+ All Categories
Home > Documents > 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning...

1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning...

Date post: 30-Jan-2016
Category:
Upload: roberta-wilkinson
View: 212 times
Download: 0 times
Share this document with a friend
Popular Tags:
20
1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda Run 8 end game issues, if any anning Meeting Web Site: http://www.c-ad.bnl.gov/esfd/RMEM_08/rhic_planning.
Transcript
Page 1: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

1

RHIC Machine/Detector Planning Meeting 29 Jan 08

Agenda

– Run 8 end game issues, if any

Planning Meeting Web Site: http://www.c-ad.bnl.gov/esfd/RMEM_08/rhic_planning.htm

Page 2: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

2

Run 8 Log

• 25 Oct, begin 45 degree cold wave (2.5 MW-NEW)• 1 Nov, Cool-down to 4.5 degrees begins• 4 Nov, Blue ring cold but still stabilizing• 6 Nov, Blue and Yellow cold and stable (0.9 weeks into run)• 8 Nov, Beam in Blue ring, “Setup Mode begins”• 16 Nov, Beam in Blue and Yellow rings• 18 Nov, First collisions (2.6 weeks into run)• 19 Nov, Experiment Magnets on, begin night shifts for experiments, “Ramp-up

Mode” begins (2.7 weeks into run)• 26 Nov (1600 hrs), Machine declared operational for Physics (3.7 weeks into run)• 29 Nov, PHENIX in physics mode• 1 Dec STAR in limited physics mode (min-bias)• 31 Dec, STAR in full physics mode• 28 Jan, 0800, end dAu run (9 weeks physics)• 28 Jan, maintenance and begin 100x100 GeV pp setup• 10 Mar, 0800 pp run ends (6.0 weeks), Low energy AuAu setup begins• 12 Mar, 0800 low energy AuAu ends• 14 Mar, Cryo warm-up complete (19.3 cryo weeks)

Page 3: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

3

Run8 RHIC dAu Integrated Luminosity for Physics (FINAL - singles corrected)

0.0

25.0

50.0

75.0

100.0

125.0

150.0

175.0

200.0

225.0

250.0

26

-No

v-0

7

3-D

ec

-07

10

-De

c-0

7

17

-De

c-0

7

24

-De

c-0

7

31

-De

c-0

7

7-J

an

-08

14

-Ja

n-0

8

21

-Ja

n-0

8

28

-Ja

n-0

8

Since beginning of Physics

inte

gra

ted

lu

min

os

ity

(n

b-1

)

STAR

PHENIX

Lmax

Lmin

PHENIX Original Goal

STAR Original Goal

Page 4: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

4

Run8 RHIC dAu Available Luminosity per day

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.0

26-No

v

3-Dec

10-Dec

17-Dec

24-Dec

31-Dec

7-Jan

14-Jan

21-Jan

28-Jan

Since beginning of Physics

m b-1

per

day

PHENIX

L Max/day

L Min/day

STAR

APEX/Maintenance days

APEX

m

Page 5: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

5

PHENIX Goals for Run-8 pp

• Plan A– If higher luminosity, polarization achievable in Run-8

– 7.5-10 pb-1 recorded, at P=0.6

– if we must plan on 1.2 pb-1/week at P=0.5

– will be forced to return to transverse spin running

– in a future year

– we’ll tell you when, when you tell us the luminosity

• Plan B– 2.5 pb-1 recorded at the maximum P you can give us

– Switch ASAP to 500 GeV p+p for ≥ 2 weeks

– We consider development so important we’ll risk the very short physics run

– Skip the low energy test run in Run-8

Page 6: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

6

STAR Goals for the 200 GeV pp run

• FMS reference data– Sample at least 9 pb-1 with fast detectors

• FMS transverse spin asymmetry measurements– Sampled figure of merit (P2L) at least 3.8 pb-1 with fast detectors

