Colorado Coordinated Planning Group
PCC UpdateMarch 6-7, 2008
PCC Presentation 2
CCPG
The CCPG is a forum to bring reliability study ideas for joint study purposes. Website: www.westconnect.com Alternate: www.ccpg.basinelectric.com
PCC Presentation 3
Map
ColoradoCoordinated
PlanningGroup
SouthwestArea
Transmission
CCPGCCPG
SWATSWAT
SIERRASIERRANew Area
PCC Presentation 4
Transmission Participants Arkansas River Power Authority Aquila Basin Electric Black Hills Power Colorado Springs Utilities Pacificorp Platte River Power Authority Public Service Company of Colorado Tri-State Generation & Transmission Western Area Power Administration
PCC Presentation 5
2008 GOALSEstablish CharterSubcommittee Formation StudiesData CoordinationSchedule Synchronization
PCC Presentation 6
08 Goals - Charter Subgroup Organization
Re-Name Subgroup? Formalize Structure
Defined Responsibilities Voting Rights Stakeholder Processes (“Attendees” vs. “Participants”) Formal Agreements?
Subcommittee Organization Existing
Long-Range, NERC Compliance, Foothills, Voltage Coordination New:
Additional Sub-Sub-Regions (Denver-metro, SECO, SWCO,WY, etc.) Area Coordination 890 Issues WECC Liaison (TEPPC)
890 Compliance
PCC Presentation 7
08 Goals - Subcommittees Existing:
Long Range Transmission Planning NERC Compliance Foothills (Sub-subregion) Voltage Coordination Rocky Mountain Area Coordinator
NEW: Additional Sub-subregions: e.g. Wyoming, Denver-metro,
SECO, SWCO, etc. SB100 890 Base Case Coordination
PCC Presentation 8
08 Goals - Studies
Long Range Transmission PlanningNERC ComplianceSenate Bill 100Sub-subregionsMega Projects
PCC Presentation 9
Long Range Planning Study
SC: Long Range Transmission Planning GroupPurpose:
Develop 10 Year Transmission Plans (2018 Models) Consider RPS & up to 30% Renewable Re-evaluate the Eastern Plains Transmission Project
Lead:TSGTKicked off December 19, 2007
PCC Presentation 10
NERC Compliance Study
SC: NERCPurpose:
Meet TPL-001,2,3,4 Requirements Near (5 yr) & Far (10yr) Windows Consider RPS & up to 30% Renewable
Lead:BEPC
PCC Presentation 11
SB100 StudySC: SB100Purpose:
Meet requirements of Colorado Senate Bill 100 Identify “Energy Resource Zones” Plan Transmission to Serve the ERZ’s File CPCN’s with CPUC
Lead:PSCo Kicked off March 4, 2008 2015 Models (Correspond to PSCo Resource Plan)
PCC Presentation 12
Sub-subregion StudiesSC: VariousPurpose:
Analyze transmission requirements for specific regions within the CCPG FootprintFoothills, Tot 3, Wyoming Joint Q, Denver-Metro, SECO,
SWCO, Front Range, etc
Lead:Various
PCC Presentation 13
Mega-Project StudiesSC: VariousPurpose:
Evaluate impacts of mega-projects on CCPG Subregion:High Plains ExpressWyoming – Colorado IntertieEPTP
Lead:Various
PCC Presentation 14
08 Goals - Area Coordination
SC: WECCPurpose:
Address Issues associated with preparation of cases for WECC Annual Study Program
Rocky Mountain Area Coordinator
Lead:PSCo
PCC Presentation 15
08 Goals - Synchronization
WestConnectSWATWECC (TEPPC)890 Requirements
PCC Presentation 16
NextNext CCPG meeting
March 25, 2008 TSGT
Contact Thomas Green 303-571-7223 [email protected]
Or Jared Griffiths (Co-chair) Phone 970-461-7603 Email [email protected]
PCC Presentation 17
2008 CCPG Study Plan Kicked Off the next Colorado Long-Range Transmission
Planning Group study effort on December 19, 2007
Will look at updated L&R’s for 2018 and 2013
Take into Account State Renewable Portfolio Standards
Address Some of the Renewable Resource Generation Development Areas Outlined in the Senate Bill 07-091 Report
Complete Initial Feasibility Study Report for the High Plains Express Project
Re-structure the CCPG Charter