+ All Categories

02hndst

Date post: 14-Apr-2018
Category:
Upload: sanjeevchhabra1
View: 219 times
Download: 0 times
Share this document with a friend
12
7/30/2019 02hndst http://slidepdf.com/reader/full/02hndst 1/12 STEAM TURBINE 500 MW ERECTION INSTRUCTIONS FOR HANDLING & STORAGE SCOPE The document covers all steam turbine components and provides the handling, inspection and storage instructions for large steam turbine components at site.  A strict adherence to these instructions is necessary to avoid damages during handling and storage at site. HANDLING OF EQUIPMENT : In any kind of rigging work it is necessary to strictly observe the safety precautions, since even the slightest negligence and non observance of the rules may result in accidents, which may cause damage to equipment or injury to men. The site for the rigging work involving lifting and conveying of loads should be well lighted. The loads must not be lifted unless the crane operator can see clearly the signals given by the rigger. The positions where the slings are to be put, are marked on the packages and on the drawings. While lifting/handling these packages/equipment, the slings should only be put at the proper places. The slings of the proper sizes and lengths should only be used for handling the equipment/packages. The angle between the two arms of the sling at the crane hook should be small (depending upon the dia of the sling) so as to have proper loading of the sling. The turbine rotors and cylinder covers (in assembled condition are lifted by the use of special lifting devices supplied by BHEL. The use of these lifting devices facilitates correct slinging and maintain horizontal position of the components. These devices, after use, should be properly stored and conserved so as to ensure that they do not get damaged during storage. Before using them, they should be thoroughly inspected. The work related to handling of the loads (packages or equipment) by crane or by other hoisting mechanism should be entrusted to trained riggers only. If the rigger/operator is not sure of the weight of the item/package (load) to be handled, he must ask for the required information before handling the equipment. Bharat Heavy Electricals Limited Rev 00, 7-98 T1-08-0202G Page No. 1 of 11
Transcript
Page 1: 02hndst

7/30/2019 02hndst

http://slidepdf.com/reader/full/02hndst 1/12

STEAM TURBINE500 MWERECTION

INSTRUCTIONS FOR HANDLING &STORAGE

SCOPE 

The document covers all steam turbine components and provides the handling,inspection and storage instructions for large steam turbine components at site.

 A strict adherence to these instructions is necessary to avoid damages duringhandling and storage at site.

HANDLING OF EQUIPMENT :

In any kind of rigging work it is necessary to strictly observe the safetyprecautions, since even the slightest negligence and non observance of the rules may result in accidents, which may cause damage to equipmentor injury to men.

The site for the rigging work involving lifting and conveying of loads shouldbe well lighted. The loads must not be lifted unless the crane operator can see clearly the signals given by the rigger.

The positions where the slings are to be put, are marked on the packagesand on the drawings. While lifting/handling thesepackages/equipment, the slings should only be put at the proper places.

The slings of the proper sizes and lengths should only be used for handlingthe equipment/packages. The angle between the two arms of the slingat the crane hook should be small (depending upon the dia of the sling)so as to have proper loading of the sling.

The turbine rotors and cylinder covers (in assembled condition are lifted bythe use of special lifting devices supplied by BHEL. The use of these lifting devices facilitates correct slinging and maintainhorizontal position of the components. These devices, after use, shouldbe properly stored and conserved so as to ensure that they do not getdamaged during storage. Before using them, they should be thoroughly

inspected.

The work related to handling of the loads (packages or equipment) by crane or by other hoisting mechanism should be entrusted to trained riggersonly. If the rigger/operator is not sure of the weight of theitem/package (load) to be handled, he must ask for the requiredinformation before handling the equipment.

Bharat Heavy Electricals LimitedRev 00, 7-98 T1-08-0202GPage No. 1 of 11

Page 2: 02hndst

7/30/2019 02hndst

http://slidepdf.com/reader/full/02hndst 2/12

STEAM TURBINE500 MWERECTION

INSTRUCTIONS FOR HANDLING &STORAGE

The rigger and the crane operator should see that the hook and the ropes of the crane occupy vertical position, before hoisting the load. Draggingof the load by slanting ropes is not allowed. The center of gravity of theload should be aligned with the vertical axis of the crane hook.

