+ All Categories
Home > Documents > 0605 Generator Compliance

0605 Generator Compliance

Date post: 03-Jun-2018
Category:
Upload: fasil-paruvanath
View: 225 times
Download: 0 times
Share this document with a friend

of 32

Transcript
  • 8/12/2019 0605 Generator Compliance

    1/32

    UK Transmission

    Generation Compliance Process

    Ian Nuttall

    Helge UrdalGeneration Dynamic

    Performance

    Operations and Trading

  • 8/12/2019 0605 Generator Compliance

    2/32

  • 8/12/2019 0605 Generator Compliance

    3/32

    Conventional Power StationsSynchronous Machines - Voltage Control

    Field Voltage, EFD

    Excitation

    System

    b

    c

    a

    b

    c

    Automatic

    VoltageRegulator

    a

    The Purpose of the AVR is to Control the Machine

    Terminal Voltage - This is achieved by adjusting the

    setting of the Excitation System which ultimately adjuststhe field voltage seen by the machine

    In the UK it is common practice to use the AVR to fix the

    terminal voltage of the machine and adjust the HV Grid

    Voltage by tapping the Generator Transformer

    Generator

    Transformer

    with Tap

    Synchronous

    Machine

    To Grid

    (400 kV)

    Signals to Measure

    Terminal Voltage, Vt

  • 8/12/2019 0605 Generator Compliance

    4/32

    Conventional Power StationsSynchronous Machines - Frequency Control

    Grid

    (400 kV)

    Power

    SignalFrequency

    Signal

    GovernorControl

    System

    Controlled

    Torque

    Power

    Turbine

    Frequency Control is achieved by the

    governor control system. TheGovernor will sense variations in

    system frequency and adjust the

    power output accordingly.

    The Governor will initiate changes tothe turbine not the Machine.

    Power Output from Machine

    Single Line Representation

    Fuel & Air

    or Steam

    Synchronous

    Machine

  • 8/12/2019 0605 Generator Compliance

    5/32

    Overview of Compliance Process

    Technical appraisal of critical control systems and Analytical /Modelling work

    Compliance Testing

    Life-time compliance / Event Investigation / System monitoring

    Main Aims:

  • 8/12/2019 0605 Generator Compliance

    6/32

    Purpose of Compliance

    Ensure compliance with Regulatory and Commercial documents

    (CUSC, Grid Code, BCA, MSA)

    Avoid connection of plant with inherent design or commissioning defects

    Excitation failures can lead to:

    Pole slipping or Generator instability

    Governor control defects can lead to

    Generators responding erratically with frequency

    Risk of generator trips at times of system stress

  • 8/12/2019 0605 Generator Compliance

    7/32

    Typical Project Timeline

    3 Months

    18 to 24 Months

    6 to 12 Months

    Application

    &

    Offer

    Tender

    &Construction

    Commissioning

    & Approval

    Preliminary Studies

    Functional Spec.

    Offer

    Data Analysis, Model

    Simulation, OperationalNotification Process

    On-site Testing

    Model VerificationModel to Database

    DurationProject Milestones NGC Activities

    Lifetime Ongoing

    Compliance

    System Incident

    Analysis

    Stage

    1

    2

    3

    4

  • 8/12/2019 0605 Generator Compliance

    8/32

    Timeline Stage 1

    Application and Offer

  • 8/12/2019 0605 Generator Compliance

    9/32

    Development of New Technology

    Liase with manufacturers on their plant compliance issues

    Understand changes in technology

    Ensure compliance process evolves to meet changes within the

    industry

    Discuss with developers the compliance issues related to any unusual

    proposals

    Application and Offer

  • 8/12/2019 0605 Generator Compliance

    10/32

    Timeline Stage 2

    Tender and Construction

  • 8/12/2019 0605 Generator Compliance

    11/32

    Technical Appraisal of Generating Plant

    Operational Notification Process

    Discuss compliance issues with project developers

    Ensure any problems are identified and addressed early

    Tender and Construction

  • 8/12/2019 0605 Generator Compliance

    12/32

    Appraisal of Excitation Control Systems

    Excitation Control System Specification to meet the Grid Code and

    Bilateral Agreement

    Ceiling voltage

    Exciter type (static or brushless)

