+ All Categories
Home > Documents > œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of...

œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of...

Date post: 26-Jul-2020
Category:
Upload: others
View: 9 times
Download: 0 times
Share this document with a friend
65
ž¸¸£÷¸ ¬¸£ˆÅ¸£ Government of India ˆ ½›Íú¡¸ ¢¨¸Ô¸º÷¸ œÏ¸¢š¸ˆÅ£μ¸ Central Electricity Authority œ¸¢©¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ WESTERN REGIONAL POWER COMMITTEE œ¸®¸½¢¨¸¬¸ ˆÅú ¢™›¸¸¿ˆÅ 30 Ÿ¸ƒÄ 2009 ˆÅ¸½ ™ú¨¸ Ÿ¸½¿ ‚¸¡¸¸½¢¸÷¸ 10 ¨¸ú¿ ¤¸¾“ˆÅ ˆÅa ˆÅ¸¡¸Ä vaR%t MINUTES OF 10 TH MEETING OF WRPC HELD ON 30 TH MAY 2009 AT DIU Ÿ¸º¿¤¸ƒÄ MUMBAI
Transcript
Page 1: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

ž¸¸£÷¸ ¬¸£ˆÅ¸£

Government of India ˆ ½›Íú¡¸ ¢¨¸Ô¸º÷¸ œÏ¸¢š¸ˆÅ£μ¸

Central Electricity Authority

œ¸¢©�¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ WESTERN REGIONAL POWER COMMITTEE

œ¸®¸½¢¨¸¬¸ ˆÅú ¢™›¸¸¿ˆÅ 30 Ÿ¸ƒÄ 2009 ˆÅ¸½ ™ú¨¸ Ÿ¸½¿

‚¸¡¸¸½¢�¸÷¸ 10 ¨¸ú¿ ¤¸¾“ˆÅ ˆÅa ˆÅ¸¡¸ÄvaR%t

MINUTES OF 10TH MEETING OF WRPC HELD ON 30TH MAY 2009 AT DIU

Ÿ¸º¿¤¸ƒÄ MUMBAI

Page 2: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Minutes of 10th WRPC meeting held on 30th May 09

C O N T E N T S Item No. Particulars

Page No.

ITEMS FOR DISCUSSION

ITEM No.1 CONFIRMATION OF THE MINUTES OF THE 9th MEETING OF WRP COMMITTEE

2

ITEM No.2 LTSA ARRANGEMENT FOR SCADA/EMS UNDER WR ULDC SCHEME

3

ITEM No.3 TRANSMISSION SYSTEM ASSOCIATED WITH THE TILAIYA ULTRA MEGA POWER PROJECT (4000 MW), IN JHARKHAND, NABINAGAR (1000MW) OF RAILWAYS AND NTPC, BARH-II (1320 MW), RIHAND-III (1000MW), VINDHYACHAL-IV (1000MW) AND MAUDA (1000MW) OF NTPC, AND IPPS IN JHARKHAND, ORISSA, MP, CHATTISGARH, AND MAHARASHTRA

10

ITEM No.4 TRANSMISSION SYSTEM CONNECTED WITH VINDHYACHAL POOLLING STATION AND PHASING OF TRANSMISSION WORK

12

ITEM No.5 ALLOTMENT OF TRANSMISSION CAPACITY TO IPPs AGAINST THEIR APPLICATION FOR AVAILING LTOA

14

ITEM No.6 PERFORMANCE OF WR GRID DURING JAN. 09 TO APR. 09

17

ITEM No.7 WIDE AREA MANAGEMENT SYSTEM OF WR

20

ITEM No.8 BILLING OF TRANSMISSION CHARGES FOR WHEELING OF CENTRAL SECTOR POWER TO UT OF DD, DNH & GOA

22

ITEM No.9 RENOVATION AND MODERNISATION OF WRPC OFFICE BUILDING

23

ITEMS FOR INFORMATION

ITEM No.10 PAYMENT OF TRANSMISSION CHARGES FOR INTER-STATE TRANSMISSION

23

ITEM No.11 COMPUTATION OF PAYMENT OF CAPACITY CHARGES FOR THERMAL GENERATING STATION

24

Page 3: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Minutes of 10th WRPC meeting held on 30th May 09

ITEM No.12 IMPLEMENTATION OF REVISED UI CHARGES W.E.F. 01.04.09 25

ITEM No.13 SHIFTING OF SLDC BHILAI TO RAIPUR

27

ITEM No.14 COMMISSIONING OF TRANSMISSION LINES AND GENERATING UNITS

29

ITEM No.15 ONGOING TRANSMISSION SCHEMES IN WESTERN REGION 30

ITEM No.16 ONGOING GENERATION SCHEMES IN WESTERN REGION 30

ITEM No.17 ANTICIPATED POWER SUPPLY POSITION IN WESTERN REGION FOR THE PERIOD FROM JUNE 09 TO AUG. 09.

31

ITEM No.18 PAYMENT OF UI AND REACTIVE ENERGY CHARGES 32

ITEM No.19 PROVISION OF 400 kV FEED TO UNION TERRITORY OF DAMAN & DIU.

32

ITEM No.20 CONTRIBUTION TOWARDS INCIDENTAL EXPENSES FOR VARIOUS MEETINGS ETC.

33

ITEM No.21 ADDITION OF DIGITAL ACCESS CROSS CONNECT SWITCH (DACS) AT JABALPUR AND ITARSI

34

ITEM No.22 LONG TERM SERVICE AGREEMENT FOR WIDEBAND TELECOMMUNICATION EQUIPMENT SUPPLIED UNDER SYSTEM COORDINATION & CONTROL PROJECT OF WR

35

ITEM No.23 SIGNING OF PPA WITH RGPPL AND ITS SCHEDULING 36

ITEM No.24 UNREQUISTIONED POWER AT KAWAS AND GANDHAR 37

ITEM No.25 DATE AND VENUE OF NEXT WRPC MEETING 37

Page 4: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Minutes of 10th WRPC meeting held on 30th May 09

ANNEXURES

Annexure

Particulars

Annexure-1(A) Participants of TCC meeting

Annexure-1(B) Participants of WRPC meeting

Annexure-3 Transmission system associated with the Tilaiya UMPP (4000 MW), Nabinagar (1000MW), Barh-II (1320 MW), Rihand-III (1000MW), Vindhyachal-IV (1000MW) and Mauda (1000MW), and IPPs in Jharkhand, Orissa, M.P., Chattisgarh and Maharashtra

Annexure-6.1(a) Frequency particulars of Western Region for the period from January 2009 to May 2009

Annexure-6.1(b) Power supply position in WR for the period from January 2009 to May 2009

Annexure-6.2 Voltages at the important 400/765 kV substations during the period from January 2009 to May 2009

Annexure-7 Presentation on smart grid implementation using PMU based WAMS for Western Region

Annexure-15 Progress of transmission lines under construction in Western Region

Annexure-16 Ongoing generation schemes in WR both under State as well as Central Sector in Western Region

Annexure-17 Anticipated power scenario in WR for the period June 2009 to August 2009

Annexure-20 Details of members of WRP Committee contributing towards incidental expenses

Page 5: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

MINUTES OF 10th MEETING OF WESTERN REGIONAL POWER COMMITTEE HELD ON 30TH MAY 2009 AT DIU

The TCC and 10th WRP Committee meetings were held on 29th & 30th May 2009

respectively at Diu. The lists of the participants are at Annexure-I (A) & I (B)

respectively.

Shri P. Patel, Member Secretary, WRPC welcomed the Members and participants to

the 10th meeting of Western Regional Power Committee. He intimated that Shri S.

Jagadeesan, Chairman, WRPC/GSECL and Principal Secretary (Energy), Govt. of

Gujarat could not attend the meeting and as desired by him, the meeting is being

chaired by Shri G. Mohapatra, Chairman, Uttar Gujarat Vij Co. Ltd.

Shri P. K. Gupta, Secretary (Power), UT of Daman & Diu and Dadra & Nagar Haveli

welcomed the Members and participants to the 10th meeting of Western Regional

Power Committee at small beautiful island of Diu. He stated that UTs of Daman &

Diu and Dadra & Nagar Haveli were under Portuguese regime and were liberated in

the year 1961. He further stated that after formation of State of Goa in the year 1987

UT of Daman & Diu was formed. Diu district remained vital sea port & naval base for

considerable strategic importance from 14th Century onwards and has a colorful

culture and mix of gujarathi and Portuguese tradition & custom in its spectrum of life

and art. He further stated that around the year 1987-88 govt. of India declared tax

holidays of 15 years for local taxes, excise & income tax loading to rapid

industrialization of territories of Daman and Diu and Dadra & Nagar Haveli. Power

demands of these UTs have grown very fast thereafter. He further stated that

demand met for DD & DNH is around 230 MW and 450 MW respectively but the

actual demand is much higher resulting in huge shortage of power. He requested

all the members to help these UTs in meeting their growing power demand.

Shri G. Mohapatra, Chairman, UGVCL welcomed members and participants of the

10th WRPC meeting. He briefly reviewed the performance of Western Regional grid

during the period from January 2009 to April 2009. He stated that from 1st April 2009,

CERC has amended the permissible frequency range for system operation to

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 1

Page 6: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

49.2 Hz – 50.3 Hz. He observed that the frequency profile during the period was

generally satisfactory except on a few days in February, 2009 and April,2009, when

drawal by NR and ER increased due to sudden weather changes / generating unit

outages

He informed that during the period January 2009 to April 2009, total 1182.5 MW

capacity were added in WR grid which comprise of 250 MW Trombay TPP in

Maharashtra, 382.5 MW by Torrent PGL in Gujarat, 300 MW, Lanco in Chhattisgarh

and second 250 MW by NSPCL in Chhattisgarh. He further informed that 400 kV

D/c Zerda-Kankroli line associated with N-W transmission corridor strengthening

scheme has been commissioned and certainly enhanced the inter-regional capacity

between WR & NR. He thanked the administration of UTs of Daman and Diu and

Dadra & Nagar Haveli for willingly hosting the WRPC meeting at Diu and making

excellent arrangements for the same. He then requested Shri P. Patel, Member

Secretary, WRPC to take up the agenda items.

ITEM No.1: CONFIRMATION OF THE MINUTES OF THE 9th MEETING OF WRP

COMMITTEE 1.1 Member Secretary, WRPC stated that the minutes of 9th meeting of WRP

Committee held on 9th January 2009 at Lonavala were sent to the members vide

letter No. WRPC/Minutes/AS/2008-09-1218 dated 3rd Feb. 2009.

He stated that comments have been received from ED, MPPTCL vide letter dated

17th Feb. 2009 on Item No. 4.5 “Transmission System for evacuation of power from

Krishnapattam UMPP and requirement for additional transmission capacity between

SR – WR”. MPPTCL have proposed the following amendment in last 4 lines of Para

4.5, Page –15:

“WR Constituents agreed to share only 25% transmission charges” may

be replaced by “WR Constituents (except Madhya Pradesh &

Chhattisgarh) agreed to share only 25% transmission charges”.

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 2

Page 7: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

1.2 The WRP Committee discussed the matter and the following amendment in

last line of 4.5, Page –15 of 9th Minutes of WRPC meeting was agreed:

“WR Constituents agreed to share only 25% transmission charges” will be

replaced by “WR Constituents (except Madhya Pradesh & Chhattisgarh)

agreed to share only 25% transmission charges. The cost component that

corresponds to Madhya Pradesh and Chhattisgarh will also be borne by

Maharashtra.”

WRP Committee confirmed the minutes of 9th WRPC meeting with the above modification.

ITEM No. 2: LTSA ARRANGEMENT FOR SCADA / EMS UNDER WR ULDC SCHEME

2.1 Member Secretary, WRPC stated that in the 8th meeting of WRPC held on

12th September 2008, WRLDC had intimated that ULDC project was under extended

AMC period upto 31.05.2009 and stressed the need for going in for a

comprehensive Long Term Service Agreement (LTSA). In this connection, it was

informed to the Committee that M/s GE had submitted their offer to take up AMC

which broadly covered the scope of SCADA / EMS / DTS software as well as

hardware at ten control centers commissioned under the ULDC project. The WRP

Committee discussed the matter and opined that ULDC / SCADA O&M committee

may discuss and negotiate the cost with M/s GE and also examine the alternative

options and the outcome should be placed before WRP Committee for consideration

and approval.

2.2 Based on the feedback given by WRLDC the matter was further deliberated

by the TCC in the meeting held on 15th January 2009 and further deliberated during

the 9th meeting of WRPC held on 16th January 2009. The WRP Committee agreed to

the recommendation of the TCC that (i) Negotiation Committee being nominated by

PGCIL may negotiate the cost with M/s GE to a reasonable acceptable level and

(ii) alternatively, PGCIL may go for inviting quotation etc. on limited bidding and

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 3

Page 8: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

formulate the specification. However, while formulating the specification by WRLDC /

PGCIL, views of SLDCs may also be taken care of. The WRP Committee felt that it

would be preferable to include five years support as a part of procurement,

considering the present scenario. After discussions, it was felt that latest features

like integration of PMUs, better GUI etc. could be specified and the replacement

system should be evergreen with the vendor providing the latest updates. It was

also agreed that WR constituents would be associated while finalizing the technical

specifications.

2.3 In this context WRLDC vide letter dated 7th May 2009 intimated the following:

(i) As per the directive of WRPC, Negotiation process with GE was initiated.

Three Negotiation Committees viz., one of WR constituents, other

POWERGRID Negotiation Committee followed by Senior level

POWERGRID Negotiation Committee held comprehensive negotiations

with M/s.GE, the original equipment manufacturer (OEM) of WR

SCADA/EMS systems. The initial price quoted by M/s.GE was Rs.46.14

crores which was brought down to Rs.32.5 crores after three rounds of

negotiations.

(ii) In respect of alternative arrangement suggested by WRPC a proposal

was received from M/s. OSI, however the same has many issues like

IPR, OSI not being the OEM and absence of competitive bidding. Based

on the experience of all other RLDCs, it is felt that OEM would be the

best option.

(iii) The extended AMC is to end on 31.05.2009, it is proposed that

maintenance be got done through M/s GE, the Original Equipment

Manufacturer in light of the above, considering all the related aspects to

ensure interrupt-free operation of the SCADA/EMS functionality at all the

Control Centers in WR.

2.4 Member Secretary, WRPC further stated that the above matter was discussed

in the TCC meeting held on 29th May 2009 and the various constituents expressed

their views.

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 4

Page 9: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Executive Director, WRLDC informed the TCC about the action taken by the SCADA

O&M Committee and WRLDC / PGCIL regarding LTSA arrangement for SCADA /

EMS under ULDC of WR. He stated that after two negotiations with M/s. GE, the

original equipment manufacturer (OEM), followed by third at Senior level PGCIL

Negotiation Committee constituted by Chairman, PGCIL the initial price of Rs. 46.14

Crores quoted has been brought down to Rs.32.5 Crores for 5 years maintenance.

He stated that with the stringent regulations from CERC, the RLDCs / SCDCs can

not afford to have any interruption in the process of monitoring the power system

through SCADA / EMS. This ULDC SCADA / EMS project is very complex and

having application software which is proprietary in nature and cannot be maintained

by other vendor. The third party cannot maintain the system unless they replace the

existing system. Further the kind of exposure and manpower we have, it will not be

possible to maintain the ULDC equipment by RLDC and SLDCs. In PGCIL the issue

has been seriously thought of and it has been opined that this maintenance should

be got done through OEM route. Also, this particular activity has been outsourced in

all other regions to OEM. The cost after negotiation has substantially come down

and accordingly the monthly charges will be of the order of about Rs. 5 to 8 Lakhs

per month per centre. Further, considering the distinct advantage of going through

OEM route and the kind of application we are spending for, the negotiated cost is

justified. He earnestly requested the TCC members to consider this favourably.

General Manager I/c (LD &C), PGCIL stated that the life expectancy of SCADA/EMS

system is about 7 years and the system becomes obsolete not totally but in terms of

software and the technological development and new addition that are going on. In

WR the SCADA / EMS system was commissioned in Feb. 2006 and as its cost-

recovery has not been fully made, replacement of the existing system cannot be

thought of at this stage. He further stated that PGCIL is now in process of planning

back up and up-gradation of Control Centres at RLDC as well as at SLDCs. The

future systems will be equipped with latest up to date technology available in the

market at the time of replacement / up gradation. So far as LTSA is concerned, he

stressed that there are always advantages of going through OEM route in this field

as it is highly technical area and the OEM has all historical data base besides issues

like IPR, source code protection etc. He added that other regions have also gone for

maintenance of their system through OEM route only. He further stated that the cost

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 5

Page 10: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

per control centre of WR with the negotiated price Rs. 32.5 Crs for 5 years works out

lower than the cost paid in SR. He felt that above negotiated price is reasonable and

the maintenance of WR SCADA/EMS can be entrusted to M/s GE. He assured that

PGCIL would make efforts to ensure that pending issues, if any, besides training etc.

will be looked into.

OSD, MPPTCL stated that though in their view the negotiated cost of Rs. 32.5

Crores is not reasonable, we do not have any alternative other than going to OEM.

