+ All Categories
Home > Documents > 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar...

10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar...

Date post: 09-Feb-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
17
10/9/2015 1 ABC Using Full-Depth Precast Concrete Deck Panel Systems October 28, 2015 Raj Navalurkar, PhD, PE Vice President, NYC Metro Area – Surface Transportation Group AECOM Clifton, NJ James Hamilton, PE Project Engineer, Ohio – Surface Transportation Group AECOM Columbus, OH Cost Duration Quality Most of the time – we settle for 2 of the 3 Challenges / Goals COST DURATION QUALITY Brooklyn Bridge Rehabilitation Geometry – Fabrication Tolerances Quality Control & Quality Assurance Innovation – Traffic Monitoring Handling Field Conditions – Contingency Plan Executing on ‘Accelerated Bridge Construction’
Transcript
Page 1: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

1

ABC Using Full-Depth Precast Concrete Deck Panel Systems

October 28, 2015

Raj Navalurkar, PhD, PEVice President, NYC Metro Area – Surface Transportation GroupAECOMClifton, NJ

James Hamilton, PEProject Engineer, Ohio – Surface Transportation GroupAECOMColumbus, OH

• Cost

• Duration

• Quality

• Most of the time – we settle for 2 of the 3

Challenges / Goals

COST DURATION

QUALITY

Brooklyn Bridge Rehabilitation• Geometry – Fabrication Tolerances

• Quality Control & Quality Assurance

• Innovation – Traffic Monitoring

• Handling Field Conditions – Contingency Plan

Executing on ‘Accelerated Bridge Construction’

Page 2: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

2

• Minimizing Disruptions to Traffic/Community

• Applying innovative strategies in planning, construction and design

• Sufficient durability to provide required service life

• Employing prefabricated bridge element systems

• Concrete maturity method to expedite bridge reconstruction

• Grout Systems

• Sufficient Seismic Performance

Accelerated/Rapid Bridge Replacement

• The Brooklyn Bridge is a Designated Historic Landmark

• Opened to Traffic in 1883,

• Construction is Scheduled 2009-2014

– Overnight Construction

– Limited Weekend Construction Rehabilitation of Approach Ramps and Seismic Retrofit

• Accelerated Construction ~ 250,000 SF Re-decking

• Widening of Ramps (Ramp A/C, Ramp A/G Merge)

• Overnight and Limited Weekends

• 4,000,000 SF of Repainting

• Structural Repairs to Main Bridge

• Complex MPT and Innovative Staging

– Maintain Traffic at all Times

• Over $500 Million Construction Cost

NYCDOT Brooklyn Bridge

• Rehabilitation of the Approach (Roadway Pavement)

• Rehabilitation of the Manhattan Side Ramp Structures

• Painting of the Ramp Structures and Main Span

• Rehabilitation of Approach Steel Structures

– Select Options – Enhance Life Expectancy

– Selected Options that Minimizes Traffic Impacts

– Reduce Costs and Overall Project Duration

• Improve Safety

• Improve Aesthetics

Brooklyn Bridge Project Overview

• Replace Waterproofing Membrane under the Approach Roadway Pavement

• Replace Reinforced Concrete Decks (Bridges)

• Correct Deterioration of Steel Framing (Bridges)

• Improve Earthquake Resistance

• Maintain Traffic – No 24/7 Closures

• Increase Capacity

– SB FDR Exit Ramp (Widen Ramp A)

– Meter Traffic Flow of NB FDR Exit Ramp

– Improve Traffic Flow at Merge with Main Approach

– Widen Road F (Brooklyn Side)

Project Challenges

Page 3: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

3

Brooklyn Bridge

• Restrictive Roadway Width

Executing on ‘ABC Requirements’

Pavement Rehabilitation Deck Replacement

Ramp Rehabilitation (Deck Replacement)

Manhattan Approach

Arch Block C (South View)

Arch Block A (South View) Arch Block B (North View) Franklin Square (South View)

