7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 1/96
LOMUT - LOKORI (C46) ROAD
PRESENTATION OF THE
PRELIMINARY DESIGN REPORT18TH JULY 2013
Kenya National HighwaysAuthority
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 2/96
PRESENTATION
PART 1: PROJECT BACKGROUND ANDCOMMENCEMENT OF THE CONSULTANCYSERVICES
PART 2: PROJECT LOCATION MAP AND SELECTEDPROJECT ROAD PHOTOGRAPHS
PART 3: DOCUMENTS PREPARED AND SUBMITTED TO
CLIENT
PART 4: THE INCEPTION REPORT
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 3/96
PART 5: THE PRELIMINARY ENGINEERING DESIGNREPORT
PART 6: THE PRELIMINARY MATERIALS & PAVEMENTREPORT
PART 7: PRELIMINARY DESIGN BOOK OF DRAWINGS
PART 8: THE ECONOMIC FEASIBILITY STUDY REPORT
PART 9: THE ENVIRONMENTAL AND SOCIAL IMPACTSTUDY REPORT
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 4/96
PART 1:
PROJECT BACKGROUND AND COMMENCEMENT OF
THE CONSULTANCY SERVICES
1. PROJECT BACKGROUND
The Kenya National Highways Authority (KeNHA) on behalf of the
Government of the Republic of Kenya issued an Invitation to Tender dated
August 2010, for eligible Consultancy firms to submit both Technical and
Financial Proposals for Consultancy Services for Preliminary and DetailedEngineering Design of Lomut - Lokori(C46) Road.
CAPEconsult Ltd. submitted both Technical and Financial Proposals for this
project.
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 5/96
• The Director General of the Kenya National Highways Authority (KeNHA)
awarded the contract for consultancy services for this project to
CAPEconsult Ltd. (hereinafter called the Consultant) vide letter of
Notification of Award Ref. No. KeNHA/363/2011 dated 25th January 2012.
• The Consultant consequently accepted the offer in their letter to the
Director General of the Kenya National Highways Authority Ref. No.
J.1201/001/pw dated 6th February 2012.
• On 2nd April 2012 vide his letter Ref. No. KeNHA/D&C/D/C46/5545, the
General Manager (Design and Construction), issued Commencement
Order to the Consultant. The order instructed the Consultant to
commence the services within 14 days of the order to commence. The
Consultant consequently commenced the services on 16th April 2012
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 6/96
2. PROJECT DESCRIPTION
The C46 Lomut-Lokori road is situated in West Pokot and Turkana Counties
in Northern Kenya. The road starts at the junction of C46 and B4 roads at
Lomut. It runs in a Northerly direction through Nyangaita, Amaler,
Lochakular, before ending at Lokwamosing centre at the junction with
C113.
The entire length of the project road is to earth un-engineered standards.
The main economic activity is livestock keeping.
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 7/96
3. CONSULTANT’S DESIGN TEAM
The Consultant mobilized the following personnel to carry out the
assignment;
1. Eng. P. O Wanday – Project Director
2. Eng. M. O. Ogola – Highway Engineer
3. Eng. J. Ruigu – Materials/Pavement Engineer
4. Eng P. O. Oyunga – Bridge/Structural Engineer5. Eng. H.A. Ndugah – Hydrologist/Drainage Engineer
6. J.K. Ndede – Surveyor
7. W.H. Ngiringacha - Environmentalist
8. Z. Oyier – Traffic Engineer/Transport Economist
The Consultant also engaged the following Assistant Engineers
1. Mr. Antony Oloo
2. Mr. Jacob Odhiambo Imbo
3. Mr. Joseph Majiwa
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 8/96
4.0 SCOPE OF THE ASSIGNMENT
As called for in the Terms of Reference the Scope of the Consultancy serviceincluded the following;
In stage I, the Consultant shall perform the following duties: -
1) Review of the existing data on the proposed road project and social andeconomic activities in the project study area and producing an economicfeasibility study report;
2) Collection of social, environmental, and physical data that is necessary toassist in the design of the project road;
3) Preliminary engineering survey and design work for the optimum alignmentand design standards including preliminary costs estimates andimplementation schedule;
4) Carrying out an environmental impact assessment study of the project area
in relation to the proposed project.• In stage II and subject to approval of stage I above by the General Manager(Design and Construction), the Consultant shall then carry out a detailedengineering surveys and investigations, design, cost estimates and tenderdocuments for the road project.
.
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 9/96
4.0 FINANCING
• This Study is financed by the Government of Kenya (GoK).
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 10/96
PART 2
PROJECT LOCATION MAPS AND SELECTEDPHOTOGRAPHS
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 11/96
PROJECT LOCATION MAP
LOCHAKULAR AMALER
SIGOR
MARICH PASS
LOKORI
LOKICHAR
LOKWAMOSING
NGAMIA-1
LOMUT
TOT
NYANGAITA
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 12/96
PROJECT ROAD PHOTOGRAPHS
Start of the Project Km 0+000 at Lomut
Road Alignment and Geometry
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 13/96
Recently graded section between km 0+000 to km 38+500
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 14/96
Typical road section from km 38+500 to the project end
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 15/96
A section Of the Project Road Within the National Reserve with vegetation
encroaching onto the road
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 16/96
Km 0+700: Erosion problems and lack of drainage facilities highlighted by deep gulleys
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 17/96
This Makeshift culvert was the only “Designed” Drainage Structure along the Entire
Road
Drainage Structures
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 18/96
Typical dry riverbed crossings “Laghas” that are distributed along the entire
length of the project road
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 19/96
Km 0+000: Nyangaita Trading Centre, the only settlement along the entire
project road
Trading Centers
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 20/96
The Settlement Camp at Lokwamosing
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 21/96
Amaler Police Post
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 22/96
ALIGNMENT SOILS AND POTENTIAL MATERIAL SOURCESPROSPECTING
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 23/96
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 24/96
TOPOGRAPHIC SURVEY ACTIVITIES
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 25/96
CONSULTATIONS WITH THE LOCAL COMMUNITY
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 26/96
PART 3
DOCUMENTS PREPARED AND SUBMITTED FOR THE
PRELIMINARY DESIGN STAGEAs required by the TOR the Consultant prepared the following Documentsand submitted to the Client as part of the Preliminary Design;
1. PRELIMINARY ENGINEERING DESIGN REPORT
2. PRELIMINARY DESIGN BOOK OF DRAWINGS
3. PRELIMINARY PAVEMENT AND MATERIAL REPORT
4. ECONOMIC FEASIBILITY STUDY REPORT
5. DRAFT ENVIRONMENTAL & SOCIAL IMPACT STUDY REPORT
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 27/96
PART 4
INCEPTION REPORTThis was Prepared by the Consultant and covered the following main areas;
1. INTRODUCTION AND BACKGROUND FOR TO CONSULTANCY SERVICES
2. MOBILIZATION AND LIASON WITH THE CLIENT
3. CONSULTANTS SITE VISIT AND OBSERVATIONS
4. TRAFFIC SURVEYS AND ANALYSIS• Including type of surveys to be carried out
• Methodology to be adopted
• Proposed Locations for the Traffic Surveys
5. ENGINEERING SURVEYS
• Including the topographical and Aerial surveys
• Hydrological surveys
• Soils and Material investigations
• Identification of the most appropriate route location
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 28/96
5. ECONOMIC ANALYSIS
6. ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT
– Outlining the Study Approach that would detail both the positive
and negative impacts of the project and how to mitigate them7. CONSULTANT’s REVISED WORK PROGRAM
THE INCEPTION REPORT WAS DISCUSSED AND APPROVED IN OCTOBER
2013
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 29/96
PART 5
PRELIMINARY ENGINEERING DESIGN REPORT
The Report Summarizes the findings from Engineering Investigations, field surveys andthe subsequent analysis and design of the project Road
Rainfall and Climate
• The rainfall within the project area is largely influenced by the altitude and thevegetation cover.
