissemination and Use of Small Area Statistics for 2010 Population Census in Indonesia 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Statistics Indonesia Agency (BPS) 

4. Implementing Agency  :  Directorate of Census and Survey Methodology Development, Statistics Indonesia Agency 

5. Duration  :  36 months 

6. Location  :  DKI Jakarta  

7. Objectives a. Regional  development  through  effective  planning  and  programs  by  local  governments 

using  reliable  and detailed  statistical data will  be  attained  in  Indonesia, particularly  in remote areas. 

b. Statistical capacity of staffs of central and  local governments, particularly  in eastern part of Indonesia will be improved. 

 

8. Scope of Projects  Development, processing and analysis of small area statistics 

 

9. Activities  Activities  Implementation Locations  Project Implementation Units 

Equipment procurement  DKI  Jakarta   

Training   DKI  Jakarta and other 3 cities 

Workshop  DKI  Jakarta and other 12 cities 

Directorate of Census and Survey Methodology Development 

 

10.  Funding Source 

Implementing Agency Foreign Funding  (US $ 000) 

Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate of Census and Survey Methodology Development 

1,808  ‐  1,808  Japan (JICA) 

Total  1,808  ‐  1,808    

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

902  453  453      1,808 

 

 

T ‐ 170 

 GB ID :  GBT1‐06‐05500‐0801‐09‐068482  

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services Constructions Goods  Trainings  Others 

Equipment procurement      375     

Training        533   

Workshops          900 Total      375  533  900 

  

13. Project References : BB 2006 – 2009 ID: T‐06‐05500‐0101‐068482 

  

 

T ‐ 171 

  

Ministry of Religious Affair 

   

 

T ‐ 173 

 GB ID :  GBT1‐05‐02500‐0801‐09‐061059 

1. Project Title  :  Supporting Islamic Leadership through Islamic Institutions of Higher Education (SILE) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Religious Affair 

4. Implementing Agency  :  Ministry of Religious Affair 

5. Duration  :  36 month 

6. Location  :  IAIN Surabaya, UIN Makassar, IAIN Palembang, IAIN Mataram and IAIN Banjarmasin 

 

7. Objectives The project  is  to  build  the  capacity  of UIN/IAIN  community  outreach  functions with  local communities, as well as the capacity of the Ministry of Religious Affairs (MoRA)  in order to effectively  integrate democratic governance practices and  issues  in their strategies, programs and budgets. a. Outcome 1  is: Civil  society groups  (especially  those  representing and working with  the 

poorest  and most marginalized)  are more  effective  in  enhancing  local  participation  in public  fora  and  in  civic  education  on  issues  related  to  democratic  governance  at  the provincial, district and sub‐district levels.  

b. Outcome  2  is:  UIN/IAINs  are  more  effective  in  developing  and  planning  policies, programs and systems for effective outreach. 

c. Outcome 3: MoRA is more effective in developing, implementing, and monitoring policies and plans,  in consultation with  the UIN/IAINs, particularly  in relation  to  their outreach functions for affected communities 

 8. Scope of Projects  

Capacity building of UIN/IAIN community 

 9. Activities 

Activities Implementation 

Locations Project Implementation 

Units a.  Strengthening democratic governance 

practices at the community level b.  Organizational capacity development c.  Curriculum review and development d.  Internships, scholarships, sabbatical 

programs, exchanges and linkages e.  Research and Dissemination 

IAIN Surabaya, UIN Makassar, IAIN Palembang, IAIN Mataram and IAIN Banjarmasin 

IAIN Surabaya, UIN Makassar, IAIN Palembang, IAIN Mataram and IAIN Banjarmasin 

 

 

 

T ‐ 174 

 GB ID :  GBT1‐05‐02500‐0801‐09‐061059  

10.  Funding Source Implementing 

Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Ministry of Religious Affair 

18,000    18,000  Canada 

Total  18,000    18,000    

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

4,040  8,100  5,860      18,000 

 

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services  Constructions Goods  Trainings  Others 

Project management  900         

Outreach           1,800 

Strengthening of UIN/IAINs        13,500   

Institutional Strengthening MORA 

    1,800     

Total  900    1,800  13,500  1,800  

13. Project References : BB 2006 – 2009 ID:P‐05‐02500‐1008‐061059 

 

 

T ‐ 175 

 

Ministry of Home Affairs 

 

T ‐ 177 

 GB ID :  GBT1‐03‐05502‐0901‐076095 

1. Project Title  :  Aceh Government Transition Programme (AGTP) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Home Affair 

4. Implementing Agency  :  a.  MOHA b.  Nanggroe Aceh Darussalam (NAD) Government  c.  Ministry of National Development Planning/National 

Development Planning Agency (BAPPENAS) 

5. Duration  :  48 months 

6. Location  :  Nanggroe Aceh Darussalam 

 

7. Objectives To  support  the newly elected provincial government  lead and  coordinate ongoing  recovery efforts across the province in NAD 

 

8. Scope of Projects  AGTP  is  designed  to  address  critical  gaps  in  the  Aceh  government’s  policy‐making  and technical  capacity. The  first gap  lies  in  the  executive’s  capacity  to  coordinate  the  transition. The  second  gap  lies  in  the  technical  capacity  of  the  provincial  and  district  government agencies  to  process  assets  and  projects  transferred  from  BRR,  and  to  implement  ongoing recovery  work.  The  third  gap  is  the  administration’s  broader  institutional  capacity  to coordinate and implement reconstruction and rehabilitation work beyond the transition. 

 

9. Activities 

Activities Implementation 

Locations Project 

Implementation Units a.  Enchanced capacity of the Provincial 

Executive. NAD  UNDP 

b.  Enhanced operational capacity of key provincial government agencies. 

MOHA, Local Government of NAD, and Bappenas 

c.  Enhanced capacity of the provincial Training and Human Resources Body. 

MOHA and Pemda NAD 

d.   Monitoring, reporting and auditing.  

NAD and Jakarta 

UNDP, MoHA & Government of NAD  

 

 

 

T ‐ 178 

 GB ID :  GBT1‐03‐05502‐0901‐076095  

10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

a.  MOHA  600  ‐  600 

b.  Bappenas  50  ‐  50 

c.  Local Government of NAD 

6,000  ‐  6,000 

d.  UNDP  6,350  ‐  6,350 

UNDP 

Total  13,000.00  ‐  13,000.00    

11. Disbursement Plan  Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

3,000  5,000  3,000  2,000    13,000  

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services 

Constructions 

Goods  Trainings  Others 

a.  Enchanced capacity of the Provincial Executive. 

2,300 ‐ 1,100 600  400 

b.  Enhanced operational capacity of key provincial government agencies. 

1,600 ‐ 1,000 1,000  400 

c.  Enhanced capacity of the provincial Training and Human Resources Body.

1,350 ‐ 800 800  300 

d.  Project monitoring, reporting and auditing. 

600 ‐ 300 300  150 

Total  5,850  ‐ 3,200  2,700  1,250  

13. Project References : BB 2006 – 2009 ID: T1‐03‐05502‐0490‐076095 

 

T ‐ 179 

 GB ID :  GBT1‐03‐05502‐0902‐076095 

1. Project Title  :  Disaster Risk Reduction in Development (DRR – A) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Home Affair 

4. Implementing Agency  :  a.  Ministry of Home Affair b.  Local Government of Nanggroe Aceh Darussalam (NAD)  

5. Duration  :  42 months 

6. Location  :  Nanggroe Aceh Darussalam 

 7. Objectives 

This project is aiming at making disaster risk reduction as normal part of development process established in core functions of Aceh’s local government and their public and private partners especially in Aceh’s local community where the most effective and direct actions can be taken to reduce physical, economic, and social vulnerability to disasters. Specifically the objectives of project are following : a. Local Government Agencies of Aceh apply knowledge of development/disaster  linkage 

and incorporate DRR, mitigation and preparedness in local community planning process, development, disaster recovery and reconstruction throughout Aceh. 

b. TDMRC‐UNSYIAH strengthen and integrated in Aceh’s DRR processes as key provincial provider of DRR product, services and knowledge (multi‐hazard risk assessments, maps, analysis and DRR methodologies) for local government Agencies and other users of Aceh. 

 8. Scope of Projects  

A  “Culture of  Safety”  and  “Disaster Mitigation Know‐How”  established  among  the people and  institution  of  Aceh,  through  on‐going  DRR  Public  Awareness  programmes  and  by making DRR a part of all existing Teaching and Education Courses and Curricula 

 9. Activities  

Activities Implementation 

Locations 

Project Implementation 

Units a.  Output 1 :Institutional arrangement and enabling 

environment established to facilitate participatory and concerted implementation of DRR measures 

b.  Output 2: Demonstration of gender sensitive projects implemented in selected locations to test and improve measures for reducing risk from natural disasters 

NAD   Local  Government of NAD 

 

 

T ‐ 180 

 GB ID :  GBT1‐03‐05502‐0902‐076095 

 

Activities Implementation 

Locations 

Project Implementation 

Units c.  Output 3: TDMRC‐UNSYIAH strengthened to 

provide science‐based information, service and knowledge assistance to the local government and other DRR proponents in implementing their DRR activities. 

d.  Output 4: DRR public awareness programmes implemented to promote a gender sensitive “Culture of Safety” among the people and  institutions of Aceh

e.  Output 5 : Project effectively and efficiently managed, monitored, evaluated, and audited. 

   

 10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Ministry of Home Affair  600    600 

NAD Government  3,700    3,700 

TDMRC UNSYIAH  4,800    4,800 

UNDP  900    900 

UNDP 

Total  10,000    10,000   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

1,700  4,300  4,000      10,000 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services Construc ‐tions 

Goods  Trainings  Others 

a.  Output 1 :Institutional arrangement and enabling environment established to facilitate participatory and concerted implementation of DRR measures 

400  0  70  250  35 

 

 

T ‐ 181 

 GB ID :  GBT1‐03‐05502‐0902‐076095 

 Categories (US $ 000) 

Detail of Activities Services 

Construc ‐tions 

Goods  Trainings  Others 

b.  Output 2: Demonstration of gender sensitive projects implemented in selected locations to test and improve measures for reducing risk from natural disasters 

250  0  40  90  50 

c.  Output 3: TDMRC‐UNSYIAH strengthened to provide science‐based information, service and knowledge assistance to the local government and other DRR proponents in implementing their DRR activities. 

1,200  0  300  3650  300 

d.  Output 4: DRR public awareness programmes implemented to promote a gender sensitive “Culture of Safety” among the people and  institutions of Aceh. 

800  0  330  1,000  385 

e.  Output 5 : Project effectively and efficiently managed, monitored, evaluated, and audited. 

650  0  40  70  90 

Total  3,300  0  780  5,060  860  

13. Project References : BB 2006 – 2009 ID: T1‐03‐05502‐0490‐076095 

 

 

T ‐ 182 

 GB ID :  GBT1‐01‐05502‐0902‐073091 

1. Project Title  :  PNPM Green Kecamatan Development Program 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Home Affair 

4. Implementing Agency  :  Directorate General of Community Development, Ministry of Home Affair 

5. Duration  :  36 months 

6. Location  :  10 Selected Province  

7. Objectives a. Mainstreaming natural resources management issues into PNPM – Rural  b. Increasing  environmental  awareness  and  related management  capacity  of  communities 

and government stake‐holders c. Disbursing  block  grants  to  fund  investments  in  ‘green’  project  at  the  kabupaten  and 

kecamatan level  

8. Scope of Projects  a. Community grant b. Technical Assistance for community 

 

9. Activities  

Activities Implementation 

Locations Project Implementation 

Units a.  Block grants for micro hydro 

power (MHP) schemes b.  Block grants for natural resources 

management (NRM) and/or renewable energy (RE) projects 

c.  Technical Assistance (consultants, facilitators, workshops, etc) 

Selected Provinces  Directorate General of Community Development 

 

10.  Funding Source Implementing 

Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General of Community Development 

9,000  ‐  9,000  Danida (Trust Fund PSF) 

Total  9,000  ‐  9,000    

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

3,000  3,000 3,000    9,000 

 

T ‐ 183 

 GB ID :  GBT1‐01‐05502‐0902‐073091  

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services  Constructions Goods  Trainings  Others 

a. Expert and Support Staff Service 

3,000     

b. Non‐personal Direct Cost   200 300   

c. Maintenance and Development 

  5,500     

Total  3,000  5,500  200  300   

 13. Project References : 

BB 2006 – 2009 ID: T1‐01‐05502‐0402‐073091 

 

 

T ‐ 184 

 GB ID :  GBT1‐03‐05502‐0903‐076095 

1. Project Title  :  Nias Island Transition Programme (NITP) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Home Affair 

4. Implementing Agency  :  Ministry of Home Affair 

5. Duration  :  36 months 

6. Location  :  Nias Island 

 

7. Objectives To efficient and effective recover island of Nias. 

 

8. Scope of Projects a. Completion of  the  transition processes  from BRR  to  local government especially  for  the 

key agencies at provincial and district  levels are  implemented  in a  timely, efficient and transparent 

b. Local  Government  with  the  support  of  civil  society  resolve  priority  activities  for  the rehabilitation and reconstruction after the transition process 

c. Integration  efforts  Disaster  Risk  Reduction  into  development  activities  in  the  future conducted  by  the  Regional  Government,  including  the  recovery  and  reconstruction process 

d. The project is managed, monitored, evaluated and audited effectively and efficiently  

9. Activities  

Activities Implementation 

Locations Project Implementation 

Units 

Increasing the capacity of district government for ensuring the recovery process and manage the various local government responsibilities 

Nias Island  Ministry of Home Affairs 

 

10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Ministry of Home Affairs 3,890  ‐  3,890  UNDP 

Total  3,890  ‐  3,890    

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

1,600  1,200  1,090      3,890  

 

T ‐ 185 

 GB ID :  GBT1‐03‐05502‐0903‐076095 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a.  Transition Support  400         b.  Local Government and 

Civil Society Capacity Building 

750      700   

c.  Disaster Risk Reduction 600  300  100     d.  Project Management  600         e.  Miscellaneous          440 

Total  2,350  300  100  700  440  

13. Project References : BB 2006 – 2009 ID: T1‐03‐05502‐0490‐076095 

 

T ‐ 187 

 

Ministry of Forestry 

 

 

T ‐ 189 

 GB ID :   

1. Project Title  :  Forestry Sector Climate Change Related Program (Reducing   Emission from Deforestation and Degradation (REDD)) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Forestry 

4. Implementing Agency  :  Secretariat General, Ministry of Forestry 

5. Duration  :  84 months 

6. Location  :  DKI  Jakarta  and  4  (four)  representative  provinces  in  regionalSumatera, Kalimantan, Sulawesi, Bali and Nusa Tenggara 

 

7. Objectives Government agencies, local communities, civil society and private sector implement improved institutional and regulatory framework, approaches, methodologies, and services to promote conservation and sustainable development and  reduction of greenhouse gas emissions  from deforestation and forest degradation in selected districts. 

 

8. Scope of Projects  The  Programme  is  supporting  the  implementation  of  the Ministry’s  Strategic  Plan  and  is meant to focus on measures for reducing greenhouse gas emissions in the forest area. Based on the  future orientation  towards programmed  formation,  the  Indonesian government  is  to be given support for implementing avoids deforestation. The priority areas of the fund would be to: a. National  forest  sector  reform  improves  institutional and  regulatory  framework  towards 

the implementation of sustainable forest management including REDD. b. Framework  and  capacities  for  the  implementation  of  forest  sector  reform with  specific 

regard  to  reducing greenhouse gas emissions  from deforestation and  forest degradation improved and implemented in selected districts. 

c. Government  agencies,  local  communities,  civil  society  and private  sector use  improved institutional framework and mechanism for the effective conservation and management of natural  resources  as  well  as  for  livelihood  improvement  of  poor,  forest  dependent communities in selected districts. 

 

9. Activities  

Activities Implementation 

Locations Project 

Implementation Units a.  Consulted the strategic plan 2010‐2014 with all 

key stakeholders and refers to policies, strategies and measures to reduce greenhouse gas emissions in the forest sector. 

b.  Implemented regulatory and institutional framework for REDD in coordination with other donors. 

DKI Jakarta  Ministry of Forestry 

 

 

T ‐ 190 

 GB ID :    

Activities Implementation 

Locations Project 

Implementation Units c.  Establishment of operational Forest Management 

Units (FMU) for implementation of Sustainable Forest Management (SFM) at least in three sites. 

d.  Harmonize land use plan e.  To create benefit from REDD demonstration 

activities and related incentive mechanisms to local communities in selected districts. 