Arch Block E (North View) Arch Block D (North View)

Manhattan Approach

Page 4: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

4

Full Superstructure Replacement (Inadequate Under Clearance & Deficient Structural Rating)

Pavement Rehabilitation

Deck Replacement

Brooklyn Approach

Arch Block I (South View)

Arch Block II (South View)

Arch Block III (North View)

Brooklyn Approach

York Street (South View) Main Street (South View) Washington Street (South View)

Arch Block I (South View) Sands Street (South View)Prospect Street (South View)

Brooklyn Approach

• Provide 2 Lanes – Free Flow

Ramp A Improvements

Page 5: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

5

FDR Exit 2 Lanes

Ramp Widening(2 Lanes)

Ramp A Improvements

• Provide 2 Lanes – Free Flow

Ramp A Improvements

Road F/FS Improvements

• Provide 2 Lanes – Free FlowAging Roadway

Promenade

Aging Roadway

Brick Arch

Typical Section Through Arch

Fill

Crown of ArchDeteriorated

Closure Walls (Typ)

Failed Membrane System

Approach Roadway Rehabilitation

Page 6: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

6

Current Conditions

Heaving of Floors

Current Conditions

Deterioration of the Masonry Arches In-fill Walls

Bricks – Arch Block B

“On-site RILEM tests indicate that the initial absorption rates of the bricks are

high, suggesting that continued deterioration as a result of movement of water

and soluble salts through the brick material is likely, which will result in

increased amount of water infiltration into the structure!..”

“X-ray fluorescence and x-ray diffraction analyses confirmed the presence of

soluble salts primarily in the form of Halite, a common roadway de-icing salt

and Gypsum, a byproduct of acidic water and mortar materials. Mortar

Analyses are pending laboratory analyses results!.”

Current Conditions Current Conditions

Floor Beam

Connection Failure

Page 7: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

7

Approach Roadway Rehabilitation (Precast)

Dowel Bar (Typ)

Precast Concrete Pavement Panel

Precast Option

Sprayed-On

Waterproofing

Membrane

Distribution Channel

Grouting Ports

Existing Concrete Fill Fine Fill (Bedding)

3” Thickness

Approach Roadway Rehabilitation – Unforeseen Conditions

Manhattan Approach – Arch Block Strengthening - Complete Current Conditions

Page 8: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

8

Ramp and Approach Structures Rehabilitation

Existing Steel Beam

Limits of Deck Removal

Ramp and Approach Structures Rehabilitation

Existing Steel Beam

Limits of Temporary Mabey Bridge Units

Over Filled Steel Grid Deck Deck Replacement – Ramp A

Page 9: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

9

Ramp A – Precast Decks Maturity Method

Data Loggers Ramp Construction

Page 10: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

10

York Street Rehabilitation York Street Rehabilitation

York Street Construction York Street Rehabilitation

Page 11: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

11

• Temporarily Close Brooklyn Bridge West Bound Weekends and Overnight Traffic

• Maintain Brooklyn Bridge East Bound Weekends and Overnight Traffic

• Divert Brooklyn Bridge West Bound Weekend and Overnight Traffic to Manhattan Bridge

• Implement Disincentive and Incentives Clauses (User Cost Based)

Maintenance & Protection of Traffic

• Weekend Closures are Critical, total number 24 (12 EB and 12 WB)

• Weekend Closures, Demolition/Erection Work on the Approach Bridges

– 6 Structures x 2 = 12 (All bridges except Park Row)

• Weekend Closures, Installation of Precast Panels on the Approaches (Concurrent to Bridges)