• The rainfall pattern is usually bi-modal with the first rains occurring in the February -April period while the second rainfall season occurs between August and September.
• The average temperature is 20C during the cold season with a maximum of 30Cduring the hot season. January is the hottest month while July is the coldest.
Topography and Geology
• The terrain is rolling to flat.
• The Altitude at the start of the road at Lomut is 1020 metres. From here the terrain
gently rises to it’s the highest point at km 22+500 (1080 metres. Thereafter thealtitude steadily drops at a rate of about 9 metre per kilometre to Lokwamosing at analtitude of 686 metres.
• The rocks of the project road are mostly of the basement type comprising mainly of banded hornblende biotite gneisses. In the plains west of the Kailongol-Masol rangeoutcrops are rare, as there is thick sand and grits cover on the surface of the plains. Tothe East of the project road corridor the rocks are of volcanic types comprising mainlyof pink, buff and white tuffs, olivine basalts and pyroclastic
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 30/96
Land Use
• The vegetation along the project area is predominantly semi-arid shrubs andbushes. The first 40 km is fairly dense thorny acacia vegetation and this givesway to open grassland towards the end of the project.
• The main economic activity over the project road corridor is nomadicpastoralism with rearing of large herds of goats and cattle, and in additioncamels in the northern parts of the corridor.
• Some cultivation is practiced in the area north east of Lomut and to thesouth at the foot of Elgeiyo escapement where the soils are volcanic andfertile. To less extent other economic activities include mining and tourism.
• Recent discovery of oil in the area to the north of the project road will sparkan economic revolution in the area. The improved Project Road willtherefore play a key role in the anticipated growth of the local economy andconnecting market centres such as Sigor, Tot, Lomut and Lokori.
• Between Km 40 and Km 75, the project road crosses the Eastern edge of Turkana National Reserve. Due to the poor state of the project road, tourism
is not very well developed put has a good potential to grow.
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 31/96
2. ENGINEERING STUDIES
2.1 AERIAL AND TOPOGRAPHICAL SURVEYS
The Consultant carried out an Aerial Survey of the project road. The data wasused to design the alignment for the project road. The Aerial Survey also
produced digital images clearly showing the project area features.
LIDAR Data was used in the Preliminary Design
Survey controls were done using GPS traverse at every 2.5km interval.
A Digital Terrain Model (DTM) from Topographic survey of the project road
using both real time GPS and conventional Total Station survey equipmentfor ground data capture is to be used for the final design
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 32/96
GPS CONTROLS AND PRELIMINARY SURVEY
The following equipment and software were used in the Survey activity;
• GPS/GNSS Solutions
• South GPS Processor• Total Station
• Automatic Level
• Hand Held GPS
• Eagle point
• AutoCAD
• Excel
WORK PROCEDURE In establishing the Survey Controls, the Survey team adopted the following
procedure;
• Marking the existing road centerline
• Establishing survey monuments on the ground
• Road marking exercise
• GPS survey
• Traversing
• Leveling
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 33/96
LIST OF NATIONAL CONTROL POINTS(ARC 1960-ZONE 36N) POINT NO.
POINT NAME
NORTHING(m)
EASTING(m)
ELEVATION(m)
1 63ST2 169921.54 785425.84 - 2 63ST3 176584.52 804715.91 1203.046 3 63ST4 195065.28 809592.58 912.266 4 63ST5 207121.05 815096.03 941.832 5 63ST6 214982.55 821238.28 826.922
1. GPS Surveying
A set of three GPS points were established at intervals of 2km-2.5km and were
connected to the National grid by making observations from and to available
trigonometric points. Table below shows the National Primary Control Points
used.
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 34/96
List of GPS Controls Established GPS LIST(WGS84/UTM ZONE 36N)
N0. NAME NORTHING EASTINGS ELEVATION CHAINAGE 1 GPS1 155183.05 786958.73 1013.441 0+000 2 GPS2 155108.99 787108.56 1017.996 0+000 3 GPS3 155129.43 786798.00 1017.910 0+000 4 GPS4 156790.95 787881.27 969.401 2+000 5 GPS5 156726.80 787986.96 969.666 2+000 6 GPS6 156656.98 788067.55 969.273 2+000 7 GPS7 158555.72 788832.18 952.446 4+000 8 GPS8 158482.55 788885.42 953.450 4+000 9 GPS9 158631.34 788787.64 953.506 4+000
10 GPS10 159392.95 790584.96 943.493 5+900 11 GPS11 159412.11 790541.45 942.807 5+900 12 GPS12 159349.83 790630.97 943.756 5+900 13 GPS13 160860.94 791710.06 931.934 7+740 14 GPS14 160847.08 791640.79 931.325 7+680 15 GPS15 160818.36 791762.77 933.165 7+760 16 GPS16 162349.91 793912.06 957.933 10+410 17 GPS17 162247.15 793950.56 957.016 9+380 18 GPS18 162231.12 794032.03 955.891 10+420 19 GPS19 163394.64 795499.11 972.288 12+320 20 GPS20 163263.62 795479.34 971.148 12+220 21 GPS21 163479.75 795457.52 971.404 12+340 22 GPS22 164015.36 797430.39 958.715 14+340 23 GPS23 163866.55 797498.78 957.287 14+360
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 35/96
105 GPS105 215193.46 822180.68 755.013 75+905 106 GPS106 216757.76 823977.80 731.968 78+442 107 GPS107 216669.66 824172.98 728.338 78+467 108 GPS108 216951.66 824052.66 727.194 78+625 109 GPS109 217860.92 825280.53 713.381 80+180 110 GPS110 217869.12 825479.37 711.761 80+280 111 GPS111 218112.30 825397.81 722.473 80+460 112 GPS112 220941.01 826813.95 699.074 83+800 113 GPS113 220713.35 827178.28 689.410 83+700 114 GPS114 221070.90 827277.45 684.121 84+000
A sketch of all the locations of the GPS controls is included
Table is truncated….
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 36/96
Traverse Surveying Due deteriorating security situation in the project region, the Consultant’s Surveyor
Mr. Ken Ndede made a request to the Client’s surveyor Mr Okwaro that the Traverse
survey be replaced with additional GPS control points. The request was granted and
so additional GPS control points were monumented at intervals of 2 to 2.5km. Other factors that contributed to the request to carry out GPS traverse:- Most Traverse points were vandalized even before being observed.
The vegetation cover hindered the inter-visibility between traverse points and
bush clearing was limited along the survey corridor.
The inter-community hostility between the Pokots and Turkana made survey
work a challenge in this project.
However a number of Traverse points were installed in the first 5km of the projectroad but they were later vandalized even before the survey team left the site
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 37/96
CADASTRAL SURVEYS Upon approval of the horizontal alignment by the Client, the Consultant
shall obtain all the cadastral maps and carry out a cadastral survey of allaffected parcels for the purpose of preparing Land acquisition plans. During the Preliminary Survey work and setting of the Survey controls, it
was established that the road section falling under the Pokot community
(Km 0 to 40) has been adjudicated and cadastral plans are available.
From Km 40 to 65 the project road falls under Kenya Wildlife Servicesbecause its within South Turkana National Reserve. The rest of the project
is still under Trust/community land. The Survey Team is currently working on the cadastral plans awaiting the
approval of the alignment after which cadastral strip plans will be prepared
and results tabulated showing all affected land parcels and their
ownership.
