1
Barts & The London
BIM Case Study
David Throssell
UK BIM Technical Manager
2
Agenda
− Barts & London Case Study− Project description− The Business Case for BIM− Technology / BIM Tools− Elements of the BIM− Cost, Value & Benefits
− Where do we go from here?− BIM Experiences
3
Barts & The London Project description
Barts New Build (~£350m)− Phase 1: 25,650 Sq m,160 beds− Phase 2: 34,587 Sq m, 223 beds− Phase 3: 6,650 Sq m Refurb’ &
Energy Centre− Total of 2,400.new rooms
The London New Build (~£650m)− Phase 1: 142,300 Sq m 905 beds− Phase 2 - 12,600 Sq m new & 32,000
Sq m refurbished− Phase 3 – 8,600 Sq m multi-storey
car park− Total of 5,000 new rooms
4
The Business Case for BIM
− Leaps of faith
− Cost vs. Value
− Discovering the benefits
− Connecting the dots
5
Technology / BIM Tools Map
Autodesk Design Review
Codebook Database
ArtrANavisworks
ADT
StruCAD
Autodesk Design Review
Tekla
ADT
Autodesk Design Review
Navisworks
IESTAS
Hevacomp
ABS
Navisworks
ArtrA
Geneva
AutoCAD
Archibus
Micro Drainage
Navisworks
STAAD Pro
CSC 3D+
FEM Design
3D Studio MAX
Codebook Database
Navisworks
ADB Database
ADB Database
Owner
AutoCAD ADT
Structural Engineer
MAP CAD-Duct
AutoCAD & LT
Sub Contractor
Design
Main Contractor
AutoCAD ADT
ArchitectFacilities Management
Skandocs Intranet
AutoCAD
MAP CAD-Duct
Services Coordinator
Services Engineer
6
What does BIM look like?
7
Elements of the BIM - Design
Safety Reviews Material Take Off
Virtual Briefing / Snagging Clash Prevention
8
Elements of the BIM - Construction
Drawing Retrieval Room progress monitoring
Construction Planning Plant & Equipment Installation
Site
Offi
ceSi
te –
Tabl
et P
C
9
Tablet PC Applications
− Room progress monitoring
− Room Finishes Monitoring
− Portable Project Dataset
− Room Data Sheets
− Compliance− Equipment check lists− Independent Tester
− Snagging, defects & non conformance
10
Elements of the BIM - Post construction
O&M Manual Route Map Way Finding
Asset Register Links to CAFM / Help Desk
11
Cost of BIM – over 3 years
£1Total
£ -Tablet PC's with Docking stations
£ -Upgraded graphics Cards
£ -PC's for BIM SpecialistsHardware
£ -Artra Software for Tablets
£ -Artra Database Development
£ -Artra Database
£ -Skandocs Development
£ -Networked Navisworks (3D Viewer)
£ -CAD Software for BIM SpecialistsSoftware
£ -2 No. BIM Specialist for 3 No. YearsAdditional Staff
CostDescriptionResource / Material
12
Value of BIM – to date
£ -1 Hour per day x 5 days x 12 weeks x 11 tabletsAccess to latest drawings on tablet PC's to date
£2.12Total£ -2 No total saved over 6 monthsSite records Administrators
£ -Average savings identified per route check 12 No. totalPlant InstallationVerification
£ -Average savings identified per route check 13 No. totalMedical Equipment Instalation Verification
£ -125 No. MTO's Carried out saving QS feesMaterial Take Off
£ -Average savings identified per review 48 No. totalCo-ordination Reviews
ValueJustificationDescription
Shell & Core M&E Package Co-ordination errors, %age of value 0.08%
13
Other benefits of BIM
− Time− 6 No. weeks saved on partition tenders
− Waste− Dry lining waste reduced from 30% (industry norm) to 8%− Blockwork waste reduced from 10% (industry norm) to 5%
− Environmental− NEAT, WRAP, BREEAM & Embedded Carbon analyses
− Quality− Fit first time
− Safety− Improved safety for FM and Users (150 No. issues identified)
14
BIM experiences
− BIM as a contractual deliverable
− Compatibility issues & inter-operability
− MEP consultants & 3D modelling
− Importance of commitment
− Leadership and control
− Careful selection of designers
− Clear deliverables & procedures
− Ownership of the model
− Design change control
15
Summary
− It’s real, it’s happening− Design− Construction− Operations
− Lessons learned− People, process & technology
− Where do we go from here?− Win hearts & minds− Amend appointments− Shrink wrap technology