Date post: | 18-Jan-2016 |
Category: |
Documents |
Upload: | amice-carter |
View: | 220 times |
Download: | 0 times |
VISAFiducialization and AlignmentR. Ruland, B. Fuss, Z. Wolf, D. Arnett, G. Bowden, R. Carr,B. Dix and C. Le Cocq, SLAC
G. Rakowsky, J. Aspenleiter, J. SkaritkaBNLPresented by Brian Fuss
TasksFiducializationRelate fiducials to magnetic centerlineAlignmentPosition undulator magnets with respect to each other Reference Laser BeamSetup RLB with respect to undulator position
Alignment Error Budget
[m]
Magnetic Centerline Determination
20
Transfer onto Fiducials
23
Positioning
28
Setup RLB with respect to Undulators
29
Total (added in quadrature)
51
First TaskFiducializationRelate fiducials to magnetic centerline
Fiducialization Procedural StepsPosition wire to represent magnetic centerlineDetect wire with Wire Finders and reference wire position to mechanical fiducials (metric measurement)Measure WF and undulator fiducials with respect to straight line using SI (relative measurements)Calculate undulator fiducial offsets using a similarity transformationRepeat above steps with undulators rolled in 90 incrementsCheck closure
Fiducialization: Step 2Wire Finder DesignA PSD detects light from a laser diode which is aperture limited by a slit. Slit width is a fraction of wire diameter. Detector assembly scans across wire. PSD response clearly indicates wire edges.
Fiducialization: Step 2 Wire Finder MeasurementsMeasuring wire positionDetector assembly is driven across wire profile. Micrometer readings are recorded at two defined detector voltage output levels on either side of the wire. The mean of the micrometer readings yields the wire center position.
Chart2
2560
2560
2560
2560
2540
2540
2540
2540
2560
2560
2560
2540
2540
2620
2690
2690
2600
2460
2400
2450
2560
2740
2920
3060
3160
3160
3020
2740
2320
1860
1360
1000
760
660
655
680
740
770
750
715
660
660
730
910
1300
1800
2260
2700
3000
3140
3140
3080
2940
2780
2640
2480
2420
2440
2580
2680
2700
2660
2580
2560
2570
2590
2590
2580
2580
2580
2580
2590
2580
2580
2580
Horizontal Position [m]
Diode Current [mVolt]
Wire Finder Calibration Curve
Sheet1
0462.5462.525302560462.5-462.52560
12.5450450.025302560450.0-450.02560
25437.5437.525302560437.5-437.52560
37.5425425.025302560425.0-425.02560
50412.5412.525202540412.5-412.52540
62.5400400.025202540400.0-400.02540
75387.5387.525202540387.5-387.52540
87.5375375.025202540375.0-375.02540
100362.5362.525302560362.5-362.52560
112.5350350.025302560350.0-350.02560
125337.5337.525302560337.5-337.52560
137.5325325.025202540325.0-325.02540
150312.5312.525202540312.5-312.52540
162.5300300.025602620300.0-300.02620
175287.5287.526002700287.5-287.52690
187.5275275.025502600275.0-275.02690
200262.5262.524902480262.5-262.52600
212.5250250.024502400250.0-250.02460
225237.5237.524802460237.5-237.52400
237.5225225.025302560225.0-225.02450
250212.5212.526202740212.5-212.52560
262.5200200.027102920200.0-200.02740
275187.5187.527152930187.5-187.52920
287.5175175.027803060175.0-175.03060
300162.5162.528303160162.5-162.53160
312.5150150.028303160150.0-150.03160
325137.5137.527603020137.5-137.53020
337.5125125.026202740125.0-125.02740
350112.5112.524102320112.5-112.52320
362.5100100.021801860100.0-100.01860
37587.587.51930136087.5-87.51360
387.57575.01750100075.0-75.01000
40062.562.5163076062.5-62.5760
412.55050.0158066050.0-50.0660
42537.537.5157064037.5-37.5655
437.52525.0159068025.0-25.0680
45012.512.5161072012.5-12.5740
462.500.016407800.00.0770
475-12.5-12.51620740-12.512.5750
487.5-25-251610720-2525.0715
500-37.5-37.51580660-37.537.5660
512.5-50-501585670-5050.0660
525-62.5-62.51605710-62.562.5730
537.5-75-751705910-7575.0910
550-87.5-87.519001300-87.587.51300
562.5-100-10021501800-100100.01800
575-112.5-112.523802260-112.5112.52260
587.5-125-12526002700-125125.02700