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 38/96
2.0 TRAFFIC SURVEYS AND ANALYSIS
Traffic volume was determined by conducting traffic counts. The traffic
surveys were done in September 2012 for seven (7) continuous days. The
counts were undertaken using manual counts method. Data collectedcomprised the following;
• 12hr manual classified counts.
• 24hr manual classified counts.
STATION JUNCTION TYPE SURVEY TYPE REMARK
(1) Marich Pass T – Junction with six (6)
movements. 5 days-12hr classified counts
2 days-24hr classified counts
2 days O/D survey.
2 day axle load survey on A.
Junction on A1.
(1) Lokichar T – Junction with six (6)
movements. 5 days-12hr classified counts
2 days-24hr classified counts
2 days O/D survey.
Junction on A1.
V hi l l ifi i f ll
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 39/96
• Vehicle classification were as follows;
No Vehicle Category Description
1 Motor cycles All mopeds and other motor cycle
2 Cars Include saloon cars, station wagon passenger cars.
3 Pick-ups, Jeeps, 4WDs, Vans All pick-ups, 4 WD cars and private vans
4 Matatus and Minibuses All public service mini-buses with seating capacity less than45
5 Buses All public service buses with seating capacity more than 45
6 Light Goods Vehicles (LGV) All trucks with maximum laden weight of 5 tonnes
7 Medium Goods Vehicles (MGV) All trucks with 2 axles and laden weight more than 5 tonnes
8 Heavy Goods Vehicles All trucks with 3/4 axles and weight greater than 12 tonnes
9 Articulates Trucks 5-6 Axles truck
10 Other Vehicles Tractors, construction equipment, etc
Th A A l D il T ffi (AADT) i t b l t d b l f th t
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 40/96
• The Average Annual Daily Traffic (AADT) is tabulated below for the two
stations
Marich Pass ADT
VEHICLE TYPE To and from Sigor To and from Kitale To and from Lokichar
Cars 7 9 6 Pickups, jeeps, vans 32 59 51 Matatus 29 36 5 Buses and Minibuses 0 4 3 Light Goods Vehicles 14 16 13 Medium Goods Vehicles (2 axles) 1 11 6
Heavy Goods Vehicles (3 & 4 axles) 0 15 14
Heavy Goods Vehicles (5, 6, & 7 axles) 0 10 10 Other 0 0 0 ADT 83 158 109
Di t d T ffi
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 41/96
Diverted Traffic
• Noting that the normal traffic plying the project road is zero, an origin
destination survey was conducted along A1 road at Marich pass and
Lokichar. This was to establish the volume of traffic likely to divert to the
project road after opening.
Lokichar on
A1
(ADT=109)
To Sigor to C46
road (ADT=83)
Kitale on A1
road
(ADT=158)
Targeted
Motorists for
interviewed
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 42/96
DESTINATION
O r i g i n
T o t a l O f V e h i c l e
T y p e
K a i n u k
K a k u m a
K a l o k o l
K a t i t o
L o d w a r
L o k i c h a r
L o k i c h o g i o
M a r i c h p a s s
N a d a p a l
O r w a
S e k e r
S i g o r
T u r k w e l l
Chepareria 1 1 1.1% Eldoret 17 1 1 9 4 1 1 18.7% Kapenguria 9 1 3 1 2 2 9.9% Kibugon 1 1 1.1% Kisumu 1 1 1.1% Kitale 40 2 4 1 27 1 2 1 2 44.0% Mombasa 6 4 2 6.6% Nairobi 13 1 1 2 3 2 3 1 14.3% Nakuru 1 1 1.1% Ortum 1 1 1.1% Sigor 1 1 1.1% TOTAL 91 6 10 1 3 42 4 9 5 1 1 4 2 3 100 Percentage 6.6
11.
0 1.
1 3.3 46.2 4.4 9.9 5.5 1.1 1.1 4.4 2.2 3.3
O-D survey Matrix at Marich Pass on A1 road
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 43/96
Vehicle Type To and from Sigor Percentage
Diverted
Traffic
Cars 7 5.50% 0 Pickups, jeeps, vans 32 5.50% 2 Matatus 29 5.50% 2 Buses and Minibuses 0 5.50% 0 Light Goods Vehicles 14 5.50% 1 Medium Goods Vehicles (2 axles) 1 5.50% 0 Heavy Goods Vehicles (3 & 4 axles) 0 5.50% 0 Heavy Goods Vehicles (5, 6, & 7 axles) 0 5.50% 0 Other 0 5.50% 0 ADT 83 5.50% 5
Table 1.6: Diverted Traffic at Marich Pass
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 44/96
Vehicle Type To and from Lokori To and from Kitale To and from Lodwar Cars 81 139 118 Pickups, jeeps, vans 1 2 0 Matatus 8 6 1 Buses and Minibuses 0 0 0 Light Goods Vehicles 0 5 5 Medium Goods Vehicles (2 axles) 4 9 4 Heavy Goods Vehicles (3 & 4 axles) 11 21 40 Heavy Goods Vehicles (5, 6, & 7 axles) 2 68 72 Other 0 11 10 ADT 106 261 250
Table 1.7: Normal Traffic at Lokichar on A1 road
The directional layout is shown below.Lodwar on A1 (ADT=250)
To Lokori to C46 road (ADT=106)
Kitale on A1 road
(ADT=261)
Targeted Motorists for
interviewed
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 45/96
O r i g i n
T o t a l O f V e h i c l e
E l d o r e t
K i s u m u
K i t a l e
M a k u t a n o
M o m b a s a
N a i r o b i
N a k u r u
O r t u m
S i g o r
T h i k a
T O T A L
P e r c e n t a g e %
Choro 1 1 1 1.8 Kainuk 2 2 2 3.5 Kakuma
3
1
2
3
5.3
Kalokol 1 1 1 1.8 Lodwar 30 4 1 16 1 4 3 1 30 52.6 Lokichar 2 1 1 2 3.5 Lokichogio 5 2 1 2 5 8.8 Lokitaung 1 1 1 1.8
Marich Pass
1
1
1
1.8
Seker 3 3 3 5.3 Turkwel 8 1 3 1 2 1 8 14.0 TOTAL 57 8 1 23 1 2 11 3 5 2 1 57 Percentage 14.0% 1.8% 40.4% 1.8% 3.5% 19.3% 5.3% 8.8% 3.5% 1.8%
Table 1.8: Origin-Destination Matrix for Lokichar
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 46/96
Vehicle Type To and from Lokori %
Diverted
Traffic Cars 7 6.2% 5 Pickups, jeeps, vans 32 6.2% 0 Matatus 29 6.2% 0 Buses and Minibuses 0 6.2% 0 Light Goods Vehicles 14 6.2% 0 Medium Goods Vehicles (2 axles) 1 6.2% 0 Heavy Goods Vehicles (3 & 4 axles) 0 6.2% 1 Heavy Goods Vehicles (5, 6, & 7 axles) 0 6.2% 0 Other 0 6.2% 0 ADT 83 6.2% 7
Table 1.9: Diverted Traffic at Lokori
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 47/96
Generated Traffic
At year of opening of the project road, the generated traffic is not expected to exceed the local
traffic. This derives from the premise that the current local traffic derives sustainability from
the existing economic activities.
Timing of opening of the oil mining at Ngamia cannot be predetermined at the time of
undertaking this study. It is therefore not possible to predetermine the timing of the generated
traffic due to this specific activity. It can however be conservatively assumed to be ten years
after opening of the project road. Therefore, ten years after opening of the project road, it is
assumed that 10% of the local traffic will be generated traffic
This traffic is however loaded at the timing of opening of the project road and projected
through the ten year duration. This follows the general guideline that generated traffic can
never exceed double the rate of growth of GDP in the country which is currently taken as 7%.
