+ All Categories
Home > Documents > 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5...

0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5...

Date post: 16-Oct-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
65
Point Beach Nuclear Plant PLANT CHANGE INITIATION PLANT MODIFICATION/MINOR PLANT CHANGE NO.:t 02-029 WO# INITIATION Title: AUX FEED MINI RECIRC SAFETY UPGRADE I REMOVE AF-117 INTERNALS 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE SAFETY FUNCTION OF THE AUXILIARY FEEDWATER MINI. RECIRC AOVS TO HAVE A SAFETY FUNCTION TO OPEN Proposed Scope: AUX FEED MINI I Initiated By: REMOVE INTERNALS OF AF-117 TO PREVENT COMMON MODE FAILURE OF RECIRC LINE Rob Chapman Date: 8/20/2002 CHANGE DETERMINATION Is the change Temporary? Is this a Setpoint Only change? Is this an Equivalent change? Document change only? Does previous evaluation encompass change? Commercial Facility Change? For Commercial Facility Change Only: Document Updates? Is this small scope? YES NO x x ___ x X X x If YES go to NP 7.3.1 Temp Mod If YES go to NP 7.3.8 Setpoints If YES go to NP 9.3.3 SPEED If YES.determine if previously evaluated If YES proceed with document changes If YES, determine if document updates are required. If YES contact design supervisor. If NO proceed outside of Engineering process controls. Document below. X If YES perform Minor Plant Change If NO, it is a Plant Modification. Go to EAC for review and approval (NP 7.2.1) If it is determined that this is not a Plant Change or Modification, document and/or attach justification. Also, attach document update checklist if necessary. ENGINEERING CHANGE PROCESS TO USE: Minor Plant PBF-1605a Revision 0 10/02101 Page I of 2
Transcript
Page 1: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant PLANT CHANGE INITIATION

PLANT MODIFICATION/MINOR PLANT CHANGE NO.:t 02-029 WO#

INITIATION

Title: AUX FEED MINI RECIRC SAFETY UPGRADE I REMOVE AF-117 INTERNALS

0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR:

Project Objectives: UPGRADE THE SAFETY FUNCTION OF THE AUXILIARY FEEDWATER MINI.

RECIRC AOVS TO HAVE A SAFETY FUNCTION TO OPEN

Proposed Scope:

AUX FEED MINI I

Initiated By:

REMOVE INTERNALS OF AF-117 TO PREVENT COMMON MODE FAILURE OF

RECIRC LINE

Rob Chapman Date: 8/20/2002

CHANGE DETERMINATION

Is the change Temporary?

Is this a Setpoint Only change?

Is this an Equivalent change?

Document change only?

Does previous evaluation encompass change?

Commercial Facility Change?

For Commercial Facility Change Only: Document Updates?

Is this small scope?

YES NO

x

x

___ x

X

X

x

If YES go to NP 7.3.1 Temp Mod

If YES go to NP 7.3.8 Setpoints

If YES go to NP 9.3.3 SPEED

If YES.determine if previously evaluated

If YES proceed with document changes

If YES, determine if document updates are required.

If YES contact design supervisor. If NO proceed outside of Engineering process controls. Document below.

X If YES perform Minor Plant Change If NO, it is a Plant Modification. Go to EAC for review and approval (NP 7.2.1)

If it is determined that this is not a Plant Change or Modification, document and/or attach justification. Also, attach document update checklist if necessary.

ENGINEERING CHANGE PROCESS TO USE:

Minor Plant

PBF-1605a Revision 0 10/02101 Page I of 2

Page 2: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Temporary Modification - See NP 7.3.1.

A generally non-recurring physical change to operational plant systems, components, or equipment that exists for a short duration.

Equivalent Change - See NP 9.3.3. A hardware change that results in the installation of an item, not identical to the original item, that does not result in a change to those bounded technical requirements that 1) ensure performance of design bases functions, or 2) ensure compliance with the plant licensing basis of either the item(s) or applicable interfaces.

Commercial Facility Change - See NP 7.2.6. Must answer NO to the following:

S1. Does the change impact licensing basis? 2. Will it impact the Electrical Distribution System? 3. Will the change affect HVAC or air systems within the Plant? 4. Does the change interface with existing fire suppression/detection systems or introduce any new

combustibles? 5. Will the change impact Emergency Planning? 6. Have a seismic interaction with Plant Equipment? 7. Will the change benefit from the Design Change Process?

PBF-1605a Reviston 0 10/02/01 Page 2 of 2

i

Page 3: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant PLANT DESIGN CHANGE CHECKLIST PLANT MODIFICATION/MINOR PLANT CHANGE NO.: 02-029

Title: AUX FEED MINI RECIRC SAFETY UPGRADE / REMOVE AF-117 INTERNALS

DESIGN SUPERVISOR

Design Controls and Project Controls: (Ref. NP 7.2.1, Commentary, for completion of this section.)

Check Applicable Design Controls: Clarifications/Basis:

0] Design Input Checklist (PBF-1584)

0] DUC (PBF-1606)

0] Design Verification Notice (PBF-1583)

.] Calculations

0] Design Documentation (PBF-1585), or equivalent

0] Design Change In Progress DCNs

El Engineering Change Requests

El Specifications

El El

Check

13

El El El El

Applicable Project Controls:

Modification Team Required (indicate minimum groups to request)

Conceptual Design Package Required

Budget Design Project (Impact) Number

Detailed Project Schedule

IWP Required

Assigned Modification Engineer:

Design Supervisor:

Clarifications/Basis:

Roy Chapman

Date: 94/i07

PBF-1605 Revision 8 06/12/02 Reference(s): NP 7.2.1. PBF-1583. PBF-15S4

NP7 2.2. PBF-1585. PBF-1606

(7.

Pagce I of 4

Page 4: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant PLANT DESIGN CHANGE CHECKLIST PLANT MODIFICATION/MIOR PLANT CHANGE NO.: 02-029

CONCEPTUAL DESCRIPTION/REFERENCE INFORMATION (IF APPLICABLE)

GROUP HEAD CONCEPTUAL DESIGN REVIEW AND ACCEPTANCE [Check here if not required: Z] Review conceptual design. Attach comments on NPBU Document Review Comment Sheet (PBF-1622 or equivalent)

Grou2 Acceptance Signature Date Comments

Radiation Protection -_1= None D- Attached

Fire Protection E-"] None El Attached

Installing Organization [-_ None [-] Attached

_-"_ None E1 Attached

"El None R- Attached

__-E None R- Attached

[-_ None E] Attached

DesiEn Supervisor E-l None E-] Attached

PBF-1605

Revision 8 06/12102 Reference(s). NP 7.2.1. PBF-1583, PBF-1584 NP722.PBF-1535 PBF-1606

SL

Page 2 of 4

Page 5: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant PLANT DESIGN CHANGE CHECKLIST PLANT MODIFCATION/MINOR PL CHAGE NO.: 02-029

TRAINING AND PRA GROUP NOTIFICATION

Training and PRA group notified of modification. TWR#: 012. 4o

Modification Engineer: "-o OZc../ • 4 "A- Date: - $ .

FINAL DESIGN REVIEWS -Review final design. Attach comments on Document Review Comment Sheet (PBF-1622 or equivalent)

Group Acceptance Signature Date Comments

Oprtin None ['] Attached

Fire Protection Engineer 9-6 7 iDýoe E] Attached

Mechanical Maintenance VI'M,1 1112None ~IAttached

Systems Engineering [DNone ElAttached El None El Attached

ER None El Attached

E- None Attached

Tech. Review _ _ _ _ _ _ _re. _ _ _ _d--~

INDEPENDENT REVIEW OF INSTALLATION DOCUMENTS (IWP or Work Order Plan) List all IWP's and WO's

used for installation

IWP's/WO#(s) WO 0212107

All design and licensing requirements have been incorporated in the installation and testing document(s).

Reviewer: L-- k - _ _ _ _ _ _ _ Date: 9 - -Oý

RELEASE FOR INSTALLATION All design controls have been properly implemented and the project has been appropriately reviewed. All necessary documents

are approved. This design is released for installation. Comments regarding release of this design are noted below:

Design Supervisor: Date: 44oz,

COMMENTS

PBF-1605 Revision 8 06/12/02 Reference(s)' NP 7.2.1. PBF-1583, PBF-1584

NP 7.2 2. PBF-1585. PBF-1606Page 3 of 4

I,24ý,, .4ýý,/---4

k,,.o- --- __

Page 6: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

PB F- 1605 Revision 8 06/12/02 Reference(s): NP 7.2.1. PBF-1583. PBF-1584

NP 7.2 2. PBF-1585, PBF-1606

Point Beach Nuclear Plant PLANT DESIGN CHANGE CHECKLIST PLANT MODIFICATION1MINOR PLANT CHANGE NO.: 02-029

ACCEPTANCE

Plant modification is installed, tested, and all documents required for acceptance are complete.

Modification Engineer: 9o C ,,,.,,. - Date: 01i \0-o

CLOSEOUT

Plant modification is complete, including submittal of all document updates in the Document Update Checklist (PBF-1606). Reference change tracking numbers on PBF-1606 where appropriate (DCN numbers, FCR numbers, etc.).

Modification Engineer: Date:

Design Supervisor: Date:

NUCLEAR INFORMATION MANAGEMENT Microfilm the entire modification package.

Page 4 of 4

Page 7: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

FINAL DESIGN DESCRIPTION MR 02-029

t September 12, 2002 AUX FEED MINI RECIRC SAFETY UPGRADE / Revision 1 REMOVE AF-1 17 INTERNALS UNIT 0

Purpose

As committed to the NRC by letter NRC 2002-0068, the Auxiliary Feedwater minimum flow recirculation AOVs will be upgraded to have a safety-related function to open. This will provide an additional level of safety with regards to the potential common mode AFW pump failure originally identified by CR 01-3595 and LER 26612001005-00. This modification will track all updates required to facilitate this change in safety classification.

Scope

MR 02-029 will remove the internals for AF-117 to prevent a common mode active failure of all Auxiliary Feedwater pumps due to an isolation of the mini-recirculation line. This valve is non-QA, non-Seismic, non ASME class. Significant improvement in core damage probability (CDP) can be achieved by preventing this check valve from failing to open, and removing the internals is the best way to achieve this.

MR 02-029 will document the upgraded design basis of the Auxiliary Feedwater minimum flow recirculation AOVs (1/2AF-4002, AF-4007, AF-4014) and piping to support the safety-related function to provide a flow path for the AFW pumps to prevent overheating and hydraulic instabilities.

Desian Inputs

" PBNP Licensing Basis:

TS 3.7.5 - Auxiliary Feedwater System FSAR 9.7 - Instrument Air I Service Air FSAR 10.2 - Auxiliary Feedwater System FPER 5.2.2 - Safe Shutdown Systems and Equipment SSAR 2.3.1.4 - Reactor Heat Removal Function LER 266/2001-005-00 50.59 SCR 2002-0010-01

"* Correspondence:

Letter NPM 2002-0228, Dated 4/25/2002, Designation of Backup Pneumatics for AFW Mini-Recirculation Valves as Safety-Related

Letter NRC 2002-0068, Dated 8/1212002, Reply to a Notice of Violation (EA-02-031)

"* Corrective Action:

CR 01-2278 CR 01-3595

"* Applicable Codes:

USAS B31.1 - 1967, Power Piping

"* Permanent Drawings:

BECH M-217 Sh. 1 - Auxiliary Feedwater BECH P-103 -Emergency Feedwater Pumps to Main Feedwater Lines 4" & 3" DB-3

Page 1 of 5

Page 8: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

FINAL DESIGN DESCRIPTION MR 02-029 September 12, 2002

AUX FEED MINI RECIRC SAFETY UPGRADE / Revision I REMOVE AF-1 17 INTERNALS UNIT 0

BECH P-159 - Aux Feedwater from Condensate Return & Pump Recirc to CST 6" & 3" JG-4

ALOYCO A-46037 - #376-SP 150# Swing Check Valve

Plant Modifications:

MR 88-099 (*A/*B/*C/*D) MR 01-144 MR 02-001

Design Description and Analysis

Background

CR 01-2278, CR 01-3595 and LER 266/2001-005-00 identified an issue that could cause a common mode failure of all Auxiliary Feedwater pumps. If an accident or event has occurred that has led to the loss of instrument air, then the AFW pump minimum recirculation control valves 1/2AF-4002 for 1/2P-29, AF-4007 for P-38A, and AF-4014 for P-38B will all fail closed. During this event, it will become necessary for operations to reduce auxiliary feedwater flow to control steam generator level and prevent overfilling, especially if all four auxiliary feedwater pumps are feeding the steam generators (which is likely in a Loss of Offsite Power event). Typically this is done by throttling down AFW pump flow as opposed to securing the pumps. If care is not taken to ensure that the minimum recirculation valves are open when the pump discharg; valves are shut, then the pumps will dead head and fail in a very short time due to overheating. After discovery of this issue, guidance was added to EOP 0, EOP 0.1, ECA 0.0, and AOP 5B to direct operations to verify adequate pump flow if instrument air has been lost before reducing flow to the steam generators, or to stop the pump.

The minimum recirculation flow AOVs (1/2AF-4002, AF-4007, AF-40r4) have a safety-related function to close to ensure adequate AFW flow to the steam generators during several events, with a seismic induced Loss of Normal Feedwater (LONF) and an Anticipated Transient Without Scram (ATWS) being the most limiting events. FSAR Section 10.2 also discusses the effects of a failure of a mini-recirc AOV to close and gives the flow that is diverted from the steam generators through the recirculation line as limited by the flow restricting orifices (1/2RO-4003, RO4008, RO-4015).

These mini-flow recirc AOVs have never been classified as having a safety-related function to open to prevent pump damage. This has been described as a non-safety related function only, since the AFW pumps will always have

forward flow to the steam generators on auto-start. These recirculation lines are most frequently utilized during pump testing, and on unit startup when the required flow is less than what is recommended for AFW pump cooling.

These recirculation line AOVs have an augmented quality function to be opened for Appendix R fires to support AFW pump operation, per SSAR 2.3.1.4.

Following the discovery of the potential common mode failure, backup pneumatic sources were installed for all

minimum flow recirculation valves by MR 01-144 and MR 02-001 to provide additional assurance that the auxiliary feedwater pumps would not be damaged on a loss of instrument air. These modifications were an enhancement that reduced the core damage probability from a loss of instrument air and increased the time for an operator to take

manual action to override the fail-closed action and open the valves. Instrument air accumulator tanks were

installed by MR 02-001 for the 1/2P-29 mini-flow recirc valves (1/2AF-4002), and the existing nitrogen backup

system for the MDAFP discharge valves (AF-4012/4019) was tied in by MR 01-144 for the P-38A/B recirc valves

(AF-4007, AF-4014). These backup pneumatic sources will provide a safety-related motive force for 2 hours for the

TDAFP recirc valves (I/2AF-4002), and for 90 minutes for the MDAFP recirc valves (AF-4007/4014).

These modifications were installed primarily for the purpose of risk reduction, and the components installed were

not originally classified as safety-related for MR 02-001. However, safety related controls were applied to the

Parge 2 of 5

Page 9: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

FINAL DESIGN DESCRIPTION MR 02-029 September 12,2002

AUX FEEI5 MINI RECIRC SAFETY UPGRADE / Revision 1 REMOVE AF-1 17 INTERNALS UNIT 0

installation and safety related parts were installed. Internal memo NPM 2002-0228 was subsequently issued during installation of MR 02-001, and documented the decision to conservatively upgrade the safety classification of the backup air accumulators and tubing for the 1/2AF-4002 valves to safety-related, while maintaining the open function for the AOVs as non safety-related. ECR 2002-0077 and a revision to SCR 2002-0010 were prepared to document this change.

Components for the nitrogen backup to the AF-4007/4014 valves installed per MR 01-144 were originally installed and scoped safety related, since the backup nitrogen for the MDAFP discharge valves (AF-4012/4019) was classified safety-related, and the connections to the mini-recirc AOVs became part of the safety-related pressure boundary.

Design Changes

0 Safety-Related Classification Uporade

Letter NRC 2002-0068 dated 8/12/2002 states that PBNP will classify the open function for the AFW pump minimum flow recirculation valves as safety-related. The letter also states that because not all of the recirculation flow path is safety-related, operability of the AFW pumps will not be dependent on the availability of that flow path. However, it has been conservatively decided to tie AFW pump operability to this recirculation line. Therefore, even though recirculation line downstream of the orifices is not safety-related, it is required to be inservice to consider the AFW pumps fully operable per TS 3.7.5.

The 1/2AF-4002, AF-4007, and AF-4014 will be classified as having a safety-related function to open to ensure adequate flow through the AFW pumps to prevent pump damage. The valves are already classified as safety related, due to their safety function to close to ensure adequate AFW flow to the steam generators. The backup pneumatic systems installed by MR 01-144 and MR 02-001 were already classified safety-related to support this function.

The current safety-related boundary for the recirculation lines is at the flow restricting orifices. This boundary will not change, and the recirculation piping downstream of these orifices will remain non safety-related. This piping feeds into the condensate storage tanks, which are non safety-related tanks at atmospheric pressure. This line can be credited to support a safety-function while not being classified safety-related because failure of the piping would be conservative in terms of AFW pump protection. The only credible failure of the piping that would cause AFW pump damage would be if check valve AF-1 17 failed to open (an active fiilure). Therefore the internals for this check valve will be removed. All other non-conservative failure modes for the recirc line are passive in nature. Several manual valves exist in the recirculation lines, and all of these valves are currently red-locked open. Mispositioning is not credible due to procedural controls in place (red locks), and a disk separation failure of a manual valve is considered passive.

a AF-1 17 Internals Removal

To prevent a common mode active failure of the recirculation piping, the internals to check valve AF-1 17 will be removed. This valve has no specified function to isolate, since each recirculation line has a check valve upstream of the mini-recirc AOV, and it is unlikely that the system would be aligned in such a way that would generate a driving head to force water backwards through the line to the AFW pumps. It is likely that the check valve was installed to isolate relief valve AF-4035 from the CST, or to prevent heating steam condensate from entering the recirculation header. After the internals are removed, leakage of the AF-4035 relief valve could cause leakage of CST water into the turbine building, which would be a flooding concern. This, however, does not adversely affect the AFW system. The heating steam condensate return to the CSTs is no longer used due to condensate water quality concerns.