600-137.5-137.527503000-137.5137.53000
612.5-150-15028203140-150150.03140
625-162.5-162.528203140-162.5162.53140
637.5-175-17527903080-175175.03080
650-187.5-187.527202940-187.5187.52940
662.5-200-20026402780-200200.02780
675-212.5-212.525802660-212.5212.52640
687.5-225-22524902480-225225.02480
700-237.5-237.524602420-237.5237.52420
712.5-250-25024702440-250250.02440
725-262.5-262.525402580-262.5262.52580
737.5-275-27525902680-275275.02680
750-287.5-287.526002700-287.5287.52700
762.5-300-30025802660-300300.02660
775-312.5-312.525402580-312.5312.52580
787.5-325-32525302560-325325.02560
800-337.5-337.525352570-337.5337.52570
812.5-350-35025452590-350350.02590
825-362.5-362.525452590-362.5362.52590
837.5-375-37525402580-375375.02580
850-387.5-387.525402580-387.5387.52580
862.5-400-40025402580-400400.02580
875-412.5-412.525402580-412.5412.52580
887.5-425-42525452590-425425.02590
900-437.5-437.525402580-437.5437.52580
912.5-450-45025402580-450450.02580
-462.525402580-462.5462.52580
Sheet2
Sheet3
Fiducialization: Step 2Wire Finder Implementation
Fiducialization: Step 2Wire Finder CalibrationObjective:Calibration relates wire position measurements to reference fiducialPrinciple:Distance between fiducials known. Wire position is determined two times but with WF yawed 180 after 1st measurement
Fiducialization: Step 2Wire Finder CalibrationFrom these two wire measurements we obtain AI and AII; these are all the parameters needed to calculate calibration offset
Fiducialization: Step 2Wire Finder CalibrationCalibration Example
1st Cal 4_15
Laser Wire Finder Calibration Procedure
Golden Fixture
Operator:Time:Date:
Goal:Determine calibration offset (center of slit relative to reference
tooling ball when micrometer reads zero).
Procedure:
1)Enter L, the distance between the centers of the tooling balls A
and B, as determined on the CMM.
101.135250.5676
2)Set units: push toggle button until read-out shows millimeter.
3)Set Wire finder on calibration mount with reference tooling ball in cup.
4)Reset micrometer: drive cross slide against reference stop, press reset.
5)Find the wire position relative to the micrometer by finding the wire edges
at the 200mV and 400 mV signal level.
6.3376.512
6.3366.512
6.3366.513
6.33636.5123
6.4243
6.3646.489
6.3346.49
6.3646.489
6.35406.4893
6.4217
6.4230
6)Rotate the Wire Finder by 180 around its vertical axis
7)Find the wire position relative to the micrometer again
8.2468.07
8.2458.071
8.2468.071
8.24578.0707
8.1582
8.2238.097
8.2238.097
8.2238.098
8.22308.0973
8.1602
8.1592
8)
43.2765
&L&F &A&R&D &T
2nd Cal 4_15
Laser Wire Finder Calibration Procedure
Golden Fixture
Operator:Time:Date:
Goal:Determine calibration offset (center of slit relative to reference
tooling ball when micrometer reads zero).
Procedure:
1)Enter L, the distance between the centers of the tooling balls A
and B, as determined on the CMM.
101.135250.5676
2)Set units: push toggle button until read-out shows millimeter.
3)Set Wire finder on calibration mount with reference tooling ball in cup.
4)Reset micrometer: drive cross slide against reference stop, press reset.
5)Find the wire position relative to the micrometer by finding the wire edges
at the 200mV and 400 mV signal level.
6.3376.513
6.3376.513
6.3376.513
6.33706.5130
6.4250
6.3646.49
6.3656.49
6.3656.489
6.36476.4897
6.4272
6.4261
6)Rotate the Wire Finder by 180 around its vertical axis
7)Find the wire position relative to the micrometer again
8.0868.261
8.0868.26
8.0858.26
8.08578.2603
8.1730
8.1128.236
8.1128.237
8.1128.236
8.11208.2363
8.1742
8.1736
8)
43.2678
&L&F &A&R&D &T
3rd Cal 4_15
Laser Wire Finder Calibration Procedure
Golden Fixture
Operator:Time:Date:
Goal:Determine calibration offset (center of slit relative to reference
tooling ball when micrometer reads zero).