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 48/96
Vehicle Type To and from
Lokori To and from
Sigor Average (Local-
Traffic) Generated
Traffic (10%) Cars 81 7 44 5 Pickups, jeeps, vans 1 32 16.5 2 Matatus 8 29 18.5 2 Buses and Minibuses 0 0 0 1 Light Goods Vehicles 0 14 7 1 Medium Goods Vehicles (2 axles) 4 1 2.5 1 Heavy Goods Vehicles (3 & 4 axles) 11 0 5.5 1 Heavy Goods Vehicles (5, 6, & 7 axles) 2 0 1 1 Other 0 0 0 1 ADT 106 83 94.5 15
Table 1.10: Generated Traffic
Table below shows the adopted generated traffic. In the table, unit figures have been given to vehicle categories which
registered zero volumes at the time of undertaking this survey.
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 49/96
Design Traffic (AADT)
At the time of undertaking this survey, the normal traffic plying the project road
was zero. The design traffic has been taken as a sum of the diverted traffic and
the generated traffic. Details of the diverted and generated traffic are discussed
in the preceding sub sections.
Table 1.11 below presents a summary of the design traffic.
Vehicle Type Design Traffic % M/Cycles 10 27.8% Cars 10 27.8% Pickups, jeeps 4 11.1% Matatus /Vans 4 11.1% Buses and Minibuses 1 2.8% Light Goods Vehicles 2 5.6% Medium Goods Vehicles (2 axles) 1 2.8% Heavy Goods Vehicles (3 & 4 axles) 2 5.6% Heavy Goods Vehicles (5, 6, & 7 axles) 1 2.8% Other 1 2.8% ADT 36 100.0%
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 50/96
Traffic Growth Scenarios
traffic growth rates are given for three scenarios; low, medium and
high growth rates. The medium traffic growth scenario has been
adopted for design purposes. The low traffic growth scenario and
the high traffic growth scenario are used for sensitivity analysis
considering a situation where the growth rates are either lower or
higher than estimated. Summary of the adopted traffic growth
rates for (the project road) normal traffic is presented in Table 1.12
below.
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 51/96
ADOPTED TRAFFIC GROWTH RATES Vehicle Type LOW MEDIUM HIGH
CARS 6.5 7.0 8.5 PICK-UPS, JEEPS, VANS 5.0 6.0 7.0 MATATU AND MINIBUSES 3.5 4.0 5.0 BUSES 3.5 4.0 5.0 LGV 3.5 4.0 5.0 MGV 4.0 5.0 6.0 HGV-3 & 4 Axles 5.0 6.0 7.0 HGV-5 & 6 Axles 5.0 6.0 7.0 TRACTORS 1.5 2.0 2.5
Table 1.12: Adopted Traffic Growth Rates for Generated and Diverted Traffic
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 52/96
GEOMETRIC CHARATERISTICS
Cross Section
The recommended cross section as derived in the Traffic Report is given in table 1.13 below.
Road Section Medium Growth Scenario
AADT (pcu) Cross Section
Type Lomut – Lokori (C46) Road 90 V
The design manual recommends cross section Type V comprising of a 4 m
carriageway and 1.5 m wide shoulders on each side. However, the consultant
recommends 7.0 m carriageway and shoulders of 2.0 m on each side (Type III)
to match the design of adjoining roads A1, B4 and C113 as illustrated below.
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 53/96
1. The Government through its implementing agency KeNHA is
currently carrying out a upgrade design of Road B4 from Tot to
Marich-pass to international trunk road standard with 7m
carriageway and 2m shoulders. 2. The A1 Kitale-Lokichar-Lodwar-Nadapal road is also being designed
to international trunk road standard. 3. The C113 road through to Lomut and continuing into C46 from
Lokwamosing to Lokichar is also being upgraded to international
trunk road standards. 4. The recently discovered Ngamia 1 oils field is located some 20 km
from the end of the project between Lokwamosing and Lokichar.
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 54/96
PAVEMENT LOADING TRAFFIC
AXLE LOAD SURVEYS
Axle load survey was done at Marich Pass for six continuous days as shown inTable below. The days comprised five week days and one weekend
No DAY DESCRIPTION 1 Sunday 9th Sept 2012 Axle load survey from 6am-6pm 2 Monday 10th Sept 2012 Axle load survey from 6am-6pm 3 Tuesday 11th Sept 2012 Axle load survey from 6am-6pm 4 Wednesday 12th Sept 2012 Axle load survey from 6am-6pm 5 Thursday 13th Sept 2012 Axle load survey from 6am-6pm 6 Friday 14th Sept 2012 Axle load survey from 6am-6pm
The axle Load data were analysed and used to compute the vehicle
equivalent factors. The results are presented in Table below.
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 55/96
NO. WEIGHED TOTAL E. F. AVERAGE E. F. BUSES 47 109.22 2.32 MGV 34 70.23 2.07 LGV 29 30.75 1.06 HGV 1 4.37 4.37
111
Adopted Vehicle Equivalency Factors
Cumulative Number of Standard Axles (CNSA)• The pavement design period was taken as 20 years after opening of the
project road.
• It was estimated that the project road would be open in the year 2016. The
design year is therefore 2036.• Due to variations in the nature and volume of traffic along the project road,
analysis for the traffic loads was carried out for each of the design sections.
The cumulative number of standard axles in both directions for the whole of
the pavement design period was calculated from the total AADT at the
opening of the road (January 2016).
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 56/96
DESIGN SECTION
20-yr Cum. No. of Std. Axles (x 106)
Low Medium High
Lomut - Lokori (C46) Road CNSA 0.53 0.69 0.91 Traffic Class T5 T5 T5
Summary of Cumulative Number of Standard Axles (CNSA).
The recommended Design Traffic class is T5.
3 0 SOILS MATERIAL INVESTIGATIONS AND PAVEMENT DESIGN
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 57/96
3.0 SOILS MATERIAL INVESTIGATIONS AND PAVEMENT DESIGN
Geology / Soils and Condition of Existing Road
• The rocks of the project road are the basement type of rocks
comprising of banded hornblende and biotite gneisses.• On the project road corridor and extending to the west, outcrops are
rare, as there is thick sand and grits cover on the surface of the plains.To the East of the project road corridor the rocks are of volcanic origincomprising mainly of olivine basalts and pyroclastic. Where drainage isimpended black cotton soils have formed
• The design manual recommends that black cotton soils (or any swelling/ collapsing soils) should be mass excavated to depths of 1.0 meterbelow the existing ground level and backfilled with stable materialcompacted to formation levels to remove all unstable material withinthe zone of seasonal moisture fluctuation and as a result minimize the
swelling / shrinkage / collapse associated with such moisturevariations.
• Tables below gives a summary of the geology and subgrade soils, thesub grade homogenous sections based on the soaked CBR strength andthe improvement required to bring the various sections to a uniformsub grade class S3.
G l / S il d C di i f i i d C
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 58/96
Geology / Soils and Condition of Existing Road – Cont.
