Pearl GTL Project
LINDE ENGINEERING
Shell Project No: HP-3000-QAT Contractor Project No : 5887
Project Document Number: T- 4.250.921 Project Rev.: A Page 2 of 18
Purchase Order Number:
2MH127
Tag/Item Number(s): 1A-2121, 1A-2221, 1A-2321, 1A-2421 2A-2121, 2A-2221, 2A-2321, 2A-2421
Unit(s): 1-2100, 1-2200, 1-2300, 1-2400 2-2100, 2-2200, 2-2300, 2-2400
PCWBS: FA02, FB02, FC02, FD02 GA02, GB02, GC02, GD02
QATAR SHELL GTL PROJECT (PEARL) C2 AIR SEPARATION UNITS CONSTRUCTION
E A 20.01.09 Company Comments Incorporated SK EO AG CCI
D A 17.01.09 Ready for Construction SK EO AG RFC
C O 15.03.08 Issued for Company Comments BR AU/MC ZG ICC
B 03.02.08 Issued for Review BR AU/MC ZG IFR
A 31.01.08 Issued for Internal Review BR AU/MC ZG IIR
GAMA Rev.
Project Rev
Date Description Prepared
By Checked
By
Approved By
Status
No. No. ORIGINATOR
LINDE ENGINEERING AG
Document Title:
INSPECTION TEST PLAN FOR AIR COOLED STEAM CONDENSER
Contractor
Gama Qatar Co. W. L. L.
Document No. LOC470
GAM MTS QAC GTL 034 E
Org.
Code
Doc.
Type
Disc. Code
Geogr. Area
Seq.
No
Rev. No
Vendor Code
Project Document Number: T-4.250.921
Rev No: A
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-034
ITP FOR INSTALLATION OF AIR COOLED
STEAM CONDENSER DATE: 20.01.2009 REV. E
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR-(SPX)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test
Frequency Reference Document Acceptance Criteria
Responsible Party
Verifying Documents S A x C
T-4.250.921 REV-A Page 4 of 18
1.0
GENERAL
1.1 Contractor drawings, project specifications, manuals, codes
100% TECHINICAL
OFFICE H R R
1.2 Lifting studies (For Heavy Equipments)
100%
T.4.234.084 HSSE H R R
1.3 Paint /Galvanize touch up 100% Refer Painting ITP T.4.250.919/T.4.096.672 QCI GAM-QCR-QAC-GTL-056
(T.4.318.598) I S S S
1.4 Procedures 100% T.4.186.019;T.4.121.350 - QCI Verify the documents R R R R
2.0 EQUIPMENT
2.1 Equipment identification and name plate verification and visual inspections
100% T.4184.662;
T-4.250.944
Approved drawing
DEP 31.10.03.10, DEP 31.29.00.10,T.4.121.350
STORE
INCHARGE
GAM-QCR-QAC-GTL-080 (T.4.318.599)
I S S S
2.2 Receiving inspection 100% Shifted to Item no: 2.1
2.3 Storage, preservation and documentation (FSI)
100% T.4.186.019;T-4.250.932,
T-4.250.944;T.13.377.360E
Approved drawing,
DEP 70.10.70.11,
T.4.121.350,Vendor instruction
FSI GAM-QCR-QAC-GTL-069
(T.4.318.599) I R S S
2.4 Periodic Preventive
maintenance Deleted
2.5
Inspection measuring and test
equipment calibration
100% T-4.250.915, Valid Certificate QCI Calibration certificate H R R R
3.0 STRUCTURAL STEEL
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-034
ITP FOR INSTALLATION OF AIR COOLED
STEAM CONDENSER DATE: DATE: 20.01.2009 REV. E
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR-(SPX)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test
Frequency Reference Document Acceptance Criteria
Responsible Party
Verifying Documents S A x C
T-4.234.075 Rev. A Page 5 of 18
3.1 Main Structure
3.1.0
Foundations complete and
Accepted (Including chipping, anchor bolt control and pocket cleaning)
100% T-4.250.944;T.4.186.019
Approved drawing DEP 34.19.20.31
DEP 34.28.00.31;
T.13.376.359E;T.4.121.350
QCI GAM-QCR-QAC-GTL-113
(T.4.318.599) I I I
W/R
3.1.1 Foundation chipping to sound
metal Ref. Item Code 3.1.0
3.1.2 Anchor bolts control & pocket
cleaning Ref. Item Code 3.1.0