This valve is an ALOYCO model #376-SP 150# class 3" swing check valve. The disk, clapper arm, and clapper arm shaft will be removed to prevent the valve from isolating flow. The existing cover and bolting will be reused.

Ptige 3 of 5

Page 10: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

FINAL DESIGN DESCRIPTION MR 02-029 #-'"•-1 September 12, 2002

AUX FEED MINI RECIRC SAFETY UPGRADE / Revision 1 "REMOVE AF-1 17 INTERNALS UNIT0

Licensing Basis Updates

FSAR Section 10.2 will be revised to document the safety function of the AOVs to open. FSAR Section 9.7 will be revised to document the safety functions of the backup air sources. Tech Spec Bases B3.7.5 will be updated to clarify that the operability of the AFW pumps requires the minimum flow recirculation line to be inservice.

IST Updates

Several changes are required within the IST program to reflect the new safety function of the AOVs to open. IT 08A, IT 09A, IT 10, IT 10A, and IT 10B will all be revised to provide stroke open time acceptance criteria for the air-operated valves. Additionally, a full stroke open exercise test of the recirculation check valves (1/2AF-1 14, AF115, AF-116) was added to these procedures. A closure test of instrument air check valves I/2AF-173 was previously added to IT-0gA and IT-09A after the installation of MR 02-001, however, acceptance criteria •till now be added. The MDAFP Nitrogen backup check valves (AF-133/153) were already in the IST program for their safety function to support the AF-401214019 dicharge AOVs. The IST background document will be updated to document the safety-related open function for the AOVs and recirc check valves, as well as the isolation functions of the instrument air check valves.

Installation

Both units may be in any condition, but the commoh recirculation line must be isolated to remove the AF-117 internals. While this line is out of service, the AFW pumps will be considered fully operable. Manual operator action will be credited to prevent pump damage by stationing a level 3 dedicated operator at the AF-4035 relief valve. If the minimum flow recirculation line is needed, and the relief valve does not open automatically while the line is isolated, then the dedicated operator will notify the control room that the recirculation flow path is not available. Although OM 3.26 allows a level 3 dedicated operator to perform other duties, this will not be allowed during this installation. A dedicated operator can be utilized to support AFW pump operability since there will not be a time requirement for the operator to take action, and the dedicated operator is only relaying information. This action for the dedicated operator will be required only when the control operator has taken action to reduce AFW flow.

AF-4035 was replaced by MR 88-099, which upgraded the size of the minimum recirculation line. The valve has a setpoint of 50 psig, and a capacity of 268 gpm (at 55 psig). This is enough flow capacity to provide cooling flow for

. all four AFW pumps. Calculation 2002-0026 and SCR 2002-0377 has been performed to document the acceptability of relying on this relief valve to support AFW pump operability while the common recirculation line is out of service for removal of the AF-1 17 internals.

Post Modification Testing

Since no welding is being performed, and the internals removal requires only the disassembly of a mechanical joint (flanged connections), an initial service leakage test per ASME B31.1 is not required. A non-code leak check will be performed at normal operating conditions (with an AFW pump running) to check for gasket leakage.

Pdge 4 of 5

Page 11: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

FINAL DESIGN DESCRIPTION MR 02-029 September 12,2002 Revision 1AUX FEED MINI RECIRC SAFETY UPGRADE!

REMOVE AF-1 17 INTERNALS UNIT 0

Desien Outputs

0

S

6

0

0

0

50.59 Safety Screening, PBF-1515c, SCR 2002-0359 (Modification MR 02-029)

50.59 Safety Screening, PBF-1515c, SCR 2002-0377 (Operability During Mod Installation)

DCN 2002-1547 - M-217 Sh. 1 DCN 2002-1548 - ALOYCO A-46037 WO 0212107 for AF-117 Calculation 2002-0026

Pige 5 of 5

�::� �

Page 12: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

_________ -- �

I ~VI

z

I~w w

;jJt I. .

p TIT

wa

f-W.9~i ............... .....

-I al

®r~ -~~lo

001I-1. * III

T~ . ;1z;L

U 1..

........................ .... v

I -. j ~~oil)

ITI

---- -------- ------

t T -- t~r

U.

'1

bVWjmjjjjj ý

N

0 0 0 0 0

- �Ii

v*

I

91061

t

I .II

0 I0 I. Ld

Page 13: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant

10 CFR 50.59/72.48 SCREENING (NEW RULE)

(.,,:Title of Proposed Activity:

Associated Reference(s) #:

SCR 2002-0359

Verify SCR number on all pages Page I

Removal of Internals from AF-1 17 and Upgrade Open function of AFW pumps Mini-Recirc Valves to Safety-Related (MR 02-09)

SCR 2002-0010-01, SCR 2002-0321 and 2002-0339; MR 01-144, AF-4007/4014 Backup Nitrogen Supply, MR 02-001, 1/2AF-4002 Backup Air Supply; EVAL 2002-005, Permanent Plant Changes to Address Simultaneous Failure of All AFW Pumps; FCR 02-019; SE 97-085, MR 97-038 AFW Motor Driven Pump Pressure Dischsrge Valve Modification: Fay Letter to NRC, NRC Bulletin 88-04, Potential Safety-Related Pump Loss, June 28, 1988; NPM 2002-0228, Designation Of Backup Pneumatics For AFW Mini- Recirculation Valves As Safety-Related, NRC 2002-0068, Point Beach Nuclear Plant, Units I and 2 Reply to a Notice Of Violation (EA-02-03 1) NRC Special Inspection Report No. 50-266/01-17 (DRS); 50-301/01-17 (DRS).

Prepared by:

Reviewed by:

David BlackName ( Print)

Rob Chapman Name ( Print)

(fav2 6�&i�Sigriature

S64ture

PART I (50.59/72.48) - DESCRIBE THE PROPOSED ACTIVITY AND SEARCH THE PLANT AND ISFSI LICENSING BASIS (Resource Manual 5.3.1) 1

NOTE: The "NMC 10 CFR 50.59 Resource Manual" (Resource Manual) and NEI 96-07. Appendix B. Guidelines for 10 CFR 72.48 Implementation should be used for guidance to determine the proper responses for 10 CFR 50.59 and 10 CFR 72.48 screenings.

1.1 Describe the proposed activity and the scope of the activity being covered by this screening. (The 10 CFR 50.59 / 72.48 review of other portions of the proposed activity may be documented via the applicability and pre-screening process requirements in NP 5.1.8.) Appropriate descriptive material may be attached.

The scope of this screening involves the following activities associated with MR 02-029: - Remove internals for AF-117, the 4uxiliary Feedwater Pump Common Mini-Recirc Header Check Valve to prevent a common

mode active failure in the recirc return header. - Upgrade open function for all Auxiliaryfeedwaterpump mini-recirc valves to safety-related (also being done by ISTgroupfor

procedure changes under screenings SCR 2002-0321 and 2002-0339. -State in the FSAR (FSAR 10.2) and Technical Specification Bases(B 3.7.4) that (I) the open fi.uction for all Auxiliary feedwater pump mini-recirc valves is safety-related, and(2) the recirculation line downstream of the flow restricting orifices has a safetyfunction and is requiredfor AFW operability, but the line is not safety-related since failure of the line is conservative. The Bases will indicate that the mini-recirculationflowpaths have to be OPERABLE for the AFWsystem to be operable.

A simplified P&ID of the mini-recirc header is shown below

From 1 P-29

PBF-1515c R oI O-1/03,02

From P.38A. P385. & 2P-29

3*-jr-4

To Condensate Storage Tank T-24B

To Condensate Storage Tank T.2.1A

1'-dG-4

RcIicrnc: N1p 5 1 .1

Date: -D 0 oL_

Date: .-- 02.

Page 14: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant SCR 2002-0359

10 CFR 50.59/72.48 SCREENING (NEW RULE) Verify SCR numberon all pages Page 2

EVAL 2002-005 evaluated permanent procedure changes that were implemented in response to a condition (CR 01-3595)

that was identified where, with a procedure-directed operator action to control steam generator level (which could be

accomplished by reducingflow through one or more AFW pumps), concurrent with a loss of instrument air (which would

cause the AFW pumps' mini-recirculation valves to fail close), the potential existed for a simultaneous failure of the multi

stage high pressure AFW pumps due to very low or no flow through running AFW pumps. The procedure changes added

instructions to the operators that ifanyAFWpump mini-recirc valve fails shut OR anminciator COI A 1-9, INSTRUMENT

AIR HEADER PRESSURE LOW is in alarm, then monitor and maintain minimum AFW flow or stop the affected AFW pump

as necessary to control SIG levels. Minimum flow values for each pump were also included in the procedures. The majority

of the changes were associated with EOP and ECA foldout pages. The procedures were initially revised as a compensatory

measure to support AFW pump operability. The 50.59 evaluation reviewed the procedure changes as a permanent change

to the procedures as described in the FSAR to confirm consistency with the licensing basis. The permanent procedure

changes restored the AFW pumps tofully operable status.

This evaluation also was the basis for changes to the FSAR to clarify that the mini-recirculation valves require instrument air

to function and that either a pump minimum flow is maintained or pumps are secured if the valve fails or instrument air is

lost (FCR 02-019).

Screening SCR 2002-0010-01 reviewed modifications to provide backup air sources to all AFW pump minimum flow

recirculation valves. These modifications were an enhancement that reduced the core damage probabilityfrom a loss of

instrument air and increased the time for an operator to take manual action to override the valves open. Instrument air

accumulator tanks were installed by MR 02-00lfor the 1/2P-29 valves (l/2AF-4002), and the existing nitrogen backup

system for the MDAFP discharge valves were tied in by MR 01-144 for the P-3 8A/B valves (AF-4007. AF-4014).

Point Beach has made an NRC commitment to upgrade the open fitnction for all mini-recirc valves to safety-related as stated in NIMC letter NRC 2002-0068:

(7' "To fitrther improve the future effectiveness ofthe AFW system by providing additional pump

protection against low flow, Point Beach is classifying the open function of the pump recirculation

flow control valves, as safety-related This will provide a redundant method ofproviding for minimum

AFW pump flow and consequently, pump cooling. As a result, testing and quality assurance requirements requiredfor safety-related functions will be applied to the open function of these valves.

As discussed previously, internal pump cooling is designed to be provided by minimum forwardflow

through the pumps. Classifying the recirculation flow control valves as safet-related will provide

greater assurance that minimum flow will be available to provide internal pump cooling The

pneumatic backup supply to the recirculation flow control valves is limiting and therefore Point Beach

will also continue to specify operator action to manually open these recirculation valves. Similar to

other plants, Point Beach has one common recirculationflowpath from all the AFW pumps to the

condensate storage tanks"

The scope ofthis screening also includes FSAR changes and Technical Specification Bases changes to coincide with the

mini-recirculation safety upgrade described above.

12 Search the PBNP Current Licensing Basis (CLB) as follows: Final Safety Analysis Report (FSAR), FSAR Change Requests

(FCRs) with assigned numbers, the Fire Protection Evaluation Report (FPER), the CLB (Regulatory) Commitment Database,

the Technical Specifications, the Technical Specifications Bases, and the Technical Requirements Manual. Search the ISFSI

licensing basis as follows: VSC-24 Safety Analysis Report, the VSC---4 Certificate of Compliance. the CLB (Regulatory)

Commitment Database, and the VSC-24 10 CFR 7P.212 Site Evaluation Report. Describe the pertinent design function(s),

performance requirements. and methods of evaluation for both the plant and for the cask, ISFSI as appropriate. Identify

where the pertinent information is described in the above documents (by document section number and title). (Resource

Manual 5.3.1 and NEI 96-07. App. B. B 2)

The .4uxiliar Feedwater t..IFO) system has theJbllowmngfuncttons described in the licensing bas is.

a. To automatically start and ensure that adequateftedwater is sutpplied to the steain generators 1br heat removal

during accidents ishcwh may result in a main steam .- e,.jr, valve opening (Lo.5s o] ,Vormal Feedivater - includinz

.4 TI VS and Loss tf'.-IC to the Staton .4Azciliarwýl

PI3F-151lc Rc,,t,,i~n I O OI}-~},)2 R¢.cretncL N' .I 'I

Page 15: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant SCR 2002-0359

10 CFR 50.59/72.48 SCREENING (NEW RULE) Verify SCR number on all pages

Page 3

b. To automatically start and provide flow to maintain steam generator levels during accidents which require or result in rapid reactor coolant system cooldown (Steam Generator Tube Rupture and Rupture of a Steam Pipe).

c. To allow the isolation of all lines to the ruptured steam generator in the SGTR event. d To provide sufficient feedwater to remove decay heat from both units for one hour during a station blackout

(SBO) event (TDAFP only). e. To provide sufficient flow to the steam generators to remove decay heat to achieve cold shutdown within 72

hours following a plant fire (Appendix R). f To withstand a seismic event (i.e., the seismic Class 1 portions of the system) and to ensure that steam

generator levels are maintained during a seismic event. g. To provide flow to the steam generators during plant startup and shutdown, and during hot shutdown or hot standby

conditions for chemical additions and when operation of the main feedwater and condensate systems is not warranted.

These modifications affect the operation of the minimum recirculation valves for the auxiliaryfeedwater pumps (1/2AF4002, AF-4007, AF-4014). These valves have the following design functions:

1. To isolate the minimum recirculation line to ensure that the auTiliaryfeedwater pumps deliver the requiredflow to the steam generators as needed to support the following accidents or events: LONF. LOA C, MSLB, SGTR, A TWS, Appendix R, and SBO.

2. To open to provide flow through the auxiliary feedwater pumps to prevent hydraulic instabilities and to dissipate pump heat.

3. To maintain the pressure boundary integrity of the auxiliary feedwater system.

FSAR 10.2.2, System Design and Operation, states: 'The auxiliary feedwater system consists of two electric motor-driven pumps, two steam turbine-driven pumps, pump suction and discharge piping, and the controls and instrumentation necessary for operation of the system. Redundancy is provided by utili:ing two pumping systems, two different sources ofpower for the pumps, and two sources of water supply to the pumps. The system is categoriked as seismic Class I and is designed to ensure that a single fault will not obstruct the system function."

CLB References: FSAR 7.2.3.2- Specific Control and Protection Interactions FSAR 7.3.3.4 - Manual AFW Flow Control During Plant Shutdown FSAR Section 7.4.1 - AMSA C FSAR Section 10.1 - Steam and Power Conversion System FSAR Section 10 2 -Awriliary Feedwater FSAR Figure 10.2-1 Sheet I - Bech M-217 Sh. 1-A uxiliary Feedwater System FSAR Figure 10.2-1 Sheet 2- Bech M-217 Sit 2- Auxiliary Feedwater System FSAR Section 14.1.10 - Loss of Normal Feedwater FSAR Section 14. 1. 11 - Loss ofAll AC Power to the Station Auxiliaries FSAR Section 14.2.4 - Steam Generator Tube Rupture FSAR Section 14.2.5 - Rupture of a Steam Pipe FSAR Appendix A.I - Station Blackout FPER 5.2.2 - Safe Shutdown Systems and Equipment FPER 5.2.5.2.3 - Auxiliary Feedwater Pump Room Tech Spec 3..".5- Azriliary Feedwater Tech Spec Bases B 3.7.5- A ucxiliary Feedwater NRC 2002-0068, Point Beach Nuclear Plant, Units I and 2 Reply to a Notice Of Violation (EA-02-031) NRC Special Inspection Report No. 50-266/01-17 (DRS); 50-301/01-17 (DRS)

1.3 Does the proposed activity involve a change to any Technical Specification? Changes to Technical Specifications require a License Amendment Request (Resource Manual Section 5.3.1.2).

Technical Specification Change: [] Yes 0 No

Ifa Technical Specification change is required. explain what the change should be and %hy it is required.

PBr.1s51 ; Revi61on I 0-4,03 02 R."reni.. NP 51 l

Page 16: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant SCR 2002-0359 10 CFR 50.59/72.48 SCREENING (NEW RULE) Verify SCR number on all pages

Page 4

;" 1.4 Does the proposed activity involve a change to the terms, conditions or specifications incorporated in any VSC-24 cask Certificate of Compliance (CoC)? Changes to a VSC-24 cask Certificate of Compliance require a CoC amendment request.

El Yes 0 No

If a storage cask Certificate of Compliance change is required, explain what the change should be and why it is required.

10 CFR 50.59 SCREENING

PART 11 (50.59) - DETERMINE IF THE CHANGE INVOLVES A DESIGN FUNCTION (Resource Manual 5.3.2)

Compare the proposed activity to the relevant CLB descriptions, and answer the following questions:

YES NO QUESTION ED El Does the proposed activity involve Safety Analyses or structures, systems and components (SSCs) credited in the

Safety Analyses?

0] El Does the proposed activity involve SSCs that support SSC(s) credited in the Safety Analyses?

0] El Does the proposed activity involve SSCs whose failure could initiate a transient (e.g., reactor trip, loss of feedwater, etc.) or accident, OR whose failure could impact SSC(s) credited in the Safety Analyses?

0 El Does the proposed activity involve CLB-described SSCs or procedural controls that perform functions that are required by, or otherwise necessary to comply.with, regulations, license conditions, orders or technical specifications?

"'. El 0] Does the activity involve a method of evaluation described in the FSAR?

El 0 Is the activity a test or experiment?. (i.e., a non-passive activity which gathers data)

El 0] Does the activity exceed or potentially affect a design basis limit for afission product barrier (DBLFPB)? (NOTE: If THIS questions is answered YES, a 10 CFR 50.59 Evaluation is required.)