Table 3.1.1: Sub Grade Homogeneous Sections (from the main report) From (Km) To (Km) Length (Km) SGC / (TC) Geology
0+000 60+000 60 S1 (T5) Reddish sandy silts / Black Cotton Soils – Black cotton
soils sections to be mass excavated to 1.0 m depth and
backfill with stable material + Improve Sub grade to S3
60+000 62+500 2.5 S2 (T5) Reddish sandy silts / greyish Soils / Black cotton soils
sections to be mass excavated to 1.0 m depth and
backfill with stable material + Improve Sub grade to S3
62+500 88+500 26 S1 (T5) Reddish sandy silts / greyish Soils / Black cotton soils
sections to be mass excavated to 1.0 m depth and
backfill with stable material + Improve Sub grade to S3
I d S b d
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 59/96
Improved Subgrade
Table 3.1.2 – Improved sub grade Section
Sub
gradeClass /
(Traffic
Class)
Backfill after MassExcavate Black Cotton
Soils to 0.5 m depth New Subgrade
Class Additional Improved Sub
grade Design Sub
grade Class Proposed Source of Improved Subgrade
Materials From
(km) To (km) Length
km
0+000
60+000
60.0
S1
Whole length (S2 fill)
S3 325 mm of S4 gravel
(195,000 M3) S3
MS1 (S5), MS2
(S6), MS4 (S5),
MS5 (S5), MS3
(S5) and MS6
60+000 62+500 2.5 S2 Whole length 600 mm
depth (S4 fill) S3 200 mm of S4 gravel
(5,000 M3) S3 From Km 84+000 to
Km 87+000
62+500
88+500
26.0
S1
Whole length (S2 fill)
S3 325 mm of S4 gravel
(84,500 M3) S3 From Km 84+000 to
Km 87+000
Requirements Fill Class S2 = From sections with
subgrade soils CBR greater than or equal
to 7%.
Requirements Improved Sub grade (S4)
Plus Fill Class S4
Investigated. Investigated Sources are all within the first 50 Km. Therefore all to
be used over the section as improved subgrade. 195,000 M3 of
materials required against 56,000 M3 from identified sources
leaves a huge deficit which can be partly met by extension of
MS1, MS2 and MS5 and partly from additional sources to be
identified in the next design stage.
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 60/96
Field Investigations – Gravel, Hard stones, Sand and Water.
• There is scarcity of good gravel sources and the few identified
sources all being at the first 50.0 Km. A total of 6 gravel sourceswere identified within this section of the corridor of the projectroad. Materials from these sources were sampled by digging trialpits to an approximate 30 m grid.
• Six hard stone sources were identified and investigated throughsampling from outcrops and testing to ascertain their suitability for
layer work.• Most of the Laghas crossing the project road have sand deposits.
Samples were collected from five ruggers at Km 1+400, Km 8+200,Km 42+500, Km 59+800 and at Km 87+500.
• The project road runs more or less parallel to River Kerio throughout
with offset distances between 0.2 km and about 14 Km• In addition River Lomut runs near the project road at Km 0+000.
Both these rivers are perennial and will provide reliable construction
water throughout the year.
l l bl
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 61/96
Materials Available For Pavement Construction
• The sub grade soils over most of the alignment (Km 0+000 to Km
88+500 (end)) comprises of mainly of silty sandy or black cotton soils
most of which exhibit collapse characteristics upon wetting andloading and are generally falling in the subgrade class S1.
• Native subgrade will therefore be excavated to a depth of about 1.0
m and replaced with stable fill.
• From the laboratory testing, gravel from all the six investigated
sources fails to satisfy the requirement for sub base in their neatform. They however achieve sub base quality after treatment with
2% cement or 2 - 4% lime.
• Gravel from all the six sources achieves base quality with 4%
cement. GCS and cement improved gravel will be considered for sub
base.• Due to scarcity of gravel, base construction will be GCS throughout.
Hard stone source QS5 at Km 31+000 is suitable for production of
GCS and will limit haulage to within 57 Km.
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 62/96
PAVEMENT DESIGN
General Considerations
Hence from the above available materials and considering the traffic
loading, the scarcity of good gravel within the corridor of the projectroad. Pavements types 7 and type 9 are considered for the project road.
– Type 7 - Cement improved gravel sub base and GCS base. This type of
base is suitable for up to T3 traffic but will require special attention to
drainage and end restraint. To prevent rapid progression of pot holes a
2% cement bidder can be added to the GCS. 50 mm AC surfacingextending to include shoulders adopted.
– Type 9 - GCS sub base and base. This type of base is recommended due
to the scarcity of good gravel. Special attention will be paid to drainage
and end restraint. 50 mm AC surfacing extending to include shoulders
will be adopted in lieu of the surface dressing recommended in the
design manual. – The difference in the two pavements is in sub base construction.
Selection of cement improved or GCS sub base will be based on cost
considerations
P d P S
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 63/96
Proposed Pavement Structures
Two alternatives pavement type 7 and type 9 are recommended. The
cheaper of the two will be adopted for the project road.
Alternative I - Pavement Type 7
– Improved sub grade as in table 3.1.2
– 125 mm thick cement improved (2 %) sub base layer extending
over the shoulders.
– 125 mm thick GCS base layer extending over the shoulders. – 50 mm thick asphalt concrete type I surfacing on carriageway
and shoulders followed by a single seal surface dressing (10/14).
Alternative II - Pavement Type 9
– Improved sub grade as in table 3.1.2
– 125 mm thick GCS sub base layer extending over the shoulders.
– 125 mm thick GCS base layer extending over the shoulders.
– 50 mm thick asphalt concrete type I surfacing on carriageway
and shoulders followed by a single seal surface dressing (10/14).
Cost Comparisons
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 64/96
Cost Comparisons
Table 5.3 – Cost comparisons Alternative I (Type 7) Cement improved Sub Base (carriageway + shoulders)
Material Layer Volume (M3) Rate
(Ksh)/M3 Total (Ksh)
Cement
improved (2%)
sub base
Sub Base (0.125 m * 11 m * 1,000
m) = 1,,375 3,250 4,468,750
Total Alternative I (Ksh/Km) 10,243,750 Alternative II (Type 9) GCS Sub base (carriageway +shoulders)
Material Layer Volume (M3) Rate (Ksh) Total (Ksh)
GCS Sub Base
(carriageway +
Shoulders) (0.125 m * 11 m * 1,000
m) = 1,375 4,200 5,775,000
Total Alternative II (Ksh per Km) 11,550,000
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 65/96
Proposed Pavement Structures Cont
Although alternative I is about 24.6 % cheaper than alternative II.
Alternative II is recommended as it will address the scarcity of naturalgravel. Thus;
– Improved sub grade as in table 3.1.2 in main report.
– Sub base – 125 GCS (carriageway +Shoulders)
– Base – 125 mm GCS (carriageway +Shoulders)
– Surfacing – 50 mm Asphalt Concrete Type I (carriageway +Shoulders)
followed by a Single surface dressing - 10/14 chippings.
2 4 HYDROLOGICAL (DRAINAGE) INVESTIGATIONS
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 66/96
2.4: HYDROLOGICAL (DRAINAGE) INVESTIGATIONS
The project road is in the Kerio River Basin but also has a few ephemeral
streams emanating from surrounding hills and Ranges
The Scope of the hydrological and the Hydraulics design was to evaluatethe drainage characteristic of the road crossings, estimation of the design
peak floods and sizing of the proposed drainage structures.
THE SCOPE COVERED THE FOLLOWING TASKS
Comprehensive Catchment investigation to establish characteristics such as
climatic conditions, geological and land use information and soil drainagecharacteristics along the road alignment such as soil/surface drainability,
drainage impedance and flooding.
Undertake condition assessment of existing drainage structures at crossings
along the existing/proposed road alignments,
Determine hydrological catchment parameters such as surface areas, run-off coefficient, hydraulic slopes and design flood discharge for the
appropriate design frequencies for each crossing
Undertake hydraulic designs and proposes sizes for proper drainage and
crossing systems and structures.