The eye bolts, 'D' shackles, turn buckles, and wire ropes of suitable sizesshould only be used for handling of the equipment. Before using, theyshould be thoroughly inspected to their full threads, so as to avoid anychance of slipping then the load comes on them.

Before giving a signal to lift the load, the rigger must check and ensure thatthere are no loose parts or tools on the load, which might fall duringlifting. Then the load must be lifted 100 or 200 mm high for checkingthe uniformity of sling tensioning and reliability of lashing. If it isnecessary to rearrange the sling lengths, the load must be loweredand then the slings rearranged.

Before horizontal conveyance of the load the rigger must see that the load hasbeen lifted to a height at least 0.5 M above the tallest object, on the pathof the load. While the load is being conveyed, the rigger mustaccompany it and see that it is not moved above any person. Prior tolowering the load the rigger should examine the ground on which theload will be, lowered and make sure that these is no risk of falling or slipping of the load.

If any one of the personnel present during lifting or lowering of the loaddetects some defect of the crane or sling of notices some conditions

 jeopardizing the lifting or lowering operation, he must give a signalfor emergency grounding of the package or components.

Smooth lifting and transportation of equipment must be ensured. Shocks and jerks should be avoided.

 All lifting devices, slings must be properly conserved after use and periodicallyinspected and tested.

In the turbines having diaphragms, it is prohibited to handle diaphragms byputting slings in between the blades. For handling the weldeddiaphragms, special lifting devices is supplied by BHEL and thecast diaphragms are handled by putting the eye bolts, for which theprovision of threads holes have been made in the diaphragms.

While handling the bearings, it is prohibited to put the sling across the rabbitsurface of the bearings. Threaded holes have been provided; in which theeye bolts have to be put for handling of the bearings.

Bharat Heavy Electricals LimitedRev 00, 7-98 T1-08-0202GPage No. 2 of 11

Page 3: 02hndst

7/30/2019 02hndst

http://slidepdf.com/reader/full/02hndst 3/12

STEAM TURBINE500 MWERECTION

INSTRUCTIONS FOR HANDLING &STORAGE

While handling the cylinders, it must be ensured that the slings or any other material does not get rubbed at their horizontal and vertical partingplanes or at any other machined surface.

The handling of the long components such as longitudinal girder, endwall etc.should be done with extra care. When they are placed on the floor, inaddition to the end supports, few extra supports at the intermediatepositions must be provided.

While handling LP rotor with free standing blades, care must be taken to ensurethat no force is exerted on the free standing blades to avoid collapsing of clamping pieces under blade root.

MARKINGS ON PACKING CASES

Various symbols are marked on the packing cases as per 0456.001 tofacilitate storage and handling of the crates and protection of equipment inside.

INSPECTION

Before storing the equipment it should be opened for visual examination or the internal packing, protective coating and condition of the equipment.

 Any damage to packing and conservation should be immediatelyrectified.

It is necessary to carryout first inspection within three weeks of arrival of theconsignment. Thereafter, all the equipment should be inspected once inevery three months to insure that the conservation is intact. During rainyseason, the inspection should be done once in a month. At any time, if any original conservation is found damaged, it should be reconserved asper relevant conservation instructions No. ST 33004.

While inspecting the packages containing rotors, special care should be takento check the journals. In case of slightest sign of pitting on the journalsand thrust collar, immediate steps for rectification should be taken andequipment reconserved as per relevant conservation instructions.

STORAGE

 All steam turbine equipment should be accommodated in the designated placeof storage immediately after arrival at destination. This is very essentialparticularly during the rainy season.

Bharat Heavy Electricals LimitedRev 00, 7-98 T1-08-0202GPage No. 3 of 11

Page 4: 02hndst

7/30/2019 02hndst

http://slidepdf.com/reader/full/02hndst 4/12

STEAM TURBINE500 MWERECTION

INSTRUCTIONS FOR HANDLING &STORAGE

Store houses fall into the following categories

TYPE OF CONDITIONSSTOREHOUSE

TEMP. RELATIVEHUMIDITY

ARRANGEMENT

'P' +50 Cto

500 C

< 70 % Totally enclosed, rain proof, ventilatedand dry with cemented floor.

'Q' upto500 C

- Roofed area with walls (of brick /asbestos/ GI sheet ) around and

cemented / pucca hard floor.