DKI Jakarta  Ministry of Forestry 

 

10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Secretariat General of Ministry of Forestry 

30,000  3,000  33,000  Germany 

Total  30,000  3,000  33,000    

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th  6th  7th Total 

5,500  6,000  6,000  5,000  5,000  3,500  2,000  33,000 

 

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services  Constructions Goods  Trainings  Others 

a.  NPMU Implementation 800         b.  DPMU Implementation 2,700         c.  Consultancy  3,000         d.  Monitoring          2,800 e.  Demo Activities    16,400       f.  Physical Contingencies          2,500 g.  Financial Contingencies         1,800 h.  Miscellaneous           3000 

Total  6,500  16,400      10,100  

13. Project References : BB 2006 – 2009 ID:T1‐04‐02904‐0503‐075013 

 

 

T ‐ 191 

 

Ministry of Marine Affairs and Fisheries 

 

T ‐ 193 

 GB ID :  GBT1‐04‐03205‐0900‐075014 

1. Project Title  :  Arafuru and Timor Seas Ecosystem Action Programme (ATSEA) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Marine Affairs and Fisheries 

4. Implementing Agency  :  Agency for Marine and Fisheries Research (AMFR), Ministry of Marine Affairs and Fisheries Indonesia 

5. Duration  :  48 months 

6. Location  :  Arafuru and Timor Seas  

7. Objectives To ensure  the  integrated, cooperative, sustainable, ecosystem‐based management and use of the  living  coastal  and marine  resources,  including  fisheries  and biodiversity of  the Arafura and Timor Seas region,  through  the  formulation and  intergovernmental adoption and  initial implementation  of  a  Regional  Strategic  Action  Programme  (SAP)  and  Nation  Action Programme (NAPs) 

 

8. Scope of Projects  a. Component  1: 

Undertake  trans‐boundary Diagnostic Analysis  (TDA)  study  in  the Arafura  and Timor Seas. 

b. Component 2: Development of SAP in relation to NAP containing prioritized national efforts 

c. Component 3: Initial implementation of some SAP and NAP components. 

d. Component 4: Regional  cooperation  through development  of  a  formal mechanism  in management  of Marine  and  Fisheries  Resources  and  strengthen  ATSEF  as  an    effective  regional mechanism for the cooperative ecosystem based management of the Arafura and Timor Seas Regions 

e. Component 5: Sustainable  self‐financing  mechanism  through  development  of  regional  self‐financing mechanism 

f. Component 6: Effective Project Coordination and Management 

 

9. Activities 

Activities Implementation 

Locations Project 

Implementation Units a.  Component 1: 

Undertake trans‐boundary Diagnostic Analysis (TDA) study in the Arafura and Timor Seas. 

b.  Component 2: Development of SAP in relation to NAP containing prioritized national efforts  

Arafuru and Timor Seas 

AMFR 

 

T ‐ 194 

 GB ID :  GBT1‐04‐03205‐0900‐075014 

 

Activities Implementation 

Locations Project 

Implementation Units c.  Component 3: 

Initial implementation of some SAP and NAP components.  

d.  Component 4: Regional cooperation through development of a formal mechanism in management of Marine and Fisheries Resources and strengthen ATSEF as an  effective regional mechanism for the cooperative ecosystem based management of the Arafura and Timor Seas Regions 

e.  Component 5: Sustainable self‐financing mechanism through development of regional self‐financing mechanism 

f.  Component 6: Effective Project Coordination and Management 

   

 10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Ministry of Marine Affairs and Fisheries Indonesia 

6,350  2,348  8,698  UNDP 

Total  6,350  2,348  8,698    11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

2,000  2,000  2,698  2,000    8,698  12. Funding Allocations  

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others Capacity building for ministry of Marine Affair and Fisheries 

8,698         

Total  8,698          

13. Project References : BB 2006 – 2009 ID: T1‐04‐03205‐0504‐075014 

 

T ‐ 195 

 GB ID :  GBT1‐04‐03200‐0700‐08‐09‐065115 

1. Project Title  :  Assistance for SMEs in Fish and Shrimp Industry 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Marine Affairs and Fisheries 

4. Implementing Agency  :  Directorate General for Fish Processing and Marketing, Ministry of Marine Affairs and Fisheries 

5. Duration  :  12 months 

6. Location  :  East Java, North Sumatera, Lampung, South Sulawesi, East Kalimantan, and Papua  

 

7. Objectives a. To develop, produce, sale of marketing acceptable fishermen products to increase fisheries 

income. b. To address problem on most fishermen who are living under the poverty line. c. Promoting  to  develop,  produce,  sale  of  valuable  fisheries  products  taken  account  of 

market needs.  

8. Scope of Projects  a. Providing  facilities  of  production  chains  of  the  small‐ medium  fisheries  enterprises  in 

satisfying  requirements  of  international  standard,  such  as  cold  storage,  packaging, labeling; 

b. Setting‐up business incubator in production base areas. c. Building facilities and infrastructure of the business incubator for fisheries products. d. Setting up  information networking among SMEs and between SMEs and other  relevant 

agencies, private sectors, industries and academics  e. Developing production clusters of SMEs in given areas; f. Capacity building for fisheries business development:  

1) increase SME knowledge on standard quality and safety requirements 2) increase SME capacity to promote their products 3) encourage  technical  and  facilitate  financial  support  for  clustering  small  scale 

processor activities to ensure long term viability. 4) strengthen the abilities of Indonesia’s small – medium scale fishermen and enterprises 

in helping them to broaden and to improve their human resources  

9. Activities 

Activities Implementation 

Locations Project 

Implementation Units a.  Facility/equipment installation b.  Capacity building c.  Research and surveying d.  Institutional strengthening e.  Fisheries infrastructure for monitoring, 

controlling & surveillance 

East Java, North Sumatera, Lampung, South Sulawesi, East Kalimantan, Papua 

Directorate  General for Fish Processing and Marketing    

 

T ‐ 196 

 GB ID :  GBT1‐04‐03200‐0700‐08‐09‐065115 

 10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General for Fish Processing and Marketing 

3,500  34  3,534  Japan (JICA) 

Total  3,500  34  3,534   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

3,534          3,534 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others 

Training and Expert  700      200   

Equipment and other    900  1,500    234 

Total  700  900  1500  200  234 

 13. Project References : 

BB 2006 – 2009 ID: T‐04‐03200‐0403‐065115 

 

T ‐ 197 

 GB ID :  GBT1‐04‐03200‐0901‐065124 

1. Project Title  :  Capacity Building in Fisheries and Aquaculture 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Marine Affairs and Fisheries 

4. Implementing Agency  :  Ministry of Marine Affairs and Fisheries 

5. Duration  :  12 months 

6. Location  :  DKI Jakarta, Bali  

7. Objectives a. To build competence  in  the  fields of  fisheries management  (including stock assessment) 

and aquaculture aiming at sustainable development of Indonesian marine resources b. To  facilitate  the  implementation  of  specific  capacity  building  activities  in  fisheries 

management and aquaculture within the indicated time frame and within the budget  

8. Scope of Projects  In order to achieve the above mentioned objectives, the activities of the project will be focused on the following: a. Setting  forth  the  terms  and  procedures  for  ʹCapacity  Building  in  Fisheries  and 

Aquacultureʹ  b. Extending the existing or including new Programme elements within the Programme, as 

well as on reallocating funds within the Programme.  9. Activities 

Activities Implementation 

Locations Project Implementation Units 

a.  Training in bioacoustics  Bali  Marine Observation Research Center (BROK) 

b.  Participation in survey  DKI Jakarta  Secretary General c.  Scientific Survey d.  Development and validation of 

numerical models 

Bali  BROK 

e.  Recording of catch landings  Secretary General and Dir. Gen. Capture Fisheries 

f.  Workshop in fisheries management 

Secretary General and Dir. Gen. Capture Fisheries, Marine and Fisheries Research Agency 

g.  Marine culture development h.  National health program 

Dir. Gen. Aquaculture 

i.  Aquaculture seminars 

DKI Jakarta 

Dir. Gen. Aquaculture & Secretary General 

 

T ‐ 198 

 GB ID :  GBT1‐04‐03200‐0901‐065124 

 

Activities Implementation 

Locations Project Implementation Units 

j.  Master Studies Overseas k.  Short term courses in 

Indonesia 

Secretary General & Marine and Fisheries Human Resources Development Agency 

l.  Study tours   Secretary General m.  Project coordination and 

auditing Secretary General and Inspectorate General 

n.  Project steering committee 

DKI Jakarta 

Secretary General 

 10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Ministry of Marine Affairs and Fisheries 

770  ‐  770  Norway 

Total  770  ‐  770   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

770          770 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a.  Training in bioacoustics       25   b.  Scientific Survey          97 c.  Development and 

validation of numerical models 

        18 

d.  Recording of catch landings 

        22 

e.  Workshop in fisheries management 

      61   

f.  Marine culture development 

        130 

 

 

T ‐ 199 

 GB ID :  GBT1‐04‐03200‐0901‐065124 

 Categories (US $ 000) 

Detail of Activities Services  Constructions Goods  Trainings  Others 

g.  National health program 

        47 

h.  Aquaculture seminars        47   i.  Master Studies         183   

j.  Short term courses        30   

k.  Overseas Study        25   l.  Project coordination 

and auditing         35 

m.  Project steering committee 

        35 

n.  Miscellaneous          15 

Total        371  399 

 13. Project References : BB 2006 – 2009 ID: P‐04‐03200‐0403‐065124 

 

T ‐ 200 

 GB ID :  GBT1‐04‐03200‐0700‐08‐09‐065117 

1. Project Title  :  Sustainable Indonesia Fisheries Product Competitiveness 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Marine Affairs and Fisheries 

4. Implementing Agency  :  Directorate  General  of  Fish  Processing  and Marketing, Ministry  of Marine Affairs and Fisheries 

5. Duration  :  24 months 

6. Location  :  East Java, North Sulawesi, Lampung, Southeast Sulawesi, North Maluku, Papua 

 7. Objectives 

a. To strengthen National Centre of Quality in responsible for the development of National Fisheries Safety policy 

b. To  design  sustainable  Indonesia  fisheries  product  competitiveness  for  implementing suitable fisheries management 

c. To improve the standard required by consumers and standard of food safety in particular in the international market. 

 8. Scope of Projects  

a. Plan formulation in developing sustainable Indonesia fisheries product competitiveness. b. Site selection and commodities selection for sustainable fisheries product competitiveness c. Development infrastructure for ensuring the effectiveness of monitoring, controlling and 

surveillance of sustainable fisheries management d. Infrastructure  development  for  post‐harvesting  in  monitoring,  testing  and  controlling 

fisheries product safety and quality e. Collaboration  and  consultation  with  research  institutes  and  academic  bodies  for 

promotion and information network for responsible management  9. Activities 

Activities Implementation 

Locations Project 

Implementation Units a.  Plan formulation; 

b.  Site selection and commodities selection for sustainable fisheries product competitiveness:

c.  Developing infrastructure;  

d.  Infrastructure development  for post‐harvesting in monitoring, testing and  

East Java, North Sulawesi, Lampung, Southeast Sulawesi, North Maluku, Papua 

Directorate General of Fish Processing and Marketing 

 

 

T ‐ 201 

 

GB ID :  GBT1‐04‐03200‐0700‐08‐09‐065117 

 

Activities Implementation 

Locations Project 

Implementation Units e.  Collaboration and consultation with research 

institutes and academic bodies  East Java, North Sulawesi, Lampung, Southeast Sulawesi, North Maluku, Papua 

Directorate General of Fish Processing and Marketing 

 10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General of Fish Processing and Marketing 

3,400  34  3,434  Japan (JICA) 

Total  3,400  34  3,434   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

1,534  1,900        3,434 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a.  Training  400         b.  Counterpart  700         c.  Equipment    500  1,000     d.  Expert          200 e.  Training in Japan           f.  Others        234  400 

Total  1,100  500  1,000  234  600 

 13. Project References : 

BB 2006 – 2009 ID: T‐04‐03200‐0403‐065117 

 

 

T ‐ 202 

 GB ID :  GBT1‐04‐03200‐0901‐065109 

1. Project Title  :  Value Capture Fisheries 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Marine Affairs and Fisheries 

4. Implementing Agency  :  a.  Agency for Marine and Fisheries Human Resources Development, 

b.  Directorate General of Capture Fisheries, and c.  Directorate General of Marketing and Fisheries Processing, 

Ministry of Marine Affairs and Fisheries 

5. Duration  :  24 months 

6. Location  :  DKI Jakarta 

 7. Objectives 

Development on marine and  fisheries human  resources development  to  support  infestation prolongation  

 8. Scope of Projects  

Human  resources  development  and  establishment  of  Centre  of  Excellent  that  follows  the International Standard for the sustainable fisheries to maintain quality and health insurance of fisheries products.  Scope and component of the project activity is divided into 5 phases  a. Phase 1: The Introductions 

In  this phase, every partner  / side will provide detail explanation related  to  the  training program  to  the  participants.  At  the  end  of  the  phase,  training  program  that  will  be conducted is every program that are approved by all participants.  

b. Phase 2: Orientation visit and Benchmarking visit c. Phase 3: Training for Lecturer of Jakarta Fisheries University and Harbour Officials 

The  training  is  about  the  fish  capture method,  fishing  gear  to maintain  the  fish  stock, trainings on fish capture and handling method, and captured fisheries freshness.  

d. Phase 4: Practice ( 1 January – 31 December 2010) In this phase, lecturers that are join the training expected to develop curriculum / syllabus of the study that will be implemented in Jakarta Fisheries University.  

e. Phase 5: Establishment of Centre of Excellence Centre of Excellence will  established  and become  an  institution known  in national  and international on the field of fisheries product processing and fisheries quality. 

 

T ‐ 203 

 GB ID :  GBT1‐04‐03200‐0901‐065109 

 9. Activities 

Activities Implementation 

Locations Project Implementation 

Units a.  The introduction b.  Orientation visit and Benchmarking visit c.  Training for Lecturer of Jakarta Fisheries 

University and Harbor Officials d.  Practice e.  Establishment of Centre of Excellence 

DKI Jakarta  Agency for Marine and Fisheries Human Resources Development, Directorate General of Capture Fisheries, and Directorate General of Marketing and Fisheries Processing, 

 10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Ministry of Marine Affairs and Fisheries 

733  183  916  Netherlands 

Total  733  183  916   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

300  616        916 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a.  Result I: Project Inception      20  150   b.  Result II: Orientation visit 

and Benchmarking visit       175   

c.  Result 3 : Training Framework 

    30  200   

d.  Result 4: Implementation Phase 

    25  180   

e.  Result 5: Centre of Excellent 

    36  100   

Total      111  805   

 13. Project References : 

BB 2006 – 2009 ID: T‐04‐03200‐0403‐065109 

 

T ‐ 205 

 

Ministry of Finance 

 

T ‐ 207 

 GB‐ID : GBT1‐06‐01500‐0901‐064144 

1. Project Title  :  Capacity Building of Regulatory Compliance and Human Resources for the Capital Market 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Finance 

4. Implementing Agency  :  Indonesia Capital Market and Financial Institution Supervisory Agency (Bapepam‐LK) 

5. Duration  :  24 months 

6. Location  :  DKI Jakarta 

 7. Objectives 

a. To increase the financial and operational autonomy of Bapepam‐LK further changes to the regulatory framework and capacity building; 

b. To raise Indonesia’s growth rate and enhancing the economy’s resilience; c. To  create more  demands  and  supplies  for  capital market  products  and  in  developing 

securitized market to enhance market liquidity; d. To reduce  the risk of Non‐Bank Financial  Institutions being used as conduits  for money 

laundering,  regulations,  supervision  (capacity, enforcement powers, and  sanctions), and capacity for compliance need to be strengthened to achieve parity with the banking sector. In this regard, adequate enforcement capacity; 

e. To protect investors in the event of broker default.  

8. Scope of Projects  The  capital markets  regulatory authority, Bapepam‐LK has  sought  the  expert  support  for  a number of key activities  identified for the next medium‐term action plan. Likewise, requests have  been made  by  PT  SMF  (for mortgage  insurance),  Finance Companies  and Guarantee Bureau, and General Insurance Association of Indonesia for their respective key medium‐term initiatives.  The  medium‐term  initiatives  were  identified  and  developed  through  intense discussions and consultations the stakeholders. This program will also provide  focused  support  for  the  implementation of  selected  reforms under the Program 

 9. Activities 

Activities Implementation 

Locations Project Implementation 

Units a.  Consultants b.  Equipment c.  Training, Seminars, and Conferences d.  Miscellaneous Administration and 

Support Costs e.  Office Facilities f.  Contingencies 

DKI Jakarta  Bapepam‐LK 

 

T ‐ 208 

 GB‐ID : GBT1‐06‐01500‐0901‐064144 

 10. Funding Source 

Implementing Agency Foreign Funding

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Bapepam‐LK  1,000  ‐  1,000  ADB 

Total  1,000  ‐  1,000   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

500  500        1,000 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a.  Consultants  515         b.  Equipment      5     c.  Training, Seminars, and 

Conferences       85   

d.  Miscellaneous Administration and Support Costs 

        15 

e.  Office Facilities      50    250 f.  Contingencies          80 

Total  515    55  85  345 

 13. Project References : 

BB 2006 – 2009 ID: T‐06‐01500‐0101‐064144 

 

T ‐ 209 

 GB‐ID : GBT1‐06‐01500‐0902‐064144 

1. Project Title  :  Fostering Knowledge Partnership to Strengthen Indonesiaʹs Financial Early Warning System 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Finance 

4. Implementing Agency  :  Fiscal Policy Office, Ministry of Finance 

5. Duration  :  24 months 

6. Location  :  DKI Jakarta 

 7. Objectives 

a. To develop a blueprint for a comprehensive financial early warning system (EWS) b. To Improve economic monitoring and policy response system c. To  improve  macroeconomic  and  financial  stability  once  the  blueprint  has  been  fully 

implementated  

8. Scope of Projects  a. Blueprint for a comprehensive EWS developed b. Strengthened and customized EWS c. Ministry of finance staff operating the enhanced EWS independently d. Strengthened regional partnerships on EWS 

 9. Activities 

Activities Implementation 

Locations Project 

Implementation Units a.  Consultants b.  Training, seminars, and conference 

DKI Jakarta  Fiscal Policy Office 

 10. Funding Source 

Implementing Agency Foreign Funding

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Fiscal Policy Office, Ministry of Finance 

500  ‐  500  ADB 

Total  500  ‐  500   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

250  250        500 

 

 

T ‐ 210 

 GB ID :  GBT1‐06‐01500‐0902‐064144 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a.  Consultants  388         b.  Training, seminars, and 

conference       37   

c.  Miscellaneous Administration and Supporting Costs 

        25 

d.  Others (Contingencies)          50 

Total  388      37  75 

 13. Project References : 

BB 2006 – 2009 ID: T‐06‐01500‐0101‐064144 

 

T ‐ 211 

 GB‐ID : GBT1‐06‐01500‐0903‐064144 

1. Project Title  :  Support for Local Government Finance and Governance Reform (LGFGR) II 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Finance 

4. Implementing Agency  :  a.  Directorate General Fiscal Balance, Ministry of Finance (MOF) b.  Ministry of National Development Planning/National 

Development Planning Agency (BAPPENAS) 

5. Duration  :  24 months 

6. Location  :  DKI Jakarta 

 7. Objectives 

a. to  support  the  government  in  building  institutional  capacity  in  the  development  and implementation of a medium‐term reform agenda  in regional government financing and governance;  

b. to  facilitate  the  achievement  of delivery  targets  and  commitments  of  the  Second Local Government Finance and Governance Reform (LGFGR 2) policy matrix. 

