1
LNG REFIT
“EIGER – NORDWAND”
Ben Maelissa,25 September 2014
Co-financed by European UnionTrans-European Transport Network (TEN-T)
Ben Maelissa
o Privately owned companyo Founded in 1982o Headquarters in Sliedrechto Branch offices :
o Sliedrecht (NL)o Antwerp (B)o Brussels (B)o Basel (CH)o Strasbourg (F)o Ottmarsheim (F)o Lille (F)
o Number of employees : 140 o Danser owned vessels : 4 o Danser chartered vessels : 60 o Transported in 2013 : > 1,0 million
TEU
Company profile
2Co-financed by European UnionTrans-European Transport Network (TEN-T)
Ben Maelissa
Operating Area
3Co-financed by European UnionTrans-European Transport Network (TEN-T)
Ben Maelissa
“ Eiger-Nordwand”
Built 2000Overall lenght 177 meterWidth 11,45 meterDraft 2,56 meterTonnage 5300 tonnesCapacity (4 layers) 348 TEUEngines 2x 900 kW
Vessel particulars
1st LNG Refi t on In land Vesse l
4Co-financed by European UnionTrans-European Transport Network (TEN-T)
Ben Maelissa
Project Targets
• Meet customer demand; green transportation• Meet upcoming legislation by ports and governments • Meet Danser Group strategy: Frontrunner in clean & safe
transportation • Emission meeting (expected) CCR4 requirements• Pilot for LNG refit on 4 more container vessels
How:• Installation Dual-Fuel propulsion system
(Wärtsilä Engine, Tank/ Coldbox)• Increased performance; fully redundant • Safety leading parameter in overall design
5Co-financed by European UnionTrans-European Transport Network (TEN-T)
Ben Maelissa
REFIT Arrangement
• Proven design of all major components, based on multiple years of experience • Dual-Fuel Engine: automatic switch over to gasoil in case of failure/ alarm• Dual-Fuel Engine: designed for LNG as main fuel (minimum 95%)• Dual-Fuel Engine with a/o double wall piping; gas safe Machinery Room ! • Gas detection and auto shut down of main LNG valve • Double redundant ventilation• Trained crew & management
6Co-financed by European UnionTrans-European Transport Network (TEN-T)
Ben Maelissa
Project Summery
• Feb 2012• Jun 2012• July 2012• Dec 2012• Feb 2013• Mar 2013• Aug 2013• Sept 2013• Oct 2013• Feb 2014• Apr 2014• Jun 2014• Jul 2014
• Start project, initial discussions• Conceptual design by project team • Presentation to LRoS• Introduction to Ministery of Infrastructure (IL&T, I&M)• Submission call for TEN-T project• Start detailed design • Presentation at ADN meeting in Geneve• Presentation at CCR meeting in Strasbourg• HAZID study by LROS• Recommendation of CCR is recieved• Start refit• Tests, commissioning & trials • Refitted ship started its normal operations
7Co-financed by European UnionTrans-European Transport Network (TEN-T)
Ben Maelissa
Reflecting current operations
• Between 20-25% reduction on fuel costs
• 95-99% LNG
• Building up confidence of crew on “working with” – “sailing on” LNG
• Less noise generation
• Bunkering time reduced to 3 hours
8Co-financed by European UnionTrans-European Transport Network (TEN-T)
Ben Maelissa
THANK YOUQUESTIONS ?
www.danser.nl 9Co-financed by European Union
Trans-European Transport Network (TEN-T)Ben Maelissa