The project road has no existing drainage structures The assessment was
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 67/96
The project road has no existing drainage structures. The assessment wastherefore limited Detailed examination of the road was undertaken during thefieldwork to collect necessary information. The field investigations focused onthe following;
• Observation of the catchment conditions and delineation of streamcatchments
• Identification and location of new drainage structures
Watersheds and catchment boundaries of the waterways across the projectroad were examined from 1: 50,000 SoK topographical maps of the area.
Catchment Boundaries were examined from the following 1:50,000 SoKtopographical maps
• Sheet 51-3 Sheet 51-3
• Sheet 63-1 Sheet 63-2
• Sheet 63-3 Sheet 63-4
• Sheet 76-1 Sheet 76-2
The capacity of existing crossing was determined using managing equations
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 68/96
The capacity of existing crossing was determined using managing equations
for culvert flows. A hydraulic slope of 0.5% and a freeboard of 25% of the
culvert depth was assumed for all the culverts.
Topographical characteristic of some of the crossings are presented below.
A more Elaborate list detailing approximately 90 crossings is provided in the
Hydrology and Engineering Reports
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 69/96
Catchment Length
(Km)Name of
WaterwayArea(km2)
Lengthof water
way(Km)
Elevationat Start(m.asl)
Elevation at
crossing(m.asl)
Slope(m/m)
C1 8+040 33.42 3.72 1000 934 0.018
C2 13+520 0.38 0.27 980 947 0.124C3 14+500 3.60 4.36 1020 949 0.016
C4 15+420 10.39 10.11 1240 968 0.027
C5 16+240 0.33 1.07 1000 982 0.017
C6 16+420 2.72 3.07 1060 986 0.024
C7 18+800 5.03 3.66 1300 1004 0.081
C8 19+910 0.29 0.42 1000 1036 -0.086C9 21+140 0.56 0.51 1260 1036 0.438
C10 21+640 0.51 0.58 1260 1063 0.341
C11 22+060 2.18 3.13 1380 1076 0.097
C12 23+240 1.71 2.48 1380 1032 0.140
C13 25+140 4.12 4.72 1440 973 0.099
C14 25+640 5.52 4.88 1500 969 0.109C15 26+200 0.65 1.66 1020 969 0.031
C16 26+950 5.29 5.43 1620 969 0.120
• Proposed Structures
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 70/96
• The design standards and manuals adopted for the design of all the
proposed medium and major drainage structures here included but not
limited to BS 5400, BS 4449, BS 5950, BS 8666, BS 8110, and old RoadDesign Manual part IV
• There are seven proposed bridges in the project road whose locations are
given in Table 2. These vary from single span to three span RC deck bridges
at Km 8 + 040, Km 38 + 500, Km 39 + 850, Km 40 + 100, Km 41 + 300, Km 50+ 280, and at Km 83 + 050.
Cr. No. Chainage Location Bridge Geometry
x y Size Flow F-Level(m) Orientation
Effective Span Height 1 008+040 30.60 4.00 L to R Assum. Right 2 038+500 21.38 4.20 L to R Assum. Right 3 039+850 13.60 3.00 L to R Assum. Right 4 040+100 41.80 4.20 L to R Assum. Right 5 041+300 14.60 3.00 L to R Assum. Right 6 050+280 36.60 4.20 L to R Assum. Right 7 083+050 30.60 4.00 L to R Assum. Right
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 71/96
There are twenty proposed standard box culverts in the project road of
varying sizes and openings/cells. All these structures are new since there
are no existing structures on the project road.
Cr.
No.Chainage
Location Proposed Box Culvert Geometry
x y Type No. of Cells Size Flow Orientation
1 018+800 CBC 2 4 x 2 L to R Assum. Right
2 021+150 CBC 1 3 x 2 L to R Assum. Right
3 021+640 CBC 1 2 x 2 L to R Assum. Right
4 022+060 CBC 1 4 x 2 L to R Assum. Right
5 023+240 CBC 1 4 x 1.5 L to R Assum. Right
6 025+640 CBC 2 4 x 2 L to R Assum. Right
7 026+200 CBC 1 3 x 2 L to R Assum. Right
8 027+590 CBC 1 3 x 2 L to R Assum. Right
9 046+990 CBC 1 4 x 2 L to R Assum. Right
10 029+720 CBC 1 3 x 2 L to R Assum. Right
11 031+240 CBC 1 4 x 2 L to R Assum. Right
12 037+300 CBC 3 4 x 2 L to R Assum. Right
13 039+300 CBC 1 3 x 2 L to R Assum. Right
14 039+400 CBC 2 4 x 2 L to R Assum. Right
15 046+990 CBC 1 4 x 2 L to R Assum. Right
16 061+750 CBC 1 4 x 1.5 L to R Assum. Right
17 071+340 CBC 1 3 x 2 L to R Assum. Right
18 071+730 CBC 1 4 x 2 L to R Assum. Right
19 078+000 CBC 1 4 x 1.5 L to R Assum. Right
20 079+750 CBC 1 4 x 1.5 L to R Assum. Right
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 72/96
The above structures were recommended in order to provide a 500mm
freeboard between the highest water level and the soffit of the top slab,
• Adopted Standards for Hydraulic Analysis
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 73/96
Adopted Standards for Hydraulic Analysis
TYPE OF
STRUCTURE
SIZE HYDROLOGICAL STANDARDS
Pipe Culvert Minimum 0.9m dia. 1 in 10 year flood, check for overtopping
against 1 in 25 year floodBox Culvert Minimum 2m (width)
x 1m (height
1 in 25 year flood, checked for overtopping
against 1 in 50 year flood. Invert to be a
minimum of 1.5D below the road surface
Bridges Dependent on
catchment,
river/stream channel
geometry
1 in 50 years checked against 1 in 100 years
3. PRELIMINARY ENGINEERING DESIGN
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 74/96
GEOMETRIC DESIGN
The design guidelines as provided in the Road Design Manual Part I was
adopted for the Preliminary Design.
The objectives as set out in the Terms of Reference were considered in
detail.
For Class C road in level and Rolling Terrain, RDM gives guide values for
speed as 90-100kph and 60-90kph respectively.
The design speeds adopted were;
Km 0+000 to 40+000 : 90 Km/h
Km 40+000 to 84+500: 100 Km/h
Speed reduced to 50kph at trading centers with pedestrian crossings.
The following Cross Section was adopted;
7m Carriageway with 2.0 m Shoulders(Cross Section type II)
Normal Crossfall of 2.5% and 4% for Shoulders
Side ditch Type B.1 adopted to allow more capacity and check erosion.
Design Vehicle Type SP (Semi Trailer combination)
Rumble strips bumps and pedestrian crossings with adequate sign
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 75/96
Rumble strips, bumps and pedestrian crossings with adequate sign
proposed to ensure safety and conformity to the lower speeds.
AutoCAD Civil 3D software was used for the geometric design
The Horizontal Alignment Design carried out to achieve the following;
• Straights less than 20Vd ( 1800m)
• Straights between Circular Curves in the same direction > 6Vd
(540m).
• Minimum Stopping site distance = 120m
• Min Radius of Horizontal curve = 450m.
• Maximum Superelevation = 6%
• Rate of Change of Superelevation = 0.5.
The vertical alignment was designed to achieve the following parameters
•Maximum Gradient = 4.5%
• Length of Crest/Sag Curves: Not < 2Vd (180m).
• Sag Radii = 3000m (for 90kph).
• Crest Radii = 4000m (for 90kph).
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 76/96
Climbing Lanes: Not considered at the moment due to low AADT (90 pcu)
in design year 10.
Junction Design
At Km 0+000-Junction with B4 road: Proposed Junction type B.
Km 40+700-Kolosia, junction to Kainuk: Type C.