'R' - - Raised platform with shed of asbestos /GI sheet / water proof tarapaulin.

'S' - - Raised Platform.

Bharat Heavy Electricals LimitedRev 00, 7-98 T1-08-0202GPage No. 4 of 11

Page 5: 02hndst

7/30/2019 02hndst

http://slidepdf.com/reader/full/02hndst 5/12

STEAM TURBINE500 MWERECTION

INSTRUCTIONS FOR HANDLING &STORAGE

The platforms and store-houses should be built up in conformity with the fireprevention rules and standards. Complete storage area especially the ‘R’& ‘S’ catagory must be adequately fenced & protected against theft &pilferage.

These store houses and areas around them should have proper drainagefacility for the sub-soil, surface and rain water. The water should not beallowed to stand or get accumulated in these areas, especially wherethe material has been stored.

Store house should be provided with proper ventilation facilities.

Level should be maintained for all the packages and equipment and shouldbe uniformly supported to avoid distortion. The long packages shouldbe supported at intermediate places also, so as to avoid sagging duringstorage.

Store houses should preferably be equipped with proper lifting devices toensure normal handling of equipment.

Small and medium size parts can be kept on shelves with proper identificationtags.

Packages upto 5 tones can be placed on upon the other upto 2.5m in heightusing required number of wooden spacers 50 mm thick. In doing so,lighter packages would be laid upon heavier once to avoid any damageto lower packages.

 Articles weighing more than 5 tones should be laid in a single tier.

For heavier components under ‘Q’, the roof/walls may be constructed/fabricatedafter placement of the component on cemented/pucca hard floor.

