COSTANTZA HARBORCOSTANTZA HARBOR DEVELOPMENT DEVELOPMENT
MASTER PLANMASTER PLAN
speaker: Nicoleta DOGARUHead of Development DepartmentNational Company “Maritime Ports Administration ” SA ConstantzaConstantza, ROMANIA31st May 2007
PLANCOASTPLANCOAST
2
Port of Constantza – short overviewPort of Constantza – short overview
Largest and deepest port at the Largest and deepest port at the Black Sea Black Sea
•Total surface: 3,926 ha;
•156 berths (out of which 140 operational berths);
•Quay length - almost 30 km;
•Length of breakwaters (north+south) – 14 km;
•Total handling capacity – over 120 million tons/year;
•Natural water depths between 8 and 18.5 m;
•Safe port;
•Port complying with the ISPS Code and the EU security regulation in force;
•Friendly environmentally management;
•Free port status starting with January 2007.
3
Port of Constantza – short overviewPort of Constantza – short overview
Constantza Port geographical position& connectionsConstantza Port geographical position& connections
Corridor no. VII
- Danube-Corridor no. IX
-road-
Corridor no. IV
-rail and road-
Pan European Transport Corridor no. VII – the Pan European Transport Corridor no. VII – the DanubeDanube
Pan European Transport Corridor no. IV (railroad)Pan European Transport Corridor no. IV (railroad) Pan European Transport Corridor no. IX (road)Pan European Transport Corridor no. IX (road)
TRACECA CorridorTRACECA Corridor
4
Port of Constantza – short overviewPort of Constantza – short overview
Traffic dataTraffic data
Total traffic(thousand tonnes) 57,138
Transit 12,846
Import 20,466
Export 15,820
Cabotage 8,006
transit
import
export
cabotage
2006
Total traffic(thousand tonnes) 14,323
Transit 3,829
Import 5,260
Export 3,273
Cabotage 1,959
First quarter of 2007
transit
import
export
cabotage
5
Port of Constantza – short overviewPort of Constantza – short overview
Traffic data - containersTraffic data - containers
Unloaded 525,211
- full 372,802
- empty 152,409
Loaded 511,857
- empty 316,995
- loaded 194,862
TOTAL 1,037,068
505000
510000
515000
520000
525000
530000
unloaded loaded
unloaded
loaded
2006 (TEUs)
Unloaded 147,126
- full 103,342
- empty 43,784
Loaded 150,861
- empty 51,905
- loaded 98,926
TOTAL 297,987
First quarter of 2007 (TEUs)
145000
146000
147000
148000
149000
150000
151000
unloaded loaded
unloaded
loaded
6
Port of Constantza – DevelopmentsPort of Constantza – Developments
Master Plan, Development Strategy (2020) &Master Plan, Development Strategy (2020) &Short Term Development Plan (2013) Short Term Development Plan (2013)
The Master Plan, the Development Strategy of Constantza Port for the period up to 2020, and the Feasibility Study on the projects to be developed in the Short Term Development Plan for the period up to 2013, have been drawn up by the Japan International Cooperation Agency during 2001 – 2002.
The projects comprised by the Master Plan, Short Term Development Plan and Feasibility Study are related to:
-Traffic demand
-Improvement of the port operation
-Improvement of the port access
Roads connection
Waterway connection
Railways connection
7
Port of Constantza – DevelopmentsPort of Constantza – Developments
Projects related to the traffic demand Projects related to the traffic demand - specialized dedicated terminals - - specialized dedicated terminals -
Pier III S Infrastructure- By completing this infrastructure, a specialized terminal will be achieved (new container terminal), which will assure accommodation of big tonnage capacity vessels - Reclaiming land into the sea (aprox. 35 ha) - Estimated cost of the project EUR 67 millionsNC MPA SA Constantza intends to promote the project for a Public Private Partnership.
Pier III
Pier IV
8
Port of Constantza – DevelopmentsPort of Constantza – Developments
Projects related to the traffic demand Projects related to the traffic demand - specialized dedicated terminals - - specialized dedicated terminals -
Pier IV S Infrastructure - Three Stages -By building this infrastructure in 3 phases we create the possibility of development of new specialized terminals, providing big depths for large vessels-Phase I: 35 ha = EUR 118 millions-Phase II: 55 ha = EUR 155 millions-Phase III: 70 ha = EUR 140 millionsNC MPA SA Constantza shall promote the project for financing.