 

8. Scope of Projects  Regional autonomy, financing, governance, service delivery, and capacity development 

 9. Activities 

Activities Implementation 

Locations 

Project Implementation 

Units a.  Extending the NAPFD to 2010 – 2014.  Bappenas b.  Designing and implementing a system of 

forward estimates for intergovernmental transfers and shared revenues. 

c.  Developing and disseminating new regulations and guidelines for the specific allocation fund 

d.  Developing and implementing a targeted package of incentives and sanctions for selected intergovernmental transfers. 

e.  Supporting the early stages of devolution of the property tax. 

MOF 

f.  Human and systems capacity building in the decentralization locations 

DKI Jakarta 

MOF & Bappenas 

 

 

T ‐ 212 

 GB ID :  GBT1‐06‐01500‐0903‐064144 

 10. Funding Source 

Implementing Agency Foreign Funding

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

MOF & Bappenas  1,000  ‐  1,000  ADB 

Total  1,000  ‐  1,000   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

350  650        1,000 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others 

Technical Assistance  1,000         

Total  1,000         

 13. Project References : 

BB 2006 – 2009 ID: T‐06‐01500‐0101‐064144 

   

 

T ‐ 213 

  

Ministry of Communication and Information Technology  

 

T ‐ 215 

 GB‐ID : GBT1‐03‐05900‐0901‐066187 

1. Project Title  :  Extending Telecommunications in Rural Indonesia 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Communication and Information Technology 

4. Implementing Agency  :  Ministry of Communication and Information Technology 

5. Duration  :  36 months 

6. Location  :  Western Java, Banten, Lampung 

 7. Objectives 

To  establish  pilot  project  deployments  of  Community  Access  Points  (CAP)  in  a  limited number of locations where public access to advanced communication is not currently available or affordable (but telecommunications network access is already in place) 

 8. Scope of Projects  

Provision  of  CAP  facilities  to  222  disadvantaged  rural  district  centers  using  output‐based scheme. A competitive tender will be organized to award a services contract, based on lowest subsidy  bid  received,  to  provide  a  stipulated  number  of  either  directly  administered  or franchised Communication Points across the whole pilot area.  

 9. Activities 

Activities  Implementation Locations  Project Implementation Units 

Provision of CAP facilities 

222 disadvantaged rural district in Western Java, Banten and Lampung 

Directorate for ICT Empowerment, Ministry of Communication and Information Technology 

 10. Funding Source 

Implementing Agency Foreign Funding

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Ministry of Communication and Information Technology 

1,868  273  2,141  World Bank  

Total  1,868  273  2,141   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

749.35  963.45  428.20  ‐  ‐  2,141 

    

 

T ‐ 216 

  GB‐ID : GBT1‐03‐05900‐0901‐066187 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions  Goods  Trainings  Others a.  Development of  CAP in 

Western Java and Banten   638.82       

b.  Development of CAP in Lampung 

  901.27       

c.  Consulting Services  319.25         d.  Incremental Operating Costs          282.70 

Total  319.25  1,539.09      282.70 

 13. Project References : 

BB 2006‐2009 ID : T‐03‐05900‐1005‐066187

 

T ‐ 217 

 

Ministry of Public Works  

 

T ‐ 219 

Agency for Research and Development GB‐ID : GBT1‐04‐05502‐0901‐075087 

1. Project Title  :  Identification of Ecopolis Component in Term of Rethinking Principles of Urban Development in Indonesia 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Public Works 

4. Implementing Agency  :  Agency and Research and Development, Ministry of Public Works 

5. Duration  :  12 months 

6. Location  :  DKI Jakarta 

 

7. Objectives a. To understand the concept of ecopolis both in the academic reference and practical users’ 

perception. b. To develop policies regarding ecopolis based urban development. 

 

8. Scope of Projects  a. Studying various terms and concepts and definition of ecopolis. b. Study  and  coordination  in  developing  policies  regarding  the  implementation  of  the 

ecopolis concept for urban development c. Field observation of ecopolis potential implementation in selected cities in Indonesia. 

 

9. Activities 

Activities  Implementation Locations Project Implementation 

Units a.  Research and development  b.  Design development c.  Building people awareness d.  Evaluation 

DKI Jakarta  Agency and Research and Development 

 

10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Agency and Research and Development 

500  ‐  500  Germany (KfW) 

Total  500  ‐  500   

 

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

500          500 

 

 

T ‐ 220 

 GB‐ID : GBT1‐04‐05502‐0901‐075087  

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services  Constructions  Goods  Trainings  Others 

a.  Research and development  

b.  Design development c.  Building people 

awareness d.  Evaluation 

500         

Total  500         

 

13. Project References : BB 2006‐2009 ID: T1‐04‐05502‐0503‐075087 

 

T ‐ 221 

 GB‐ID : GBT1‐04‐05502‐0902‐075087 

1. Project Title  :  Development of Green Housing Model with Minimizing CO2 Emission as a Control Micro Climate Change 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Public Works 

4. Implementing Agency  :  Agency for Research and Development, Ministry of Public Works 

5. Duration  :  36 months 

6. Location  :  DKI Jakarta 

 

7. Objectives To develop a model of building technology and housing design that promotes sustainability in which ecological, social, and livelihood of setting are matters of consideration. 

 

8. Scope of Projects  a. Identification of domestic activities and perception on housing b. Identification of existing building design and production system through literature study 

and field survey c. Identification  of  existing  housing  compound  design  (accessibility  to  public  facility, 

transportation system, greenery, utility system) d. Analysis  on  CO2  emission  potential  of  existing  building  component  production  and 

housing compound design e. Concept development of green housing design f. Scale‐up residential green building model g. Workshops and seminars h. Standard formulation 

 

9. Activities 

Activities Implementation 

Locations Project Implementation Units 

a.  Consultancy b.  DSA & Transport c.  Laboratory & Construction Worksd.  Equipment Supply e.  Workshop/Seminar f.  Others 

DKI Jakarta  Agency for Research and Development 

 

10.  Funding Source 

Implementing Agency Foreign Funding

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Agency for Research and Development 

500  ‐  500  Germany (KfW) 

Total  500  ‐  500   

 

T ‐ 222 

 GB‐ID : GBT1‐04‐05502‐0902‐075087 

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

230  115  155      500 

 

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services  Constructions  Goods  Trainings  Others 

a.  Consultancy  135         b.  DSA & Transport          90 c.  Laboratory & 

Construction Works   100       

d.  Equipment Supply      100     

e.  Workshop/Seminar        38   

f.  Others          37 

Total  135  100  100  38  127 

 

13. Project References : BB 2006‐2009 ID: T1‐04‐05502‐0503‐075087 

 

T ‐ 223 

Directorate General for Highways GB‐ID : GBT1‐03‐03300‐0700‐09‐066212 1. Project Title  :  Capacity Building for Public‐Private Partnership (PPP) Operation 2. Project Type  :  Technical Assistance 3. Executing Agency  :  Ministry of Public Works 4. Implementing Agency  :  Directorate General for Highways, Ministry of Public Works 5. Duration  :  48 months 6. Location  :  DKI Jakarta  7. Objectives 

The project  is to train government officials of the PPP related  institutions to understand and work on the new scheme. 

 8. Scope of Projects  

Training on: a. Setting up the PPP administration unit in Ministry of Public Works; b. Administrating, monitoring, and controlling the PPP toll road development project; c. Providing necessary support from the Government; d. Monitoring  the  private  actors  (developers  and  investors)  in  terms  of  integrity  and 

compliance; and e. Supervising the financial flows of PPP projects. 

 9. Activities 

Activities  Implementation Locations  Project Implementation Units Trainings  Jakarta  Directorate General of Highways 

 10.  Funding Source 

Implementing Agency Foreign Funding

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General for Highways 

1,.370  ‐  1.370  Japan (JICA) 

Total  1,370  ‐  1,370    11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

300  370  350  350    1,370  12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions  Goods  Trainings  Others Trainings   1,370         

Total  1,370          13. Project References : 

BB 2006‐2009 ID: T‐03‐03300‐0408‐066212 

 

T ‐ 224 

 GB‐ID : GBT1‐03‐03300‐0700‐08‐09‐066210 

1. Project Title  :  Road Policy Advisor 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Public Works 

4. Implementing Agency  :  Directorate General for Highways, Ministry of Public Works 

5. Duration  :  24 months 

6. Location  :  DKI Jakarta 

 7. Objectives 

To  establish and  implement  rational and  efficient  road policy with decentralization process and private sector involvement to be taken into consideration. 

 8. Scope of Projects  

a. To provide advice and/or guidance on road sector issues and to assist formulation of road policy and projects. 

b. To support on‐going studies and projects for their smooth implementation.  9. Activities 

Activities  Implementation Locations  Project Implementation Units Technical Assistance  Jakarta  Directorate General for Highways 

 10.  Funding Source 

Implementing Agency Foreign Funding

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General for Highways 

1,000  ‐  1,000  Japan (JICA) 

Total  1,000  ‐  1,000   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

400  600        1,000  

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services  Constructions  Goods  Trainings  Others 

Development Study  1,000         Total  1,000         

 

13. Project References : BB 2006‐2009 ID: T‐03‐03300‐0408‐066210 

 

T ‐ 225 

Directorate General of Human Settlement GB‐ID : GBT1‐04‐04300‐ 0902‐065586 

1. Project Title  : Capacity Development of 3R and Domestic Solid Waste Management System 

2. Project Type  : Technical Assistance 

3. Executing Agency  : Ministry of Public Works 

4. Implementing Agency  : a.  Directorate General for Human Settlement (DGHS), Ministry of Public Works (MPW) 

b.  Ministry of the Environment 

5. Duration  : 36 months 

6. Location  : Natonal wide 

 

7. Objectives a. To reduce the amount of solid waste as part of the national policy b. To extend the life span of final disposal site c. To reuse recyclable solid waste  d. To help the local economy e. To reduce social problems at final disposal site f. To increase the efficiency of solid waste management g. Improving competency of human resources involved in 3R 

 8. Scope of Projects  

a. Development of national policy on 3R and domestic solid waste management systems b. Capacity Development of MPW and Ministry of the Environment  

9. Activities 

Activities Implementation 

Locations Project 

Implementation Units a.  Develop action plan  Provinces b.  Develop technical guidance  Jakarta c.  Extend networking through coordination with 

local government and socialization to communities 

d.  Train 3R facilitators 

Provinces 

DGHS, MPW and Ministry of the Environment 

 10.  Funding Source 

Implementing Agency Foreign Funding

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

DGHS, MPW and Ministry of the Environment 

8,520  ‐  8,520  Japan (JICA) 

Total  8,520  ‐  8,520   

 

 

T ‐ 226 

 

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

2,000  3,000  3,520      8,520 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others 

Develop action plan, develop technical guidance, extend networking through coordination with local government and socialization to communities, train 3R facilitators 

5,964  

‐  ‐  2,556  

‐ 

Total  5,964      2,556   

 13. Project References : 

BB 2006‐2009 ID: T‐04‐04300‐0504‐065586 

GB‐ID : GBT1‐04‐04300‐ 0902‐065586 

 

T ‐ 227 

 GB‐ID : GBT1‐03‐03300‐0900‐066265 

1. Project Title  :  Flood Management in Selected River Basins, PFR1 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Public Works 

4. Implementing Agency  :  Directorate General of Water Resources, Ministry of Public Works 

5. Duration  :  12 months 

6. Location  :  Ciujung Ciliman, Jratun Seluna, Sampean, Progo Opak Oyo River 

 

7. Objectives The  project  will  prepare  the  proposed  Multitranche  Finance  Facility  (MFF)  for  Flood Management in Selected River Basins (FMSRB) in Indonesia.   

8. Scope of Projects  The overall scope of the assignment will include: (i) preparation of the Sector Roadmap for the MFF; (ii) preparation of the proposed MFF  including the analysis of technical, economic and financial feasibility, and assessment of social and environmental safeguards; (iii) development of detailed activities  to be financed under  the  first  tranche of  the MFF; and  (iv) assisting  the GOI to meet the project readiness criteria for the proposed investment program. The Sector Road Map defines  (i)  the  strategic directions  for  the  sector;  (ii)  its  importance  to growth, poverty reduction, and inclusiveness (or the extent to which it is a binding constraint); and  (iii)  the  list  of  success  factors  for  better  performance.  The  road map  needs  detailed assessments of physical and nonphysical  investments. These assessments highlight  the main investment and non‐investment bottlenecks, risks, and mitigation measures. Such information then informs the strategic context, policy framework, and investment programs, as well as the interventions needed and their sequencing. 

 

9. Activities 

Activities Implementation 

Locations Project Implementation 

Units a.  Detailed review of the reports 

prepared under TA 4159‐INO: Flood Management in Selected River Basins, 

b.  Updating the sector analysis c.  Gathering and collating existing 

information on flooding in Java, conducting stakeholder workshops and meetings 

d.  Identifying and undertaking additional technical, economic, financial, social and environmental safeguard studies, including additional stakeholder consultations 

West Java  Directorate General of Water Resources 

 

 

T ‐ 228 

 GB‐ID : GBT1‐03‐03300‐0900‐066265 

 

Activities Implementation 

Locations Project Implementation 

Units e.  Developing a climate change 

adaptation strategy f.  Preparaion of necessary 

documentation for submission of the proposed MFF 

West Java  Directorate General of Water Resources 

 

10.  Funding Source 

Implementing Agency Foreign Funding

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate  General  of Water Resources 

1,000  200  1,200  ADB 

Total  1,000  200  1,200   

 

11. Disbursement Plan  Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

1,200          1,200 

 

12. Funding Allocations  Categories (US $ 000) 

Detail of Activities Services  Constructions  Goods  Trainings  Others 

Development study  1,200         

Total  1,200         

 

13. Project References : BB 2006‐2009 ID: P‐03‐03300‐0404‐066265 

     

 

T ‐ 229 

 GB‐ID : GBT1‐03‐03306‐0900‐076046 1. Project Title  :  Policy Advisor for Irrigation Management 2. Project Type  :  Technical Assistance 3. Executing Agency  :  Ministry of Public Works 4. Implementing Agency  :  Directorate General for Water Resources, Ministry of Public Works 5. Duration  :  24 months 6. Location  :  National wide  

7. Objectives Dispatch a policy advisor for irrigation management that supports the GOI in establishing the holistic strategy and institutional framework to implement the irrigation policy in Indonesia in a proper manner. 

 

8. Scope of Projects  a. A holistic strategy for the implementation of the new irrigation is drafted b. A master‐plan for irrigation asset management is drafted based on the strategy  c. Implementation program and  institutional  framework are drafted based on  the master‐

plan  d. Capability of the policy implementation of the related Government staff is enhanced 

 9. Activities 

Activities  Implementation Locations  Project Implementation Units Dispatch Advisor  DKI Jakarta  Directorate General for Water 

Resources  10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General for Water Resources 

2,000  ‐  2,000  Japan (JICA) 

Total  2,000  ‐  2,000    11. Disbursement Plan  

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

1,000  1,000        2,000  12. Funding Allocations  

Categories (US $ 000) Detail of Activities 

Services  Constructions  Goods  Trainings  Others Dispatch advisor  2,000         

Total  2,000          13. Project References : 

BB 2006‐2009 ID: T1‐03‐03306‐0403‐076046 

 

T ‐ 230 

Directorate General for Water Resources GB‐ID : T1‐03‐03306‐0900‐076049 

1. Project Title  :  Technical Assistance for Capacity Building in Water Sector 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Public Works 

4. Implementing Agency  :  Directorate General for Water Resources, Ministry of Public Works 

5. Duration  :  12 months 

6. Location  :  DKI Jakarta  

7. Objectives The primary outcome of the project  improved capacity development among water resources sector stakeholder. The  impact of the TA will be to contribute to sustainable management of natural resources in Indonesia 

8. Scope of Projects  a. Regional water resources agency capacity development process strengthening b. Nationwide assessment of capacity building needs in water resources agencies c. Selective  capacity  development  support  activities  to  civil  society  water  resources 

stakeholder  

9. Activities Activities  Implementation Locations  Project Implementation Units 

Trainings Workshops Seminars 

DKI Jakarta  Directorate General for Water Resources 

 

10.  Funding Source 

Implementing Agency Foreign Funding

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General for Water Resources 

850  75  925  ADB 

Total  850  75  925    

11. Disbursement Plan  Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

925          925  

12. Funding Allocations  Categories (US $ 000) 

Detail of Activities Services  Constructions  Goods  Trainings  Others 

Training, Workshop, Seminar 

      925   

Total        925    

13. Project References : BB 2006‐2009 ID: T1‐03‐03306‐0605‐076049 

 

T ‐ 231 

Ministry of National Education 

 

T ‐ 233 

 GB‐ID : GBT1‐05‐02300‐0901‐061528 

1. Project Title  :  Basic Education Sector Programme 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of National Education 

4. Implementing Agency  :  Ministry of National Education 

5. Duration  :  60 months 

6. Location  :  National wide 

 

7. Objectives  a. The overall objective of  the Program  is  to  contribute  to poverty  reduction  in  Indonesia 

through policies and strategies  for  i) equitable access  to high quality basic education;  ii) improved  quality  and  relevance  of  basic  education;  and  iii)  improved  governance  and accountability. An overhancing objective is to help promote policy dialogue, institutional and  organizational  reform  that  underpin  policy  implementation  and  help  reduce provincial and district education performance disparitas 

 

8. Scope of Projects  a. The  program  will  support  Gol  Renstra  2010/14  policies  and  strategies  for  achieving 

education  EFA/MDG’s,  with  a  specific  focus  on  :  (i)  Access  :  construction  of  junior secondary schools; (ii) Governance and Quality : leadership and management training for district  officials  and  school  principals;  and  (iii)  Governance  and  Quality  support  the development of an analytical and capacity development partnership. 

