Date post: | 04-Jun-2018 |
Category: |
Documents |
Upload: | keith-choo-chian-hao |
View: | 217 times |
Download: | 0 times |
of 28
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
1/28
Evaluation of Spot and Sweep
Blasting as a Cost Effective Method
of Underwater and Outer HullSurface Preparation
Stephen Cogswell, BAE Systems Southeast ShipyardsPMT:Gordon Kuljian, Pete Ault, John Odwanzy
Non-Export Controlled Information Releasableto Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
2/28
Spot and Sweep, in progress
Non-Export Controlled Information Releasableto Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
3/28
Concept
Reduce Total Ownership Cost of cleaning andpainting underwater hulls on US Navy ships byleaving intact anti-corrosive on the hull during
repainting This paper is a result of the work being
accomplished by the NSRP SurfacePreparation and Coating Panel project team:Steve Cogswell, Pete Ault, Gordon Kuljian &John Odwazny
Non-Export Controlled Information Releasableto Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
4/28
Spot & Sweep to well adhered Epoxy
& , spot & sweep/fullremoval, edge check in progress
Spot & Sweep, DFT in tact epoxy7 to 15 mils
Non-Export Controlled Information Releasableto Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
5/28
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
6/28
Project Goals
Demonstrate commercial technology on US
Navy ships
Document performance issues
Identify process refinements
Determine life cycle cost impact
Develop NSI 009-32 language
Process requirements
Objective Quality Evidence (OQE)
Non-Export Controlled Information Releasableto Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
7/28
USS KLAKRING (FFG 42)
Demonstration in February, 2011
BAE Systems Southeast Shipyards, Jacksonville FL
Existing coating applied in November, 2002
Performed on freeboard and underwater hull
Data collected
Production rates
Adhesion of coating before and after cleaning
Extent of coating removed
Non-Export Controlled Information Releasableto Non-US Persons: DSEA-S2-2010-0118
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
8/28
USS KLAKRING (FFG-42) Spot & Sweep
The surfaceSpot and sweep to existing welladhered epoxy coating
Non-Export Controlled Information Releasableto Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
9/28
Chariot Robotics
Articulating robotic head makinga turn. Vertical, cutting path
Non-Export Controlled Information Releasableto Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
10/28
Flow Hydro Cat
& , Chariot(left), Flow (right) Hydro Cat tracking vertically
Non-Export Controlled Information Releasable toNon-US Persons: DSEA-S2-2010-0118
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
11/28
Adhesion Values, Spot & Sweep
1stand 2ndAC, cut through 2030 psi
Non-Export Controlled Information Releasableto Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
12/28
Hull Plating from the Side Shell
Retained for Laboratory Testing
Non-Export Controlled Information Releasableto Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
13/28
APL-65 Berthing Barge Dry-docking
Graving Dock, NAVSTA San Diego July 2011
Non-Export Controlled Information Releasableto Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
14/28
APL-65 Initial Condition
Calcareous Biofouling on flat-bottom
Heavy corrosion on Stern U/WPort side looking aft
Close-up of Stern Corrosion
Non-ExportControlledInformationReleasable
toNon-USPersons:S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
15/28
Spot and Sweep Demonstration (APL-65)
General result of high speed spot/sweep. Due to the wide-spread coating defects, much of the
underwater hull coating was removed to bare steel. This platform would not meet our criteria
of a good candidate for spot and sweep removal, however meaningful data was gathered.
Criteria appears to be in the 5% range of general defects, vs. 40% found on this hull.Non-ExportControlledInformationReleasable
toNon-USPersons:S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
16/28
APL-65 Initial Condition
After pressure washing, minor W/L grass remaining, heavy base plate
calcareous shell remaining on flat underbelly, widespread corrosion alongwelds and at stern.
Flat Bottom avg. DFT 21.4 mils
Starboard Mid-ship avg. DFT 18.2 mils
Centerline flat bottom fwd avg. DFT 38.4 mils
Initial Coating applied approximately yr 2000
Standard MIL-PRF-24647 system applied
Overall coating showed approximately 40% coating defects in the form of
blistering and isolated corrosion. Defects were predominantly wide-spread.
Job involved a complete WJ-2 water-jetting of the underwater hull and
freeboard - 19,000 ft2removed by Chariot Robotics Envirobot. Remainder of
hull coatings removed by men-on-guns (open cycle UHPWJ).
Spot and Sweep demonstration performed along bow underwater hull prior
to complete re-blast to SSPC SP-12, WJ-2
Non-Export Controlled Information Releasableto Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
17/28
Spot and Sweep Demonstration
Data (APL-65)
Trial runs were optimized at 30,000 psi with spray bar in highest position
from substrate. (9 GPM Pump)
Resulting surface - 25% bare steel, approx 75% red primer and grey mid-
coat (both MIL-PRF-24647 epoxy)
Run 1 stripping rate 3260 ft2
/hour Run 2 stripping rate - 1830 ft2/hour
Adhesion of initial epoxy (after A/F carefully sanded away and solvent
wiped: 1316 psi (3 dolly avg. ASTM D4541)
Adhesion of epoxy remaining after spot and sweep:
1615 psi (3 dolly avg. ASTM D4541)
Non-Export Controlled Information Releasableto Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
18/28
USS RODNEY M DAVIS (FFG-60) SPOT-AND SWEEP
DEMONSTRATION VIGOR SEATTLE FEBRUARY 2012INITIAL CONDITIONS - (after 5000 psi
pressure wash)
Hull coating in great shape. Less
than 0.5% overall coating defects.