Pier IV
Pier III
Pier IV
9
Port of Constantza – DevelopmentsPort of Constantza – Developments
Projects related to the traffic demand Projects related to the traffic demand - specialized dedicated terminals - - specialized dedicated terminals -
Container Terminal on Pier 2S – Stage 3- Increasing the handling capacity up to 2,000,000 TEU`s/year in the next two years- The project will be completed by the present operator CSCT-DP World, from its own sources.
New Container TerminalNew Container Terminalon Pier II South –CSCT-on Pier II South –CSCT-
Constantza Port, Constantza Port, the biggest the biggest container hub in container hub in the Black Sea the Black Sea regionregion
10
Port of Constantza – DevelopmentsPort of Constantza – Developments
Projects related to the improvement of Projects related to the improvement of Port Operation Port Operation
Extension by 1 km of the North Breakwater- Improving the exploitation conditions by diminishing wave stirring in the port basins, improving navigation safety and reducing destructive effects of waves over existing arrangements in the port basins- The Feasibility Study & Technical Design were drawn up by SC IPTANA in 2002; SC IPTANA SA completed revision of Project Cost and TECHINCAL DESIGN in April 2007.-Estimated value of Feasibility Study is EUR 120 millions.NC MPA SA Constantza proposed the project for SOP-T 2007-2013 financing.
Completion of the north breakwater
11
Port of Constantza – DevelopmentsPort of Constantza – Developments
Projects related to the improvement of Projects related to the improvement of Port Access - Roads ConnectionPort Access - Roads Connection
Road Bridge over the Danube-Black Sea Canal km 0+540 - it is a necessity due to the possibility of connecting with Bucharest-Constantza Highway through the by-pass financed by EBRD- providing a better connection of the South area of the port with the national roads network-Estimated cost is EUR 28.8 millions.NC MPA SA Constantza proposed the project for SOP-T 2007-2013 financing.
Road Bridge over the link canal - construction of a steel road bridge with unitary span of 105 m, which will link the river-maritime area and the artificial island- it is a priority in order to achieve territories and the future development of the artificial island -Estimated cost of the Feasibility study is EUR 31 millions.
12
Port of Constantza – DevelopmentsPort of Constantza – Developments
Projects related to the improvement of Projects related to the improvement of Port Access - Waterway ConnectionPort Access - Waterway Connection
Development of a barge terminal - The necessity of this investment was generated by:
- the increase of the river traffic in the Port of Constantza - hence the need to ensure adequate facilities mainly dedicated to river convoys accommodation and formation
- the need to streamline the navigation in the river-maritime sector of the port.
- improvement of the inland waterway transport (IWT) infrastructure in the port is of strategically importance for the Port of Constantza
- Estimated cost of first stage (in progress) is EUR 24 millions.Financed by a non-sovereign loan from EBRD (75%) and own sources of NC MPA SA Constantza.
The barge terminalStage I
The barge terminalStage II
13
Port of Constantza – DevelopmentsPort of Constantza – Developments
Projects related to the improvement of Projects related to the improvement of Port Access - Railways ConnectionPort Access - Railways Connection
Extension of railway system in the river-maritime area of Constantza Port - necessity:
improvement of railway operations in the river-maritime area by building of a systematized railway complex- In the first stage railway lines shall be created, in order to attend the actual operators and their 2020 traffic forecast.
-Estimated cost of first stage Feasibility Study is EUR 15 millions.NC MPA SA Constantza proposed the project for SOP-T 2007-2013 financing.
Development of the railway capacity in the river-maritime area
14
Port of Constantza – DevelopmentsPort of Constantza – Developments
Other projectsOther projects
Consolidation, stabilization and arrangement of Constantza Port`s Shore - Necessity:
- this project is a priority considering the need of ISPS compliance
- the investment for the city seashore is conducted on the basis of a protocol between NC MPA SA Constantza and Constantza Municipality, so that a unitary development of city architecture is achieved
- Estimated cost of first stage Feasibility Study is EUR 13.4 millions.NC MPA SA Constantza promoted for financing this project to Romanian Ministry of Transport.
15
COSTANTZA HARBORCOSTANTZA HARBOR DEVELOPMENT MASTER DEVELOPMENT MASTER
PLANPLAN
NC MPA SA Constantza31st May 2007