10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification). Participants Type and Number Include tasking and performing activity personnel responsible for the area or item being reviewed, key representatives for lower level items, and other personnel who have a stake in the specific objectives of the review. Objectives 1. Demonstrate progress 3. Verify the expected maturity 2. Ensure issues have been resolved 4. Confirm that risks are acceptable
Transcript
Page 1: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-1

GENERAL GUIDANCE ON CONDUCT OF

TECHNICAL REVIEWS

Selection should be based on the complexity of the program and the phase of development (modification).

Participants

Type and Number

Include tasking and performing activity personnel responsible for the area or item being reviewed, key representatives for lower level items, and other personnel who have a stake in the specific objectives of the review.

Objectives

1. Demonstrate progress 3. Verify the expected maturity2. Ensure issues have been resolved 4. Confirm that risks are acceptable

Page 2: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-2

• Confirm that issues addressed during previous reviews have been satisfactorily resolved.• Only areas requiring close scrutiny should be addressed in detail. Proper integration and management of interim, subsystem, and functional reviews (as planned in SEMP) should make a detailed total evaluation unnecessary.• Opportunity to modify program emphasis for the next phase based on risk levels.

In General

FOCUS IN MAJOR REVIEWS

Page 3: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-3

TYPES OF REVIEWS

Major: Demonstrate that risk levels are acceptable and provide an opportunity to modify program emphasis for next phase/effort. (Examples: ASR, SRR, SFR, PDR, CDR, SVR, PCA)

Functional: System wide review conducted by involved disciplines to address progress and issues associated with one functional area. (Examples: Development, Training, Support, Verification, Manufacturing, Disposal, etc.)

Subsystem: Multidisciplinary reviews to assess progress in defining and satisfying subsystem requirements.

Interim: Reviews held between major reviews that cover spectrum of system, segments, and configuration items.

Page 4: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-4

Integrated Technical Reviews (Cont.)

Major Technical Reviews include:

- Alternate System Review (ASR): The ASR forms the basis for determining which system concepts should be continued as candidate development programs. It provides the data for recommendations to eliminate potential systems concepts.- System Requirements Review (SRR): The SRR forms the basis early in System Development and Demonstration whether customer requirements are understood. It should confirm the progress and direction of technology verifications and demonstrations and convergence on viable system requirements

Page 5: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-5

Integrated Technical Reviews (Cont.)

Major Technical Reviews include:

- System Functional Review (SFR): The SFR (formally called the SDR) forms the basis to establish and verify an appropriate set of functional and performance requirements for the complete system.- Preliminary Design Review (PDR): The PDR forms the basis for determining whether a preliminary physical architecture and design approach for configuration item or aggregation of configurations (including software) is ready to start detailed design. A configuration item development spec must be complete and ready for use in detailed design

Page 6: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-6

Integrated Technical Reviews (Cont.)

Major Technical Reviews include:

- Critical Design Review (CDR): The CDR confirms the detailed design for each configuration item (including software), each aggregation of configuration items, and that requirements are satisfied.- System Verification Review (SVR): The SVR demonstrates the total system (people, products, and processes) satisfies functional and allocated configuration documentation requirements and confirms readiness for production, support, training, deployment, operations, an disposal. The Production Readiness Review (PRR) is a part of the SVR.

Page 7: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-7

Customary System Level Review Accomplishments

SRR - Review system functional and performance requirements.

SDR/SFR - Review allocation of system requirements to configuration item (CI) aggregates. Assess maturity

of system spec. and CI aggregates.

PDR - Review design progress for each CI and aggregate of CIs: 1. Review predicted performance 2. Review physical and functional interfaces 3. Verify integration of specialty eng. req. 4. Evaluate risk resolution

Page 8: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-8

Customary System Level Review Accomplishments (Cont.)

