7/30/2019 011013_3CRailServiceAdjustments
1/21
Custom er Service and Operat ions Comm it t ee
I n format ion I tem I I I -C
January 10 , 2013
Rail Service Adjustm ents for Stat e of Good Repair
7/30/2019 011013_3CRailServiceAdjustments
2/21
Washington Metropolitan Area Transit AuthorityBoard Action/Information Summary
Action InformationMEAD Number:
103186
Resolution:
Yes No
TITLE Rail Service Adjustments for State of Good Repair
PRESENTATION SUMMARY
To rebuild the system to a steady state of good repair, Metro continues the aggressivework program it launched in 2011. The outstanding amount of infrastructure andsystem work cannot be achieved without scheduled service interruptions that span fromsingle tracking on days, nights and weekends to total weekend shutdowns.
PURPOSETo update the Board on the upcoming 2013 service adjustments required to supportachieving a state of good repair.
DESCRIPTION
Key Highlights:
Metro has undertaken an aggressive rebuilding program that expends capital fundsto ensure a safer system and provide: Improved service reliability
Rehabilitated track system infrastructure
Smoother ride quality
Continued completion of National Transportation Safety Board (NTSB)
recommendations
BACKGROUND AND HISTORY
In 2011, Metro moved forward to rebuild the regions transit system investing $5 billionover the next six years to produce a better service for customers, made possibleth h f di t f th Di t i t f C l bi M l d Vi i i d th
7/30/2019 011013_3CRailServiceAdjustments
3/21
This major investment is already showing results in the form of improved reliability onMetrorail and improved safety. Last May Metro completed the installation of the
Guarded No. 8 switches throughout the system, one of the NTSB recommendations.
DISCUSSION
The Fiscal 2013 Capital Budget continues to accelerate efforts to rebuild Metro, withnearly a billion dollars ($997M) in investment. Over the next three months Metro hasscheduled 43 single tracking/11 shutdowns to accomplish:
Rehabilitation of station platforms Rehabilitation of 3rd rail Repair/replacement of insulators, fasteners, ties and turnouts Operational testing for the Silver Line Installation of Neutral Host cable Replacement of track circuits Rail welding Replacement of track Replacement of #10 turnouts Repair of tunnel leaks Radio remediation Greenbelt test track
A chronological listing of upcoming single tracking outages and shutdowns is provided
in the attached Appendix. Outages have been planned to complete the project work inthe shortest time while minimizing customer impact. This is accomplished by multipleprojects working in parallel during outages. Further review of required maintenance andinfrastructure work is ongoing to assess the need for additional outages.
There are no planned shutdowns during: Martin Luther King/Presidential Inauguration Cherry Blossoms 4th of July Thanksgiving Christmas
Metro has conducted a proactive and aggressive customer outreach campaign toensure that as part of the Metro Forward Campaign the public is aware of upcoming
7/30/2019 011013_3CRailServiceAdjustments
4/21
Call Center (on-hold) recordings Added personnel on-site
Community briefings, outreach Outreach to local Departments of Transportation News media advisories Newspapers, radio advertisements
ALTERNATIVES
None
FUNDING IMPACT
All projects are funded in the FY13 approved Capital budget.
MEAD AMOUNT
$0
TIMELINE
Previous Actions Provided the Board an update July 2012AnticipatedActions AfterPresentation
The Board and public will continue to be informed regardingupcoming work through the Metro Forward Campaign andCustomer Outreach.
RECOMMENDATIONNo recommendation, information item only.