He stated that earlier WRLDC had given the impression that third party can maintain

the system. Executive Director, WRLDC stated that earlier in WRP Committee

meeting held at Jabalpur, WRLDC told the Committee that maintenance of SCADA /

EMS is of proprietary nature and the third agency cannot maintain the application

software. However, as per the directions of WRP Committee, the SCADA O&M

Committee of WR looked into the matter and the progress was reported to the WRP

Committee.

Chhattisgarh State Power Transmission Co. Ltd. representative stated that even

though the WRP Committee was considering the maintenance through OEM route,

they advised to explore the alternate route so as to put pressure on bringing down

the cost offered by M/s GE. He felt that this has been done and the negotiated price

of Rs. 32.5 Crores is reasonable and may be accepted.

Chief Engineer (LD), MSETCL also felt that the price has now come down but still it

is felt that the same is more. He further stated that after 3-5 years we may have to go

for new system. He suggested that we may go for maintenance with M/s GE for

three years instead of 5 years and look for other alternative system within this period.

He opined that we should go for OEM route with exit option after 3 years as 2-3

years time will be required for establishment of new system. In this context, ED,

WRLDC stated that we could exit from the contract after 3 years, however, about

10% extra cost of the balance period will be required to be paid.

Chief Engineer (LD), GETCO stated that today we have not any alternative other

than OEM. He enquired whether any up-gradation of the existing system will be

possible during LTSA period. In this context, ED, WRLDC stated that this issue was

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 6

Page 11: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

discussed during the SCADA O&M committee meeting and M/s GE said that any up-

gradation would have to be done at extra cost. MD, Chhattisgarh State Power Transmission Co. Ltd., who chaired the TCC meeting

said that the TCC may recommend for LTSA through OEM route and the action for

going for alternate new system should be started two years earlier before expiry of

contract. After detailed deliberation, the TCC recommended the following:

(i) Real time Data availability is of utmost importance for grid operation,

for which interrupt free maintenance of LD equipment has to be

ensured.

(ii) In view of the above, it is preferable to assign the maintenance of

sophisticated load dispatch system to OEM.

(iii) So far as the alternative proposal of M/s. OSI is concerned, the same

has many issues like IPR, proprietary rights concerning the source

code, legal problems, etc. Awarding of contract on single bid to the

OSI will have its own problems and going for open tenders at this

stage will end up in non-availability of any maintenance service to the

existing SCADA facilities for a considerable period.

(iv) TCC recommended that LTSA be taken up with M/s GE for five years

at about Rs. 32.5 crores. Further action may be initiated in advance

i.e. in the 3rd year itself for alternative scheme.

2.5 The matter was further deliberated in the WRPC meeting. Director (O),

MSETCL said that the OSI had made earlier presentation and offering the good

system at very competitive rates. He also opined that there is still scope for further

negotiation with M/s GE.

Executive Director (F), GUVNL stated that during last meeting, WRLDC was

requested to go for alternative option also, prepare new specification, go for bidding

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 7

Page 12: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

for entirely new system. Further, the issue of IPR would have been arisen, if the

existing system is offered for maintenance to third party. It was also suggested that

while making specifications, provisions should be made for 10 years AMC. He

enquired the action taken in this regard.

2.6 Executive Director, WRLDC explained the background of the efforts taken to

finalize LTSA arrangements for SCADA / EMS system in Western Region. While

stating the actions taken in regard to the directions of WRPC in their 9th meeting for

exploring the alternative options, he emphasized the need for adopting OEM route

for ensuring interrupt-free availability of SCADA / EMS system for real time

monitoring and control of Western Region. He explained the difficulties likely to be

encountered in the gap period i.e. the period of commissioning of the replacement

system if the alternative option is adopted. In the light of this he strongly advocated

that WR constituents should unitedly opt for OEM route as the finally negotiated

price of Rs.32.5 Crores for five years i.e. Rs.6.5 Crores per year is comparable to the

LTSA arrangements tied up in Southern Region with the same OEM.

2.7 General Manager (LD & C), PGCIL stated that the present ULDC scheme in

WR is relatively new, just commissioned about three years ago and as such this is

not the right time to discard the same. He informed that the Pradhan Committee

report recommends that the RLDC / SLDC SCADA scheme have to be replaced and

re-looked after 7 years of service. He suggested that right now, the present ULDC

SCADA / EMS scheme of WR be continued and maintained through OEM and after

3 years or so, replacement of it could be thought of. He added that replacement of

the existing system with new system is not an easy task as lot of activities such as

operation of new system in parallel with the existing one; its evaluation etc. will go

into it.

Director, ESSAR Power Ltd. stated that new system should not be introduced for the

sake of changing the system. Studies may be carried out and whatever up-gradation

is possible may be done. While going for the new system, it may be ensured that the

vendor will be responsible for up-gradation/maintenance, which is required in future

also as the life of the equipment is around 10 years plus. He opined that LTSA may

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 8

Page 13: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

be done through OEM who will take responsibility if something goes wrong

tomorrow. He further observed that the price has been negotiated to the best value.

2.8 Director (O), PGCIL also highlighted the need and advantages of OEM route

and stated that there is no need for replacement as the existing system is

commissioned only in February, 2006 and the capability of the systems are required

to be fully explored. Further, the existing system should be continued till there is a

major technological change like integration of PMUs etc. takes place and available in

the market. He further stated that in future we need a dynamic & intelligent system

as compared to passive system what we have today as many actions in real time

have to be done automatically due to complexity of the grid. He added that PGCIL

has already initiated action in this area. He desired that the maintenance of

SCADA/EMS of ULDC of WR may be awarded for five years to OEM with a provision

of coming out of it after three years.

Director (O), MSETCL suggested that one more round of meeting may be held with

M/s GE, wherein MD, GETCO and CMD, MPPTCL should also be requested to

participate. Date of this meeting could be fixed in consultation with them.

2.9 The matter was deliberated in detail. The WRP Committee agreed for LTSA through OEM route and decided that senior level officers of WR constituents would also interact with M/s GE for further negotiation, if any. It was tentatively proposed to have the meeting of WR constituents with M/s GE on 9th June, 2009 and Member Secretary, WRPC would coordinate the same. It was also agreed that after the negotiation with M/s GE at the senior level, WRLDC/PGCIL would go ahead with awarding of maintenance of SCADA/EMS system in Western Region to M/s GE and LTSA arrangements with them. The WR constituents further opined that replacement action for the new system should be initiated before the end of three year period so that the new system could be in place by the end of the LTSA period. PGCIL agreed to take necessary action in this matter.

(Action: WRPC/WRLDC)

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 9

Page 14: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

ITEM No.3: TRANSMISSION SYSTEM ASSOCIATED WITH THE TILAIYA ULTRA MEGA POWER PROJECT (4000 MW) IN JHARKHAND, NABINAGAR (1000MW) OF RAILWAYS AND NTPC, BARH-II (1320 MW), RIHAND-III (1000MW), VINDHYACHAL-IV (1000MW) AND MAUDA (1000MW) OF NTPC, AND IPPS IN JHARKHAND, ORISSA, MP, CHATTISGARH AND MAHARASHTRA

3.1 Member Secretary, WRPC stated that in 28th meeting of the Standing

Committee on Power System Planning in WR held at Aurangabad on 6th December

2008, the transmission system associated with Tilaiya Ultra Mega Power Project

(4000 MW) in Jharkhand, Nabinagar (1000 MW) of Railways and NTPC, Barh-II

(1320 MW), Rihand-III (1000 MW), Vindhyachal-IV (1000 MW) and Mauda (1000

MW) of NTPC, and IPPs in Jharkhand, Orissa, MP, Chhattisgarh, and Maharashtra

were discussed and identified. The transmission scheme were identified in four

groups, viz. (i) generation specific, (ii) system strengthening common for WR and

NR, (iii) system strengthening for WR and (iv) pooling stations for IPPs in Orissa.

Also, proposal for sharing of transmission charges had been discussed and

recommended in the above Standing Committee Meeting. Further, the

recommendations of the above Standing Committee were discussed in detail during

9th meeting of WRP Committee held on 16th January 2009 wherein some of the

members expressed that the minutes of Standing Committee Meeting were received

only few days earlier and they needed time to examine the same. After discussions

in the 9th WRP Committee meeting, it was decided that:

(i) The constituents will furnish their comments on the minutes of

28th Standing Committee Meeting on power system planning in WR to

CEA at the earliest.

(ii) The constituents if so desire may seek any clarification from CEA and

communicate their views to them.

(iii) CEA will convey a meeting to discuss and finalize the transmission

scheme and in case, the clearance is given, by the constituents of WR to

the same, the matter will not again put up to WRPC for its approval.

3.2 Member Secretary, WRPC informed that subsequently, comments were sent

to CEA by Chhattisgarh, MPPTCL and MSETCL. CEA accordingly clarified the

matter in a Special Meeting of the Standing Committee on Power System Planning

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 10

Page 15: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

of WR held on 18th April 2009. Member (PS), CEA in the meeting stressed that the

proposal circulated in the agenda for the 9th WRPC meeting identifying the

transmission scheme etc. was basically a sort of master plan for evacuation of power

from various IPPs and other projects anticipated in the same time frame. Also, as

desired by MSETCL in their comments, PGCIL made a presentation in the above

Special Standing Committee meeting, highlighting how the transmission charges

would vary with the commissioning of System strengthening for WR and System

strengthening common for WR and NR and its impact on pooled transmission

charges. Members desired that the details of the calculations and the assumptions

made should be circulated to the various constituents of the WR along with the

calculation of corresponding transmission charges of NR which is likely to share the

capacity of the project(s). CSPTCL suggested that only one Rourkela-Raigarh 400

kV D/c line be LILOed at Jharsurgada instead of all the 4 circuits, as proposed in the

28th SCM. Member (PS), CEA explained that LILO of all the 4 circuits is a temporary

arrangement, and once the Jharsurgada-Dharamjaygarh-Jabalpur link is available,

LILO of one D/c will be removed at Jharsurgada.

3.3 Member Secretary, WRPC stated that the detailed transmission scheme as

decided in the 28th meeting of the Standing Committee on Power System Planning in

WR held at Aurangabad on 6th December 2008 and subsequent modification therein

suggested by PGCIL in name of pooling station etc. during Special Meeting of the

Standing Committee on Power System Planning of WR held on 18th April 2009 is

enclosed at Annexure- 3. The actual programme with each of the projects once

finalized would be brought forth in the SCM. He added that the matter was

discussed in detail in the Special Meeting of the Standing Committee on Power

System Planning of WR held on 18th April 2009 and all the constituents agreed with

the proposal.

3.4 In the TCC meeting held on 29th May 2009, representative of Chhattisgarh

State Power Transmission Co. Ltd. (CSPTCL) stated that in the Special Meeting of

the Standing Committee on Power System Planning of WR held on 18th April 2009,

CEA stated that the above transmission scheme is a master plan for evacuation of

power from various IPPs and other projects anticipated in the same time frame. The

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 11

Page 16: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

actual programme with each of the projects, once finalized, will brought forth in the

Standing Committee meeting.

3.5 In the TCC meeting held on 29th May 2009, the members agreed to the scheme and stressed that the actual programme with each of the projects, once finalized, will be brought forth in the Standing Committee meeting and to WRPC meeting. Also, any change in the transmission scheme, if any, subsequent to discussion in other region, will have to be brought to the notice of WRP Committee for its approval. It was also stressed that as discussed in the Special SCM, held on 18th April 2009, the details of cost of transmission scheme should be sent to all the constituents by PGCIL. 3.6 WRP Committee discussed the matter and endorsed the views of the TCC. PGCIL representative stated that the details of the transmission cost will be furnished to all the concerned by 5th June 2009.

(Action: PGCIL)

ITEM No.4: TRANSMISSION SYSTEM CONNECTED WITH VINDHYACHAL POOLLING STATION AND PHASING OF TRANSMISSION WORK

4.1 Member Secretary, WRPC stated that during the Special meeting of Standing

Committee on Power system Planning of WR held on 18th April 2009 at WRPC

office, Mumbai, it was intimated that Vindhyachal-IV, Rihand-III and Aryan Coal were

presently proposed to be connected to 765/400 kV Vindhyachal pooling station. As

the generators would be coming in different time frame, the transmission system

from Vindhyachal pool onwards up to Gwalior would need to be initially operated at

400 kV to avoid reactive power management problem. Therefore, CEA suggested

the following phasing of transmission system interconnected from Vindhyachal pool.

(i) When the initial unit at Vindhyachal stage-IV and Rihand-III generation are

commissioned they could be connected to Vindhyachal Pooling point and

the Vindyachal Pooling-Satna-Gwalior 765 kV link be charged at 400 kV

level.

(ii) In this time frame few units at Sasan would only be commissioned and

there would not be any short circuit level problems at Vindhachal 400 kV

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 12

Page 17: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

generating bus due to LILO of Vindhyachal- Jabalpur 400 kV D/C at

Sasan.

(iii) When the entire planned generating stations connected to Vindhyachal

pooling station are commissioned, at that stage the Vindyachal Pooling-

Satna-Gwalior link can be charged at 765 kV level along with

interconnection of Sasan-Vindyhachal 765 kV S/C.

(iv) After charging at 765 kV level the LILO of Vindhyachal – Jabalpur 400 kV

D/C line at Sasan could be disconnected with suitable switching

arrangements at Sasan 400 kV switchyard to meet its starting power

requirements in future.

The above was agreed to in the Special meeting of Standing Committee and it was

also decided that for implementation the following works could be taken up as a

separate project associated with Vindhyachal-IV and Rihand-III.

Transmission System associated with Vindhyachal-IV and Rihand-III A. Generation Specific Transmission System

Rihand-III (1000MW)

• Rihand-Vindyachal pooling 2xS/C 765kV lines operated at 400kV

(under preview of NTPC)

Vindhyachal-IV (1000MW)

• Vindhyachal-IV – Vindhyachal pooling 400kV quad D/C line (under

preview of NTPC)

B. System strengthening common for WR and NR

• Vindhyacal pooling station with 2x1500MVA 765/400kV (initially to be

a switching station at 400 kV level)

• Vindhyachal pooling-Satna 2XS/C 765kV lines ( initially to be

operated at 400 kV)

• Satna-Gwalior 765kV 2XS/C (initially to be operated at 400 kV)

• Vindhyachal-Sasan 765 kV S/C

4.2 Member Secretary, WRPC stated that in the TCC meeting held on 29th May

2009, NTPC requested that the transmission scheme from the generator to the

nearest pooling point may be taken up by PGCIL. In this context, it was pointed out

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 13

Page 18: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

that as per the minutes of Standing Committee on Power system Planning of WR

held on 18th April 2009, the lines mentioned under generation specific system are

under NTPC purview. PGCIL, however, stated that they could take up the job on

deposit basis.

4.3 General Manager (Comml.), NTPC stated that allocation of power from

Vindhyachal-IV (1000 MW) will be done to the various beneficiaries of WR by the

MoP and as such for Vindhyachal IV – Vindhyachal pooling 400 kV D/c line should

be pooled in the regional transmission scheme. GUVNL representative enquired

whether the full generation of Vindhyachal –IV will be allocated to WR beneficiaries.

NTPC stated that allocation will be made by the Ministry of Power. It was also

clarified by NTPC that Rihand-III is for Northern Region and as such charges for the

line from Rihand-III to Vindhyachal pooling will be borne by NR beneficiaries.

4.4 WRP Committee deliberated the matter in detail and agreed to the transmission scheme as proposed in the para 4.1 above. So far as sharing of transmission charges for Vindhyachal IV – Vindhyachal pooling line was concerned, the WRP Committee requested NTPC to discuss the matter again in the Standing Committee on Power System Planning of WR and thereafter may be taken up in TCC and WRPC for further discussion. NTPC agreed to the same.

(Action: NTPC) ITEM NO. 5: ALLOTMENT OF TRANSMISSION CAPACITY TO IPPs AGAINST

THEIR APPLICATION FOR AVAILING LTOA 5.1 Member Secretary, WRPC stated that various issues raised by the

constituents concerning granting of Long Term Open Access were deliberated in the

last meeting of TCC held on 15th Jan. 2009 and in the 9th meeting of WRPC held on

16th January 2009, and it was recommended that:

(i) CTU should circulate a paper to the constituents of WR on the criteria,

procedure etc. being followed by them in processing of application for

granting of Long Term Open Access.

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 14

Page 19: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

(ii) A meeting should be convened by PGCIL by first week of Feb. 2009 to

discuss the above issues on LTOA.

(iii) It was also suggested that LTOA meeting may be separately held well

before Standing Committee meeting on Power system Planning of WR.

5.2 Accordingly, General Manager (Engg), PGCIL vide letter dated 23rd Feb. 2009

circulated a base paper on procedure for granting of LTOA to all the beneficiaries.

Subsequently, in the Special Meeting of the Standing Committee on Power System

Planning of WR held on 18th April 2009, PGCIL made presentation regarding the

methodology, procedure and the payment security mechanism being adopted by

them for grant of Long Term Open Access.