3.1.4 Temporary earthing 100%
T-4.250.944
Approved drawing DEP 34.19.20.31, T.4.121.350
QCI GAM-QCR-QAC-GTL-120 (T.4.318.600)
I I S S
3.1.5 Preassembly/installation Fixation and reinstallation of bracings
100% T-4.250.944: T-4.250.907
T.4.186.019
Vendor specification DEP 34.28.00.31;T.13.376.351G,
T.4.121.350 QCI
GAM-QCR-QAC-GTL-037; GAM-QCR-QAC-GTL-040
(T.4.318.598)
I S S S
3.1.6 Paint Temporary bolts blue All - - - Visual Check S S S S
3.1.7 Leveling, orientation,
Alignment/Elevation 100%
T-4.250.944: T.4.186.019
T-4.250.907;T.13.377.360;
T.4.193.320
Approved drawing DEP 34.28.00.31;T.13.376.351G,
T.4.121.350Vendor specification
QCI GAM-QCR-QAC-GTL-038 GAM-QCR-QAC-GTL-039
(T.4.318.598) H I W/R
W/R
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-034
ITP FOR INSTALLATION OF AIR COOLED
STEAM CONDENSER DATE: DATE: 20.01.2009 REV. E
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR-(SPX)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test
Frequency Reference Document Acceptance Criteria
Responsible Party
Verifying Documents S A x C
T-4.234.075 Rev. A Page 6 of 18
3.1.8 Final bolting up/torqueing
100%
T-4.250.944: T.13.377.360 T.4.186.019;T.4.193.320
DEP 34.28.00.31;
T.13.376.351G, T.4.121.350 QCI GAM-QCR-QAC-GTL-041
(T.4.318.598) I S/R S/R S
3.1.9 Remove Temporary bolts blue All All temporary bolts removed after completion of erection
No blue bolts QCI Visual Check S S S S
3.1.3 Grouting 100% T-4.250.944, T-4.234.545 DEP 34.19.20.31
T.13.376.358; T.4.121.350 QCI GAM-QCR-QAC-GTL-025
(T.4.318.598) I I S S
3.2
Upper Structure/Fans Deck/Fan Screens
3.2.1 Installation/Location Cut outs fixation
100% T-4.250.944 DEP 31.29.00.10
T.4.121.350 QCI
GAM-QCR-QAC-GTL-121 (T.4.318.600)
I I S S
3.2.2 Fan Tip Clearance 100% T-4.250.944;T.13.377.360E
Approved drawing DEP 31.29.00.10 T.4.121.350,
T.4.245.161(SPX) T.4.233.731(SPX)
QCI GAM-QCR-QAC-GTL-119 (T.4.318.600)
H I W/R W
3.2.3 Vane Angle 100% T.4.250.944
Approved Drawing DEP 31.29.00.10,T.4.121.350;
Vendor Instruction Manual
QCI GAM-QCR-QAC-GTL-119
(T.4.318.600) H I W/R W
3.2.4 Final Bolting Up/Torqueing 100% T-4.250.944;T.13.377.360
T.4.186.019 DEP 31.29.00.10
T.4.121.350; T.13.376.351G QCI GAM-QCR-QAC-GTL-041
(T.4.318.598) I I S S
3.9 Stairs & Ladders/Walkways and Platforms/Hand Rails
3.9.1 Foundations 100% T-4.250.944: T-4.250.907 Approved Drawing ;DEP
34.28.00.31;T.13.376.351G, T.4.121.350
QCI GAM-QCR-QAC-GTL-040 (T.4.318.598)
H I I W/R
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-034
ITP FOR INSTALLATION OF AIR COOLED
STEAM CONDENSER DATE: DATE: 20.01.2009 REV. E
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR-(SPX)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test
Frequency Reference Document Acceptance Criteria
Responsible Party
Verifying Documents S A x C
T-4.234.075 Rev. A Page 7 of 18
3.9.2 Installation/elevation fixation 100% T-4.250.944: T-4.250.907
T.4.186.019
Approved Drawing ;DEP 34.28.00.31;T.13.376.351G,
T.4.121.350 QCI GAM-QCR-QAC-GTL-041
(T.4.318.598) I S/R S/R S
3.9.3 Final Bolting-up/ Torquening 100% T.4.250.897;T.13.377.360
T.4.186.019 DEP 31.29.00.10
T.4.121.350; T.13.376.351G QCI GAM-QCR-QAC-GTL-040
(T.4.318.598) I S/R S/R S
3.9.4 Grating & clips toe plate
hand railings 100% T-4.250.944: T-4.250.907
DEP 34.28.00.31;
T.13.376.351G, T.4.121.350 QCI
Confirm to drawing No openings toe plate to