Requested Closure Hours

Westbound Detours Traffic Studies

Manhattan Side Study Area

Page 12: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

12

Traffic Studies

Brooklyn Side Study Area NEWARK BAY BRIDGE

REHABILITATION

INTERCHANGE 14

INTERCHANGE 14A

Pier W15

E. Abutment

ZONE 1 – MP N0.00 TO INT. 14A

ZONE 2 – INT. 14A TO INT. 14C

ZONE 3 – INT. 14C TO TERMINUS

Project Location / Zone 1 And Zone 2 Limits

NJTA Casciano Memorial Bridge

• Rehabilitation of 1.5 Miles of Viaduct

– Total Design/Construction Support Services

• Accelerated Construction ~ 500,000 SF of Redecking

• Preliminary Seismic Evaluations

• Tie-Chord Redundancy

• First Time for NJTA to use Precast Panels

• Maintain 4 Lanes of Traffic at all Times

• Over $100 Million Construction Cost

Page 13: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

13

Scope Of Work

• Major Items

– Deck Reconstruction

– Structural Steel Repairs/Strengthening

– Gusset Plate Retrofitting

– Lighting Improvements

– Drainage Improvements

Girders (General Condition)

Floorbeams (Typical Repair Locations)

Page 14: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

14

Critical Gusset PlatesGusset Plate Inspection Findings

PANEL POINT

TRUSS LOCATION

PLATE LOCATION ON PLATE

MAXIMUM MISALIGNMENT

[G]

RANGE OF MISALIGNMENT

TYPE OF DEFORMATION

WEST

EDGE 1/2" 12" FREE END

OUTBOARD DIAGONAL

MEMBER 1/2" 48" INTERIOR

EAST

EDGE 1/4" 48" INTERIOR

SW

INBOARD WEST

EDGE 1/4" 48" INTERIOR

EAST

EDGE 1/4" 24" INTERIOR

OUTBOARD WEST

EDGE 1/4" 18" INTERIOR

EAST

EDGE 1/4" 24" INTERIOR

SE

INBOARD WEST

EDGE 1/4" 18" INTERIOR

EAST

EDGE 3/4" 12" FREE END

OUTBOARD VERTICAL

MEMBER 1/4" 24" FREE END

INBOARD EAST

EDGE 1/4" 24" INTERIOR

NE

INBOARD

TOP EDGE

TO

DIAGONAL

1/2" 18" FREE END

OUTBOARD WEST

EDGE 1/2" 24" FREE END

EAST

EDGE 1/4" 24" INTERIOR

L7

NW

INBOARD WEST

EDGE 1/4" 24" INTERIOR

SW INBOARD TOP EDGE 3/8" 8" FREE END

SE OUTBOARD BOTTOM

EDGE 1/4" 24" INTERIOR M7

NE INBOARD TOP EDGE 1/2" 18" FREE END

U2 NW INBOARD WEST

EDGE 1/4" 24" FREE END

U8 NW OUTBOARD BOTTOM

EDGE 3/16" 24" INTERIOR

L11 NE INBOARD TOP EDGE 1/8" 48" INTERIOR

L15 NW INBOARD WEST

EDGE 1/8" 24" INTERIOR

Precast Deck Details Precast Deck Panel Details

Page 15: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

15

Maximum concrete deck strain at for Scheme C1 Ⅲ for Girder span. (Trucks GVW 55 kips)

Cast-In-Place Precast

S1

S2

S3

S4

S5

S6

S7

S8

S9

S10

S11

S12

New Concrete

-20

0

20

40

60

80

100

120

140

0 20 40 60 80 100 120 140

Deck StrainDeck Strain + IMCracking Strain

Te

ns

ile

Str

ain

(µεµε µεµ

ε)

Distance ( ft)

-20

0

20

40

60

80

100

120

140

0 20 40 60 80 100 120 140

Deck StrainDeck Strain + IMCracking Strain

Te

ns

ile

Str

ain

(µεµε µεµ

ε)

Distance ( ft)

Deck Cracking Studies Precast Deck Benefits

• Minimize the number of shear stud pockets (fatigue and ultimate strength)