If the answers to ALL of these questions are NO mark Part III as not applicable, document the 10 CFR 50.59 screening in the conclusion section (Part IV), then proceed directly to Part V - 10 CFR 72.48 Pre-screening Questions.

If any of the above questions are marked YES, identify below the specific design function(s), method of evaluation(s) or DBLFPB(s) involved.

1. The AF-117 check valve has an implicit finction to open to allow minimum recirculationflowfrom the auxiliaryfeedwater pumps to return to the condensate storage tank(s). There is no direct discussion of this finction in the licensing basis, other than that the valve appears in FSAR Figure 10.2-1.

A search of plant documents did not yield any reference to a needfor valve AF-) 17 to close (or remain closed). The following uses were considered as possible functions for the closed position:

a. To prevent backflow of heating steam condensate from entering the mini-recirculation return header. Given that the minrecirculation header is not drained and remains filled with water during and after pump operation, migration of heating steam condensate into the header in any stgniflcant amounts is unlikely Further, the plant no longer returns heating steam condensate to the condensate storage tank because of water quality concerns, and it is extremely unlikely that this plant design feature will ever be used again. Regardless. this reason for preventing backtlow does not constitute a licensing basis clesignfinction Therefore this function will not be evaluated for adverse effects.

b To prevent backflow and sithonin! of vater from the condensate storage tanks through AF-4035 in the event that this valve onens due to hieh pressure in the line or due to a break in the header. The valve's nominal relief setting is 50 psi. For AF-4035 to open, either tn event occurs where multltple pumps start with high recircflowrates and pressurt:e the line. or there is a blockage in the line. The safetv-relatedJlow restricting orifices in the recirc line front each AFW puip hinnt the flow and pressure from each pump Further if the line is blocked either by mispostuomng nf/manual valves or failure of the check valve to

R: N ion I 0o-Im)3 ) R()crn1LC ,lp I

Page 17: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant SCR 2002-0359

10 CFR 50.59/72.48 SCREENING (NEW RULE) Verify SCR number on all pages

Page 5

open, there is noflowpathfor backflow. The only credible way for the header to break is during a seismic event, in which case water from the condensate storage tank cannot be credited for accident mitigation. The prevention of backflow from the condensate storage tanks cannot be considered a licensing basis design function. Therefore this finction will not be evaluated for adverse effects.

2. The minimum recirculation valves for the auxiliary feedwater pumps (1/2AF- 4002, AF-4007, AF-4014) have the design functions to isolate the minimum recirculation line to ensure that the auxiliary feedwater pumps deliver the requiredflow to the steam generators as needed to support the mitigation of accidents or events. The proposed activity is to make the open finction for these valves a safety-related function. The new components for modifications MR 02-001 and MR 01-144 as discussed above were installed safety-related due to their risk significance. These components were classified safety-related based on a PBNP management decision, as described in NPM 2002-0228. These modifications ensure a safety-related supply of air or nitrogen to ensure that the auxiliaryfeedwater pumps have adequate cooling.

PART 111 (50.59) - DETERMINE WHETHER THE ACTIVITY INVOLVES ADVERSE EFFECTS (Resource Manual 5.3.3)

If ALL the questions in Part II are answered NO, then Part III is C] NOT APPLICABLE.

Answer the following questions to determine if the activity has an adverse effect on a design function. Any YES answer means that a 10 CFR 50.59 Evaluation is required; EXCEPT where noted-in Part 111.3.

II. 1 CHANGES TO THE FACILITY OR PROCEDURES

YES NO QUESTION

[] 0] Does the activity adversely affect the designfunction of an SSC credited in safety analyses?

,"• [ 0] Does the activity adversely affect the method of performing or controlling the design function of an SSC credited in the safety analyses?

If any answer is YES, a 10 CFR 50.59 Evaluation is required. If both answers are NO, describe the basis for the conclusion (attach additional discussion as necessary):

1. The only function identifiedfor the AF-117.check valve was to open to allow mini-recirculation water from AFW pumps to return to the condensate storage tank. It has no design function to close Therefore removing the check valve internals has no adverse effect on the open function and precludes the valve from failing to open.

2. The change in designation of the open finction ofmini-recirculation valves 1/2AF- 4002, AF-4007. AF-4014 as safetyrelated has no adverse affect on the valve'sfunction to open or close. The open function was a design function desribed in the FSAR. Designating the open function as safety-related requires addition quality control and testing and should. therefore, make the open functions of the valve more reliable. The necessary backup air/nitrogen supplies were installed as safety-related so no additional physical changes to the plant are required SCR 2002-0010-01 assessed the installation of these backup pneumatic supplies on the close finction of the valves and no adverse effects were identified. Therefore there is no adverse effect on the functions of these valves.

3. Changes will be made in the FSAR to state that the open function for all.4 uAxliaryfeedwater pump mini-recirc valves is safety-related The Technical Specification Bases will indicate that the mini-recirculationflowpaths have to be OPERABLE for the AFW system to be operable. These changes only reflect the activities discussed above, which have already been assessed and determined that there is no adverse effect on a design function FSAR changes will also be made to reflect the recirculation line downstream ofthe flow restricting orifices has a safetyfiunction and is requiredfor .4FWY operabiliot but the line is not safety-related since failure of the line is conservative. No physical changes were made to this line. If the line fails, a break or opening will be created which inay increase overall flow through the recirculation line. The service-water s.stem is the safet. -related itater supply for the.4FW system. The loss of CST inventory due to the line failing and recirculation water spilling only affects the non-safety-related water source for the ,4FWV system. The required mintminn CST water is based on the station blackout(SBOJ event; SBO is not an event that would cause this line to fail (open). Therefore. based on the above, the licensing basis documents changes do not have an adverse effect on any design functions

PBF-1lSc Rcviýaon I 0o-,03,02 R,!Cr01L. %,' 1 '1

Page 18: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant SCR 2002-0359

10 CFR 50.59172.48 SCREENING (NEW RULE) Verify SCR number on all pages Page 6

! :)111.2 CHANGES TO A METHOD OF EVALUATION

(If the activity does not involve a method of evaluation, these questions are Z NOT APPLICABLE.)

YES NO QUESTION

El El Does the activity use a revised or different method of evaluation for performing safety analyses than that described in the CLB?

[E [0 Does the activity use a revised or different method of evaluation for evaluating SSCs credited in safety analyses than that described in the CLB?

If any answer is YES, a 10 CFR 50.59 Evaluation is required. If both answers are NO. describe the basis for the conclusion (attach additional discussion, as necessary).

111.3 TESTS OR EXPERIMENTS

If the activity is not a test or experiment, the questions in III.3.a and III.3.b are 0 NOT APPLICABLE.

a. Answer these two questions first:

YES NO QUESTION

E- [I Is the proposed test or experiment bounded by other tests or experiments that are described in the CLB?

El El Are the SSCs affected by the proposed test or experiment isolated from the facility? (7*,

If the answer to BOTH questions in V.3.a is NO, continue to 1II.3.b. If the answer to EITHER question is 'YES, then describe the basis.

b. Answer these additional questions ONLY for tests or experiments which do NOT meet the criteria given in III.3.a above.

If the answer to either question in III.3.a is YES. then these three questions are Z NOT APPLICABLE.

YES NO QUESTION

El El Does the activity utilize or control an SSC in a manner that is outside the reference bounds of the design bases as described in the CLB?

l [El Does the activity utilize or control an SSC in a manner that is inconsistent with the analyses or descriptions in the CLB?

0l Dl Does the activity place the facility in a condition not previously evaluated or that could affect the capability of an SSC to perform its intended functions?

If any answer in III.3.b is YES, a 10 CFR 50.59 Evaluation is required. If the answers in I1.3.b are ALL NO, describe the basis for the conclusion (attach additional discussion as necessary):

, ...... i , i V, i , I '

Page 19: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant SCR 2002-0359

10 CFR 50.59/72.48 SCREENING (NEW RULE) Verify SCR number on aH pages Page 7

". Part IV- 10 CFR 50.59 SCREENING CONCLUSION (Resource Manual 5.3.4).

Check all that apply:

A 10 CFR 50.59 Evaluation is [] required or Z NOT required.

A Point Beach FSAR change is 0 required or E] NOT required. If an FSAR change is required, then initiate an FSAR Change Request (FCR) per NP 5.2.6.

A Regulatory Commitment (CLB Commitment Database) change is El required or [0 NOT required. If a Regulatory Commitment Change is required, initiate a commitment change per NP 5.1.7.

A Technical Specification Bases change is [9 required or C] NOT required. If a change to the Technical Specification Bases is required, then initiate a Technical Specification Bases change per NP 5.2.15.

A Technical Requirements Manual change is C] required or Z NOT required. If a change to the Technical Requirements Manual is required, then initiate a Technical Requirements Manual change per NP 5.2.15.

10 CFR 72.48 SCREENING

NOTE: NEI 96-07, Appendix B. Guidelines for 10 CFR 72.48 Implementation should be used for guidance to determine the proper responses for 72.48 screenings.

PART V (72.48) - 10 CFR 72.48 INITIAL SCREENING QUESTIONS

Part V determines if a full 10 CFR 72.48 screening is required tý be completed (Parts VI and VII) for the proposed activity.

i'.•'YES NO QUESTION

C 0] Does the proposed activity involve IN ANY MANNER the dry fuel storage cask(s), the cask transfer/transport equipment, any ISFSI facility SSC(s), or any ISFSI facility monitoring as follows: Multi-Assembly Sealed Basket (MSB), MSB Transfer Cask (MTC), MTC Lifting Yoke, Ventilated Concrete Cask (VCC), Ventilated Storage Cask (VSC), VSC Transporter (VCST), ISFSI Storage Pad Facility, ISFSI Storage Pad Data/Communication Links, or PPCSIISFSI Continuous Temperature Monitoring System?

C 0] Does the proposed activity involve IN ANY MANNER SSC(s) installed in the plant specifically added to support cask loading/unloading activities, as follows: Cask Dewatering System (CDW), Cask Reflood System (CRF), or Hydrogen Monitoring System?

C 0] Does the proposed activity involve IN ANY MANNER SSC(s) needed for plant operation which are also used to support cask loading/unloading activities, as follows: Spent Fuel Pool (SFP), SFP Cooling and Filtration (SF),

Primary Auxiliary Building Ventilation System (VNPAB), Drumming Area Ventilation System (VNDRM), RE-105 (SFP Low Range Monitor), RE-135 (SFP High Range Monitor), RE-221 (Drumming Area Vent Gas Monitor), RE-325 (Drumming Area Exhaust Low-Range Gas Monitor), PAB Crane, SFP Platform Bridge, Truck Access Area, or Decon Area?

C 0] Does the proposed activity involve a change to Point Beach CLB design criteria for external events such as earthquakes, tornadoes, high winds, flooding, etc.?

C 0] Does the activity involve plant heavy load requirements or procedures for areas of the plant used to support cask loading/unloading activities?

C] 0] Does the activity involve any potential for fire or explosion where casks are loaded, unloaded, transported or stored?

If ANY of the Part V questions are answered YES then a full 10 CFR 72.48 screening is required and answers to the questions in

Part VI and Part VII are to be provided. If ALL the questions in Part V are answered NO. then check Parts VI and VII as not applicable. Complete Part VIII to document the conclusion that no 10 CFR 72.48 evaluation is required.

PG F. 15 IScRdicrenmc NI' . 1 ,

Page 20: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant SCR 2002-0359

10 CFR 50.59172.48 SCREENING (NEW RULE) Veif SCR nunmber on all pages Page 8

,-- PART VI (72.48) - DETERMINE IF THE CHANGE INVOLVES A ISFSI LICENSING BASIS DESIGN FUNCTION

(If ALL the questions in Part V are NO, then Part VI is 0 NOT APPLICABLE.)

Compare the proposed activity to the relevant portions of the ISFSI licensing basis and answer the following questions:

YES NO QUESTION

El El Does the proposed activity involve cask/ISFSI Safety Analyses or plant/cask/ISFSl structures, systems and components (SSCs) credited in the Safety Analyses?

El El Does the proposed activity involve plant, cask or ISFSI SSCs that support SSC(s) credited in the Safety Analyses?

E] nl Does the proposed activity involve plant, cask or ISFSI SSCs whose function is relied upon for prevention of a radioactive release, OR whose failure could impact SSC(s) credited in the Safety Analyses?

El El Does the proposed activity involve cask/ISFSl described SSCs or procedural controls that perform functions that are required by, or otherwise necessary to comply with, regulations, license conditions, CoC conditions, or orders?

El 0l Does the activity involve a method of evaluation described in the ISFSI licensing basis?

El El Is the activity a test or experiment? (i.e., a non-passive activity which gathers data)

El El Does the activity exceed or potentially affect a cask design basis limit for a fission product barrier (DBLFPB)?

(NOTE: If THIS questions is answered YES, a 10 CFR 72.48 Evaluation is required.)

If the answers to ALL of these questions are NO, mark Parts VII as not applicable, and document the 10 CFR 72.48 screening in the

conclusion section (Part VIII).

__. If any of the above questions are marked YES, identify below the specific design function(s), method of evaluation(s) or DBLFPB(s)

( involved.

PART VII (72.48) - DETERMINE WHETHER THE ACTIVITY INVOLVES ADVERSE EFFECTS (NEI 96-07,

Appendix B, Section B.4.2. 1)

(If ALL the questions in Part V or Part VI are answered NO then Part VII is E] NOT APPLICABLE.)

Answer the following questions to determine if the activity has an adverse effect on a design function. Any YES answer means that a

10 CFR 72.43 Evaluation is required; EXCEPT where noted in Part VII.3.

VII.1 Changes to the Facility or Procedures

YES NO QUESTION

El El Does the activity adversely affect the designfinction of a plant, cask, or ISFSI SSC credited in safety

analyses?

El El Does the activity adversely affect the method of performing or controlling the design function of a plant,

cask, or ISFSI SSC credited in the safety analyses?

If any answer is YES, a 10 CFR 72.48 Evaluation is required. If both answers are 'NO. describe the basis for the conclusion

(attach additional discussion, as necessary):

PBI-151.;c t) . - -I ININ iRC,.rCl.! NP ; I ý

Page 21: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant SCR 2002-0359

10 CFR 50.59/72.48 SCREENING (NEW RULE) Verify SCR number on all pages

Page 9

VII2 Changes to a Method of Evaluation

(If the activity does not involve a method of evaluation, these questions are Z NOT APPLICABLE.)

YES NO QUESTION

El El Does the activity use a revised or different method of evaluation for performing safety analyses than that described in a cask SAR?

El El Does the activity use a revised or different method of evaluation for evaluating SSCs credited in safety analyses than that described in a cask SAR?

If any answer is YES, a 10 CFR 72.48 Evaluation is required. If both answers are NO, describe the basis for the conclusion (attach additional discussion, as necessary):

VII.3 Tests or Experiments

(If the activity is not a test or experiment, the questions in VII.3.a and VII.3.b are 0 NOT APPLICABLE.)

a. Answer these two questions first:

YES NO QUESTION

El El Is the proposed test or experiment bounded by other tests or experiments that are described in the cask

ISFSI licensing basis?

El El Are the SSCs affected by the proposed test or experiment isolated from the cask(s) or ISFSI facility?

If the answer to both questions is NO, continue to VII.3.b. If the answer to EITHER question is YES, then briefly describe

the basis.

b. Answer these additional questions ONLY for tests or experiments which do not meet the criteria given in VII.3.a above.

If the answer to either question in VII.3.a is YES, then these three questions are 0 NOT APPLICABLE:

YES NO QUESTION

El E] Does the activity utilize or control an SSC in a manner that is outside the reference bounds of the design

bases as described in the ISFSI licensing basis?

El El Does the activity utilize or control a plant, cask or ISFSI facility SSC in a manner that is inconsistent with

the analyses or descriptions in the ISFSI licensing basis?

El El Does the activity place the cask or ISFSI facility in a condition not previously evaluated or that could affect

the capability of a plant, cask, or ISFSI SSC to perform its intended functions?

If any answer in VII.3.b is YES, a 10 CFR 72.48 Evaluation is required. If the answers are all NO describe the basis for the

conclusion (attach additional discussion as necessary):

P13['-SISCqlcf'rtný NI1 '; I ý

Page 22: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant

10 CFR 50.59/72.48 SCREENING (NEW RULE)SCR 2002-0359

Verify SCR number on all pageps Page 10

.-.. PART VIII- DOCUMENT THE CONCLUSION OF THE 10 CFR 72.48 SCREENING

"Check all that apply:

A 10 CFR 72.48 Evaluation is E] required or Z NOT required. Obtain a screening number and provide the original to Records Management regardless of the conclusion of the 50.59 or 72.48 screening.

A VSC-24 cask Safety Analysis Report change is C] required or [] NOT required. If a VSC-24 cask SAR change is required, then contact the Point Beach Dry Fuel Storage group supervisor.

A Regulatory Commitment (CLB Commitment Database) change is E] required or Z NOT required. If a Regulatory Commitment Change is required, initiate a commitment change per NP 5.1.7.

A change to the VSC-24 10 CFR 72.212 Site Evaluation Report is El required or (Z NOT required. If a VSC-24 10 CFR 72.212 Site Evaluation Report change is required, then contact the Point Beach Dry Fuel Storage group supervisor.

P F-I S I-5c Rei:,on I ../0 3,O2 Rc ern, "41 .I N

Page 23: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant SCR 2002-0377

10 CFR 50.59/72.48 SCREENING (NEW RULE) Verify SCR number on alt pages

Page 1

";'.Title of Proposed Activity: AFW System Operability during Removal of Internals from Check Valve AF-l 17 (MR 02-029)

Associated Reference(s) #: EVAL 2002-005, "Permanent Plant Changes to Address Simultaneous Failure of All AFW Pumps;" FCR 02-019; SCR 2002-0359, "Removal of Internals from AF-1 17 and Upgrade Open function of AFW pumps Mini-Recirc Valves to Safety-Related (MR 02-09)," Work Order Work Plan 0212107 - MR -02029, Calculation 2002-0026, "Evaluation of AFW Recirculation Line Relief Valve AF-4035," OM 3.26, "Use of Dedicated Operators."