 9. Activities 

Activities Implementation 

Locations Project Implementation Units 

a.  Construction of junior secondary schools  

b.  Leadership and management training 

c.  Support the development of an analytical and capacity development partnership 

National wide  Ministry of National Education 

 

10.  Funding Source Implementing 

Agency Foreign Funding

(US $ 000) Local Funding(US $ 000) 

Total of Funding(US $ 000) 

Remarks 

Ministry of National Education  

655  ‐  655  Australia (AusAid) European Union 

Total  655  ‐  655   

 

 

T ‐ 234 

 GB‐ID : GBT1‐05‐02300‐0901‐061528 

 

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

142.5  163.3  184.7  82.6  81.9  655 

 

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services  Constructions  Goods  Trainings  Others 

Sector budget support           629 Contribution of analytical and capacity development partnership 

      26   

Total        26  629 

 

13. Project References :  BB 2006‐2009 ID: T‐05‐02300‐1006‐061528 

 

T ‐ 235 

 GB‐ID : GBT1‐05‐02304‐0800‐09‐071057 

1. Project Title  :  Enhancement of Global Carbon Sequestration Potential from Indonesian Tropical Forest (Phase II) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of National Education 

4. Implementing Agency  :  Bandung Institute of Technology 

5. Duration  :  6 months 

6. Location  :  National wide 

 

7. Objectives  a. To demonstrate the existing rate and location of deforestation in Indonesia and its impacts 

on climate condition; b. To demonstrate the benefit of carbon sequestration from Indonesian‐wide reforestation on 

lessening the negative impacts of climate change; c. To develop the “blue print” of a reforestation company in which the main business line is 

planning and managing reforestation program; d. To implement the reforestation program in selected priorities regions; e. To extend the implementation of reforestation program to other parts of Indonesia. 

 8. Scope of Projects  

This project is divided into three phases: a. Phase I : Preliminary study b. Phase II : Development of reforestation program an company c. Phase III : Implementation of reforestation program 

 9. Activities  

Activities Implementation 

Locations 

Project Implementation 

Units a. Preparation of solid baseline data for 

benchmarking the achievement of reforestation program with 2007 data as the baseline 

a.  Projection of future carbon sequestration and its impacts on climate variability in Indonesia 

b.  Development of the blue print of the restoration company 

c.  Selection of three priority regions for implementing the reforestation program 

Indonesia Regions  Bandung Institute of Technology and Directorate General of Higher Education 

 

 

T ‐ 236 

 GB‐ID : GBT1‐05‐02304‐0800‐09‐071057 

 

10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General of Higher Education,  Ministry of National 

200  ‐  200  IDB, European Union 

Total  200  ‐  200   

 

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

200          200 

 

12. Funding Allocation Categories (US $ 000) 

Detail of Activities Services  Constructions  Goods  Trainings  Others 

a.  Salary          63 b.  Consumable          29 c.  Transport          66 d.  Additional          42 

Total          200 

 

13. Project References :  BB 2006‐2009 ID: T‐05‐02300‐1006‐071057 

 

 

T ‐ 237 

 GB‐ID : GBT1‐05‐02300‐0901‐061529 

1. Project Title  :  Higher Education Policy Advisor 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of National Education 

4. Implementing Agency  :  Directorate General for Higher Education, Ministry of National Education (DGHE, MONE)  

5. Duration  :  24 months 

6. Location  :  National wide  

7. Objectives  a. To  assist  the DGHE, MONE  in  formulating programs  and projects  to be  carried out  in 

cooperation  with  International  development  agencies,  reflecting  DGHE’s  needs  and policies as well as agencies priorities and approaches 

b. Coordinating  the  implementation of  international  cooperation programs and projects  in higher education 

 8. Scope of Projects  

a. Institutional and capacity building for an International cooperation unit in DGHE b. Development of ICT programs for higher educations institution 

 9. Activities 

Activities  Implementation Locations  Project Implementation Units International expert  DKI Jakarta  DGHE, MONE 

 

10.  Funding Source Implementing 

Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

DGHE, MONE  314  ‐  314  Japan (JICA) Total  314  ‐  314   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

144  170        314  

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services  Constructions  Goods  Trainings  Others 

International expert  314         Total  314         

 13. Project References :  

BB 2006‐2009 ID: T‐05‐02300‐1006‐061529 

 

T ‐ 238 

 GB‐ID : GBT1‐05‐02300‐0700‐09‐061308 

1. Project Title  :  Higher Education Training on Developing Education Content for Mobile Learning 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of National Education 

4. Implementing Agency  :  Directorate General for Higher Education, Ministry of National Education 

5. Duration  :  12 months 

6. Location  :  DKI Jakarta 

 

7. Objectives Gaining the knowledge and skill to develop the contents of remote education by themselves (lecturer)  

8. Scope of Projects  Training on developing education consent for mobile learning 

 

9. Activities Activities  Implementation Locations  Project Implementation Units 

Lecturer and practice  SAGA University  MONE 

 

10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General for Higher Education 

2,000    2,000  Japan (JICA) 

Total  2,000    2,000   

 

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

2,000          2,000 

 

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services  Constructions Goods  Trainings  Others 

Lecturer/Practice Training        2,000   

Total        2,000   

 

13. Project References :         BB 2006‐2009 ID: T‐02‐09000‐0401‐064317 

 

T ‐ 239 

 GB‐ID : GBT1‐05‐02300‐0902‐061529 

1. Project Title  :  Long‐term Training (C/P of PREDICT) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of National Education 

4. Implementing Agency  :  Ministry of National Education 

5. Duration  :  12 months 

6. Location  :  Surabaya, East Java 

 7. Objectives  

To strengthen the ITS research abilities and human resources capability  8. Scope of Projects  

a. Dispatch of international expert b. Training and graduate studies c. Research activity funding 

 9. Activities 

Activities  Implementation Locations Project Implementation Units a.  Dispatch of international 

expert b.  Training and graduate studies c.  Research activity funding 

Surabaya  ITS 

 10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

ITS  215  ‐  215  Japan (JICA) Total  215  ‐  215   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

215          215  12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a.  Dispatch of international expert b.  Training and graduate studies c.  Research activity funding 

215         

Total  215          13. Project References :  

BB 2006‐2009 ID: T‐05‐02300‐1006‐061529 

 

T ‐ 240 

 GB‐ID : GBT1‐05‐02300‐0903‐061529 

1. Project Title  :  Polytechnics Education Development Sector Project 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of National Education 

4. Implementing Agency  :  Directorate General of Higher Education (DGHE) 

5. Duration  :  12 months 

6. Location  :  Jakarta 

 

7. Objectives  To  assist  the Government  in preparing Polytechnics Education Development  Sector Project leading to sustainable economic growth, poverty reduction, and employment on the basis of social and geographical education equity. Outcome of the proposed Project will include: a. Increased  access  to  polytechnic  education  through  expansion  of  selected  existing 

institutions b. Enhanced capacity of selected/existing polytechnics c. Certified programs of polytechnics with international standards d. Greater role for private polytechnics in provisions of relevant training e. Improved quality, efficiency, and relevance of instructions through facility and equipment 

development, and technical teachers and managerial staff development  

8. Scope of Projects  a. Restructuring and modernization of the existing curriculum b. Establishments of polytechnic’s facilities c. Improving the quality of existing staff 

 9. Activities 

Activities Implementation 

Locations 

Project Implementation 

Units a.  Review existing polytechnics education system, 

asses its strength, weaknesses, and opportunity for further development 

b.  Review current employment opportunity of skilled‐level employees in the job market 

c.  Recommend policies and actions for the strengthening of polytechnic education 

d.  Formulate a project design to strengthen polytechnic education 

e.  To undertake consultation with key stakeholder in polytechnic education 

Jakarta  Directorate of General Higher Education 

 

 

T ‐ 241 

 GB‐ID : GBT1‐05‐02300‐0903‐061529  

10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

ADB & DGHE  1,000  ‐  1,000  ADB 

Total  1,000  ‐  1,000   

 

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

1,000  ‐  ‐  ‐  ‐  1,000 

 

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services  Constructions  Goods  Trainings  Others 

TA consultant & management 

850        150 

Total  850        150 

 

13. Project References :  BB 2006‐2009 ID: T‐05‐02300‐1006‐061529 

 

 

T ‐ 243 

 

Ministry of Trade  

 

T ‐ 245 

 GB‐ID : GBT1‐05‐09004‐0901‐074058 

1. Project Title  :  The Project on Service Improvement of NAFED as a Major Trade Promotion Organization in Indonesia 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Trade 

4. Implementing Agency  :  National Agency for Export Development (NAFED) 

5. Duration  :  36 months 

6. Location  :  DKI Jakarta  

7. Objectives To strengthen export development services by NAFED. 

 

8. Scope of Projects  a. Training  courses  on market  intelligence,  product  development,  and  export  promotion 

activities b. Training courses on improving management efficiencies of export promotion organization 

 

9. Activities Activities  Implementation Locations Project Implementation Units 

a.  Export information services b.  Export promotion service c.  Export products developmentd.  Export training service 

DKI Jakarta  NAFED 

 

10. Funding Source 

Implementing Agency Foreign Funding

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

NAFED  3,518  ‐  3,518  Japan (JICA) 

Total  3,518  ‐  3,518    

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

910  1,408  1,200      3,518  

12. Funding Allocation Categories (US $ 000) 

Detail of Activities Services  Constructions  Goods  Trainings  Others 

Capacity building for NAFED  3,518         

Total  3,518          

13. Project References :  BB 2006‐2009 ID: T1‐05‐09004‐0410‐074058 

 

T ‐ 246 

 GB‐ID : GBT1‐05‐09004‐0801‐09‐074058 

1. Project Title  :  Trade and Support Programme II 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Trade 

4. Implementing Agency  :  Ministry of Trade, Ministry of Industry, Ministry of Agriculture, Ministry of Fisheries, BSN, KAN 

5. Duration  :  48 months 

6. Location  :  DKI Jakarta 

 

7. Objectives To facilitate a further integration of Indonesia into the international trade system. The specific objectives of the programme are: to improve coordination and transparency in the process for formulation  and  implementation  of  trade policy;  to upgrade  the  quality  infrastructure  that supports  Indonesia’s  access  to  international  markets,  and  to  strengthen  the  capacity  of Indonesian business associations to promote the internationalization of their members and the openness of the Indonesian economy. 

 

8. Scope of Projects  a. Integrated trade policy b. Export quality infrastructure c. Capacity building of business associations 

 

9. Activities 

Activities Implementation 

Locations 

Project Implementation 

Units 

Integrated trade policy:  Technical assistance to strengthen the capacity of MOT 

and relevant stakeholders to formulate trade policy for improvement of export quality infrastructure 

Support the strengthening of the dialogue between MOT 

TA to support the clarification of roles and responsibilities of different agencies involved in export quality infrastructure 

Ministry of Trade 

Export quality infrastructure:  TA to develop and implementation action plans to 

strengthen the capacity of export quality infrastructure agencies 

TA to facilitate the access of Indonesian SMEs yo up‐to‐date technical conformity assessment and recognized testing and certification 

TA improve the quality of testing laboratories 

DKI Jakarta 

MOT, MOF, MMAF, BSN, KAN 

 

T ‐ 247 

 GB‐ID : GBT1‐05‐09004‐0801‐09‐074058 

 

Activities Implementation 

Locations 

Project Implementation 

Units 

TA to operate and maintain installation of laboratory equipment with accordance to EU trade policy 

Capacity building of Business Associations/Civil society on management and export skills, improvement 

DKI Jakarta   

 

10. Funding Source 

Implementing Agency Foreign Funding

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

MOT, MOF, MMAF, BSN, KAN 20,528  ‐  20,528  European Union 

Total  20,528  ‐  20,528   

 

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

5,000  5,000  5,000  5,528    20,528 

 

12. Funding Allocation Categories (US $ 000) 

Detail of Activities Services  Constructions  Goods  Trainings  Others 

a.  Technical Assistance  12,191         b.  Training Logistic        1,162   c.  Study Tours/International 

Travel       839   

d.  Studies and Publication  387         e.  Monitoring and 

Evaluation 194         

f.  Auditing  194         g.  Equipment       2,324     h.  Operating Cost          452 i.  Information          258 j.  Contingencies          646 

k.  Others           1,162 

Total  13,685    2,324  2,001  2,518 

 

13. Project References :  BB 2006‐2009 ID: T1‐05‐09004‐0410‐074058 

 

T ‐ 249 

 

Ministry of Transportation  

 

T ‐ 251 

Directorate General of Land Transportation GB‐ID : GBT1‐03‐02200‐0800‐09‐066372 

1. Project Title  :  Integrated Public Transportation Master Plan for the Bandung Metropolitan Area 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Transportation 

4. Implementing Agency  :  Directorate General of Land Transportation, Ministry of Transportation  

5. Duration  :  36 months 

6. Location  :  Bandung, West Java Province  

7. Objectives a. To establish of urban transportation policy     b. To formulate public transportation master plan c. To prepare funding schemes for public transportation system development d. To set‐up institutional and to specify the role of each level of government. 

 

8. Scope of Projects a. Review  the  current master  plan,  blue  print,  and  strategic  plan  for  related  institution, 

ministries  etc,  that  responsible  in  land  transportation  sub‐sector  for  Bandung Metropolitan Area. 

b. Review  past  and  recent  studies  that  focused  on  the  Land  Transport  Sub‐Sector Development Plan. 

c. Formulating  a  comprehensive  general  plan  in  central,  regional,  and  local  government level  for harmonizing and  synchronizing  in policy  framework  (as macro plan) and will consist of: 1) Policy framework on Land Transport Development General Plan with synchronizing 

to Mid Term Development Plan of Transportation Sector. 2) Policy framework on safety management for each land transport mode. 

d. Formulating  implementing plan for short term/immediate plan, mid term and  long term development plan for the materialization of the above general plan. 

e. Strategy and program for integrated land transport development plan. f. Project identifications and project screening for immediate, short term, mid term, and long 

term development plan. g. Feasibility study for high priority for sub‐project selected. 

 9. Activities 

Activities Implementation 

Locations Project Implementation Units 

Development study 

Bandung  Directorate General of Land Transportation, Ministry of Transportation 

 

 

T ‐ 252 

 

GB‐ID : GBT1‐03‐02200‐0800‐09‐066372  

10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General for Land  Transportation 

1,000  ‐  1,000  France 

Total  1,000  ‐  1,000    

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

300  300  400      1,000 

 

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services  Constructions Goods  Trainings  Others 

Dev elopement Study  1,000         

Total  1,000          

13. Project References : BB 2006‐2009 ID: T‐03‐02200‐0408‐066372 

 

T ‐ 253 

 GB‐ID : GBT1‐03‐02200‐0700‐08‐09‐066334‐07 

1. Project Title  :  Program for Improvement of Transport System in Medium‐Sized Cities 

2. Project Type  :  Technical Assistance 

3. Executing Agency  : Ministry of Transportation 

4. Implementing Agency :  Directorate General of Land Transportation, Ministry of Transportation 

5. Duration  :  24 months 

6. Location  :  National wide 

 7. Objectives 

a. To establish of urban transportation policy in medium cities     b. To formulate public transportation master plan c. To prepare funding schemes for public transportation system development d. To set‐up institutional and to specify the role of each level of government 

 8. Scope of Projects  

a. Development study b. Training 

 9. Activities 

Activities  Implementation Locations  Project Implementation Units a. Development Study b. Training 

National wide  Directorate General for Land  Transportation 

 10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General for Land  Transportation 

5,000    5,000  Germany (GTZ) 

Total  5,000    5,000    11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

3,000  2,000        5,000  12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a. Development study  4,000         

1) Training        1,000   

Total  4,000      1,000    13. Project References : 

BB 2006‐2009 ID: T‐03‐02200‐0408‐066334‐07 

 

T ‐ 254 

 GB‐ID : GBT1‐03‐02200‐0901‐066344‐07 

1. Project Title  :  Port Security Management Project (Phase II) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Transportation 

4. Implementing Agency  :  Directorate General of Sea Transportation (DGST), Ministry of Transportation  

5. Duration  :  24 months 

6. Location  :  National wide 

 7. Objectives 

1) To assist DGST to make a new regulation in accordance with the amendment of the Shipping Law in which International Ship Port Security (ISPS) will be included. 

2) To give technical transfer to Indonesia Port Administration  

3) Plan‐Do‐See System including Port Facility Security Assessment (PFSA) and Port Facility Security Plan (PFSP) to Indonesian Port Administration. 

4) To examine curriculums of systematic and integrated training for DGST, PELINDO, and local government staff in charge 

5) To assist DGST to renew PFSPs. 

