Working meeting
Warsaw, 20-05-2010
9:00 – 13:00 – WORKING MEETING
Progress of the project: activities, budget changes – LP-Part
Project schedule & plan – LP-Part
1st analysis: progress, discussion – PP07-Powys
Communication plan – main assumptions, messages – PP03-Inorde
Agenda study visit in France – PP06-Auvergne
13:00 – 14:00 LUNCH offered by PART
14:00 – 15:30 – WORKING MEETING
Meeting of the working group (environmental and entrepreneurship WG)
2
PROGRESS OF THE B2N PROJECTPROGRESS OF THE B2N PROJECT
Working meeting
Warsaw, 20-05-2010
3
WHERE WE ARE NOW?
C1: 1st SC meeting organised
C1: Partnership agreement is being signed
C1: 1st Internal Report received from all partners
C1: Project Handbook prepared – LP-Part
C2: Launch Conference organised!
C2: Website launched
C2: Logo and visual identity prepared – PP3-Inorde
C2: First brochure designed – PP11-Pivka
C3: Templates for 1st analysis prepared and completed – PP7-Powys
4
WHAT ELSE SHOULD WE DO?
(1st semester 2010)
C1: Partnership agreement signed by all partners
C1: 1st Progress Report submitted
C1: “Monitoring and Evaluation Plan” – LP-Part
C1: 2nd SC meeting in Auvergne
C2: “Communication and dissemination Plan” – PP3-Inorde
C2: Brochure 1 to be printed: LP-Part, PP1-WM, PP11-Pivka
C2: Press releases (5 units: PP2-WM, PP3-Inorde, PP6-Auvergne, PP8-Paradis, PP11-Pivka) and advertisments (2 units: LP-Part, PP3-Inorde)
C3: 1st analysis prepared and results discussed
C3: Study visit to France (including workshop and 2nd SC meeting)
C3: “Common methodology” prepared – PP7-Powys + LP-Part
5
COMPONENT 1: MANAGEMENT AND COORDINATION
ISSUES TO DISCUSS
1st Internal Reporting (Jan-Feb 2010) – conclusions
How to continue with internal reporting?
Formal requirements: Approbation certificates
Preparation for 1st Progress Report
6
COMPONENT 1: MANAGEMENT AND COORDINATION
Internal reporting – summary Jan-Feb 2010 (1)
Eligible expenditure by budget line - summaryAll amounts in EUR. (All fields calculated automatically on the basis of data from sheets C1-C5)
1 196.464,45 0,00 43.586,95 43.586,95 22,2% 152.877,492 26.671,29 0,00 3.412,47 3.412,47 12,8% 23.258,823 84.486,00 0,00 11.839,36 11.839,36 14,0% 72.646,644 56.390,17 0,00 3.518,31 3.518,31 6,2% 52.871,855 Equipment 1.500,00 0,00 0,00 0,00 0,0% 1.500,00
TOTAL 365.511,91 0,00 62.357,09 62.357,09 17,06% 303.154,81
Travel and accommodationExternal expertise and services
Accumulated %Remaining
BudgetSpecificationPreviously reported
Current Report
Staff Administration
Budget line Total Partner's Budget
7
COMPONENT 1: MANAGEMENT AND COORDINATION
Internal reporting – summary Jan-Feb 2010 (2)
8
COMPONENT 1: MANAGEMENT AND COORDINATION
Stick to the original figures
9
SC meeting in WarsawLC Warsaw SV France
Travel and accomodation costs
10
Administration costs
NO!!
YES!!