Prepared by: David Black _ _ _,, _ _ _ Date:

Name ( Print) Sigrhature

Reviewed by: Rob Chapman Date: c7- O - G2

Name ( Print) 0nature

PART I (50.59/72.48) - DESCRIBE THE PROPOSED ACTIVITY AND SEARCH THE PLANT AND ISFSI LICENSING BASIS (Resource Manual 5.3.1)

NOTE: The "NMC 10 CFR 50.59 Resource Manual" (Resource Manual) and NEI 96-07. Appendix B. Guidelines for

10 CFR 72.48 Implementation should be used for guidance to determine the proper responses for 10 CFR 50.59 and 10 CFR 72.48 screenings.

"(•I. I Describe the proposed activity and the scope of the activity being covered by this screening. (The 10 CFR 50.59 /72.48 "review of other portions of the proposed activity may be documented via the applicability and pre-screening process requirements in NP 5.1.8.) Appropriate descriptive material may be attached.

The scope of this screening involves the isolation (danger tagging) of the AFW pump recirculation line in order to remove the internals of check valve AF- 117.

The NMC guidance for the new 10 CFR 50.59 rule (NMC Resource Manual) states that modification activities (i.e., interim conditions) are to be assessed as maintenance activities under 10 CFR 50.65 (a)(4) of the Maintenance Rule. However, the

guidance also states that the status of systems, structures, and components during these type of activities should be addressed

to ensure operability in accordance with Technical Specifications. This scope of this screening is to assess operability of the

AFW pumps during the period the line is isolated.

In preparation for removing the internals ofAF-117, this check valve will be isolated by closing manual valves on both sides

ofAF-117. Since the line where AF-) 17 is located is common to all four AFW pumps, an alternate mini-recirc flowpath is

desirable for AFW system operability. The header upstream ofAF-Il 7 and the manual isolation valve AF-I includes relief

valve AF-4035 which is installed in the line to prevent over-pressuri:ation of the line. The nominal relief setting is 50psig

with an accumulation of 5 psig. The valve is not classified as a safety-related valve..

The 50.59 evaluation EVAL 2002-005 established that manual control ofAFWflow to maintain steam generator level

following a transient or accident was part of the plant's licensing basis. This was done in response to a condition that was

identified where, following a loss of instrument air, all the AFW mini-recirc control valves willfail (closed) and may not be

detected by the operator. Normal practice for controlling AFW flow is to throttle or close the discharge valve even up to the

point of no forward flow through the pump. In this situation, the operator would have to establish sufficientforwardflow to

maintain pump cooling or secure the pump(s) as needed There was no procedural direction in the EOPs to do either of

these actions. EVAL 2000-005 evaluated the procedure changes which added directions to operators to respond to a recirc

valve failure or a loss of instrument air, and the impacts on the AFW pump and motors if the AFW pumps had to be secured

and restarted to maintain SG level. It was determined that the changes did not require NRC approval.

PBF-1515c

Page 24: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant SCR 2002-0377

10 CFR 50.59/72.48 SCREENING (NEW RULE) Verify SCR number on all pages Page 2

In order to maintain a recirculationflowpath for the AFW pumps while removing the internals ofAF-117, a recirculation flow path will be provided during the time the recirculation header back to the condensate storage tank (CST) isolated. The

flow path that will be credited is through the relief valve AF-4035 which is located upstream of the AF-! valve. AF-) will be closed to isolate the AF-) 17 valve. If the AFW pumps start during the time the header is isolated, then the line will become

pressurized because the line is isolated, andrelief valve AF-4035 should lift. Calculation 2002-0026, "Evaluation ofAFW

Recirculation Line Relief Valve AF-4035, " evaluates the relief capacity of the piping network of the individual pump recirc lines to the header and through the relief valve. This calculation determined that adequate the relief valve can pass the requiredflow for cooling all pumps

AF-4035 is not a safety-related valve and there is no redundant valve. Ifa transient or accident occurs and this valve fails to function, the control room operators will have to maintain adequate forward flow in the running pumps and secure other pumps as required.. In order to alert the control room ifthe relief valve fails to open, a Level 3 Dedicated Operator per OM

3.26, "Use of Dedicated Operators" will be stationed near the AF-4035 valve during the time the recirculation line is isolated. The Level 3 Dedicated Operator will remain in constant radio communications with the control room, and the operator's only function is to monitor actuation ofAF-4035, and to notify the control room if the valve fails to open after AFW pumps start. 1IfAF-4035 fails to relieve (open), the dedicated operator will notify the control room immediately while the pumps are still being cooled byforwardflow, and the control room operators will know that when they reduce AFWflow to control steam generator level they will have to maintain the required minimum forward flow in AFW pumps or secure pumps as necessary as directed by the EOPs as discussed above.

A discharge hose will be attached to AF-4035, and the hose will be routed to an appropriate location. The hose will be secured to prevent movement in the event of a AFWpump auto start. These measures will prevent damage to other plant equipment should the relief valve open after an AFW pump auto start.

-(1.2 Search the PBNP Current Licensing Basis (CLB) as follows: Final Safety Analysis Report (FSAR), FSAR Change Requests (FCRs) with assigned numbers, the Fire Protection Evaluation Report (FPER), the CLB (Regulatory) Commitment Database, the Technical Specifications, the Technical Specifications Bases, and the Technical Requirements Manual. Search the ISFSI licensing basis as follows: VSC-24 Safety Analysis Report, the VSC-24 Certificate of Compliance, the CLB (Regulatory) Commitment Database, and the VSC-24 10 CFR 72.212 Site Evaluation Report. Describe the pertinent design function(s), performance requirements, and methods of evaluation for both the plant and for the cask/ISFSI as appropriate. Identify where the pertinent information is described in the above documents (by document section number and title). (Resource Manual 5.3.1 and NEI 96-07, App. B, B.2)

The Auxiliary Feedwater (AFW) system has thefollowingfunctions described in the licensing basis:

a. To automatically start and ensure that adequate feedwater is supplied to the steam generators for heat removal during accidents which may result in a main steam safety valve opening (Loss of Normal Feedwater - including

A TWS, and Loss ofAC to the Station Auxiliaries). b. To automatically start and provide flow to maintain steam generator levels during accidents which require or

result in rapid reactor coolant system cooldown (Steam Generator Tube Rupture and Rupture of a Steam Pipe).

c. To allow the isolation of all lines to the ruptured steam generator in the SGTR event. d To provide sufficientfeedwater to remove decay heat from both units for one hour during a station blackout

(SBO) event (TDAFP only). e. To provide sufficient flow to the steam generators to remove decay heat to achieve cold shutdown within 72

hours following a plant fire (Appendix R). f To withstand a seismic event (i.e., the seismic Class I portions of the system) and to ensure that steam

generator levels are maintained during a seismic event. g. To provide flow to the steam generators during plant startup and shutdown, and during hot shutdown or hot standby

conditions for chemical additions and when operation of the main feedwater and condensate systems is not warranted

The minimum recirculation lines for the auxiliary feedwater pumps and the recirculation header for the auxiliary feedwater

pumps have the design function to provide recirculationflowpaths from the auxiliary feedwater pumps to prevent hydraulic

instabilities and to dissipate pump heat.

CLB References FSAR 7.2.3.2- Specific Control and Protection fnteradtions

ý01 --

Page 25: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant SCR 2002-0377

10 CFR 50.59/72.48 SCREENING (NEW RULE) Verify SCR number on all pages I Page 3

FSAR 7.3.3.4 - Manual AFW Flow Control During Plant Shutdown FSAR Section 7.4.1 - AMSA C FSAR Section 10. 1 - Steam and Power Conversion System FSAR Section 10.2 -Auxiliary Feedwater FSAR Figure 10.2-1 Sheet I - Bech M-217 Sh. I - Auxiliary Feedwater System FSA R Figure 10.2-1 Sheet 2 - Bech Mf-217 Si 2 - A uxiliary Feedwater System FSAR Section 14. 1. 10 - Loss of Normal Feedwater FSAR Section 14.1.11 -Loss ofAllAC Power to the Station Auxiliaries

FSAR Section 14.2.4 - Steam Generator Tube Rupture FSAR Section 14.2.5 - Rupture of a Steam Pipe FSAR AppendL€ A. 1 - Station Blackout FPER 5.2.2 - Safe Shutdown Systems and Equipment FPER 5.2.5.2.3 -Auxiliary Feedwater Pump Room

Tech Spec 3.7. 5 - A muxiliary Feedwater

Tech Spec Bases B 3.7.5 - Auxiliary Feedwater

13 Does the proposed activity involve a change to any Technical Specification? Changes to Technical Specifications require a License Amendment Request (Resource Manual Section 5.3.1.2).

Technical Specification Change: El Yes 0 No

If a Technical Specification change is required, explain what the change should be and why it is required.

1.4 Does the proposed activity involve a change to the temis, conditions or specifications incorporated in any VSC-24 cask

Certificate of Compliance (CoC)? Changes to a VSC-24 cask Certificate of Compliance require a CoC amendment request.

- ]Yes ED No

If a storage cask Certificate of Compliance change is required, explain what the change should be and why it is required.

-_ 10 CFR 50.59 SCREENING

PART 11 (50.59) - DETERMINE IF THE CHANGE INVOLVES A DESIGN FUNCTION (Resource Manual 5.3.2)

Compare the proposed activity to the relevant CLB descriptions, and answer the following questions:

YES NO QUESTION

0 C3 Does the proposed activity involve Safety Analyses or structures, systems and components (SSCs) credited in the

Safety Analyses?

0] El Does the proposed activity involve SSCs that support SSC(s) credited in the Safety Analyses?

0] El Does the proposed activity involve SSCs whose failure could initiate a transient (e.g., reactor trip, loss of feedwater, etc.) or accident, OR whose failure could impact SSC(s) credited in the Safety Analyses?

0] El Does the proposed activity involve CLB-described SSCs or procedural controls that perform functions that are

required by, or otherwise necessary to comply with, regulations, license conditions, orders or technical specifications?

El 0 Does the activity involve a method ofevaltation described in the FSAR?

El 0] Is the activity a test or experiment? (i.e., a non-passive activity which gathers data)

El 0] Does the activity exceed or potentially affect a design basis limit for afission product barrier (DBLFPB)?

(NOTE: If THIS questions is answered YES, a 10 CFR 50.59 Evaluation is required.)

Page 26: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant SCR 2002-0377 10 CFR 50.59/72.48 SCREENING (NEW RULE) Verify SCR number on all pages

Page 4 I. t.

Sf fthe answers to AL.L ofthese questions are NO, mark Part III as not applicable, document the 10 CFR 50.59 screening in the conclusion section (Part IV), then proceed directly to Part V - 10 CFR 72.48 Pre-screening Questions.

If any of the above questions are marked YES, identify below the specific design function(s), method of evaluation(s) or DBLFPB(s) involved.

The minimum recirculation lines for the auxiliaryfeedwater pumps and the recirculation header for the auxiliaryfeedivater pumps have the finction ofproviding recirculationflowpathsfrom the auxiliaryfeedwater pumps to prevent hydraulic instabilities and to dissipate pump heat. Hydraulic instabilities are prevented by the presence offlow restricting orifices in the individual AFW pump recirculation lines, so the function of maintaining individual pump cooling and the impact of diverted CST water are the concerns.

PART III (50.59) - DETERMINE WHETHER THE ACTIVITY INVOLVES ADVERSE EFFECTS (Resource Manual 5.3.3)

If ALL the questions in Part II are answered NO, then Part III is E] NOT APPLICABLE.

Answer the following questions to determine if the activity has an adverse effect on a design function. Any YES answer means that a 10 CFR 50.59 Evaluation is required; EXCEPT where noted in Part II1.3.

111.1 CHANGES TO THE FACILITY OR PROCEDURES

YES NO QUESTION

[] 0] Does the activity adversely affect the design function of an SSC credited in safety analyses?

1] 0] Does the activity adversely affect the method of performing or controlling the design function of an SSC credited in the safety analyses?

If any answer is YES, a 10 CFR 50.59 Evaluation is required. If both answers are NO, describe the basis for the conclusion (attach additional discussion as necessary):

The current licensing basis method for maintaining and controlling adequate AFW pumpflowfor pump cooling was established in E VAL 2002-005 and associated FSAR change request FCR 02-019. 50.59 evaluation EVAL 2002-005 evaluated the procedure changes which added directions to operators to respond to a recirculation valve failure or a loss of instrument air, and the impacts on the AFW pump and motors ifthe AFW pumps had to be secured and restarted to maintain SG level. The proposed method of maintaining AFW system operability utilizing relief valve AF-4035 and having a dedicated operator to notify the control room if the valve fails to open provides prompt notification to the control room operators that the recirculation header is not functional, and therefore there is no adverse effect on manual control ofAFW pump forward flow to ensure AFW pump cooling is maintained

If the recirculation header relief valve opens, recirculation water flow will be diverted from the CST. The loss of CST inventory due to the valve opening and recirculation water spilling only affects the non-safety-related water source for the AFW system. The required minimum CST water is based on the station blackout (SBO) event. In a SBO event, only the steam -driven AFW pump is available to provide AFWflow to maintain steam generator level. TS Bases B 3.7.6, Condensate Storage Tank (CS7) states, "...the minimum amount of water in the CST assures the capability to maintain the unit in MODE 3for at least one hour concurrent with a Loss of all AC power, while then allowing sufficient operator action time to transfer AFWsuction to the service water system." A concurrent single failure or design basis accident need not be assumed during a station blackout event (FSAR Appendix A. 1, Station Blackout). The closing of the recirculation valve can be credited to prevent flow diversion. RequiredAFWflowfor the first hour is approximately 200 gpm (see FSAR 14. 1.1, for example) which is well above the value required for pump cooling. After the first hour, service water will be the source of AFW water which is essentially a limitless source. Therefore, based on the above, maintaining AFWV operabilit in the manner described above does not have an adverse effect on the design fitnctions of providing sufficient water to the steam generators or for ensuring pump cooling

Pn1u*.1;1'

Page 27: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant SCR 2002-0377 10 CFR 50.59/72.48 SCREENING (NEW RULE) Verify SCR number on all pages

i Page 5

1.. 11I.2 CHANGES TO A METHOD OF EVALUATION

(If the activity does not involve a method of evaluation, these questions are Z NOT APPLICABLE.)

YES NO QUESTION

El [I Does the activity use a revised or different method of evaluation for performing safety analyses than that described in the CLB?

0l El Does the activity use a revised or different method of evaluation for evaluating SSCs credited in safety analyses than that described in the CLB?

If any answer is YES, a 10 CFR 50.59 Evaluation is required. If both answers are NO, describe the basis for the conclusion (attach additional discussion, as necessary).

111.3 TESTS OR EXPERIMENTS

If the activity is not a test or experiment, the questions in III.3.a and III.3.b are 0 NOT APPLICABLE.

a. Answer these two questions first:

YES NO QUESTION

E] El Is the proposed test or experiment bounded by other tests or experiments that are described in the CLB?

Cl El Are the SSCs affected by the proposed test or experiment isolated from the facility?

If the answerto BOTH questions inV.3.a is NO continue to III.3.b. If the answer to EITHER question is'YES, then describe the basis.

b. Answer these additional questions ONLY for tests or experiments which do NOT meet the criteria given in III.3.a above.

If the answer to either question in III.3.a is YES, then these three questions are Z NOT APPLICABLE.

YES NO QUESTION

El El Does the activity utilize or control an SSC in a manner that is outside the reference bounds of the design bases as described in the CLB?

[E El Does the activity utilize or control an SSC in a manner that is inconsistent with the analyses or descriptions in the CLB?

El El Does the activity place the facility in a condition not previously evaluated or that could affect the capability of an SSC to perform its intended functions?

If any answer in III.3 .b is YES, a 10 CFR 50.59 Evaluation is required. If the answers in III.3.b are ALL NO describe the basis for the conclusion (attach additional discussion as necessary):

Pnc.s t 4:-

Page 28: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant

10 CFR 50.59/72.48 SCREENING (NEW RULE) I

SCR 2002-0377

Verify SCR number on all pages

Page 6

a.;•.:art IV - 10 CFR 50.59 SCREENING CONCLUSION (Resource Manual 5.3.4).

Check all that apply:

A 10 CFR 50.59 Evaluation is [] required or 0 NOT required.

A Point Beach FSAR change is 0] required or [] NOT required. If an FSAR change is required, then initiate an FSAR Change Request (FCR) per NP 5.2.6.

A Regulatory Commitment (CLB Commitment Database) change is E] required or [D NOT required. If a Regulatory Commitment Change is required, initiate a commitment change per NP 5.1.7.

A Technical Specification Bases change is [I required or 0 NOT required. If a change to the Technical Specification Bases is required, then initiate a Technical Specification Bases change per NP 5.2.15.

A Technical Requirements Manual change is I[ required or 0D NOT required. If a change to the Technical Requirements Manual is required, then initiate a Technical Requirements Manual change per NP 5.2.15.

10 CFR 72.48 SCREENING

NOTE: NET 96-07. Appendix B. Guidelines for 10 CFR 72.48 Implementation should be used for guidance to determine the proper responses for 72.48 screenings.

PART V (72.48) - 10 CFR 72.48 INITIAL SCREENING QUESTIONS

Part V determines if a full 10 CFR 72.48 screening is required to be completed (Parts VI and VII) for the proposed activity.