– Equivalent to 9 pb-1 at 65% polarization

• Slow detector measurements for non-photonic electrons– Sample at least 4.5 pb-1

• This requires:– C-AD deliver at least 18 pb-1 (assumes 50% STAR up time)

– STAR operate the slow detectors with at least 50% live time

– FMS fast detector data recorded when the slow detectors are both live and dead

• Has not been done during this year’s d+Au run

• Was done during Run 6 p+p

Page 7: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

7

Run 8 pp projections

0

5

10

15

20

25

30

35

40

45

50

0 1 2 3 4 5 6

Weeks in physics mode

Inte

gra

ted

Lu

min

os

ity

(p

b-1

)

minimum

maximum

PHENIX Plan A60% pol

PHENIX Plan BWhatever % polThen switch to s=500 GeV andNo Low E AuAu

STAR65% pol

End of run

STAR50% pol

p.pile understanding of experiment goals

max

min

PHENIX Plan A50% pol

Page 8: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

8

Through 28 Jan 2008

BNL Energy Use FY 2006-8(C-AD Bldg 911 power is in AGS-Exp/Mach)

0

5

10

15

20

25

30

35

40

45

50

55

601-

Oct

-05

1-D

ec-0

5

1-F

eb-0

6

1-A

pr-0

6

1-Ju

n-06

1-A

ug-0

6

1-O

ct-0

6

1-D

ec-0

6

1-F

eb-0

7

1-A

pr-0

7

1-Ju

n-07

1-A

ug-0

7

1-O

ct-0

7

1-D

ec-0

7

Date

Da

ily A

ve

rag

e P

ow

er

(MW

)

$-

$10

$20

$30

$40

$50

$60

$70

$80

$90

$100

$110

$/M

Wh

r

RHIC Cryo RHIC otherAGS-Mach CAD Bldg less SMDTandem BoosterAGS-Exp NSRLSite Base Peak-Av$/MWhr

begin "balanced billing"

Page 9: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

9

Through 28 Jan 2008

RHIC Cryo Operations FY06-08

0.00

1.00

2.00

3.00

4.00

5.00

6.00

7.00

8.00

9.00

10.00

-30 -10 10 30 50 70 90 110 130 150 170 190

Days since beginning of Run

MW

RHIC Cryo 06

RHIC Cryo 07

RHIC Cryo 08

Page 10: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

10

Through 28 Jan 2008

RHIC Operations FY06-08

0.00

5.00

10.00

15.00

20.00

25.00

30.00

35.00

-30 -10 10 30 50 70 90 110 130 150 170

Days since beginning of Run

MW

CAD Power 06

CAD Power 07

CAD Power 08

Page 11: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

11

Through 28 Jan 2008

BNL Energy Use FY 2007-8(C-AD Bldg 911 power is in AGS-Exp/Mach)

0

1

2

3

4

5

6

7

8

9

10

11

12

1-O

ct-0

6

1-D

ec-0

6

1-F

eb-0

7

1-A

pr-0

7

1-Ju

n-07

1-A

ug-0

7

1-O

ct-0

7

1-D

ec-0

7

1-F

eb-0

8

Date

Dai

ly A

vera

ge

Po

wer

(M

W)

AGS-Mach RHIC otherRHIC Cryo CAD Bldg less SMDTandem AGS-Exp

NSRL BoosterSite Base Peak-Av

Page 12: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

12

FY 2006-7 Power Bill

$-

$20

$40

$60

$80

$100

$120

$140

Jun

-05

Se

p-0

5

De

c-0

5

Ma

r-0

6

Jun

-06

Au

g-0

6

No

v-0

6

Fe

b-0

7

Ma

y-0

7

Au

g-0

7

No

v-0

7

Fe

b-0

8

Ma

y-0

8

Au

g-0

8

No

v-0

8

Fe

b-0

9

$/M

Wh

rWith Balanced Billing

Without BalancedBilling

Projection

Through Dec 2007

Trouble!