Bharat Heavy Electricals LimitedRev 00, 7-98 T1-08-0202GPage No. 5 of 11

Page 6: 02hndst

7/30/2019 02hndst

http://slidepdf.com/reader/full/02hndst 6/12

STEAM TURBINE500 MWERECTION

INSTRUCTIONS FOR HANDLING &STORAGE

STORAGE OF STEAM TURBINE COMPONENTS

SNO. DESCRIPTION OF THE COMPONENT TYPE OFSTORAGE

1. FOUNDATION BOLT Q

2. EMBEDDED PARTS (ADDITIONAL) R

3. COMPONENTS OF BASE PLATE ASSLY. Q

4. BASE PLATE LP CASING R

5. LP OUTER CASIONG R

6. LONGITUDINAL GIRDER (LEFT & RIGHT) R

7. LP FRONT WALL (TS&GS) R

8. LP SHAFT SEALING (FRONT & REAR) Q

9.  AUXILIARIES OF TURBINE Q

10. HP/IP BEARING PEDESTAL Q

11. HP/IP BEARING PEDESTAL ASSEMBLY PARTS Q

12. IP/LP PEDESTAL ASSEMBLY Q

13. LP/GEN. PEDESTAL Q

14. BEARING PEDESTAL PARTS Q

15. FRONT BEARING PEDESTAL Q

16. LIFTING BEAM R

17. LP CASING EXTRACTION A1 R

18. LP EXTRACTION A2 R

19. LP EXTRACTION A3 R

20. LP EXTRACTION PIPE SHEATHING R

21. INNER GUIDE PLATE DIFFUSER R

22. DIFFUSER (UPPER & LOWER HALVES) R

23. LP INNER-OUTER CASING (VH) Q

24. LP INNER CASING ASSEMBLY (LH & VH) Q

25. HEATING DEVICE Q

26. LP CASING ASSEMBLY Q

27. LP INNER CASING ASSEMBLY (FASTENER) Q

28. INNER GUIDE PLATE DIFFUSER (GS) R

Bharat Heavy Electricals LimitedRev 00, 7-98 T1-08-0202GPage No. 6 of 11

Page 7: 02hndst

7/30/2019 02hndst

http://slidepdf.com/reader/full/02hndst 7/12

STEAM TURBINE500 MWERECTION

INSTRUCTIONS FOR HANDLING &STORAGE

29. LP ROTOR Q

30. IP TURBINE Q

31. IP TURBINE PARTS Q

32. IP INLET PIPES Q

33. HP TURBINE Q

34. HP INLET ASSEMBLY Q

35. HP EXHAUST ELBOW Q

36. HPT RELATED PARTS Q

37. FRAME FOR SUSPENSION (ESV) R

38. SUSPENSION OF VALVE (ESV) Q39. ESV & CV CASING WITH VALVE Q

40. ESV SERVOMOTORS WITH LIMIT SWITCH Q

41. HP CONTROL VALVE SERVOMOTORS Q

42. SUSPENSION OF VALVE (IV) Q

43. IV & CV CASING WITH VALVE Q

44. IV SERVOMOTORS WITH LIMIT SWITCH Q

45. IP CONTROL VALVE SERVOMOTORS Q

46. FRAME FOR SUSPENSION (IV) R

47. IV SERVOMOTORS WITH LIMIT SWITCH Q

48. STEAM BLOWING & HYD. TEST DEVICE Q

49. TOOLS FOR GOVERNING SYSTEM Q

50. SUSPENSION OF LPB VALVE Q

51. WATER INJECTION VALVES Q

52. CHEST LPB WITH STOP & CONTROL VALVE q

53. LPB STOP VALVE SERVOMOTOR Q54. LPB CONTROL VALVES SERVOMOTORS Q

55. INJR. FOR SUCTION PIPE NB 350 R

56. INJR. FOR SUCTION PIPE NB 300 R

57. MAIN OIL TANK R

58. MAIN OIL TANK & NOZZLE ASSEMBLY R

59. OIL STRAINER Q

Bharat Heavy Electricals LimitedRev 00, 7-98 T1-08-0202GPage No. 7 of 11

Page 8: 02hndst

7/30/2019 02hndst

http://slidepdf.com/reader/full/02hndst 8/12

STEAM TURBINE500 MWERECTION

INSTRUCTIONS FOR HANDLING &STORAGE

60. LEVEL MONITOR INSTALLATION Q

61. INSTRUMENTS Q

62. LEAKAGE / DIRTY FLUID TANK R

63. VARIABLE ORIFICES & THROTTLE Q

64. CONTROL FLUID TANK R

65. CONTROL FLUID TANK NOZZLE ARRANGEMENT R

66. EXPANSION TANK R

67. FILTER & PR. DAMPING DEVICES Q

68. CROSS AROUND PIPE R

69. SUPPORT FOR CAP R70. CHANGE OVER VALVE R

71. RATING & MONOGRAM PLATES Q

72. OIL STRIPER R

73. HOUSING FOR HRH STEAM STRAINER R

74. HOUSING FOR MAIN STEAM STRAINER R

75. MS & HRH STR.HSG GASKET Q

76. STEAM STRAINER MS Q

77. STEAM STRAINER HRH Q

78. COMPENSATOR Q

79. TURBINE CONTROL LPB / SUPPLY RACK Q

80. TEMPERATURE & PRESSURE CONNECTIONS Q

81. PR. TRANSMITTERS BAR. PROBES THERMOCOUPLES Q

82. TRANSMITTERS & JUNCTION BOXES Q

Bharat Heavy Electricals LimitedRev 00, 7-98 T1-08-0202GPage No. 8 of 11

Page 9: 02hndst

7/30/2019 02hndst