 8. Scope of Projects  

a. Enforcement of Port Security System and Administration body b. Enhance Plan‐Do‐See System including Port Facility Security Assessment (PFSA) and Port 

facility Security Plan (PFSP) c. Revision the curriculums of Trainings for DGST, PELINDO, and local government staff in 

charge  9. Activities 

Activities  Implementation Locations  Project Implementation Units 

Development Study  National wide  Directorate General of Sea Transportation 

 

10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General of Sea Transportation 

9,500  ‐  9,500  Japan (JICA) 

Total  9,500  ‐  9,500    

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

4,750  4,750        9,500 

 

T ‐ 255 

 GB‐ID : GBT1‐03‐02200‐0901‐066344‐07 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others 

Consulting services  8,500      1,000   

Total  8,500      1,000   

 13. Project References : 

BB 2006‐2009 ID: P1‐03‐02200‐0408‐066344‐07    

 

 

T ‐ 256 

 GB‐ID : GBT1‐03‐02200‐0700‐08‐09‐066342 

1. Project Title  :  Strengthening Maritime Safety and Security Especially for Anti Piracy and Anti Maritime Terrorism 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Transportation 

4. Implementing Agency :  Directorate General of Sea Transportation, Ministry of Transportation  

5. Duration  :  24 months 

6. Location  :  National Wide  

7. Objectives a. To ensure maritime security especially in the Strait of Malacca. b. To reduce the number of pirate attack against ships in Indonesia territorial waters. c. To provide a system to prevent piracy armed robbery, and maritime terrorism. d. To provide equipments and facilities of 11 public ports facilities to comply ISPS Code 

 

8. Scope of Projects  Preliminary Report, Intermediate Report, Interim Draft Final Report, and Final Report 

 

9. Activities 

Activities  Implementation Locations  Project Implementation Units Development Study  National Wide  Directorate General of Sea Transportation 

 

10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General of Sea Transportation 

440  ‐  440  Japan (JICA) 

Total  440  ‐  440    

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

220  220        440  

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services  Constructions Goods  Trainings  Others 

Consulting Services  440      Total  440         

 

13. Project References : BB 2006‐2009 ID: T‐03‐02200‐0408‐066342 

 

 

T ‐ 257 

Directorate General of Civil Aviation GB‐ID : GBT1‐03‐02200‐0801‐09‐066355 

1. Project Title  :  Introduction of New CNS/ATM System 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Transportations 

4. Implementing Agency  :  Directorate General of Civil Aviation, Ministry of Transportations 

5. Duration  :  12 months 

6. Location  :  Central Office Jakarta 

 7. Objectives 

To  assist  Directorate  General  of  Civil  Aviation  (DGAT)  in  implementing  New Communications, Navigation Surveillance/Air Traffic Management (CNS/ATM) System based on International Civil Aviation Organization (ICAO) Standard. 

 8. Scope of Projects  

Expert in DGAT to help in the area of CNS/ATM 

 9. Activities 

Activities  Implementation Locations  Project Implementation Units 

Expertise  Jakarta  DGAT 

 10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

DGAT  200  ‐  200  Japan (JICA) 

Total  200  ‐  200   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

200          200 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others 

Expertise  200         

Total  200         

 13. Project References : 

BB 2006 ‐ 2009 ID: T‐03‐02200‐0408‐066355 

 

T ‐ 258 

 GB‐ID : GBT1‐03‐02205‐0901‐076070 

1. Project Title  :   Project for Improvement on Aviation Safety Policy  

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of  Transportation 

4. Implementing Agency  :  Directorate General of Civil Aviation (DGCA) To collaborate with National Transportation Safety Commission (NTSC) 

5. Duration  :  60  months 

6. Location  :  DKI Jakarta 

 7. Objectives 

To improve Aviation Safety in Indonesia 

 8. Scope of Projects  

To improve a. Aviation Safety and Security regulation complying with ICAO standard b. SMS for ATS and Airport operation c. Enforcement of Human Resource Development for new CNS/ATM d. Implementation of new CNS/ATM project  e. Investigation skill of aircraft accident investigations f. Aircraft Accident Investigation reports 

 9. Activities 

Activities  Implementation Locations Project Implementation Units 

Technical Assistance 

Jakarta  Directorate General of Civil Aviation (DGCA) to collaborate with National Transportation Safety Commission (NTSC) 

 10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

DGCA & NTSC  3,300  ‐  3,300  Japan (JICA) 

Total  3,300  ‐  3,300   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

600  700  700  700  600  3,300 

 

 

T ‐ 259 

 GB‐ID : GBT1‐03‐02205‐0901‐076070 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others 

Development study  3,300         

Total  3,300         

 13. Project References : 

BB 2006 ‐ 2009 ID: T1‐03‐02205‐0408‐076070 

 

T ‐ 260 

 GB‐ID : GBT1‐03‐02200‐0801‐09‐066529 

1. Project Title  :  Project for Strengthening Capacity on Ensuring Safe and Efficient Aircraft Operations 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Transportations 

4. Implementing Agency  :  Directorate General of Civil Aviation, Ministry of Transportation 

5. Duration  :  24 months 

6. Location  :  Jakarta  

7. Objectives To enforce supervision capacity for ensuring safety of air carrier operation. 

 

8. Scope of Projects  a. Expertise b. Seminar/Workshop 

 

9. Activities 

Activities  Implementation Locations  Project Implementation Units 

a.  Expertise b.  Seminar/Workshop 

Jakarta  National Transportation Safety Committee 

 

10. Funding Source 

Implementing Agency Foreign Funding

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

National Transportation Safety Committee 

721  ‐  721  Japan (JICA) 

Total  721  ‐  721    

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

300  421        721  

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services  Constructions Goods  Trainings  Others 

a.  Expertise  350         b.  Seminar/Workshop  371         

Total  721          

13. Project References : BB 2006 ‐ 2009 ID: T‐03‐02200‐0408‐066529 

 

T ‐ 261 

Directorate General of Railways GB‐ID : GBT1‐03‐02200‐0700‐08‐09‐066364 

1. Project Title  :  Bandung Urban Railway Transport Development, Electrification Padalarang ‐ Cicalengka Line (Phase I: Engineering Services) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Transportation 

4. Implementing Agency  :  Directorate General of Railways, Ministry of Transportation 

5. Duration  :  24 months 

6. Location  :  Bandung‐Cicalengka Line 

 7. Objectives 

a. To  enhance  the  quality  of  urban/commuter  railway  services  in  Padalarang Cicalengka line,  while  improving  the  connectivity/accessibility  of  intercity  train  services  from/to Bandung. 

b. To reduce  the environmental  impacts or pollutions due  to emmisions  from  the roads as well  as  current  operations  of  rail‐vehicles  through  electrification  of  the  Padalarang  ‐ Cicalengka line. 

c. To  support  the  conservation/saving  the  use  of  non‐renewable  energy  by  the  use  of electricity in Bandung urban/commuter railway operation. 

 8. Scope of Projects  

a. Detail Engineering Design of Construction  b. Tender Assistance. 

 9. Activities 

Activities Implementation 

Locations Project 

Implementation Units a. Detail Engineering Design of Construction   Bandung b.  Tender Assistance  DKI Jakarta 

Directorate General of Railways 

 10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General of Railways 

10,000  1,500  11,500  France 

Total  10,000  1,500  11,500   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

7,245  4,255        11,500 

 

 

T ‐ 262 

 GB‐ID : GBT1‐03‐02200‐0700‐08‐09‐066364 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a.  Detail Engineering Design 

of Construction  9,775 

       

b.  Tender Assistance  1,725         

Total  11,500         

 13. Project References : 

BB 2006‐2009 ID: P‐03‐02200‐0408‐066364 

   

 

T ‐ 263 

Ministry of Industry 

 

T ‐ 265 

 GB‐ID : GBT1‐01‐01900‐0901‐064375‐07 

1. Project Title  :  SME Human Resources Development under Economic Crisis 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Industry 

4. Implementing Agency  :  Agency for Research and Development of Industry, Ministry of Industry 

5. Duration  :  12 months 

6. Location  :  National wide 

7. Objectives a. To  assess  the  current  condition  of  Indonesia  shipbuilding  industries,  and  their 

maintenance and shipbuilding capability throughout the country. b. To assess the current: component supply chain and manufacturing capability. c. To study the possibility of establishing Indonesia Ship Design Center. 

 8. Scope of Projects  

The scope of project is to develop and contribute the SMEs after economic crisis  9. Activities 

Activities Implementation 

Locations Project Implementation Units 

a.  Training for trainers  Center for Education and training, MOI 

b.  In‐Country Training Management and Technology Improvement for SMEs in Indonesia 

Center for R&D under MOI 

c.  Survey on Regional policy measures in 33 provinces 

National wide 

Local Government, Regional Offices for Trade and Industry 

 10.  Funding Source 

Implementing AgencyForeign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Ministry of Industry  11,500  ‐  11,500  Japan (JICA) 

Total  11,500  ‐  11,500   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

11,500          11,500 

 

 

T ‐ 266 

 GB‐ID : GBT1‐01‐01900‐0901‐064375‐07 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others 

Field study & trainings  11,500         

Total  11,500         

 13. Project References : 

BB 2006‐2009 ID: P1‐01‐01900‐0407‐064375‐07 

 

 

T ‐ 267 

 

Ministry of Agriculture  

 

T ‐ 269 

 GB‐ID : GBT1‐05‐01800‐0901‐065405 

1. Project Title  :  Immediate Support for Improving Resilience of Agriculture Based Livelihood and Enhanced Food Security Response in East Nusa Tenggara (NTT) Province 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Agriculture 

4. Implementing Agency  :  a. The Agency for Food Security and Agricultural Extension in NTT Province 

b. Food Security Office, East Sumba District c. Food Security and Agriculture Extension Office in North West 

Sumba 

5. Duration  :  12 months 

6. Location  :  East Nusa Tenggara (NTT) 

 7. Objectives 

Principal Objective:    To improve the resilience of vulnerable households to better withstand shocks that cause food insecurity in key districts of NTT Province, Indonesia. Specific Objective : To mitigate the impacts of multiple shock on food security in NTT Province through support of farm activities and better planning, monitoring and response by farming communities and local authorities. 

 8. Scope of Projects  

a. Livelihoods  –  based  food  security  and  nutrition  analysis  completed  for  seven  targeted most  vulnerable  districts  and  two  high  quality  food  security  and  nutrition  strategies mainstremed into the government planning and budgeting processes of Sumba districts; 

b. at  Least  7.5000  vulnerable  farming  households  engaged  and  supported  in  activities  to improve  resilience  to  factors  that  threaten  food  security, with a  focus on  local seed and crop production, water management, household/post harvest storage. 

 9. Activities 

Activities Implementation 

Locations Project 

Implementation Units a.  Assess the planning and operational 

capacities at district, sub‐district and community levels through a participatory capacity assessment.   

b.  On the basis of the ongoing joint analysis, work with the key actors to develop comprehensive district food security and nutrition strategies which address causes and effects of food and nutrition insecurity as reported in the assessment.  

7  priority  districts  of NTT 

Food Security Agencies 

 

T ‐ 270 

 GB‐ID : GBT1‐05‐01800‐0901‐065405 

 

Activities Implementation 

Locations 

Project Implementation 

Units c.  Undertake a consultation to ensure that the activities 

undertaken under result 2 are well integrated with other complementary activities being undertaken or planned by other actors to maximize impact in support of the goals of the district strategies.  

d.  Work with district government to develop a program for the strategies and integrate this with the relevant 2009 – 10 budget submissions.  

e.  Prepare and implement advocacy messages on the strategy targeting key decision makers at district, province and national level   

f.  Organize donor meetings / conference as appropriate and disseminate funding proposals. 

g.  Support local Farmer Groups through the provision of agriculture inputs appropriate to local conditions to build resilience to food security threats 

h.  Provision of technical assistance to 60 Farmer Groups (1,500 HH) with high quality composite maize for seed production to support provincial government efforts to increase food production 

i.  Provide training to Farmer Facilitators (extension agents, community leaders, local teachers, progressive farmers, etc.) to support local Farmer Groups’ implementation of strategies and response that build resilience to food security threats, appropriate to local conditions, constraints and opportunities. 

j.  Provide training to Farmer Groups in organization/administration skills and simple book keeping, development of business/activity plans, as well as technical training on plant production (vegetables and banana); water and soil management; maize seed production; silos management and the concept of community disaster preparedness.in each of the two target districts 

k.  Implement impact monitoring and evaluation methods, tools and techniques and conduct preliminary (before support) and final (after support) assessment to identify the most efficient and effective innovations and initiatives, and document lessons learned and recommendations for follow‐up action in the NTT Province 

7 priority districts of NTT 

Food Security Agencies 

 

 

T ‐ 271 

 GB‐ID : GBT1‐05‐01800‐0901‐065405 

 10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Food Security Agencies  785   785 FAO 

Total  785   785  

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

785         785 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others 

a. Salaries Profesional  21         

b. Consultants  185         

c. Contracts  138         

d. Locally Contracted Labour   3         

e. Travel and DSA        74   

f. Expendable Procurement      228     

g. Non‐Expendale Procurement 

    15     

h. Technical Support Services  22         

i. General Operating Expenses 39         

j. Visibility cost          9 

k. Indirect Cost (max 7%)          51 

Total  408    243  74  60 

 13. Project References : 

BB 2006‐2009 ID: T‐05‐01800‐0403‐065405 

 

 

T ‐ 272 

 GB‐ID : GBT1‐05‐01800‐0801‐09‐065405 

1. Project Title  :  Improvement of Countermeasure on the Productive Diseases of Dairy Cattle 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Agriculture 

4. Implementing Agency  :  Directorate General of Livestock Services, Ministry of Agriculture 

5. Duration  :  24 months 

6. Location  :  West Java 

 7. Objectives 

a. Improvement  the  technology  of  veterinary  practice  and  dairy  farming  management system through the application for the small scale dairy farmers 

b. Implementation the training programs for veterinary practice of local veterinary as well as paravet practitioner from dairy cooperative and extension workers for dairy farming 

c. Dissemination  of  the  veterinary  practice  technology  and  dairy  farming  management through  the  on‐farming  training  by  collaboration with  local  dairy  cooperative  training activities with self management system for the future operation 

 8. Scope of Projects  

a. Training b. Capacity Building c. Dissemination 

 9. Activities 

Activities Implementation 

Locations Project 

Implementation Units a.  Formulate the training program for veterinary 

practice and dairy farming management according to need survey of dairy farming problems; 

b.  Support the implementation of veterinary practice for dairy farming and dairy farming management; 

c.  Support to disseminate the veterinary practice technology and skill for dairy farming and dairy farming management by on‐farm training in the collaboration  with the local dairy cooperative  

West Java  Directorate General of Livestock Services, Ministry of Agriculture 

 

 

T ‐ 273 

 GB‐ID : GBT1‐05‐01800‐0801‐09‐065405 

 10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General of Processing and Marketing for Agricultural Product 

800  ‐  800  Japan (JICA) 

Total  800  ‐  800   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

400  400        800 

 12. Funding Allocations  

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others 

Capacity Building, trainings, and dissemination 

     800   

Total        800   

 13. Project References : 

BB 2006‐2009 ID: T‐05‐01800‐0403‐065405 

 

 

T ‐ 274 

 GB‐ID : T‐04‐01800‐0701‐09‐065535 

1. Project Title  :  Livestock Development Policy Advisor 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Agriculture 

4. Implementing Agency  :  Directorate General for Livestock Services, Ministry of Agriculture 

5. Duration  :  6  months 

6. Location  :  DKI Jakarta 

 7. Objectives 

a. Obtaining  data  and  information  as  a  source  of    national  breeding  system  formulation under decentralization era 

b. Learning a modern breeding technique that possibly applied in Indonesia c. Comparing the implementation of breeding policy Indonesia with other countries 

 8. Scope of Projects  

 Study to overseas about livestock development  9. Activities 

Activities  Implementation Locations  Project Implementation Units Study and trainings overseas  Overseas  Secretariat, DGLS 

 10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General for Livestock Services 

300    300  Japan (JICA) 

Total  300    300    11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

300          300  12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others Study and training overseas        300   

Total        300    13. Project References : 

BB 2006‐2009 ID: T‐04‐01800‐0403‐065535 

 

T ‐ 275 

 GB‐ID : GBT1‐04‐01800‐0900‐065534‐07 

1. Project Title  :  Standardization and Quality Control for Horticulture Production of Indonesia 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Agriculture 

4. Implementing Agency  :  Directorate General for Horticulture, Ministry of Agriculture 

5. Duration  :  24 months 

6. Location  :  West and East Java 

 7. Objectives 

a. To  strengthen  implementation  for  fruit  flies  control  in  Indonesia  to meet  international standard 

b. To  improve  and  strengthen  capacity  building  in  order  to  reduce  pre  and  post  harvest losses. 

