+ All Categories
Home > Documents > 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional...

1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional...

Date post: 02-Jan-2016
Category:
Upload: alexis-sanders
View: 220 times
Download: 0 times
Share this document with a friend
Popular Tags:
38
1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual governance
Transcript
Page 1: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

1

Per Willy HetlandStatoil Project Academy

Project owner

General contractor

Project functional units/Sub-suppliers

Engineering contractor

Contractual governance

Page 2: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

2

The new wave in project management New realities for managing projects New leadership principles New project challenges New competencies Shift in mindsets Change of behaviour Excerpts from Statoil Project Executive Programme

Page 3: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

3

Maturity

Time1950 2000

Enhancing Business Value

Execution Excellence

Page 4: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

4

CorporateBusinessStrategies

LeadershipPrinciples

New ProjectChallenges

NewCompetencies

Shift inMindset

Change ofBehaviour

ProjectBusiness Value

Page 5: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

5

Stimulating new ideas and creativity Chasing business opportunities Challenging accepted truths Entering unfamiliar territory Setting ambitious targets

That increase uncertainties and risk simultaneously sharpen personal accountabilities to deliver as promised

Page 6: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

6

Increasing variety and complexity New technology New business practices Unfamiliar locations Turbulent geopolitical contexts

That require new and enhanced project competencies

Page 7: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

7

Craft and apply project execution strategies that: Enhance business value Over the complete project life cycle Considering uncertainties, risks and opportunities By applying the new leadership principles

The new world for project managers requires a step change from the past practices where focus was on delivering projects as specified on time and within budget to deliver project business value

Page 8: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

8

THE PAST

ConceptDevelopment

BusinessStrategy

Project Execution Planning

Quality (Performance)

Time Cost

Deliver as specified on time and within budget

Comply with prescriptive project execution proceedures

Page 9: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

9

THE PRESENT

ConceptDevelopment

BusinessStrategy

Project Execution Planning

Quality (Performance)

Time Cost

Strategy

Execution

Stage gated approach to reduce risks

Align project execution to project strategy

Page 10: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

10

THE FUTURE

•New Project Challenge (1)

•Shift in Mindset (2)

•Added Knowledge (3)

•Change of Behaviour (4)

12

34

Leadership driven project value enhancement

Drive project business value and master risks

Page 11: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

PE AlumniM0 ME

M1

M2 M3

M4

Conte

xt

Context

Conte

xt Context

Turning Business Opportunities into Project Strategies

Exp

lora

tive

Beh

avio

r

Adapting to geo-political context

Adaptive Behavior

Driving Execution

Excellence

Skills

Skills

Skills Skills

New Knowledge

Del

ive

ry-o

rien

ted

Be

hav

ior

CHANGE OF BEHAVIOR

Page 12: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

12

Project strategies Project environments The project supply chain Project eco-systems Project contract archetypes Conventional pricing Conventional dilemmas Alignment of interests Incentive contracts

Page 13: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

13

Project

ExecutionSanction Hand over

Development Implementation

Value p

otentia

l

Value cre

ation

Value delivery

Business o

pportunity

Productio

n start-up

Abandon

Hand over

Sanction

Development planning

The project owner perspective

Page 14: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

14

ProjectBusiness case

Corporate

Supplier’s external project environment

Supplier’s internal project environment

External environment

Page 15: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

15

EC

IC

CVNV

FCMS

MaterialTake Off

Vendorinformation

Drawings

Materials

Modules

Services

Horizontal ties

Page 16: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

16

Vertical ties

O

V

FC

IC

Project owner

1st tier suppliers

2nd tiersuppliers

Page 17: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

17

The General Contractor StructureProject owner

General contractor

Project functional units/Sub-suppliers

Engineering contractor

Contractual governance

Page 18: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

18

LegalAspects

Aspects ofTrust

CommercialAspects

IncentivisedConcepts

ConventionalPricing

RelationalContracts

PartneringContracts

MarketContracts

Page 19: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

19

Probability

Cost

+ -Motivational effect

EV(P) EV(0) EVC

-+

Competition Moral hazardHRLR

Client net benefit

Riskpremium

PriceBasedContract

CostBased Contract

Page 20: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

20

Owner interests

Supplier interests(fixed price contracts)

