Date post: | 15-Dec-2015 |
Category: |
Documents |
Upload: | armani-clemence |
View: | 214 times |
Download: | 0 times |
1
The information contained in this Presentation is confidential information as per your terms and conditions with British Telecommunications plc (BT).
Please treat it accordingly and do not forward, republish or permit unauthorized access.
BT reserves the right to make changes to the information in this Presentation at any time without further notice.
BTW Planned Engineering Works 90 day overviewMay to July 2012
2
BTW 2012 Network Changes – 3 month rolling plan
• Whilst BTW has continually worked to enhance its network, we are currently undergoing an exceptional level of change driven by four main drivers:-
– Stability – to improve the reliability of the network, BTW is targeting certain network elements with hardware and software improvements.
– Capacity – the need for additional capacity is driven by an increase in the number of broadband users on the 21C network (through migration from 20C and growth) and also by the ever-increasing bandwidth demands of those users.
– Resilience –to improve the resilience of the network , BTW is actively removing single points of failure from the network
– New Functionality – to meet the needs of the market BTW needs to enhance its network to deliver the services its customers require.
• This presentation outlines the key upgrade programmes, their drivers, customer impact and the number of upgrades per programme per week.
• BTW is keen to deliver all the required improvements as quickly as possible whilst actively managing the risk to customers. For this reason a range of run-rates against each programme has been outlined. The actual run-rates achieved will be determined by this ongoing live analysis of risk.
• Customer outage times for the PEWs start between 00:01 and 02:00 with the aim of completing customer impacting work by 04:00. This allows 2 hours for roll-back should the PEW be unsuccessful.
• Business as usual capacity upgrades and upgrades to resilient structures have not been listed here.
3
BTID Network Change – Major Project Summaries
Network change
Status Programme Number
Summary
MSPE software upgrade.
Status – 3 Core
upgrades remain to be completed
Code upgrade (3.9.1 + SMU patches) is required on the Cisco MSPE to improve platform stability.
• Two upgrades complete since last report – Edinburgh and Preston.• Completion is targeted for 13th June.
11
Network change
Status Programme Number
Summary
HT BEA-VS Introduction
Status – Deployment
ongoingIntroduce High throughput BEA-VS into the 21c platform
• 3rd migration at Glasgow completed on 17th May.• Next site will be Colindale on 7th June.• Pre-Olympic scope of this project is 5 sites to be completed by 5 th July.
22
4
BTID Network Change – Major Project Summaries
20
Network change
Status Programme Number
Summary
2nd Vendor MSPE
Status – Deployment
Ongoing
Introduce 2nd vendor MSPE for WCC and WBMC shared resilience.
• Upgrade of 17th site for WCC resilience complete on 30 th May. 6 more remain to be completed for WCC• Upgrade of 12th device complete for WBMC resilience on 30th May. 1 remain to complete for WBMC shared.
23
5
BTID Network Change – Major Project Summaries
Network change
Status Programme Number
Summary
21c BRAS Software Upgrade
Status – Deployment
Ongoing (37% complete)
Upgrade software on 21c BRAS to fix known defects.
• Defects in the software which will require resolution. • BAU deployment is now proceeding, 74 now upgraded.• Upgrade plan is agreed, current plan for software is to complete by 6 th July.
26
Network change
Status Programme Number
Summary
2nd vendor MSAN Software
Upgrade
Status – Deployment
Pending
Upgrade software on 2nd vendor MSAN to fix known defects.
• Resolves software defects.• 183 out of 688 upgrades complete.• Deployment completion due19th June.
30
6
20C Upgrades
Prog No:
Upgrade Key Drivers
Upgrades Complete / Total
EUs per upgrade
Upgrades per PEW
Affected Products
Av. End user outage (Mins)
Upgrades per week
Progress Planned End
May
June
July
Aug
Edinburgh LPA
Capacity 2/2 Non customer impacting
1 None 0 1 May 12
29 Edinburgh LPA– To meet ongoing 20c usage growth bigger LPA is required.
7
21C Upgrades
SVLAN moves - these moves offload SVLAN’s (bundles of Broadband traffic) from one BRAS to another. This is carried out to alleviate capacity issues mplet
Access MCLAG – removes single point of failure between MSAN (mostly Fibre MSAN which could aggregate several Copper MSAN’s) and Metro Node to improve overall availability
MPLS Core Router Upgrades required as existing software is soon to become “End of Life”. Phase 1 commenced no customer impact. Phase 2 due to commence Dec 11.