 8. Scope of Projects  

a. Implementation for fruit flies control in Indonesia b. Improving and strengthening capacity building  in order  to reduce pre and post harvest 

losses  9. Activities 

Activities Implementation 

Locations Project 

Implementation Units a.  Identification of location and project socialization b.  Field Survey c.  Study on eco‐biology of fruit flies on mango d.  Laboratory equipment and   supplies e.  Fruit fly control f.  Dispatch Experts g.  Monitoring and evaluation h.  After care 

West and East Java 

Directorate General for Horticulture,  Ministry of  Agriculture 

 10.  Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate General for Horticulture 

2,600    2,600  Japan (JICA) 

Total  2,600    2,600   

 

 

T ‐ 276 

 

GB‐ID : GBT1‐04‐01800‐0900‐065534‐07 

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

800  1,800        2,600 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a.  Capacity Building        1,400   b.  Laboratory equipment      500     c.  Dispatch Experts  600         d.  Monitoring and evaluation 

after care         100 

Total  600    500  1,400  100 

 13. Project References : 

BB 2006‐2009 ID: T1‐04‐01800‐0403‐065534‐07 

  

 

T ‐ 277 

 GB‐ID : GBT1‐04‐01800‐ 0901‐065420 

1. Project Title  :  Strategy for Improving the Rice Post Harvest System in Indonesia 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Agriculture 

4. Implementing Agency  :  Directorate General for Livestock Service, Ministry of Agriculture 

5. Duration  :  24 months  

6. Location  :  Jakarta  

7. Objectives To support achievement of increasing national rice availability by 2.0 million tones/annum in 2009  and  achieving  comparable  additional  increases  in  subsequent  years  which  will  be accomplished  through  increasing  the  efficiency  of  the  rice  post  harvest  sector,  involving operations such as handling, drying, storage and processing, as well as capacity building of the key actors i.e. farmers and extension worker, in the post harvest sector  

8. Scope of Projects  a. To indentify and analyse main factor of post harvest losses b. To  build  capacity  of  extension  workers,  famers,  traders  and  millers  in  post  harvest 

management  of  the  rice  sector  through  training programmes, development  of  resource material, and creation of an awarness, creation campaign.  

c. TO  revie,  test  and  validate  improved  rice  post  harvest  technologies with  farmers  and extensions workers. 

d. To prepare project document for a medium‐term programme on sustainable post harvest actions that will scale‐up and replicate the activities of the current TCP 

 

9. Activities 

Activities  Implementation Locations Project 

Implementation Units a.  Consultant   b.  Contracts  c.  Travel d.  Training e.  Expendable equipment f.  Non Expendable equipment g.  Technical support Services 

Directorate General of Product Processing and Marketing 

Jakarta 

 

10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

DG of product Processing and Marketing  

429  429  FAO 

Total  429    429   

  

 

T ‐ 278 

 GB‐ID : GBT1‐04‐01800‐ 0901‐065420 

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

200  229   429 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a.  Consultant    100    b.  Capacity building  250   c.  Others     79 

Total  100 250  79 

 13. Project References : 

BB 2006‐2009 ID: T‐04‐01800‐0403‐065420 

 

T ‐ 279 

 

Commission for Supervision of Business Competition 

 

 

T ‐ 281 

 GB‐ID : GBT1‐02‐11400‐0901‐062446 

1. Project Title  :  Project for Competition Policy (Phase II) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Commission for Supervision of Business Competition (KPPU) 

4. Implementing Agency  :  Commission for Supervision of Business Competition 

5. Duration  :  36 months 

6. Location  :  DKI Jakarta  

7. Objectives Enhancement of the implementing of competition law and policy 

 

8. Scope of Projects  a. Training b. Seminar/Workshop c. Internship d. Research 

 

9. Activities 

Activities Implementation 

Locations Project 

Implementation Units a.  Development of Competition Policy And Law. 

The activities will be based on  KPPU’s activities  in developing the competition  law and producing guidelines to support the enactment of Law No.5/1999.  

b.  Capacity Building of  KPPU Within this activity, the main goal is to develop the human resources of KPPU in implement the law. The activities also done inline with stakeholders of KPPU; 

1) Advance Level Training  

2) General Training 

3) Daily Training 

4) In Country Training 

5) Internship. 

6) Postgraduate Scholarship 

c.  New Issues Studies  

1) Research  

2) Dissemination 

DKI Jakarta  KPPU 

 

 

T ‐ 282 

 GB‐ID : GBT1‐02‐11400‐0901‐062446 

 10. Funding Source 

Implementing Agency 

Foreign Funding (US $ 000) 

Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

KPPU  3,850    3,850  Japan (JICA) 

Total  3,850    3,850   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

1,500  1,350  1,000      3,850 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others Capacity building         3,850   

Total        3,850   

 13. Project References : 

BB 2006 – 2009 ID: T‐02‐11400‐0401‐062446  

  

 

T ‐ 283 

 

Indonesian Institute of Sciences 

 

T ‐ 285 

 GB‐ID : GBT1‐04‐07900‐0800‐09‐065452 

1. Project Title  :  Establishing Research Laboratory for Energy, Environment, and Natural Substances 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Indonesian Institute of Sciences (LIPI) 

4. Implementing Agency  :  Research Center for Chemistry, Indonesian Institute of Science  

5. Duration  :  12 months 

6. Location  :  Serpong, Tangerang 

 7. Objectives 

Collecting  information  about  sustainable‐energy‐related  research  program  and  Indonesian potential resources by serial scientific method and analyzing the data for being very valuable based  information  in  order  to  determining  research  priority  in  sustainable  energy development. 

 8. Scope of Projects  

The scope of this project will relate to collecting these following data: a. Existing energy source that had already developed in Indonesia b. Existing research result and on going research for potential energy source that available in 

Indonesia and level of technology acceptance to local society and local environment if this potential energy source was used. 

c. Existing  research  result  and on going  research  in developing  energy  source utility  and sustainability  in  Indonesia  and  level  of  technology  acceptance  of  the  results  to  local society and local environment. 

d. Opinion  and  suggestion  from  researcher  in  Indonesia  for  research  priorities  in  energy resource development 

e. Global trend in energy resource development  9. Activities 

Activities  Implementation Locations Project Implementation 

Units a. Collecting data from National 

and International publications Research Centre for Chemistry LIPI.Puspiptek Serpong 

Research Centre for Chemistry LIPI. Puspiptek Serpong 

b. Survey and Interview  Surabaya, Jakarta, Jawa barat, Riau, Palembang, Medan, Banjarmasin, Palangkaraya Manado, Kupang 

Research Centre for Chemistry LIPI. Puspiptek 

 

 

T ‐ 286 

 GB‐ID : GBT1‐04‐07900‐0800‐09‐065452 

 10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

LIPI  3,000  14  3,014  Korea (KOICA) 

Total  3,000  14  3,014    

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

3,014          3,014  

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services  Constructions Goods  Trainings  Others 

a.  Collecting data from National and International publications 

500         

b.  Human Resource Development  

      1.014   

c.  Survey and Interview  1,000         d.  Analyzing data   500         

Total   3,000          

13. Project References : BB 2006‐2009 ID: T‐04‐07900‐0403‐065452 

 

 

T ‐ 287 

 

Ministry of Cooperatives and Small and Medium Enterprises 

 

T ‐ 289 

 GB‐ID : GBT1‐02‐04000‐0901‐064458 

1. Project Title  : Sustainable SMEs Growth through Improved Services and Competitiveness 

2. Project Type  : Technical Assistance 

3. Executing Agency  : Ministry of Cooperatives and Small and Medium Enterprises  

4. Implementing Agency  : Ministry of Cooperatives and Small and Medium Enterprises  

5. Duration  : 24 months 

6. Location  : DKI Jakarta 

 7. Objectives 

a. Improving the capacity of independent Business Development Services – Providers (BDS‐Ps)  private  sector  to  provide  accessible,  quality,  and  sustainable  services  to  Small  and Medium Enterprise (SMEs), according to SMEs’ needs and market changes 

b. Increasing  SMEs’  capacity  in  producing  eco‐friendly  products  (clean  products), particularly  through practicing  energy  efficient principles  (clean  technologies) and high awareness for any environmental impacts 

c. Improving  the competitiveness of SMEs’ products and services  through  implementation of quality management system that supports efficency and productivity. 

 8. Scope of Projects  

a. Identifying  potential  BDS‐Ps  in  selected  provinces,  and  selecting  potential  SMEs  to participate in the quality management system and clean product technology programs.  

b. Disseminating information regarding the importance of quality management system and clean product technology through seminars, workshop and printed materials. 

c. Reviewing, mapping and standardizing the criteria and competency of BDS‐Ps and their services 

d. Training  of  trainers  for  BDS  consultants,  quality  management  system  training,  clean product technology 

e. Monitoring,  evaluation,  knowledge  transfer,  and  strengthening  relevant  institution  for possible replication as well as for ensuring the sustainability of the initiatives and benefits. 

 9. Activities 

Activities  Implementation Locations  Project Implementation Units 

Capacity  building  of BDS for SMEs 

DKI Jakarta  Ministry of Cooperatives and Small and Medium Enterprises 

 

 

T ‐ 290 

 GB‐ID : GBT1‐02‐04000‐0901‐064458  10. Funding Source 

Implementing Agency 

Foreign Funding(US $ 000) 

Counterpart Funding(US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Ministry of Cooperatives and Small and Medium Enterprises 

2,520  ‐  2,520  Germany (KfW) 

Total  2,520  ‐  2,520    

11. Disbursement Plan 

Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

1,000  1,520        2,520  

12. Funding Allocations` 

Categories (US $ 000) Detail of Activities 

Services Construct‐

ions Goods  Trainings  Others 

a. Capacity building of BDS for SMEs 

1,500      1,020   

Total  1,500      1,020    

13. Project References : BB 2006 ‐ 2009 ID: T‐02‐04000‐0401‐064458 

 

 

T ‐ 291 

 

Ministry of Environment 

 

T ‐ 293 

 GB‐ID : GBT1‐04‐04300‐0901‐065586 

1. Project Title  :  Indonesian Training Course for Co‐Benefits Approach 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Environment 

4. Implementing Agency  :  Ministry of Environment 

5. Duration  :  36 months 

6. Location  :  Banjarmasin (South Kalimantan) and Palembang (South Sumatera) 

 

7. Objectives To develop knowledge and skill related  to Co‐benefit approach of Ministry of Environment (MoE) and local government staffs. 

 

8. Scope of Projects  Training on co‐benefits approach for government officials 

  

9. Activities 

Activities  Implementation Locations Project Implementation 

Units 

Training Course  Ministry of Environment  Ministry of Environment  

10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Ministry of Environment 

359  ‐  359  Japan (JICA) 

Total  359  ‐  359    

11. Disbursement Plan Disbursement Plan (US $ 000) 

1st  2nd  3rd  4th  5th Total 

110  120  129      359  

12. Funding Allocations Categories (US $ 000) 

Detail of Activities Services  Constructions Goods  Trainings  Others 

Training Course  359   

Total  359    

13. Project References : BB 2006‐2009 ID: T‐04‐04300‐0504‐065586 

 

 

T ‐ 295 

 

Ministry of Women Empowerment 

 

T ‐ 297 

 GB‐ID : GBT1‐06‐04700‐0901‐061584 

1. Project Title  :  Strengthening Indonesia’s National Mechanism to Enhance State Effectiveness in Promoting Women’s Right and Gender Equality 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of Women Empowerment 

4. Implementing Agency  :  Komnas Perempuan 

5. Duration  :  24 months 

6. Location  :  DKI Jakarta 

 7. Objectives 

General objectives: The goal of this funding proposal is to provide institutional support to Komnas Perempuan so it can maintain its leadership role in promoting women’s rights and facilitate the sustainability of recent breakthroughs for the second decade of reform Indonesia.  Specific objectives: a. To advance the development of knowledge and expertise  in addressing violence against 

women (VAW) among strategic groups and institutions b. To strengthen Komnas Perempuan’s managerial capacity and institutional development c. To clarify Komnas Perempuan’s legal basis and relationship to the Government’s financial 

and  administrative  agencies  in  order  to  obtain  a  more  substantial,  effective  and sustainable support from GOI 

d. To increase Komnas Perempuan’s capacity in influencing relevant policy debates affecting women’s rights 

e. To improve public access to Komnas Perempuan’s work and project management unit  

8. Scope of Projects  Capacity building for Komnas Perempuan 

 9. Activities 

Activities Implementation 

Locations 

Project Implementation 

Units a.  Advance the development of knowledge and 

expertise in addressing VAW among strategic groups and institutions 

b.  Strengthen KP’s institutional capacity and development 

c.  Clarity KP’s legal basis and relationship d.  Increase KP’s capacity in influencing relevant policy 

debates effecting women’s rights e.  Improve public access to KP’s work and project 

management 

DKI Jakarta  Komnas Perempuan 

 

T ‐ 298 

 GB‐ID : GBT1‐06‐04700‐0901‐061584 

 10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Komnas Perempuan  1,018  ‐  1,018  Australia (AusAid) 

Total  1,018  ‐  1,018   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

500  518        1,018 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a. Advance the development of 

knowledge and expertise in addressing VAW among strategic groups and institutions 

455         

b. Strengthen KP’s institutional capacity and development 

145         

c. Clarity KP’s legal basis and relationship 

18         

d. Increase KP’s capacity in influencing relevant policy debates effecting women’s rights 

195         

e. Improve public access to KP’s work and project management 

205         

Total  1,018         

 13. Project References : 

BB 2006 – 2009 ID: T‐06‐04700‐1105‐061584 

  

 

T ‐ 299 

 

Ministry of Administrative Reform 

 

T ‐ 301 

 GB‐ID : GBT1‐06‐04800‐0901‐062585 

1. Project Title  :  Capacity Building for Public Officials for Government Innovation in Indonesia Stage II 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  State Secretariat 

4. Implementing Agency  :  Ministry of Administrative Reform 

5. Duration  :  36 months 

6. Location  :  DKI Jakarta 

 7. Objectives 

a. To  support  the  implementation  of  bureaucracy  reform  in  Indonesia  by  introducing expertise and know‐how through training, dispatch of experts, and workshops in the field of government innovation; 

b. To  help  improve  the  capacity  and  skill  set  of  human  resources  in  the  Republic  of Indonesia in the field of government innovation; 

c. To strengthen the relationship and cooperation between countries through the successful implementation of the project. 

 

8. Scope of Projects  The scope of  the project  is  to achieve  the above mentioned objectives and shall comprise of, but not be limited, the items as follows: a. Bureaucracy Reform and Action Plans 

Supporting the implementation of the already existing bureaucracy reform as well as the action plans of the participating organizations. 

b. Reform Leadership Facilitate  training  in reform  leadership, help building reform vision, and help exercising leaderships. 

c. Culture Change  Help  improving  working  attitude,  strengthening  work  ethics,  and  developing  work motivation. 

d. Structure and System Change Strengthening  and  facilitating  performance  management  system,  change  management system, knowledge management system, e‐government, incentive system, monitoring and evaluation for reform activities 

e. Innovation Capacity (Human Resources) Help  improving  Human  Resources  Department  (HRD)  and  Human  Resource Management (HRM) 

f. Performance Improvement Help  implementing  performance management  system, measurement  and  evaluation  of performance. 

 

T ‐ 302 

 GB‐ID : GBT1‐06‐04800‐0901‐062585 

 9. Activities 

Activities  Implementation Locations  Project Implementation Units a.  Overseas training b.  Joint study and evaluation c.  Workshop 

DKI Jakarta  Ministry of Administrative Reform 

 10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Ministry of Administrative Reform 

2,000  ‐  2,000  Korea (KOICA) 

Total  2,000  ‐  2,000   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

500  750  750      2,000 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others Capacity Building        2,000   

Total        2,000   

 13. Project References : 

BB 2006 – 2009 ID: T‐06‐04800‐0101‐062585 

 

T ‐ 303 

 

Ministry of National Development Planning/ National Development Planning Agency 

(BAPPENAS) 

 

T ‐ 305 

 GB‐ID : GBT1‐06‐05500‐ 0901‐068475‐07 

1. Project Title  :  Support to Aid for Development Effectiveness Secretariat (A4DES) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry  of National Development  Planning/National DevelopmentPlanning Agency (BAPPENAS) 

4. Implementing Agency  :  Deputy of Development Funding, Bappenas 

5. Duration  :  12 months 

6. Location  :  DKI Jakarta 

 7. Objectives 

To  strengthen  the  capacity  of  the  Ministry  of  National  Development  Planning/National Development Planning Agency/Bappenas through the office of Deputy of Development Funding in  order  to  support  improving  effectiveness  of  aids  utilization  and  to  strengthen  country ownership over developing, delivering and accounting for development result.  

8. Scope of Projects  The TA will provide advice and assistance to support aid effectiveness with scope of works are:   a. Preparing the Action Plan to achieve indicators of Paris Declaration  b. Developing Management Information System (MIS) in Deputy of Development Funding;  c. Developing Operation Manual for office of Deputy of Development Funding;  d. Providing skills training for staff; and  e. Providing comparative study to look at experience in Asia Pacific. 

 9. Activities 

Activities Implementation 

Locations 

Project Implementation 

Units a. Preparing the Action Plan to achieve indicators of 

Paris Declaration  b. Developing Management Information System 

(MIS) in Deputy of Development Funding/Monitoring System 

c. Developing management   d. Providing skills training for staff; and  e. Providing comparative study to look at experience 

in Asia Pacific 

Jakarta (Bappenas) 

Deputy Development Funding, Bappenas 

 

 

T ‐ 306 

 GB‐ID : GBT1‐06‐05500‐ 0901‐068475‐07 

 10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Deputy of Development Funding, Bappenas 

500  ‐  500  Australia (AusAid), USAID 

Total  500  ‐  500   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

500          500 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others Capacity Building  500         

Total  500         

 13. Project References : 

BB 2006‐2009 ID: T1‐06‐05500‐0101‐068475‐07 

 

 

T ‐ 307 

 GB‐ID : GBT1‐06‐05500‐0801‐09‐068475‐07 

1. Project Title  :  Aid Information Management System (AIMS) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry  of National Development Planning/National Development Planning Agency (BAPPENAS) 

4. Implementing Agency  :  Deputy for Development Funding, Bappenas 

5. Duration  :  24  months 

6. Location  :  DKI Jakarta 

 7. Objectives 

To  support GOI  and development partners  to  accelerate management of  external  assistances  in effective and efficient way,  through development of a single management  information system  in planning, preparation, implementation and monitoring and evaluation of external assistances.  