SYES NO QUESTION

El 0 Does the proposed activity involve IN ANY MANNER the dry-fuel storage cask(s), the cask transfer/transportequipment, any ISFSI facility SSC(s), or any ISFSI facility monitoring as follows: Multi-Assembly Sealed Basket (MSB), MSB Transfer Cask (MTC), MTC Lifting Yoke, Ventilated Concrete Cask (VCC), Ventilated Storage Cask (VSC), VSC Transporter (VCST), ISFSI Storage Pad Facility, ISFSI Storage Pad Data/Communication Links, or PPCSIISFSI Continuous Temperature Monitoring System?

El 0] Does the proposed activity involve IN ANY MANNER SSC(s) installed in the plant specifically added to support cask loading/unloading activities, as follows: Cask Dewatering System (CDW), Cask Reflood System (CRF), or Hydrogen Monitoring System?

El 0] Does the proposed activity involve IN ANY MANNER SSC(s) needed for plant operation which are also used to support cask loadinglunloading activities, as follows: Spent Fuel Pool (SFP), SFP Cooling and Filtration (SF), Primary Auxiliary Building Ventilation System (VNPAB), Drumming Area Ventilation System (VNDRM), R.E-105 (SFP Low Range Monitor), RE-135 (SP High Range Monitor), RE-221 (Drumming Area Vent Gas Monitor), RE-325 (Drumming Area Exhaust Low-Range Gas Monitor), PAB Crane, SFP Platform Bridge, Truck Access Area, or Decon Area?

El 0] Does the proposed activity involve a change to Point Beach CLB design criteria for external events such as earthquakes, tornadoes, high winds, flooding, etc.?

El 0] Does the activity involve plant heavy load requirements or procedures for areas of the plant used to support cask loadinslunloading activities?

El z Does the activity involve any potential for fire or explosion where casks are loaded, unloaded, transported or stored?

If ANY of the Part V questions are answered YES, then a full 10 CFR 72.43 screening is required and answers to the questions in Part VI and Part VII are to be provided. If ALL the questions in Part V are answered NO, then check Parts VI and VII as not applicable. Complete Part VIII to document the conclusion that no 10 CFR 72.48 evaluation is required.

flf. I ; 4

Page 29: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant SCR 2002-0377

10 CFR 50.59/72.48 SCREENING (NEW RULE) Verify SCR number on all pages Page 7

-'.?ART VI (72.48) - DETERMINE IF THE CHANGE INVOLVES A ISFSI LICENSING BASIS DESIGN FUNCTION

(If ALL the questions in Part V are NO then Part VI is [D NOT APPLICABLE.)

Compare the proposed activity to the relevant portions of the ISFSI licensing basis and answer the following questions:

YES NO QUESTION

El El Does the proposed activity involve cask/ISFSI Safety Analyses or plant/caskIISFSI structures, systems and components (SSCs) credited in the Safety Analyses?

0l E3 Does the proposed activity involve plant, cask or ISFSI SSCs that support SSC(s) credited in the Safety Analyses?

El El Does the proposed activity involve plant, cask or ISFSI SSCs whose function is relied upon for prevention of a radioactive release, OR whose failure could impact SSC(s) credited in the Safety Analyses?

[E E] Does the proposed activity involve cask/ISFSI described SSCs or procedural controls that perform functions that are required by, or otherwise necessary to comply with, regulations, license conditions, CoC conditions, or orders?

El El Does the activity involve a method of evaluation described in the ISFSI licensing basis?

El El Is the activity a test or experiment? (i.e., a non-passive activity which gathers data)

El El Does the activity exceed or potentially affect a cask design basis limit for afission product barrier (DBLFPB)? (NOTE: If THIS questions is answered YES, a 10 CFR 72.48 Evaluation is required.)

If the answers to ALL of these questions are NO, mark Parts VII as not applicable, and document the 10 CFR 72.48 screening in the conclusion section (Part VIII).

Ifany of the above questions are marked YES. identify below the specific design function(s), method of evaluation(s) or DBLFPB(s) involved.

PART VII (72.48) - DETERMINE WHETHER THE ACTIVITY INVOLVES ADVERSE EFFECTS (NEI 96-07,

Appendix B, Section B.4.2.1)

(If ALL the questions in Part V or Part VI are answered NO then Part VII is [] NOT APPLICABLE.)

Answer the following questions to determine if the activity has an adverse effect on a design function. Any YES answer means that a

10 CFR 72.48 Evaluation is required; EXCEPT where noted in Part VII3.

VII.1 Changes to the Facility or Procedures

YES NO QUESTION

El El Does the activity adversely affect the design function of a plant, cask, or ISFSI SSC credited in safety

analyses?

El El Does the activity adversely affect the method of performing or controlling the design function of a plant,

cask, or ISFSI SSC credited in the safety analyses?

If any answer is YES, a 10 CFR 72.48 Evaluation is required. If both answers are NO, describe the basis for the conclusion

(attach additional discussion, as necessary):

PlBF-- 51 5

Page 30: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant SCR 2002-0377 10 CFR 50.59/72.48 SCREENING (NEW RULE) Verify SCR number on all pages

Page 8

!tlI.2 Changes to a Method of Evaluation

(If the activity does not involve a method of evaluation, these questions are Z NOT APPLICABLE.)

YES NO QUESTION

El El Does the activity use a revised or different method of evaluation for performing safety analyses than that described in a cask SAR?

El [3 Does the activity use a revised or different method of evaluation for evaluating SSCs credited in safety analyses than that described in a cask SAR?

If any answer is YES. a 10 CFR 72.48 Evaluation is required. If both answers are NO, describe the basis for the conclusion (attach additional discussion, as necessary):

VII.3 Tests or Experiments

(If the activity is not a test or experiment, the questions in VII.3.a and VII.3.b are ED NOT APPLICABLE.)

a. Answer these two questions first:

YES NO QUESTION

D El Is the proposed test or experiment bounded by other tests or experiments that are described in the cask ISFSI licensing basis?

."l El Are the SSCs affected by the proposed test or experiment isolated from the cask(s) or ISFSI facility?

If the answer to both questions is • continue to VII.3.b. If the answer-to EITHER question is YES, then briefly describe

the basis.

b. Answer these additional questions ONLY for tests or experiments which do not meet the criteria given in VII.3.a above.

If the answer to either question in VII.3.a is YES. then these three questions are 0 NOT APPLICABLE:

YES NO QUESTION

El El Does the activity utilize or control an SSC in a manner that is outside the reference bounds of the design bases as described in the ISFSI licensing basis?

El El Does the activity utilize or control a plant, cask or ISFSI facility SSC in a manner that is inconsistent with the analyses or descriptions in the ISFSI licensing basis?

El El Does the activity place the cask or ISFSI facility in a condition not previously evaluated or that could affect the capability of a plant, cask, or ISFSI SSC to perform its intended functions?

If any answer in VII.3.b is YES, a 10 CFR 72.48 Evaluation is required. If the answers are all NO, describe the basis for the conclusion (attach additional discussion as necessary):

PBF-1515cRer,-nee NqP -, I It

Page 31: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant SCR 2002-0377

10 CFR 50.59/72.48 SCREENING (NEW RULE) Verify SCR number on all pages

Page 9

I.. ?ART VIII - DOCUMENT THE CONCLUSION OF THE 10 CFR 72.48 SCREENING

Check all that apply:

A 10 CFR 72.48 Evaluation is E] required or 0 NOT required. Obtain a screening number and provide the original to Records Management regardless of the conclusion of the 50.59 or 72.48 screening.

A VSC-24 cask Safety Analysis Report change is [] required or 0Z NOT required. Ifa VSC-24 cask SAR change is required, then contact the Point Beach Dry Fuel Storage group supervisor.

A Regulatory Commitment (CLB Commitment Database) change is E] required or (0 NOT required. Ifa Regulatory

Commitment Change is required, initiate a commitment change per NP 5.1.7.

A change to the VSC-24 10 CFR 72.212 Site Evaluation Report is [] required or 0 NOT required. If a VSC-24 10 CFR 72.212 Site Evaluation Report change is required, then contact the Point Beach Dry Fuel Storage group supervisor.

PBF-15 l .c S,...... I AlfV );'111

Rdlcren•.e "NP' 4 1

Page 32: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant DESIGN INPUT CHECKLIST

Sdification or Temporary Modification Number: MR 02-029

Title: AUX FEED MINI RECIRC SAFETY UPGRADE / REMOVE AF-117 INTERNALS

INSTRUCTIONS: Consider the basic functions of each structure, system, and component, (SSC), when answering the questions. The designer shall check the appropriate box for each design input or section. All inputs that apply to the design shall be explained. The

explanation may be documented on this checklist or in the design summary. The reviewer shall review the checklist, and any differences between the designer and the reviewer should be addressed. This checklist addresses most design concerns, but is not all encompassing. Any additional concerns should be addressed in the design summary.

(Updates to this form covered by SCR 97-411.)

APPLIES TO DESIGN

YES NO

A. General codes, standards, regulatory requirements, and design criteria.

1. Are any of the PBNP FSAR general design criteria applicable? (Reference FSAR, Section 1.3. Identify and address design criteria as appropriate.)

GDC 1, Quality Standards - The AOVs are already safety related. No physical changes are

required to these valves. The AF-117 valve is not safety related.

GDC 2, Performance Standards - The recirculation piping is already analyzed as seismic Class 1 up to the manual valves (AF-1527/40/53), and is non-seismic downstream to the CSTs. This classification upgrade will not affect the seismic analysis.

GDC 4, Sharing of Systems - The recirculation piping is common to both units. The check valve

internals are being removed to prevent a single active failure from affecting allfour of the AFW pumps.

GDC 5, Records Requirement - This modiftcation package meets this requirements for records.

GDC 37, Engineered Safety Features Basis for Design -The safety upgrade will improve the ability

of the AFW pumps to perform their emergency cooling function.

GDC 38, Reliability and Testability of Engineered Safety Features - The recirculation line allows

for testing of the AFW pumps without sending flow to the steam generators.

GDC 41, Engineered Safety Features Performance Capability - The recirculation line will now

support the operation of the AFW pumps to prevent a common mode failure of all AFWpumps.

The AF-117 check valve internals will be removed to support this.

2. Are any design requirements contained in commitments affected? (Reference CLB database and the 0 n Safety Evaluation/Screening associated with this change.)

i•., Upgrade is being performed in accordance with letter NRC 2002-0068, which committed PBNP to

i - upgrade the open function of the AFWpump mini-recirc AOVs to safety related. See 50.59 SCR

2002-0359 and SCR 2002-0377.

3. Meet State of Wisconsin Administrative Code requirements? (Refer to ILHR 41.42, PSC 114, and 0 other sections as appropriate for requirements.)

4. Meet existing DNR permits or require DNR approval? (Contact WE Environmental Department.) El 0

5. Consider the effect of design and accident conditions, such as pressure, temperature, fluid chemistry, El and radiation on components, including internal elastomers and material coating compatibility

PBF- 1584R etrent e NP722P-1cf. I ný I I

Page 33: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

DESIGN INPUT CHECKLIST APPLIES TO DESIGN

YES NO

(Changes in design parameters may impact Environmental Qualification.)

6. Incorporate new types/models of equipment not presently used at PBNP? (Contact EPIX coordinator.) El 0

7. Affect accessibility of any equipment? Consider interim conditions, future maintenance, and in-service inspection. (Reference CIMs and drawings for manufacturer's clearance requirements.)

8. Require breaching a High Energy Line Break (HELB) barrier? (Reference NP 8.4.16) If yes, EQ engineer review required.

9. Consider operating experience from PBNP and industry events. (Reference DG-G04 for operatingCE experience reviews and NPRDS, NODIL, CHAMPS, INPO Keywords, or other databases.)

Discussion with similar vintage plants has confirmed that a single non-safety related recirculation line has been used to support AFW pump operation.

10. Consider failure effects on structures, systems, and components: (Contact the NSA-PSA group for guidance and scope).

a. The design discusses those events/accidents which the system/components are to withstand? 0 El The AFW recirculation line is required to support AFW pump operation during events where AFW is required to provide reactor heat removal, Most of the recirculation piping is nonSeismic, as are the CSTs, but afailure would be conservative in terms of recirc flow.

'" • b. The failure effect of the system/components: (Reference the NSA-PSA Group, Operating

Experience, & IEEE-352-1975.) El 9 How components may fail, and the effect of the failure on the system and related systems? * What mechanisms might produce failures? (Consider both equipment and human induced

failures.) * How a failure would be detected? * What provisions are included to compensate for the failure?

AF-117 internals are being removed to prevent a single active failure from making alIAFW

pumps inoperable.

11. Does the design add or remove components in containment?

a. Change the amount of exposed aluminum or zinc in containment? (Reference DG-G07 and El El FSAR Section 5.6.)

b. Introduce materials into containment that could affect sump performance or lead to equipment degradation? (Reference DG-G07.)

c. Decrease free volume of containment? El El

d. Require addition or modification of a containment penetration boundary? (Consult the E containment system engineer.)

e. Require painting in containment? (Reference MI 36.3.) El El

PBF-1584 Revtsion t0 081I9/02 Paee 2 of 13 Reference NP 7 2 2

Page 34: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

DESIGN INPUT CHECKLIST

(7-" 12. Consider potential for fuel failure?

a. Affect fuel handling equipment?

b. Present the potential for introducing foreign material/debris into the RCS or connected systems?

c. Affect core barrel flow patterns? ("Baffle jetting" concerns)

13. Meet requirements to abandon equipment if applicable. (Reference NP 7.1.5)

B. Mechanical requirements. (Contact Mechanical Design Engineering for guidance.)

1. Have applicable ASME Boiler & Pressure Vessel codes or other standards been identified? (Reference the applicable specification. In addition, safety-related components should be reconciled with DG-M16, and QA components should be reconciled with ANSI N45.2.)

Installation will beperformed in accordance with USAS B31.1 -1967.

2. Affect or add components/systems to ASME Section XI class 1, 2, or 3 equipment? (Reference PBNP CHAMPS, CBD drawings, and IST Coordinator. If YES, follow NP 7.2.5, Repair/Replacement Program.)

3. Require State of Wisconsin Administrative Code permits/approvals? (Reference NP 7.4.9, Wisconsin Administrative Code for Boilers and Pressure Vessels or the Authorized Inspector.)

4. Consider component performance requirements such as capacity, rating, output?

5. Consider hydraulic requirements such as pump net positive suction heads, allowable pressure drops, allowable fluid velocities and pressures, valve trim requirements, packing/seal requirements?

6. Provide vents, drains, and sample points to accommodate operational, maintenance and testing needs?

7. Require service water? (Both essential and nonessential service water loads are modeled, and load changes must be evaluated. Contact the SWAP Coordinator.)

8. Require the addition of check valves? (Reference DG-M13 for selection guidance.)

9. Require and evaluate any additional loading on instrument or service air, circ, fire protection, or demineralized water, or other system?

PBF-1584

Reviston 10 08119/02

APPLIES TO DESIGN

YES NO

ED

El 1:1

o3 El []

El

El

El

El

El

1:1

0

0]

0]

0]

Reference NP 7 2.2Page 3 of 13

Page 35: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

DESIGN INPUT CHECKLIST

10. Evaluate any additional loading on HVAC systems or affect ventilation flow during or after \k- J installation? (This will require an EQ review for potential updates to EQSS, EQML & EQMR.)

I1. Affect ventilation barriers, including containment, primary auxiliary building, or control room?

12. Require insulation? (Reference WE specification PB-485 for insulation, and NP 1.9.10 for asbestos control.)

13. Require lubrication? (Reference Lubrication Manual.)

14. Require an independent means of pressure relief? (Reference B31.1.)

15. Affect the assigned system design pressure or temperature?

16. Involve cobalt-laden materials into the RCS or into systems that supply the RCS? (Reference NP 4.2.29, "Source Term Reduction Program.")

17. Are new materials and their coatings/plating compatible with system chemistry and disposal systems (. (NP 8.4.15)?

18. Affect embedded or buried piping?

C. Electrical requirements. (Contact Electrical Design Engineering for guidance.)

1. Consider design conditions such as ampacity, voltage drop?

2. Consider component and system performance requirements, such as current, voltage, or power?

3. Consider redundancy, diversity and separation requirements of structures, systems and components? (Reference DG-E07 for separation of electrical circuits.)

4. Comply with protective relaying requirements of equipment and systems?

5. Selection of overcurrent devices for proper protection and coordination? (Reference DG-E04 for selection of molded case circuit breakers.)

6. Affect available fault current at any bus?

PBF-1584 n .. : ._- ,, ,oi n,.,l-, PR _gc 4 of I I

APPLIES TO DESIGN

YES NO

[] [

[] [

[] [

[] [

El [

El

[] [

[] [

[] [

El [

[] [

El [

El [

El [

El [

Reterence NP 7 2 2

Page 36: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

DESIGN INPUT CHECKLIST

7. Assure that all added cables meet fire retardancy requirements? (Reference FPER Section 4.1.8, IEEE 383.)

8. Be compatible with existing electrical insulation and wiring?

9. Affect ampacity of existing cables?

10. Maintain UL (or equivalent) listings?

11. Alter the voltage harmonic distortion content or change the non-linear loading (i.e., the addition of

switching power supplies, the alteration of the circuit's power factor, etc.) on a vital or sensitive

instrument bus?

12. Add new raceways? (Reference DG-E03 for electrical raceway sizing and DG-E02.)

13. Add cables to existing electrical raceways?

14. Be routed through fire wrapped raceways?

15. Affect the station grounding or lightning protection system?

16. Make any vital circuit susceptible to ground?

17. Affect emergency diesel loading? (Contact Electrical Design Analysis group for guidance.)

18. Add more station battery loading?

19. Add load to a vital bus?

20. Add load to a non-vital bus?

21. Be compatible with service transformer capacity?

22. Consider electromagnetic interference between new/existing equipment and electromagnetic coupling

interactions between circuits?