Page 13: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

13

http://www.bnl.gov/cad/esfd

AGS-Booster-Tandem/Linac Startup

RHIC Cryo Cooldown/Warm-up

RHIC Cryo Operation

RHIC Cryo off

RHIC Research with s = 200 GeV/n d-Au

RHIC Research with s = 200 GeV pp

RHIC Au-Au development at s = 9 GeV

NSRL (NASA Radiobiology)

Shutdown (RHIC)

C-A Operations-FY08

Program Element Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

FY 2008

29 Jan 08

setup with beams in both rings

Planned, subject to change

19.3 weeks

Sep

concurrent with RHIC

ramp up luminosity

9 weeks

4

Page 14: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

14

RHIC Machine/Detector Planning Meeting

Next Meeting

5 Feb 08

Planning Meeting Web Site: http://www.c-ad.bnl.gov/esfd/RMEM_08/rhic_planning.htm

Page 15: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

15

Through Nov 2007

FY 2006-7 Power Bill

$-

$20

$40

$60

$80

$100

$120

$140

Jun

-05

Se

p-0

5

De

c-0

5

Ma

r-0

6

Jun

-06

Au

g-0

6

No

v-0

6

Fe

b-0

7

Ma

y-0

7

Au

g-0

7

No

v-0

7

Fe

b-0

8

Ma

y-0

8

Au

g-0

8

No

v-0

8

Fe

b-0

9

$/M

Wh

rWith Balanced Billing

Without BalancedBilling

Projection

Page 16: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

16

Experiments luminosity goals for Run 8, 100 x 100 GeV pp

– PHENIX• Delivered luminosity = 140 nb-1

• Recorded luminosity = 35 nb-1

– Longitudal Polarization goal: 26 nb-1

– Transverse polarization luminosity goal: 9 nb-1

• Assumed efficiencies: 48% vertex, 64% up, 82% live 25% overall• Assumed polarization: 65%• Approximate physics weeks: 12

– STAR• Delivered luminosity = 90 nb-1

– Longitudal polarization goal: 60 nb-1

– Transverse polarization luminosity goal: 30 nb-1

• Slow detector sampled luminosity (Transverse and Longitudal) = 30 nb-1

• Assumed efficiencies: 50% uptime, 65% live 33% overall• Assumed polarization: 65%• Approximate physics weeks: 12

• pp2pp: 3 days of dedicated running • Goals: 20M elastics, 300K double pomeron exchange events

An issue: In 2006 it took 6 weeks of physics running to get from ~45% polarization to ~60% polarization, above goals assume 65% from physics day 1

(Last update 23 Oct 07)

Page 17: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

17

(last update 10/23/07)

Experiments luminosity goals for Run 8 100 x 100 GeV/n d-Au

– PHENIX• Delivered luminosity = 230 nb-1

• Recorded luminosity = 58 nb-1

• Assumed efficiencies: 48% vertex, 53% live 25% overall• Approximate weeks: 10

– STAR• Delivered luminosity = 120 nb-1

• Fast Detector sampled luminosity = 60 nb-1

• Slow Detector sampled luminosity = 30 nb-1

• Fast detector overall sampling efficiency = 50%• Approximate weeks: 10

– Monopole Proposal – Detector Tests• Once ~ 20:1 signal to background is achieved in building 902, move to 10:00 IR,

reestablish good signal to background and then request collisions

Page 18: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

18

Phenix Goal

Phenix GoalPHENIX Goal

STAR Goal

STAR and PHENIX Plan

Page 19: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

19

PHENIX Goal

STAR Goal

STAR and PHENIX Plan

Page 20: 1 RHIC Machine/Detector Planning Meeting 29 Jan 08 Agenda –Run 8 end game issues, if any Planning Meeting Web Site: .

20

Fischer et.al. Possible 30 week run schedule


Recommended