8. Scope of Projects  Scope of works for this services are as follows, but not limited to : a. Identification  of  external  assistances  report  format  of  development  partners  in  supporting 

GOI’s economic development.  b. Standardize report of external assistance and  its workflow of  involved parties  (development 

partners and GOI agencies) in order to support transparent process. c. Development of Management Information System in reporting of external assistance that will 

include planning, implementation, and monitoring and evaluation process. d. Develop database and its user friendly manual of external assistances to support management 

information system in reporting of external assistances. e. Develop training program to increase capabilities of stakeholders officers in implementation of 

the management information system.  9. Activities 

Activities  Implementation Locations  Project Implementation Units 

Development of management information system 

DKI Jakarta  Deputy for Development Funding, Bappenas 

 10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Deputy for Development Funding, Bappenas 

500  15  515  Germany (GTZ) 

Total  500  15  515   

 

 

T ‐ 308 

 GB‐ID : GBT1‐06‐05500‐0801‐09‐068475‐07 

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

265  250        515 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a. Develop MIS  180         b. Develop Database  300         c. Training          35 

Total  480        35 

 13. Project References : 

BB 2006‐2009 ID: T1‐06‐05500‐0101‐068475‐07 

 

 

T ‐ 309 

 GB‐ID : GBT1‐06‐05500‐0901‐068482 

1. Project Title  :  Articulate Governance and Local Development (AGI) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of National Development Planning/National Development Planning Agency (BAPPENAS) 

4. Implementing Agency  :  Deputy for Regional Development and Local Autonomy, Bappenas 

5. Duration  :  24 months 

6. Location  :  National wide 

 7. Objectives 

The program  aims at  supporting  the national policies and  local practice  in  the  field of  regional development  as  a  means  to  contribute  to  the  achievement  of  the  MDGs  and  to  facilitate coordination  and  effectiveness  of  external  aid  at  the  provincial  level.  The  approach  to  the provincial development will be participatory, cross sectoral, integrated, and open to partnerships and networking with other Indonesian and worldwide experiences. The support will be provided at the local, national, and international levels  

Intended Impact of the Project:   Contribute to increased opportunities for achieving sustainable livelihoods and reducing poverty through the development and implementation of appropriate participatory policies and programs.   

Project  Outcomes:  UNDP  ART  GOLD  programs’  outcomes  are  usually  divided  in  Local  or Provincial / National / International levels:  a. Outcome 1 – Local‐ : Upon completion of the project, the provincial governments will use the 

appropriate participatory instruments, aligned with the Musrenbang, allowing them to fulfill their roles as facilitators, promoters and monitors of regional strategic development, open to international opportunities.  

b. Outcome 2 –Local‐  : The  strategic development guidelines  for  improving  community  living standards  are  clearly  identified  across  sectors  and  districts,  and  the  provinces  are  in  the capacity  to  orient  both  public  expenditure  and  external  aid  resources  accordingly,  in  a cooperative effort among the different tier of sub national governments, the private sector and citizens’ associations;  

c. Outcome 3 – National  ‐:  the national  institutions  in  charge of  regional development will be provided  with  tested  models  for  reinforcing  the  role  of  the  Provinces  as  promoters  and facilitators of inclusive and balanced regional development.  

d. Outcome 4 – International – the Provinces and the national  institution are reinforced  in their capacity of coordinating external aid resources in line with strategic regional planning. 

 

T ‐ 310 

 GB‐ID : GBT1‐06‐05500‐0901‐068482 

 

8. Scope of Projects  The approach to provincial development will be: a. Participatory, thus requiring long term wide‐ranging partnerships between the public, private 

and  civil  society  sector;  for  instance,  through  the  establishment  of Working Groups,  at  the Provincial, District and Thematic levels. 

b. Cross‐sectoral,  emphasizing  strategic development  across  sectors  and public  functions,  and not limiting it to a few or specific development sectors 

c. Integrated,  thus  earmarked  in  national  governmental  priorities  and  in  support  of  the implementation role of districts and municipalities; 

d. Open  –  Internationalized:  to  partnerships  and  networking  with  other  Indonesian  and worldwide  experiences  for  cross  learning,  exchange  of  best  practices,  and  resources mobilization 

 The support will be provided at three levels: e. At the sub‐national level, to facilitate formulation of Provincial Development guidelines, and the 

implementation  of  actions  and  initiatives  in  5 major  thematic  areas  linked  to  the MDGs: Democratic Governance, Local Economic Development, Welfare Services and Public Facilities, Environmental  Protection  and  Territorial  Planning,  Education  and  Cultural  Development, through participatory decision making processes. 

f. At  the  national  level,  to  support  national  regional  development  priorities;  promote  policy improvements ‐based on lessons learned‐ and gradually expand the implementation of project tools and methodologies to additional areas. 

g. At  the  international  level,  to  facilitate  decentralized  cooperation  partnerships,  resource‐ mobilization,  and  the  internationalization  of  the  Indonesian  experience,  through  ART international Services and cooperation partners. 

 The  support  will  be  provided  through  program  technical  assistance,  specialized  technical assistance  (through  centers  of  excellence  throughout  the world)  and  co‐financing  resources  to provincial development Plans and national activities. 

 9. Activities 

Activities  Implementation Locations  Project Implementation Units Capacity Building   DKI Jakarta  Deputy for Regional Development 

and Local Autonomy, Bappenas 

 10. Funding Source 

Implementing Agency 

Foreign Funding (US $ 000) 

Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

  6,000  ‐  6,000  UNDP 

Total  6,000  ‐  6,000   

 

T ‐ 311 

 GB‐ID : GBT1‐06‐05500‐0901‐068482 

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

3,000  3,000        6,000 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others 

Capacity Building  6,000         

Total  6,000         

 13. Project References : 

BB 2006‐2009 ID: T‐06‐05500‐0101‐068482  

 

T ‐ 312 

 GB‐ID : GBT1‐06‐05500‐0802‐09‐068482 

1. Project Title  :  Decentralization Support Facility (DSF) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry  of National Development  Planning/National DevelopmentPlanning Agency (BAPPENAS) 

4. Implementing Agency  :  Bappenas, Ministry of Finance, and Ministry of  Home Affairs 

5. Duration  :  36 months 

6. Location  :  National wide 

 7. Objectives 

Assisting  GoI’s  efforts  to  implement  systematic  and  coherent  decentralization,  using  a harmonized, and aligned appropriate  international development  framework. The overall goal of DSF Programmes is to ensure that decentralization is effective and results in improvement services delivery for all citizens.  

8. Scope of Projects  The scope of this project is in decentralization process in Indonesia, especially in these 4 areas: a. Public services b. Fiscal decentralization and capacity development c. Government reform d. Planning and performance measurement. 

 9. Activities 

Activities Implementation 

Locations Project Implementation 

Units a.  Study/survey for policy development b.  National workshop c.  Database system development support d.  Monitoring and evaluation e.  Capacity building f.  Supporting activity for its program 

National wide  Bappenas, Ministry of Finance, and Ministry of  Home Affairs 

 10. Funding Source 

Implementing Agency 

Foreign Funding (US $ 000) 

Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Bappenas,  MOF, MOHA 

20,000  ‐  20,000  Australia (AusAid) 

Total  20,000  ‐  20,000   

 

 

T ‐ 313 

 GB‐ID : GBT1‐06‐05500‐0802‐09‐068482 

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

600  700  700      20,000 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a.  Study/survey for policy 

development 300         

b.  National workshop  400         c.  Database system 

development support 300         

d.  Monitoring and evaluation  400         e.  Capacity building        300   f.  Supporting activity for its 

program 300         

Total  17,000      300   

 13. Project References : 

BB 2006‐2009 ID: T‐06‐05500‐0101‐068482 

 

T ‐ 314 

 GB‐ID : GBT1‐06‐05500‐0803‐09‐068482 

1. Project Title  :  Delivery Improvement and Local Governance (DIALOG) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry  of National Development  Planning/National DevelopmentPlanning Agency (BAPPENAS) 

4. Implementing Agency  :  Bappenas, Ministry of Finnance, Ministry of Home Affairs, Local Governments, and  Universities/NGOs 

5. Duration  :  60 months 

6. Location  :  Eastern Indonesia 

 7. Objectives 

The primary objective of DIALOG is to improve the quality of public service delivery and public financial management in the participating regions through: a. Plotting an incentive system for local government based on their performance improvements, 

congruent to the task and responsibilities of each level of government; and b. Operationalizing  local government’s performance monitoring  and  evaluation  system, based 

on existing framework, for central and provincial government to use.  

8. Scope of Projects  a. Government and service delivery reform b. District block grant c. Capacity building and technical assistance d. Implementing support, monitoring, and evaluation 

 9. Activities 

Activities Implementation 

Locations Project 

Implementation Units 

Government and service delivery reform a.  District block grant b.  Capacity building and technical assistance c.  Implementing support, monitoring, and 

evaluation 

Eastern Indonesia  Bappenas, Ministry of Finnance, Ministry of Home Affairs, Local Governments, and  Universities/NGOs 

 10. Funding Source 

Implementing Agency 

Foreign Funding (US $ 000) 

Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Bappenas  3,066  60  3,126 

Local government  11,530  7,535  19,065 

Universities/NGO  3,950  ‐  3,950 

World Bank  2,502  ‐  2,502 

Australia (AusAid) 

Total  21,048  7,595  28,643   

 

T ‐ 315 

 GB‐ID : GBT1‐06‐05500‐0803‐09‐068482 

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

2,423  6,294  9,388  7,599  2,939  28,643 

 12. Funding Allocations  

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others 

Capacity Building  9,518         

District block grant          11,530 

Others           7,595 

Total  9,518        19,125 

 13. Project References : 

BB 2006‐2009 ID: T‐06‐05500‐0101‐068482 

 

 

T ‐ 316 

 GB‐ID : GBT1‐06‐05500‐0904‐068482 

1. Project Title  :  Formulation of the National Medium Term Development Plan on Decentralization and Functional Assignment Reform 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  National Development Planning Agency (Bappenas) 

4. Implementing Agency  :  Deputy for Regional and Local Autonomy, Bappenas 

5. Duration  :  36 months 

6. Location  :  DKI Jakarta 

 7. Objectives 

The project has the following main objective: 

a. Robust  regional  autonomy/decentralization  strategy  in  the  national mid‐term  development plan (RPJM 2010‐2014) 

b. Involvement and inputs for law 32/2004 revision process c. Enhanced  knowledge  in Bappenas, particularly  on  functional  assignment  and  other  related 

issues on national development d. Effective  guidance  to  sector  ministries  and  local  government  on  development  roles  and 

intergovernmental/institutional arrangements to support harmonious development  8. Scope of Projects  

Support  to  government  for  policy  analysis  on  decentralization  and  local  autonomy  and  in coordination/harmonization of sectoral and regional policies 

 9. Activities 

Activities Implementation 

Locations Project Implementation 

Units a.  Develop inputs for the formulation of a 

robust section in the Mid‐Term National Development Plan (RPJM) 2010‐2014 

b.  Map relevant functional assignment issues to national development and develop strategic plan to harmonize legal strems 

c.  Develop inputs, strategy of methodology to improve local government financial management and assure ʺmoney follow functionʺ scheme can be widely realized 

d.  Develop inputs for the decentralization reform  to enhance Bappenas roles and the perspective  

DKI Jakarta  Deputy for Regional and Local Autonomy 

 

 

T ‐ 317 

 GB‐ID : GBT1‐06‐05500‐0904‐068482 

 10. Funding Source 

Implementing Agency 

Foreign Funding (US $ 000) 

Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Deputy for Regional and Local Autonomy 

600  ‐  600  Germany (KfW) 

Total  600  ‐  600   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

230  200  200      600 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others 

Study and capacity building  600         

Total  600         

 13. Project References : 

BB 2006‐2009 ID: T‐06‐05500‐0101‐068482 

 

T ‐ 318 

 GB‐ID : GBT1‐06‐05500‐0803‐09‐068475‐07 

1. Project Title  :  Monitoring and Evaluation System 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry  of National Development  Planning/National DevelopmentPlanning Agency (BAPPENAS) 

4. Implementing Agency  :  Deputy of Development Funding, Bappenas 

5. Duration  :  24 months 

6. Location  :  DKI Jakarta 

 7. Objectives 

The purposes of this program are:  a. To draw together the extensive and growing body of experience with the institutionalizing of 

government  monitoring  systems  including  program  assessment,  particularly  those  in developed countries. 

b. To  establish  the  cooperation  with  developed  countries,  which  have  institutionalized development monitoring system. The lesson can be used as an experience to be learned. 

c. To review existing government regulation on monitoring for development program/project. d. To strengthen the development monitoring capacity‐building work, to undertake the assigned 

roles and responsibilities. e. To  support  exchange  of  skills,  knowledge  and  expertise  between  Australia  Government 

Agency and Bappenas. f. To strengthen the capacity‐building in BAPPENAS as a leading institution in coordination of 

development monitoring and evaluation, especially focuses on the ability of government and civil society to conduct good‐quality monitoring practices. 

 8. Scope of Projects  

a. Monitoring‐Evaluation Development System b. Training c. Workshop 

 9. Activities 

Activities  Implementation Locations  Project Implementation Units a. Monitoring‐Evaluation 

Development System 

b. Training 

c. Workshop 

DKI Jakarta  Deputy of Development Funding  

 

 

T ‐ 319 

 GB‐ID : GBT1‐06‐05500‐0803‐09‐068475‐07 

 10. Funding Source 

Implementing Agency 

Foreign Funding (US $ 000) 

Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Deputy of Development Funding  

300  10  310  Australia (AusAid) 

Total  300  10  310   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

125  185        310 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a.  Monitoring‐Evaluation 

system Development 200         

b.  Improvement Capacity (comparative study) 

      70   

c.  Procurement of Supporting Facilities 

    30     

d.  Workshops        6   e.  Others          4 

Total  200    30  76  4 

 13. Project References : 

BB 2006‐2009 ID: T1‐06‐05500‐0101‐068475‐07 

 

T ‐ 320 

 GB‐ID : GBT1‐06‐05500‐0804‐09‐068475‐07 

1. Project Title  :  Planning and Budgeting Reform 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry  of National Development  Planning/National DevelopmentPlanning Agency (BAPPENAS) 

4. Implementing Agency  :  Deputy of Development Funding, Bappenas 

5. Duration  :  36 months 

6. Location  :  Jakarta 

 7. Objectives 

To support central and  local government officer  in developing and  implementing medium  term and result based planning and budgeting into a planning and budgeting system.  

 8. Scope of Projects  

Technical  Assistance  in  public  finance  (medium  term  planning  and  budgeting  –  result  based planning and budgeting – central –  local transfer system), capacity building for central and  local government official through training/study tour in Indonesia and abroad, Seminar/Workshop. 

 9. Activities 

Activities Implementation 

Locations Project 

Implementation Units 

Technical Assistance. a.  Capacity Building for Central and Local 

Government Officer on Planning – Budgeting  system. 

b.  Workshop and Seminars among stakeholders (Central and Local Government). 

DKI Jakarta  Deputy of Development Funding, Bappenas 

 10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Deputy for Development Funding Affairs, Bappenas 

1,120  500  1,620  Japan (JICA) 

Total  1,120  500  1,620   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

540  540  540      1,620 

 

 

T ‐ 321 

 GB‐ID : GBT1‐06‐05500‐0804‐09‐068475‐07 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a.  Local/International Experts  850         b.  Long Term/Short Term 

Training/Education       470   

c.  Seminar/Workshop          170 d.  Secretariat support      130     

Total  850    130  470  170 

 13. Project References : 

BB 2006‐2009 ID: T1‐06‐05500‐0101‐068475‐07 

 

 

T ‐ 322 

 GB‐ID : GBT1‐06‐05500‐ 0801‐09‐068482 

1. Project Title  :  Long‐term Finance Security for National Backbone Infrastructure Development 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry  of National Development  Planning/National DevelopmentPlanning Agency (Bappenas) 

4. Implementing Agency  :  Deputy for Infrastructure, Bappenas 

5. Duration  :  48 months 

6. Location  :  DKI Jakarta 

 7. Objectives 

Overall Goal To realize the  long‐term and mid‐term dynamic nation economic development through realizing the National Backbone Infrastructure Development  Project Purpose a. To  create  the  long‐term  perspective  public  finance  plan  to  realize  dynamic  and  efficient 

national development b. To  streamline  the  backbone  infrastructure  finance  demand  best  combining  the  possible 

financial resources c. To  create  the  mutual  trust  between  the  GoI  and  private  sector  and  to  promote  private 

investment and stabilize the macro economy  8. Scope of Projects  

a. Comprehensive National Development Program b. Authorize ‘the National Backbone Infrastructure Project” c. Optimize the long‐term budgeting plan for National Backbone Infrastructure Projects d. Hold periodical consultative meetings between GoI and private sectors e. Comparative research of cases in other countries f. Formulating the 2010‐2014 Blue Book 

 9. Activities 

Activities Implementation 

Locations Project 

Implementation Units a.  Development Study b.  Seminar/Training 

DKI Jakarta  Deputy for Infrastructure, Bappenas 

 

 

T ‐ 323 

 GB‐ID : GBT1‐06‐05500‐ 0801‐09‐068482 

 10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Deputy for Infrastructure, Bappenas 

1,818  ‐  1,818  Japan (JICA) 

Total  1,818  ‐  1,818   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

318  500  600  400    1,818 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a.  Development Study  1,218         b.  Seminar/Training        600   

Total  1,218      600   

 13. Project References : 

BB 2006‐2009 ID: T‐06‐05500‐0101‐068482 

 

T ‐ 324 

 GB‐ID : GBT1‐06‐05500‐ 0902‐068482 

1. Project Title  :  Provincial Governance Support Programme (PGSP) 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of National Development Planning/National Development Planning Agency (Bappenas) 

4. Implementing Agency  :  BAPPENAS,  Ministry  of  Home  Affairs,  Ministry  of  Finance, Ministry of Administrative Reform, and selected province 

5. Duration  :  45 months 

6. Location  :  National wide  

 7. Objectives 

Provincial  government  roles  and  functions  strengthened  through  effective  participatory  policy making,  regional  development  planning  and  public  service  delivery,  leading  to  realization  of national and local development objectives and the improvement of quality of life for the poorest.  

