1 Market Operations Presentation Board of Director’s Meeting September 16, 2003
Transcript
Page 1: 1 Market Operations Presentation Board of Director’s Meeting September 16, 2003.

1

Market Operations PresentationBoard of Director’s Meeting

September 16, 2003

Page 2: 1 Market Operations Presentation Board of Director’s Meeting September 16, 2003.

2

Market Services – YTD Perspective

Page 3: 1 Market Operations Presentation Board of Director’s Meeting September 16, 2003.

3

Client Relations - Wholesale

Wholesale Market Participants

10 Account Managers

Market Participants per Account Manager

Dispute Activity: 3+ / per Account Manager / Day

89 Qualified Scheduling Entities – includes 25 Sub-QSEs

128 Resource Entities

142 TDSPs – includes 130 non opt-in entities

9 QSEs, 12 Resources, 14 TDSPs

Page 4: 1 Market Operations Presentation Board of Director’s Meeting September 16, 2003.

4

2003 Year to Date: 5,199

Granted w/ Exceptions, 970

Denied, 3,091

Granted 354

Open 784

Dispute Status

Page 5: 1 Market Operations Presentation Board of Director’s Meeting September 16, 2003.

5

Settlement Disputes Genesis

Errors / omissions

Repetitive disputes/ placeholders

Challenges to protocol language

Sometimes used to lodge complaints

Market events often drive up dispute volumes

Disputes required by protocol

SCR 727 load imbalance disputes

February local congestion / market solution issue

Page 6: 1 Market Operations Presentation Board of Director’s Meeting September 16, 2003.

6

Client Relations - Retail

Retail Market Participants

6 Account Managers

Market Participants per Account Manager

FasTrak Activity: 10 / per Account Manager / Day

74 Competitive Retailers

12 TDSPs

12 CRs, 2 TDSPs

Page 7: 1 Market Operations Presentation Board of Director’s Meeting September 16, 2003.

7

FasTrak 2003 “Day to Day”Issue Stats (as of 09-12-2003)

Total ESI IDs worked to date since January 1, 2003 = 204,883

IssueCount

Issues as a% of Total

In Progress 583 6.09%

Resolved 8,425 88.05%

Rejected 560 5.86%

TOTAL 9,568

IssueCount

Issues as a% of Total

In Progress 1,485 55.79%

Resolved 1,131 42.49%

Rejected 46 1.72%

TOTAL 2,662

Non-ERCOT

ERCOT

Number of ESI IDs not tracked

Page 8: 1 Market Operations Presentation Board of Director’s Meeting September 16, 2003.

8

Upcoming Highlights• ERCOT 101 – Retail Market – September 18th

64 people from 26 companies

• Q4 2003 V1.6 Market TestNew CRs: Alliance Power Company

Pegasus Star EnergyProviron Energy LimitedTrizec HoldingPedernales Co-op

• 2004 Market Tests

Flight 0104 – V1.6 for New MPsFlight 0304 – V1.6 for New MPsFlight 0504 – V2.0 MIMO Stacking SolutionFlight 0904 – V2.0 for New MPs

• ProjectsV1.6 Competitive MeteringV2.0 MIMO Stacking SolutionETS Continued Evolution

Page 9: 1 Market Operations Presentation Board of Director’s Meeting September 16, 2003.

9

• Market Operations – Top Issues

– Data Extract Variance Tracking– 2002 and 2003 True Ups and Proposed

Resettlements

Page 10: 1 Market Operations Presentation Board of Director’s Meeting September 16, 2003.

10

FasTrak Data Extract VarianceIssue Stats (as of 09-12-2003)

Service History Usage

TotalIssues

Issues% of Total

In Progress 622 0 622 44.68%

Resolved 131 0 131 9.41%

Rejected 611 28 639 45.91%

TOTAL 1,364 28 1,392

Service History Usage

TotalIssues

Issues% of Total

In Progress 586 898 1,484 64.55%

Resolved 236 274 510 22.18%

Rejected 102 203 305 13.27%

TOTAL 924 1,375 2,299

Non-ERCOT (CR to TDSP)

ERCOT

number of ESI IDS not tracked

number of ESI IDS not tracked

Page 11: 1 Market Operations Presentation Board of Director’s Meeting September 16, 2003.

11

2002 and 2003 True ups

Current Schedule:

2003 True ups

Oct 1 ‘03

2002 True ups

Page 12: 1 Market Operations Presentation Board of Director’s Meeting September 16, 2003.

12

Current Schedule:

2003 True ups

Oct 1 ‘03

Proposed Schedule: Oct 1 ‘03 Feb 1 ‘04

2002 and 2003 True ups

2002 True ups

2002 True ups

Page 13: 1 Market Operations Presentation Board of Director’s Meeting September 16, 2003.

13

Current Schedule:

2003 True ups

Oct 1 ‘03

Proposed Schedule:

2003 True ups

Oct 1 ‘03 Feb 1 ‘04

min 120 daysuspension

Preserves dispute rights

2002 and 2003 True ups

2002 True ups

2002 True ups

Page 14: 1 Market Operations Presentation Board of Director’s Meeting September 16, 2003.

14

Current Schedule:

2003 True ups

Oct 1 ‘03

Proposed Schedule:

2003 True ups

Oct 1 ‘03 Feb 1 ‘04

min 120 daysuspension

New 2003 Resettlements

Preserves dispute rights

Participant cash flow approx the same

2002 and 2003 True ups

2002 True ups

2002 True ups

Page 15: 1 Market Operations Presentation Board of Director’s Meeting September 16, 2003.

15

Current Schedule:

2003 True ups

2002 True ups

Oct 1 ‘03

Proposed Schedule:

2003 True ups

2002 True ups

Oct 1 ‘03 Feb 1 ‘04

min 120 daysuspension

New 2003 Resettlements

Preserves dispute rights

Participant cash flow approx the same

Initial resettlements will be for unusual days in June ‘03

2002 and 2003 True ups


Recommended