ELECTRONIC ATTACHMENTS
None
7/30/2019 011013_3CRailServiceAdjustments
5/21
Washingt on Met ropolit an Area Transit Aut horit y
2013 Rail Service Adjustments for
State of Good Repair
Customer Service and Operations CommitteeJanuary 10, 2013
Page 61 of 78
7/30/2019 011013_3CRailServiceAdjustments
6/21
1st Quart er Upcoming Single Tracking &Shutdowns
43 single trackingrd,
o ETS cableo Silver Line operational testing
o Installation of Neutral Host cable (Cell Phone Carriers)
o Track circuit replacement NTSB recommendation
11 shutdowns - multiple projects in parallelo Rail welding
o Replacement of track/#10 turnouts
o Repair of tunnel leaks
o
o Greenbelt Test Track
o Repair/replacement of insulators, fasteners,
ties turnouts
Page 62 of 78
7/30/2019 011013_3CRailServiceAdjustments
7/21
Upcoming Shut dow n Notes
No planned shutdowns duringMartin Luther King/PresidentialInauguration weekend
No planned shutdowns duringCherr Blossoms 4th of JulThanksgiving and Christmas
weekend shutdowns beingevaluated
Page 63 of 78
7/30/2019 011013_3CRailServiceAdjustments
8/21
Customer Out reach Conducted
As part of Metro Forward Campaign
o Electronic display screens at kiosk in every stationo In station banners, signs, murals, take ones
o Social media messages, videos
o Web site postings
o Metro alerts customer advisories
o Call Center (on-hold) recordings
o Added personnel on-site
o Communit briefin s outreach
o Outreach to local Departments of Transportation
o News media advisories
o Newspaper, radio advertisements
Page 64 of 78
7/30/2019 011013_3CRailServiceAdjustments
9/21
Page 65 of 78
7/30/2019 011013_3CRailServiceAdjustments
10/21
Single Tracking Operat ions
Start Finish Line Type Locat ion
January 10,2012 January12,2013 Red 3rd Rail Friendship Heights MedicalCenter
January10,2013 January17,2013 Blue Station Dome FederalCenterSW Eastern Market
January10,2013 January28,2013 Green FenceInstallation College Park Greenbelt
January 10,2013 January 12,2013 Red PlatformRehab RhodeIslandAve Takoma
January11,2013 January14,2013 Green FenceInstallation College Park Greenbelt
January11,2013 January 14,2013 Red ETSCable RhodeIslandAve FortTotten
Januar 11 2013 Januar 14 2013 RedFastener/Insulator
VanNess Friendshi Hei htsRenewa
Outages scheduled as of January 2, 2013
Page 66 of 78
7/30/2019 011013_3CRailServiceAdjustments
11/21
Single Tracking Operat ions
St ar t Finish Line Type Locat ion
January
22,
2013 January 24,
2013 Red 3
rd
Rail Friendship Heights
Medical
Center
January14,2013 January17,2013 Red NeutralHost FarragutNorth JudiciarySquare
January19,2013 January22,2013NoSingleTracking
MartinLuther King/PresidentialInauguration
January22,2013 January31,2013 Blue Turnouts StadiumArmory Morgan Blvd
January25,2013 January28, 2013 OrangeDTPOperational
TestingEastFallsChurch WestFallsChurch
January25,2013 January28,2013 OrangePlatform
Rehab/
FastenerRenewalStadium Armory Cheverly
January25,2013 January28,2013 Green FenceInstallation College Park Greenbelt
Outages scheduled as of January 2, 2013
Page 67 of 78
7/30/2019 011013_3CRailServiceAdjustments
12/21
Single Tracking Operat ions
St ar t Finish Line Type Locat ion
January 28,2013 February 07,
2013 Red Platform
Rehab Rhode
Island
Ave
Takoma
January28,2013 February 02,2013 Red FastenerRenewal VanNess FriendshipHeights
February1,2013 February4,2013 Green TestTrackProject College Park Greenbelt
February1,2013 February4,2013 Red NeutralHost Farragut North JudiciarySquare
February1,2013 February4,2013 OrangeDTPOperational
TestingEast FallsChurch WestFallsChurch
February4,2013 February7,2013 Orange DTPBrakeTesting East FallsChurch WestFallsChurch
February4,2013 February7,2013 Red JointElimination Dupont Circle VanNess
Outages scheduled as of January 2, 2013
Page 68 of 78
7/30/2019 011013_3CRailServiceAdjustments
13/21
Single Tracking Operat ions
Start Finish Line Type Locat ion
February 4,2014 February14,2014 Blue Turnout StadiumArmory MorganBlvd
February 6,2014 February212014Green/
Yellow
CamerasandCeiling
TileInstallationMt. VernonSquare LEnfantPlaza
February 8,2013 February11, 2013 Orange
JointElimination/Rail
&FastenerRenewal Ballston WestFallsChurch
PlatformRehab/e ruary , e ruary , range
FastenerRenewala um rmory ever y
February 8,2013 February11, 2013 Green TestTrackProject College Park Greenbelt
February 8,2013 February