11
Partners who asked for budget changes
Pivka
Ostergotland
Veliko Tarnovo
Gran Paradis
Powys
As few changes as possible
Flexibility rule on the level of the partner (each component or budget line can increase by a maximum of 10%) – except for external expertise
Changes accepted by the LP
For Jan-June period – last request for changes to be sent to the LP by the 15/06
12
How to continue with internal reporting? Prolong the internal reporting periods from 2 months to 3 months
Starting from 1st July 2010
…1st July – 30th September
…1st October – 31th December
Simplified (general table + checklist) or detailed internal progress report
Timesheets
Partner’s progress report to be submitted to the FLC
COMPONENT 1: MANAGEMENT AND COORDINATION
13
Reporting and Financial Control System
Project Partner
Lead Partner (LP)
Managing AuthorityJoint Technical Secretariat (JTS)
Certifying Authority
Project PartnerProject Partner
Payment to LP
Payment to
PPs
4. CA checks and initiates payment
3. Progress Reportschecked by Project Officer and FinanceOfficer in JTS
2. LP compiles the joint progress report,collection of the partner control confirmations and expenditurecontrolled by LP-controller
1. Expenditurecontrolled by PP-controller
COMPONENT 1: MANAGEMENT AND COORDINATION
14
Forecast of costs paid out during reporting periods:January - June July – December
Projects not reporting in time and in full risk losing funds
01.01.2010 – 30.06.2010
365.512 euros to be reported
COMPONENT 1: MANAGEMENT AND COORDINATION
15
1st Progress Report 1st Progress Report - Covering the the reporting period from 1 January 2010 to 30 June 2010
- Pre-filled Excel file sent JTS to Lead Partner (e-mail)
- Completed document sent back by LP at given deadline by e-mail and by post (only the printable summary)
Deadllines:
For the LP: on 1 October 2010 (at the latest) - submission of PR by LP to JTS
For the PPs: on the 15th of August (at the latest) - Submission of PP input to PR to LP (incl. PP controller’s confirmation)
COMPONENT 1: MANAGEMENT AND COORDINATION
16
Timing for ERDF reimbursementTiming for ERDF reimbursement
Submission of PR by LP
to JTS (confirmed
by LP controller)
30/06
End of reporting
period
01/1015/08
Submission of PP input to PR to LP (incl. PP
controller’s confirmation)
01/11
Feedback on PR by
JTS to LP, clarification
request
22/11
Approval of PR +
clarification by JTS
22/06
Payment by Certifying Authority
~ 4 weeks
~ 4 weeks
3 months
COMPONENT 1: MANAGEMENT AND COORDINATION
17
All expenditure reported by a project has to be certified by an
independent controller, before submission to the JTS
=
first level control (FLC) INORDE
PERUGIA
AUVERGNE
POWYS
GRAN PARADIS
ADRAT
VELIKO TARNOVO
PART
WARMIA-MAZURY
OSTERGOTLAND
PIVKA
COMPONENT 1: MANAGEMENT AND COORDINATION
18
Selection of a first level controller and obtainingan approbation certificate (decentralised system)
1. Select a first level controller, respecting public procurement rules.
2. Propose this first level controller to the central approbation body of the Member State. A
specific checklist for approving the FLC will be provided by the MS.
3. The MS checks the information and independence of the controller. If OK, the MS
issues an approbation certificate to the partner.
4. This approbation has to be finalised before the end of the first reporting period (30th
of June 2010) so that FLC can be carried out after end of reporting period.
5. PP provide approbation certificate to LP.
INORDE, PERUGIA, AUVERGNE, POWYS, GRAN PARADIS, ADRAT, VELIKO TARNOVO
COMPONENT 1: MANAGEMENT AND COORDINATION
19
The first level controller... (2/2)Control of
Accounting documents
Project documentation
100% check
confirms the expenditure and signs the
1) Partner Control Confirmation
2) Control Report (incl. control checklist)
COMPONENT 1: MANAGEMENT AND COORDINATION
20
1) Partner Control Confirmation - ANNEX 5b programme manual
Issued by your FLC!
Send to LP-PART!
COMPONENT 1: MANAGEMENT AND COORDINATION
21
2) Control Report (incl. control checklist) –ANNEX 6 programme manual
Issued by your FLC!
Send to LP-PART!
COMPONENT 1: MANAGEMENT AND COORDINATION
22
What documents should you prepare for your FLC?
list of expenditure invoices bank statements procurement documentation: procurement note, terms of reference,
offers/quotes, order form, contract documentation of calculations (if only a share was allocated to the
project) time sheets, employees’ contracts, pay slips proofs for delivery of services and goods (studies, brochures,
newsletters, minutes of meetings, translated letters, participants’ list etc), record of assets
COMPONENT 1: MANAGEMENT AND COORDINATION
23
ISSUES TO DISCUSS
Website – translations to local languages
Website – intranet
“Communication and dissemination Plan” - Inorde
Brochure 1 to be printed: LP-Part, PP1-WM, PP11-Pivka
Brochures – translation to local languages
Press releases (5 units: PP2-WM, PP3-Inorde, PP6-Auvergne, PP8-Paradis, PP11-Pivka) and advertisments (2 units: LP-Part, PP3-Inorde)
Copies of all press releases and advertisements to be sent to PART
COMPONENT 2: COMMUNICATION AND DISSEMINATION
24
WEBSITE – TRANSLATION TO LOCAL LANGUAGES
25
WEBSITE – TRANSLATION TO LOCAL LANGUAGES
26
WEBSITE - INTRANET
27
WEBSITE - INTRANET
28
BROCHURE
29
If you have any doubt, please send to the LP before printing the final
version of each document to be published! – to make sure that it
complies with all publicity requiremets. If not, you are risking that the
related costs will not considered as eligible
Send to LP 3 copies of each project publication (brochures,
press releases, advertisement) – to be sent to the JTS later on
Scanned version of all articles on B2N project in the press in Scanned version of all articles on B2N project in the press in
your country, any media apparitions – to be included on the your country, any media apparitions – to be included on the
websitewebsite
Information & Publicity guidelines
COMPONENT 2: COMMUNICATION AND DISSEMINATION
30