Defects were generally isolated to
discharges, welds, rudder and
stabilizers. U/W hull last painted in
2003 (according to Port Engineer)
Coating average DFT - 30-35 mils
(Consists of primarily 17-20 mils A/C,
and remainder is A/F, as verified by
destructive Tooke Gage readings)
Initial A/C adhesion - 1414 psi
Practice Section Under Stbd, fwd
anchor , fwd of forward sonar
Demo section - FWD of FR 100 STBD,
aft of forward sonar Non-Export Controlled Information Releasableto Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
19/28
RODNEY DAVIS (FFG-60) DEMONSTRATION
INITIAL JEWEL CHECK DEPLOYMENT OF ROBOT TO HULL
START OF PRACTICE SECTION:
EXISTING MIL-PRF-24647 SYSTEM
RED EPOXY PRIMER
GREY EPOXY MID-COAT
(WHITE IS SUBSEQUENT TOUCH UP
EPOXY OF ANCHOR CHAIN DAMAGE)
SSPC-SP-10
Non-Export Controlled Information Releasableto Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
20/28
RODNEY DAVIS (FFG-60) DEMONSTRATION
HIGH PRESSURE SWEEP LEFT LESS A/C
PREDOMINANTLY RED PRIMER
LOWER PRESSURE SWEEP LEFT CONSIDERABLY MORE
A/C WITH MINIMAL REMOVAL DOWN TO RED PRIMER
AFTER OPTIMIZING
REMOVAL TO GREY A/C,ROBOT PERFORMED
SPOT-AND-SWEEP AT
2100 FT2/HOUR
DFT OF REMAINING
GREY - 16.5 MILS
DFT OF REMAINING RED
8.5 MILS
RESULTING SURFACE IS
INTACT A/C WITH
COMPLETE A/F REMOVAL.
POORLY ADHEREDCOATING HAS BEEN
REMOVED TO BARE
METAL.
FORWARD PRACTICE SECTION
Non-Export Controlled Information Releasableto Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
21/28
RODNEY DAVIS (FFG-60 DEMONSTRATION)
DEMONSTRATION SECTION
BEFORE SPOT-AND-SWEEP
DEMO SECTION DURING
SPOT AND SWEEP
TENSILE ADHESION AFTER SWEEP
GREY A/C 2170 PSI (AVG OF 3)
RED A/C - 2189 PSI (AVG OF 3)
REMAINING GREY DFT - 18.8 MILS
REMAINING RED A/C 8.9 MILS
OBSERVED PRODUCTION - 695 FT2/HOUR
Non-Export Controlled Information Releasableto Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
22/28
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
23/28
NSRP Spot and Sweep Blasting Project
Remember - We are trying to reduce this:
Non-
ExportControlledInforma
tionReleasable
toNon-USPersons:S2DSE
A2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
24/28
DRAFT- PROCESS FOR SPOT AND SWEEP BLAST DEMONSTRATION
1. The spot and sweep process preformed by the Chariot Robotics unit (or equivalent) may beused for all areas of the underwater-hull and freeboard on approved surface ships. For areas not
prepared using the Chariot Robotics or equivalent; Ultra High Pressure (UHP) lances, abrasiveblasting, may be used to create either an SSPC SP-12 WJ-2/M surface or an SSPC SP-10 surface.SSPC SP-3 Power tool cleaning may be authorized for fairing in the spot and sweep surface as
required.
2. The contractor shall inspect the existing coating on the hull and shall determine the sequenceof the epoxy coatings currently on the hull prior to blasting. The anticipated sequence is red
primer followed by gray epoxy tie coat. The contractor shall note these colors for use in
NAVSEA inspection of the hull prior to application of the first coat of epoxy primer.
3. The Chariot Robotics unit (or equivalent) shall be set up to accomplish the following:(a) Remove all rust and fouling from areas of bare metal to create a SSPC SP-12, WJ-2/M
surface condition in accordance with specified NAVSEA Standard Item 009-32, FY 12 Change 1processes.(b) Remove all antifouling coating and remove approximately 1/2 of the thickness of the current
epoxy tie coat thickness from the underwater hull area.(c) Remove all silicone alkyd, regardless of coating thickness, and remove approximately 1/2 of
the thickness of the current epoxy topcoat from the freeboard area.(d) Smoothly feather or transition from areas of bare metal to the retained epoxy primer/tie coat.