    With or without Power System Stabiliser (PSS) Manufacturers PSS tuning study results

  • 8/12/2019 0605 Generator Compliance

    13/32

    Appraisal of Governor Control Systems

    Governor System / Module Load Controller details

    Droop settings

    Target frequency setting facility

    Module frequency operating range 47 to 52Hz

    Governor deadband

    Load rejection / island mode operation

    Compliance with CC6.3.3 / BC3.7.2

  • 8/12/2019 0605 Generator Compliance

    14/32

    Timeline Stage 3

    Commissioning and Approval

  • 8/12/2019 0605 Generator Compliance

    15/32

    Compliance Testing

    Commissioning and Approval

  • 8/12/2019 0605 Generator Compliance

    16/32

    Compliance Testing

    Why do we need to test?

    To confirm that what is expected from the design is put in place

    .... and the right place! Are the systems working correctly ?

    Verify the stability and performance of the control systems

    Check the model supplied accurately represents the plant as connected

  • 8/12/2019 0605 Generator Compliance

    17/32

    Typical Excitation System Tests

    Open circuit and full load step responses

    Step test with and without power system stabiliser if applicable

    On load power spectrum analysis for PSS applications

    Under and Over-excitation limiter functionality

  • 8/12/2019 0605 Generator Compliance

    18/32

    Typical Governor System Tests

    On load frequency injections at a number of loading points to

    determine;

    Control System robustness

    Governor deadband and droop

    CC6.3.3 functionality Plant frequency response capability data to populate a MSA frequency

    response matrix

    Load rejection tests to determine the capability to regulate frequency ina power island

  • 8/12/2019 0605 Generator Compliance

    19/32

    Timeline Stage 4

    Ongoing Compliance

  • 8/12/2019 0605 Generator Compliance

    20/32

    When do we get involved ?

    Event based analysis of performance

    Requests to changes in machines response capability

    Changes to key performance affecting components

    Ongoing Compliance

    E t A l i

  • 8/12/2019 0605 Generator Compliance

    21/32

    Event Analysis

    Investigate events of non-compliance or unusual plant behaviour

    Check responsive plant against contract for frequency events outside

    operational limits

    For significant frequency deviations conduct a review against CC6.3.3 /BC3.7.2 requirements

    E t A l i l (R )

  • 8/12/2019 0605 Generator Compliance

    22/32

    Good Response Performance

    80%

    85%

    90%

    95%

    100%

    105%

    0 5 10 15 20 25 30

    TIME (mins)

    G

    ENSETOUTPUT(%

    ofRegCap)

    49.8

    49.9

    50

    50.1

    50.2

    50.3

    FREQUENCY

    (Hz)

    CAPPED COMMITTED LEVEL (MW ) MEL FREQUENCY

    Event Analysis example (Response)

    Good Response Performance

    80%

    85%

    90%

    95%

    100%

    105%

    0 5 10 15 20 25 30

    TIME (mins)

    GENSETOUTPUT(%

    ofRegCap)

    49.8

    49.9

    50

    50.1

    50.2

    50.3

    FREQUENCY(Hz)

    CAPPED COMMITTED LEVEL (MW ) EXPECTED RESPONSE (MW ) MEL FREQUENCY

    Good Response Performance

    80%

    85%

    90%

    95%

    100%

    105%

    0 5 10 15 20 25 30

    TIME (mins)

    G

    ENSETOUTPUT(%

    ofRegCap)

    49.8

    49.9

    50

    50.1

    50.2

    50.3

    FREQUENCY

    (Hz)

    GENSET OUTPUT CAPPED COMMITTED LEVEL (MW ) EXPECTED RESPONSE (MW ) MEL FREQUENCY

    E t A l i l (R )

  • 8/12/2019 0605 Generator Compliance

    23/32

    Event Analysis example (Response)

