Date post: | 20-Jan-2018 |
Category: |
Documents |
Upload: | ruth-white |
View: | 216 times |
Download: | 0 times |
1
Radiation worries in the Radiation worries in the caverncavern
L.Jirdén 17.6.02L.Jirdén 17.6.02
2
AccessAccess
~55m
PLUG
ALICEDETECTOR
CR1
CR3CR2
CR4
ACR
BEAM
~50m
~15m
Cavern only accessible during shutdowns !
3
Magnetic fieldMagnetic field
~55m
PLUG
ACR
BEAM
~50m
~15m
0.5 T
No impactStray fields, impact ?Shielding DC/DC’s, etc
Two main magnetsL3 and MUON dipole
4
Radiation levels in Radiation levels in ALICEALICE
Simulation made by B.Pastircak 3 main sources:
Particle production at interaction point: 90% Beam-gas interactions: 10% Beam loss at injection: 1%
Conditions Global running scenario PbPb, CaCa, pp Geometry as known early 2002
Results Normalized to 10 years normal operational scenario Total dose [krad] Fluency [n*cm-2] Rack on the floor ~ 1 ~109
Rack 12m above floor ~ 0.006 ~107
5
Radiation levelsRadiation levels
~55m
PLUG
ALICEDETECTOR
ACR
BEAM
~50m
~15m
200 175 rad hard el. required 2 4.3 COTS ok, SEU strateg 1 0.9 SEU strategy ?0.006 0.0006 minor effects?
racks in c-rooms
gas distribution
racks in cavern
dose n.fl.Krad E10 n/cm2
6
7
Radiation testsRadiation tests
8
9
ConsequencesConsequences Test by experiments
Extensive tests of “on-detector components” Very few tests of ALICE “cavern components” ATLAS ELMB test since 3 years Wiener Power supplies, CAEN DC/DC
Test of equipment by LHC machine Ongoing effort since 5 years Wide range of equipment tested
power supplies, PLC’s, sensors, gagues, vacum equipment, etc Mainly using TCC2 facility Levels in LHC tunnel and ALICE cavern similar? To be checked!
10
SPS - North SPS - North Experimental HallExperimental Hall
TCC2 Hall and Beam Lines
TAX collimatorM2 beam line
T6 TargetRadiation Damage Test Area
LHC tests
11
Modular Power SuppliesModular Power Supplies Denis Hundzinger - SL/PO Denis Hundzinger - SL/PO
Test of 3 Different Technologies: Serial Regulation Switching with Bipolar, Transformer Coupling Switching with MOS-FET, Transformer Coupling
28 Units Tested – 11 Types – 6 Manufacturers
Remarks: Some Units Do Not Restart after Switch-Off Output Voltage Drifts With or Without Input Power
LHC tests
12
Switching Switching Power SuppliesPower SuppliesType: - VERO PK55 (2 Modules)
- Triple Switching
+ 5V/5A and 2x 5-15V/1A
Notes:- Measurement on 5 Volt Output Only
- Load = ~ 4 Amp
- Output Voltages increase with the Radiation Dose
- Both 5 Volt Output Voltages Start to Deteriorate at ~ 5 Grays
~ 5 Gray
~ 540 Gray
LHC tests
13
Preliminary ResultsPreliminary Results
PLC - First Error (Isolated Effect) at < 1 Gy - After Reload, Systematic Memory Error 4-8sec. 5 Gy - No Reply 20 Gy Edwards Gauges (With Integrated Electronics) - Gauge AIMX-X 50 Gy - WRG-S 1000 Gy Balzers Gauges - 2 Gauges PKR 251 290 Gy and 430
Gy - 1 Gauge PKR 265 450
Gy
LHC tests
14
Lessons LearnedLessons Learned Electronic Equipment that Will not Work Reliably
in the LHC Tunnel:
Intelligent Sensors and Actuators (Few Exceptions)
(Remote Electronics and Cables Required)
Complete Industrial PLCs (COTS)
Intelligent I/O Modules (COTS) with Micro and Memory
Conventional Switching Power Supplies (NMOS)
Processors Without Error Correction Memory
LHC tests
15
Lessons LearnedLessons Learned LHC Electronic Equipment That Needs to be Tested
before Installation:
Passive Components (Optical Fibers, Resistors, Capacitors)
Active Components (Signal Conditioners, MUXs, Op.-Amp.,
ADCs, DACs, FPGAs, EPROMs SRAMs with EDAC)
Sensors, Actuators, Gauges, Positioners,Valves, Flowmeters
Modular Power Supplies (Serial Regulation, Bipolar Transistors,
Transformer Coupling Feedback, No OptoCouplers)
LHC tests
16
Lessons LearnedLessons Learned RadHard Developments are Required for:
Simple Input/Output Modules with Fieldbus Interfaces to WorldFIP or Profibus (Command/Response Operation)
Dedicated Power Supplies (Quench Protection) Orbit Corrector Power Converters Control Processors with EDAC Memory and
Remote Reset Capability.
LHC tests
17
ConclusionsConclusionsPresent Results Suggest that ALL Electronic
Systems, Intended for Installation in the Tunnel, Should be Radiation Qualified
The Radiation Test Facility is Qualified to Provide a Radiation Environment
Similar to That of the LHC Tunnel (Arcs)
The On-Line Test Facility can be Used for the Final Qualification of Complete Working
Systems
LHC tests
18
What equipment is planned What equipment is planned for ALICE cavern?for ALICE cavern?
Power distribution (Hazemeyer) + control Network equipment LV supplies
CAEN 1527, Wiener PL500, AREM Pro, Eutron, ? HV supplies
CAEN 1527, ISEG, ? Gas
Distribution for some detectors Cooling
Cooling plants & its control Detector cooling I/O
VME Crates and modules
Others?
19
ConclusionConclusion More detailed simulations needed Effects (at middle and low levels) to be
better understood Strategy to be defined Possibility to move equipment from UX to
PX? Systematic qualification of “cavern
equipment”? Who does what?