Procedure:
1)Enter L, the distance between the centers of the tooling balls A
and B, as determined on the CMM.
101.135250.5676
2)Set units: push toggle button until read-out shows millimeter.
3)Set Wire finder on calibration mount with reference tooling ball in cup.
4)Reset micrometer: drive cross slide against reference stop, press reset.
5)Find the wire position relative to the micrometer by finding the wire edges
at the 200mV and 400 mV signal level.
6.336.507
6.336.507
6.3316.507
6.33036.5070
6.4187
6.3576.482
6.3576.482
6.3586.482
6.35736.4820
6.4197
6.4192
6)Rotate the Wire Finder by 180 around its vertical axis
7)Find the wire position relative to the micrometer again
8.0868.26
8.0868.26
8.0868.26
8.08608.2600
8.1730
8.1128.236
8.1128.236
8.1128.236
8.11208.2360
8.1740
8.1735
8)
43.2713
&L&F &A&R&D &T
4th Cal 4_15
Laser Wire Finder Calibration Procedure
Golden Fixture
Operator:Time:Date:
Goal:Determine calibration offset (center of reference
tooling ball to micrometer zero).
Procedure:
1)Enter L, the distance between the centers of the tooling balls A
and B, as determined on the CMM.
101.135250.5676
2)Set units: push toggle button until read-out shows millimeter.
3)Set Wire finder on calibration mount with reference tooling ball in cup.
4)Reset micrometer: drive cross slide against reference stop, press reset.
5)Find the wire position relative to the micrometer by finding the wire edges
at the 200mV and 400 mV signal level.
6.3286.505
6.3286.504
6.3286.505
6.32806.5047
6.4163
6.3556.479
6.3556.48
6.3556.479
6.35506.4793
6.4172
6.4168
6)Rotate the Wire Finder by 180 around its vertical axis
7)Find the wire position relative to the micrometer again
8.0878.261
8.0868.261
8.0868.261
8.08638.2610
8.1737
8.1118.236
8.1128.236
8.1118.236
8.11138.2360
8.1737
8.1737
8)
43.2724
&L&F &A&R&D &T
&L&F &A&R&D &T
5th Cal 4_16
Laser Wire Finder Calibration Procedure
Golden Fixture
Operator:Time:Date:
Goal:Determine calibration offset (center of slit relative to reference
tooling ball when micrometer reads zero).
Procedure:
1)Enter L, the distance between the centers of the tooling balls A
and B, as determined on the CMM.
101.135250.5676
2)Set units: push toggle button until read-out shows millimeter.
3)Set Wire finder on calibration mount with reference tooling ball in cup.
4)Reset micrometer: drive cross slide against reference stop, press reset.
5)Find the wire position relative to the micrometer by finding the wire edges
at the 200mV and 400 mV signal level.
6.3256.502
6.3256.503
6.3256.502
6.32506.5023
6.4137
6.3516.477
6.3516.47
6.3516.477
6.35106.4747
6.4128
6.4133
6)Rotate the Wire Finder by 180 around its vertical axis
7)Find the wire position relative to the micrometer again
8.0848.258
8.0838.258
8.0848.258
8.08378.2580
8.1708
8.118.235
8.118.234
8.118.234
8.11008.2343
8.1722
8.1715
8)
43.2752
&L&F &A&R&D &T
Fiducialization: Step 2Wire Finder RepeatabilityBoth Wire Finders were calibrated four times each in the morning before a fiducialization run and after the run in late afternoon.
