Date post: | 14-Feb-2017 |
Category: |
Engineering |
Upload: | dr-fereidoun-dejahang |
View: | 44 times |
Download: | 0 times |
NETWORK PROGRAMMING
PTN=PROJECT NETWORK TECHNIQUE
TWO FAMILIESACTIVITY ON NODE EG and
ACTIVITY ON ARROW A.O.A
NETWORK PROGRAMMING
A DUMMY IS USED –IT IS ALWAYS SHOWN AS DOTTED LINE
Total FloatThe total amount by which an activity can be extended or
delayed without affecting the total project time (TPT)CalculationLatest Time Finish Event (LTFE) – Earliest Time Start
Event (ETSE) –Duration OrThe total amount by which an activity can be extended or
delayed without affecting succeeding (subsequent) activities or the Total Project Time.
NETWORK PROGRAMMING
2
NETWORK PROGRAMMINGEvery activity most be uniquely identified-
4
A
B
INCORRECT
Dummy activities and additional events will enable correct identification:
2
3
4
A=2-4B=3-4A
B
Dummy=2-3
A=2-4B=2-4
I J
NETWORK PROGRAMMING
Building up a network The time flow from left to right The start and end of each activity has an
event Activities are shown by arrows activity on
arrow networks Events are given numeric or ALFA
numeric number to identify
NETWORK PROGRAMMING
Head node numbers are higher than tail node numbers
Tail node is known as ‘I’ number Head nude is known as ‘j’ number Together they are shown as I J An event is a point where activities start or
end. All activities terminating at an event must be
completed before the next activity starts.
NETWORK PROGRAMMING
2 4
3
A=2-4B=2-3Dummy=3-4The dummy always have zero duration
I J
NO END DANGLES PERMITTEDNO LOOP PERMITTED
NOTE:
IF C AND D ARE BOTH DEPENDANTS ON A, AND D IS DEPENDANT ON B, ISNETWORK 1 CORRECT OR NETWORK 2 ?
NETWORK PROGRAMMINGNO END DANGLES PERMITTEDNO LOOP PERMITTED
NOTE:
IF C AND D ARE BOTH DEPENDANTS ON A, AND D IS DEPENDANT ON B, ISNETWORK 1 CORRECT OR NETWORK 2 ?
NETWORK 1A
B
C
D
Incorrect-because D id dependant on A and B,and C is dependant on A and B
NETWORK PROGRAMMING
2
2
A
B
C
D
zero duration
NETWORK 2
CORRECT DIAGRAM-A ZERO DURATION DUMMY IS INTRODUCEDThe start of D could be delayed for a specific time after the completion of A by putting a time duration on thedummy(ie a time transient dummy).
Note-there are 3 types of dummies:
1-Identical2-logical3-Transit
NETWORK PROGRAMMINGNetwork programming-Splitting work into section
Design a Network programming for an excavation, framework and concreting
One sectionExCAVATION FMWK CONCRETE
Two SectionsEXC. HALF FMWK HALF CONC HALF
EXC. HALF FMWK HALF CONC HALF
NETWORK PROGRAMMINGEXC. HALF FMWK HALF CONC HALF
EXC. HALF FMWK HALF CONC. HALF
Three Sections
START EXC. START FMWK START CONC.
CONTINUE EXC.CONTINUE FMWK CONTINUE CONC.
COMPLETE EXC. COMPLETE FMWKCOMPLETE CONC
NETWORK PROGRAMMINGNetwork Programming
The steps in producing a network are:
A) Listing the activitiesB) Producing a network showing the logical relationship
between activitiesc) Assessing the duration of each activitiesD) Determining the start and finish times of each
activities and the available floatE) Determining the resources requiredF) Produce the schedule
NETWORK PROGRAMMING
Ask yourself1) Which activity must be completed
before the next activity can start?2) Which activity can not start until this
activity is complete?3) Which activities have no logical
relationship with this activity and can not start at the same time?
NETWORK PROGRAMMING
Prepare a Network Diagram for the above project and reduce the duration of the project by at least 5 weeks.
NETWORK PROGRAMMING
2
7 0
Sequential Activities
Start
0 10 16 36 weeks
0 10 16 36
0 0
A -START A-CONTINUE A-FINISH
B -START B-CONTINUE B-FINISH
C -START C-CONTINUE C-FINISH
3 3 8 8
8 8 10 15
15 15 21 2128 28
3 5 2
2 2
6 7
21-2=19
21-6=15
GOING BACKWARD
GOING BACKWARD
15-0=15
GOING BACKWARD
NETWORK PROGRAMMING
Try this question- As a project manager you are asked to run a trench in three section prepare a networkdiagram to show total time, and a bar chart for the client.
MH-1 MH-2 MH-3
sewer
NETWORK PROGRAMMING
Start
Excavate section -1 Pipe bed section- 1 Lay pipe section-1 Back fill section- 1
Excavate section- 2 Pipe bed section- 2 Lay pipe section-2 Back fill section -2
Excavate section 3 Pipe bed section 3 Lay pipe section 3
3 1 1
Back fill section-3
3 1 1 2
4 6
NETWORK PROGRAMMING
20 30 40
50 60 70
80 90 100
110
2 2 3 5 4 6
55 76 7 8
88 99
10 10
3 1 1 2
3 1 1
2
12 12
2 2 2
0 1 1 1
0 0 0
0
NETWORK PROGRAMMING
ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 12
10 20
20 50
50 80
20 30
50 60
80 90
30 40
60 70
90 100
40 70
70 100
100 110
float
float
float
float
float
float
1
3 4
6
5
7
2
du=12crash time(10)
du=10crash time(8)
du=13crash time(10)
du=8crash time(5)
du=15crash time(15)
du=10crash time(18)
du=11crash time(8)
1
3 4
6
5
33 3323 23
0 0
25 38
46 46
7
2
12 12
10 23
du=12crash time(10)
du=10crash time(8)
du=13crash time(10)
du=8crash time(5)
du=15crash time(15)
du=10crash time(18)
du=11crash time(8)
A
2
B
4
D2
C6
E4
F6
G8
K
10
H
5
P
8
J3
L1
N
M3
Q
7
S
U
1
T6
V
7W
3
X
10
AA
5
BB
Y
7
CC9
EE4
FF
12
GG14
HH
6
JJ
7
R5
DD
Z
1 2
12
14 17 19
13
15
16
18
3
5
4 9
6
11
7
10
21 22
20
S
8
DU=2
DU=4
DU=2
DU=6DU=8 DU=10
DU=3
DU=5
DU=1
DU=7DU=8DU=6
DU=9DU=7
DU=1
DU=5
DU=
DU=4
DU=6
DU=14
DU=12DU=10
A
B
D
F
G
K
C P Q
DU=6
DU=8
DU=3
DU=7
DU=5
UT
V
W
Y
H
L
CC
HH
EE
AA
FFX
GG
0 0
2 2
8 8
6 21
8 2914 35
DU=4E
19 42
19 43
16 16 26 26
26 48
38 38
DD
BB
22 43
32 5319 52
12 38J
20 46
32 53
R M
65 65
58 5826 49
52 52