11 T Dipole for DS Status of CERN Activities M. Karppinen CERN TE-MSC On behalf of B. Auchmann, L....

Date post: 15-Jan-2016
Category:
Upload: jaheim-stoner
View: 221 times
Download: 0 times
Share this document with a friend
Popular Tags:
13
11 T Dipole for DS Status of CERN Activities M. Karppinen CERN TE-MSC On behalf of B. Auchmann, L. Bottura , B. Holzer, L. Oberli, L. Rossi, D. Smekens, T. Sahner, L. Favre
Transcript

11 T Dipole

11 T Dipole for DSStatus of CERN ActivitiesM. Karppinen CERN TE-MSC

On behalf ofB. Auchmann, L. Bottura , B. Holzer, L. Oberli, L. Rossi, D. Smekens, T. Sahner, L. Favre

11 T Activities2-in-1 DemonstratorEM-design optimization has startedStructural analysis in progressTooling design based on FNAL tooling is in progressQuench analysis has startedCabling trials (14.7 mm) imminentBeam dynamics studies in progressCryo-magnet integration including (cryo-)collimator will commence in Q3Common activities with other CERN HFM projects: Sc-strand and cable, insulation, impregnation, reaction, thermal models, quench analysis, instrumentation etc..

May 13, 2011 Collaboration meetingM. Karppinen CERN TE-MSC2

May 13, 2011 Collaboration meetingM. Karppinen CERN TE-MSC3Mid-20132-in-1 #2CERN CoilsEnd-20111-in-1 Demo

End-20135.5 m Model

End-20122-in-1 #1FNAL Coils

May 13, 2011 Collaboration meetingM. Karppinen CERN TE-MSC4

Status of cable production at CERN (1/2)15.1 mm, 40 strands cable produced in 2010 and beginning 2011 (0.7 mm Cu and OST 108/127 stack material)Stable key-stoned cabling at pitch 90 mmAverage cabling degradation on OST 108/127 0.7 mm stack is 2.7 % at 12 T, 4 % at 11 T (good)Maximum single strand degradation observed is 7 %May 13, 2011 Collaboration meetingM. Karppinen CERN TE-MSC5

Status of cable production at CERN (2/2)14.7 mm, 40 strands tools being finalized (mandrel OK, rollers to re-touch). Cabling imminentOST 108/127 0.7 mm strand order status4.7 km delivered (Jc > 2500 A/mm2, RRR 70)25 km expected by May 31st (delivery to be verified)Bruker PIT 0.7 mm strand order statusSpecifications preparedMeeting at Hanau on May 31st

May 13, 2011 Collaboration meetingM. Karppinen CERN TE-MSC6

Cable Insulation DevelopmentS-glass braiding (on 4.5 mm cable)May 13, 2011 Collaboration meetingM. Karppinen CERN TE-MSC7

Coil Fabrication Tooling The Fermi mandrel design is being adapted to our winding and curing tooling. The mandrel blocks have been redrawn and converted metric & ISO. Price enquiry to launch this week. MB (Jeumont) curing moulds will be used for curing the binder Spacers, oil circuits connections, coil handling tools to designMay 13, 2011 Collaboration meetingM. Karppinen CERN TE-MSC8

Winding ToolingMay 13, 2011 Collaboration meetingM. Karppinen CERN TE-MSC9

End SpacersCNC-machined set #1 complete (minimum strain design)Lead-time at CERN 8-10 weeks/setIndustrial procurement:3 offers for 5-axis machining (to confirm after decision on spacer design)Lead-times 6-10 weeks for the 1st setRelatively high programming and tooling costSLS as fallback solution May 13, 2011 Collaboration meetingM. Karppinen CERN TE-MSC10

Curing ToolingRecycle LHC MB mouldsSpacers and base plate being designedLongest available block 1960 mmOil circuit to refurbishDimensional control to doRe-use LHC MQ curing press

May 13, 2011 Collaboration meetingM. Karppinen CERN TE-MSC11

2-in-1 Structural AnalysisMay 13, 2011 Collaboration meetingM. Karppinen CERN TE-MSC12

Pre-loading at the pole

Summary11 T Dipole project is progressing on several fronts at CERN:EM studiesQuench analysisStructural analysisBeam optics studiesCable developmentTooling design & procurementsCoil winding is expected to commence in Nov-Dec this year May 13, 2011 Collaboration meetingM. Karppinen CERN TE-MSC13