5.3 In the above Special meeting, PGCIL clarified that grant of LTOA was being

done in four stages. In the first stage discussion were held with the IPPs regarding

achieving of various milestones viz. acquisition of land, allocation of coal and water,

environment clearance, placement of orders for equipment, payment of advance to

manufacturers, EPC contractors etc., and only after some progress was noted and

after observing the progress of project take off, further discussion were held with the

IPPs and grant of LTOA was considered. In the second stage discussions with IPPs

and beneficiaries were undertaken in the SCM and LTOA meetings. The third and

fourth stage was security mechanism like Bank Guarantee from IPPs along with

signing of BPTA and 6 months advance transmission charges corresponding to the

capacity for which PPA had not been signed by the IPP with beneficiary states(s).

Regarding time frame for granting LTOA, PGCIL informed that as per draft open

access regulations the nodal agency was required to dispose of the application for

connectivity within 60 days and norms for medium term open access were even

stringent and suggested holding of Standing Committee Meetings every two months.

In the special SCM, it was also clarified by Member (PS), CEA that as per the

Electricity Act 2003 and the existing regulations, non-discriminatory open access had

to be granted in case existing margins were available. In case the existing

transmission margins were not adequate for grant of LTOA, additional transmission

lines were being planned and built. The transmission capacity was for the

beneficiaries and was not allocated to the generators. As and when the allocation

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 15

Page 20: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

from the generator would get finalized and the beneficiary signs BPTA with the CTU

then the transmission capacity would get allocated to the beneficiary. Many of the

IPPs were indicating target beneficiaries because the distribution / transmission

licensees could procure their power requirements only through competitive bidding

process and this process took time. To facilitate IPPs, the above methodology was

being adopted. In case of Merchant Power Plants if the actual sale of power was

different from the one indicated and for which open access had been granted then as

per present regulations, in addition to long term open access charges, short term

open access charges would also be applicable. Regarding planning of transmission

system CEA further clarified that planning of transmission was being done

considering various perspective load generation scenarios during different periods of

the year and transmission was being planned considering the worst case scenario.

CEA also further clarified that any transmission capacity built and not allocated to

any agency on long-term basis would be allocated to other agency on medium term

or short-term basis. In the event there is a delay in commissioning of any IPP, the

long term transmission capacity granted to it would be made available to any other

generator coming up in the time frame and the additional transmission required for

the delayed IPP would be built to match with its commissioning so that unutilized

transmission capacity is not built up and the Transmission companies are not

unnecessary burdened with additional transmission charges. The transmission

system would be optimal to take care of the requirement meeting the planning

criteria.

5.4 Representative of CSPTCL stated that transmission system over loading

problems have been experienced in their system after injection of generation by

LANCO-Amarkantak station, which has been granted LTOA. He requested that

LTOA to various IPPs from the existing transmission capacity should not be granted

till Hon’ble CERC issues new regulations concerning to LTOA etc.

In the above context, representative of PGCIL stated that they have granted LTOA

after consultation with all the constituents and CEA in accordance with existing

CERC regulation. Further, till Hon’ble CERC issues the new regulations, LTOA

applications received by them have to be processed on the basis of existing

regulations only.

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 16

Page 21: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

5.5 ED (L & RA), M.P. Trading Co. Ltd. stated that MP Tradco has entered a long

term power purchase agreement with M/s PTC India Ltd. for availing entire power

generated by Unit No. 1 (300 MW) of LANCO-Amarkantak TPS. However, M/s

LANCO-Amarkantak Pvt. Ltd., issued notice vide letter dated 13.03.2008 for

termination of PPA which has been stayed by Hon’ble High Court of M.P. vide order

dated 31.3.2008. As the matter is sub-judice, M.P. Tradco requested that M/s

LANCO should not be granted either long term or short term open access for supply

of power to any utility other than Madhya Pradesh. He requested the WRP

Committee to accordingly address the issue and take a decision in the matter.

In this context, Member Secretary, WRPC stated that responsibility of granting long

term or short term open access, as the case may be, vests with CTU / RLDC as per

the provisions under the CERC regulations and WRP Committee is not empowered

to give any directions in the matter.

Director (O), PGCIL while endorsing the views of Member Secretary, WRPC, stated

that, as the matter is sub-judice, it should not be discussed. The request of M.P.

Tradeco not to grant either long term or short term open access to LANCO-

Amarkantak for supply of power to any utility other than Madhya Pradesh is a legal

issue and have to be addressed accordingly.

5.6 During the TCC meeting held on 29th May 2009, the members stressed that

the details regarding the status of LTOA applications granted by PGCIL should be

made available on their web site. PGCIL was accordingly requested to do the

needful, which was agreed to by PGCIL.

The WRP Committee members noted as above.

(Action: PGCIL) ITEM No.6: PERFORMANCE OF WR GRID DURING JAN. 09 TO MAY 09 6.1 SYSTEM PERFORMANCE Member Secretary, WRPC stated that during the period January 2009 to March

2009, the grid operated in the frequency range of 49.0 Hz to 50.5 Hz for 98.51% of

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 17

Page 22: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

time. The percentage time when frequency was within this range varied between

97.79 % to 99.66 %. During this period, frequency remained below 49.0 Hz for 2.43

% of time. From 1st April 2009, CERC has amended the permissible frequency

range for system operation to 49.2 Hz – 50.3 Hz. During the months of April and

May 2009, grid frequency remained in the revised frequency band for 80.93 % and

91.21 % respectively time and it remained below 49.2 Hz for 18.75 % and 6.45 % of

time respectively . The frequency profile during the period was generally satisfactory

except on a few days in February, 2009 and April, 2009, when drawal by NR and ER

increased due to sudden weather changes / generating unit outages. The

comfortable system performance during most of the period was due to marginal drop

in unrestricted demand as compared to last year and improved availability due to

synchronization of new generating units at Sugen, NSPCL-Bhilai, Sipat and

Trombay. The details of frequency profile during the period from January 2009 to

May 2009 are furnished at Annexure 6.1(a).

The unrestricted demand of Western Region during the period varied between 35700

MW to 37400 MW. The corresponding figures for the previous year were between

36600 MW to 39800 MW. The maximum demand met during the period was 31608

MW and the region faced capacity shortage in the range of 5300 MW to 6400 MW.

The details of Unrestricted Demand vs. Demand Met and Energy Requirement vs.

Availability are furnished at Annexure.6.1 (b).

During the discussions in the TCC and WRPC meetings, ED, WRLDC pointed out

that though the frequency regime during the period was generally satisfactory, on

some days frequency was quite low. During the month of April 2009, system

frequency touched 48.8 Hz for more than 300 times. However, operation of under

frequency relays installed under AUFLS Scheme was found to be inadequate .He

stated that UF relays are required to be kept in service to act as defense mechanism

against any unforeseen incidents. He requested the constituents to ensure

healthiness of UF relays and to keep them in readiness to provide desire load relief.

WRP Committee endorsed the above

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 18

Page 23: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

6.2 Voltage Profile 6.2.1 Committee noted the month wise details of voltages at 400 kV & 765 kV sub-

stations during the month of January, 2009 to May, 2009 is placed at Annexure-6.2.

6.2.2 During the period low voltage was observed at Sipat and Seoni 765 kV sub-

stations which touched 726 kV & 720 kV respectively on few occasions.

High voltage was recorded at 400 kV throughout the period at Dhule, Itarsi and

Karad S/s in the order of 415 kV to 440 kV. To contain high voltages WRLDC had to

resort to opening of 5 to 6 lines on many days. In order to control incidences of high

voltages during low load periods, installation of reactors at following locations has

been planned by various utilities:-

Sl.No. 400 kV Substation

Size (MVAR)

Implementing Agency

Expected Commissioning date

1. Khandwa 1x125 PGCIL June,2010 2. Dhule 2x50 MSETCL Oct.,2009 / Dec.,2009 3. Dehgam 1x125 PGCIL June,2010 4. Kasor 1x125 GETCO November,2009 5. Karad 1x80 MSETCL May,2009 6. Nardipur 1x80 GETCO October,2009

Constituents were also requested to ensure timely commissioning of these reactors

as this would help in smoothening of high voltage profile in Western Regional Grid.

MS, WRPC informed that the issue regarding high voltage in Dhule area was

discussed in the 9th meeting of WRPC held on 16th January, 2009. It was pointed

that even after taking all other actions, including opening of a number of lines, high

voltage problem was still persisting. PGCIL was therefore requested to carry out

fresh studies to examine the requirement of bus reactor around 400 kV Nagda /

Rajgarh sub-station.

He further informed that the matter was also discussed in the special meeting of the

Standing Committee on Power System Planning in Western Region held on

18th April, 2009. In this meeting, PGCIL intimated that according to studies carried

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 19

Page 24: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

out by them, installation of 1 X 125 MVAR bus reactor at Nagda / Rajgarh would be

beneficial to control over voltages. After examining various options, installation of

1 x 125 MVAR bus reactor at Rajgarh sub-station was agreed to in the standing

committee meeting.

WRP committee discussed the matter and concurred with the proposal. ITEM No.7: WIDE AREA MANAGEMENT SYSTEM OF WR

7.1 Member Secretary, WRPC stated that WRLDC vide letter dated 7th May 2009

intimated that the existing SCADA / EMS provides the data which are steady state in

nature and not suitable for dynamic monitoring and control of Grid due to high

degree of latency of telemeter data and also non-synchronization of sampling of

data. Emerging technologies like Wide Area Measurement System (WAMS) using

Phasor measurement Unit (PMU) provide more advanced measurement system that

will utilize synchronized measurements from geographically distant locations and

increase the situational awareness by monitoring a wide area of power system in

real time.

In this regard WRLDC intimated that TCS has approached PGCIL to join the

consortium team of TCS, IIT Bombay and Tata Power for executing a PMU based

project which has been approved by Council of Scientific and Industrial Research

(CSIR) of Department of Science & Technology, Government of India, under the

NMITLI (New Millennium India Technology Leadership Initiative) program. CSIR will

provide Loan for the project. The main features of the project are as follows:

(i) Installation of PMUs (Phasor Measurement Units) at around 25 to 30

locations in Western Region Grid. The data from PMUs shall be acquired

at Western Regional Load Despatch Centre (WRLDC)

(ii) Development of software functions using PMU data.

WRLDC further intimated that the PGCIL share of total estimated cost of the project

is Rs. 8.76 crores. The loan from CSIR is to be repaid over 10 years at an interest

rate of 3% after completion of the project. The annual installments shall be ranging

from Rs. 90.267 lakhs to Rs. 127.01 lakhs. WRLDC further informed that a Pilot

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 20

Page 25: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Project for implementation of PMUs in Northern Region has been agreed upon in

Northern Region during the last NRPC meeting held on 22.04.2009. WRLDC have

proposed that the PMU project in respect of Western Region could be funded

through UI CAP fund or Additional UI funds. Alternatively the constituent may finance

the project and make yearly advance payment to PGCIL.

7.2 In the TCC meeting held on 29th May 2009, GM I/C (LD & C), PGCIL made

detailed presentation on CSIR approved project under their NMITLI (New Millennium

India Technology Leadership Initiative) programme namely “Intelligent monitoring &

Control of the interconnected Power Grid using Wide Area Measurements (WAM)”. A

copy of the presentation is enclosed at Annexure- 7.2. The presentation was well

received and appreciated by the constituent members. However, as this project is of

high/new technology area, the TCC recommended that the technical details etc. of

the project may be discussed in a meeting of all the constituents of WR at working

level and thereafter the matter should be put up to TCC/ WRPC for further direction.

7.3 During the RPC meeting, Director (O), MSETCL stated that in Maharashtra

they had already commenced the work relating to Wide Area Measurement in

collaboration with CPRI and IIT, Kanpur after discussing the same with CEA and

MoP. At such a juncture, parallelly doing the same in WR is not desirable. In

Maharashtra they are quite serious about this project, which is highly technical and

first of this nature. He desired that let this project be implemented in small system

and then can be thought at region as whole. Further, in PGCIL proposal what

activities are going to carried out under the proposed cost of Rs. 8.76 crores is not

clear.

Director (O), PGCIL stated that taking up the above project at Regional level is not a

duplication of work. It is a development work, which is complex in nature. Executive

Director, WRLDC stated that for Regional Grid like WR, which is very large,

technically getting exposed to WAM technology is the need of the day. The

integration of heterogeneous PMU of Maharashtra with matching protocol with rest of

regional system will certainly needs expertise and experience. He requested that this

matter could be discussed separately to understand the WAM technology etc.

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 21

Page 26: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

7.4 The matter was deliberated in detailed and the WRP Committee endorsed the

decision of TCC. It was decided that technical details of the project may be

discussed in the Regional Protection Committee meeting and hereafter the matter

will be put up to TCC / WRPC for further direction.

ITEM No. 8: BILLING OF TRANSMISSION CHARGES FOR WHEELING OF

CENTRAL SECTOR POWER TO UT OF DD, DNH & GOA 8.1 Member Secretary, WRPC stated that WRTS-I, PGCIL during 52nd meeting of

Commercial Committee held on 9th April 2009, intimated that Service Tax Cell of

Central Board of Excise and Customs have issued summons for furnishing data

regarding Service Tax recovery. PGCIL therefore felt that collection of wheeling

charges by POWERGRID for MSETCL / MSEDCL and GETCO / GUVNL may have

to be discontinued from April 2009 and the concern transmission companies viz.

GETCO and MSETCL should take up the billing/collection from April 2009. During

the above meeting of Commercial Committee, it was pointed out that the decision of

pooling of wheeling charges in PGCIL bill was taken in WRE board meeting.

Further, the matter regarding fixation of and adjudication of the transmission charges

of GETCO system used for transmission of Central Sector power to DD / DNH was

under consideration of Hon’ble CERC and was scheduled for hearing shortly. As

such, constituents of WR stressed that till such time any order is given by CERC, the

present methodology of billing of transmission charges for wheeling of central sector

power to DD & DNH and Goa should be continued. This would facilitate the

adjustment/recovery of any transmission charges, as the entire record and billing

details are available with PGCIL.

8.2 The above matter was discussed in the TCC meeting held on 29th May 2009

and TCC agreed to the views of CCM i.e. till such time any order is given by the

Hon’ble CERC in respect of determination of transmission charges for GETCO

system for wheeling of Central Sector power to DD & DNH, the present methodology

of billing of transmission charges for wheeling of central sector power to DD & DNH

and Goa through PGCIL should be continued. This would facilitate the

adjustment/recovery of any transmission charges, as the entire record and billing

details are available with PGCIL. Thereafter the billing of the transmission charge for

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 22

Page 27: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

wheeling of central sector power should be done by GETCO / MSETCL directly, as

per REA issued by WRPC.

WRP Committee endorsed the decision of TCC. ITEM No. 9: RENOVATION AND MODERNISATION OF WRPC OFFICE

BUILDING Member Secretary, WRPC informed the Committee that WRPC office building is

around 30 years old and is in urgent need of major repairs. The building also needs

architectural renovation and improvement in facilities such as conference Hall, guest

house etc. He further informed that according to preliminary assessment the

complete R&M of the building is estimated to cost about 4 crores. However, the

actual estimate will have to be prepared by the executing agency. He proposed that

the cost of R&M be shared by the members of WRPC who are sharing the

establishment expenditure of WRPC Secretariat. Also agency for carrying out these

works needs to be decided.

Member ( GO& D) , CEA stated that Powergrid have sometime back renovated the

WRLDC building which is adjacent to WRPC. He, therefore, proposed that R & M of

WRPC could also be carried out by Powergrid so that the similarity of the two

buildings can be maintained.

WRP Committee discussed the matter and agreed that the R & M of WRPC building

could be carried out by Powergrid on deposit basis. Cost of R & M shall be equally

shared by the members of WRPC who are bearing the establishment expenditure of

WRPC Secretariat. WRP Committee also authorized the Chairman, WRPC to

approve the estimate submitted by Powergrid.

ITEM No. 10: PAYMENT OF TRANSMISSION CHARGES FOR INTER-STATE

TRANSMISSION Member Secretary, WRPC informed that in accordance with Central Electricity

Regulatory Commission (Terms & Condition of Tariff) Regulation, 2009, the monthly

Energy account (REA) issued by RPC shall also include a statement specifying the

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 23

Page 28: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

ratio in which transmission charges for interstate transmission system for that month

are to be shared by transmission users in accordance with regulation 3.3. Also, the

bill for transmission charges (inclusive of incentive) for transmission charges for a

month should be raised by the transmission licensee based on its estimate of

Transmission System Availability Factor (TAFM) for the month and adjustment, if

any, has to be made on the basis of TAFM to be certified by the Member Secretary

of WRPC within 30 days from the last day of the relevant month.

This matter was discussed in 52nd meeting of Commercial Committee held on 9th

April 2009 and it was proposed that PGCIL would make available the details of

outages (certified by WRLDC) to all the beneficiaries by 10th of the following month.