Km 85+500-Lokwamosing, junction with C113: Type B
Access Junctions as necessary
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 77/96
PART 7 ECONOMIC FEASIBILITY STUDY REPORT
The TOR required that The Consultant to carryout an EconomicEvaluation of the Project Road. The report was prepared and presented
as follows;
1. DEFINITION OF THE PROJECT ROAD
The road is situated in Turkana and West Pokot Counties in North Rift
Kenya. The road starts at the junction of C46 and B4 at Lomut trading center. It
then runs in a Northerly direction to Lokwamosing.
2. SCOPE AND OBJECTIVES OF THE REPORT
The HDM – 4 Economic analysis was based on the Preliminary and
detailed Engineering design and the Engineer’s cost estimates, to establish
the viability of the project.
The analysis period is 20 years.
A sensitivity analysis was done for a 20% Cost over run and a Reduction of
traffic growth rate to the low growth scenario.
3 METHODOLOGY
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 78/96
3. METHODOLOGY The following steps were adopted in the execution of this study:
• Field reconnaissance
• Review of existing data and literature
• Collection of the HDM – 4 Input Parameters. These included:
– Calibration data
– Traffic data
– Road data
– Improvement and Maintenance Standards
4. HDM4 RESULT ANALYSIS The following criteria were adopted in the analysis:
• No benefit to be derived during construction phase and that all benefitswere to be realized upon the full implementation of the road project
• Exogenous and Non quantifiable benefits accruing to the project such as
agriculture, trade, tourism and fishing were not included in the analysis• A sensitivity analysis was done for a 20% Cost over run and a Reduction of
traffic growth to a low growth scenario
• A discount rate of 12% and salvage value of 10% and was adopted
• The Economic analysis period of 20 years
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 79/96
INVESTMENT ALTERNATIVES
Two options are compared in the HDM-4 analysis. These arepresented in Table 1.18 below.
Option Description
Base Case “Base Case” Maintain Existing Road
Option 1 Upgrade Lomut_Lokori (C46) Road with Pavement Type-7 Option 2 Upgrade Lomut_Lokori (C46) Road with Pavement Type-9
• HDM4 OUTPUT
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 80/96
• Net Present Value (NPV)
• The NPV is defined as the difference between the discounted benefits andcosts of a project. In the economic appraisal of road projects, benefits arederived mainly from savings in road user costs and also in road maintenancecosts (where possible). The calculation of NPV is therefore simplified by takingthe difference between the present values of costs for the two alternativesbeing compared.
•
• Internal Rate of Return (IRR)
• The NPV depends on the discount rate used in the calculation of presentvalues. When high discount rates are used, a lower NPV is obtained resultingin negative values. The IRR of a project is defined as the discount rate at whichthe present value of costs equals the present value of benefits, that is, whenNPV is zero
•
• Benefit: Cost Ratio (BC ratio) • The BCR provides a simple measure of the profitability of a project (that is,
amount ofbene fits derived for every dollar invested). It represents thedimensionless index obtained by dividing the calculated benefits of the projectby the discounted capital costs of the investment
HDM 4 R N R
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 81/96
HDM-4 RESULTS FOR NORMAL RUNS
The summary of the economic analysis is presented in the Table below.
Analysis Alternative NPV
(USD millions) EIRR (%) B/C ratio Option-1 Upgrade Lomut-Lokori Road with
Pavement Type -7 -13.288 9.4% -0.229
Option-2 Upgrade Lomut-Lokori Road with
Pavement Type -9 -32.236 6.9% -0.419
HDM-4 RESULTS FOR COST REDUCTION BY 23%
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 82/96
HDM-4 RESULTS FOR COST REDUCTION BY 23%
A sensitivity test has been undertaken by reducing the cost by 23%. This was done to evaluate the
minimum threshold necessary to yield an economic viability. A summary of the cost reduction by
23% is shown in Table 1.20 below.
An economic analysis was done after reducing the costs by 23%. A summary of the economic
indicators generated from the HDM-4 analysis is shown in the following Table.
cost reduction by 23% Section Total Financial Cost (USD) Length (km) Financial Unit cost
(USD/km) Economic Unit cost
(USD/km)
OPTION-1 0+000 - 85+500 63,243,867 85.50 739,694 591,755
OPTION-2 0+000 - 85+500 67,111,000 85.50 784,924 627,939
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 83/96
Analysis Alternative NPV
(USD millions) EIRR (%) B/C ratio Option-1 Upgrade Lomut-Lokori Road
with Pavement Type -7 0.062 12.0% 0.001 Option-2 Upgrade Lomut-Lokori Road with
Pavement Type -9 -2.671 11.4% -0.056
HDM-4 results for cost reduction by 23%.
As shown, reducing the cost of the project by 23% yields an Economic Internal
Rate of Return of 12.0% for Option 1- Pavement type 7, which is the threshold
required for economic justification. The reduction however does not improve theviability of option 2-pavement type 9 beyond the minimum threshold for
economic viability.
7. CONCLUSIONS AND RECOMMENDATIONS
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 84/96
7. CONCLUSIONS AND RECOMMENDATIONS
• On the basis of strategic planning and road network development, it is
recommended that the project road be considered for reconstruction.
•The HDM-4 analysis however gives negative NPV and EIRR lower than12.0% unless the project cost is reduced by 23%.
• The project is viable on the basis of regional economic development alone
and not due to savings in road user costs.
•
• However, the benefits to the Kenyan economy as a whole and the localeconomy will be substantially higher, inasmuch; no exact Figure can be
provided of these additional benefits. These include the non-quantifiable
exogenous benefits accruing to the project such as increased access,
security, service provision and attraction of trading activities
PART 8
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 85/96
PRELIMINARY BOOK OF DRAWINGS
Includes The Following;
• DRAWING INDEX
• PLAN AND PROFILE DRAWINGS
• MAJOR JUNCTIONS DRAWINGS
•CROSS SECTION AND PAVEMENT DRAWINGS
• STANDARD DRAWINGS
• ROAD SIGNS DRAWINGS
• STANDARD DRAINAGE DETAIL DRAWINGS
• STRUCTURES DRAWINGS
• RE’S OFFICE AND HOUSING DRAWINGS
• MISCELLANEOUS DRAWINGS
PART 9
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 86/96
ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT
• Road construction and improvement poses both positive and negative impacts tothe physical, biological, social as well as economic setting of the affected areas.
• While the project should enhance the positive aspects, measures should be
integrated in the project to minimize or eliminate adverse impacts. It is worth
understanding that, building a more environmentally stable future clearly
requires some vision and as a basic component of any strategy it should be
sustainable and sound.
• The measures to be put in place should be developed such as to cover the
construction and post commissioning phases. This environmental and social
impact assessment study was commissioned to assess the baseline
environmental and social setting, establish any anticipated impacts from the
project and develop appropriate preventive action plans.• The ESIA study process was undertaken in accordance with the Environmental
impacts regulations (2003) under the EMCA 1999. In addition experiences from
other road projects in country have also been applied as references.
KEY OBSERVATIONS
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 87/96
KEY OBSERVATIONS Lomut – Lokwamosing road (C46) is basically an earth road which at present
is in poor condition and is likely to be impassible during the rainy seasons. At
the time of this study grading and clearance works on the West Pokot side up
to Amaler police post had been done. The road in this section is clear and the
carriage way is elaborate. The section from Amaler police post through
Lochakula, Turkana South National reserve to Lokwamosing is a bush area
with some sections not clearly defined making navigation in the area very
difficult. The road corridor is generally gentle to undulating with breaks of
shallow valleys and many lagers which becomes flooded during the rainy
seasons or when the upper side of Cherangani Hills experiences rains. The
road alignment also has sharp bends in a number of locations. It was also
observed that traffic volume (and especially public transport) is none-exist in
the whole section of the road due to its poor condition, insecurity issues and
very low population.
