Contract UpdatesNYP GC –CM Conference
November 4, 2015Ralph Bohnenberger, Facilities Finance Manager, Business Administration
2
We Pu
t Patients F
irst
Introduction Key Contract Highlights Subcontractors Choices Contractor Badges & Orientation Document Handover General Instructions Recurring Issues Violations Liens Q & A
OverviewOverview
3
We Pu
t Patients F
irst
Key ContractHighlights
4
We Pu
t Patients F
irst
Key ContractHighlights
• Contracts and General Instructions are being updated
• General Instructions updated by the end of 2015
• Contract Updates for Document Handover distributed by 12/1/15
• How are they applicable to work at NYP?
• Key Personnel• Lien Removal• Violations / Contract Reductions
• Contracts and General Instructions are being updated
• General Instructions updated by the end of 2015
• Contract Updates for Document Handover distributed by 12/1/15
• How are they applicable to work at NYP?
• Key Personnel• Lien Removal• Violations / Contract Reductions
Lien
5
We Pu
t Patients F
irst
Key ContractHighlights
• Sub Contractor Selection• Approved Vendor List• New Sub Contractors
• Contractor Badges• New Contractor Badges• Contractor Orientation
• Sub Contractor Selection• Approved Vendor List• New Sub Contractors
• Contractor Badges• New Contractor Badges• Contractor Orientation
6
We Pu
t Patients F
irst
Sub‐Contractors • MEP, Fire Alarm, Elevator, DDC, etc. all are
controlled vendors
• We are open to additional vendors, but it takes time
to approve
• DO NOT base bids on new vendors without PM
approval AND minimum 4‐6 weeks to get sub‐
contractor approval
• The Facilities Finance Manager is the
gatekeeper to the addition process
• If you are unsure about a sub, ask
• MEP, Fire Alarm, Elevator, DDC, etc. all are
controlled vendors
• We are open to additional vendors, but it takes time
to approve
• DO NOT base bids on new vendors without PM
approval AND minimum 4‐6 weeks to get sub‐
contractor approval
• The Facilities Finance Manager is the
gatekeeper to the addition process
• If you are unsure about a sub, ask
7
We Pu
t Patients F
irst
DocumentHandover
Problem NYP is not able to consistently update its master drawings and databases to reflect project changes.
Root Cause• Handover content … not clearly defined• Handover responsibilities …not clearly defined
• Handover process … not clearly defined
Consequences• Information gets stored in multiple locations
Lots of unnecessary work for Project Team Information is difficult to retrieve for Operating Teams
• Information is lost after project NYP has to pay to re-create information (re-survey, re-permit)
8
We Pu
t Patients F
irst
DocumentHandover
We have defined the:content responsibilities process
of the handover packages.
We have streamlined process, and are using our project management system to transmit handover packages.
Architects / Engineers,Contractors,
Commissioning Agents,Expeditors
Submit handover package electronically in PM Software
Project Manager
Reviews handover package
Operations Teams(Asset Mgt / Compliance / Space / EHS / Interiors
etc.) Review and accept handover package
9
We Pu
t Patients F
irst
DocumentHandoverAfter completion of abatement:1. Hazmat Package
After Substantial Completion and before Move‐In:
2. Design Team’s FF&E Package
3. Design Team’s Record Drawings
4. CxA’s MEP Pre‐Move‐In Package (incl. Test Reports)
5. Contractor’s Fire Alarm Package (incl. Test Reports)
6. NYP Project Manager’s Pre‐Occupancy Survey Package
Before Final Payment:7. Expeditor’s Permit Package
8. Contractor’s Record Document Package
9. Contractor’s Attic Stock Package
10. Design Team’s Completed Punch List
11. CxA’s Commissioning Package
10
We Pu
t Patients F
irst
An important part of data handover is tagging and barcoding of new equipment.
1) Contractors are obligated to tag the equipment with the Design ID as shown on the drawing schedules (Engineers must use the NYP equipment abbreviations).