CDR - Review maturity of design for each CI and aggregate CIs:

1. Verify that functional and performance requirements of CI specs are satisfied.2. Verify that engineering specialty requirements have been satisfied.3. Verify compatibility between CIs and hardware, software, facilities and personnel.4. Review preliminary product specs.5. Assess producibility risks.

Page 9: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-9

Customary System Level Review Accomplishments (Cont.)

SVR - Confirms readiness to enter full rate production:

1. Verify work on all CIs – all functions & performance levels met.

2. FCA conducted for CIs.See page 107 of Sys. Eng. Fundamentals for

additional accomplishments.

Page 10: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-10

Systems Engineering Master Schedule (SEMS)

Purpose:

• Contractual Agreement Between Contractor and Customer on Critical Tasks Required for Completing Each Major Program Milestone and Defining the Criteria for Successful Completion of Those Tasks.

Page 11: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-11

Role of SEMS in Acquisition Planning

The SEMS Outlines the Integration of All Major Tasks Necessary to Design, Develop, Test, Produce, Deploy and Support the System.

Support Training

System

Prime Mission Equipment

Performance

Producibility

Reliability

Cost

Schedule

RiskManagement

Balanced Process/Productto Satisfy User Needs

Page 12: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-12

SEMS Key Tasks

• Typical Tasks• Develop Test Plans• Develop Software Plans

• Tasks Define Interim Steps to Developing and Producing System

• Tasks Should Include Verification Criteria

Page 13: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-13

SEMS Accomplishment Guidelines

• Typical Accomplishment for Sample Tasks– Test Plan Complete– Software Development Plans Complete

• Accomplishment Should Be Easily Measurable• Example of Difficult to Measure Accomplishment

– Test Plan 85% Complete

Page 14: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-14

SEMS Sample Accomplishment

Milestone 3 - Test Readiness Review (TRR)

Accomplishments

3.1 Complete Software Test Procedures3.2 Complete System Integration Test Procedures3.3 Complete All Major Subsystem TRRs3.4 Complete All Action Items from Milestone 2

Page 15: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-15

Page 16: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-16

Page 17: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-17

Section L - Instructions, Conditions, and Notices to Offerors

Systems Engineering Master Schedule(SEMS)

volume 3 attachment 1

Systems Engineering Master Schedule(SEMS)

volume 3 attachment 1

Page 18: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-18

Section L - Instructions, Conditions, and Notices to Offerors (Cont.)

3.0 SEMS PROGRAM EVENTS

Listed below are the Major Program Events and their scheduled time of achievement. Each event shall be considered achieved upon successful demonstration of criteria accomplishments. Criteria for each event is defined in Section 4.0.Event Number Event Title Event Date

1. System Hardware Preliminary 5 MACADesign Review(PDR)

2. System Software PDR 7 MACA

3. ILS Management Team (ILSMT) 9 MACAMeeting

4. System Hardware Critical Design 11 MACAReview (CDR)

5. System Software CDR 13 MACA6. System Test Readiness Review 22 MACA7. Ground Durability/Qualification 24 MACA

Test Release

Page 19: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-19

Section L - Instructions, Conditions, and Notices to Offerors (Cont.)

Event Number Event Title Event Date

8. (Reserved)9. RF-4C #1 Development Flight 29 MACA

Test Release10. RF-4C DT&E/IOT&E start 29 MACA11. UARS #1 Development Flight 29 MACA

Test Release12. UARS DT&E/IOT&E start 29 MACA

13. F/A-18 DT&E/IOT&E Start 29 MACA14. FSD Maintainability Demonstration 34 MACA15. Production Readiness Review 35 MACA16. System Function Configuration 36 MACA

Audit (FCA)17. RF-4C DT&E/IOT&E Complete 38 MACA18. UARS DT&E/IOT&E Complete 38 MACA

Page 20: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-20

Section L - Instructions, Conditions, and Notices to Offerors (Cont.)