PBF-1584 v-.; in nvoivn' Pace 5 of 13

APPLIES TO DESIGN

YES NO

El0 El 0]

El 0]

El 0]

El

El

El

El

El

El

El

El El

El

0]

0]

0]

0]

0]

0]

0]

0]

0]

Reterence NP 7 2 2

Page 37: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

APPLIES TO DESIGN

DESIGN INPUT CHECKLIST YES NO

- 23. Affect embedded conduits or buried cables, including the station grounding system? El (-,

D. Instrumentation and control requirements. (Contact I&C Design Engineering for guidance.)

1. Consider design conditions such as pressure, temperature, fluid chemistry, amperage, voltage? E 0

2. Have the instruments been properly selected for the application? El 0

3. Have sufficient instruments for operators to monitor the process? El 0

4. Have appropriate instrument scales? El 0

5. Have the instruments, control switches, and indicating devices been appropriately located for human E0 0 factors (both for operations and maintenance)? (Reference DG-GO 1.)

6. Have alarms for off-normal conditions? El 0

7. Be capable of or require remote and/or local operation? El 0

8. Be capable of or require manual and/or automatic operation? El 0

9. Require calibration and maintenance requirements for the instruments to be specified? El 0

10. Have specified the instruments with proper range and accuracy? El 0

11. Address solid state vulnerability to RFI? El 0

12. Consider software and programming/programmable settings of digital or electronic equipment? El 0

13. Affect logic circuits or associated GL 96-01 review/required testing? Contact I&C System

Engineering group.

PBF-1584 Pnae 6 of 13 Reteren.c NP7 2 2

Revisio)n' |10 "8,19,02.;

Page 38: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

DESIGN INPUT CHECKLISTAPPLIES TO DESIGN

YES NO

(>.. Structural requirements. (Contact Civil Design Engineering for guidance.) 1. Affect or scope seismically qualified equipment (Class I or 2) and therefore require a seismic

qualification evaluation? (Reference NP 7.7.2, "Seismic Qualification of Equipment.")

2. Affect seismic boundaries?

3. Affect stress calculations of pipe? (Reference DG-M09.)

The removal of the internals will have a negligible effect on the piping analysis caused by the slight weight reduction.

4. Affect the loading or require changes to existing equipment foundations?

5. Affect wall stress calculations for pressurized concrete cubicles or structures?

6. Require analysis of non-seismic components placed over or adjacent to seismic components?

7. Add items which span between two separate seismic areas/buildings? (The effect of the relative movement must be addressed.)

8. -Require clearance review for seismic movement or thermal expansion considerations?

9. Require a floor or wall loading analysis? (Reference Bechtel C-dwgs.)

10. Require the addition of new supports, hangers, or foundations or add weight to or between existing supports, hangers, embeds, or foundations during installation or post-installation? (Reference DG-M09 and DG-M10 for pipe support.)

11. Add new or add load to seismically qualified raceways? (Reference NP 7.7.2, "Seismic Qualification of Equipment.")

12. Modify, attach to, or locate within the proximity of masonry block walls? (Reference IEB 80-11 Block Wall Program.)

13. Require core drills, expansion anchors, or re-bar cuts? (Reference DG-C0l for expansion anchor

design and installation.)

14. Create an external or internal missile hazard?

15. Consider wind and storm loading on external structures?

PBF-1584 p ......... M MOM• Paue 7 of 13

El

0

El

El

El

El

El

[]

El

El

El

El

El

0]

0]

0]

0]

0]

0]

Reference NP 7 2 2

Page 39: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

APPLIES TO DESIGN DESIGN INPUT CHECKLIST YES NO

' 16. Require protection from high energy line breakjet? (Refer to FSAR Appendix A.2.) El 0

17. Consider dynamic requirements such as live loading, vibration, and shock/impact? El 0

F. Programs

1. ASME Section XI and QA considerations:

a. Affect IST acceptance criteria or calculations? (Contact Component Engineering.) 0 El

The 1I2AF-4002, AF-4007, and AF-4014 valves will now have acceptance criteria for

stroking open. Check valves 1/2AF-114, AF-115, and AF-116 have acceptance criteria to

pass flow. Check valves 1/2AF-173 will be given leakage acceptance criteria.

b. Require classification of new components? (Reference DG-G06 for system, component, and El 0 j(Y part classification.)

c. Affect QA-scope systems or boundaries? (Contact Site Programs Engineering Support for 0 El Q-List.)

The safety-related boundary in the recirculation piping is not being moved. The boundary

Awill remain at theflow restricting orifices (112R0-4003, RO-4008, RO-4015). All components upstream are currently safety related (QA Code 04). QA Code 06 will be added to the Q.listfor the mini-recirc AOVs and check valves, since they now have a function to provide cooling water flow to the AFW pumps.

d. Require special personnel/equipment qualifications not proceduralizecdat PBNP (i.e., El 0 underwater welding)?

e. Require material certification or other certification to ensure quality equal to or better than the affected SSC? (These requirements need to be specified in the specification or purchase El 0 requisition.)

f. Have all design requirements, such as pressure or current rating, been reviewed against lot El 0 descriptions or been specified on purchase requisitions/specifications?

2. Fire protection considerations:

a. Affect access to a fire zone, fire protection equipment or Appendix R safe shutdown equipment, El 0 including manual fire fighting activities? (Reference Section 5.2.1 of Design Guide DG-F01)

b. Affect a fire barrier? (Reference NP 8.4.11 and Fire Barrier Drawings WE PBC-218 El 0 Sheets 1-20, Section 5.2.2 of Design Guide DG-F01)

C. Affect a fire protection system or its performance? (Reference Section 5.2.3 of Design Guide El 0 DG-F01)

PBF-1584 .. ... . of I RclerenLC NP 7 2 2

--- 1. "RIMM 8 •4 ...... I I ••

Page 40: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

APPLIES TO DESIGN DESIGN INPUT CHECKLIST YE...S N._O

d. Increase or decrease permanent combustible loading in a room? (Reference Section 5.2.4 of Design Guide DG-F01)

e. Based on Section 2 and Appendix A of the SSAR, will the change add to, delete from, or affect the performance of safe shutdown systems or equipment? (Reference Section 5.2.5.1 of Design fl Guide DG-F01)

The AFW system is a safe shutdown system credited for Appendix R. The mini-recirc AOVs are credited to be opened in this scenario to provide AFW pump cooling. Upgrading the safety function of the AOVs and removing the AF-117 internals improves this capability.

f. Based on Sections 3, 4, and Appendix C of the SSAR, will the change affect a cable associated with safe shutdown equipment, a safe shutdown power supply, or the physical location of a safe El 0 shutdown cable? (Reference Section 5.2.5.2 of Design Guide DG-FO1)

g. Based on Table 1-1, Section 5 and Appendix D of the SSAR, will the change affect fire area analysis and compliance with Appendix R separation criteria or the conditions of an approved Appendix R exemption for any PBNP Fire Area? (Reference Section 5.2.5.3 of Design Guide DG-FO1, Table 3.2-2 of DBD T-40)

b. Will the change add, remove, or affect the performance of any emergency lighting required for compliance with Section III.J of Appendix R? (Reference Section 5.2.6 of Design Guide DG- El F01)

Will the change add, remove, or affect the performance of any plant communications system relied upon for fire fighting or safe plant shutdown? (Reference Section 5.2.7 of Design Guide El 0 DG-F01)

j. Will the change affect the Reactor Coolant Pump Oil Collection System? (Reference El 09 Section 5.2.8 of Design Guide DG-FO1)

k. Will the change affect the Fire Protection Manual?

1. Will the change affect any of the Supporting Documents listed in the SSAR (Section 6.0) or the El 0 FHAR (Section 4.0)?

If any of the questions a through j are answered "yes", an evaluation must be performed using the applicable sections of the FPCC checklist, PBF-2060 per Section 5 of Design Guide DG-FO0.

3. Flooding protection considerations:

A flooding analysis should be performed if any of the following questions are applicable and answered yes. (Reference Section 4.3 of DG-C02.)

a. Modify potential flooding sources or add new potential flooding sources to a flood zone and thereby increase the direct and/or indirect flooding vulnerability of essential equipment'?

By removing the AF-117 internals, it is now possible for a failure of the AF-4035 relief valve to drain the CSTs and potentially create a flooding problem in the Unit I turbine building.

PBF-1584 Revimon 10 0,JI19/02 Page 9 of 13 Relerence NP7 2 2

Page 41: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

APPLIES TO DESIGN DESIGN INPUT CHECKLIST YES N__O

However, the flow rate would be limited through the reliefvalve, depending on the nature of the failure. Even if the relief valve was passing its design capacity (268 gpm), this water "would adequately drain from the 8' Unit I turbine building through floor drains, subsoil drains, and under doors to the exterior. This flooding would not be as severe as a failure of a

service water or circulating water pipe, and can therefore be considered to be bounded by these events.

b. Degrade existing flood barriers or flood mitigation features providing unanalyzed pathway for flooding to propagate? (Reference Section 3.2 of DG-C02.)

c. Involve the opening of potential flood sources anywhere at the station? (Installation procedures need to address inadvertent flooding. Reference DG-C02, Section 4.4.)

The recirculation line connects to the CSTs. If leakage exists past the AF-2 or AF-9 valves, then the potential exists for draining the CST into the Unit I turbine building. Precautions will be added to the work plan.

d. Reduce the capacity to isolate or cope with flooding? (Reference Sect. 4.2 of DG-C02.) El 0

e. Change plant drainage/backfill requirements? Q

f. Locate essential equipment or supporting systems where it would be susceptible to flooding?

(Flooding conditions may also impact Environmental Qualification.)

r". 4. Environmental considerations:

a. Be subject to adverse environmental conditions during storage or construction? (Reference [i. 0 NP 9.5.2.)

b. Require freeze protection or affect existing freeze protection? El 0

c. Locate safety-related or post accident monitoring equipment in a HARSH environment? El 0 (Reference NP 7.7.1.)

d. Require Environmental Qualification (EQ)? (Reference NP 7.7.1 for EQ qualification.) El 0

e. Be attached to an EQ system/component? (This will require an EQ review for potential updates El 0 to EQSS, EQML & EQMR. Reference EQ master list.)

f. Change environmental parameters (e.g., pressure, temperature, radiation, humidity)? (Reference El 0 NP 7.7.1, "Environmental Qualification of Electrical Equipment."

5. Radiation Protection (RP) and ALARA considerations: (Reference DG-G03, "ALARA Consideration

Guideline for Design & Installation.)

The areas mentioned below are normally within the RCA, but radiological concerns should be considered for SSC outside the RCA also.

PBF-1584 V-.- in nQ,1iwrn Pa.e 10 of 13 Reference NP 722

Page 42: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

APPLIES TO DESIGN DESIGN INPUT CHECKLIST YE...S N...O

a. Affect any SSC in an RWP required area, a contaminated area, or a radiation area, including tI4 opening of a system that may be a radiological concern?

b. Will the change generate excessive radwaste or highly radioactive/contaminated waste? El 0

c. Remove any plant equipment from a potentially contaminated system (including BOP systems)? El 0

d. Result in an anticipated increase in operational or maintenance exposures? (Consider equipment rearrangement to reduce plant life dose?)

e. Result in an expected exposure of greater than I rem for any individual during installation of the change?

L. Result in an anticipated collective exposure of greater than 2 rem for the installation of the change?

If questions d, e, or f apply and are answered yes, then an ALARA review shall be performed.

(Reference NP 4.2.1, Plant ALARA Program.)

,'.: 6. Chemistry considerations:

a. Require or affect established chemistry limits? (Contact system engineer and review chemistry procedures.)

b. Require any routine chemical analyses? (Contact system engineer and review chemistry El 0 procedures.)

c. Require chemical additives? (Contact PBNP Chemistry.) El 0

d. Do new fluids/chemicals need to be evaluated for TRI (Toxic Release Inventory), Control Room habitability, CHES, critical applications, or special disposal requirements? (Contact El 0 Chemistry/Chemical Engineering.) Reference OE 11400, RG 1.78 and NP 3.1.6.

G. Installations

1. Installation requirements/plant conditions have been determined? 0 El

The common recirculation line will be taken out of service for the check valve removal The AFW pumps will be considered operable during this installation by taking credit for relief valve AF-4035 to open and provide adequate flow for pump cooling (per Calculation 2002.0026). Additionally, a level 3 dedicated operator will be present to monitor the relief valve, and notify the control room if it fails to open.

2. Consider test and inspection requirements, including the conditions under which they will be performed? (Reference NP 7.4.1 for pressure test requirements, NP 7.4.3 for post-maintenance and 0 El modification NDE rcquirements, NP 1.2 5 for special test procedures, and OM 4.2.2 for in-service

PBF-1584 v.. nicfrll Paue I I o" 13 Reference NP722

Page 43: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

APPLIES TO DESIGN

DESIGN INPUT CHECKLIST YES NO

tests.)

A non-ASME code leak check will be performed on the check valve gasket.

3. Have post-installation acceptance criteria been properly specified to test the intended function of the E ] component(s)/system?

4. Comply with all WE lifting and rigging requirements? (Reference WE Safety Manual, PBNP Safe Load Path procedures, and NP 8.4.7.)

5. Consider ALARA for installation activities? (i.e., shielding, monitoring water level, etc.) El 0

6. Require special handling, shipping, or environmental conditions for storage or construction? 0 (Reference NP 9.5.2 for material storage.)

7. Consider transportability requirements such as size and shipping weight limitations. El 0

8. Require spare parts or special non-standard items or tools? El 0

9. Will any added components introduce chemical contaminants to the system? (i.e., preservative coating El 0 4. on valves, coatings on weld rod can also introduce contaminants)

10. Consider personnel requirements and limitations, including the qualification.and number of personnel

available for plant operation, maintenance, testing and inspection, and permissible personnel radiation El 0 exposures?

11. Operational requirements under various conditions, such as plant startup, normal plant shutdown, plant

emergency operation, special or infrequent operation, and system abnormal or emergency operation.

a. Require new procedures or procedure changes? (Reference NP 1.2.5.) 0 El Revisions to several IT procedures are required to add acceptance criteria for stroking the

AOVs open, add an exercise test for the recirc check valves, and add acceptance criteria for

the instrument air accumulator AF-173 check valves.

b. Potentially impact other systems, components, or structures during installation? 0 El The AFW system will be affected when the recirculation line is taken out of service.

c. Present installation impacts on plant operations (i.e., fire watches, etc.)? 0 El Per CM 3.26, a level 3 dedicated operator will be used to notify the control room if relief

valve AF-4035 fails to open automatically as needed.

12. Access and administrative requirements for plant security: If any security requirements are applicable,

notify Security.

a. Create an opening >96 in.2 in any wall, ceiling, or other barrier? El 0

b. Require work within 20' of fence? El 0

PBF-1584 Revision 10 08/19/02 Reference NP 7 2 2Page 12 of 13

Page 44: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

APPLIES TO DESIGN DESIGN INPUT CHECKLIST YES NO

YES NOf

c. Affect security equipment and documents, including those containing safeguards information? (Contact Security for design development requirements and design concurrence.)

d. Affect access controls? El 0

13. Safety requirements: a. Affect safety equipment and thereby create personnel hazards (i.e., removal of handrails)? El 0

b. Introduce hazardous material into the plant? (Reference NP 1.9.1.) Ei 0

c. Affect evacuation routes or escape provisions from enclosures? Ei 0

d. Meet OSHA regulations? (Reference Wisc. Electric Safety Manual and OSHA 29 CFR 1910.) 0 0 Installation will be performed in accordance with the safety manual

e. Move any energy sources? If yes, verify installation document covers move, including E transferring danger tags.

f. Require that equipment be grounded? El 0

Designed by: Rob Chapman Date: _ -,___-_

Reviewed by: Kevin Krause Date: 9 " o

PBF-1584 Revision 10 08119/02 Page 13 of 13 Reference NP 7.2 2

Page 45: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

NUCLEAR POWER BUSINESS UNIT

DESIGN VERIFICATION NOTICE

Title of Document AUX FEED MINI RECIRC SAFETY UPGRADE / REMOVE AF-117 INTERNALS

-Document No. MR 02-029 Rev. 0 Date 9/5/2002 Design Verification Method: Design Review [ [ Alternate Caics L.. Qualification Testing

UPDATES TO THIS FORM COVERED BY EXISTING SCR 97-410

REVIEWER CHECKLIST CONSIDERATIONS:Yes No N/A

Were the inputs correctly selected and incorporated into design?

Are assumptions necessary to perform the design activity adequately described and reasonable? Where necessary, are the assumptions identified for subsequent reverifications when the detailed design activities are completed?

Are the appropriate quality and quality assurance requirements specified?

Are the applicable codes, standards, and regulatory requirements including issue and addends properly identified and are their requirements for design met?

Have applicable construction and operating experience been considered?

Have the design interface requirements been satisfied?

Was an appropriate design method used?

Is the output reasonable compared to inputs?

Are the specified parts, equipment and processes suitable for the required application?

Are the specified materials compatible with each other and the design environmental conditions to which the material will be exposed?

Have adequate maintenance features and requirements been specified?

Are accessibility and other design provisions adequate for performance of needed maintenance and repair?

13. Has adequate accessibility been provided to perform the in-service inspection expected to be required during the plant life?

14. Has the design properly considered radiation exposure to the public and plant personnel?

15. Are the acceptance criteria incorporated in the design documents sufficient to allow verification that design requirements have been satisfactorily accomplished?

16. Have adequate pre-operational (IST, PMT, ISI, snubber, etc.), subsequent periodic test, and inspection requirements been appr ately pecifed, including acceptance criteria?

17. Are adequate handling, storage, cleaning, an shipping requirements specified?

18. Are adequate identification requirements specified?

19. Are requirements for records adequately specified?

20. Will the change remain within the analyzed or specified capabilities of any affected equipment?

21. Has a field inspection been done?

22. Have impacts on other systems been identified? COMMENTS: 2 None D Attached (Use lornmPBF-1633)

"Design Prepared By: Rob Chapman D

Reviewed By: Kevin Krause -D

*Approval By: 49,13'A4 D

7 _

7 U,- _ _

ate

ate

ate

C/--

Reference- NP722

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11. 12.