Concerned beneficiaries, after examining these details, should furnish their

comments / observations, if any, to WRPC by the 20th of the month. For example,

outage details for the month of April 2009 will be made available by PGCIL to

beneficiaries by 10th of May 2009. Comments of beneficiaries should be furnished to

WRPC 20th May 2009. In case of non-receipt of the same by this time period, it will

be taken, as no comments. Member Secretary, WRPC, will certify the TAFM

accordingly. All the members agreed to the same.

WRP Committee noted as above. ITEM No.11: COMPUTATION OF PAYMENT OF CAPACITY CHARGES FOR

THERMAL GENERATING STATION

Member Secretary, WRPC informed that Clause 21(4) of Central Electricity

Regulatory Commission (Terms and Conditions of Tariff) Regulation, 2009, which

has come into force w.e.f. 1.04.2009, envisaged that in case of fuel shortage in a

thermal generating station, the generating company might propose to deliver a

higher MW during peak-load hours by saving fuel during off-peak hours. The

concerned Load Despatch Centre may then specify a pragmatic day-ahead schedule

for the generating station to optimally utilize its MW and energy capability, in

consultation with the beneficiaries. Average Declared Capacity i.e. DCi in such an

event shall be taken to be equal to the maximum peak-hour ex-power plant MW

schedule specified by the concerned Load Despatch Centre for that day.”

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 24

Page 29: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Member Secretary, WRPC further stated that the matter was deliberated in 52nd

meeting of Commercial Committee held on 9th April 2009 and it was decided that the

following methodology will be adopted in WR for computation of DCi in case of fuel

shortage:

(i) Peak Hours would generally be worked out by taking into regional load of

previous days or similar day of the previous week.

(ii) It would be of continuous 5 Hrs. (20 time blocks of 15 minutes)

(iii) The entire year will be divided in two seasons i.e. April to September as

summer and October to March as winter season.

(iv) Peak Hours during the month of April to September- 1800 Hrs to 2300 Hrs.

(v) Peal Hours during the month of October to March – 1700 Hrs to 2200 Hrs.

(vi) DCi will be taken equal to maximum ex-power plant MW schedule

specified by the WRLDC continuously during the above defined peak

hours for that day

WRP Committee noted the same. ITEM No.12 : IMPLEMENTATION OF REVISED UI CHARGES W.E.F. 01.04.09 Member Secretary, WRPC informed that Central Electricity Regulatory Commission

(Unscheduled Interchange charges and related matters) Regulation, 2009 has been

notified by the Commission vide Notification No.L-1(1)/2009-CERC dated 30th March

2009. These regulations have come into force on 01.04.2009. Clause 7 of the above

regulation “Limit on UI volume and consequences of crossing limits envisages the

following:

(a) The over-drawal of electricity from the schedule by any beneficiary or a buyer

during a time-block shall not exceed 12% of its scheduled drawal or 150 MW (whichever is lower) when frequency is below 49.5 Hz, and 3% on a daily aggregate basis.

(b) The under-injection of electricity from the schedule by a generating station or by a seller during a time-block shall not exceed 12% of the scheduled injection of such generating station or seller when frequency is below 49.5 Hz, and 3% on daily aggregate basis.

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 25

Page 30: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

(c) In addition to UI Rate corresponding to frequency of 49.2 Hz, as stipulated under regulation 5, an Additional Unscheduled Interchange Charge at the rate equivalent to 40% of the UI Rate corresponding to frequency of 49.2 Hz shall be applicable for over-drawal or under-injection of electricity for each time-block when grid frequency is below 49.2 Hz. Provided that for under-injection of electricity during the time-block when grid frequency is below 49.2 Hz for the generating stations using coal or lignite or gas supplied under Administered Price Mechanism (APM) as the fuel, Additional Unscheduled Interchange Charge shall be equivalent to 40% of the UI Cap Rate.

(d) Payment of Unscheduled Interchange Charges under regulation 5 and the Additional Unscheduled Interchange Charge under (c) above, shall be without prejudice to any action that may be considered appropriate under section 142 and section 149 of the Act for contravention of the over-drawal and under-generation limit specified in these regulations, for a time block when frequency is below 49.5 Hz.

(e) The Commission may from time to time, if considered necessary, prescribe the Additional Unscheduled Interchange Charge for over-drawal or under-injection of electricity during the time-block when grid frequency is below 49.5 Hz and up to 49.2 Hz.

(f) Any over-drawal and under-injection of electricity shall be computed in

accordance with the methodology used for preparation of ‘Regional Energy Accounts’.

(g) Provided that the Regional Load Despatch Centre shall prepare and publish on its website the records, on monthly basis, of the UI Accounts, specifying the quantum of over-drawal/under-generation and corresponding amount of UI paid/received for each beneficiary or buyer and generating station or seller for the time-blocks when grid frequency was below 49.2 Hz and between 49.5-49.2 Hz separately.

Further, UI rate in a time block (15 minute) will be capped at 408 paise per kWh for

all generating stations using coal or lignite or gas supplied under Administered Price

Mechanism (APM) as fuel in case when actual generation is higher or lower than the

scheduled generation in the frequency range between 50.3 Hz and upto 49.2 Hz.

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 26

Page 31: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

In view of the above, the procedure to be followed w.e.f. 1st April 2009 for

preparation of UI charges was discussed in 52nd meeting of Commercial Committee

held on 9th April 2009 and agreed.

So far as Application of fund collected through UI is concerned, Clause 11 of Central

Electricity Regulatory Commission (Unscheduled Interchange charges and related

matters) Regulation, 2009 envisages that the amount left after final settlement of

claims of Unscheduled Interchange charges of the generating station and the

beneficiaries shall be utilised, with the prior approval of the Commission, for either or

both of the activities viz. (a) Servicing of investment for transmission schemes of

strategic importance and (b) Providing ancillary services including but not limited to

‘load generation balancing’ during low grid frequency as identified by the Regional

Load Despatch Centre, in accordance with the procedure prepared by it, to ensure

grid security and safety. However, the amount of fund, allocable for the above

purposes shall be decided by the Commission from time to time.

WRP Committee noted the same.

ITEM No. 13: SHIFTING OF SLDC BHILAI TO RAIPUR 13.1 Member Secretary, WRPC stated that in order to improve the data reliability

from SLDCs to RLDC and vice versa, scheme for backup communication links from

SLDCs and strategic locations in the network of ULDC scheme of WR was

discussed and approved in the 7th meeting of WRP Committee held on 3rd May 2008.

During this meeting, CSEB intimated that SLDC, Bhilai is to be shifted to Raipur and

as such the corresponding expenditure for data communication link from Raipur to

Bhilai shall required to be pooled in regional system. The WRP committee had

agreed to the same. Subsequently, during 9th meeting of WRP Committee held on

16th Jan. 2009 WRTS-I, PGCIL intimated that cost estimates (about Rs. 5.16 Crores)

have been worked by them based on inputs from CSEB and requested WRP

Committee for its approval. The WRP Committee members deliberated the matter

and gave in principle approval for the same. However, it was suggested by MPPTCL

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 27

Page 32: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

that the SCADA Committee of WR may examine the cost estimates worked out by

PGCIL.

13.2 In view of above, in the meeting of Regional SCADA/Communication Co-

ordination group (RSCG) held at WRLDC, Mumbai on 12th March 09, the details of

break up of cost estimates of Rs. 5.16 Crores was examined and discussed in detail.

The SCDA/ Communication Committee found the above estimates technically

justified. However, some of the constituent states of Western Region did not agree to

pool the expenditure. CSEB insisted that the issue of sharing the above expenditure

has been agreed in WRP Committee meeting and the decision already taken should

not be reviewed. In view of this, WRLDC, PGCIL requested to discuss the matter by

the member of Commercial Committee.

13.3 Member Secretary, WRPC informed that the matter was discussed in the 52nd

meeting of Commercial Committee. It was stressed that this Committee cannot

review the decision taken by WRP Committee for pooling the expenditure in the

regional system. Further, it was reiterated that the WRP Committee gave the

mandate to the SCADA Committee to the extent of examination of the cost estimate.

13.4 In the TCC meeting held on 29th May 2009, Chief Engineer (SLDC), GETCO

pointed out that the proposed work of Chhattisgarh including wideband equipment at

400 kV Bhilai to Urla S/s, 400 kV Urla to Gudiyari and Urla to Raipur includes the

requirement of Chhattisgarh only and is not the requirement of SLDC to WRLDC link

and as such its cost should not be pooled.

In this context, WRTS-I representative clarified that the above link is essentially

required for transmission of data/communication from SLDC to WRLDC and is part

of scheme for shifting of SLDC Bhilai to Raipur. As such its cost needs to be pooled.

WRP Committee deliberated the matter and approved the cost estimates of Rs 5.16 crores towards extending the data communication link from Raipur to Bhilai for pooling in regional system.

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 28

Page 33: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

ITEM No.14: COMMISSIONING OF TRANSMISSION LINES AND GENERATING UNITS

14.1 Commissioning of transmission elements by PGCIL The Committee noted the commissioning and commercial operation of the following

elements of transmission system by PGCIL:

Sl. No.

Name of the transmission elements Date of commercial Operation

1 40% FSC of 400 kV Ranchi-Sipat D/c under Kahalgaon-II phase-II

1.03.2009

2 315 MVA ICT-II at Bhatapara S/s under Sipat-II 1.01.2009 3 Bur reactor at Damoh ICT-II at Damoh under WRSS-IV 1.01.2009 4 Agra-Gwalior 765 kV Ckt-II under N-W Inter connector 1.04.2009 5 400/220 kV, 315 MVA ICT-II at Rajgarh S/s along with

associated bays under Sipat-I transmission system 1.04.2009

6 765 kV S/c Seoni-Wardha Ckt-I with associated bays (initially charged at 400 kV)

1.04.2009

7 400 kV D/c Wardha-Akola transmission line with associated bays

1.04.2009

8 400 kV D/C Zerda-Kankroli line (Associated with North-West Transmission Corridor Strengthening scheme)

Test charged in March 09

14.2 Commissioning of generating units

S.No State/Agency Name of Project

Unit No.

Capacity in MW

Date of Synchronization

1 Maharashtra Trombay TPP (TPC)

8 250 Taken full load w.e.f. 26.3.2009

2 Torrent Power Co., Gujarat

Sugen CCPP- Torrent Power

Block-II 382.5 29.01.09

3 Torrent Power Co., Gujarat

Sugen CCPP- Torrent Power

Block-III 382.5 27.03.09

4 LANCO Pathadi TPP 1 300 Synchronised on 1.05.2009

5 Bhilai TPP (Joint venture with SAIL)

NSPCL 1 250 COD w.e.f 22.04.09

6 Bhilai TPP (Joint venture with SAIL)

NSPCL 2 250 Synd. On 28.03.09

WRP Committee noted the same.

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 29

Page 34: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

ITEM No.15: ONGOING TRANSMISSION SCHEMES IN WESTERN REGION

The details of ongoing transmission schemes in WR are enclosed at Annexure- 15.

The important EHV lines, which are expected to be commissioned during the current

year, are as below:

S.No. Name of transmission element Expected date of commissioning

1 400 kV D/C Akola-Aurangabad June 2009

2 765 kV S/C Seoni - Bina line (to be charged at 400kV) Sep. 2009

3 400 kV D/c Ranchi - Rourkela Mar-2010

4 400 kV D/c Rourkela - Raigarh Mar-2010

5 400 kV D/c Raigarh – Raipur Mar-2010

6 765 kV Seoni – Wardha Ckt-II (initially to be charged on 400 kV)

Mar-2011

7 LILO of Kankroli-Zerda at Bhinmal Oct-2009

WRP Committee noted the same. ITEM No. 16: ONGOING GENERATION SCHEMES IN WESTERN REGION

The details of on going generation schemes in WR both under State as well as

Central Sector are enclosed at Annexure-16. The generating units expected to be

commissioned during the next one year are as follows:

Name of the Power Projects Unit No. Capacity (MW)

Schedule Date of Commissioning

GUJARAT (i) Surat Llignite expansion-PH-I GIPCL 1 125 Nov. 2009 2 125 Mar. 2010 (ii) Utran GPP GT+ST 374 Aug. 2009 (iii) Mundra TPP Ph-I, APL 1 330 May 2009 2 330 July 2009 3 330 Feb. 2010 4 330 May. 2010 (iv) Hazira CCPP (GSECL) GT+ST 350 Apr. 2010

CHHATTISGARH (i) Pathadi TPP (Lanco) 2 300 Dec. 2009

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 30

Page 35: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Name of the Power Projects Unit No. Capacity (MW)

Schedule Date of Commissioning

MAHARASHTRA (i) New Parli TPS Extn. 2 250 Nov. 2009 (ii) Paras TPS Extn. 2 250 Feb. 2010 (iii) JSW Energy, Ratnagiri (4x300) 1 300 Feb. 2010 CENTRAL SECTOR – NTPC (i) Sipat-I, TPP 1 660 Nov. 2009 2 660 Dec. 2009 3 660 Mar. 2010 (ii) Bhilai TPP (Joint venture with SAIL) 2 250 COD exp in May. 2009 (iii) Korba STPP Stage-III 7 500 May. 2010

WRP Committee noted the same.

ITEM No.17 ANTICIPATED POWER SUPPLY POSITION IN WESTERN

REGION FOR THE PERIOD FROM JUNE 09 TO AUG. 09.

The Committee noted the anticipated power supply position in the region for the period from June, 2009 to August, 2009 as furnished at Annexure-17. It was noted that this period under consideration was monsoon season and the regional demand was likely to be low as compared to summer period. The unrestricted demand would vary from 31900 MW to 33800 MW and deficit would vary from 0.22 % to 11.40 %. In terms of energy, the unrestricted requirement would be varying from 20769 MUs to 21375 MUs with regional deficit varying from 7.59 % to 16.31 %. The anticipated Peak demand shortages for Gujarat, Chhattisgarh, Maharashtra, MP, Goa, DD and DNH was 910 to 1989 MW, 223 to 396 MW, 2816 to 3940 MW, 144 to 1336, 84 to 122 MW, 29 to 45 MW and 28 to 63 MW respectively.

Although deficit was expected to be comparatively less than other peak period due to monsoon season, Constituent states were requested to be vigilant as regards to frequent tripping of lines and high voltages in certain pockets. Also, maintenance programme of generating units will have to be planned after taking into consideration regional demand and also diversity in demand of NR and ER in an integrated combined N-E-W grid. WRP Committee noted.

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 31

Page 36: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

ITEM No.18: PAYMENTS OF UI AND REACTIVE ENERGY CHARGES

As per the information received from WRLDC, the status of payment to UI pool

account and Reactive Energy Pool account as on 27.05.09 i.e. upto week

10.05.2009 to 17.05.2009 of the current financial year is given below: -

(All figures in Rupees)

UI Pool Account Reactive Energy Pool Account

Constituents Dues Constituents Dues GUJARAT (590,950,216) GUJARAT 3,879,291 MADHYA PRADESH (205,123,077) MADHYA PRADESH 1,931,417 CHHATTISGARH (487,007,243) CHHATTISGARH (4,670,778)MAHARASHTRA 67,124,145 MAHARASHTRA (2,137,983)GOA 4,696,018 GOA (2,164,298)DD 122,155,982 DD 186,410 DNH 2,659,566 DNH 665,062 NTPC (113,203,154) NR Exchange 1,620,374,923 SR Exchange (810,943,295) ER Exchange 518,489,422 Jindal Power 61,177,686 HVDC Vindhyachal (248,694) HVDC Bhadravati (2,206,505) LANCO Amarkantak (4,043,223) Diff. due to capping (1,807,030,511) Diff. due to Additional UI (81,140,953) Net Total (1,705,219,129) (2,310,879)

Figures in bracket ( ) are receivables from pool

WRP Committee noted the same. ITEM No.19 PROVISION OF 400 kV FEED TO UNION TERRITORY OF DAMAN &

DIU. Member Secretary, WRPC stated that in the 9th Meeting of WRP Committee held on

16.01.2009, request of Union Territory of Daman & Diu for providing 400 kV feed to

the Union Territory by establishment of 400 kV substation in Daman was considered

and the Committee gave in-principle approval to the proposal. PGCIL were

requested to carry out the survey and identify a suitable location in the territory for

the proposed 400/220 kV sub-station.

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 32

Page 37: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

In this context, Executive Director (WR-II), PGCIL, vide his letter No.WRTS-

II.VDR:Engg: dated 14.05.2009 intimated that joint exercise for identification of land

in Daman was carried out by them alongwith the Electricity Department of Daman &

Diu. However, no Government land could be located for the proposed substation.

As such, they requested that Daman & Diu administration may provide 10-12 acres

of land (preferably Government owned) for construction of GIS substation at Daman.

In the TCC meeting held on 29th May 2009, Special Secretary (P), UT of Daman &

Diu informed that private land is available at the market price. PGCIL accordingly

agreed to interact with DD authorities for taking further action.

WRP Committee noted the same.

ITEM No.20: CONTRIBUTION TOWARDS INCIDENTAL EXPENSES FOR VARIOUS MEETINGS ETC.