2) CxA and specialty subcontractors for Fire Alarm, Fire Suppression and Med Gas must barcode the equipment and produce a list inventory of the equipment and the associated test reports.
The Commissioning Agent will consolidate the list’s and the test reports into handover package #4: “CxA’s MEP Pre‐Move‐In Package”
NYP Barcodes
EquipmentTags
11
We Pu
t Patients F
irst
Process Overview: Barcoding, Testing and Handover
1. Planning of barcoding• CxA coordinates with Asset Mgt Team (Henry Cordova) to
distribute barcodes.• CxA adds the coordination of barcoding and data
collection to the project agenda, and informs all parties (Fire Alarm, Fire Suppression, Med Gas)
2. Before performing testing• The firm that is performing or witnessing the test must
apply the barcode before testing. The barcode must be included in test record.
3. All firms must prepare an Equipment Log• The log must list each piece of equipment and reference
the test report and O&M Manual.• Firms must send their excel Equipment log with the test
reports and O&M Manual, to Commissioning Agent.
4. The CxA will collect all asset information• CxA consolidates information and submits to the NYP
Project Team as the “Pre‐Move‐In MEP Handover Package.”
12
We Pu
t Patients F
irst
Document Handover Content
The NYP Project Data Handover Guide defines foreach package:
‐ Party responsible to generate package
‐ Expected content‐ Expected data format‐ Recipient on NYP side
13
We Pu
t Patients F
irst
Accessing the Handover Guide + Folder Structure
14
We Pu
t Patients F
irst
Folder Structure for Contractor’s Handover Packages
1. Save Handover documents in the folder structure and format as outlined in the Project Data Handover Guide.
2. Once done, move all folders and files into one single ZIP file.
3. Upload the ZIP file to NYP’s Project Management System.
15
We Pu
t Patients F
irst
Uploading Handover Packages
Contact the NYP System Administrator to participate in a training and to obtain a user account. Email: [email protected]
16
We Pu
t Patients F
irst
General InstructionsTo Contractors
• What are the General Instructions?
• How are they applicable to work at NYP?
• More than work and safety rules
• What are the General Instructions?
• How are they applicable to work at NYP?
• More than work and safety rules
17
We Pu
t Patients F
irst
Emergency Call List• Contractor Contacts
• Must have primary and backup contacts
• At least 1 number must be answered 24/7
• PM must be notified of changes immediately
• These numbers are posted at the job site and circulated to On Call Administrators
• Contractor Contacts• Must have primary and backup contacts
• At least 1 number must be answered 24/7
• PM must be notified of changes immediately
• These numbers are posted at the job site and circulated to On Call Administrators
18
We Pu
t Patients F
irst
ConstructionSignage
• All entrances to site
• As detailed in
Construction Sign
Procedure on the
website
• Must have multiple
contact numbers for
NYP & Contractor
Required Signs• Permits• Caution• RACE/PASS• Dust Control
Plan• Contractor
Sign In• Customer
Service Sign
19
We Pu
t Patients F
irst
Work Rules • Superintendent on site
• No smoking
• Where can you smoke?
• Badges
• Workers represent NYP
• Entrance and Exit to sites
• Follow the Dust Control plan
• Noise Control
• No radios
• Be respectful in elevators and outside
• No gifts
• Superintendent on site
• No smoking
• Where can you smoke?
