+ All Categories
Home > Documents > 1 Market Reform Forum Update on business reform 26 May 2005 Andy Brookes LMP/Lloyds BPR.

1 Market Reform Forum Update on business reform 26 May 2005 Andy Brookes LMP/Lloyds BPR.

Date post: 28-Mar-2015
Category:
Upload: nicholas-miles
View: 216 times
Download: 3 times
Share this document with a friend
Popular Tags:
10
1 Market Reform Forum Update on business reform 26 May 2005 Andy Brookes LMP/Lloyd’s BPR
Transcript
Page 1: 1 Market Reform Forum Update on business reform 26 May 2005 Andy Brookes LMP/Lloyds BPR.

1

Market Reform Forum

Update on business reform

26 May 2005

Andy Brookes

LMP/Lloyd’s BPR

Page 2: 1 Market Reform Forum Update on business reform 26 May 2005 Andy Brookes LMP/Lloyds BPR.

2

Objective: up to speed in half an hour……

A reminder – why we are doing this

Contract Certainty

LMP slips

CC Implementations

Evidence of cover

Supporting projects, including Kinnect

Back office electronic infrastructure

Accounting and Settlement

Electronic Claims Files

What you should be doing

Today special topic: measurement

Page 3: 1 Market Reform Forum Update on business reform 26 May 2005 Andy Brookes LMP/Lloyds BPR.

3

Why do this? The challenge

In London sufficient talent (underwriting, broking,advisory) meets sufficient capital to create “a market”

But business is mobile and….. cost of business process is too high operational risk is too high

- lack of audit trail, lack of proper/timely documentation

London does not meet increasing regulatory standards

- Spitzer – transparency; Tiner – certainty

So, London (including Lloyd’s) must improve its processes to Reduce cost Reduce risk Increase transparency

Page 4: 1 Market Reform Forum Update on business reform 26 May 2005 Andy Brookes LMP/Lloyds BPR.

8

Contract certainty: FSA challenge

Tiner’s speech: end to “deal now, detail later”

End 2006 deadline

Lit the already smouldering platform

Answering the FSA requires:

- clear plan pulling together components

- measurable progress against that plan

- your participation

Page 5: 1 Market Reform Forum Update on business reform 26 May 2005 Andy Brookes LMP/Lloyds BPR.

9

Contract certainty: the programme Key projects

Improve LMP slips – 99% March 2006 During bind: agree wordings; get checking done

- Contract Certainty Implementation, CCI

- 30% of business end 2005; 85% end 2006 Evidence of cover – within 30 days

Supporting projects Kinnect/placement systems –

- Consistent with all this, but reduce compliance cost Policy checking by Xchanging

- Prudential Practice Requirements; binders done; publish open market checks (June); publish compliance stats (Q4 2005)

Legacy- Agree cross market priority rules – end June

- Recalculate stats; that’s it?

Page 6: 1 Market Reform Forum Update on business reform 26 May 2005 Andy Brookes LMP/Lloyds BPR.

11

LMP Slips – wider and deeper

March BSA headline: 92%

Continue to check 25% of Lloyd’s slips in 2005; IUA timetable set for companies

LMP Slip 2005

- published in April

Extending to lineslips

- Should be agreed in Q2

- Mandated late Q3?

Monitoring BA LMP Slips – commenced Jan 05- March 05 94%

Page 7: 1 Market Reform Forum Update on business reform 26 May 2005 Andy Brookes LMP/Lloyds BPR.

12

Kinnect 3 additional customers announced in May

- Chaucer, Cathedral, Limit/QBE

Three brokers and fifteen carriers

- +60% of Lloyd’s capacity

500 risks, 1300 signed lines and $800m of premium in last year New release 1 June as planned

- Enhanced placing functionality

- Slip creation by brokers in Kinnect

- One-way data flow initially but appetite for two-way

Risk class expansion

- North American property Now

- Terrorism June

- International property Nov.

Further risk classes agreed for 2006 Data light template for any risk class being considered

Page 8: 1 Market Reform Forum Update on business reform 26 May 2005 Andy Brookes LMP/Lloyds BPR.

13

Accounting & Settlement

Technical and data information: Phase 1, published in April

- Who is digesting it in your firm/supplier? Views please

- Phase 2 likely to be June (was May) – claims, ORI

Accounting splits: Code of practice being finalised

Migration (legacy and crossover): Complete for premium, claims (Section 2 of technical information)

MRIB and Project Board working on implementation timetable

- Key deliverable is content, sequence and dates in implementation timetable

- Key issue is risk appetite and management: dearer or slower?

- Don’t doubt commitment to progress

- Had planned to publish in Q1, aiming for Q2

Page 9: 1 Market Reform Forum Update on business reform 26 May 2005 Andy Brookes LMP/Lloyds BPR.

14

Electronic Claims File Purpose: electronic claims for Lloyd’s (and then…..) XIS development work

Phase 1 - Operational in February Phase 2 - Now live Overall business process spec being signed-off later than planned

- Better end outcome for practitioners; but pressure on timelines Phase 3 DRI design signed-off

- Wider functionality issues; LMA, LMBC and Claims Project Board managing Implementation

6 partnerships operational (was 4) Low volumes – 44 claims completed; major volume increase post-DRI 57 (up from 40 last month) potential partnerships identified

Governance – Project Board and MRIB- Named brokers commit to deliver 100% new claims from Q3 2006

- Named Managing Agents commit to use ECF for new claims from Q3 2006 Live issues

Cross market procedures and practices Policy issues starting to surface eg access control

Page 10: 1 Market Reform Forum Update on business reform 26 May 2005 Andy Brookes LMP/Lloyds BPR.

15

Market Reform Forum

Update on business reform

26 May 2005

Andy Brookes

LMP/Lloyd’s BPR


Recommended