Grating
I S S S
3.8 Fan Bells
3.8.1 Preassembly segments
Fixation 100% T-4.250.944: T-4.250.907
DEP 34.28.00.31;
T.13.376.351G, T.4.121.350 QCI GAM-QCR-QAC-GTL-037
(T.4.318.598) I S S S
3.8.2 Installation Air Inlet bells
fixation 100% T-4.250.944: T-4.250.907
DEP 34.28.00.31;
T.13.376.351G, T.4.121.350 QCI GAM-QCR-QAC-GTL-037
(T.4.318.598) I S S S
3.8.3 Alignment 100%
T-4.250.944;T.13.377.360 T.4.186.019
DEP 31.29.00.10 T.4.121.350
QCI GAM-QCR-QAC-GTL-038 GAM-QCR-QAC-GTL-039
(T.4.318.598)
H W/R
W/R I
3.8.4 Final Bolting up / Torqueing 100% T-4.250.944;T.13.377.360
T.4.186.019 DEP 31.29.00.10
T.4.121.350; T.13.376.351G QCI GAM-QCR-QAC-GTL-041
(T.4.318.598) I S/R S/R S
3.3 Motor Bridge support structure
3.3.1 Top under structure 100% T-4.250.907; T.4.186.019
Approved Drawing;DEP 34.28.00.31;
T.13.376.351G, T.4.121.350
QCI GAM-QCR-QAC-GTL-037
(T.4.318.598) H W/R W/R I
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-034
ITP FOR INSTALLATION OF AIR COOLED
STEAM CONDENSER DATE: DATE: 20.01.2009 REV. E
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR-(SPX)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test
Frequency Reference Document Acceptance Criteria
Responsible Party
Verifying Documents S A x C
T-4.234.075 Rev. A Page 8 of 18
3.3.2 preassembly/Installation fixation
100% T-4.250.907
Approved Drawing DEP 34.28.00.31;
T.13.376.351G, T.4.121.350
QCI GAM-QCR-QAC-GTL-037 (T.4.318.598)
I S S S
3.3.3 Alignment/elevation 100%
T-4.250.944;T.13.377.360 T.4.186.019
Approved Drawing ;DEP 31.29.00.10 T.4.121.350
QCI GAM-QCR-QAC-GTL-038 GAM-QCR-QAC-GTL-039
(T.4.318.598)
I W/R W/R I
3.3.4 Final Bolting up
/Torqueing 100%
T-4.250.944;T.13.377.360 T.4.186.019
DEP 31.29.00.10 T.4.121.350; T.13.376.351G
QCI GAM-QCR-QAC-GTL-041 (T.4.318.598)
I S/R S/R S
3.3.5 Grating & Clips toe plate
hand railings 100% T-4.250.907
DEP 34.28.00.31;
T.13.376.351G, T.4.121.350 QCI
Confirm to drawing No openings toe plate to
Grating
I S S S
4.3 Gear Boxes/Motors/Fans
4.3.1 Preassembly motor-gear box
coupling Motor-gear box 100%
T.4.250.944,T.4.250.945 T.4.186.019
Approved Drawing;
T.4.121.350;Vendor Specifications
QCI GAM-QCR-QAC-GTL-037
(T.4.318.598) I S S S
4.3.2 Installation Motor-gear box fixation
100%
T.4.250.944,T.4.250.945 T.4.186.019
Approved drawings; Vendor SpecificationsT.4.121.350
QCI GAM-QCR-QAC-GTL-115
(T.4.318.600) I S S S
4.3.3 First oil fill gearbox 100%
T.4.250.944,T.4.250.945 T.4.186.019
Approved drawings; Vendor SpecificationsT.4.121.350
QCI Check oil Type/level I I W/R S
4.4.4 Installation hub plate/retaining plate fixation
100%
T.4.250.944,T.4.250.945 T.4.186.019
Approved drawings; Vendor SpecificationsT.4.121.350
QCI GAM-QCR-QAC-GTL-121
(T.4.318.600) I I W/R
W/R
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-034
ITP FOR INSTALLATION OF AIR COOLED
STEAM CONDENSER DATE: DATE: 20.01.2009 REV. E
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR-(SPX)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test
Frequency Reference Document Acceptance Criteria
Responsible Party
Verifying Documents S A x C
T-4.234.075 Rev. A Page 9 of 18
4.4.5 Installation of fan blades blade angle fixation
100%
T.4.250.944,T.4.250.945 T.4.186.019
Approved drawings; DEP 31.29.00.10,Vendor
SpecificationsT.4.121.350 QCI
GAM-QCR-QAC-GTL-121 (T.4.318.600)
I I W/R W/R
4.4.6 Tip clearance 100%