• Badges
• Workers represent NYP
• Entrance and Exit to sites
• Follow the Dust Control plan
• Noise Control
• No radios
• Be respectful in elevators and outside
• No gifts
20
We Pu
t Patients F
irst
Facilities WebSite
http://e-net.nyp.org/facilities
21
We Pu
t Patients F
irst
Recurring IssuesPatient Safety:1. Unauthorized shut down of fire detection & suppression systems2. False alarm activations3. Fire Extinguishers4. Incomplete fire stopping 5. Doors: Leaving those open that should be closed & locking those
that should locked6. Blocking exits & / or stairs7. Unauthorized tapping into utilities
Housekeeping:1. Housekeeping in Mechanical & electrical closets2. Housekeeping in Tunnels
1. Materials left behind; surplus & packing crates2. Equipment stored in tunnels
3. Tracking of dirty boots through space
Behavioral:1. Smoking in or on hospital premises (including sidewalks)2. Language/conversations on elevators & in front of patients & staff3. Lack of ID’s
Patient Safety:1. Unauthorized shut down of fire detection & suppression systems2. False alarm activations3. Fire Extinguishers4. Incomplete fire stopping 5. Doors: Leaving those open that should be closed & locking those
that should locked6. Blocking exits & / or stairs7. Unauthorized tapping into utilities
Housekeeping:1. Housekeeping in Mechanical & electrical closets2. Housekeeping in Tunnels
1. Materials left behind; surplus & packing crates2. Equipment stored in tunnels
3. Tracking of dirty boots through space
Behavioral:1. Smoking in or on hospital premises (including sidewalks)2. Language/conversations on elevators & in front of patients & staff3. Lack of ID’s
22
We Pu
t Patients F
irst
Violations • NYP ‐ intensive and extensive regulatory environment
• Code Compliance / Site Safety are CRITICAL
• NYP paid over $20,000 in fines to FDNY for false
alarms in 2013 related to construction
• Failure to comply with NYP Safety Rules (ICRA, ILSM,
Safety, etc.)
• Currently carries a contract reduction (LD’s) per
General Instructions of $1,000 per incident
• In 2015 we are updating the “Contract Reduction”
schedule for violations. Published by 12/31/15
• NYP expends substantial resources to monitor it’s
environment of care, quality, and compliance
• NYP ‐ intensive and extensive regulatory environment
• Code Compliance / Site Safety are CRITICAL
• NYP paid over $20,000 in fines to FDNY for false
alarms in 2013 related to construction
• Failure to comply with NYP Safety Rules (ICRA, ILSM,
Safety, etc.)
• Currently carries a contract reduction (LD’s) per
General Instructions of $1,000 per incident
• In 2015 we are updating the “Contract Reduction”
schedule for violations. Published by 12/31/15
• NYP expends substantial resources to monitor it’s
environment of care, quality, and compliance
23
We Pu
t Patients F
irst
Violations (cont’d)• Repeat violations will carry increasing contract
reductions
• Violations will carry different contract reduction
amounts based on the seriousness of the violation
• For documented false alarms caused by contractors, we
will begin to pass these fines through to the contract,
effective April 1, 2014. This is already in the contract.
• We do not mean to be punitive, but things have to change
and we want you to be PARTNERS in making things better!
• Repeat violations will carry increasing contract
reductions
• Violations will carry different contract reduction
amounts based on the seriousness of the violation
• For documented false alarms caused by contractors, we
will begin to pass these fines through to the contract,
effective April 1, 2014. This is already in the contract.
• We do not mean to be punitive, but things have to change
and we want you to be PARTNERS in making things better!
24
We Pu
t Patients F
irst
Liens • NYP has a very low tolerance for Liens
• Liens do not solve problems
• As the GC or CM, the lien MUST be removed within 10 days (A201, 14.2.5)
• Bond – OK; Payment – OK
• Must have copy of Filed Lien Satisfaction
• NYP has a very low tolerance for Liens
• Liens do not solve problems
• As the GC or CM, the lien MUST be removed within 10 days (A201, 14.2.5)
• Bond – OK; Payment – OK
• Must have copy of Filed Lien Satisfaction
Lien
25
We Pu
t Patients F
irst
Change Orders• NYP has a need to keep construction moving forward
• We also need to keep cost control at the forefront
• ACE’s (Anticipated Change Estimates) allow construction to move forward while controlling cost
• Need to resolve to a change order sooner
• NYP has a need to keep construction moving forward
• We also need to keep cost control at the forefront
• ACE’s (Anticipated Change Estimates) allow construction to move forward while controlling cost
• Need to resolve to a change order sooner
26
We Pu
t Patients F
irst
Questions