Event Number Event Title Event Date

19. F/A-18 DT&E/IOT&E Complete 38 MACA20. Formal Qualification Review (FQR) 38 MACA21. Milestone IIIA 39 MACA22. System Physical Configuration 57 MACA

Audit (PCA)23. LRIF Maintainability Evaluation 57 MACA24. Milestone IIIB 66 MACA

25. F-14D/TARPS DT&E/IOT&E 72 MACAStart

26. F-14D/TARPS DT&E/IOT&E 81 MACAComplete

27. Initial Operational Capability See(IOC) Appendix

28. Delivery Per Table 4-2 As Required*MACA: Months After Contract Award

Page 21: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-21

Page 22: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-22

Page 23: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-23

Page 24: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-24

Page 25: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-25

Page 26: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-26

Page 27: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-27

Page 28: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-28

Page 29: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-29

EXERCISE #2

Exercise: Develop the portion of a Systems Engineering Master Schedule (SEMS) for the AJS design and development tasks. Assume the system level schedule for Peace Whey includes a SRR, SFR, PDR, CDR, and PRR. Your SEMS should identify a list of AJS program reviews with accomplishment criteria.

• Part 1: Referring to the system level Peace Whey reviews, identify and list the major reviews which need to be supported by inputs from the AJS design and development tasks. Based upon this list, determine a set or reviews for the AJS development effort required to support the Peace Whey program.

• Part 2: Identify the accomplishment criteria for one AJS review.

You will have 20 minutes to complete this exercise.

Page 30: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-30

IMP/SEMS & IMS/SEDS Relationships

Integrated Master Plan (IMP)

Integrated Master Schdule(IMS)

ProgramOffice

Contracts

Security

System

Engineering

Master

Schedule

(SEMS)

ProgramOffice

Contracts

Security

System

Engineering

Detailed

Schedule

(SEDS)

Page 31: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-31

IMP/IMS Development Steps

A

SYSTEM PRODUCT HIERARCHY

SPEC TREEWBSIPT

CB D E

L MKJ

IHGF

SPEC TREEWBSIPT

SPEC TREEWBSIPT

SPEC TREEWBSIPT

ProductEvent No.

AccomplishmentCriteria

IMS Task

A NN NN NN NN

1. Define Events, Accomplishments (RFP “Shalls”), and Criteria

2. Define a Product Oriented Management Structure (SPEC Tree, WBS, and IPT Organization)

3. Build a Top Down, Layered IMP/IMS with Activity Numbers as Shown Below

Page 32: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-32

Integrated Master Plan (IMP) and Integrated Master Schedule (IMS) Terms

• Product - Hardware, Software, Facilities, Data, or Materials

• Event - Decision Point at End of Major Project Activity (EX. - CDR)

• Accomplishment - Desired Result at Specified Events

• Criteria - Measure of Meeting Accomplishment

• Task - Specific Activity to Complete a Criteria

Page 33: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-33

Top Level Task Relationships

RequirementsFor Design

RequirementsFor

Integrated Test

SoftwareImplementation

SoftwareDesign

Hardware Design

Suppliers

Component& SystemTesting

RequirementsDevelopment

• Primary • Derived

Production

• Inventory Control• Parts Production• Assembly

WeaponSystem

Integration& Testing

FEEDBACK

• Requirements• Design

Product DefinitionDelivered Product

Parts Assemblies

Product

Page 34: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-34

Network Chart Example

Network Layout

Conversion to Milestone Chart

K

2 4 6 8 10 12 14

J

C G

A D

BE H

F I

S C

(D) 6 Weeks

(A) 4 Weeks (E) 3 Weeks

(I) 4 Weeks

(H) 2 Weeks

(C) 1 Week (G) 4 Weeks

(J) 5 Weeks

(B) 2 Weeks (F) 8 Weeks

(K) 8 Weeks

Page 35: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-35

Integrated Master Schedule(IMS) and Network Schedules

• IMS Show Dates for Major Tasks and Milestones- Usually Presented as Gantt (Bar) Chart- Shows Tasks Corresponding to Entry/Exit Criteria- Must Include All IMP Milestones