PBF-1583 Revision 1 08/08/97 Page I of I

Page 46: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

DOCUMENT UPDATE CHECKLISTPlant Modification/rvlinor Plant Change No. 02-029

Work Order No.:

PBF-1606 Revision 6 10/02/01 Reference(s) NP 7 2 1

DOCUMENTATION UPDATE SHEET AND CLOSEOUT CHECKLUST

Required For

N/A Release Acceptance Closeout

(Completion) (Submittal)

A. TRAINING

X 1. Copy Submitted to Training (Design Description)

X 2. TWR Generated (TWR # o2.- -2.L" ) Ref. SIMGL CI.1

X 3. Simulator Changes Initiated (SDR # 02- o0-'4 )

X 4. Plant Status Update/Just In Time Training

B. FINAL DESIGN ORGANIZATION

1. Drawings

X - a. Design Change In Progress DCI's Initiated

X .' J b. Construction sketches Issued

.,, X c. Revised Drawings Issued for Priority I and 2 Control Room _____ -________ __ -Drawings - Logics, P&IDs, 499 series elementaries.

x ' d. Revised Drawings Issued for Work Control Center DrawingsP&IDs

X e. Revised Drawings Issued for I&C Drawings - Reactor

Protection and Safeguards Elementaries.

X f. Master Dita Book - Control Room, Work Control Center, and Local Panel - PBF-2093

SXg. DCN's released for incorporation

X "- h. Sketches Voided - PBF-1592

X 2. Specifications (Conformed at Closeout, ref NP 9.2.1)

X 3. Component Instruction Manuals (for issue, revision, deletion) PBF-1586

X 4. Cable and Raceway Data Schedule Revisions - PBF-0091

X 5. Environmental Qualification Documentation Updates - Ref. NP -. - 7.7.1

X - 6. Seismic Qualification Updates NP 7.7.2

- 7. Calculations or engineering evaluations added/deleted I revised PBF-1608

X 8. DBD Revisions - PBF-1653

X 9. PSA Models and Documentation - PBF-1626

10. EPIX Update - report Equipment changes/additions to the EPIX X Coordinator.

i

Pag-e I of 4

Page 47: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

DOCUMENT UPDATE CHECKLIST Plant ModificationlMinor Plant Change No. 02-029

[ Work Order No.:

SOrI IMFNTATION I IPnATF.MAFT•T ANnr ! l £0FrT rrHrKi jT

Required For

Release Acceptance Closeout (Completion) (Submittal)

C. LICENSING (Conformed at Acceptance)

X 1. Technical Specification - change; specify section(s) affected and change request number.

X 2. Tech Spec Basis/Technical Requirements Manual

X 3. FSAR - change; NP 5.2.6. Report major changes to the containment aluminum inventory list with FSAR update.

X 4. FPER - FHAR - SSAR Revisions - NP 5.2.11

"x a. Safe Shutdown Analysis Management System Revisions - NP

X ...._______:_____5. Offsite Dose Calculation Manual (ODCM)

X ___ -- 6. Radiological Effluent Control Manual (RECM)

x,"-: - 7. Emergency Plan and EPIPs

X 8. Notification to Security for Security plan update

X 9. Report major changes to radwaste treatment systems with annual FSAR update per RECM 1.6.3

D. CHAMPS DATABASE

X 1. Equipment Identification - additions assigned from CHAMPS

X 2. Permanent Labeling - labels on new equipment; PBF-9900

X 3. Temporary Labeling - labels on new equipment; PBF-2074

x 4. Equipment Record - update to CHAMPS coordinator specify change(s); PBF-9922

X 5. Spare parts stocking and scrapping inputs into CHAMPS; PBF-9925, PBF-1023

X _'"-'"_" 6. Unused material removed from modification bin.

t , E. OPERATIONS

_____ -_____ _____ euligPoedrs-PB-0 1. Abnormal Operating, Normal Operating, System Operating, and --. Refueling Procedures - PBF-0026a

X 2. Operating Instructions and Checklists - PBF-0026a

- 3. Alarm Response and RMS Alarm Setpoint and Response Books X_-_____-__ PBF-0026a

X 4. Testing - TS, IT, ORT, other - PBF-0026a

X 5. EOPs, ECAs, CSPs, SAMGs - PBF-0026a

X 6. Periodic Surveillances - PBF-9920

X 7. Fire Protection Procedures - PBF-0026a

8. EOP Setpoints, EOP Instrument Uncertainty Calculations PBF-8001

9. Tank Level Book - PBF-0026a

PBF-1606Reference(s) NP 7 2 IPace 2 nf 4

Page 48: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

DOCUMENT UPDATE CHECKLIST t

Plant Modification/Minor Plant Change No. 02-029 Work Order No.:

DOCUMENTATION UPDATE SHEET AND CLOSEOUT CHECKLIST

Required For

NIA Release Acceptance Closeout (Completion) (Submittal)

F. MAINTENANCE/I&C

X 1. Maintenance Procedures/Instructions - PBF-0026a

X 2. ICPs - PBF-0026a

X 3. Setpoint Document - PBF-8001

x 4. Preventative Maintenance - initiate/revise CHAMPS callups; PBF-9921/9920

x - - 5. Ensure station batteries' load profile changes are incorporated into the appropriate discharge test RMPs.

X -, 6. Lubrication Manual (NP 7.3.11)

..- G. SECURITY

x ""-' 1. Security Procedures

H. ENGINEERING/MISC.

X 1. ISI Program

X 2. IST Program

X 3. Miscellaneous-HX ECT/Cleaning program

"x 4. Reactor Engineering Instructions - change; specify section(s) -. affected.

x " 5. Reactor Engineering Procedures - change; specify section(s) affected.

x 6. Software Control - specify system affected and software change _______ _ request number.

- 7. Component maintenance programs.

x 8. Governing calculations and models (e.g., SW model, DC loading, EDG loading, piping analysis, structural loading, etc.).

X 9. Design Guidelines (ref. NP 7.1.2)

I. OTHER (CHEM, HP, ETC.)

X 1. Other (Misc. Procedures, etc.)

J. ECRs

1. ECR Final Resolution completed and approved by Design Supervisor.

2. ECR Implementation completed.

Rere,'nr' e¢•" NP7 2 I

.1

PBF-1606

Page 49: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Section Specific Updates Required

"*.-: A.1 Design description submitted to training.

A.2 TWR 02-240

A.3 Simulator Change Initiated

A.4 JIT notified of modification

B.1.a DCN toBECH M-217 Sh. I

B.1.a DCN to ALOYCO A-46037

B.l.c Control room drawings issued

B.L.d WCC drawings issued

B.l.g DCN to ALOYCO A-46037 issued.

B.7 Calculation 2002-0026 approved.

B.8 DBD-01, AFW, revised

B.8 DBD-06, IA/SA, revised

B.9 PSA updated

C.2 FSAR 9.7 revised

"C.2 FSAR 10.2 revised

C.3 TS B 3.7.5 revised

D.4 CHAMPS records updated

EA4 IT 08A revised

E.4 IT 09A revised

E.4 IT 10 revised

E.4 IT 10A revised

E.4 IT OB revised

F.4 Delete callup M-A6 (for AF- 17)

H.2 DST Background Doc Updated

1.1 New procedure IT 0oC issued

1.1 New procedure IT 09C issued

T.1 CwvAPS cd-Lis-r (T209issue

Prior to

Release

LI LI

LI FI

LI

LI LI

z

El LI

L2 LI

LI nI [L] LI LI LI

LI

Prior to

Acceptance

F] [2

D1

Dq

Lq

D:

LI LI

Prior to

Closeout

LI

LI

LI

LI LI LI ELI LI

LI

[I LI LI] LI LI

LI

Change No. (if Applicable) /BY/ Date

t",i.•.4Z . •,. c.,1 °-;- oz.- P•c.•.c

"CAt "S.- 2- t• S-2- r

~ACV_

. . 9. -- w- FZ3 L-,o-.. •C._

Q~eJ rz "" ,, , O-3-02. •c.r,

PBF-1606 Revtmon6 10/01/01 Referenccs) NP 7 2 1Pag~e 4 of 4

Page 50: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Section Specific Updates Required Prior to Prior to Prior to Change No.

Release Acceptance Closeout (if Applicable) /By/ Date

•>')A. 1 Design description submitted to E[training.

A.2 TWR 02-240 F71 _-'

A.3 Simulator Change Initiated "' ']

A.4 JIT notified of modification [] I __[--]

B.l.a DCN to BECH M-217 Sh. I ka- ' D B.I.a DCN to ALOYCO A-46037 M- [-_

B.l.c Control room drawings issued M 0 B. .d WCC drawings issued [I L_ _ _ _

B.l.g DCN to ALOYCO A-46037 issued. [-0_ ___['_

B.7 Calculation 2002-0026 approved. R" 0-_ B.8 DBD-01, AFW, revised L' L- __

B.8 DBD-06, IA/SA, revised E- [_ _ _ _

B.9 PSA updated -] [7 [_

C.2 FSAR 7.3 revised -' -I

C.2 FSAR 9.7 revised

C.2 FSAR 10.2 revised - [I [_

C.3 TS B 3.7.5 revised LI L- __

D.4 CHAMPS records updated [] [] [_

E.4 IT 08A revised [- __ __--_

E.4 IT 09A revised L L___ E.4 IT 10 revised [] __ __-'_

E.4 IT I0A revised LI L__ _ _

E.4 IT 10B revised LI [__F_ F.4 Delete callup M-A6 (for AF-1 17) "- L__["_ H.2 IST Background Doc Updated El [-1 [__

1.1 New procedure IT 08C issued EI [L] __

1.1 New procedure IT 09C issued LI LI __

PBF-1606I,- 'II

Page 51: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant

FIRE PROTECTION CONFORMANCE CHECKLIST

"" MR Number MR 02-029 Unit 1 Unit 2 Common Facilities X

System AUXILIARY FEEDWATER Location 26' El, Control Building

AFFECTED FIRE ZONE(S)-FIRE AREAS FZ 320 / A01-E (see FPER Sect. 9)

PURPOSE

The Fire Protection Conformance Checklist (FPCC) was developed to help evaluate the impact of plant modifications, procedural

changes, and tests on the plant fire protection program and safe shutdown capability for compliance with 10 CFR 50 Appendix R and

other plant fire protection license commitments.

The FPCC also provides the screening criteria to ensure that a 10 CFR 50.59 safety evaluation is performed on activities that affect the

design basis of fire protection equipment or plant's capability to achieve and maintain safe shutdown for any design basis fire. If the FPCC screening indicates the plant fire protection or safe shutdown design basis will be affected, a 10 CFR 50.59 screening shall be

performed per NP 10.3.1, Authorization of Changes, Tests, and Experiments (10 CFR 50.59), with consideration of the FPCC information, to determine if an unreviewed safety question is involved. The design basis fire is the accident to be considered in the 10 CFR 50.59 evaluation. The FPCC becomes part of the documentation supporting the 10 CFR 50.59 screening and safety

evaluation.

The FPCC is comprised of this main form, PBF-2060 and sub-forms, PBF-2060a through h that address different topical areas of the

PBNP fire protection program. The intent of multiple sub-forms is to eliminate unnecessary burden in completing forms for areas of

fire protection clearly not affected by a particular change. Based upon the nature of the change (as identified by answers to the

6,...questions on the Design Input Checklist PBF-1584), the applicable sections on the FPCC will be filled out. The appropriate sections

on the FPCC to be filled out shall be indicated below on the FPCC Applicability Matrix. The applicable sections that are completed

will be attached to the main form PBF-2060 and included with the plant change package.

INSTRUCTIONS

1. Complete the FPCC Applicability Matrix below, based on the nature of the change and answers to questions on the Design

Input Checklist PBF-1584 for the applicable change.

2. Complete the appropriate sub-forms, based upon the nature of the change as defined on the FPCC applicability matrix. It is

not necessary to complete sub-forms for areas of fire protection that are clearly not affected by the subject change.

3. Use the paragraphs in Section 5 of Design Guide DG-FO1 that correspond to the FPCC sections for additional information

and guidance when answering the questions in the checklist.

4. Consider requirements for a 10 CFR 50.59 screening by reviewing the RESULTS section below.

5. Ensure that the appropriate documents required for update (i.e., FPER, FHA, SSAR, SSAMS, FPDS, Calculations, FPEEs,

etc.) are properly identified for future revision in the governing document update procedures. This includes documents that

must be updated for changes that could potentially adversely affect fire protection conformance, as well as changes that are

determined by the checklist not to adversely affect fire protection conformance (but still require document updates).

6. Sign and date the FPCC. If the NPBU Fire Protection Engineer is not the preparer of the FPCC, then the Fire Protection

Engineer shall review, sign and date, the FPCC.

PBF-2060 Rev- %" (yifl'n 1 Paie I of 2

Page 52: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

FIRE PROTECTION CONFORMANCE CHECKLIST

RESULTS

If the completion of any FPCC screening from Sections 1.0 - 10.0 on forms PBF-2060a through 2060h indicates the modification has potential adverse impact, then the plant fire protection or safe shutdown design basis may be affected. A 10 CFR 50.59 screening must be performed per NP 10.3.1, Authorization of Changes, Tests, and Experiments (10 CFR 50.59), with consideration of the FPCC information to determine if an unreviewed safety question is involved, the design basis fire is the accident to be considered in the 10 CFR 50.59 evaluation. The FPCC becomes part of the documentation supporting the 10 CFR 50.59 screening and safety evaluation.

Inform the NPBU Fire Protection Engineer if fire protection program commitments or compliance with 10 CFR 50, Appendix R will be affected.

Fire Protection Conformance Checklist Applicability Matrix

Applicable? Yes No

E3 N

0 0 0] 0

[] [

Section

1.0 2.0 3.0 4.0

5.0

6.0

El ED 7.0

El0 E50 El ED

8.0 9.0 10.0

To2ic

Plant Access Fire Barriers Fire Protection Systems Combustible Loading/Fire Hazards Safe Shutdown Systems and Equipment Safe Shutdown Cables, Including Associated Circuits Fire Area Analysis, Including Exemptions/Evaluations Emergency Lighting Plant Communications Reactor Coolant Pump Oil Collection System

Design Input Checklist Section

F.2.a F.2.b F.2.c F.2.d

F.2.e

F.2.f

F.2.g

F.2.h F.2.i F.2.j

Action

Complete & attach PBF-2060a Complete & attach PBF-2060b Complete & attach PBF-2060c Complete & attach PBF-2060d

Complete & attach PBF-2060e

Complete & attach PBF-2060e

Complete & attach PBF-2060e

Complete & attach PBF-2060f Complete & attach PBF-2060g Complete & attach PBF-2060h

Conformance checklist (including all applicable attachments) completed.

Comments: Removal ofAF-117 internals and upgrading the AFW mini-recircAOVs to have an open safety-related function will

improve AFW pump reliability.

By: DateDate: 0i- Z -

PBF-2060 1. 2 •,, 0tfftQff'l!

Page 53: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Point Beach Nuclear Plant FIRE PROTECTION CONFORMANCE CHECKLIST

SECTIONS 5, 6, & 7 - APPENDIX R SAFE SHUTDOWN EVALUATION

Complete the evaluation (Sections 5.0, 6.0, and 7.0) and attach to form PBF-2060.

APPENDIX R SAFE SHUTDOWN EVALUATION

5.0 SAFE SHUTDOWN SYSTEMS AND EQUIPMENT (Ref. Section 5.2.5.1 of Design Guide DG-FOI)

5.1 Does the modification require addition of a safe shutdown component? Is the new component located within the Appendix R flowpath boundaries shown in the Appendix R Highlighted P&IDs, SSAMS Database, SSEL Module, or the SSAR Section 2, Safe Shutdown Logic Diagrams in Appendix B of SSAR.

LII Yes, go to 5.11, complete actions and resume at 5.2 Z No, go to 5.3

Comments:

5.2 Will the new component support other safe shutdown systems or component(s)? (Refer to SSAMS Database, SSEL Module, SSAR Section 2, Safe Shutdown Logic Diagrams in Appendix B of SSAR)

M' Yes, go to 5.11, complete actions and resume at 5.3

E' No, go to 5.3

Comments:

5.3 Does the modification require deletion of a safe shutdown component? (SSAMS Database, SSEL Module, SSAR Section 2)

M Yes, go to 5.11, complete actions and resume at 5.4. 0 No, go to 5.4

Comments:

5.4 Does the modification require a design change to a safe shutdown component? (SSAMS Database, SSEL Module, SSAR Section 2)

E] Yes, go to 5.11, complete actions and resume at 5.5

Z No, go to 5.5

Comments:

PBF-2060e

Page 54: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

FIRE PROTECTION CONFORMANCE CHECKLIST SECTIONS 5, 6, & 7 - APPENDIX R SAFE SHUTDOWN EVALUATION

5.5 Does the modification add/delete/revise safe shutdown equipment to the system flow path or boundary isolation from interconnecting systems? (the Appendix R Highlighted P&IDs, SSAMS Database, SSEL Module, and the SSAR Section 2)

Z Yes, go to 5.11, complete actions and resume at 5.6

"] No, go to 5.6

Comments:

5.6 Does the modification affect the operation of a system relied upon for post-fire safe shutdown (e.g., changes in system flow rate, change in normal positions, etc. See SSAMS, SSEL Module, SSAR Section 2)?

[ Yes, go to 5.11, complete actions and resume at 5.7 I"' No, go to 5.7

Comments:

5.7 Does the modification violate the safe shutdown systems performance goals as presented in FPER Section 7.2 and SSAR Section 2?

E] Yes, go to 5.11, complete actions and resume at 5.8 Z No, go to 5.8

Comments:

5.8 Does the modification affect any mechanical sub- or support components of safe shutdown components not listed on the safe shutdown equipment list? (e.g., SOVs, check valves, etc.) (See CHAMPS Appendix R listing)(. If it is a support component for safe shutdown equipment, then it should be considered a safe shutdown component for the purposes of review for impact.