Areas of sharp or "step" transition between bare metal and paint shall be noted by the NAVSEArepresentative for detailed inspection. *under review: Feather edges where the Chariot Robotics
unit (or equivalent) leave behind markings in the existing paint (concentric circle areas whichsome describe as crop circles).Non-
ExportControlledInforma
tionReleasable
toNon-USPersons:S2DSE
A2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
25/28
4. Upon completion of standard zones or work areas, in accordance with current, standard
contractual requirements, the contractor shall inform the NAVSEA representative when they areready to apply the first coat of primer to the zone or work area. NAVSEA representative shall
conduct all standard data reviews and inspections on bare metal areas in accordance withspecified Standard Item 009-32 requirements. Areas of retained paint shall be visually inspectedand shall satisfy the following:
(a) There shall be no more than two colors of paint visible in any area of retained coating.Inspectors shall observe the red primer adjacent to any bare metal areas and then continue
observations into the bulk of the retained epoxy. Gray epoxy may be retained on top of thered primer, but any visual evidence of additional coats of red or black paint on top of the grayshall be cause for closer inspection. Closer inspection shall be conducted from a minimum
distance of 3 feet. Upon closer inspection, a solvent-wipe test with a white rag shall beconducted using the antifouling coating clean-up solvent. If the solvent wipe test shows
color transfer onto the rag, the area shall be rejected. Rejected areas shall be cleaned againuntil no color transfers to the rag.
(b) There are no areas of sharp transition or steps between bare metal and paint. Any such areas
shall be inspected and tested with a dull putty knife to determine adhesion. If the paint flakesor can be dislodged, the area shall be rejected and cleaned again to remove the loose paint.
(c) *Under review Effort will be needed to smooth out the transition areas where partial blastedareas occur next to bare steel blasted areas. Sharp edges shall be removed in accordance withSSPC SP-3 and the areas feathered for a smooth transition.
(d) Measurements of existing DFT shall be recorded for historical purposes in accordance withSSPC PA-2.
Non-
ExportControlledInforma
tionReleasable
toNon-USPersons:S2DSE
A2012-0051
5. Upon approval of the surface preparation, the contractor shall apply one coat of AC primer, in
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
26/28
accordance with established Standard Item 009-32 requirements to all areas in the zone or work
area (i.e., bare metal and retained epoxy primer) to achieve the specified 5-7 mil dry filmthickness. The contractor is not obligated to apply a thin or varied primer thickness when
traversing areas between bare metal and retained epoxy. Again following standard practices,SUPSHIP shall inspect the zone or work area coating thickness. Because the coating thicknessretained will vary notably, DFT readings shall be taken and recorded; however high DFT
readings shall not be means for rejection, such readings shall only be taken for documentationpurposes. In place of DFT readings for determining proper coating thickness, WFT readings
shall be taken and recorded on each coat to confirm proper coating thickness (i.e. follow the 009-32 requirement for taking WFT readings in place of DFT readings for accept/reject criteria). All
other QA requirements of 009-32 shall be accomplished.
6. Once the primer has cured to overcoat the surface area shall be inspected for edge lifting of the
remaining epoxy that was over coated. This inspection shall be conducted at a maximumdistance of 15 feet. The curing epoxy primer will lift any loose edges of the existing coating as it
cures that may not have been visible during the initial surface preparation inspection. Theseareas shall be prepared in accordance with SSPC-SP-3 and primed.
7. For underwater hull areas, apply second or tie coat of epoxy and first coat of antifouling inaccordance with Standard Item 009-32 requirements (using WFT readings).
8. For underwater hull areas, apply complete antifouling system in accordance with StandardItem 009-32 requirements and note final coating thickness. Again, use WFT readings in place of
DFT readings for determining proper coating application, with DFT readings being recorded fordocumentation purposes.
9. For freeboard areas, apply second coat of epoxy then the topcoat in accordance with StandardItem 009-32 requirements (using WFT readings).
10. The contractor and NAVSEA representative shall retain time, cost, or productivity metrics to
report to NAVSEA and to be used to provide supporting data for any future Standard Item 009-32 proposal to incorporate spot and sweep processes.
Non-
ExportControlledInforma
tionReleasable
toNon-USPersons:S2DSE
A2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
27/28
Potential Cost Savings to the Fleet
Defining the cost savings is a deliverable of the project due March 31,
2012.
Schedule and budget savings measured against the life cycle of the
coating system to docking evolutions.
Freeboard preservation may be the land of opportunity. Non Critical,often top coated for aesthetics only. Easily inspected. Greater than
double the square footage over the UWH. Cost per square foot for
surface preparation freeboard and UWH are close.
Draft document was explained to inspectors who accomplished the G
point on the following day. Their comments/feedback will be
incorporated into final revision. PSNS, NWRMC, VIGOR.
We have successfully demonstrated Spot and sweep on both coasts to
the draft document.
Non-Export Controlled Information Releasable
to Non-US Persons: S2DSEA2012-0051
8/13/2019 021512 Evaluation of Spot and Sweep Blasting
28/28
QUESTIONS
Special thanks to the Project Team:
Chariot Robotics; John Odwazny, Gordon Kuljian
Elzly technologies; Pete Ault
NAVSEA: Mark Ingle, David CisconThe commands of FFG-42 and FFG- 60, PSNS code 400, SERMC
and the PMTs of BAE Systems SSYI and Vigor Shipbuilding
Non-Export Controlled Information Releasableto Non US Persons: DSEA S2 2010 0118