    Poor Response Perfomance

    80%

    85%

    90%

    95%

    100%

    105%

    0 5 10 15 20 25 30

    TIME (mins)

    G

    ENSETOUTPUT(%

    ofRegCap)

    49.8

    49.9

    50

    50.1

    50.2

    50.3

    FREQUENCY

    (Hz)

    GENSET OUTPUT CAPPED COMMITTED LEVEL (MW ) EXPECTED RESPONSE (MW ) MEL FREQUENCY

    E t A l i l (O ill ti )

  • 8/12/2019 0605 Generator Compliance

    24/32

    Event Analysis example (Oscillations)

    Example of unexpected oscillations

    40%

    45%

    50%

    55%

    60%

    65%

    70%

    0 5 10 15 20 25 30

    TIME (mins)

    GENSETPOWER(%RegCap)

    49.8

    49.9

    50

    50.1

    50.2

    50.3

    50.4

    FREQUENCY(Hz)

    GENSET OUTPUT CAPPED COMMITTED LEVEL (MW ) SEL FREQUENCY

    Summary

  • 8/12/2019 0605 Generator Compliance

    25/32

    Summary

    Our compliance process and the team aims are to:

    work with Generators to achieve an understood compliance position

    adopt a pragmatic approach to confirming compliance

    witness compliance tests to confirm the expected performance

    investigate events which could indicate failure of plant to maintain

    compliance

    Maintaining compliance throughout the plant

    lifetime is vital to transmission system integrity

    A new Era

  • 8/12/2019 0605 Generator Compliance

    26/32

    A new Era

    World of Wind - What difference does it make?

    Compliance of Power Park Modules

  • 8/12/2019 0605 Generator Compliance

    27/32

    Compliance of Power Park Modules

    Key Issues

    Compliance task - different requirements & project characteristics

    Process reviewed

    Guidance Notes for Power Park Developers

    Help available to get started - site specific documentation

    Your feedback on process awaited

    Compliance task

  • 8/12/2019 0605 Generator Compliance

    28/32

    Compliance task

    Different requirements - New issue of Grid Code

    Different project characteristics

    Thermal Power station - few large synchronous plant

    Power Parks - many asynchronous generators

    Different types of asynchronous generators

    Extensive use of power electronics

    New Grid Code - 1 June 2005

    web address < www.nationalgridinfo.co.uk/grid_code/index.html >

    Requirements based on Point of Connection - variations size & location

    New topic - Fault Ride Through

    Projects characteristics

    Size range extended from 5 MW to 1000MW+

    Volume of projects - 10 fold increase.

    Compliance Process review

  • 8/12/2019 0605 Generator Compliance

    29/32

    Compliance Process review

    Fresh look at process starting with objectives. For:

    System Operator / Transmission Owner

    Generator / Developer

    Contractor / manufacturer

    Compliance moved from Generator Terminals to Point of Connection

    Generic Review of Type information

    Strong emphasis on self certification Minimise expensive site activity

    Less predictable source of power

    Consideration of part move to remote access to live data during testing

    Guidance Notes for Power Park Developers

  • 8/12/2019 0605 Generator Compliance

    30/32

    Guidance Notes for Power Park Developers

    Guidance notes on how to demonstrate compliance - now issued

    web address < www.nationalgridinfo.co.uk/grid_code/mn_associated.html >

    Intended to provide Project Managers with clarity

    Practical methodology to save resources for 3 interest groups by maximising reuse of compliance material

    providing a clear path to Operational Notification

    Uniform compliance review by standardised summary & compliance sheets

    Help available to get you started

    project specific compliance sheets - removes N/A requirements

    Compliance

  • 8/12/2019 0605 Generator Compliance

    31/32

    Compliance

    .... and at sea

    On land .

    Any questions about Compliance

  • 8/12/2019 0605 Generator Compliance

    32/32

    Any questions about Compliance

    for Generators - Contact us

    We will both be around through lunch

    In NGT House in Warwick

    By telephone to the team phone on (01926) 654601


Recommended