MSE Upgrades- Provide BB edge functionality on 7750 switches and additional BB capacity. Achieved by upgrading existing Ethernet Edge devices
Prog No:
Upgrade Key Drivers Upgrades Complete / Total
EUs per upgrade
Upgrades per PEW
Affected Products
Av. End user outage (Mins)
Upgrades per week
Progress Planne
d EndM
ayJune
July
Aug
SVLAN moves Capacity,Stability
Ongoing Av 800Min 0
Max 1000
1 – 5 WBC 35 Up to 75 Ongoing
Access MCLAG
Resilience 460/520 Av 2500Min 0
Max 8000
1 WBC 1 8 - 12 Dec 12
MPLS Core Router Upgrades
Code Update
Phase 183/83 (No Customer impact) Phase 2 23/26
Av 20000Min 0
Max 100000
1 WBMC Phase 1 – No Outage
Phase 2-180
(240 Max)
1-4Jun 12
MSE Upgrades
Capacity 2/70 Various 1 WBCMEAS
ETHERNET
5-8 minutes TBA (will not
start until
2012)
Sept 12
6
9
11
20
8
21C Upgrades
Additional BEA capacity is required and this is being achieved by introducing a bigger switch.
To increase platform resilience a 2nd vendor MSPE is being introduced.
21c BRAS software upgrade to increase stability of the platform
Software upgrade which supports new line cards for capacity and stability benefits and also delivers energy efficiency savings.
Progr
No:
Upgrade Key Drivers
Upgrades Complete / Total
BB EUs and/or Ethernet Circuits per upgrade
Upgrades per PEW
Affected Products
Av. End user outage (Mins)
Upgrades per week Progress
Planned End
May
June
July
Aug
EEA – EES Backhaul Uplift
Capacity 285/1060 Non Customer impacting
40 None 0 5 Jan13
High ThroughputBEA-VS
Capacity 3/5 Av 120K 1 WBC / WCC
45 mins 1 June 12
2nd Vendor MSPE
Stability 29/51 Av 20k 1 WBC / WCC /
Ethernet
30 secs – 10 mins
2 June 12
BRAS software Upgrade
Stability 74/200 Av 17000Max
32000
1 WBC / WBMC/
WCC
45 mins Up to 50 July 12
Copper MSANSoftware Upgrade
Stability / Capacity
5642/5844 Average 700
120 WBC /WBMC
30 mins 480 May 12
2nd vendor MSAN Upgrade
Stability 183/688 Average 700
40-50 WBC / WBMC/WCC
40 mins 200 - 250 June 12
24
22
23
26
27
EEA – EES 7750 Lag Migration - This change provides increased scalability .
30
9
Completed 20C Upgrades
1
14
2
10
Completed 21C Upgrades
3
5
8
10
12
11
Completed 21C Upgrades
7
13
19
18
21
12
Completed 21C Upgrades
Progr No:
Upgrade Key Drivers
Upgrades Complete / Total
BB EUs and/or Ethernet Circuits per upgrade
Upgrades per PEW
Affected Products
Av. End user outage (Mins)
Upgrades per wee
Date Ende
d
Copper MSAN Upgrade
Functionality
5594/5594 Non-Customer Impacting
Up to 120 None 0 Up to 480 Dec 11
EAD Chassis Code Upgrade
Stability 6950/6950 Up to 15 Ethernet Circuits
Up to 200 Ethernet,Mobile
Ethernet
<1 Up to 1000
Feb 12
21C BRAS Core Migration
Capacity 151/151 Non Customer Impacting
Up to 12 WBC 0 16-30 Feb 12
BEA VS Card Upgrade
Capacity 20/20 – Complete
Non-Customer Impacting
1 None 0 Up to 4 Mar 12
DDR Hardware replacement
Stability 200/200 Non Customer impacting
10 None 0 50 May 12
15
16
3
17
28
13
Broadband Services on 21CN
29
279
24
20
628 26
22
23 11
30
14
Ethernet Service on 21CN
15
Descriptions
16
Management of risk