• Network Schedules Are Essential to the IMS- Helps Determine if IMS Dates and IMP Events Are Achievable- Critical-Path Method (CPM) Schedule Software is Essential- Essentials: Tasks, Relationships, Durations, Resources

Page 36: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-36

IMP/IMS Summary

• Negotiated IMP Will Be Place on Contract, Changes Will Require a Contract Change Proposal• IMS Shall Support the IMP. IMS Updates Shall Be Approved Prior to Implementation of

Changes. IMS is Time-Based• Customer May Provide Government IMP in RFP. Government IMP Should Provide Detailed

Information for Next Acquisition Phase to Identify Specific Events, Accomplishments and Criteria Necessary to Satisfy Planned and Required Technical Exit Criteria

• IMP Is a Key Control Element of SE Process. IMP Can Be Used as the Basis for Quantitative Requirements for Award Fees

Page 37: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-37

Exercise # 3

Exercise:Referring to the SEMS from Exercise #2, develop a System Engineering Detailed Schedule (SEDS) for the AJS design and development task. The AJS Safety of Flight unit must be available in month 26 and first production aircraft in month 36. Be prepared to report your results to the class. You will have 20 minutes for this exercise.

Hint – Use building block tasks on next page.

Page 38: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-38

ElectronicWarfare

Page 39: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-39

Backup

Page 40: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-40

Progressive Subsystem

Informal Subsystem

Formal Subsystem

Limited Formality

Formal

Issues

Roll-Up

Page 41: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-41

Integrated Technical Reviews (Cont.)

Technical reviews are a series of systems engineering activities by which the technical progress of a program is demonstrated relative to its technical or contractual requirements. They are conducted at logical transition points in the development effort to reduce risk by assessing progress against SEMS requirements and identifying and correcting problems/issues resulting from the work completed before the program is disrupted or delayed. They provide a method for the contractor and government to determine if the development of a system and/or configuration item and its documentation have met contract requirements.

Page 42: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-42

Planning Guidance from DoDD 5000.1(Defense Acquisition)

Part 2.B.3 Acquisition Strategies, Exit Criteria, and Risk Management

“Event driven acquisition strategies and program plans must be based on rigorous, objective assessments of a program’s status and the plans for managing risk during the next phase and the remainder of the program. The acquisition strategy and associated contracting activities must explicitly link milestone decision reviews to events and demonstrated accomplishments in development, testing and initial production. The acquisition strategy must reflect the interrelationships and schedule of acquisition phases and events based on logical sequence of demonstrated accomplishments not on fiscal or calendar expediency.”

Page 43: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-43

Integrated Technical Reviews

The government assesses the status, maturity, risk, and verification status by conducting reviews that will:

• Be adequately planned prior to the initiation technical work• Have event-driven entry and exit criteria with defined accomplishments and success metrics via the SEMS.• Be conducted incrementally (as appropriately) to measure progress towards achieving major accomplishments and obviate unexpected issues resulting from incomplete or inconclusive development activities.• Be conducted by multidisciplinary teams to ensure that all the system's functions are addressed and all system elements are integrated and balanced across the system.

Page 44: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-44

DoD Risk ManagementPolicies and Procedures

Page 45: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-45

Risk Assessment and Management (DoD 5000.1)

“Program Managers and other acquisition managers shall continually assess program risks. Risks must be well understood, and risk management approaches developed, before decision authorities can authorize a program to proceed into the next phase of the acquisition process. To assess and manage risk Program Managers and other acquisition managers shall use a variety of techniques, including technology demonstrations, prototyping, and test and evaluation. Risk management encompasses identification, mitigation, and continuous tracking, and control procedures that feed back through the program assessment process to decision authorities. To ensure an equitable and sensible allocation of risk between government and industry, Program Managers and other acquisition managers shall develop a contracting approach appropriate to the type of system being acquired.”