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 88/96
• Environmental characteristics for Pokot Central and Turkana South
districts are greatly influenced by the arid conditions of Kerio Valley
and the cool wet nature of the southern Cherangani Hills and the
western Kailongoi mountains. The project corridor lies within the lowlying Kerio valley and the Kailongoi highlands on the western side of
the road. Kerio valley presents dry conditions, un-cohesive top soils
and with a general drainage linked to Kerio River. As a result
population is low; the area depicts poor productivity, and experience
very high temperatures and low rainfall. Crop agriculture in the Pokotarea and livestock production are the significant economic activities
while very few institutions are present along the road corridor. Lomut
– Lokwamosing road (C46) runs through the Turkana South National
Reserve which is inhibited by such wild animals as elephants, lions,
leopards, dikdik, squirrels and other herbivores and carnivores. Theplant species in the area is mainly of indigenous tree with very
isolated exotic species indicating minimal interference with the flora
and fauna.
Other Observations Include;
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 89/96
(i) The general land use is characterized by low percentage of human
settlements, crop and livestock production activities. Most of the land has
been left fallow with isolated areas cleared for animal enclosure and thesettlement villages.
(ii) The population along the project corridor is very low but more concentrated
near settlement areas due to insecurity concerns.
(iii) Nomadic Livestock keeping seems to be the main backbone of economic
wellbeing of the area. The land is owned at communal level hence productionper area is low. There is huge potential for goats and sheep husbandry and
also crop agriculture such as Wei Wei area in Sigor. (iv) Cattle rustling between the Pokot and the Turkana posses the biggest
challenge to the security in the area. The vice has led to militarization of the
communities living in the area which has increased the number of illegalarms substantially. The cattle theft has led to almost irreparable relation
between the Pokots and Turkana.
(v) Road linkages seem to present the biggest challenge to social development
in the area and the region in general; among them being access to markets,
amenities and other service locations,
ANTICIPATED IMPACTS No. FOCAL AREAS LINKAGES/ENVIRONMENTAL CONCERNS
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 90/96
1. Natural Resources
(wildlife, forests,
vegetation/plant species,
water sources, land, air,
wetlands, etc.)
Land degradation through soil loosening and loss through erosion, Siltation of sources of water e.g. stream, rivers, etc., Water quality degradation from road construction and use of related pollutants (oil, grease, paint
and asphalt), Permanent destruction of vegetation cover along the road routes, diversions, contractors camp
sites and materials sites,
Disruption of wildlife and general biodiversity,
Emissions into the air of dust (during earth moving and machinery movement) and
smoke/hydrocarbons from equipment, Degradation of wetlands and other hydrological regimes along the route,
Interference with the wildlife habitats and migratory corridors, 2. Physical Environment
(topography, land forms,
geology, hydrology,
climate, etc.)
Changes in micro-topographic patterns along the route, Interference with the hydrological trends and hence surface runoff, Effects on the drainage systems and hydrological regimes,
Open quarries, materials borrow site, effectively changes land forms, Effects on sub-surface geological formations in some areas as a result of earth moving and rock
breaking activities, Interference with sensitive features such as old trees, historical buildings, public amenities,
cultural features, etc. 3. Social and economic
environment (Populations
trends, settlement, land
use, infrastructure,
economic activities, etc.)
Population and settlement trends upon commissioning of the road, Migration of outsiders for construction, Increased moral decay during construction, Changes in land use and urban growth trends, Changes in major economic activities e.g. agricultural and settlements. Benefits of the road to the communities, Accessibility and efficiency in transport of people and their goods, Changes in socio-cultural practices and lifestyles due to external influence, Additional issues anticipated from social interactions.
4 Health, Safety and Security
aspects (construction
safety measures, role of
road in security, road
safety and security upon
commissioning, etc.)
Safety of the construction equipment to the workers, general public and the wildlife, Interaction with the construction workers may lead to high HIV/AIDS cases, Noise to the residents and wildlife living immediately along the road, Signage to road users during construction, especially at night, Increased traffic flow upon commissioning implying higher risks of road accidents to the people
and wildlife, Easy access by medical suppliers and security agents, Sanitation from construction sites,
Handling of health risk sites and materials, Increased insecurity especially cattle rustling
RECOMMENDATIONS
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 91/96
RECOMMENDATIONS The following recommendations have been found appropriate; (i) The road should be upgraded to bitumen standard to a level usable by
heavy load traffic; this is in line with agricultural activity within the Pokot
area requiring heavy trucks to carry mangoes produced in the region. The
road will also form the main transit route from the southern district to the
northern region through Turkana East district, (ii) All sensitive environments and habitats will be minimally disturbed. These
particularly include South Turkana National reserve and the Lochakula
area which forms the springs where the communities use to water their
animals, (iii) Ensure adequate provision of speed calming measures near institutions,
major settlement areas and wildlife migration routes along the projectroad,
(i) Th t k t l th d t h ld b id d ith
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 92/96
(i) The two markets along the road route should be provided with
appropriate service roads while safe bus stops are integrated at
strategic locations,
(ii) Provide appropriate junctions and entrances to institutions and major locations,
(iii) Provide safety barriers at locations too close to the escarpment edges, (iv)Appropriate re-vegetation and grassing would be necessary along the
road reserve upon completion of the road construction, (v) Install and maintain adequate road safety furniture and signage. These
should also be accompanied by social engineering for the local
communities including sensitization and education on wise and safe use
of road,
(vi)The Local Authorities should embark on appropriate physical planning of
the towns and markets along the road corridor to facilitate focusedgrowth of the markets in terms of service provisions, land use, etc.,
RESETTLEMENT ACTION PLAN
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 93/96
OVERVIEW
The ESIA, through utilization of the survey exercise will establish
whether there will be need for Resettlement Action Plan. From theinitial inspection of the existing alignment, the section of the project
road lying within the Pokot community (Km 0 to 40) has been
adjudicated, the section between Km 40 and km 65 lies within Turkana
East National Reserve. The remaining section between Km 65 to 90 is
mostly under Turkana community Trust land. Government valuers willneed to be requested to give an indication of the value of land/property
to be acquired for the proposed development.
SCO O C O R S AC O P
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 94/96
SCOPE AND OBJECTIVE OF THE RESETTLEMENT ACTION PLAN The main objective of the resettlement plan is among others to:-
(i) Identify the affected persons in order to determine those likely to be
adversely affected by the project works, the severity and extent of theimpacts. An assessment of the impacts on their assets, infrastructure,
livelihoods within the road reserve of the road sections will be made
including their income and assets survey.
(ii) Identify the poor and vulnerable groups so as to develop strategy to
ensure that they proactively benefit from the project.(iii) Ensure that there are adequate consultations and participation
by all the stakeholders (iv) Review of the legal and other institutional framework (v) Develop mitigation measures in consultation with the affected
people.(vi) Prepare detailed entitlement matrix and an implementation
plan (vii) Prepare a resettlement budget (viii) Put in place a Monitoring and Evaluation and reporting system
for the Resettlement Plan.
GENERAL OBSERVATION
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 95/96
The project road lies in an arid and very sparsely populated area with mainly
Livestock keeping as the main economic activity. The Consultant will quantify
the number of Project Affected People (PAPs) and may carry out an abridged
Resettlement Action Plan if the number is determined to be low.
7/27/2019 01_Preliminary Design Presentation July 18 2013
http://slidepdf.com/reader/full/01preliminary-design-presentation-july-18-2013 96/96
END OF PRESENTATION
THANKYOU
Kenya National Highways Authority