T.4.250.944,T.4.250.945 T.4.186.019
Approved drawings; DEP 31.29.00.10,Vendor
SpecificationsT.4.121.350 QCI
GAM-QCR-QAC-GTL-121 (T.4.318.600)
I I W/R W/R
4.4.7
Final Bolting up/torqueing gear box, retaining plate fixation
Hub plate fixation fan blade
Fixation
100%
T.4.250.944,T.4.250.945,
T.13.377.360 T.4.186.019
Approved drawings; Vendor SpecificationsT.4.121.350
QCI GAM-QCR-QAC-GTL-041
(T.4.318.598) I W/R W/R I
3.4 " A Frames/Sliding & fixed supports
3.4.1 Top under structure 100% T-4.250.944: T-4.250.907
T.4.186.019
Approved Drawing;DEP 34.28.00.31;T.13.376.351G,
T.4.121.350 QCI
GAM-QCR-QAC-GTL-037 (T.4.318.598)
I W/R W/R W/R
3.4.2 Preassembly /Installation
fixation 100% T-4.250.944: T-4.250.907
Approved Drawing;DEP 34.28.00.31;T.13.376.351G,
T.4.121.350 QCI GAM-QCR-QAC-GTL-037
(T.4.318.598) I S S S
3.4.3 Alignment/elevation( A frames and sliding & fixed supports)
100% T-4.250.944;T.13.377.360
T.4.186.019 Approved Drawing ;DEP 31.29.00.10 T.4.121.350
QCI GAM-QCR-QAC-GTL-038 GAM-QCR-QAC-GTL-039
(T.4.318.598)
H I W/R W/R
3.4.4 Final Bolting Up
/Torqueing 100%
T.13.377.360;T-4.250.907 T.4.186.019
DEP 31.29.00.10 T.4.121.350; T.13.376.351G
QCI GAM-QCR-QAC-GTL-041 (T.4.318.598)
I S/R S/R S
3.4.5 Doors(Removable parts for
Hoist device) 100% T-4.250.944: T-4.250.907
DEP 34.28.00.31;
T.13.376.351G, T.4.121.350 QCI Confirm to Drawing, Check
correct opening (direction) I S S S
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-034
ITP FOR INSTALLATION OF AIR COOLED
STEAM CONDENSER DATE: DATE: 20.01.2009 REV. E
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR-(SPX)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test
Frequency Reference Document Acceptance Criteria
Responsible Party
Verifying Documents S A x C
T-4.234.075 Rev. A Page 10 of 18
3.4.6 Sheeting install/Location cut
outs fixation 100% T-4.250.944: T-4.250.907
DEP 34.28.00.31;
T.13.376.351G, T.4.121.350 QCI
Confirm to drawing, Check cable/Pipe protrusion-Check Fixation type/length
I S S S
3.4.7 Remove temporary bolts 100% All temporary bolts removed after completion of erection.
No blue bolts QCI Visual Check I S S S
3.5 Wind wall structure & Sheeting
3.5.1 Top under Structure 100% T-4.250.944: T-4.250.907
Approved Drawing; DEP 34.28.00.31;
T.13.376.351G, T.4.121.350
QCI GAM-QCR-QAC-GTL-037
(T.4.318.598) I S S S
3.5.2 Pre assembly/installation
fixation 100% T-4.250.944: T-4.250.907
Approved Drawing ;DEP 34.28.00.31;
T.13.376.351G, T.4.121.350
QCI GAM-QCR-QAC-GTL-037 (T.4.318.598)
I S S S
3.5.3 Alignment/elevation 100%
T-4.250.944;T.13.377.360 T.4.186.019
Approved Drawing ;DEP 31.29.00.10 T.4.121.350
QCI GAM-QCR-QAC-GTL-038 GAM-QCR-QAC-GTL-039
(T.4.318.598)
H I W/R W/R
3.5.4 Final Bolting up
/Torqueing 100%
T-4.250.944;T.13.377.360 T.4.186.019
DEP 31.29.00.10 T.4.121.350; T.13.376.351G
QCI GAM-QCR-QAC-GTL-041 (T.4.318.598)
I S/R S/R S
3.5.5 Doors 100% T-4.250.944: T-4.250.907 DEP 34.28.00.31;
T.13.376.351G, T.4.121.350 QCI Confirm to Drawing, Check
correct opening (direction) I S/R S/R S
3.5.6 Sheeting install/Location cut-
outs fixation 100% T-4.250.944: T-4.250.907
DEP 34.28.00.31;
T.13.376.351G, T.4.121.350 QCI
Confirm to drawing, Check cable/Pipe protrusion-
Check Fixation type/length
I S S S
3.6 Air Seal Plates
3.6.1 Installation/Location cut-outs
fixation 100% T-4.250.944: T-4.250.907
DEP 34.28.00.31;
T.13.376.351G, T.4.121.350 QCI Confirm to Drawing /Check