Page 46: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-46

Cost, Schedule, and Performance Risk Management (DoD 5000.2-R)

“The Program Manager shall establish a risk management program for each acquisition program to identify and control performance, cost, and schedule risks. The risk management program shall identify and track risk drivers, define risk abatement plans, and perform periodic assessments to determine how risks have changed. Risk reduction measures shall be included in cost-performance tradeoffs, where applicable. The risk management program shall plan for back-ups in risk areas and identify design requirements where performance increase is small relative to cost, schedule, and performance risk. The acquisition strategy shall include identification of the risk areas of the program and a discussion of how the Program Manager intends to manage those risks.”

Page 47: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-47

Risk Management Structure(DoD Risk Management Study)

Risk Management

Risk Planning Risk Assessment

RiskHandling

RiskMonitoring

RiskDocumentation &Communications

RiskIdentification

RiskAnalysis

Page 48: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-48

Definitions

• Risk - A measure of likelihood to achieve objectives - Two components (probability and consequences)

• Risk Management - Act or practice of controlling risk

+ Identifying and tracking risk drivers+ Defining risk mitigation plans+ Performing periodic risk assessments

Page 49: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-49

Risk Planning

• Process has two segments– Implementing a comprehensive and active strategy to continuously identify,

mitigate and track program risks• Who does it• What do they do• When do they do it• How risk is shared

– Documenting risk elements of program activities

How do I getthere from here?

Page 50: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-50

Risk Assessment

• Process of identifying and analyzing program risks to increase the chances of meeting performance, schedule, and cost objectives

• Two segments– Risk Identification– Risk Analysis

Page 51: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-51

Risk Identification

• Process of specifying, describing and documenting program risks and their sensitivities to other risks

– Internal– External

Page 52: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-52

Risk Analysis

• Process of evaluating program risks for their impacts to performance, cost, and schedule objectives• Process includes assessing each risk’s:

– Probability of occurrence, and– Consequences of failure to mitigate the risk

Page 53: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-53

Risk Handling

• Process that identifies, evaluates, selects, and implements risk handling options– to set risk at acceptable levels– give program constraints

• Typical risk handling strategies can include:– replan to eliminate the identified risk– avoid risk by changing requirements– transfer the risk– control the risk through active steps– assume the risk without special efforts

Page 54: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-54

Risk Monitoring

• Process that systematically tracks and evaluates the performance of risk mitigation actions

- against established metrics throughout the acquisition* process, and- develops further risk handling options as appropriate

* Acquisition includes any procurement from government or contractor sources within all phases from early research through logistics, operations, support, and disposal

Page 55: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-55

Risk Management Process

Evaluate RiskHandling Options

•Avoid• Information Gathering• Transfer• Assume• Control

Program Requirements

AssessRisk

• Identify• Analyze• Quantify Risk

Evaluate Subcontractor

Risks

Analyze Impacts

• Performance• Cost• Schedule

Manage Risk

• Review Indicators• Abatement Actions

Page 56: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-56

Assess Risks

Program Requirements

AssessRisks

Evaluate RiskHandling Options

EvaluateSubcontractor

Risks

Establish Cost,Schedule, &Performance Impacts

ManageRisks

EstablishApproach

DevelopTeam

IdentifyRisk

Areas

AnalyzeRisk

Create RiskManagement

Tools

Page 57: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-57

Risk Identification

The WBS is normally used to organize and ensure completeness of the risk identification effort.

Identification is generally performed at the 3rd or 4th level of the WBS.

