Procedure for the determination of time
required to perform a task involving either human
or machine under certain standard conditions of
measurement
• Direct time study
• Predetermined time system
• Standard time data
• Work sampling
2
Systematic procedure that divides an
operation into motions or work elements, with a
set of time data assigned to each elements
• Allowance excluded
• Various available systems, for examples
• Work - Factor System
• Method - Time Measurement (MTM)
3
• Developed from 4-year implementation of Micromotion study
• Employed in 1938
• Four techniques:
• Detailed• Ready • Brief• Mento-Factor
4
• Body Members
Finger, Hand, Arm, Body, Leg , Foot, etc.
• Distance by Inch
• Weight & Resistance
• Manual Control
Basic, Definite stop, Directional control,
Care, Change of direction
Time Unit: 1/10,000 min
5
• Body Members
• Distance by Inch
• Weight & Resistance
• Manual Control
T, FT, L, HT
F, H, A, FS
0 = Basic
1, D = Definite stop
2, S = Directional control
3, P = Care
4, U = Change of direction
6
A10
Description of job: …..
Time Required: …...
A30WS
Description of job: …..
Time Required: …..
7
• More Focus on Basic elements
• First developed for Drill Press Work
• Time Unit: 1/ 100,000 hr
(TMU, 0.0006 min)
• A family of MTM
8
• Transport (Reach & Move)
• Grasp
• Pre-Position
• Assemble
• Use (Manual, Process or Machine)
• Disassemble
• Mental Process
• Release
9
Reach• Class of Reach: A - E
• Distance measured in Inch
• Motion of hand
• Example: R8C, Time Unit= 11.5
• Equivalent to …… Min.
10
Move• Class of Move: ……..
• Load measured in …….
• Motion of hand ??
• Example: mM10C, Time Unit= …...
• Equivalent to …… Min.
11
• Trial time study, Based on work instruction & work station layout
• Verify time data, Compared to Direct time study
• Applicable to most of jobs
• No Rating Factor
• Facilitate Motion-Minded training
• Tools & equipment Design / Setup
• Estimate processing time required for cost
estimation
12
• Selection of Various Systems
• Well trained analyst
????
13
14
Applications
1) Determine machine utilization / downtime
2) Determine allowances
3) Establish time standards
Concept: To find out the proportions of total time
devoted to various activities that constitute a
job, by taking a large number of observations
at random times.
15
Basic idea
• Random sampling over a long period of working hour
• Binomial distribution: p,q ratio out of n observations,
which approaches Normal distribution when n is large
npq
Distribution of a proportion: at 95%CI and +/- 5% relative accuracy, Z = 1.96
Mean, proportion of working time = p
Standard Deviation =
16
0) Obtain cooperation from all concerns
1) Trial observations or a past record
2) Determine the number of obs. needed: Alignment chart
3) Design data collection procedure
a. Observer: number of person, position
b. Period of the study
c. Time table for daily random observation
d. Observation sheet
4) Assure 95% CI and +/- 5% relative accuracy
5) Calculate utilization ratio or standard time
17
Table of Random Numbers
Daily working hours
Frequency of daily obs.
Routes of observation
Observation sheet
Observe At First sight
Data Summary and control
Recheck CI and accuracy level
18
Control Chart (P chart) is to make sure every reading is in normal condition
mean
UCL = p + 3sigma
LCL = p - 3sigma
day
p, daily
mean = expected value of relevant proportion, p
sigma = standard deviation of p
3 sigma = 99.7% of population should fall within the range
19
P chart: To detect unusual situation during the study
Within chart values
Out of chart values
Reasons of the unusual daily p
a) accident
b) lack of proper production flow
c) a change in expected value of p reconstruct the p chart, using the new information
20
• 95% CI & +/- 5% relative accuracy
• Alignment chart or
Table for determining the number of obs.
given degree of accuracy, value of p at 95% CI
• Table for determining the degree of accuracy given number of obs., value of p at 95% CI
21
total output during total time
Rep. Time = (total time spent) (proportion)
Normal Time = Rep. Time (Performance Index)
Std. Time = Normal Time + Allowances
22
Advantages: compared with Direct time Study
• No continuous observation
• Normally less cost
• Study crew operation by one analyst
• Study long cycle time operation
• Easy to observe
• Don’t need specialist
• Operator would not feel under too much attention
23
Disadvantages
• No details about operation
• Not suitable for short cycle task
• ??