Sheet1
Laser Finder Calibration Comparison
Golden FixtureBlack Fixture
beforeDafterDbeforeDafterD
43.2745-0.00343.27420.00043.40170.00043.40380.0000.000150.0000000225
43.26980.00243.2752-0.00143.4035-0.00243.4057-0.002-0.001650.0000027225
43.27130.00143.27290.00243.40060.00143.40250.0010.001250.0000015625
43.2724-0.00043.2758-0.00143.40160.00043.40380.0000.000250.0000000625
0.000150.0000000225
43.27243.27543.40243.404-0.001750.0000030625
-0.003-0.0020.001450.0000021025
0.000150.0000000225
StD.1.5mStD.1.2m0.00000958
0.0011698596
&L&F.xls&R&D &T
Sheet2
Sheet3
Fiducialization: Step 3 Measure fiducials w/r to straight line Requested straightness tolerance excludes standard surveying methodsStraightness interferometry method of choiceStraightness Interferometer cannot measure directly w/r to fiducialsInterface between fiducials and Wollaston prism provided by constant length rod
Fiducialization: Step 3 ArcingRod needs to be placed perpendicular to SI reference lineNot a new problem, typical to optical tooling measurementsSolution: arcing (best-fit circle)
Fiducialization: Step 3 Arcing
Fiducialization: Step 4 Calculate fiducial offsetsAll information now available to calculate the undulator fiducial offsets
Fiducialization: Step 4 Repeatability, DataSteps one through four were repeated four times; to guarantee independent measurements, the undulators and the SI reference line were moved after each iteration
Sheet1
Wire (Magnetic Axis)Interferometer Readings1.5
xyuv4.6
050.53300.2981.5
222350.50322230.92931.1
169.000008288750.53572573071690.351
1134.000081845450.639456674211340.74182.3
1162.000049341250.526027214511620.6367
2129.00009157450.524163200821290.9225
Wire (Magnetic Axis)Interferometer Readings
xyuv
050.5320-0.3343
222350.50122230.2683
169.000008327150.5371315786169-0.281
1134.000064925850.649818704111340.0551
1162.000046003250.52780647671162-0.0073
2129.000084022850.523391900921290.2639
Measurement 1Measurement 2Measurement 3Measurement 4Average
M1_TB450.53650.53750.53550.53850.537
Wire (Magnetic Axis)Interferometer ReadingsM1_TB850.63950.65050.64150.64450.644
xyuvM2_TB450.52650.52850.52450.52650.526
050.53401.9019M2_TB850.52450.52350.52250.52450.523
222350.50422232.5144
169.000007363650.53505497051691.9518DDDD
1134.00007841950.641446957911342.3371M1_TB40.84-0.561.51-1.796.5347
1162.000045688150.524154295211622.2279M1_TB84.29-6.262.30-0.3362.9001
2129.000085416450.521868239321292.5051M2_TB4-0.09-1.871.790.166.7066
M2_TB8-0.710.061.59-0.943.9127
Wire (Magnetic Axis)Interferometer Readings2.3102
xyuv
050.5320-0.0784
222350.50122230.5409
169.000009092250.5383619878169-0.0226
1134.000081304850.644068010111340.3654
1162.000047898950.52577710211620.2553
2129.000088871150.524398063621290.5368
Sheet2
WireInterferometer
(Magnetic Axis)Readings
zyuv
WF_G050.53300.298
WF_B222350.50322230.9293
M1_TB41690.351
M1_TB811340.7418
M2_TB411620.6367
M2_TB821290.9225
WF_G050.5320-0.3343
WF_B222350.50122230.2683
M1_TB4169-0.281
M1_TB811340.0551
M2_TB41162-0.0073
M2_TB821290.2639
WF_G050.53401.9019
WF_B222350.50422232.5144
M1_TB41691.9518
M1_TB811342.3371
M2_TB411622.2279
M2_TB821292.5051
WF_G050.5320-0.0784
WF_B222350.50122230.5409
M1_TB4169-0.0226
M1_TB811340.3654
M2_TB411620.2553
M2_TB821290.5368
Sheet3
Fiducialization: Step 4 Repeatability, ResultsAll but two of the 16 individual measurements agree to within 2 m compared to the respective mean. Standard deviation of all measurements is 2.3 m.
