- Recommendations status
- PRR Review report: actions
- Conclusion
E U S O - B A L L O O N D E S I G N R E V I E W, 1 8 . 1 2 . 2 0 1 2 , C N E S T O U L O U S E
Guillaume PrévôtAPC, Paris
Status on PRR recommendations and actions
Recommendations
3 recommendations:
- Project organization
- First flight as soon as possible
- Schedule control
Project organization“ Defining the CNES organization, introducing an electrical architect, identifying all the activities relative to the harness, clarify the participations to the AIT, the instrument GSE responsibilities.”
- Action 1.1: The team has provided the updated organization.- Action 1.2: The team has provided the updated development plan to CNES.
CDR – 18.12.2012
Status on PRR actions 2
Recommendations
First flight as soon as possible“In consequence, the review panel supports the Euso-Balloon Project in its demand to obtain the first flight as soon as possible considering the project schedule and the opportunities of the CNES Balloon campaigns. A first launch before mid 2014 is recommended.”
Schedule control“In consequence, the review panel supports the Euso-Balloon Project in its demand to obtain the first flight as soon as possible considering the project schedule and the opportunities of the CNES Balloon campaigns. A first launch before mid 2014 is recommended.”
- Action 3.1.1: The 3 laboratories have done a proposition for a new project manager and it has been accepted by CNES.
- Action 3.4.1: The team has provided the updated instrument planning to CNES.
CDR – 18.12.2012
Status on PRR actions 3
PRR Review report: actions
41 actions have been taken with answers from the project team expected for the design review.
- Updates of: - The Technical Specifications document (EUSO-TS-INST-206-LAL_V2.0)- The Instrument Definition document (EUSO-DF-INST-204-LAL_V2.0)- The Organization Note (EUSO-ON-INST-201-LAL_V2_6)- The Compliance Matrix (EUSO-PA-INST-203-LAL_V2.0)- The Risk Analysis document (EUSO-RI-INST-404-IRAP V1.1)- The Development Plan (EUSO-DP-INST-207-LAL_V2.0)
- Writing of: - A Thermal Analysis document (EUSO-TA-INST-409-IRAP V1.0)- A Mission Analysis document (CNES)- ICD documentation (EUSO-IC-INST-407-IRAP_V1.0 (electronics) and
EUSO-MI-INST-408-IRAP_V1.0 (mechanics)) - A AIT Plan document (EUSO-AI-INST-251-LAL_V1.0)- A calibration Note (EUSO-CN-INST-003-APC_V1.0)
CDR – 18.12.2012
Status on PRR actions 4
PRR Review report: actions
39 actions have been closed by the team.
2 actions are open (about cleanliness strain).
- FB-14 and OLM-14 are open and they will be dealt with on a specific note delivered at the AIT Key Point.
CDR – 18.12.2012
Status on PRR actions 5