Visual Installation I S S S
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-034
ITP FOR INSTALLATION OF AIR COOLED
STEAM CONDENSER DATE: DATE: 20.01.2009 REV. E
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR-(SPX)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test
Frequency Reference Document Acceptance Criteria
Responsible Party
Verifying Documents S A x C
T-4.234.075 Rev. A Page 11 of 18
3.7 Hoisting beam
3.7.1 Installation fixation 100% T-4.250.944: T-4.250.907 Approved Drawing ;DEP
34.28.00.31;T.13.376.351G, T.4.121.350
QCI GAM-QCR-QAC-GTL-037 (T.4.318.598)
I S S S
3.7.2 Final Bolting up
/Torqueing 100% T-4.250.944;T.13.377.360
DEP 31.29.00.10 T.4.121.350; T.13.376.351G
QCI GAM-QCR-QAC-GTL-041 (T.4.318.598)
I S/R S/R S
3.7.3 Load Test 100%
T-4.250.944: T-4.250.907; T.13.377.360 T.4.186.019
DEP 34.28.00.31;
T.13.376.351G, T.4.121.350 QCI LOAD TEST REPORTS
(TPI) H H/R H/R I
3.7.4 Mark Hoisting Beam 100% T-4.250.944: T-4.250.907 Approved Drawing ;DEP
34.28.00.31;T.13.376.351G, T.4.121.350
QCI Mark Certified SWL on beam
H S S S
5.3 Steam Distribution Manifold (CCM)
5.3.1 Top "A" –Frames/supports 100% T.4.250.944,T.4.250.945 Approved drawings; Vendor SpecificationsT.4.121.350
QCI GAM-QCR-QAC-GTL-037
(T.4.318.598) I S/R S/R S
5.3.2 Installation Condensate collecting Manifold (CCM)
100% T.4.250.944,T.4.250.945 Approved drawings; Vendor SpecificationsT.4.121.350
QCI GAM-QCR-QAC-GTL-115
(T.4.318.600) I S S S
5.3.3
Alignment/elevation(Manifolds-connection risers + Tack
welding)
100% T.4.250.944,T.4.250.945
T.13.377.360 Approved drawings; Vendor SpecificationsT.4.121.350
QCI GAM-QCR-QAC-GTL-115
(T.4.318.600) H I S/R S
5.3.4 Fixed/Sliding saddle 100% T.4.250.944,T.4.250.945 Approved drawings; Vendor SpecificationsT.4.121.350
QCI Check Position/Assembly I S S S
5.3.5
Final Bolting up-
Torqueing(Fixed/Sliding Support)
100% T.4.250.897;T.13.377.360 Approved drawings; Vendor SpecificationsT.4.121.350
QCI GAM-QCR-QAC-GTL-041
(T.4.318.598) I R R S
4.0 Air Cooled Condenser Equipment
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-034
ITP FOR INSTALLATION OF AIR COOLED
STEAM CONDENSER DATE: DATE: 20.01.2009 REV. E
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR-(SPX)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test
Frequency Reference Document Acceptance Criteria
Responsible Party
Verifying Documents S A x C
T-4.234.075 Rev. A Page 12 of 18
4.1 Secondary Bundles
4.1.1 Installation 100% T-4.250.944: T-4.250.907 Approved Drawing DEP
34.28.00.31;T.13.376.351G, T.4.121.350
QCI GAM-QCR-QAC-GTL-124 (T.4.318.600)
I W/R W/R S
4.1.2 Alignment/Elevation 100% T-4.250.944:
T-4.250.907;T.13.377.360
DEP 34.28.00.31;
T.13.376.351G, T.4.121.350 QCI GAM-QCR-QAC-GTL-124
(T.4.318.600) I I W/R
W/R
4.1.3 welding 100% T.4.250.944; T.4.121.350 T.13.377.441;DEP
31.38.01.31;T.13.376.796E; QCI
GAM-QCR-QAC-GTL-161 (T.4.318.600)
I I S S
4.1.4 Jacking Screws 100% T.4.250.944; T.4.250.945 T.13.376.351G, T.4.121.350 QCI GAM-QCR-QAC-GTL-124
(T.4.318.600) I S S S
4.1.1 Primary Bundles
4.1.1.1 Installation 100% T-4.250.944: T-4.250.907 Approved Drawing DEP
34.28.00.31;T.13.376.351G, T.4.121.350
QCI GAM-QCR-QAC-GTL-124 (T.4.318.600)
I W/R W/R S
4.1.1.2 Alignment/Elevation 100% T-4.250.944:
T-4.250.907;T.13.377.360
DEP 34.28.00.31;
T.13.376.351G, T.4.121.350 QCI GAM-QCR-QAC-GTL-124