Sheet1
Wire (Magnetic Axis)Interferometer Readings1.5
xyuv4.6
050.53300.2981.5
222350.50322230.92931.1
169.000008288750.53572573071690.351
1134.000081845450.639456674211340.74182.3
1162.000049341250.526027214511620.6367
2129.00009157450.524163200821290.9225
Wire (Magnetic Axis)Interferometer Readings
xyuv
050.5320-0.3343
222350.50122230.2683
169.000008327150.5371315786169-0.281
1134.000064925850.649818704111340.0551
1162.000046003250.52780647671162-0.0073
2129.000084022850.523391900921290.2639
Measurement 1Measurement 2Measurement 3Measurement 4Average
M1_TB450.53650.53750.53550.53850.537
Wire (Magnetic Axis)Interferometer ReadingsM1_TB850.63950.65050.64150.64450.644
xyuvM2_TB450.52650.52850.52450.52650.526
050.53401.9019M2_TB850.52450.52350.52250.52450.523
222350.50422232.5144
169.000007363650.53505497051691.9518DDDD
1134.00007841950.641446957911342.3371M1_TB40.84-0.561.51-1.796.5347
1162.000045688150.524154295211622.2279M1_TB84.29-6.262.30-0.3362.9001
2129.000085416450.521868239321292.5051M2_TB4-0.09-1.871.790.166.7066
M2_TB8-0.710.061.59-0.943.9127
Wire (Magnetic Axis)Interferometer Readings2.3102
xyuv
050.5320-0.0784
222350.50122230.5409
169.000009092250.5383619878169-0.0226
1134.000081304850.644068010111340.3654
1162.000047898950.52577710211620.2553
2129.000088871150.524398063621290.5368
Sheet2
WireInterferometer
(Magnetic Axis)Readings
zyuv
WF_G050.53300.298
WF_B222350.50322230.9293
M1_TB41690.351
M1_TB811340.7418
M2_TB411620.6367
M2_TB821290.9225
WF_G050.5320-0.3343
WF_B222350.50122230.2683
M1_TB4169-0.281
M1_TB811340.0551
M2_TB41162-0.0073
M2_TB821290.2639
WF_G050.53401.9019
WF_B222350.50422232.5144
M1_TB41691.9518
M1_TB811342.3371
M2_TB411622.2279
M2_TB821292.5051
WF_G050.5320-0.0784
WF_B222350.50122230.5409
M1_TB4169-0.0226
M1_TB811340.3654
M2_TB411620.2553
M2_TB821290.5368
Sheet3
Fiducialization: Step 5 Repeat in other roll orientationTo avoid first order errors, all measurements are recorded in the principal planes, i.e. TB on the side is used for horizontal measurements, TB on the top for vertical measurements onlyHence, all fiducialization measurements are one-dimensional plus distance along beamTo determine second dimension, undulator is rolled by 90, and above measurements are repeated
Fiducialization: Step 6 Closure CheckTo check for systematic errors, the undulators are also measured in their 180 and 270 positionsAdding the fiducial offsets of opposing TBs should equal the spatial distance between the two TBs as previously measured on high accuracy CMM
Fiducialization: Step 6 Closure DataUndulator one and two as a pair were used to commission the fiducialization set-up. Several closure measurements are available
Sheet1
[mm][mm]
Magnet 01
TB01_TB04101.129846101.12525
TB05_TB08101.157786101.1780-20
Magnet 02
TB01_TB04101.152198101.1570-5
TB05_TB08101.208586101.2279-19
Magnet 01
TB01_TB04101.1298101.1488-19
TB05_TB08101.1743101.163011
Magnet 02
TB01_TB04101.1522101.132819
TB05_TB08101.1593101.2079-49
M01_TB01101.129846
101.1298460
M01_TB04101.1252
101.1488-24
M01_TB05101.2086
101.159349
M01_TB08101.1780
101.163015
M02_TB01101.1522
101.15220
M02_TB04101.1570
101.14888
M02_TB05101.2086
101.159349
M02_TB08101.2279
101.207920
Sheet2
Sheet3
Fiducialization: Step 6 Closure DataAnother check is provided by comparing fiducial offsets from different iterations
Sheet1
[mm][mm]
Magnet 01
TB01_TB04101.1298101.12525
TB05_TB08101.1578101.1780-20
Magnet 02
TB01_TB04101.1522101.1570-5
TB05_TB08101.2086101.2279-19
Magnet 01
TB01_TB04101.1298101.1488-19
TB05_TB08101.1743101.163011
Magnet 02
TB01_TB04101.1522101.132819
TB05_TB08101.1593101.2079-49
UD
[mm]
M01_TB01101.1298
101.12980
M01_TB04101.1252
101.1488-24
M01_TB05101.1578
101.1743-17
M01_TB08101.1780
101.163015
M02_TB01101.1522
101.15220
M02_TB04101.1570
101.14888
M02_TB05101.2086
101.159349
M02_TB08101.2279
101.207920
Sheet2
Sheet3
Second TaskAlignmentPosition undulator magnets with respect to each other inside the vacuum chamber
AlignmentPhilosophyAlignment step uses analogous approach to fiducialization measurements: straightness interferometry. To permit simultaneous measurement of both dimensions, two straightness interferometers are used