20.1 Member Secretary, WRPC stated that the erstwhile WRE Board in its 120th

meeting held on 20th December 2002 passed Resolution to create Board Fund for

meeting the expenditure of Board viz. periodic and special forum meetings,

seminars, workshop, meetings with deferent power sectors / advisors, management

consultant of power sector of WR at WREB head quarters etc. Subsequently, due to

the formation of WRPC and change in the membership of WRPC as per GoI

Resolution, the WRP Committee in its 4th meeting held on 29th June 2007 decided

that the contribution towards the above fund be made by the following:

(i) All State GENCOs (ii) All State TRANSCOs (iii) All State owned DISCOMs (by rotation, if more than one in a State) (iv) NTPC Ltd., PGCIL, NPCIL, IPPs having IC above 1,000 MW – contribution

to be made by each separately. (v) Representative of IPPs and (vi) Representative of Trading Company

Accordingly, the above members are making the contribution @ Rs. 50,000/- per

year to the Board Fund.

20.2 Member Secretary, WRPC further stated that with the subsequent

amendment to the Resolution regarding establishment of Western Regional Power

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 33

Page 38: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Committee made by MoP vide Resolution dated 9th May 2008, there is some change

in the membership. Accordingly the details of members of WRP Committee that will

contribute Rs. 50,000/- each towards the Board Fund for the year 2009-10 and

thereafter is enclosed at Annexure-20.

WRP Committee members noted the same and agreed to send their contribution accordingly. ITEM No. 21: ADDITION OF DIGITAL ACCESS CROSS CONNECT SWITCH

(DACS) AT JABALPUR AND ITARSI Member Secretary, WRPC stated that during 7th meeting of WRP Committee held on

3rd May 2008 PGCIL intimated that Western Region ULDC network is expanding

continuously with the addition of new transmission lines and sub-stations by all

constituents resulting in congestion of wide band communication channel between

Jabalpur 400 kV S/s and Itarsi 400 kV S/s. As such there was a necessity of

addition of DACS (Wide Band Communication Equipment) at Jabalpur 400 kV S/s

and Itarsi 400 kV S/s. This proposal was also discussed by constituents of WR in the

4th O & M Meeting held on 16th April 2008 at WRLDC to review SCADA / EMS

issues. In this meeting, constituents agreed to the proposal of PGCIL to add DACS

(Wide Band Communication Equipment) at Jabalpur 400 kV S/s and Itarsi 400 kV

S/s. PGCIL intimated that the estimated cost of the above will be Rs. 10 lakhs. The

matter was discussed and the WRP Committee accorded their approval to the above

proposal.

Member Secretary, WRPC further stated that PGCIL, vide letter dated 15th May 2009

have intimated that based on the offer from M/s Aastra (earlier M/s Ericsson), the

original equipment manufacturer (OEM), the cost estimate got revised to Rs.

25lakhs approximately excluding taxes and duties. In view of change in the

estimated cost, PGCIL have requested for concurrence.

The matter was discussed in the TCC meeting held on 29th May 2009 and TCC agreed to the same. WRP Committee endorsed the decision of TCC and gave their concurrence.

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 34

Page 39: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

ITEM No.22: LONG TERM SERVICE AGREEMENT FOR WIDEBAND TELECOMMUNICATION EQUIPMENT SUPPLIED UNDER SYSTEM COORDINATION & CONTROL PROJECT OF WR

22.1 Member Secretary, WRPC informed that PGCIL vide letter dated 15th May

2009 intimated that during the SCADA coordination meeting held at WRLDC Mumbai

on 06.01.2009 WR constituents principally agreed to give AMC for Wideband

Telecommunication Equipment to M/s Ericsson India Pvt Ltd for a period of 3years

and requested POWERGRID to finalise the terms and conditions and price with M/s

Ericsson keeping in view of expiry of the existing AMC for wideband

telecommunication equipment by 09.04.2009. Accordingly, PGCIL finalised terms

and conditions and technical specifications and price for Long Term Service

agreement for AMC of wideband telecom equipment supplied and commissioned

under System Coordination and Control project of Western Region with M/s Ericsson

India Pvt. Ltd for 3years at a price of Rs. 6,59,16,762.00 ( inclusive of service tax @

10.36%). The contract may further be extended for 2 years at the same terms and

conditions and technical specifications on mutually agreed rates. The price has been

negotiated from the earlier offered price of Rs 6,83,55,770 (inclusive of service tax

@10.36%). The new AMC shall be effective from 10.04.2009 retrospectively. The

cost sharing shall be on the basis of cost ratio of the equipment cost to the total

equipment cost submitted to CERC for telecom equipment. The Cost sharing by

POWERGRID, Madhya Pradesh, Chhattisgarh and Gujarat for their portion of AMC

will be as below:

S. No Description Unit price Incl. of service tax (in Rs.)

Quantity In months

Amount (in Rs.)

For WRTS-I Portion

A. Price Breakdown for Maintenance Services – Central Sector

1 For Central Sector equipment under Chhatisgarh and Maharashtra

444572 36 16004590

B. Price Breakdown for Maintenance Services – Chhattisgarh

1 For Chhattisgarh equipment in Chhatisgarh

254878 36 9175613

Total for Maintenance Services – WRTS-I Portion (A+B) 25180203For WRTS-II Portion

C. Price Breakdown for maintenance Services – Central Sector

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 35

Page 40: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

S. No Description Unit price Incl. of service tax (in Rs.)

Quantity In months

Amount (in Rs.)

1 For Central Sector equipment under MadhyaPradesh, Gujarat

444572 36 16004590

D. Price Breakdown for Maintenance Services – Madhya Pradesh 1 For MPSEB equipment in

Madhya Pradesh 471671 36 16980158

E. Price Breakdown for Maintenance Services – Gujarat

1 For GEB equipment in Gujarat 215328 36 7751811

Total for Maintenance Services – WRTS-II Portion (C+D+E) 40736559 TOTAL(A+B+C+D) 65916762

The payment of AMC to M/s Ericsson shall be done by PGCIL on monthly basis. Madhya Pradesh, Gujarat and Chhattisgarh need to provide quarterly advance to POWERGRID for their portion of AMC cost. The reconciliation of accounts shall be done on annual basis.

The matter was discussed and WRP Committee gave their approval for the same. ITEM No.23: SIGNING OF PPA WITH RGPPL AND ITS SCHEDULING In the TCC meeting, Special Secretary (P), UTs of DD & DNH stated that MoP had

allocated power to the tune of 1.5 % capacity of RGPPL each to DD and DNH about

a year back. However the scheduling of power from RGPPL to them has yet not

commenced. He stated that the matter was discussed during the last WRP

Committee meeting and accordingly RGPPL was requested to address the issues

concerning signing of PPA etc. urgently so that the scheduling of power form RGPPL

could be commenced immediately.

In this context, the representative of RGPPL stated that the issue concerning

allocation of 5% power from RGPPL by the MoP was discussed in the RGPPL Board

meeting held in Feb. 2009 and it was decided that scheduling of 5 % power to other

states should be commenced only after the project reaches its full capacity.

Subsequently, the RGPPL Board decision was discussed in the review meeting

taken by Secretary (P), GoI and it was requested to keep the above allocation in

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 36

Page 41: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

abeyance till the project start generating at it full capacity. Accordingly, Director

(OM), MoP was requested to initiate action.

The beneficiaries of WR viz. DD & DNH, Madhya Pradesh and Goa unanimously stated that no communication has been received by them from MoP till date, as such the allocation made to them out of 5% capacity from RGPPL stands as on date. They requested RGPPL to take urgent steps for scheduling of the above allocated power immediately. Representative of RGPPL stated that he would look into the matter and revert back.

(Action: RGPPL) ITEM No.24: UNREQUISTIONED POWER AT KAWAS AND GANDHAR Member Secretary, WRPC stated that NTPC representative in the TCC meeting

made a presentation regarding the un-requisitioned power at Kawas and Gandhar

and proposed that they may be allowed to schedule the same to other regions a

variable cost only. MSEDCL representative stated that the same should be

scheduled as per the present practice to outside the region (Fixed Charge + Variable

charge) whereas within the region it can be scheduled at variable charge as

proposed by NTPC.

The matter was discussed and NTPC was requested to come out with detailed

Agenda item highlighting the cost implication etc. so that the same will be discussed

in CCM and thereafter in TCC/WRP Committee meeting. NTPC representative

agreed to the same.

ITEM No.25: DATE AND VENUE OF NEXT WRPC MEETING

The next meeting i.e. 11th WRP Committee meeting will be held in Aug/Sept 2009.

Chhattisgarh State Power Transmission Co. Ltd. agreed to host the same. The

venue of the meeting will be intimated separately.

The meeting ended with a vote of thanks to the Chair.

* * * * *

Minutes of 10th meeting of WRP Committee held on 30th May 2009 at Diu 37

Page 42: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Minutes of 10th WRPC meeting held on 30th May 09

ANNEXURE

Page 43: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Annexure-1(A)

LIST OF PARTICIPANTS OF TCC MEETING HELD ON 29.05.2009 AT DIU

A. TECHNICAL COORDINATION COMMITTEE

MEMBERS

1. Shri S. N. Chauhan, MD, CSPTCL (in chair) 2. Shri R. P. Sharma, OSD (LD), MPPTCL 3. Shri R. K. Saxena, ED (O&M : Gen), MPPGCL 4. Shri S. G. Kelkar, CE (LD), MSETCL 5. Shri N. H. Suthar, CE (LD), SLDC, GETCO 6. Shri M. R. Ingle, EE, DNH 7. Shri Alok Gupta, CE(GM), CEA 8. Shri M. L. Jadhav, CE (Trans.), NPCIL 9. Shri D.K. Valecha, ED, WR-I, PGCIL 10. Shri R. K. Bhatnagar, GM(Power), RGPPL 11. Shri T. S. Bhatt, Sr. VP, PTC India Ltd. 12. Shri R. B. Mathur, GM(ISP), NHDC 13. Shri Atul G. Patil, CE, BEST Undertaking 14. Shri P. Patel, Member Secretary, WRPC

B. OTHERS I. CHHATTISGARH

1. Shri G. S. Deshpande, MD, CSPDCL 2. Shri Shiv Raj Singh, Advisor, CSPTCL

II. MADHYA PRADESH

1. Shri D. Khandelwal, ED (L & RA), MPTradco III. MAHARASHTRA

1. Shri G. S. Trimukhe, CE (PP), MSEDCL 2. Shri M.R. Khadgi, CE (STU), MSETCL

IV. GOA ELECTRICITY DEPT.

1. Shri Nirmal Braganza, CEE 2. Shri B. Nigalye, AEE

V. ADMINISTRATION OF UT OF DD & DNH

1. Shri Vikas Anand, Sp. Sectretary (Power) 2. Shri Sanjay Goel, Collector, Diu

VI. CENTRAL ELECTRICITY AUTHORITY

1. Shri Mohd. Afzal, DD, CEA

Page 44: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

VII. POWERGRID CORPN. OF INDIA LTD.

1. Shri M. G. Raoot, ED, WRLDC 2. Shri N. S. Sodha, GM (I/C), LD & C, CC 3. Shri N. Ravi Kumar, GM(O&M), POWERGRID, WR-I 4. Shri S. K. Gupta, GM, POWERGRID, WR-II 5. Shri P. Pentayya, AGM (OS), WRLDC 6. Shri Prashant Sharma, AGM (Comml.), CC 7. Dr. Subir Sen, DGM (Engg.), CC 8. Shri Abhinav Verma, CM(Engg), CC 9. Shri C.A. Bhat, CM(SS), WRLDC 10. Shri P. P. Bandyopadhyay, CM(GM), WRLDC

VIII. NTPC LTD.

1. Shri A. Chaudhuri, GM (OS), 2. Shri S. K. Sharma, DGM (Comml.) 3. Shri H. Harchandani, DGM(Comml.)

IX. TATA POWER COMPANY

1. Shri V.R. Shrikhande, AGM, TPC X. ESSAR POWER LTD.

1. Shri R. K. Narayan, Director XI. BEST UNDERTAKING

1. Shri S. A. Puranik, DGM(ES) XII. WESTERN REGIONAL POWER COMMITTEE

1. Shri S.D. Taksande, SE (Opn.), WRPC 2. Shri S.G. Tenpe, SE (Comml.) , WRPC 3. Shri M.M. Dhakate, AS, WRPC 4. Shri S. Satyanarayan, EE(Prot.), WRPC 5. Shri V.K. Gupta, EE (Opn.) , WRPC

Page 45: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Annexure-1(B)

LIST OF PARTICIPANTS OF 10th WRPC MEETING HELD ON 30.05.2009 AT DIU

A. WESTERN REGIONAL POWER COMMITTEE

MEMBERS

1. Shri G. Mohapatra, Chairman, UGVCL (in Chair) 2. Shri S. M. Dhiman, Member(GO & D), CEA 3. Shri S.N. Chauhan, MD, CSPTCL 4. Shri G. S. Deshpande, MD, CSPDCL 5. Shri D. N. Prasad, CMD, MPPGCL 6. Shri N. H. Suthar, CE (LD), SLDC, GETCO 7. Shri R. P. Sharma, OSD (LD), MPPTCL 8. Shri S. G. Kelkar, CE (LD), MSETCL 9. Shri Nirmal Braganza, CEE, ED, Goa 10. Shri P. K. Gupta, Secretary (Power), UT of DD and DNH 11. Shri R. N. Nayak, Dir.(Opn.), Powergrid 12. Shri M. G. Raoot, ED, WRLDC 13. Shri Uttam Khobragade, GM, BEST Undertaking 14. Shri R. K. Narayan, Director, Essar Power Ltd. 15. Shri P. Patel, Member Secretary, WRPC

B. OTHERS I. CHHATTISGARH

1. Shri Shiv Raj Singh, Advisor, CSPTCL

II GUJARAT

1. Shri S. B. Khyalia, ED(Finance), GUVNL

III. MADHYA PRADESH

1. Shri D. Khandelwal, ED (L & RA), MPTradco 2. Shri R. K. Saxena, ED (O&M: Gen), MPPGCL

IV. MAHARASHTRA

1. Shri Anjan Roy, Dir.(Opn.), MSETCL 2. Shri G. S. Trimukhe, CE (PP), MSEDCL 3. Shri M.R. Khadgi, CE (STU), MSETCL

V. GOA ELECTRICITY DEPT.

1. Shri B. Nigalye, AEE VI. ADMINISTRATION OF UT OF DD & DNH

1. Shri Vikas Anand, Sp. Sectretary (Power) 2. Shri Sanjay Goel, Collector, Diu 3. Shri M. R. Ingle, EE, Elect. Dept., Daman & Diu

VII. CENTRAL ELECTRICITY AUTHORITY

1. Shri Alok Gupta, CE(GM) 2. Shri Mohd. Afzal, DD

Page 46: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

VIII. POWERGRID CORPN. OF INDIA LTD.

1. Shri D.K. Valecha, ED, WR-I, PGCIL 2. Shri N. S. Sodha, GM (I/C), LD & C, CC 3. Shri N. Ravi Kumar, GM(O&M), WR-I 4. Shri S. K. Gupta, GM, WR-II 5. Shri P. Pentayya, AGM (OS), WRLDC 6. Shri Prashant Sharma, AGM (Comml.), CC 7. Dr. Subir Sen, DGM (Engg.), CC 8. Shri Abhinav Verma, CM(Engg.), CC 9. Shri C.A. Bhat, CM(SS), WRLDC 10. Shri P. P. Bandyopadhyay, CM(GM), WRLDC

IX. NTPC LTD.

1. Shri V. K. Padha, GM(Comml), CC 2. Shri A. Chaudhuri, GM (OS), Mumbai 3. Shri S. K. Sharma, DGM (Comml.), CC 4. Shri H. Harchandani, DGM(Comml), Mumbai

X. NUCLEAR POWER CORPORATION OF INDIA LTD.

1. Shri M. L. Jadhav, CE (Trans.), NPCIL XI. TATA POWER COMPANY

1. Shri V.R. Shrikhande, AGM, TPC XII. RATNAGIRI GAS AND POWER PRIVATE LTD.

1. Shri R. K. Bhatnagar, GM(Power), RGPPL XIII. ESSAR POWER LTD.

1. Shri T. S. Bhatt, Sr. VP, PTC India Ltd. XIV. NATIONAL HYDROELECTRIC DEVELOPMENT CORPORATION

1. Shri R. B. Mathur, GM (ISP), NHDC

XV. PTC INDIA LTD.

1. Shri Santosh Kumar, Advisor XVI. BEST UNDERTAKING

1. Shri Atul G. Patil, CE, BEST Undertaking 2. Shri S. A. Puranik, DGM(ES) 3. Shri S. M. Sakpal, Supdt. Eng., GM’s Office

XVII. WESTERN REGIONAL POWER COMMITTEE

1. Shri S.D. Taksande, SE (Opn.) 2. Shri S.G. Tenpe, SE (Comml.) 3. Shri M.M. Dhakate, AS, 4. Shri S. Satyanarayan, EE (Prot.) 5. Shri V.K. Gupta, EE (Opn.)