– AASHTO 24” Current

– 1941 – limit 3 to 4 deck thickness

– NCHRP Report 48” – No Negative Effects

• HSS Tube Used to Provide Confinement

• No Exposed Pockets

• Eliminate the need for an overlay and waterproofing system

• Eliminate Post Tensioning

Panel to Panel Joints

• Female-to-female joints filled with non-shrink grout provide superior performance compared with match-cast, male-to-female joints

• Sharp corners of the shear key enhance the shear transfer across the joint

• The design criteria for a successful joint detail - no cracks and no water leakage

• Although longitudinal posttensioning, which puts the joint in compression and secures it against leakage, increases the cost of the deck system

Local Post-tensioning

• Hand Held Torque Wrench

• Hair Pin Reinforcement can

be used in lieu of Spiral

Page 16: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

16

Grout SystemsGrout Types Set 45 Set 45 HW SS Mortar Masterflow

928

Masterflow

648 CP +

Polymer Grout

Description Magnesium

phosphate patching

and repair mortar. It

sets in 15 minutes.

Hot weather,

magnesium

phosphate patching

and repair mortar

High-precision,

high-strength,

cement-based,

metallic aggregate

mortar.

High-precision,

hydraulic-cement

based, mineral

aggregate grout.

High-precision, Plus

is a solvent-free,

high flow epoxy

resin based grout.

High-precision, Polymer grout.

Features - High early strength

at 1 hour

- Superior bonding

- Very low drying

shrinkage -

Resistant to

freeze/thaw, sulfate

and deicing

chemicals

- Superior bonding

- Very low drying

shrinkage

- Resistant to

freeze/thaw, sulfate

and deicing

chemicals

Nonshrink grout

- High flowability,

suitable for

pumping in tight

spaces

- Can be used over

wide range of

temperature

- Nonshrink grout

- Resistant to

freeze/thaw &

sulfates

- High flowability,

suitable for pumping

in tight spaces

- Designed for the

40º F to

90º F range

- Nonshrink grout

- Resistant to

freeze/thaw &

sulfates

- High flowability,

suitable for

pumping in tight

spaces

- Designed for the

55º F to

90º F range.

- Nonshrink grout

- Resistant to freeze/thaw & sulfates

- High flowability, suitable for pumping

in tight spaces

- Designed for the 14º F to

90º F range

Compressive

Strength

1,200 psi @ 6 hours

(36º F)

1,200 psi @ 6 hours

(36º F)

4,000 psi @ 1 day

(70º F)

No data at lower

temperatures

1,000 psi @ 3 days

(70º F)

No data at lower

temperatures

1,300 psi @ 1 day

(55º F)

No data at lower

temperatures

2,500 psi @ 2 hours (15º F)

Flexural Strength 600 psi 600 psi 1,000 psi 1,000 psi 4,600 psi 5,900 psi

Finish Color Dark Brown Dark Brown Dark Brown Dark Gray Dark Gray Concrete Gray

LAFARGE® Ductal Joint Fill Material (UHPC) and the FORT MILLER (PRO-SPEC)

GEORGE WASHINGTON BRIDGE

REHABILITATION

PANY&NJ George Washington Bridge

• In-Depth Inspection and Design Approval Documents• 178th Street and 179th Street Ramps, Bus Ramps

and Turnabout• New Jersey Anchorage and Hudson Terrace• Upper Level Sidewalks Construction Documents for• Rehabilitation• Redecking Alternative• Seismic Evaluations and Retrofitting• Value Engineering• Complex MPT and Innovative Staging

PANY&NJ George Washington Bridge

Page 17: 10/9/2015 - dot.state.oh.us...10/9/2015 16 Grout Systems Grout Types Set 45 Set 45 HW SS Mortar Masterflow 928 Masterflow 648 CP + Polymer Grout Description Magnesium phosphate patching

10/9/2015

17

• What are the 3 most important Mobility Requirement needed for ABC ?

• What is important when considering Precast Construction?

• What is Maturity Method?

• Why is the 2,500 year return period earthquake used?

• Why was the WB Traffic Detoured?

Questions

Questions and Answers


Recommended