(T.4.318.600) I I W/R
W/R
4.1.1.3 welding 100% T.4.250.944; T.4.121.350 T.13.377.441;DEP
31.38.01.31;T.13.376.796E; QCI
GAM-QCR-QAC-GTL-161 (T.4.318.600)
I I S S
4.1.1.4 Jacking Screws 100% T.4.250.944; T.4.250.945 T.13.376.351G, T.4.121.350 QCI GAM-QCR-QAC-GTL-124
(T.4.318.600) I S S S
4.2 Condensate Tanks
4.2.1 Supporting Structure 100% T.4.250.944; T.4.250.945 Approved Drawing ,
T.4.121.350 QCI
GAM-QCR-QAC-GTL-037 (T.4.318.598)
I I W/R W/R
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-034
ITP FOR INSTALLATION OF AIR COOLED
STEAM CONDENSER DATE: DATE: 20.01.2009 REV. E
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR-(SPX)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test
Frequency Reference Document Acceptance Criteria
Responsible Party
Verifying Documents S A x C
T-4.234.075 Rev. A Page 13 of 18
4.2.2 Installation/tank expansion
fixation 100% T.4.250.944; T.4.250.945
Approved Drawing , T.4.121.350
QCI GAM-QCR-QAC-GTL-037
(T.4.318.598) I S S S
4.2.3 Check condition of flange faces, Gaskets and fixings
100%
T.4.250.944; T.4.250.945 T.4.186.019
Approved Drawing , T.4.121.350 DEP
31.38.01.31;T.13.376.796E QCI
GAM-QCR-QAC-GTL-142 (T.4.318.600)
I S S S
4.2.4 Cleanliness (FSI) 100%
T.4.250.944; T.4.250.945;T.13.377.360
T.4.186.019
DEP 70.10.70.11,
T.4.121.350;Vendor Instructions Manual
FSI GAM-QCR-QAC-GTL-070
(T.4.318.599) I W S S
4.2.5 Final bolting-up/torqueing 100% T.4.250.897,T.4.250.944;
T.13.377.360
DEP34.28.00.31,
T.13.376.351G,T.4.121.350 QCI
GAM-QCR-QAC-GTL-041 (T.4.318.598)
I S/R S S
4.2.6 closure of Manholes 100%
T.4.250.944; T.4.250.945 T.4.186.019
T.13.376.351G, T.4.121.350 QCI VISUAL I R R R
5.5 Main steam duct and Risers (Steam Distribution Manifold)
5.5.1 Cleanliness(FSI) 100% T.4.250.930 T.13.377.360
T.4.121.350,
DEP 70.10.80.11;Vendor Specifications
FSI GAM-QCR-QAC-GTL-070
(T.4.318.599) H W W S
5.5.2 Closure of Man Holes 100% T.4.250.944,T.4.250.945 Vendor Specifications;
Approved Drawings;T.4.121.350
QCI VISUAL I S S S
5.5.3 Check of Duct fixed & Sliding supports, Expansion
100% T.4.250.944,T.4.250.945 DEP 31.38.01.31
T.13.376.796E QCI
GAM-QCR-QAC-GTL-094 (T.4.318.599)
H I I W
4.4 pumps
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-034
ITP FOR INSTALLATION OF AIR COOLED
STEAM CONDENSER DATE: DATE: 20.01.2009 REV. E
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR-(SPX)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test
Frequency Reference Document Acceptance Criteria
Responsible Party
Verifying Documents S A x C
T-4.234.075 Rev. A Page 14 of 18
4.4.1 Foundations/Grout 100%
T.4.250.944,T.4.250.945, T.4.186.019
Approved drawings; DEP 31.29.00.10,Vendor
SpecificationsT.4.121.350 QCI
GAM-QCR-QAC-GTL-120 (T.4.318.600)
H I S/R S
4.4.2 Installation fixation 100%
T.4.250.944,T.4.250.945, T.4.186.019
Approved drawings; DEP 31.29.00.10,Vendor
SpecificationsT.4.121.350 QCI
GAM-QCR-QAC-GTL-120 (T.4.318.600)
I S S S
4.4.3 Alignment/elevation
(Pump-Motor) 100%
T.4.250.944,T.4.250.945, T.13.377.360 T.4.186.019
Approved drawings; DEP 31.29.00.10,Vendor
SpecificationsT.4.121.350 QCI
GAM-QCR-QAC-GTL-115 (T.4.318.600)
H I S/R S
4.4.4 Check Condition of flange
faces, Gaskets and fixings 100%
T.4.250.944,T.4.250.945, T.4.186.019
Approved drawings; DEP 31.29.00.10,Vendor
SpecificationsT.4.121.350 QCI
GAM-QCR-QAC-GTL-142 (T.4.318.600)
I I S S
4.4.5 Internal cleanliness(FSI) 100%