Page 47: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Annexure - 3 Transmission System Associated with the Tilaiya Ultra Mega Power Project (4000 MW), in Jharkhand, Nabinagar (1000MW) of Railways and NTPC, Barh-II (1320 MW), Rihand-III (1000MW), Vindhyachal-IV(1000MW) and Mauda (1000MW) of NTPC, and IPPs in Jharkhand, Orissa, MP, Chattisgarh, and Maharashtra

The transmission system requirements were identified based on studies carried out by CEA and PGCIL. The evolve transmission scheme was deliberated during the 28th meeting of the Standing Committee on Power System Planning held on 6th December 2008 at Aurangabad and its Special meeting held on 18th April 09 at WRPC office Mumbai The transmission scheme agreed is in four parts, viz. (i) Generation specific transmission scheme, (ii) System strengthening common for WR and NR, (iii) System strengthening common for WR and (iv) Pooling Stations for IPPs in Orrissa A. Generation Specific Transmission System Tilaiya UMPP (4000MW)

1. Tilaiya UMPP – Sasaram, 765kV S/C line 2. Tilaiya UMPP – Gaya, 765kV S/C line. 3. Tilaiya UMPP – Balia 765kV S/C line

Nabinagar (1000MW)

1. Nabinagar-Sasaram 400kV D/C line Barh-II (1320MW)

1. Barh – Gorakhpur 400kV quad D/C line Rihand-IV (1000MW)

1. Rihand-Vindyachal pooling 2xS/C 765kV lines operated at 400kV (considering ageing of Rihand-Dadri HVDC system and possibility of decommission the HVDC system, a 765kV switchyard could be established at Rihand utilizing the space of HVDC terminal and considering this, 2XS/C 765kV lines operated at 400kV was suggested and agreed.

Vindhyachal-IV (1000MW)

1. Vindhyachal-IV – Vindhyachal pooling 400kV quad D/C line or 2x765kV S/C lines depending on feedback from NTPC

Mauda (1000MW)

1. Mauda-Nagpur South 400kV quad D/C 2. Mauda-Khaperkheda 400kV quad D/C

Essar(1800MW), Electrosteel(1200MW) and Corporate(800MW):

1

Page 48: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

These three IPPs in Jharkhad would connect at 400kV to Ranchi 765/400kV substation through dedicated/common 400kV transmission lines

Adunik (1000MW) and DumkaCESC (1200MW) :

These two IPPs in Jharkhand would connect to ER grid at Jamshedpur/Maithon/Gaya

Sterlite(2400MW), GMR (1050MW), Monet (1005MW), Jindal (1200MW), Essar(1200MW) and Lanco (2640MW)

These IPPs in Orissa would connect to 765kV and 400kV system specifically proposed in ER for Orissa IPPs. Three 765/400kV pooling stations at Jharsuguda, Angul and Denkenal together with Jarsuguda-Angul-Denkenal-Jharsuguda 2xS/C 765kV lines would be connected to WR system through following provision: 1. LILO of all four circuits of Rourkela-Raigarh 2xD/C 400kV lines at

Jharsuguda. 2. Jharsuguda-Dharmjaygarh 2xD/C 765kV lines.

IPP of Sterlite would connect to 765/400 kV pooling station Jharsuguda IPPs of GMR, Monet, Jindal, Essar and LANCO would connect to Angul 765/400 kV pooling station WBPDCL projects To be connected to West Bengal and ER grid IPPs in MP Jaiprakash (1320MW)

1. Jaiprakash-Satna(or Vindhyachal pooling) 400kV quad D/C ShahdolRIL(1050MW)

1. Shahdol-Jabalpur pooling 400kV D/C Today Home(1000MW)

1. Today Home – Jabalpur pooling 400kV D/C IPPs in Maharashtra JSW Energy(1200MW) Connected through MSETCL’s STU system Maharashtra Egy(4000MW)

1. MahaEgy – Phadghe 2X S/C 765kV lines 2. MahaEgy – Pune S/C 765kV line

IPPs in Chattishgarh

2

Page 49: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Aryan Coal (270MW), Spectrum C&P (100MW), Maruti Coal (270MW) and Dheeru (1050MW)

1. All the above projects would be connected to Sipat pooling 2. Earlier open access to Aryan Coal was agreed with connectivity to Bhatpara. In

view of revised time frame for the generation project, the revised connectivity would be to Sipat pooling. PGCIL informed that Aryan and Sepctrum had planned to have a common dedicated 400kV line to Sipat pooling.

3. Maruti C Coal and Dheeru would have their own dedicated 400kV lines connecting to Sipat pooling.

4. Open access to Dheeru was already agreed for 600MW. Their revised application seeking open access of 682 MW (382 to NR and 300 to WR) was noted and approved.

B. System strengthening common for WR and NR:

1. Creation of 765kV Switching station at Daramjaygarh by LILO of Ranchi- Sipat 765kV S/C line

2. Ranchi-Daramjaygarh 765kV S/C line 3. Jarsuguda-Daramjaygarh 2xD/C 765kV lines 4. Dhramjaygarh-Jabalpur 765kV 2xD/C 765kV lines 5. Pooling station at Jabalpur with 2x1500MVA 765/400kV 6. Jabalpur pooling-Bina 765kV lines – one D/C line and one S/C line providing 3

nos. of 765kV circuits. 7. Bina-Gwalior S/C 765kV line (3rd ckt) 8. Gwalior-Jaipur 2XS/C 765kV lines 9. Vindhyacal pooling station with 2x1500MVA 765/400kV 10. Vindhyachal pooling-Satna 2XS/C 765kV lines 11. 2x S/c 765 kV Satna-Gwalior

C. System strengthening for WR:

1. Dharamjaigarh-Bilaspur (Sipat) pooling 765kV S/C line 2. Jabalpur pooling-Bhopal 765kV S/C line 3. Bhopal-Indore 765kV S/C line 4. Indore – Vadodara 765kV S/C line 5. 765/400kV substation at Vadodara, Bhopal, Dhule, Padghe, Aurangabad, Raigarh

pool, Champa pool, and Raipur pool each with 2x1500MVA 765/400kV and interconnecting 400kV lines/LILO

6. Raigarh Pool –Raipur Pool 765kV S/C 7. Raigarh Pool –Champa Pool 765kV S/C 8. Champa Pool – Bilaspur (Sipat) pooling 765kV S/C 9. Champa Pool -Raipur Pool 765kV S/C 10. Bilaspur (Sipat) pooling-Raipur Pool 765kV S/C 11. Raipur-Wardha 2XD/C 400kV lines upgradable to 2XS/C 1200kV lines with FSC

(40%) will be provided on 400 kV lines and will be removed once upgraded to 1200 kV.

12. Wardh-Aurangabad D/C 400kV line (2nd line) upgrdabale to 1200kV S/C line(2nd line) will be provided on 400 kV lines and will be removed once upgraded to 1200 k.V

13. Pune-Padghe 765kV S/C line

3

Page 50: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

14. Aurangabad-Padghe 765kV S/C line 15. Aurangabad-Dhule 765kV S/C line 16. Dhule-Vadodara 765kV S/C line 17. Wardha-Nagpur South 400kV quad D/C with new 2x500MVA 400/220kV s/s at

Nagpur South (Butibori) ( with 220kV interconnectivity under preview of MSETCL)

18. 400 kV level interconnection from proposed new 765 kV S/s at vadodara, Bhopal, Dhule and Padghe

(i) Vadodara-Pirana (PG) 400 kV D/C quad. (ii) Vadodara-Asoj (GETCO) 400 kV D/C quad. (iii) Bhopal-Bhopal (MPPTCL) 400 kV D/C quad. (iv) Dhule – Dhule (MSETCL) 400 kV D/C quad. (v) Padghe – Padhge (MSETCL) 400 kV D/C quad

D. Pooling Stations for IPPs in Orissa

• Establishment of 765/400kV Pooling Station at Jharsuguda • Establishment of 765/400kV Pooling Station at Dhenkanal • Establishment of 765/400kV Pooling Station at Angul • Dhenkenal Pooling Station – Angul Pooling Station 765kV 2xS/c • Angul Pooling Station – Jharsuguda Pooling Station 765kV 2xS/c • Jharsuguda Pooling Station – Dhenkenal Pooling Station 765kV 2xS/c • LILO of Rourkela – Raigarh 400kV 2xD/c at Jharsuguda Pooling station • * LILO of Meramundali – Jeypore 400kV S/c line at Angul pooling station • * LILO of one ckt of Talcher - Meramundali 400kV D/c line at Angul pooling

station • * LILO of Meramundali-Chandaka 400kV D/c line at Dhenkenal Pooling station

[* These LILO would be later disconnected when Angul and Dhenkanal pooling stations are developed as 765kV as otherwise it would cause short circuit level problem.]

4

Page 51: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Sr.No. PARTICULARS Jan-09 Feb-09 Mar-09 Apr-09 May-09

1 MAXIMUM FREQUENCY (Hz)

1.1 Integrated over an hour 50.36 50.34 50.35 50.27 50.62

1.2 Instantaneous 50.86 50.72 50.55 50.53 50.82

2 MINIMUM FREQUENCY (Hz)

2.1 Integrated over an hour 48.97 48.97 49.02 48.94 49.03

2.2 Instantaneous 48.76 48.76 48.77 48.73 48.78

3 AVERAGE FREQUENCY (Hz) 49.58 49.45 49.60 49.45 49.68

4.1 48.6 Hz 0 0 0 0 0

4.2 48.8 Hz 23 76 10 192 36

4.3 51.0 Hz 0 0 0 0 0

5.1 Above 50.2 Hz 4.10 1.26 2.43 - -

5.2 Above 50.5 Hz 0.10 0.07 0.02 - -

5.3 Between 50.2 Hz & 49.5 Hz 53.63 39.39 58.25 - -

5.4 Between 50.2 Hz & 49.0 Hz 93.79 95.47 95.67 - -

5.5 Below 49.0 Hz 2.11 3.27 1.90 - -

5.6 Below 49.8 Hz 76.28 88.50 70.75 - -

5.7 Between 49.0 Hz & 50.5 Hz 97.79 99.66 98.08 - -

5.8 Between 50.5 Hz & 48.5 Hz 99.90 90.99 99.98 - -

5.9 Above 50.3 Hz 0.32 2.34

5.10 Below 49.2 Hz 18.75 6.45

5.11 Between 49.2 Hz & 50.3 Hz 80.93 91.21

5.12 Between 50.3 Hz & 48.5 Hz 99.68 97.66

Annexure-6.1(a)FREQUENCY PARTICULARS OF WESTERN REGION FOR THE PERIOD

JANUARY 2009 TO MAY 2009

5PERCENTAGE TIME WHEN FREQUENCY WAS

4

NUMBER OF TIMES FREQUENCY TOUCHED

Page 52: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

ANNEXURE -6.1(b) (1/2)

Jan Feb Mar April May Jan Feb Mar April May Jan Feb Mar April May Jan Feb Mar April May

Availability (MW) 2554 2996 2840 2880 2773 8042 8502 8788 8967 8732 5966 5754 5759 5468 5074 13098 13617 14265 14801 14011

Unrestricted demand (MW) 2625 3054 2907 2996 2854 9127 8757 8733 9461 8954 7168 7062 6957 6740 6076 17699 18258 18426 19154 17934

Deficit(-)/Surplus(+)

(i) MW -71 -58 -67 -116 -81 -1085 -255 55 -494 -222 -1202 -1308 -1198 -1272 -1002 -4601 -4641 -4161 -4353 -3923

( ii) % -2.70 -1.90 -2.30 -3.87 -2.84 -11.89 -2.91 0.63 -5.22 -2.48 -16.77 -18.52 -17.22 -18.87 -16.49 -26.00 -25.42 -22.58 -22.73 -21.87

Jan Feb Mar April May Jan Feb Mar April May Jan Feb Mar April May Jan Feb Mar April May

Availability (MW) 401 400 401 400 400 197 207 215 255 220 423 443 434 441 407 30165 30585 31608 31509 30273

Unrestricted demand (MW) 439 457 466 455 443 222 232 240 280 245 466 480 504 485 452 36577 36813 37392 36793 35728

Deficit(-)/Surplus(+)

(i) MW -38 -57 -65 -55 -43 -25 -25 -25 -25 -25 -43 -37 -70 -44 -45 -6412 -6228 -5784 -5284 -5455

(ii) % -8.66 -12.47 -13.95 -12.09 -9.71 -11.26 -10.78 -10.42 -8.93 -10.20 -9.23 -7.71 -13.89 -9.07 -9.96 -17.53 -16.92 -15.47 -14.36 -15.27

POWER SUPPLY POSITION IN WR FOR PERIOD FROM JANUARY 2009 TO MAY 2009 (IN MW)

Details MaharashtraChhatisgarh Gujarat Madhya Pradesh

Details Western RegionGoa Daman & Diu Dadra & Nagar Haveli

Page 53: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

ANNEXURE -6.1(b) (2/2)

Jan Feb Mar April May Jan Feb Mar April May Jan Feb Mar April May Jan Feb Mar April May

Availability (MUs) 1254 1235 1310 1334 1245 5465 5036 5940 5888 5946 3452 2955 3038 2926 2810 8705 8110 9265 9196 9428

Unrestricted Requirement (MUs) 1273 1264 1324 1376 1265 5822 5147 5953 6072 5983 4338 3801 3875 3551 3391 11116 10515 11714 11650 11288

Deficit(-)/Surplus(+)

(i) MUs -19 -28 -14 -42 -19 -357 -111 -13 -184 -37 -885 -845 -837 -625 -581 -2411 -2405 -2449 -2454 -1860

(ii) % -1.509 -2.24 -1.063 -3.04 -1.54 -6.13 -2.16 -0.216 -3.04 -0.61 -20.41 -22.24 -21.60 -17.59 -17.15 -21.69 -22.87 -20.9 -21.06 -16.48

Jan Feb Mar April May Jan Feb Mar April May Jan Feb Mar April May Jan Feb Mar April May

Availability (MUs) 233.91 218.37 261.02 275.56 255.31 131.08 124.44 120.41 136.92 137.77 288.50 281.88 310.65 278.45 257.09 19529 17968 20271 20035 20079

Unrestricted Requirement (MUs) 237.52 223.15 266.75 280.51 259.18 149.68 147.76 164.62 154.92 156.37 316.15 287.07 311.47 308.56 305.86 23252 21384 23609 23393 22648

Deficit(-)/Surplus(+)

(i) MUs -3.61 -4.78 -5.73 -4.95 -3.87 -18.60 -23.32 -44.21 -18.00 -18.60 -27.65 -5.19 -0.82 -30.11 -48.77 -3722 -3417 -3338 -3358 -2569

(ii) % -1.52 -2.142 -2.15 -1.76 -1.49 -12.43 -15.78 -26.86 -11.62 -11.89 -8.75 -1.808 -0.26 -9.76 -15.95 -16.01 -15.98 -14.14 -14.35 -11.34

Maharashtra

POWER SUPPLY POSITION IN WR FOR PERIOD FROM JANUARY 2009 TO MAY 2009 (IN MUs)

Details Chhatisgarh Gujarat Madhya Pradesh

Details Western RegionGoa Daman & Diu Dadra & Nagar Haveli

Page 54: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

400 kV S/SMonth Max Min Max Min Max Min Max Min Max Min Max Min

Jan-09 422 380 428 389 424 380 440 390 426 400 421 400

Feb-09 421 376 430 383 426 384 438 390 426 400 421 400

Mar-09 423 386 429 397 424 389 438 398 424 399 424 404

Apr-09 425 382 430 392 424 378 436 400 424 398 422 400

May-09 420 390 428 399 426 385 436 400 426 401 422 407

400 kV S/S

Month Max Min Max Min Max Min Max Min Max Min Max Min Max Min

Jan-09 418 388 419 389 422 389 424 383 431 385 762 724 774 723

Feb-09 415 389 420 394 428 385 424 389 430 383 755 727 776 720

Mar-09 417 390 424 384 433 399 430 393 429 393 761 726 775 713

Apr-09 420 394 415 382 429 396 437 389 430 392 773 725 777 721

May-09 419 393 421 390 427 394 427 381 428 399 763 734 781 729

Annexure-6.2Voltages at the important 400 and 765 kV substations during the period

January 2009 to May 2009

Indore Itarsi Karad Dhule Asoj Kasor

Nagda Sipat (765 kV) Seoni (765 kV)Bhilai Jetpur Bina Gwalior

Page 55: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

1

Presentation on Smart Grid Implementation using PMU based

Wide Area Measurement System(WAMS) for Western Region

ByN. S. Sodha

GM (I/c) LD&CPower Grid Corporation of India Limited

Annexure-7

Manmad

Pane ndro

Mehsana

ViramgamDe hga m

Limbd i

Ka wasUtran

Va v

Anjar

Deodhar PalanpurZerda (Kansari)

Dhrarnga dhra

Bhatia RanavavGondal

Vartej

Keshod

Kodinar

Savarkundla

Magarwada (D & D)

Nasik

UranAptaPa d g he

Ka lwaBorivali

Trombay

Aura nga ba d

Ahmadnagar

Lo nikha nd

PusadCHANDRAPUR

KORADI

Pench

Bhugaon

Ambazari

Sa tpuraNepanagar

Burwaha Korba (E)

RaigarhBhatapara

Sujalpur

TO KOTA

NeemuchGand hisagar

Gwalior

Malanpur

Bhop a l

Ita rsi

Bina

Katni

Damoh Vindhya chal STPS

2 x 250 MW

2 x 500 MW

AmarkantakJa b alupr (PG)

Bargi

Sa tna Bansagar TO SINGRAULI STPS(N.R.)