1 Yes, go to 5.11, complete actions, resume at 5.9 [- No, go to 5.9

Comments:

5.9 Does the modification to the sub- or support component affect the operability of its associated safe shutdown equipment? (i.e., Failure of a support component that results in failure of a safe shutdown component)

[ Yes, go to 5.11, complete actions, resume at 5.10 -- No, go to 5.10

Comments:

PBF-2060e

Page 55: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

FIRE PROTECTION CONFORMANCE CHECKLIST SECTIONS 5, 6, & 7 - APPENDIX R SAFE SHUTDOWN EVALUATION

5.10 Does the modification add/deletelrevise any electrical sub or support components which support the identified safe shutdown component(s) (e.g., power supplies, relays, switches, motor operators)? (Ref. Associated Circuit Analysis - SSAR Section 3)

I- Yes, go to 5.11 Z No, go to 6.1

Comments:

5.11 The addition/deletion/revision of safe shutdown components, sub- or support components affects the safe shutdown analysis and must be evaluated for impact on Appendix R compliance and documentation impacts in Sections 6.0 and 7.0. List the equipment and the affected systems and refer to Section 5.2.5.1 of Design Guide DG-F01. RESUME checklist completion.

Safe Shutdown System(s), Components, Sub- or Support Component(s):

AF- 117 internals are being removed per MR 02-029. This check valve will no longer be able to isolate backflow. This is more conservative in terms of forward flow through the AFW common recirculation line, and has no affect on the safe shutdown analysis. This check valve will be less likely to fail closed, and reduces the likelihood of failure of the AFW pumps.

6.0 SAFE SHUTDOWN CABLES, INCLUDING ASSOCIATED CIRCUITS (Ref. Section 5.2.5.2 of Design Guide DG-F01)

6.1 Does the modification require addition of a safe shutdown cable, including cables which could spurious operation of safe shutdown equipment (i.e., through interlocks and interfacing relays and contacts)? (Ref. Section 3 of the SSAR, Section 5.2.5.2 of Design Guide DG-F01)

"' Yes, go to 6.10, complete actions and resume at 6.2 [ No, go to 6.2

Comments:

6.2 Does the modification require deletion of a safe shutdown cable? (Ref. SSAMS Circuit Analysis Module, SSAR Sections 3, 4, and 5)

EI Yes, go to 6.10, complete actions and resume at 6.3 ] No, go to 6.3

Comments:

PBF-2060e

Page 56: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

FIRE PROTECTION CONFORMANCE CHECKLIST SECTIONS 5,6, & 7 - APPENDIX R SAFE SHUTDOWN EVALUATION

6.3 Does the modification revise an existing safe shutdown cable, such that safe shutdown equipment functionality, either during normal/emergency equipment operation, or when subjected to a fire-induced circuit failure, could be impacted? This includes changes that could impact the ability to transfer equipment control from one operating location to another and changes which affect circuit protective device performance.

-' Yes, go to 6.10, complete actions and resume at 6.4 I No, go to 6.4

Comments:

6.4 Does the modification require a change to the routing of an existing safe shutdown cable? This includes actual physical routing changes and changes in CARDS/SSAMS to correct routing discrepancies. This may involve changes to the cable endpoint, changes to the cable endpoint location, changes to the raceways in which a cable is routed, or changes to the fire zones through which a raceway is routed. (Ref. SSAMS Cable and Raceway Module, CARDS)

E'I Yes, go to 6.10, complete actions and resume at 6.5

I No, go to 6.5

Comments:

6.5 Does the modification require addition or revision of a circuit connected or to be connected to safe shutdown power supply? (Ref. Section 5.2.5.2 of Design Guide DG-F01, Appendix R Highlighted Single Line Drawings, SSAR Section 3)

El Yes, go to 6.6 i No, go to 6.7

Comments:

6.6 Will adequate electrical coordination between the safe shutdown power supply feeder breaker and the added or revised component breaker or fuse exist? (Ref. Section 5.2.5.2 of Design Guide DG-FOland SSAR Section 3)

E] Yes, go to 6.7 [' No, go to 6.10, complete actions and resume at 6.7

Comments:

PBF-2060e

Page 57: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

FIRE PROTECTION CONFORMANCE CHECKLIST SECTIONS 5,6, & 7 - APPENDIX R SAFE SHUTDOWN EVALUATION

6.7 Does the modification require addition or revision of any non-safe shutdown circuits?

L" Yes, go to 6.8 [ No, Safe Shutdown Cables Section Complete, go to 7.1

Comments:

6.8 Will the new or revised cables be equipped with properly designed circuit breakers, fuses or some kind of current limiting device? (Ref. SSAR Section 3)

M Yes, Safe Shutdown Cables Section Complete, go to 7.1 -" No, go to 6.9

Comments:

6.9 Will the new or revised cables share a common enclosure (raceway, panel etc.) with safe shutdown cables? (Ref. Section 5.2.5.2 of Design Guide DG-FOland SSAR Section 3)

-" Yes, go to 6.10, complete actions i-] No, Safe Shutdown Cables Section Complete, go to 7.1

Comments:

6.10 The modification impacts the safe shutdown circuit analysis and must be evaluated further in Section 7.0 for impact on Appendix R compliance and documentation updates. List the safe shutdown circuits and associated components and refer to Section 5.2.5.2 of Design Guide DG-F01. RESUME checklist completion.

Comments:

7.0 FIRE AREA ANALYSIS, INCLUDING EXEMPTIONS/EVALUATIONS (Ref. Section 5.2.5.3 of Design Guide DG-F01)

7.1 Do the changes to the safe shutdown systems/equipment (from Section 5.0 of the FPCC), safe shutdown circuits or the physical routing of the cables (from Section 6.0 of the FPCC) result in a change to the potential consequences of a fire in any plant fire area? This includes changes that could result in the addition/deletion/modification of a compliance strategy for a piece of safe shutdown equipment for any fire area (such as availability of redundant equipment outside of the fire area, separation in accordance with Section III.G.2 of Appendix R of Appendix R, local manual actions, repairs, etc.). (Ref. SSAR, Section 5)

L" Yes, go to 7.5, complete actions and resume at 7.2

[ No, go to 7.3

Comments:

PBF-2060e Revision 0 06/08/01 Page 5 o f 6

Page 58: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

FIRE PROTECTION CONFORMANCE CHECKLIST SECTIONS 5,6, & 7 - APPENDIX R SAFE SHUTDOWN EVALUATION

7.2 Is compliance with the separation criteria for redundant safe shutdown capability in Section III.G of Appendix R affected by the change? (Ref. SSAR Table DBD T-40, Table 3-2.2)

El] Yes, go to 7.5, complete actions and resume at 7.3 E] No, go to 7.3

Comments:

7.3 Is the modification proposed to be implemented in a fire zone/area for which an Appendix R Exemption or FPEE is in place (Ref. DBD T-40, Table 3-2.2, FHA, Table 1-1 of the SSAR)

[ Yes, go to 7.4 I"- No, Fire Area Analysis Section is complete, go to Section 8 or next applicable Section.

Comments:

7.4 Does the modification violate or potentially change the basis for the Appendix R exemption or FPEE? (Ref.: DBD T-40, Table 3.2-2, FHA, Table 1-1 of the SSAR)?

E] Yes, go to 7.5 ] No, Section 5, 6, and 7 checklists complete

Comments:

7.5 The modification impacts the Fire Area Analysis and potentially violates the basis for compliance with the separation requirements of Appendix R, the basis for an Approved Appendix R exemption, or technical evaluation such as a Fire Protection Engineering Evaluation. List the basis affected and refer to Section 5.2.5.3 of Design Guide DG-FO1. RESUME checklist completion.

Bases:

PBF-2060e Revision 0 06/08,01 Pave 6 of 6

Page 59: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Work Control Document: Equipment ID: Equipment Description: Work Plan Originator:

NUCLEAR POWER BUSINESS UNIT

WO WORK PLAN 0212107- MR 02-029 AF-1 17 AFP COMMON MINI RECIRC HEADER CHECKRob Chapman x7636 pager 0114

UNIT: PB0

Date: September 5, 2002

_______,___,WORK SCOPE

WORK SCOPE The purpose of MR 02-029 is to correct a potential common mode active failure of the AFW pump and common recirculation line, as part of the upgrade of the mini-recirc AOVs to have a safety-related

PURPOSE function to open.

The scope of this installation work plan is to remove the internals from AF-1 17.

The AF-1 17 check valve is located on the 26' elevation of the Control Building, west of the CSTs. The AF-4035 relief valve is located on the 8' elevation of the Unit 1 turbine building, west of the south Aux Feed tunnel doors.

AF-1 17 is non-QA, non Seismic, non ASME Class. An RRM is NOT required for an increase in work scope.

INITIAL None of the AFW pumps shall be running. CONDITIONS

DANGERTAG SCOPE

Prepare a tag series to isolate the AFW common recirc line at valve AF-1 17. The tag series must not isolate AF-4035. The following valves shall be tagged SHUT:

"* AF-1, AFP RECIRC HEADER ISOLATION

"* AF-2, T-24A CST MINI RECIRC ISOLATION

"* AF-9, T-24B CST RECIRC ISOLATION

* AF-10, T-24A/B CST HEATING RETURN HEADER ISOLATION

The following valves shall be tagged OPEN:

"* BE-95, T-24A/B CST FEED

"* BE-96, T-24A/B CST FEED DRAIN

THE AF-4035 RELIEF VALVE WILL BE CREDITED AS THE MINI-RECIRC FLOW PATH. A LEVEL 3 DEDICATED OPERATOR WILL BE STATIONED TO MONITOR OPERATION OF THIS RELIEF VALVE, AND NOTIFY THE CONTROL ROOM IF IT FAILS TO OPEN AUTOMATICALLY.

THE AFW PUMPS WILL BE FULLY OPERABLE DURING THE INSTALLATION OF THIS MODIFICATION.

DANGER TAG BECH M-217 Sh. 1 REFERENCES WEST 684J971 Sh. 2

H 0fATATFILESWODSWR 02-029 - AF Recwrc Satety Uograde -AF1 17%0212107 docPBF-9169 Rplvm•inn q4 (31111 P1n

Page 1 of 7

Page 60: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Work Control Document: Equipment ID: Equipment Description: Work Plan Originator:

NUCLEAR POWER BUSINESS UNIT

WO WORK PLAN 0212107 - MR 02-029AF-117 AFP COMMON MINI RECIRC HEADER CHECK Rob Chapman x7636 pager 0114

UNIT: PB0

Date: September 5, 2002

;,t-W0K SCOPEj--:,

LIMITATIONS • All pre-work staging activities shall be completed prior to tagging the recirc line out of service. AND This will include attaching a hose to the relief valve discharge. Once the system is tagged out,

PRECAUTIONS operation of the AFW pumps will cause the AF-4035 valve to open. As long as AF-1, AF-2, and AF-9 are open, there is reasonable assurance that the relief valve will not open with the AFW pumps running on recirc. Therefore, attaching and removing the hose shall NOT be performed while tags are hung. OPS shall verify that AF-1, AF-2, and AF-9 are locked open prior to attaching the hose to the AF-4035 relief valve.

* Caution should be taken when taking the bonnet off the check valve due to water present in the piping. This line may be filled with water initially, and should drain when the bonnet is cracked loose. Leakage from the CSTs past AF-2 or AF-9 could cause water to build up inside the check valve body.

* Scaffolding will be required to access the AF-4035 relief valve (8' TB1) and the AF-117 check valve (26' CB).

a STEPS IN THIS WORK PLAN SHALL BE PERFORMED IN THE ORDER SPECIFIED.

TOOLS AND

MATERIALS

* 3" 150# Class flange with hose connection

* 3" hose (minimum), approximately 40 ft

* Tools as needed to disassemble the check valve and remove the internals

a Gasket for ALOYCO 367 3" 150# check valve, SIR P102-024756, LIN 917-5440 (QTY 1)

* Screw, Hex Head Cap, Y2*-13(UNC) x 2 Y2", Grade B8, L/N 903-0397 (As needed)

• Nut, Hex, Y2"-13(UNC), Grade 8, L/N 903-0569 (As needed)

�XA

QC REVIEW OF WORK PLAN

(independent QC review required on QA classified work order only) NA if non-QA work order

Any change in scope requires WO WP review by QC inspector.

PBFo9169 Page 2 of 7 Revison 3 01/12/01

H DATATFILES'OOSWIR 02-029 - AF Reciec Safety Upgrade - AFI t7I0212107 doc

I

Page 61: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Work Control Document: Equipment ID: Equipment Description: Work Plan Originator:.

NUCLEAR POWER BUSINESS UNIT

WO WORK PLAN 0212107- MR 02-029AF-117 AFP COMMON MINI RECIRC HEADER CHECKRob Chapman x7636 pager 0114

UNIT: RBO

Date: September 5, 2002

:- ~ ~ ~-- .. SUPPORT-

SUPPORT El Chemistry

0 Engineering Rob Chapman x7636 pager 0114

El HP

El I&c

0 Maintenance Performing internals removal.

O] NDE

0 Operations Hang tags, level 3 dedicated operator

a QC Witness torquing

El Security

El Crane [ITB El PAB El Polar El Other

0 Other Component Engineer / Aaron Guenther x6422

H \DATAWILES MODSV.¶R 02-029 - AF Recirc Safety Upgrade - AF1 7"0212107 docPage 3 of 7PBF-9169

Page 62: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Work Control Document: Equipment ID: Equipment Description: Work Plan Originator:

NUCLEAR POWER BUSINESS UNIT

WO WORK PLAN 0212107 - MR 02-029 AF-117AFP COMMON MINI RECIRC HEADER CHECKRob Chapman x7636 pager 0114

UNIT: PB0

Date: September 5, 2002

Page 4 of 7PBF-9169 Revision 3 01/12/01

H %DATATILES\MOOSWR 02-029 - AF Recrc Safely Uplrade - AFt 17%0212107 doc

NOTE: The steps in this work plan must be performed in the order specified.

FME: Tools and equipment shall be checked for loose parts and debris and temporary covers should be installed for foreign material exclusion (FME) of system/components per Exclusion of Foreign Material from Plant components and Systems, NP 8.4.10.

NOTE: IF inspections or discrepancies require modifications to Work Scope:

THEN STOP work, place equipment in SAFE condition, and NOTIFY Supervision.

NOTE: The Control Room / the Work Control Center / and the watchstander (as appropriate) shall be informed of the status of jobs which:

bring in alarms, affect indications, and other work being performed on operating equipment.

NOTE: All workers shall perform all Danger Tagging requirements as defined in NP 1.9.15

NOTE: Any pen and ink change to work plan requires initial and date by the change and engineering concurrence.

NOTE: Write WO number on top/header of any supplemental pages added to work package, i.e., forms, procedures, checklists...

Page 63: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

NUCLEAR POWER BUSINESS UNIT

WO WORK PLAN Work Control Document: 0212107- MR 02-029 Equipment ID: AF-117 Equipment Description: AFP COMMON MINI RECIRC HEADER CHECK Work Plan Originator: Rob Chapman x7636 pager 0114

Page 5 of 7PBF-9169 Revision 3 01112/01

UNIT: PB0

Date: September 5, 2002

H ATATFILESWODSWMR 02-029 - AF Recirc Safety Upgrade. AFi 1T7\212107 doc

I

Page 64: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Work Control Document: Equipment ID: Equipment Description: Work Plan Originator:

NUCLEAR POWER BUSINESS UNIT

WO WORK PLAN 0212107 - MR 02-029 AF-117 AFP COMMON MINI RECIRC HEADER CHECK Rob Chapman x7636 pager 0114

UNIT: PBO

Date: September 5, 2002

Hold Point -.- Workln Description ,

7. Perform a visual inspection of the valve body for evidence of corrosion and/or erosion, and notify component engineering if any discrepancies are noted (Aaron Guenther, x6422).

MT DATE

8. Remove clapper arm shaft / pin (Item 5) from clapper arm and cover hanger.

Remove clapper arm (Item 3) and entire disk assembly from the cover hanger.

DO NOT DISCARD INTERNALS. CONTACT Rob Chapman at x7636. MT DATE

9. Prior to installing the valve in the system perform a final FME closure exam. Inspect accessible piping for dirt and debris, and remove from piping. Ensure that all removed parts are accounted for. Document the closure exam below:

FME Closure Exam: [3 SAT E] UNSAT

MT DATE

QC Hold Point 10. Re-install the check valve cover using a new gasket.

Torque bolting to 45 ft-lbs ___ __ DATE

Actual Value: MT DATE MTE Serial Number. Cal Due Date:

QC DATE

11. Clear tag series.

OPS DATE

12. Secure the Level 3 Dedicated Operator.

OPS DATE

13. The AFW pump common minimum recirculation line is available.

OPS DATE

PBF-9169 Page 6 of 7 Revision 3 01/12/01

HADATAFILESMOOSWMR 02-029 - AF Recirc Safely Upgrade o AF 117\021 2107 doc

FME

Page 65: 0D 5 Unit 2 5 0 - Nuclear Regulatory Commission · 0D QA [5 AQ [5 Non-QA 0 SR [I Non-SR Unit 1 5 Unit 2 5 Common 0 CHAMPS System Code: AF EWR: CR: Project Objectives: UPGRADE THE

Work Control Document: Equipment ID: Equipment Description: Work Plan Originator:

NUCLEAR POWER BUSINESS UNIT

WO WORK PLAN 0212107 - MR 02-029 AF-117 I AFP COMMON MINI RECIRC HEADER CHECK Rob Chapman x7636 pager 0114

UNIT: PBO

Date: September 5, 2002

Page 7 of 7PBF-9169 Revision 3 01/12/01

H DATATIESWMODSWR 02-029 • AF Recirc SaFely Upgrade - AF 117\212107doc

I


Recommended