AlignmentProcedural StepsConventional alignment techniques are used to support installation and to achieve global alignment in the beam line coordinate systemDual interferometer system is used to map the undulators positionsFit a straight line & apply similarity transformation to data such that necessary position corrections are minimized and magnetic centers are at nominal positions (i.e., follow a RLB)Apply position corrections under control of interferometersIterate if necessaryQuality Control, re-map undulators; include Laser Finder in both upstream and downstream positions
Alignment: Step 1Conventional AlignmentRoutine work, should yield 100 to 150 mm type position accuracy relative to beam line coordinate system
Alignment: Step 2Dual Interferometer SystemTest measurements showed that it would be desirable to adjust the position of the undulators under simultaneous horizontal and vertical control: hence dual systemSpecial jig was designed to facilitate the set-up of both straightness interferometersJig should be bucked-in w/r to beam line to about 0.5 mm (conventional alignment)
Alignment: Step 2Dual Interferometer System
Alignment: Step 2Dual Interferometer System
Alignment: Step 2Dual Interferometer System
Alignment: Steps 2 - 5Mapping Undulator FiducialsFiducials are mapped analogously to the technique described before for the fiducialization measurements. A full map of horizontal and vertical measurements takes about one hourOn-line data flow and custom programming allows automatic measuring and data analysisStraight line fit optimized to minimize position correctionsYields position corrections for undulators which are expressed in fractions of rotations of the adjustment screwsRe-map, check, iterate if necessary
Alignment: Step 6Quality ControlProduce final map including the fiducial positions of the Laser Finder in its upstream and downstream position
See Poster:Very High Precision Alignment of Undulator Magnets in a Vacuum Chamber
for details on these alignment steps
Third TaskReference Laser BeamSetup RLB with respect to undulator position
Reference Laser BeamPurposeAn optical diagnostics system is integrated into the system design which will aid in steering the electron beam to coincide with the photon beamA laser beam is used to reference the diagnostic system to the undulator axisTherefore the laser beam needs to be pointed such that it coincides with the axis of the undulator assemblyInitially a green laser is used which will be replaced with an infra-red (invisible) laser for final operations A Laser Finder has been designed to relate the optical beam to mechanical fiducials
Reference Laser BeamLaser Finder PrincipleThe LF consists of a frame which carries tooling balls in the same geometry and dimensions as they are mounted to the undulatorA quadrant detector is mounted on a two-dimensional cross-slide centered to the frameThe quadrant detector is used as nulling device. The laser intensity readings are detected on each of two halves of the QD and compared; this arrangement is then electronically rotated by 90 to measure the other dimension
Reference Laser BeamLaser Finder Implementation
Reference Laser BeamLaser Finder CalibrationThe detectors coordinate system needs to be related to the reference tooling ball by a calibration measurementCalibration is performed analogously to the Wire Finder
Reference Laser BeamLaser Finder Calibration
Sheet1
Laser Finder Calibration Procedure
Operator
DateTime
1)Put the detector in the standard configuration:
2)
3)Move the stages until the computer readout shows the beam
is at x = 0, y = 0. Record the micrometer readings.
2.3565mm
4.5763mm
4)Flip the detector over
5)Move the stages until the computer readout shows the beam
is at x = 0, y = 0. Record the micrometer readings.
3.5467mm
2.4365mm
6)Compute the calibration constants:
=47.1839mm
=3.5064mm
Sheet2
Sheet3
MBD00075179.unknown
MBD001B6808.unknown
Reference Laser BeamLaser Finder Buck-in ProcedureThe position of the LF in both its upstream and downstream kinematic mount is known from quality control mappingBased on these parameters, the nominal LF readings for both positions can be calculatedFirst, the beam is pointed such that the LF, preset to the nominal micrometer readings in the downstream position, detects the beam at the center of the QDSecond, the laser is translated, horizontally and vertically, in the upstream position such that the LF, preset to the nominal micrometer readings, detects the beam at the center of the QDThird, the last two steps are iterated until the corrections become insignificant
The End