Rewa

Khaparkheda

Bhadravati

BARSOORTO RAMAGUNDAM

TO L. SILERU

RAIPUR

BHILAI

Pa rli

SholapurSholapur(PG)Osmanabad

Koyna

Karad

Ti llari

Ponda To Nagjhari

To Belga um

Vijapur

HimmatnagarDhansura

Kada na

Halol

Ratlam

Godh ra

Na gda

Ujjain

Indo reSSP

Halderwa

Uka i(T)

Ichha pur Ukai(H)

PithampurDewas

GUJARAT

RAJASTHAN

UTTAR PRADESH

ORISSA

J HARKHAND

ANDHRA PRADESH

KARNATAKA

GOA

AR

AB

IA

N S

EA

MADHYA PRADESH

Ja b a lpur

Nanded

Jambuva

Je tpur

Ko rb a(W)

Hasdeo Bango

Birsinghp ur

Bable shwar

Gandhinagar

Jha nor

Bhusawa l

MAHARASHTRADhule

Chhatral

Navsari

Kakrapar1

4

Tarapur

GPEC

Kandalgao n

Aso j

Wa na kbori

Karamsad

Chalisagaon

KSTPS

TO Aura iyaMehgaon

New Ko yna

Dabho l

Ka sor

Nagothane

Q/c

TharadSankhari

Dhokadwa

Morbi

WagodiaAmre li

Naghedi

Jamnagar

Rajkot

Nakhatra naNanikhakar

Nard ipur(Soja)

BhandaraKanhan

Wardha

Butibori

Bara matiLonand

Vita

KolhapurMiraj

Parb hani

YawatmalAkola

Motijheel

To Sa waiMa d hopur

NR

Chhindwara

Seon i

Balaghat

Beed

Malkapur Paras

Paliad

Kheralu

Jamla

SachinEssa r

GSEG

WankanerSikka

Gujarat1 Achhalia2 Zagadia3 Kim4 Ranasan5 Kapadwanj6 Mangrol (Surat LPP)

2

3

5

Dhanduka

Una

Diu(D&D)

Karadpada(DNH)

PichhoreRajghat

Julwania

Narsinghpur

Khapaswami

Maihar

Kymore

ManendragarhVishramgarh

Wa idhanMorwa

To Rihand

Urla

Dongargarh

SuwasraAgar

Amravati

Badnera

Dahanu(BSES)

Malegaon

Latur

Jalna

Chinchwad

1

CHHATTISGARH

Maharashtra1

Parvati

Je juri2 Theur3

2

Bosari

BoisarKhargha r

POWER MAP OF WESTERN REGION

HYDRO POWER STATIONSTHERMAL - COA L

G AS

NUCL EAR P OWER STATION4 00 KV TRANSMISS ION LINES4 00 KV LINES UNDER P LA N UP TO MA R.2012

5 00kV HV DC B ipole

L E G E N D

P r e p a r e d b y :O S , W R L D C , M u m b a i

3

RelianceDhuvaranKhambol ia

6

Eldabad

Mapusa

Gadinglez

Kalmeshwar

Warora

UjaniUdgir

Jalgaon

VapiBhilad Ambheta

Khandwa

Indira Sagar

Kotma

Pandurna

To R.P.Sagar

TO Mo tak

Bina ( )PG

Pa rli( )PG

Pune ( )PG

ROURKELA

Korba (E)

2 x 250 MW

Navi Mumbai

Rajgarh

Sipa t

765 kV LINE

Ranchi

To Kankroli

Budhipadar

Ranchodpura

Agra

Palithane

Akrimota

Shivpuri Kalan

Mundra

Bhiwandi

Sasan

Tamnar

NSPCL

Nimrani

Om ka re shwa r

220 kV L INE

Bachhau

Western Region System – Salient Features

• Largest Regional Grid with highest installed Generation capacity (43040 MW)

• Geographically large states with high Power demands i.e. Maharashtra(~14000 MW), Gujrat(~12000 MW), M.P.(~7000 MW)

• Progressive Constituents with high Industrial & Agriculture growth

• Western Region is progressive in adopting to new Technology

Need for PMUs & WAMS Technology

• Increasing Stress on Transmission Grids– Grid is Interconnected– Open Access– Inter-Regional Power Trading

• Lack of tools for monitoring Dynamic behaviourof grid– Existing tools are not adequate

• Monitor & then “estimate” the steady state• Heavy dependence on Dispatcher’s

knowledge

Smart Grid functions

SMART GRID ENVISAGES TO ACHIEVE:• Be able to heal itself • Motivate consumers to actively participate in

operations of the grid • Provide higher quality power that will save money

wasted from outages • Accommodate all generation and storage options • Enable electricity markets to flourish • Run more efficiently

HP_Owner
Text Box
Annexure-7
Page 56: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

2

WAMS advantages

Synchro Phasor angle Measurement over Wide Area facilitates the following:

• Enhance real-time visualization of power system• Useful for real-time congestion management• Design of an advanced warning system• Validation and fine tuning of system models• Design of an adaptive protection system• Design “Special Protection Schemes” for large

Hybrid grid to prevent major grid collapses

Initiatives By POWERGRID for installation of PMUs

• Implementation of Pilot project for installation of PMUs (Phasor Measurement Units) in Northern Region – Approved by NRPC

• Implementation of CSIR approved Project “Intelligent Monitoring & Control of the Interconnected Electric Power Grid using WAM” – Proposed for Western Region

Limitations of the existing system

• Refresh Rate 4 -15 Seconds at first Control Centre & more at higher levels

• Latency & Skew

• Static view of the system

Intelligent Monitoring & Control of the Interconnected Electric Power Grid Using Wide Area Measurements (WAM)

The Project is approved by CSIR & Funded by CSIR (Council of Scientific and Industrial Research) under New Millennium India Technology Leadership Initiative (NMITLI)

• Along with POWERGRID other members of the consortium are:-– TCS-Leader– PowerAnser Labs ( PAL) of IIT Mumbai (IIT

Mumbai)– Tata Power Company Limited (Tata Power)

Wide Area Measurements (WAM) Project Highlights

• Project Duration – 3 Years– Implementation Completion 2 Years and testing

in last one year.

• Utilise the expertise of well known experts in the field such as Professor A.G.Phadke of Virginia tech

Intelligent Monitoring of the Interconnected Power Grid using Wide Area Measurements

(WAM)

Project details:• Installation of PMUs(Phasor Measurement Units) at around

25 to 30 Locations in Western Region Grid. The data from PMUs shall be acquired at Western Regional Load Dispatch Center (WRLDC)

• Development of Dynamic State estimator/Monitor including the development of algorithm for optimal placement of PMUs

• Supervised Zone-3 Blocking functionality to prevent tripping of distance relays on Power Swing, voltage stability, Load encroachment etc.

• Emergency control schemes for mitigating system instabilities. Schemes for controlling angular instability (i.e out of step protection & smart islanding)

Page 57: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

3

System Schematic

WRLDC - Mumbai

IITB Terminal

Intelligent Monitoring of the Interconnected Power Grid using Wide Area Measurements

(WAM)

• POWERGRID’s Role

– Detailed engineering specifications for the PMU – Installation & commissioning as well as operating the

PMU based WAM system – Provide the communication infrastructure for the

PMU based WAM system.– Continued maintenance of the complete system.– Post- project closure, POWERGRID would generate

periodic performance reports of the WAM system.

Wide Area Measurements (WAM) Project –Cost

1. TCS Rs. 3.77 Crores2. IIT Mumbai Rs. 2.77 Crores (Grant)3. Tata Power Rs. 1.44 Crores4. POWERGRID Rs. 8.76 Crores

Total Rs. 16.75 Crores

• Soft Loan-to be paid back over 10 years at a interest rate of 3% after completion of the project

• Annual installment ranging from Rs.90.267 lakhs to Rs. 127.01 lakhs

Agreement needed

• Member may please agree in principal for implementation of this project in Western Region

• Proposed to be funded through UI CAP fund or Additional UI fund

Page 58: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Annexure-15 1/3 PROGRESS OF TRANSMISSION LINES UNDER CONSTRUCTION IN WESTERN REGIONSr.No.

Name of transmission line Length in Ckt. Km

Anticipated Completion

REMARKS

Target

A gaujarat GUJARAT (March 2009)

I. 400 kovaI laa[-na 400 kV Lines 1 LILO of 400 kV Asoj-Amreli line at 400 kV Chorania 39.10 Dec.08 Line is charged on 18.12.08

II. 220 kovaI laa[-na 220 kV Lines2 220 kV Bardoli-Chikhali D/C 96.00 Sept. 08 Ckt-I & II made parallel on 30.9.08

3 200 kV LILO at Mota (Bardoli) S/S from 2nd Ckt. of Ukai (T)-Vav 9.60 Sept. 08 Line work complted. Feeder bay work completed.LILO point jumper work pending.

4 200 kV D/C Utran-Kosambaat Kosamba S/S from Vav-Zagadia line 172.00 Oct-09 Check survey, foundation and Erection work under progress.

7 200 kV LILO Mangrol-Mobha D/C line 218.00 Jan-09 Foundation, erection & stringing work inprogress.

8 220 KV D/C Chorania - Bala 59.12 Feb-09 Foundation, erection & stringing workcompleted. Bay work completed on 14.04.09.

9 220 KV D/C Rajpur-Dudhrej 19.16 Dec-08 Work completed.10 200 kV LILO at Dinod S/S (Kosamba) from Vav-Zagadia line 10.20 Mar.09 Profiles under scrutiny

11 200 kV LILO at Chitrod from Deodar-Anjar 2.10 Line is ready but feeder bay panel work pending at Shiviakha S/s end.

12 200 kV LILO of Shivlakha-Nanikhakhar at Varsana one ckt at Kukma s/s

34.00 Mar.09 Work under progress.

13 220 KV D/C Mundra (Adani) - Varsana D/C line 166.00 Jun-09 Erection work under progress.14 220 KV Nanikhakhar-Adani Power ProjectD/C line 32.50 Oct. 08 Circuit No-2 charged on 22.11.08B maGya p`doSa MADHYA PRADESH (March 2009)

I. 400 kovaI laa[-na 400 kV Lines 1 Extention of 400 kV Birsingpur-Katni-Damoh for PGCIL Damoh 26.04 2008-09 Line charged on 8.8.2008

2 Diversion of 400 kV Birsingpur-Katni-Damoh at Katni 1.94 2008-09 Line charged on 8.8.2008

3 Interconnector arrangement at 400 kV Birsingpur-Katni-Damoh at Birsingpur

0.66 2008-09 Line charged on 8.8.2008

II. 220 kovaI laa[-na 220 kV Lines4 LILO of 220 kV Birsinghpur-Rewa one Ckt. At Sidhi 117.56 2008-09 Line charged on 26.10.08

5 LILO of 1st Ckt. DCDS 200 kV Gwalior- Malanpur at 400KV Gwalior PGCIL S/S

16.90 2008-09 Work in Progress

6 200 kV Satna-Chhatarpur 140.00 2008-09 Work in Progress.

7 200 kV Amarkantak-Birsinghpur DCDS at 400kV s/s SUKHA(PGCIL) 300.00 2008-2009 In principle Forest approval for 4.366 Hactare received on 23.11.07. Final approval awaited. Work in progress.

8 220 kV Chhindwara-400 kV PGCIL Seoni D/C 140.00 2008-09 Work almost completed.9 LILO of first Ckts.of 200 kV Pithampura-Rajgarh for 400kV PGCIL

Rajgarh23.66 2008-09 Line Charged on 04.07.08

10 LILO of one Ckt of 200 kV Jabalpur-Itarsi at Piparia S/S 7.20 2008-09 Work almost completed.11 LILO of one Ckt of 200 kV Itarsi-Bhopal for 220kV Mandideep 12.38 2008-09 Line Charged on 25.5.0812 200 kV Shivpuri-Sabalgarh DCDS 200.56 2008-09 Line Charged on 11.02.0913 Second Ckt. Of 200 kV Pithampura-Rajgarh 68.65 2008-09 Line Charged on 25.5.0814 LILO of second Ckt of 220 kV Jabalpur-Itarsi for 220 kV Narsingpur 3.95 2008-09 Line Charged on 11.02.09

15 220 kV Bhopal (400 kV) -Ashta for Ashta S/S 194.00 2008-09 Work in Progress

25 LILO of 200 kV Birsingpur-Satna one Ckt. at ATPS Chachai 91.24 2008-09 Line Charged on 30.08.08

27 SujalpurPGCIL (400kV)-220kV Rajgarh Biaora line 134.40 2008-09 Work in progress.

28 Interconnector arrangement at 400kV Sujalpur-220kV Sujalpur 10.00 2008-0929 Jabalpur-Narsingpur part line for 400 kV PGCIL Sukha 158.00 2008-09 Work in Progress.

30 Chhindwara-Betul 270.00 2008-09 Work in Progress.134 kms survey completed

31 Chegoan-Nimrani 220.00 2008-09 Work in Progress.100.4 kms survey completed

32 LILO of one circuit of 220kV Satpura-Itarsi for 220kV Handia 220.00 2008-09 Work in Progress.

33 Rerouting of 220kV Makronia Traction Feeder through 220kV Sagar 10.18 2008-09 Work in Progress34 LILO of second circuit of 220kV Damoh-Bina line for proposed 220kV

Sager substations10.73 2008-09 Work completed. Line charged on 16.11.08

35 LILO of second circuit of 220kV Pithampur-Ratlam line for 220kV Badnagar

20.29 2008-09 Work completed exept termination of gantry

36 LILO of both circuit of 220kV Ujjain-Kota line for 220kV Badod 14.50 2008-09 Work completed.Line charged on 17.11.08

37 LILO of 1st Ckt. of 220 kV Itarsi-Bhopal for 220 kV Hosangabad 11.52 2008-09 Work completed. Line charged on 03.02.09.

38 LILO of 2nd Ckt. of 220 kV Itarsi-Bhopal for 220 kV Hosangabad 10.75 2008-09 Work in Progress39 LOLO of 1st Ckt. of 220 kV Damoh-Bina line for 220 kV sagar 15.22 2008-09 Work completed.Line charged on 07.03.09

Page 59: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Annexure-15 2/3

Sr.No.

Name of transmission line Length in Km

Anticipated Completion

REMARKS

Target

C C%tIsa gaZ CHHATTISGARH (March 2009)I. 400 kovaI laa[-na 400 kV Lines

1 LILO of 400 kV Korba (West)-Bhilai to Raipur DCDS 25.00 2008-2009 PB bid opened on 21.01.092 400 kV Korba(West)- Khedamara DCDS 220.00 2008-2009 PB bid opened on 04.03.09

II. 220 kovaI laa[-na 220 kV Lines1 200 kV Korba -Bishrampur DCSS 153.00 2008-2009 1st phase approval received from AIG(FC)

Min. of Env & Forest, New Delhi 2

LILO of 220 kV line from PGCIL Kumhari to 220 kV Doma S/S DCDS 40.002008-2009 Work under Progress, Delayed due to ROW

3 220kV DCDS Suhela-PGCIL Bhatapara line 15.00 2008-2009 Work under Progress, Delayed due to ROW

4 I/C 220 kV Raigarh-PGCIL Raigarh DCDS 10.39 2008-2009 Work under Progress5 220 kV Raigarh-Ms Jindal Power Ltd. DCDS 52.00 2008-2009 line charged on 19.11.086 LILO of 200 kV Korba-Siltara at Mopka DCDS 12.14 2008-2009 Work held up by contractor7 220 KV DCSS lines between 400 KV S/S Bhilai& Rajnandgaon+ 1 No.

bay at Khedamara52.50 2008-2009 Work under Progress, Delayed due to ROW

8 220 kV DCSS Khedamara-220 KV s/s Bemetara+ 1 No. bay at Khedamara & 1 No. at Bemetara

55.00 2008-2009 Work under Progress, Delayed due to ROW

9 220 kV DCDS lines Chhuri-Mopka(Bilaspur) 90.00 2008-2009 PB opened on 09.01.0910 220 kV I/C between New Power House at Korba(E) to prposed 220 kV

Chhuri30.00 2008-2009 Land not decided hence work not started.

11 Diversion of 200 kV line from Korba(E)-Bhilai line emanating from 200 MW PH-II to Korba(E) and 200 kV I/C in between Korba(E) PH-II

30.00 2008-2009 Land not decided hence work not started.

12 Diversion of 200 kV line from Korba-Bhatpara and 200 kV I/C in between Korba(W) and proposed 200 kV Chhuri S/S using section of Korba-Amarkantak - I & II DCSS

14.00 2008-2009 Land not decided hence work not started.