Page 58: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-58

Page 59: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-59

Page 60: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-60

Risk Categories and Consequences

• Risk Categories– Requirements - Are the Necessary Requirements ( Operational or Design) Fully Defined? Is the

Basis for the Requirements Stable (e.g. No Expected Threat Change)– Technology - Is the Technology Available Proven in Previous Use?– Engineering - How Much New Design is Needed to Achieve Requirements?– Manufacturing - Are the Required Manufacturing Processes, Facilities, and Sources of Materials

Known and Available?– Support - Are the Required Support Resources Defined and Available?– Management - Are the Processes, Resources, and Experience Available to Successfully Perform

this Program?• Risk Consequences

– Performance - Can the Item Meet Its Requirements (Operational, Support and Manufacturing)?– Cost - Can the Item Be Developed and Operated within the Funding Allocated to It?– Schedule - Can the Item Be Developed and Deployed with the Time Allocated to It?

Page 61: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-61

Sample Risk Identification

WBS 113 - Guidance System

Issues: New Design – Uses new chipset from CHIPLEAP program. Some concern exists on producibility and thermal characteristics.

Assumptions: Megalith Corporation will design guidance system. They were a participant in the CHIPLEAP effort.

Page 62: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-62

Additional risk categories such as customer satisfaction or customer expectation can be developed for identification purposes.

Risk assessment templates (shown on later charts) for subcategories can be developed and maintained by organizations.

Organization of Risk Assessment

Page 63: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-63

Page 64: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-64Ref. – Best Practices

Page 65: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-65

Funding

ComputerAided Design

Built –In Test

Parts and MaterialsSelection

Trade Studies

Design Process

Design RefMission Profile

SubcontractorControl

DesignReviews

LogisticsSupport AnalysisDesign

Requirements

Design Policy

Design Analysis

SoftwareDesign

Design For Testing

ConfigurationControl

Design Release

IntegratedTest

Failure Reporting

System

UniformTest Report

Software Test

Design Limit

Life

Test AnalyzeAnd Fix

Field FeedbackManufacturing

Screening

Computer-AidedMFG

Special Test Equipment

Tool Planning

Defect Control

Piece PartControl

Quality MFGProcess

ManufacturingPlan

Factory Improvements

Productivity Center

Manufacturing Strategy

ProductionBreaks

Modernization

ManpowerAnd Personnel

Support andTest Equipment

Training MaterialAnd Equipment

Personnel Requirements

Data Requirements

Technical Risk Assessment

Design Test Production Facilities Logistics Management

Product

Funding

Money Phasing

Spares

TechnicalManuals

Transition PlanRef. – Best Practices

Page 66: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-66Ref. – Best Practices

Page 67: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-67Ref. – AFMC 63-101

Page 68: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-68

Page 69: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-69Ref. – AFMC 63-101

Page 70: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-70

Probability (Likelihood)

1

0

Consequences

Traditional Risk Analysis

Performance

Cost

Schedule

Potential Degradation

Sys Reqt not Achieved

Element Increase > 50%

System Increase > 40%

Element Increase

Element Increase < 10%

x

x

x

Probability is Assigned

Consequences are Estimated

x

Page 71: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-71

Probability (Likelihood)

1

0Consequence

Traditional Risk Analysis

Performance

Cost

Schedule

Potential Degradation

Sys Reqt not Achieved

Element Increase > 50%

System Increase > 40%

Element Increase

Element Increase > 50%

x

x

x

x

x

High Risk – Severe disruption expected to performance, cost, and / or schedule even with risk mitigation plans in place.

Moderate Risk –Expected disruption to performance, cost, and / or schedule can be overcome by implementing risk mitigation plans.

Low Risk – Little disruption expected to performance, cost, and / or schedule.

Page 72: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).

10-72

Weaknesses of Traditional Risk Analysis Process

1. Roll-up of risks characterized as high, moderate, or low at the 3rd or 4th WBS level are difficult. Example – Are 10 low risks and 1 high risk at WBS Level 4 elements expressed as low, moderate, or high at the parent WBS at Level 3?

2. Characterizing a risk as high, moderate, or low alerts the customer to the severity of the outcomes without giving insight into the likely capability of the delivered product.

Page 73: 10-1 GENERAL GUIDANCE ON CONDUCT OF TECHNICAL REVIEWS Selection should be based on the complexity of the program and the phase of development (modification).