Supplier interests(reimbursable contracts)

Conventional pricing formats

Incentivised contracts

Page 21: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

21

Contractor’sProfit margin

Contractor’s Costs

Fixed price bid

Estimated Contract costs

Calculated Profit margin

Calculated Risk premium

Risk Cap

Risk free “bid”

Client incentive

Contractor incentive

Gai

n s

har

ing

Risk transferredto customer

Page 22: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

22

Vive la difference! Projects are different Strategies are different – effectiveness or efficiency Strategies are different - determinism or dynamism Strategies are different - implications for project risks

Page 23: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

23

• Projects are different• Project environments are different• Project strategies are different

DEFENSIVE

ADAPTIVE

OFFENSIVE

RobustnessResilience

VersatileMalleable

Agile

Page 24: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

24

Closed Open

More of the same(status quo)

Incremental improvement

Don’t know what to doBut can’t stay here(quo vadis)

Radical change

Page 25: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

25

Customize

Standardize

Reuse Innovate

Increasing efficiency

Increasing effectiveness

Page 26: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

26

Fuzzy specifications

Functional specifications

Stretched targetsPROJECT OBJECTIVES

Guidelines

Value engineering

Re-engineeringDefensive concepts

Adaptive concepts

Offensive concepts

DEFINITIVE CONCEPTS

OPTION VALUE

PROJECT DYNAMICS

PROJECT PROCESSES

Page 27: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

27

Detailed specifications

Fuzzy specifications

Stretched targets

Functional specifications

Moving targets

Defensive concepts

Adaptive concepts

Offensive concepts

Definitive concepts

Project sanction

Incr

ea

sin

g e

xecu

tion

ris

ks

Page 28: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

28

Project internal decisions Project external decisions One-directional state variables Two-directional state variables

Page 29: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

29

Ran

dom

var

iatio

ns

Doi

ng th

ings

righ

t

Doi

ng th

e rig

ht th

ings

Doing things w

rong

Doing the wrong things

IMP

AC

T O

N C

AP

EX

, LC

P, N

PW

+

_

Opportunitymanagement

Riskmanagement

FREEDOM TO ACT

Page 30: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

30

INTENTIONALDISRUPTIVE

INTENTIONALSUPPORTIVE

IMPACT ON CAPEX (-), LCP, NPW

+

_

Proactive involvement

Constructivedialogue

Reactive critique

Interference

Attack

Incompetence

Risk management

Opportunity management

Page 31: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

31

IMPACT ON CAPEX (-), LCP, NPW+

_

FORCE OF VARIABLE

Planned for

Cost of Risk buffer Worse case

scenarioCost of resiliencemeasure if activated

Page 32: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

32

IMPACT ON CAPEX (-), LCP, NPW+

_

FORCE OF VARIABLE

Decrease Increase

Sales prices

Factor prices

Planned for

Break even

Loss

Bancroft

Page 33: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

33

Offensive management of uncertainties Contractor influence on CAPEX Influence on Life Cycle Profit, LCP Influence on Net Present Worth, NPW

Page 34: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

34

NPW

EVCE

Cost of risk

p

p

p

NPW

NPW

CE EV

Cost of risk

Cost of risk

Reduce risksIncrease opportunities

DEFENSIVESTRATEGIES

OFFENSIVESTRATEGIES

Page 35: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

35

CAPEX

TIME

Influ

ence

San

ctio

n

Co

ntr

act

awar

d

Give away value potentialIn lump sum contracts

Potential risks inDecision variables• Owner’s decisions• Contractor decisions• Effects of sunk cost

Page 36: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

36

1

2

3

4 5

6

7

1 Start production 4 Planned downtime2 Production built-up 5 Unplanned downtime3 Plateau production 6 Start tail production

7 Abandoning

Added value

Pro

ject

san

ctio

n

LCP

TIME

Page 37: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

37

Option value: Investments in future extensions

Corporate risk exposure: Portfolio relevant risks Corporate strategy risk Reputation risk

Sanction Hand over TIME

NPW

Page 38: 1 Per Willy Hetland Statoil Project Academy Project owner General contractor Project functional units/ Sub-suppliers Engineering contractor Contractual.

38

Clients don’t buy project deliveries anymore

They buy project business value


Recommended