8. Scope of Projects  

PGSP scopes of projects are defined through 3 (three) PGSP Outcomes, as follow: PGSP  Outcome  1:  Enhanced  Policy  and  Regulatory  Framework  that  further  clarifies  and strengthens roles and functions of provincial government and council (DPRD); PGSP Outcome  2:  Strategic  regional  economic development  planning  strengthened,  effectively link planning an budgeting using HDI/HDR; with participatory decision‐making mechanism  in place; PGSP  Outcome  3:  Achievement  of  better  development  outcomes  at  provincial  level  through governance  innovations  implementation  of  minimum  service  standards,  civil  service  reform, participatory monitoring and evaluation and sustainable cross province learning;  PGSP will have two parts which will be undertaken in parallel (i.e. not sequentially), as follow: PART A –using  capacity development  efforts at provincial  level across  the  country  to discover ways  in  which  provincial  governments  (executive  and  legislative  functions)  implement  their policy and planning  roles and  to  replicate or develop  these.   After promulgation of  the  revised Law 32, the capacity development efforts will also support the implementation of the revised Law and supporting regulations. The Project will be operational in 6 provinces representing provinces throughout Indonesia and will also learn from the experience of “resource provinces” which have relevant special experience of provincial governance.  PART  B  ‐  continuing  support  will  be  provided  to  relevant  agencies  in  GoI  to  more  clearly distinguish  devolved,  de‐concentrated  and  assistance  tasks  of  provincial  government  in  the revision of Law 32 (and Law 33 as appropriate) and feeding the lessons learned at provincial level (through  the work of PART A)  into  the  formulation of  implementing regulations  for  the revised Law  32  and  sub‐national  regulations  and  longer  term policy on provincial government  reform.  Part B will  be  responsible  for  liaising with  the  selected  “resource provinces”.   Part B will  also support the dissemination of lessons learned more widely throughout Indonesia.   

 

T ‐ 325 

 GB‐ID : GBT1‐06‐05500‐ 0902‐068482 

 

9. Activities 

Activities Implementation 

Locations Project 

Implementation Units OUTCOME 1: Regulatory frame‐work further clarifies role and functions of executive provincial government and DPRD and resources to support them are identified by different levels of government. 

National level (Jakarta) 

National Project Management Unit  (PMU) in Jakarta 

OUTCOME 2:  Coordinated strategic regional economic development planning strengthened, including linked planning and budgeting using HDI/HDR; enhanced associated executive and DPRD democratic governance participatory mechanisms. 

3 pilot provinces in the inception (April 2009) and plans to implement in 3 more provinces starting from January 2011 

National Project Management Unit (PMU) in Jakarta; Project Implementation Management in pilot provinces. 

OUTCOME 3:  Innovations to better achieve development outcomes at provincial level, including civil service reform at provincial level which directly contributes to achievement of strategic provincial objectives; development outcomes adequately monitored and evaluated using participatory and multi‐stakeholder approaches; enhanced associated executive and DPRD democratic governance participatory mechanisms.  

3 pilot provinces in the inception (April 2009) and plans to implement in 3 more provinces starting from January 2011 

National Project Management Unit (PMU) in Jakarta; Project Implementation Management in pilot provinces. 

 10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding(US $ 000) 

Total of Funding (US $ 000)  Remarks 

National Project Management Unit 

11,370    11,370  UNDP 

Total  11,370    11,370   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

1,813  3,602  3,339  2,616    11,370  

 

T ‐ 326 

 GB‐ID : GBT1‐06‐05500‐ 0902‐068482  

12. Funding Allocations 

Categories (US $ 000) Detail of Activities Services  Constructions  Goods  Trainings  Others 

PGSP Outcome 1: Enhanced Policy and Regulatory Framework that further clarifies and strengthens roles and functions of provincial government and council (DPRD) 

2,065         

PGSP Outcome 2: Strategic regional economic development planning strengthened, effectively link planning an budgeting using HDI/HDR; with participatory decision‐making mechanism in place 

4,600         

PGSP Outcome 3: Achievement of better development outcomes at provincial level through governance innovations implementation of minimum service standards, civil service reform, participatory monitoring and evaluation and sustainable cross province learning 

4,105         

PGSP Outcome 4: Management (The project is effectively implemented, monitored, reported and audited) 

600         

Total  11,370         

 13. Project References : 

BB 2006‐2009 ID: T‐06‐05500‐0101‐068482 

       

 

T ‐ 327 

 GB‐ID : GBT1‐06‐05500‐ 0905‐068482 

1. Project Title  :  Strengthening Knowledge Management for Effective Project Planning and Implementation. 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry  of National Development  Planning/National Development Planning Agency (BAPPENAS) 

4. Implementing Agency  :  Ministry  of National Development  Planning/National DevelopmentPlanning Agency (BAPPENAS) 

5. Duration  :  24 months 

6. Location  :  DKI Jakarta 

 7. Objectives 

Performing effective project planning and implementation by strengthening systematical knowledge management sharing through: a. Analyzing policy and procedural that relevance to ADB operation in Indonesia b. Conducting  extensive knowledge  and  experience  sharing  among projects  that will  improve 

effectiveness of ADB portfolio management c. Dissemination of knowledge sharing d. Improving capacity within government stakeholders on the portfolio management 

 8. Scope of Projects  

a. To  conduct  review  analyzing planning  and  implementation process  from  both  government and donors side 

b. To conduct meeting, conference, seminar involving relevant stakeholders in government and donors/creditors for broadening knowledge network 

c. To conduct workshop, in‐house training for strengthening understanding of government and ADB strategy, policies, procedure, facility, and mechanism. 

d. To support preparation of joint review meeting. e. Comparative  study  for  getting  best  practices  in  effective  planning  and  implementation  of 

project, and experienced of knowledge management.  9. Activities 

Activities Implementation 

Locations Project 

Implementation Units 

Capacity building(workshop, seminar, conference  DKI Jakarta  Bappenas 

 10. Funding Source 

Implementing Agency 

Foreign Funding (US $ 000) 

Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Bappenas  500  14  514  ADB 

Total  500  14  514   

 

 

T ‐ 328 

GB‐ID : GBT1‐06‐05500‐ 0905‐068482 

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

64  450        514 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others 

Capacity building  514         

Total  514         

 13. Project References : 

BB 2006‐2009 ID: T‐06‐05500‐0101‐068482 

 

T ‐ 329 

 GB‐ID : GBT1‐06‐05500‐0803‐09‐068482 

1. Project Title  :  Support to Bappenas in Mainstreaming Climate Change Issue into Development Plan 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of National Development Planning/National DevelopmentPlanning Agency (BAPPENAS) 

4. Implementing Agency  :  Deputy  Ministry  for  Natural  Resources,  Ministry  of  National Development  Planning/National  Development  Planning  Agency (BAPPENAS) 

5. Duration  :  12 months 

6. Location  :  DKI Jakarta 

 7. Objectives 

a. To provide and advice for developing a Climate Change Road Map in close consultation with line ministries and donors in a timely and coordinated programmatic approach. 

b. To  provide  support  and  advice  for  capacity  building  for  staff  of  line  ministries,  and BAPPENAS as well as the regional planning agencies (BAPPEDA) and  local governments  in charge  of  development  planning  and  programme  formulation  in  order  to  enhance  their capacity to mainstream climate change into development policies.  

 

8. Scope of Projects  a. Awareness and Capacity building: 

Policy makers  and  local  governments  and  authorities  are  aware  of  climate  change  topics related  to national development planning  issues and are  in positions  to contribute  to sector specific climate change programme formulation and planning processes.  

b. Donor coordination  1) Developed jointly with and accepted by relevant stakeholders; 2) Based upon  links between policies for the different sectors and donor programs/projects 

as well as the ongoing activities; 3) An effective tool to channel donor funds into sectors related to climate change; 4) Equipped with  a monitoring  and  evaluation  system  in  order  to  assess  effectiveness  of 

donor funds; 5) Sustainable in the sense that funding of the donor coordination mechanism is secured by a 

medium to long‐term concept; c. A road map for Climate Change Programmes  is developed and  integrated  into development 

plan, which is: 1) Climate impacts are well understood and impacts management is beginning 2) Climate  mitigation  options  potentials  are  understood  and  their  synergies  with 

development priorities are exploited  3) Climate change issues are incorporated in sectoral planning for the next RPJM and RKP. 

 

T ‐ 330 

 GB‐ID : GBT1‐06‐05500‐0803‐09‐068482 

 9. Activities 

Activities Implementation 

Locations Project 

Implementation Units a.  Develop Climate change Roadmap parts b.  Awareness raising and capacity building  c.  Development and design of the Climate Change 

Trust Fund Policy framework 

DKI Jakarta  Deputy Ministry for Natural Resources 

 10. Funding Source 

Implementing Agency 

Foreign Funding (US $ 000) 

Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Deputy Ministry for Natural Resources 

300  ‐  300  Germany (GTZ)  

Total  300  ‐  300   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

300          300 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others a.  National experts  182         b.  International Experts  64         c.  Travel  12         d.  Workshop, meetings, FGD, 

training 24 

       

e.  Design, Printing, and Publication  

18  

       

Total  300         

 13. Project References : 

BB 2006‐2009 ID: T‐06‐05500‐0101‐068482 

 

T ‐ 331 

 GB‐ID : GBT1‐01‐05502‐0901‐073091 

1. Project Title  :  Support to PNPM Mandiri 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry of National Development Planning/National Development Planning Agency (Bappenas) 

4. Implementing Agencies :  PNPM Support Facility (Ministry of Home Affair, Bappenas, Ministry of Public Work) 

5. Duration  :  60 months 

6. Location  :  National wide 

 7. Objectives 

a. To  support  the  harmonization  process  of  the  PNPM Mandiri,  in  the  central  level  through PNPM  Oversight  Team,  National  Development  Planning  Agency,  and  also  an  improved coordination and synchronization with the local government 

b. To support the scaling up of the PNPM Mandiri to all sub district in Indonesia c. To support  the development of database, MIS system and monitoring‐evaluation  for a more 

effective and efficient community development program d. To empower local communities to plan and implement social and economic initiatives e. To strengthen the capacity local authorities to plan and implement pro‐poor economic policies  

8. Scope of Projects  a. Direct support/ co‐financing of the PNPM Mandiri b. Coordination and supervision support c. On granting to CSO  with engage in poverty reduction activities d. Technical assistance to PNPM include to local authorities e. To train local authorities in pro‐poor economic development planning 

 9. Activities 

Activities Implementation 

Locations Project 

Implementation Units a.  PNPM Communication Strategy b.  PNPM Management Information System c.  PNPM Community Facilitator Development 

System d.  PNPM Supervision and Monitoring e.  TA for Remote Regions, Supervision and 

Government Support (Eastern Indonesia) f.  Delivering Services to Poor Community g.  PNPM Monitoring and Evaluation, Special 

Studies 

All provinces  in Indonesia 

h.  TA for PNPM Generasi 2008  Selected provinces 

PNPM Support Facility 

 

T ‐ 332 

 GB‐ID : GBT1‐01‐05502‐0901‐073091 

 

Activities Implementation 

Locations Project 

Implementation Units i.  Poverty Engagement, Knowledge and 

Action Program All provinces in Indonesia 

j.  PSF Operational Support  DKI Jakarta 

PNPM Support Facility 

 10. Funding Source 

Implementing Agency 

Foreign Funding(US $ 000) 

Local Funding (US $ 000) 

Total of Funding(US $ 000) 

Remarks 

PNPM Support Facility 

14,531  ‐  14,531  All funds from several donors channeled through PSF 

Total  14,531  ‐  14,531   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

2,038  3,038 4,306 3,537  1,612  14,531 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services Construct‐

ions Goods 

Train‐ings 

Others 

a.  PNPM Communication Strategy  500    b.  PNPM Community Facilitator 

Development System 945    

c.  PNPM Supervision and Monitoring 

1,000    

d.  Delivering Services to Poor Community 

943    

e.  PNPM Monitoring and Evaluation, Special Studies 

  800 

f.  TA for PNPM Generasi 2008  1,000      g.  TA for Green PNPM  500    h.  Poverty Engagement, Knowledge 

and Actions 500    

i.  Community and CSO Grants  6,706      j.  Monitoring and Evaluation  137      

Total  7.025 6,706     800 

 13. Project References : 

BB 2006‐2009 ID: T1‐01‐05502‐0402‐073091 

 

T ‐ 333 

 GB‐ID : GBT1‐04‐05502‐0901‐075093 

1. Project Title  :  Supporting Medium Term Geothermal Development Plan and Accelerated Investment in Geothermal Sector 

2. Project Type  :  Technical Assistance 

3. Executing Agency  :  Ministry  of National Development  Planning/National DevelopmentPlanning Agency (Bappenas) 

4. Implementing Agency  :  Directorate  for  Energy, Natural Resources  and Mining, Ministry  ofNational Development Planning/Bappenas 

5. Duration  :  36 months 

6. Location  :  DKI Jakarta 

 7. Objectives 

To  facilitate  the  creation  of  a  National  Geothermal  Task  Force,  in  coordination  with  other Ministries  develop  a  National  Geothermal  Action  Plan  as  part  of  Indonesia  Climate  Change Activities assist with building national capacity to facilitate investments in Geothermal Energy  

8. Scope of Projects  Technical  assistance,  feasibility  studies,  awareness  raising  and  communications,  training, providing  financial  communication,  drafting  project  and  program  proposal,  economic  analysis, etc.  

9. Activities 

Activities  Implementation Locations Project Implementation 

Units a.  Preparation of Power Purchase 

Agreements Jakarta and district capitals 

b.  GE – PPDF Needs assessment and feasibility study 

Jakarta 

c.  Financial Engineering Capacity  Jakarta, District Capitals and overseas location  

Bappenas 

d.  Technical Engineering Capacity  Jakarta, Bandung, Kamojang  Bappenas, INAGA, ITB and PGE 

e.  Administrative and auditing costs (Maximum 5% or 35.000 euros) and miscellaneous 

Jakarta  Bappenas 

 

 

T ‐ 334 

 GB‐ID : GBT1‐04‐05502‐0901‐075093 

 10. Funding Source 

Implementing Agency Foreign Funding (US $ 000) 

Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

Directorate for Energy, Natural Resources and Mining, Ministry of National Development Planning/Bappenas 

1,035  ‐  1,035  Netherland, AusAid, EU, DFID (Trust Fund) 

Total  1,035  ‐  1,035   

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

400  400  235      1,035 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services Construct‐ions 

Goods  Trainings  Others 

a.  Procurement of Goods      40     b.  Procurement of Services  800         c.  Workshop        93.33   d.  Administrative Expenses          66.67 

Total  800    40  93.33  66.67 

 13. Project References : 

BB 2006‐2009 ID: T1‐04‐05502‐0405‐075093 

 

T ‐ 335 

 

State Electricity Company  (PT. PLN)  

  

 

T ‐ 337 

 GB‐ID : GBP3‐03‐02004‐0901‐076125‐08 

1. Project Title  :  Java‐Bali Crossing Interconnecting 500kv 2. Project Type  :  Technical Assistance 

3. Executing Agency  :  PT PLN (Persero) 

4. Implementing Agency  :  PT PLN (Persero) 

5. Duration  :  12 months 

6. Location  :  East Java and Bali  

7. Objectives a. To meet the high growth of electricity demand in Bali b. To increase reserve margin in Bali c. To increase reliability of supply in Bali d. To reduce oil consumption for power generation in Bali e. To reduce the cost of supply in Bali f. To supply electricity with minimum environmental impact  

8. Scope of Projects  a. Project Preparatory Technical Assistance (PPTA) b. Overhead Lines across Bali strait, 2 circuit, 2.4 km route c. Overhead Lines 500 kV Paiton – Kapal 2 circuit, 212 km route d. Extension of Paiton GIS substation, 2 diameters e. Kapal 500 kV substation, 3 diameters, interbus transformer 500/150 kV  

9. Activities 

Activities Implementation 

Locations Project 

Implementation Units a. Project Preparatory Technical Assistance (PPTA) b. Overhead Lines across Bali strait, 2 circuit, 2.4 km 

route c. Overhead Lines 500 kV Paiton – Kapal 2 circuit, 

212 km route 

East Java and Bali 

d. Extension of Paiton GIS substation, 2 diameters  East Java  

e. Kapal 500 kV substation, 3 diameters, interbus transformer 500/150 kV 

Bali 

PT PLN (Persero) Pikitring JBN 

 

10. Funding Source 

Implementing Agency Foreign Funding 

(US $ 000) Local Funding (US $ 000) 

Total of Funding (US $ 000) 

Remarks 

PT. PLN  1,000 1,000  ADB 

Total  1,000 1,000   

 

 

T ‐ 338 

 GB‐ID : GBP3‐03‐02004‐0901‐076125‐08 

 11. Disbursement Plan 

Disbursement Plan (US $ 000) 1st  2nd  3rd  4th  5th 

Total 

1,000    1,000 

 12. Funding Allocations 

Categories (US $ 000) Detail of Activities 

Services  Constructions Goods  Trainings  Others 

Engineering services  1,000    

Total  1,000    

 13. Project References : 

BB 2006 – 2009 ID: P3‐03‐02004‐0405‐076125‐08 