T.4.250.944,T.4.250.945, T.13.377.360 T.4.186.019
Approved drawings; DEP 31.29.00.10,Vendor
SpecificationsT.4.121.350
DEP 70.10.80.11
FSI GAM-QCR-QAC-GTL-070
(T.4.318.599) H I S S
4.4.6 Final Bolting up
/torqueing 100%
T.4.250.944,T.4.250.945,
T.13.377.360 T.4.186.019
Approved drawings; DEP 31.29.00.10,Vendor
SpecificationsT.4.121.350 QCI
GAM-QCR-QAC-GTL-041 (T.4.318.598)
I I W/R S
4.4.7 First oil fill pump 100%
T.4.250.944,T.4.250.945, T.4.186.019
Approved drawings; Vendor SpecificationsT.4.121.350
QCI Check oil Type/level H I W/R S
4.5 Vacuum Equipments
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-034
ITP FOR INSTALLATION OF AIR COOLED
STEAM CONDENSER DATE: DATE: 20.01.2009 REV. E
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR-(SPX)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test
Frequency Reference Document Acceptance Criteria
Responsible Party
Verifying Documents S A x C
T-4.234.075 Rev. A Page 15 of 18
4.5.1 Foundations 100% T.4.250.944,T.4.250.945,
Approved drawings; DEP 31.29.00.10,Vendor
SpecificationsT.4.121.350 QCI
GAM-QCR-QAC-GTL-037 (T.4.318.598)
H S/R S/R S
4.5.2 Installation fixation 100% T.4.250.944,T.4.250.945,
Approved drawings; DEP 31.29.00.10,Vendor
SpecificationsT.4.121.350 QCI
GAM-QCR-QAC-GTL-037 (T.4.318.598)
I W/R
W/R S
4.5.3 Final Bolting up
/torqueing 100%
T.4.250.944,T.4.250.945,
T.13.377.360
Approved drawings; DEP 31.29.00.10,Vendor
SpecificationsT.4.121.350 QCI
GAM-QCR-QAC-GTL-041 (T.4.318.598)
I W/R
W/R S
5.0 Air cooled Condenser Ducting
5.1 Turbine exhaust steam duct/Risers & expansion Bellows
5.1.1 Foundations
(turbine exhaust steam duct) 100% T.4.250.944,T.4.250.945
Approved drawings; Vendor SpecificationsT.4.121.350
QCI GAM-QCR-QAC-GTL-113
(T.4.318.599) H R R S
5.2 Main steam Duct
5.2.1
Preassembly Positioning
(Horizontal part exhaust duct)
(Vertical riser + V-piece)
100% T.4.250.944,T.4.250.945 Approved drawings; Vendor SpecificationsT.4.121.350
QCI GAM-QCR-QAC-GTL-115
(T.4.318.600) I S S S
5.2.2 Installation/Positioning
(Expansion bellow-Hinge) 100% T.4.250.944,T.4.250.945
Approved drawings;, Vendor SpecificationsT.4.121.350
QCI GAM-QCR-QAC-GTL-115
(T.4.318.600) I S S S
5.2.3 Alignment to
turbine/elevation 100%
T.4.250.944,T.4.250.945 T.13.377.360
Approved drawings;, Vendor SpecificationsT.4.121.350
QCI GAM-QCR-QAC-GTL-115
(T.4.318.600) H I I
S/R
5.2.4 Bolting up /torqueing 100% T.4.250.945;T.13.377.360 Approved drawings;, Vendor
SpecificationsT.4.121.350 QCI
GAM-QCR-QAC-GTL-041 (T.4.318.598)
I S S S
5.4 Risers
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-034
ITP FOR INSTALLATION OF AIR COOLED
STEAM CONDENSER DATE: DATE: 20.01.2009 REV. E
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR-(SPX)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test
Frequency Reference Document Acceptance Criteria
Responsible Party
Verifying Documents S A x C
T-4.234.075 Rev. A Page 16 of 18
5.4.1 Pre assembly(risers-expansion bellows)
100% T.4.250.944 Approved drawings; Vendor SpecificationsT.4.121.350
QCI GAM-QCR-QAC-GTL-037
(T.4.318.598) I S S S
5.4.2 Installation (Risers) 100% T.4.250.944 Approved drawings; Vendor SpecificationsT.4.121.350
QCI GAM-QCR-QAC-GTL-037
(T.4.318.598) I S S S
5.4.3 welding 100% T.4.250.938
ASME B 31.3;DEP 31.38.01.11
T.13.377.441;T.13.376.796E
QCI PQR,WPS,WELDER ID I S/R S/R S