http://slidepdf.com/reader/full/02hndst 9/12

STEAM TURBINE500 MWERECTION

INSTRUCTIONS FOR HANDLING &STORAGE

STORAGE & PRESERVATION OF COMPONENTS OFTURBOGENERATOR, EXCITER AND SYSTEMS

SNO. DESCRIPTION OF THE COMPONENT TYPE OFSTORAGE

1. EMBEDDED PARTS R

2. FOUNDATION PARTS R

3. WOUND STATOR WITH GAS COOLERS Q

4. TURNION FOOT PLATES Q

5. ROTOR Q

6.  ASSEMBLY OF PIPE CONTROL FOR GAS COOLERS R

7. END SHIELDS Q

8. FAN SHIELD, GEN VVIEW HEADER ASSEMBLY R

9. TERMINAL BUSHING AND HEADER ASSEMBLY Q

10. BEARING WITH BRUSH GEAR Q

11. SEAL BODY Q

12. TEMP. CONNECTION Q

13. CASING FOR TURNIONS R

14. ERECTION MATERIALS Q

15. ERECTION DEVICES R

16. SHAFT SEALS Q

17. SEAL RINGS Q

18.  ADOPTING RING Q

19.  AUXILIARY BEARING Q

20. CENTRIFUGAL FAN Q

21. CARBON DIOXIDE VAPOURISER Q

22. FILTER O.C.P. Q23. EXPANSION TANK R

24. OIL SEPARATOR R

25. PRE CHAMBER R

26. S.O.S.T. R

27. SEAL OIL UNIT Q

28. HYDROGEN DISTRIBUTION R

Bharat Heavy Electricals LimitedRev 00, 7-98 T1-08-0202GPage No. 9 of 11

Page 10: 02hndst

7/30/2019 02hndst

http://slidepdf.com/reader/full/02hndst 10/12

STEAM TURBINE500 MWERECTION

INSTRUCTIONS FOR HANDLING &STORAGE

29. CARBON DIOXIDE DISTRIBUTION R

30. VALVES FOR AUXILIARY SYSTEMS P

31. GAS UNITS Q

32. FLEXIBLE LEADS Q

STORAGE & PRESERVATION OF COMPONENTS OFHEAT EXCHANGERS

SNO. DESCRIPTION OF THE COMPONENT TYPE OFSTORAGE

PRODUCT : CONDENSER

1. BOTTOM PLATE S2. LOWER DOM WALL S

3. SIDE WALL S

4. WATER CHAMBER Q

5. UPPER DOM WALL S

6. STIFFENING PIPES S

7. STIFFENING RODS S

8. TUBE SUPPORT PLATE R

9. WATER BOX R

10.  AIR EXTRACTION PIPING R

11. HOTWELL S

12. SPRING ELEMENTS R

13. LOOSE ITEMS Q

14. INSTRUMENTS Q

15. CONDENSER TUBES (STAINLESS STEEL) R

16. CONDENSER TUBES (NON-FERROUS) Q

17. VACUUM PUMP Q

18. EJECTOR R19.  AIR MEASURING DEVICE Q

PRODUCT : HEATER

20. GLAND STEAM CONDENSER R

21. STAND PIPE Q

22. INSTRUMENTS Q

23. DRAIN COOLER R

Bharat Heavy Electricals LimitedRev 00, 7-98 T1-08-0202GPage No. 10 of 11

Page 11: 02hndst

7/30/2019 02hndst

http://slidepdf.com/reader/full/02hndst 11/12

STEAM TURBINE500 MWERECTION

INSTRUCTIONS FOR HANDLING &STORAGE

24. L.P.HEATERS R

PRODUCT : COOLER

25. OIL COOLER R

26. CONTROL FLUID COOLER R

27. STATOR WATER COOLER R

28. HYDROGEN COOLER Q

29. EXCITER AIR COOLER Q

30. INSTRUMENTS / LOOSE ITEM Q

Bharat Heavy Electricals LimitedRev 00, 7-98 T1-08-0202GPage No. 11 of 11

Page 12: 02hndst

7/30/2019 02hndst

http://slidepdf.com/reader/full/02hndst 12/12

STEAM TURBINE500 MWERECTION

INSTRUCTIONS FOR HANDLING &STORAGE

MAXIMUM PERMISSIBLE LOADING FOR WIRE ROPES IN KG.NOMINAL SINGLE DOUBLE CORD WITH INCLUDED ANGLE OFDIA (d) OF

ROPES mmCORD

0o 45o 90o 120o

9 522 1044 965 738 522

12 1170 2340 2070 1580 1170

18 2150 4300 4000 3060 2150

24 3850 7700 2100 5400 3850

30 6200 12400 11500 8800 6200

36 9000 18000 16600 12700 9000

42 12200 24400 22600 17300 12200

48 16000 32000 29500 22600 16000

54 20200 40400 37300 28500 20200

60 24900 49800 46000 35200 24900

66 30100 60200 55700 42600 30100

72 35800 71600 66200 50700 35800

78 42100 84200 77700 59500 42100

84 48800 97600 90200 69000 48800

90 56000 112000 103500 79200 56000

96 63700 127400 117700 90000 63700

102 71900 143800 132900 101700 71900

108 81000 162000 149700 114500 81000

114 89900 179800 166100 127100 89900

120 99700 199400 184300 141100 99700

Bharat Heavy Electricals LimitedRev 00, 7-98 T1-08-0202GPage No. 12 of 11