11, 2013 Red Platform
Rehab Twinbrook
Shady
Grove
February 8,2013 February11, 2013 Red PlatformRehab RhodeIslandAve Takoma
Outages scheduled as of January 2, 2013
Page 69 of 78
7/30/2019 011013_3CRailServiceAdjustments
14/21
Single Tracking Operat ions
St ar t Finish Line Type Locat ion
February11,2013 February 14,2013 Red FastenerRenewal VanNess FriendshipHeights
February11,2013 February28,2013 Red PlatformRehab RhodeIslandAve Takoma
February 15,2013 February19, 2013 Red PlatformRehab RhodeIslandAve Takoma
February19,2013 February21,2013 Red Platform Rehab Twinbrook ShadyGrove
February19,2013 February22,2013Orange/
BlueDomeRehab EasternMarket toStadiumArmory
February19,2013 March28,2013Yellow/
Blue3rd Rail NationalAirport BraddockRoad
Februar 22 2013 Februar 25 2013 Red PlatformRehab RhodeIslandAve Takoma
Outages scheduled as of January 2, 2013
Page 70 of 78
7/30/2019 011013_3CRailServiceAdjustments
15/21
Single Tracking Operat ions
St ar t Finish Line Type Locat ion
February22,2013 February25,2013 OrangePlatformRehab/
FastenerRenewal
Stadium Armory Cheverly
February22,2013 February25,2013 Green TestTrackProject College Park Greenbelt
February22,2013 February25,2013 Red RailRenewal VanNess Friendship Heights
February 25,2013 February 28.2013 Orange
TestingEast FallsChurch WestFallsChurch
February 25,2013 March 1,2013Orange/
BlueDomeRehab EasternMarket toStadiumArmory
February 25,2013 March 14,2013Green/Yellow
CamerasandCeilingTileInstallation
Mt. VernonSquare LEnfantPlaza
March 1 2013 March4 2013 Oran ePlatformRehab/
Stadium Armor CheverlFastenerRenewa
Outages scheduled as of January 2, 2013
Page 71 of 78
7/30/2019 011013_3CRailServiceAdjustments
16/21
Single Tracking Operat ions
St ar t Finish Line Type Locat ion
March 8,2013 March11,2013 OrangePlatformRehab/
FastenerRenewal
Stadium Armory Cheverly
March 15,2013 March18,2013 OrangePlatformRehab/
Stadium Armory Cheverly
Outages scheduled as of January 2, 2013
Page 72 of 78
7/30/2019 011013_3CRailServiceAdjustments
17/21
Total Shut dow ns
Start Finish Line Locat ion
January11,2013 January14,2013 Blue Rosslyn Pentagon
January19,2013 January22,2013NoShutdown
MartinLutherKing/PresidentialInauguration
January25,2013 January28,2013 Red DupontCircle RhodeIslandAvenue
February01,2013 February04,2013 Blue/OrangeFederal CenterSW Cheverly&Benning
Road
StadiumArmory Cheverly &LargoTowne ruary , e ruary , ue range
Center
February15,2013 February19,2013 Green CollegePark Greenbelt
Outages scheduled as of January 2, 2013
Page 73 of 78
7/30/2019 011013_3CRailServiceAdjustments
18/21
Total Shut dow ns
Start Finish Line Locat ion
February 22,2013 February25,2013 Orange Ballston Vienna
March01,2013 March04,2013 Blue/Yellow Crystal City BraddockRoad
March01,2013 March04,2013 Red Brookland Takoma
March08,2013 March11, 2013 Blue/OrangeFederalCenterSW MinnesotaAvenue&
BenningRoad
arc , arc , e o a a au e a oma
March15, 2013 March18, 2013 Green Congress Heights BranchAve
March22,2013 March25,2013o u own
CherryBlossoms
Outages scheduled as of January 2, 2013
Page 74 of 78
7/30/2019 011013_3CRailServiceAdjustments
19/21
Total Shut dow ns
Start Finish Line Locat ion
March29,2013 April1,2013No Shutdown
Cherr Blossoms
April5,2013 April8,2013No Shutdown
CherryBlossoms
April 12,2013 April15,2013No Shutdown
erry ossoms
April19,2013 April22,2013 Orange Rosslyn VirginiaSquare
pr , pr , e o a a au e a oma
May3,2013 May6,2013 Green CongressHeights BranchAvenue
May10,2013 May13,2013 Orange Ballston Vienna
Outages scheduled as of January 2, 2013
Page 75 of 78
7/30/2019 011013_3CRailServiceAdjustments
20/21
Total Shut dow ns
Start Finish Line Locat ion
May17,2013 May20,2013 Green CollegePark Greenbelt
May17, 2013 May20, 2013 Orange Clarendon EastFallsChurch
May24,2013 May 28,2013 Orange EastFallsChurch Vienna
May24,2013 May28, 2013 Red Twinbrook Shady Grove
ay , une , e e ro en er oo ey ar oo
June7,2013 June10,2013 Green/Yellow ShawHowardU GeorgiaAve
June14,2013 June17,2013 Red Takoma ForestGlen
Outages scheduled as of January 2, 2013
Page 76 of 78
7/30/2019 011013_3CRailServiceAdjustments
21/21
Total Shut dow ns
Start Finish Line Locat ion
June21, 2013 June24,2013 Red Takoma ForestGlen
June28,2013 July 1,2013 Green CollegePark Greenbelt
July3,2013 July5,2013No
Shutdown
o u y
Outages scheduled as of January 2, 2013
Page 77 of 78