5.4.4 Visual Examination of Welds 100% T.4.250.931
ASME B 31.3;DEP 31.38.01.11
T.13.377.441;T.13.376.796E
QCI GAM-QCR-QAC-GTL-161
(T.4.318.600) I S/R S/R S
5.4.5 NDT 100% NDT PROCEDURE
T.13.377.360 DEP 31.38.01.31;ASME B
31.3,T.13.376.796E QCI NDT REPORTS I R R R
5.4.6 Safety Valves (If any) 100% T.4.250.918 T.13.377.360 DEP 31.38.01.31
T.13.376.796E QCI
GAM-QCR-QAC-GTL-091 (T.4.318.599)
I S S S
5.4.7 Final Bolting up /torqueing 100% T.4.250.897 Approved drawings;DEP
31.29.00.10,Vendor SpecificationsT.4.121.350
QCI GAM-QCR-QAC-GTL-041
(T.4.318.598) I S/R S/R S
6.0 Interconnecting Piping/Valves
6.1 Inter connecting Piping
6.1.1 Installation Pipe supports Refer ITP 033
6.1.2 Check condition of flange
faces, Gaskets and fixings 100% T.4.250.944; T.4.250.945 T.13.376.351G, T.4.121.350 QCI
GAM-QCR-QAC-GTL-142 (T.4.318.600)
I S S S
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-034
ITP FOR INSTALLATION OF AIR COOLED
STEAM CONDENSER DATE: DATE: 20.01.2009 REV. E
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR-(SPX)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test
Frequency Reference Document Acceptance Criteria
Responsible Party
Verifying Documents S A x C
T-4.234.075 Rev. A Page 17 of 18
6.1.3 Final Bolting up
Torqueing 100% T.4.250.897 T.13.377.360
Vendor Specifications;
T.4.121.350 QCI
GAM-QCR-QAC-GTL-041 (T.4.318.598)
I S/R S/R S
6.1.4
Alignment/elevation/Draining
(Inter connecting piping)+Tack welding
100% T.4.250.944,T.4.250.945
T.13.377.360
DEP 31.38.01.31
T.13.376.796E;T.4.121.350 QCI
GAM-QCR-QAC-GTL-115 (T.4.318.600)
I S/R S/R S
6.1.5 Welding 100% T.4.250.938
ASME B 31.3;DEP 31.38.01.31
T.13.377.441;T.13.376.796E
QCI PQR,WPS,WELDER ID I S/R S/R S
6.1.6 Visual Examination of Welds 100% T.4.250.931 ASME B 31.3; DEP
31.38.01.31;T.13.377.441;T.13.376.796E
QCI GAM-QCR-QAC-GTL-161
(T.4.318.600) I S/R S/R S
6.1.7 NDT 100% NDT PROCEDURE
T.13.377.360 DEP 31.38.01.31;ASME B
31.3,T.13.376.796E QCI NDT REPORTS I R R R
6.1.8 Pressure Testing 100% T.4.250.908 T.13.377.360 Approved Drawings; DEP 31.40.40.38,T.4.121.350
QCI GAM-QCR-QAC-GTL-065
(T.4.318.599) H H H W
6.2 Valves/Strainers
6.2.1 Valve internals in Place 100% T.4.250.918
DEP 31.38.01.31,
T.13.376.815E;Approved Drawings
QCI GAM-QCR-QAC-GTL-091
(T.4.318.599) I R S S
6.2.3 Installation of Valves 100% T.4.250.918
DEP 31.38.01.31,
T.13.376.815E;Approved Drawings
QCI GAM-QCR-QAC-GTL-091
(T.4.318.599) I S S S
C2 ASU PEARL GTL PROJECT
RAS LAFFAN INDUSTRIAL CITY
Document No.: GAM-ITP-QAC-GTL-034
ITP FOR INSTALLATION OF AIR COOLED
STEAM CONDENSER DATE: DATE: 20.01.2009 REV. E
S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. VENDOR-(SPX)
I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)
Item Activity Test
Frequency Reference Document Acceptance Criteria
Responsible Party
Verifying Documents S A x C
T-4.234.075 Rev. A Page 18 of 18
6.2.3 Set Point operation of Relief Valves
100% Deleted
7.0 AIR COOLED STEAM CONDENSER
7.1 Internal check of ACC Steam ducts, piping Cleanliness (FSI)
100% T.4.250.930 T.13.377.360 DEP 70.10.80.11,
T.4.121.350 FSI
GAM-QCR-QAC-GTL-070 (T.4.318.599)
I S I S
7.5 Equipment Box up 100% T-4.250.944 - QCI GAM-QCR-QAC-GTL-133
(T.4.318.600) I W W W
7.4 MC Inspection 100% T-4.250.944 - QCI MC Inspection Reports I S I R
7.8 Handover of Quality Documents
100% Quality Documents T.13.377.555G QCI QC Inspection Reports R R R R