13 Diversion of 200 kV Korba-Amarkantak Ckt.I&II to proposed 200/132KV Chhuri S/S DCSS

4.00 2008-2009 Land not decided hence work not started.

D maharaYT/ (MAHARASHTRA) (March 2009)I. 400 kovaI laa[-na 400 kV Lines

1 400 kV Dabhol- Nagothane Ckt II 135.56 Mar-09 Severe ROW Problems in Vadvali villageII. 220 kovaI laa[-na 220 kV Lines

2 LILO on 200 kV Tarapur-Borivali for 200 kV Boisar-II S/S 8.00 Mar-10 Forest proposal recommended by Dy. COF Dahanu to Chief Conservator Thane. Court case at Loc.No.11

3 200 kV line from PGCIL to 200 kV Wada S/S 57.00 Mar-10 Work held up due to Court cases & forest clearance approval requirement

4 220 kV Therur - Magarpatta D/C 12.00 Mar-09 Line commission on 12.03.094 Interconnection between 200 kV Kolhapur II-Kolhapur III S/S 18.40 Sep-09 Not required. Agency left site.

E pavarg`aID POWERGRID (March 2009)

765 kovaI & 400 kovaI laa[-na 765kV & 400 kV Lines 1 SIPAT-I Trans. System 1.1 765 KV Sipat-Seoni line 2 354.0 Apr-08 Line commissioned in April 082 Western Region Strengthening Scheme-I 2.1 400 KV D/C Sipat - Raipur 298.0 Jul-08 Line commissioned in July 083 Sipat-II Supplimemtary Trans. System3.1 765 S/C Seoni-wardha (to be operated at 400kV) 269.0 Mar-093.2 400 kV D/C Wardha-Akola 324.0 Mar-093.3 400 kV D/C Akola-Aurangabad 482.0 Mar-09 Final checking under progress4 Western Region Strengthening Scheme-III 4.1 220 kV Vapi (PG)-Magarwada (DD) D/C line & 7 Kms.MultI-Ckt portion 31.0 Apr-08 Line commissioned in April 08

4.2 220 kV Vapi (PG)-Kharadpada(DNH) D/C line 34.0 Aug-08 Line commissioned in June 08

Page 60: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Annexure-15 3/3

Sr.No.

Name of transmission line Length in Ckt. Km

Anticipated Completion

REMARKS

Target

5 Western Region Stregthening Scheme-II5.1 SET-A: For absorbing import in eastern&central part of WR5.1.1 765 KV 2nd S/C Seoni(PG)-Wardha(PG) (initially to be operated at

400kV)268 Award placed in Feb' 09

5.1.2 400 kV D/C Wardha (PG)-Parli (PG)(Quad.) 694 - Stringing commenced from Feb'09 end5.1.3 400 kV D/C Raipur(PG)-Wardha(PG) 734 - Stringing commenced from Feb'09 end5.1.4 400 kV D/C Bhadravati (PG)-Parli(PG) 776 - Stringing commenced from Feb'09 end5.1.5 400 kV D/C Parli(MSEB)-Parli(PG) 14 - Engg. & survey under progress.5.2 SET-B: For Regional strengthening in southern Maharashtra (to

be implemented through IPTC route)-

5.2.1 400 kV D/C Parli(PG)-Pune 616 -5.2.2 400 kV D/C Pune(PG)-Aurangabad(MSEB) 450 -5.2.3 400 kV D/C Parli(PG)-Pandharpur/Solapur 392 -5.2.4 400 kV D/C Pandharpur/Solapur(PG)-Kolhapur(MSEB) 378 -5.2.5 LILO of Lonikhand(MSEB)-Kalwa(MSEB)400 kV D/C at Pune(PG) 48 -5.2.6 LILO of Solapur(MSEB)-Karad(MSEB)400 kV D/C at

Pandharpur/Solapur(PG)52 -

5.3 SET-C: For Regional strengthening in Gujarat (to be implemented through IPTC route)

-

5.3.1 400 kV D/C Rajgarh(PG)-Karamsad(GEB) 480 -5.3.2 400 kV D/C Limbdi(Chorania)(GEB)-Ranchodpura(Vadavi)(GEB) 190 -5.3.3 400 kV D/C Ranchodpura(Vadavi)(GEB)-Zerda(Kansari)(GEB) 310 -5.4 SET-D: For Regional strengthening in Northern Madhaya Pradesh

5.4.1 Bina(PG)-Gwalior(PG) 765 kV 2nd Ckt.to be operated at 400kV 233 Jul-105.4.2 400 kV D/C Korba(NTPC)-Birsighpur(MPGENCO) 462 Jul-105.4.3 400 kV D/C Birsighpur(MPGENCO)-Damoh(PG) 457 Jul-105.4.4 400 kV D/C Damoh(PG)-Bhopal(MPSEB) 430 Jul-105.5 Trans. Sy. Associated with Gandhar-II (GBPP) -5.5.1 400 kV D/C Gandhar-Kawas 190 * 33 months from investment approval or from5.5.2 400 kV D/C Gandhar-Rajkot 600 * date of tying up of FSA by NTPC whichever 5.5.3 LILO of 400 kV D/C Bina-Nagda at Shujalpur 60 * is later6 Western Region Stregthening Scheme-V6.1 400 kV Vapi(PG)-Navi Mumbai D/C line 370 Sep-10 Row problem faced6.2 220 kV Vapi-Khadoli(UT of DNH) D/C line 56 Sep-106.3 LILO of Lonikhand(MSEB)-Kalwa(MSEB) 400 kV S/C line at Navi

Mumbai 9 Sep-10 Engg. & survey in progress

7 Western Region Stregthening Scheme-VI7.1 400 kV D/C Dehgam - Pirana line 106 Nov-108 Western Region Stregthening Scheme-IX8.1 LILO of 400 kV D/C Bina-Nagda line 60 Jan-11 Tendering under progress

8 Inter-regional lines

8.1 East-West Transmission corridor strengthening scheme8.1.1 400 kV D/C Ranchi - Rourkela 286 Mar-108.1.2 400 kV D/C Rourkela - Raigarh 440 Mar-10 Stringing commenced from Mar'' 098.1.3 400 kV D/C Raigarh - Raipur 440 Mar-108.2 Kahalgaon Stage-II Transmission System8.2.1 400 kV D/C Ranchi - Sipat Lines 816 Dec. 08 Line completed&ckt I commissioned on

31.12.08&ckt II ready for commissioning.8.3 Transmission System associated with Barh Generation Project8.3.1 765 kV S/C Seoni - Bina line (to be charged at 400kV) 293 Sep-098.4 Transmission System associated with North west Transmission

corridor strengthening scheme8.4.1 765 kV Agra - Gwalior 2nd S/C line (initially to be operated at 400kV) 128 Mar-09 Line commissioned in Mar'09.

8.4.2 400 kV D/C Zerda-Kankroli 470 Mar-09 Line commissioned in Mar'09.

Page 61: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

GENERATION SCHEMES UNDER CONSTRUCTION DURING 11th PLAN IN WESTERN REGION

Sr. No. Name of the Power Projects Unit No. Capacity (MW)

Schedule Date of Commissioning

A GUJARATGeneration Schemes included in 11th Plan

1 Kutch Lignite TPS 4 75 Commissioned on 22.10.20082 Sugen CCPP (Torrent Power Gen. Ltd.) Block -1 382.5 Commissioned on 20.11.2008

Block-2 382.5 Synchronised on 29.01.09Block-3 382.5 Synchronised on 27.03.09

3 Surat Lignite expansion- GIPCL 1 125 June. 20092 125 Aug. 2009

4 Utran GPP GT+ST 374 Aug. 20095 Sikka TPP Extn. 3 250 Jan. 2010

4 250 May. 20106 Ukkai TPS Extn. 6 490 Feb. 20117 Pipavav CCPP- GPCL & GSPC joint venture Block-1 350 Sep. 2010

Block-2 350 Mar. 20118 Mundra TPP Ph-1 (Adani Power Ltd.) 1 330 May. 2009

2 330 Jul. 20099 Mundra TPP Ph-2 (Adani Power Ltd.) 3 330 Jan. 2010

4 330 Apr. 201010 Mundra Ultra Mega TPP (Tata Power Ltd.) 1 800 Sep. 2011

2 800 Mar. 101211 Hazira CCPP Expansion GSEG GT+ST 350 Dec. 2010

Other Projects1 Gujarat Lignite-NLC & GPCL joint venture Stage-I 1500 2011-12

Stage-II 500 2012-132 Dhuvaran CCPP GSECL Stage-III 360 Mar. 20103 Pipavav TPP- Torrent Power 1000 2011-124 Bhavnagar Lignite TPP-joint venture 500 Apr. 20115 Mundra STPP (Adani Power Ltd.) 1 660 Jan. 2011

2 660 June. 2011

B MADHYA PRADESHGeneration Schemes included in 11th Plan

1 Amarkantak TPS 5 210 Commissioned on 15.06.20082 500 Apr. 2011

2 Satpura TPS Extn. 10 250 Nov. 201011 250 Mar.2011

Other Projects1 Maheshwar HEP - 400 2010-112 Malwa TPP 1 500 Dec. 2010

Annexure-16 1/2

Page 62: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Sr. No. Name of the Power Projects Unit No. Capacity (MW)

Schedule Date of Commissioning

C CHHATTISGARHGeneration Schemes included in 11th Plan

1 Jindal PL 1 250 Commissioned on 08.12.072 250 Commissioned on 16.04.083 250 Commissioned on 15.06.084 250 Commissioned on 17.06.08

2 LANCO Amarkantak PL 1 300 Synchronised on 01.05.20092 300 Sept. 2009

3 Marwa TPP 1 500 Sept. 20122 500 Nov. 2012

4 Korba West-III TPP 1 500 Jun. 2012Other Projects

1 Bhaiyathan TPP Phase-I 1 500 Dec. 20122 500 Aug. 2013

2 IFFCO 1 660 Aug. 20122 660 Dec. 2012

D MAHARASHTRAGeneration Schemes included in 11th Plan

1 New Parli TPS Extn. 2 250 Aug. 20092 Paras TPS Extn. 2 250 Aug. 20093 Khaperkheda TPP Extn. 1 500 Mar. 20104 Bhusawal Extn. TPP 1 500 May. 2010

2 500 Sep. 20105 Trombay TPS Extn. (Tata Power Co.) 8 250 Commissioned on 14.01.20096 Ghatghar HPS (Hydro) 1 125 Commissioned on 13.05.08

2 125 Commissioned on 01.07.087 JSW Ratnagiri TPP (JSW Energy (Ratnagiri) Ltd.) 1 300 Jun. 2010

2 300 Sep. 20103 300 Dec. 20104 300 Mar. 2011

Other Projects1 Koradi TPS Extn. 1 800 Oct. 20122 Dhopawe TPP 1 800 Nov. 2011

2 800 May 20123 Uran CCPP Block-1 700 Feb. 2010

Block-2 340 May. 20104 Koradi TPS Extn. (Replacemet of 4 x 120) 1 800 Apr 20125 Parli TPS (Replacement of 2x30) 1 250 May. 20106 Paras TPS (Replacement of 1x62.5) 1 250 May. 20107 Bhusawal TPS (Replacement of 1x62.5) 1 250 May. 20108 Chandrapur TPS Extn. 1 500 Dec. 2011

2 500 May. 2012

E CENTRAL SECTOR - NTPCGeneration Schemes included in 11th Plan

1 Sipat-II TPP 5 500 Commissioned on 27.12.082 Sipat-I TPP 1 660 Nov. 2009

2 660 Sept. 20093 660 Mar. 2010

3 Bhilai TPP (Joint venture with SAIL) 1 250 Declared commercial w.e.f 2 250 Synchronised on 28.03.09

4 Korba STPS-III 7 500 Feb. 20105 Mauda TPP 1 500 2011-12

2 500 2012-12

Annexure-16 2/2

Page 63: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Annexure-17 (1/2)

Details Jun Jul Aug Jun Jul Aug Jun Jul Aug Jun Jul Aug

Availability (MW) 1993 2148 2056 7748 7209 7238 5144 5137 6536 13060 12660 13584Unrestricted demand (MW) 2389 2371 2329 9737 8745 8148 5000 4800 5200 16900 16600 16400Deficit(-)/Surplus(+)

(i) MW -396 -223 -273 -1989 -1536 -910 144 337 1336 -3840 -3940 -2816

( ii) % -16.58 -9.41 -11.72 -20.43 -17.56 -11.17 2.88 7.02 25.69 -22.72 -23.73 -17.17

Details Jun Jul Aug Jun Jul Aug Jun Jul Aug Jun Jul Aug

Availability (MW) 376 345 333 229 215 224 471 432 462 29941 29394 31843Unrestricted demand (MW) 460 455 455 258 260 262 505 495 490 33796 32335 31912Deficit(-)/Surplus(+)

(i) MW -84 -110 -122 -29 -45 -38 -34 -63 -28 -3855 -2941 -69

(ii) % -18.26 -24.18 -26.81 -11.24 -17.31 -14.50 -6.73 -12.73 -5.71 -11.41 -9.10 -0.22

ANTICIPATED POWER SCENARIO IN WR FOR PERIOD FROM JUNE 2009 TO AUGUST 2009 (IN MW)

Chhatisgarh Gujarat Madhya Pradesh Maharashtra

Goa Daman & Diu Dadra & nagar Haveli Western Region

Page 64: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Annexure-17 (2/2)

Jun Jul Aug Jun Jul Aug Jun Jul Aug Jun Jul Aug

Availability (MUs) 1343 1400 1340 5094 4878 5000 3014 3058 3960 7273 7058 7563Unrestricted Requirement (MUs) 1397 1509 1565 5398 5280 5009 2850 2790 2870 11000 10600 10600Deficit(-)/Surplus(+)

(i) MUs -54 -109 -225 -304 -402 -9 164 268 1090 -3727 -3542 -3037

(ii) % -3.87 -7.22 -14.38 -5.63 -7.61 -0.18 5.75 9.61 37.98 -33.88 -33.42 -28.65

Jun Jul Aug Jun Jul Aug Jun Jul Aug Jun Jul Aug

Availability (MUs) 244 231 215 112 102 103 253 228 241 17889 17610 19193Unrestricted Requirement (MUs) 270 260 255 148 163 165 312 305 305 21375 20907 20769Deficit(-)/Surplus(+)

(i) MUs -26.00 -29.00 -40.00 -36.00 -61.00 -62.00 -59.00 -77.00 -64.00 -3486 -3297 -1576

(ii) % -9.63 -11.15 -15.69 -24.32 -37.42 -37.58 -18.91 -25.25 -20.98 -16.31 -15.77 -7.59

ANTICIPATED POWER SCENARIO IN WR FOR PERIOD FROM JUNE 2008 TO AUGUST 2009 (IN MUs)

Details Chhatisgarh Gujarat Madhya Pradesh Maharashtra

Details Goa Daman & Diu Dadra & nagar Haveli Western Region

Page 65: œ¸¢© ¸Ÿ¸ ®¸½°¸ú¡¸ ¢¨¸Ô¸º÷¸ ¬¸¢Ÿ¸¢÷¸ · nabinagar (1000mw) of railways and ntpc, barh-ii (1320 mw), rihand-iii (1000mw), vindhyachal-iv (1000mw) and

Annexure -20 Details of members contributing towards incidental expenses

S. No. Organisation / State Utilities

A State Generating Companies (i) Gujarat State Electricity Corp. Ltd.

(ii) Chhattisgarh State Power Generation Co. Ltd. (iii) Madhya Pradesh Power Generation Co. Ltd. (iv) Maharashtra State Power Generation Co. Ltd.

B State Transmission Companies (i) Gujarat Electricity Transmission Corp. Ltd.

(ii) Chhattisgarh State Power Transmission Co. Ltd. (iii) Madhya Pradesh Power Transmission Co. Ltd. (iv) Maharashtra State Electricity Transmission Co. Ltd.

C State Distribution Companies (by rotation in case of more than one DISCOMs)

(i) Paschim Gujarat Vij Company Ltd., Rajkot (by rotation)* (ii) Chhattisgarh State Power Distribution Company Ltd. (iii) M.P. Paschim Kshetra Vidyut Vitaran Co. Ltd., Indore (by

rotation)* (iv) Maharashtra State Electricity Distribution Co. Ltd.

E Central Generating Co. & CTU (i) NTPC Ltd.

(ii) Power Grid Corporation of India Ltd. (CTU) (iii) Nuclear Power Corporation of India Ltd.

F GENCO having Installed Capacity

more than1000 MW (other than State / Central GENCOs) (i) Tata Power Company Ltd.

(ii) Ratnagiri Gas & Power Private Ltd. (iii) Narmada Hydroelectric Development Corp. Ltd.

(Indirasagar & Omkareshwar HEP) (iv) Narmada Control Authority (SSP)

G One member representing GENCO having IC 1000 MW and less (by rotation)

(i) ESSAR Co. Ltd. (by rotation)

H One DICOM out of private DISCOs in WR (by rotation) (i) BEST Ltd., Mumbai (by rotation)

I One member representing Electricity Traders (by rotation) (i) PTC Ltd., New Delhi (by rotation)


Recommended